ELABORADO POR:HUAMANI CONDORI ETNAN ADBEEL ENTIDAD:SENCICO

Id ModoEDT Nombre de tarea Duración Comienzo Fin


de jun 10 '19 jun 17 '19 jun 24 '19 jul 01 '19 jul 08 '19 jul 15 '19 jul 22 '19 jul 29 '19 ago 05 '19 ago 12 '19 ago 19 '19 ago 26 '19 sep 02 '19 sep 09 '19 sep 16 '19 sep 23 '19 sep 30 '19 oct 07 '19 oct 14 '19 oct 21 '19 oct 28 '19 nov 04 '19
tarea J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L
0 0 PUENTE PEATONAL QUIÑONES (PROYECTO)
114 días lun 06/10/19mié 10/30/19
1 1 OBRAS PROVISIONALES 6 días lun lun
06/10/19 06/17/19
2 1.1 CARTEL DE OBRA 2.40 X 3.60 1 día mar mar 06/11 06/11
06/11/19 06/11/19
3 1.2 AGUA PARA LA CONSTRUCCION 1 día lun 06/10/19 lun 06/10/19 06/10 06/10

4 1.3 CONTENEDOR BAÑOS 1 día lun 06/10/19 lun 06/10/19 06/10 06/10

5 1.4 ALMACEN. OFICINA Y CASETA DE 6 días lun 06/10/19 lun 06/17/19 06/10 06/17
GUARDIANIA

6 1.5 CERCO CON MALLA ARPILLERA 1 día mié mié 06/12 06/12
06/12/19 06/12/19
7 1.6 ENERGIA ELECTRICA PARA LA 1 día lun 06/10/19 lun 06/10/19 06/10 06/10
CONSTRUCCION

8 2 TRABAJOS PRELIMINARES 6 días mar mar


06/11/19 06/18/19
9 2.1 TRAZO Y REPLANTEO PRELIMINAR 1 día sáb lun 06/17/19 06/15 06/17
06/15/19
10 2.2 LIMPIEZA MANUAL DEL TERRENO 4 días mar vie 06/14/19 06/11 06/14
06/11/19
11 2.3 TRANSPORTE DE EQUIPO, 1 día lun 06/17/19 mar 06/17 06/18
MATERIALES Y HERRAMIENTAS 06/18/19
12 2.4 DESMONTAJE Y MONTAJE DE RED 1 día lun 06/17/19 mar 06/17 06/18
DE AGUA 06/18/19
13 3 PLAN DE CONTINGENCIA Y DE 1 día lun lun
IMPACTO AMBIENTAL EN OBRA 06/10/19 06/10/19
14 3.1 MITIGACION DE IMPACTO 1 día lun 06/10/19 lun 06/10/19 06/10 06/10
AMBIENTAL

15 4 MOVIMIENTO DE TIERRAS 97 días lun mié


06/17/19 10/16/19
16 4.1 EXCAVACION EN TERRENO DE 47 días lun 06/17/19 jue 08/15/19 06/17 08/15
ESTRIBOS Y MURO DE CONTENCION

17 4.2 RELLENO MANUAL CON MATERIAL 9 días vie 09/27/19 mar 09/27 10/08
PRESTAMO (dist=15km) 10/08/19
18 4.3 NIVELACION Y APISONADO PARA 1 día mar mié 10/08 10/09
GRADERIAS Y VEREDAS 10/08/19 10/09/19
19 4.4 ELIMINACION MATERIAL EXCEDENTE 4 días vie 10/11/19 mié 10/11 10/16
ACARREADO, INC. CARGUIO A 10/16/19
MAQUINA

20 5 CONCRETO SIMPLE 49 días jue mar


08/15/19 10/15/19
21 5.1 ENCOFRADO Y DESENCOFRADO DE 5 días mié mar 10/09 10/15
GRADERIAS 10/09/19 10/15/19
22 5.2 GRADAS Y VEREDAS, CONCRETO 2 días mié vie 10/11/19 10/09 10/11
175 kg/cm2 10/09/19
23 5.3 SOLADO CONCRETO ESTRIBOS Y 1 día jue 08/15/19 vie 08/16/19 08/15 08/16
MURO DE CONTENCION f'c=140
kg/cm2
24 5.4 CURADO DE CONCRETO 1 día jue 10/10/19 vie 10/11/19 10/10 10/11

25 5.5 ACABADO DE DESCANSO CEMENTO 5 días mié mar 10/09 10/15


PULIDO Y BRUÑADO 10/09/19 10/15/19
26 6 CONCRETO ARMADO 35 días jue sáb
08/15/19 09/28/19
27 6.1 ZAPATAS 8 días jue sáb
08/15/19 08/24/19
28 6.1.1 ENCOFRADO Y DESENCOFRADO 2 días mar jue 08/22/19 08/20 08/22
08/20/19
29 6.1.2 ACERO DE REFUERZO Fy=4200 4 días jue 08/15/19 mar 08/15 08/20
kg/cm2 08/20/19
30 6.1.3 CONCRETO F'C=210 KG/CM2 4 días mar sáb 08/20 08/24
08/20/19 08/24/19
31 6.2 ESTRIBOS 25 días mar vie
08/20/19 09/20/19
32 6.2.1 ENCOFRADO Y DESENCOFRADO 17 días jue 08/29/19 vie 09/20/19 08/29 09/20

33 6.2.2 ACERO DE REFUERZO Fy=4200 8 días mar jue 08/29/19 08/20 08/29
kg/cm2 08/20/19
34 6.2.3 CONCRETO F'C=210 KG/CM2 5 días jue 08/29/19 vie 09/06/19 08/29 09/06
35 6.3 SUPERESTRUCTURA 14 días mar 09/10/19vie 09/27/19
36 6.3.1 ENCOFRADO Y DESENCOFRADO 4 días vie 09/20/19 jue 09/26/19 09/20 09/26

37 6.3.2 ACERO DE REFUERZO Fy=4200 10 días mar lun 09/23/19 09/10 09/23
kg/cm2 09/10/19
38 6.3.3 CONCRETO F'C=210 KG/CM2 2 días lun 09/23/19 mié 09/25/19 09/23 09/25
39 6.3.4 JUNTA DE APOYO CON 1 día jue 09/26/19 vie 09/27/19 09/26 09/27
NEOPRENO

40 6.3.5 JUNTA DE DILATACION CON 1 día jue 09/26/19 vie 09/27/19 09/26 09/27
NEOPRENO Y PERFILES

41 6.4 MUROS DE GAVIONES 2 días jue sáb


09/26/19 09/28/19
42 6.4.1 MURO GAVIONES CAJA 2 días jue 09/26/19 sáb 09/26 09/28
5.00x1.00x1.00 M 09/28/19
43 7 CARPINTERIA METALICA PARA 5 días vie jue
COBERTURA 09/27/19 10/03/19
44 7.1 BARANDAS DE TUBERIA FIERRO 5 días vie 09/27/19 jue 10/03/19 09/27 10/03
GALVANIZADO PASAMANOS 1 1/2"

45 7.2 BARANDAS DE TUBERIA FIERRO 2 días vie 09/27/19 lun 09/30/19 09/27 09/30
GALVANIZADO PASAMANOS 4" EN
PUENTE PEATONAL

46 8 PINTURA 22 días jue 10/03/19mié 10/30/19


47 8.1 PINTURA EN BARANDAS Y 4 días jue 10/03/19 mar 10/03 10/08
PASAMANOS METALICOS (INCLUYE 10/08/19
BASE ANTICORROSIVA)

48 8.2 PINTURA DE SEÑALIZACION EN 2 días lun 10/28/19 mié 10/28 10/30


GRADAS Y VEREDAS 10/30/19
49 9 ARTEFACTOS DE ALUMBRADO 12 días mié 10/09/19jue 10/24/19
50 9.1 EXCAVACION DE ZANJAS 1 día mié 10/09/19jue 10/10/19 10/09 10/10
51 9.2 CONCRETO F´C= 175 KG/CM2 PARA 1 día lun 10/14/19 lun 10/14/19 10/14 10/14
CIMENTACION

52 9.3 ENTUBADO, CABLEADO Y 5 días mar lun 10/21/19 10/15 10/21


COLOCACION DE ACCESORIOS 10/15/19
53 9.4 HABILITACION POSTES TUBO DE 3 días mié sáb 10/09 10/12
FIERRO NEGRO DE 3" 10/09/19 10/12/19
54 9.5 PASTORAL DOBLE DE FIERRO 4 días lun 10/14/19 jue 10/17/19 10/14 10/17
GALVANIZADO

55 9.6 SALIDA DE CENTRO DE ALUMBRADO 4 días jue 10/17/19 mar 10/17 10/22
10/22/19
56 9.7 PERMISOS DE EMPRESA 1 día mié jue 10/24/19 10/23 10/24
PRESTADORA DE SERVICIOS 10/23/19
57 9.8 POZO DE TIERRA 1 día mar mié 10/22 10/23
10/22/19 10/23/19
58 10 AREAS VERDES 4 días mié lun
10/23/19 10/28/19
59 10.1 TIERRA DE CHACRA 4 días mié lun 10/28/19 10/23 10/28
10/23/19
60 10.2 SUMINISTRO Y COLOCACION DE 2 días mié vie 10/25/19 10/23 10/25
ARBOLES 10/23/19
61 10.3 SUMINISTRO Y COLOCACION DE 2 días mié vie 10/25/19 10/23 10/25
CESPED 10/23/19
62 11 SEÑALIZACION 2 días lun mié
10/28/19 10/30/19
63 11.1 SEÑALES INFORMATIVAS 2 días lun 10/28/19 mié 10/28 10/30
10/30/19
64 11.2 SEÑALES PREVENTIVAS 2 días lun 10/28/19 mié 10/28 10/30
10/30/19
65 12 VARIOS 15 días vie mié
10/11/19 10/30/19
66 12.1 LIMPIEZA FINAL DE OBRA 1 día mar mié 10/29 10/30
10/29/19 10/30/19
67 12.2 PRUEBAS DE CALIDAD DE SUELOS Y 1 día vie 10/11/19 sáb 10/11 10/12
CONCRETO 10/12/19
68 12.3 PRUEBAS ELECTRICAS 1 día jue 10/24/19 vie 10/25/19 10/24 10/25

Proyecto: PUENTE PEATONAL Q Tarea Hito Resumen del proyecto Tarea resumida Hito resumido Tareas externas Tarea inactiva Resumen inactivo solo duración Resumen manual solo fin Tarea crítica
Fecha: mar 06/04/19 División Resumen Agrupar por síntesis Tarea crítica resumida Progreso resumido Hito externo Hito inactivo Tarea manual Informe de resumen manual solo el comienzo Fecha límite Progreso