Вы находитесь на странице: 1из 8

E NGINE E RING

D ATA RE P ORT
NUMBER 49

Field Inspection of Reinforcing Bars

A SERVICE OF THE CONCRETE REINFORCING STEEL INSTITUTE


933 N. Plum Grove Rd., Schaumburg, Illinois 60173-4758

Introduction Inspector Qualifications


In a perfect or utopian world, quality control or Inspectors are individuals qualified to perform
inspection to assure compliance with project the inspection tasks. They should by education,
drawings*, project specifications, material stan- training, and experience have the ability to read
dards, and building codes would not be neces- and understand project specifications, material
sary since the project drawings and project spec- standards, project drawings, and building code
ifications would be complete without errors or requirements. In the event of field problems, they
omissions, the materials would be manufactured must work with the contractor and make deci-
exactly to the material standards, and the field sions on improvised details if the architect/engi-
workmanship would be precise. However, in the neer is unavailable to provide direction. An inspec-
present day real world, quality control programs tor must project confidence in his decisions. He
are recommended with inspection usually man- should be meticulous, correct, fair, and firm,
dated to ensure compliance with a regulatory along with the ability to compromise when faced
agency’s policies. Why is this necessary? with a dispute regarding a conflict in the contract
Project drawings are not always complete due documents or actual field conditions, or both.
to an owner’s desire for a rapid start and com- Inspection Goals
pletion of a project. Materials may vary from the
standards due to imperfections in the raw mate- The goal of any inspection or quality control pro-
rial or the manufacturing process. Workmanship gram is to ensure that the intent of the contract
is not always correct due to improper training, documents is met and that the requirements of
inadequate experience, or careless supervision. the building code are followed. Inspection and
Thus, there is recognition by owners, contrac- testing by themselves do not add quality to the
tors, architects/engineers, and regulating agen- product or the material being inspected, but only
cies that programs for quality control and inspec- confirm whether or not what is being inspected
tion are necessary to ensure compliance with the meets the criteria established by the project draw-
contract documents and the building code appli- ings, project specifications, and building code.
cable to the project under construction. Quality during the construction process is
The benefits of a quality control program and achieved almost entirely by the contractor’s
mandated inspection are mainly monetary, but quality assurance program, which depends on
they also ensure structural safety and compliance and involves all workers and field supervisors.
with architectural requirements. The owners, pri- The contractor’s inspectors are his employees
vate and governmental, benefit with lower total and are separate from the inspectors mandated
costs, on-time construction schedules, and quick- by the owner or local building department. The
er occupancy. The architect/engineer benefits in quality control inspection by the contractor helps
the knowledge that the structure will conform to assure that the finished construction meets the
the design intent. The contractor, his subcontrac- owner’s requirements, while similar programs by
tors and suppliers, and all their employees will the material producers and suppliers assure that
benefit in a similar manner. The public, as the ulti- the products and materials being supplied will
mate consumer and user of the structure, bene- meet the specific requirements of the material
fits in the knowledge that the structure has been standards. The final in-place acceptance inspection
built according to the contract documents. is a formalized procedure that provides the owner
and regulatory agency with an acceptable degree
* See the Terminology section on Page 7 for definitions of certain of assurance that the contractor has satisfied his
terms used in this report.

© Copyright 2001 by the Concrete Reinforcing Steel Institute


obligations as described in the contract documents tion on the contract documents, possible struc-
and by the building code. To accomplish this end, tural drawing discrepancy, detailing or placing
the inspector must familiarize himself with the proj- errors, and verification and acceptability of
ect specifications and project drawings, have rea- implemented field changes.
sonable knowledge of the building code require- g. Tolerances . . . A discussion with all parties
ments, have access to material standards and ref- regarding which tolerances are critical, the
erence codes, and have available industry manuals method of measurement, and the basis for either
and reports. See References. rejection or acceptance.
At the start of a construction project, whether h. Periodic Meetings . . . It is recommended that
small, medium or large, it is recommended that regularly scheduled meetings be held in order to
the inspector establish an inspection program. discuss the previous inspection reports, any prob-
The program can be established at a pre-con- lems that were encountered, solutions to the prob-
struction conference with the general contrac- lems, and the schedule of work for the next period.
tor’s superintendent, the supplier’s representa-
tive, the ironworker foreman, and other interest- Material Inspection
ed parties such as the architect/engineer or the In-place inspection of reinforcing bars starts
architect/engineer’s inspector. This meeting with the mill test report, which in some cases is
should establish a checklist procedure and mini- supplemented by a report from an independent
mum requirements for inspection acceptance. testing laboratory. Both reports should provide
data as to grade of steel, tensile properties (yield
Checklist strength, ultimate tensile strength, and percent-
The checklist for the inspection of reinforcing bars age of elongation), bend tests, chemical compo-
should include, but not be limited to, the following: sition and carbon equivalent (C.E.) in the event
a. Construction Schedule . . . A construction the reinforcing bars are to be welded, and the
schedule from the general contractor is impor- spacing and height of deformations. The report-
tant and necessary so that the inspector can fol- ed data should meet the requirements of the
low the reinforcing bar placing crew and carry out applicable ASTM standard. A visual examination
his inspection of the in-place reinforcing bars of the mill markings on a bar will identify the pro-
prior to the scheduled placing and finishing of the ducing mill, a bar size, the type of steel, and the
concrete. grade of steel.

b. Certified Mill Test and/or Bar Coating Inspection of In-Place Reinforcing Bars
(Certification) Reports . . . The reports may Inspection of the reinforcing bars installed in the
accompany the shipments of material to the job- forms is done by visual examination of the layout
site, and thus are available to the inspector. In the pattern, by measurement and count. The bar
event the reports are sent to the contractor’s office diameter, and if bent, the bar shape can be visual-
rather than to the job site, arrangements should be ly checked. Bar lengths, bar spacings, embed-
made to make them available to the inspector. ments, and bearings on walls or beams are nor-
c. Independent Testing Laboratory Reports . . . mally checked by measurement. In a slab, the
The reports on samples taken either at the rein- total number of pieces can be counted with the
forcing bar fabricator’s shop or from material spacing of the slab bars verified by measurement,
shipped to the job-site, offer verification of the all checked against the approved placing drawings
producer’s mill test report. in conjunction with the structural drawings.
Similarly, beam longitudinal bars, column vertical
d. Approved Placing Drawings . . . The latest bars, and stirrup and tie spacings are checked.
approved placing drawings should be available
for review and study by field placing personnel Bar Supports
and the inspector at least one day prior to the At the same time that the beam and slab rein-
actual placing of the reinforcing bars. forcing bars are being inspected, the heights of
e. Material Shipment . . . A schedule of antici- bar supports should be measured to verify that
pated delivery dates should be provided and the concrete cover and clearances will be as
updated as necessary so that the inspector can specified. It is extremely important that the bar
schedule his in-place inspection. supports for slab or mat top bars be checked not
only for height but also for stability, since they
f. Potential Problems . . . A discussion between can easily be displaced during the placement of
all parties to identify difficult-to-place reinforce- concrete. In fact, the entire mat and cages of
ment details, lack of specific details or informa- reinforcing bars should be checked for stability

2
for the same reason. If the project specifications If epoxy-coated or zinc-coated (galvanized)
require corrosion-protection measures, the class reinforcing bars are specified for corrosion pro-
of protection of the bar supports furnished tection, the project specifications should be stud-
should be verified. ied to determine the criteria for acceptance or
rejection in the event there is damage to the coat-
Tying Requirements ing. Any corrective actions should follow recom-
Reinforcing bars are tied together to form a mended repair procedures and should be com-
rigid mat for footings, walls, and slabs. A rigid pleted prior to acceptance by the inspector.
cage is formed when beam or column longitudinal
bars are tied to the stirrups and ties. Ironworkers Tolerances
are usually instructed to tie a minimum number of No structure is built exactly level, plumb,
intersections. Unless the project specifications straight, and true to line. Tolerances are the
are very specific about the number of intersec- means used to establish permissible variations in
tions to be tied, the inspector should accept the dimensions and locations. Thus, the archi-
work as done unless it is apparent that the mats tect/engineer, contractor, and inspector have
or cages of reinforcing bars will be displaced parameters within which the work can be per-
from their inspected position during the casting, formed and inspected. Tolerances should neither
screeding, and finishing of the concrete. The plac- be overly restrictive nor lenient. The contract
er is responsible for tying reinforcing bars in such documents should specify the standard toler-
a manner that the bars will not be displaced. The ances to be followed, usually by reference to the
inspector should only verify and agree that this ACI 117 Specification. Judgment on the part of
condition has been achieved. Only coated tie wire the inspector will establish a range of acceptabil-
should be used to tie coated reinforcing bars. ity. Incompatible tolerances should be referred to
CRSI’s book, Placing Reinforcing Bars, the the architect/engineer for resolution.
authoratative publication on placing practices,
states in its Chapter 10 under General Principles
Fabricating Tolerances
of Tying Bars: Fabricating tolerances for reinforcing bars are
established in the ACI 117 Specification, the ACI
“. . . It is not necessary to tie reinforcing bars at
Detailing Manual, and CRSI Manual of Standard
every intersection. Tying adds nothing to the
Practice. Shearing length tolerance for straight
strength of the finished structure. . . .”
bars is plus or minus 1 inch.* The out-to-out
Splices dimension of bars with hooks or bends at one
The inspector should pay particular attention end or at both ends is plus or minus 1 inch.
to the location and length of lap splices. Lap Stirrups, hoops, and ties that fit into a beam or
splices should be specified as to length and loca- column form, for bar sizes #10, #13, and #16**,
tion on the contract documents, and in turn with a gross length of 12'-0" or less, have a toler-
shown by length and location on the approved ance of plus or minus ½ inch. When a gross
placing drawings. In the event that mechanical length exceeds 12'-0", the tolerance is increased
splices are required in lieu of lap splices, the to plus or minus 1 inch.
placing foreman and/or the mechanical splice Placing Tolerances
supplier should provide literature describing the
Placing tolerances recognize the imprecise
recommended installation procedures.
nature of the placing operation and allow devia-
Coatings tion criteria. The ACI 117 Specification indicates
A light coating of rust on reinforcing bars should tolerances on clear distance to side forms and
not be a cause for rejection by the inspector. The resulting concrete surfaces, and on the clear dis-
ASTM standards and the ACI 318 Building Code tance to formed concrete soffits in the direction
describe how to inspect and evaluate rusted rein- of the tolerance. These tolerances are:
forcing bars. However, dirt, grease, or other delete- Member Size Tolerance
rious materials on the reinforcing bars must be # 4 in. + ¼ in., – 3/8 in.
removed prior to concrete placement. Tests have > 4 in., # 12 in. 3/8 in.
indicated that water soluble cutting oils, those used > 12 in., # 24 in. ½ in.
when threading ends of bars for attaching to > 24 in. 1 in.
mechanical splices, do not significantly affect bond.

* 1 inch = 25.4 millimeters


** See discussion of Soft Metric Reinforcing Bars on Pages 7-8 of
this report.

3
The ACI 117 tolerances for concrete cover For example, the length of a beam which is dis-
measured at right angles to the concrete surface continuous at each end may create a problem if
in the direction of the tolerances are: the formwork is ‘minus’ when at the same time
Member Size Tolerance reinforcing bars are ‘plus’. Each trade, carpenter
and ironworker, can claim that their work is with-
# 12 in. – 3/8 in. in tolerance, thus squarely putting the problem
> 12 in. – ½ in. into the inspector’s lap to make a decision. The
Reduction in concrete cover is permitted by ACI inspector must determine whether the encroach-
117. Generally the reduction should not exceed ment on concrete cover is detrimental to the safe-
one-third of the specified cover. For formed sof- ty and service life of the structure, or within the
fits, the reduction in cover is limited to ¼ inch. allowable limits of reduction in concrete cover.
The uniform spacing or center-to-center dis- Inspection of placement of reinforcing bars in
tance between reinforcing bars in slabs and walls walls and slabs is usually straight-forward and
have a tolerance of 3 inches from a specified normally no misplacement will be found. Small
location. The tolerance in the longitudinal loca- openings, pipe sleeves, electrical outlets, and
tion of bends and ends of bars in general is plus similar items may interfere with the specified
or minus 2 inches, but at a discontinuous end of location of the reinforcing bars, but the ironwork-
a structural member the tolerance is reduced to er usually will shift the reinforcement to one side
plus or minus 1 inch. The length of lap splices or the other to avoid the obstruction. The ACI
has a tolerance of minus 1 inch. Obviously a 117 Specification allows a maximum deviation
longer splice length would be considered safer, from the specified location of 3 inches. This devi-
hence there is no plus tolerance. Finally, the tol- ation normally is sufficient, provided that the
erance for embedded length is minus 1 inch for total number of bars in a wall or slab panel is not
bar sizes #10 to #36 and minus 2 inches for bar reduced. No cutting of reinforcing bars should
sizes #43 and #57. In terms of percentages, be done to clear obstructions without approval
these tolerances may be considered liberal, and by the architect/engineer.
normally are easily met.
The spacing tolerance for stirrups and ties in
The tolerance for beam and column forms is beams and columns is also quite flexible. The ACI
plus ½ inch and minus 3/8 inch for form dimen- 117 Specification allows a deviation from the spec-
sions larger than 12 inches but not over 36 inch- ified location equal to the least dimension of the
es. A potential problem occurs if the stirrups or member divided by 12. Thus, stirrup or tie place-
ties are fabricated to the plus tolerance of ½ inch ment in an 18-inch square beam or column could
when the forms are made to the minus tolerance vary from the specified location by 1½ inches.
of 3/8 inch. This condition has the effect of reduc-
ing the clearance to 7/16 inch on each side of the In-Situ Bending and Rebending*
stirrup or tie. The inspector must determine One of the more controversial construction proce-
whether or not this encroachment on concrete dures is the practice of bending and rebending
cover is critical. As previously stated, the ACI installed reinforcing bars. Many conditions and situ-
117 Specifica- tion permits a reduction in con- ations at the job-site require such bending and
crete cover of 3/8 inch when the member size is rebending. As an example, the horizontal leg of bent
12 inches or less, and ½ inch if the member is reinforcing bars (fabricated) projecting from a wall to
over 12 inches in the direction of tolerance. This become the top bars of a beam may have been
type of problem should be resolved with the improperly placed too low or too high, well in excess
assistance of the architect/engineer. of concrete cover and placing tolerances. These
Another example of encroachment on concrete bars will require ‘straightening’ and then ‘rebending’
cover is a formed footing; the form tolerance is to the proper position. The inspector, after consulta-
plus 2 inches and minus ½ inch, while the toler- tion with the architect/engineer, should approve the
ance on the reinforcing bars, either straight or procedure used to accomplish the task. Section
bent, is plus or minus 1 inch. Again, if the forms R7.3.2 in the Commentary of the ACI 318 Building
are ‘minus’ and the reinforcing bars are ‘plus’, Code presents guidelines for straightening and
the concrete cover at each end of the bars is rebending embedded reinforcing bars. Section 3 in
reduced from 3 inches to 2¼ inches. This condi-
* This subject is not related to the fabrication of reinforcing bars.
tion would be acceptable since the allowed
Fabrication of reinforcing bars is the cutting-to-length of straight
reduction in concrete cover is 1 inch for sizes of bars, and cutting-to-length and bending to shape of bent bars.
structural members in excess of 2 feet. The issue here is concerned with bending and straightening or
rebending of reinforcing bars that are partially embedded in
hardened concrete.

4
the ACI 301 Specifications includes provisions for The results of the testing program showed that
field bending or straightening of reinforcing bars. any effect of flame-cutting is localized to the
In some instances, the use of planned prebent end-cut surfaces. Only a very short distance or
dowels is requested by the contractor. The archi- length of bar, approximately 3/16 inch, from the
tect/engineer should review the request and flame-cut ends is affected. Hardness testing was
notify the inspector. Similarly, straight dowels used to evaluate the effects of the flame-cutting
may be planned to be field bent into place, such on the tensile properties of the bars. From an
as an outside face wall where vertical bars will be analysis of the hardness test data, it was con-
bent horizontally to become the slab end top cluded that flame-cutting had no adverse effects
bars. This procedure is intended to facilitate slab on the bars.
formwork erection. Again, the architect/engineer Flame-cutting of epoxy-coated reinforcing bars
should review the procedure and notify the is not recommended. Coating damage can be
inspector. The inspector should discuss the bend- reduced by using other means of cutting rather
ing procedure with the placing foreman to ensure than flame-cutting. After cutting epoxy-coated
that the bends conform to the ACI 315 Standard. reinforcing bars, the cut ends should be coated
Where large diameter bars are involved, some with the patching material that is used for repair-
amount of heating may be recommended by the ing damaged coating. Damaged epoxy coating in
architect/engineer to avoid brittle failure. the vicinity of the cut ends should also be prop-
erly repaired.
Field Cutting of Reinforcing Bars
An issue often occurring on construction proj- Lap Splices, Mechanical Splices, and
ects is concerned with the cutting of reinforcing Welded Splices
bars. The cutting envisioned in this discussion is Lap Splices. The location and length of lap
unplanned cutting. It is not the kind of cutting splices has always been a concern of the archi-
associated with field fabrication of reinforcing tect/engineer, estimator, detailer, placer, and
bars. CRSI discourages field fabrication.* inspector. The ACI 318 Building Code states that
Field cutting of reinforcing bars would be the design drawings shall show the location and
required, for example, when bars are too long as length of lap splices. The ACI 315 Standard
a result of design changes, or when errors were repeats the above requirement and further
made in detailing, fabrication, or placing. The field instructs the detailer to follow the archi-
cutting could involve overlength bars prior to their tect/engineer’s details, thus both the placing
placement in the formwork or overlength bars drawings and the structural drawings should
that are partially embedded in hardened concrete. show the same location and length of lap splices.
Chapter 12 of the ACI 318 Building Code con-
Various means are used for field cutting. For tains provisions for determining tension lap splice
smaller size bars, #10, #13 and #16, the cutting lengths. Lap splice lengths will vary due to con-
can usually be accomplished with bolt-cutters. All crete compressive strength, yield strength of the
bar sizes can be cut with an abrasive saw, or by bars, bar spacing, epoxy coating, concrete cover,
flame-cutting with an oxy-acetylene torch. and other factors. The inspector should make cer-
From our experience, questions are apt to sur- tain that the specified lap splice lengths are for
face regarding the suitability of flame-cutting, i.e., the strength criteria of the materials furnished to
will flame-cutting affect the reinforcing bars? The the job-site, and that the placer follows them.
answer is “No.” The rationale: A testing program Mechanical Splices. The ACI 318 Building Code
was undertaken to investigate the effect of flame- requires the architect/engineer to show the type
cutting reinforcing bars. The testing program: and location of mechanical splices on the design
• Covered bar sizes #16, #25, #36 and #57. drawings. If a full mechanical splice is required,
the inspector should make certain that a com-
• The test bars were Grade 420 [minimum yield pression-only mechanical splice is not furnished
strength /y = 420 MPa or 60,900 psi; Grade in error. In all cases, inspection should verify that
420 is the metric counterpart of Grade 60.] the splice manufacturer’s installation procedures
• The test bars were billet-steel conforming and any instructions in the project specifications
to ASTM A615/A615M, and low-alloy are followed. Dowel bar mechanical splices and
steel conforming to ASTM A706/A706M. lap-splice connector systems are used to replace
prebent or other types of dowels which connect
* According to the CRSI Manual of Standard Practice, “It is rec-
two separate pours of a reinforced concrete
ommended that all reinforcing bars be shop fabricated and so
specified by the architect/engineer, as operations can be per-
structure. The type and location should be
formed with greater accuracy in the shop.” approved by the architect/engineer.

5
Welded Splices. Welded splices of reinforcing The Uniform Building Code includes excep-
bars present the same difficulty of inspection as tions regarding tack welding. Section 1907.5.4
welded structural steel connections. The ACI 318 states: “Welding of crossing bars shall not be
Building Code (Section 3.5.2) states: “. . . Type permitted for assembly of reinforcement.” The
and location of welded splices and other required provision is followed by:
welding of reinforcing bars shall be indicated on “EXCEPTIONS:
the design drawings or in the project specifica-
tions.” Section 3.5.2 also requires: “Welding of 1. Reinforcing steel not required by design.
reinforcing bars shall conform to ‘Structural
2. When specifically approved by the building
Welding Code — Reinforcing Steel (ANSI/AWS
official, welding of crossing bars for assem-
D1.4)’ of the American Welding Society.”
bly purposes in Seismic Zones 0, 1 and 2
It should be noted, under the AWS Welding may be permitted, provided that data are
Code, the architect/engineer is not obliged to submitted to the building official to show
specify the welding procedures to be used. that there is no detrimental effect on the
Rather the Welding Code requires the contractor action of the structural member as a result
to prepare written welding procedure specifica- of welding of the crossing bars.”
tions (WPS’s) for the welded splices.
Conclusions
Regarding inspection activities at the job-site,
the inspector should review the mill test report All the foregoing seems to indicate that the
for the reinforcing bars to determine the carbon inspector has a formidable assignment when
equivalent (C.E.) and the preheat requirements. inspecting in-place reinforcing bars. This impres-
The inspector should verify the welder’s certifi- sion is not necessarily true, but it is an exacting
cation, make certain that the correct electrodes task, one that assures the workers perform their
(oven dry) are available, and that the preheat job to the best of their ability. However, mistakes
temperature crayon sticks are at hand. can and will happen, but an inspector is expect-
Continuous inspection is usually specified to ed to find them and have them corrected. All
ascertain that the welder uses the proper num- persons involved in a construction project, from
ber of passes, controls the interpass heat loss, the architect/engineer to the contractor, attempt
and uses a wire brush and chipping hammer to to do error-free work. A quality control program
remove any slag. by the contractor helps in achieving this goal,
which makes final inspection easier. The inspec-
For some projects, the contract documents will tor should not perceive his role as adversarial,
require radiographic inspection of the welded but as complementary to the workers in support
splices. This procedure is time consuming and of good construction techniques and practice.
costly, and is frequently inconclusive. More often Good inspection is assurance of a properly built
a specimen taken at random is removed for a lab- structure, one which all parties involved in the
oratory tension test and analysis. process can take pride.
The inspector should not allow field tack welding For further information on inspection, tolerances,
of reinforcing bars. Tack welding can cause a met- industry standard practices, fabricating, placing
allurgical notch which reduces strength and can and splices, consult the following references.
also have a detrimental effect on ductility and
fatigue resistance. Tack welding is not a substitute References
for tie wire for the assembly of reinforcing bars. “Standard Specifications for Tolerances for
The above recommendation, namely, “should Concrete Construction and Materials (ACI 117-
not allow field tack welding” for assembly of rein- 90),” American Concrete Institute, Farmington
forcing bars, should not be construed as a blan- Hills, Michigan.
ket prohibition of all tack welding. Shop fabrica- “Details and Detailing of Concrete Reinforce-
tion practices have emerged, mainly on the West ment (ACI 315-99),” Manual of Concrete
Coast, of using special high-technology welding Practice, Part 3, 2001, American Concrete
machines to tack weld low-alloy steel (ASTM Institute.
A706/A706M) reinforcing bars. Tests have con- ACI Detailing Manual — 1994, Publication SP-
firmed that the controlled welding process in 66, American Concrete Institute.
conjunction with the low-alloy steel reinforcing
bars is not detrimental. “Building Code Requirements for Structural
Concrete (ACI 318-99) and Commentary (ACI
318R-99),” American Concrete Institute.

6
“Specifications for Structural Concrete (ACI Terminology
301-99),” American Concrete Institute.
The source of the following terms and their defi-
“Standard Specification for Deformed and Plain nitions is “Specifications for Structural Concrete
Billet-Steel Bars for Concrete Reinforcement (ACI 301-99)”.
(A615/A615M-01),” ASTM, West Conshohock-
en, Pennsylvania. Architect/Engineer or Engineer/Architect —
The architect, engineer, architectural firm, engi-
“Standard Specification for Low-Alloy Steel De- neering firm, or architectural and engineering
formed and Plain Bars for Concrete Reinforce- firm, issuing project drawings and project speci-
ment (A706/A706M-01),” ASTM. fications, or administering work under the con-
“Standard Specification for Epoxy-Coated Steel tract documents.
Reinforcing Bars (A775/A775M-01),” ASTM.
Project Drawings — The drawings that, along
“Standard Specification for Epoxy-Coated Prefab- with project specifications, complete the descrip-
ricated Steel Reinforcing Bars (A934/A934M-01),” tive information for constructing the work requir-
ASTM. ed or referred to in the contract documents.
“Standard Specification for Zinc-Coated (Gal- Project Specifications — The written docu-
vanized) Steel Bars for Concrete Reinforcement ments that specify requirements for a project in
(A767/A767M-00b),” ASTM. accordance with the service parameters and
“Standard Specification for Deformed and Plain other specific criteria established by the owner.
Stainless Steel Bars for Concrete Reinforcement
[Metric] (A955M-96),” ASTM. Contract Documents — Documents, including
the project drawings and project specifications,
“Standard Specification for Welded or Forged Headed covering the required work.
Bars for Concrete Reinforcement (A970/A970M-
98),” ASTM. Work — The entire construction or separately
identifiable parts thereof that are required to be
“Standard Specification for Rail-Steel and Axle- furnished under the contract documents; work is
Steel Deformed Bars for Concrete Reinforce- the result of performing services, furnishing
ment (A996/A996M-01),” ASTM. labor, and furnishing and incorporating materials
Manual of Standard Practice, 27th Edition, 2001, and equipment into the construction in accor-
CRSI. dance with the contract documents.
Placing Reinforcing Bars, 7th Edition, 1997, CRSI.
Soft Metric Reinforcing Bars
Reinforcement Anchorages and Splices, 4th
Edition, 1997, CRSI. It is important for readers of this document to
be aware of current industry practice regarding
“Using Soft Metric Reinforcing Bars in Non- soft metric reinforcing bars. The term “soft met-
Metric Construction Projects,” Engineering Data ric” is used in the context of bar sizes and bar size
Report No. 42, CRSI. designations. “Soft metric conversion” means
“Commonly Asked Technical Questions Con- describing the nominal dimensions of inch-pound
cerning Cast-in-Place Reinforced Concrete reinforcing bars in terms of metric units, but not
Construction,” Engineering Data Report No. 44, physically changing the bar sizes. In 1997, pro-
CRSI. [See discussion of Field Bending of Rein- ducers of reinforcing bars (the steel mills) began
forcing Bars and Welded Splices of Reinforcing to phase in the production of soft metric bars.
Bars.] Within a few years, the shift to exclusive produc-
“Field Inspection of Reinforcing Bars”, 25-minute tion of soft metric reinforcing bars was essential-
Video, 1998, CRSI. ly achieved. Virtually all reinforcing bars current-
ly produced and used in the USA are soft metric.
“Field Handling Techniques for Epoxy-Coated
The steel mills’ initiative of soft metric conver-
Reinforcing Bars”, a Reference Guide and Video,
sion enables the industry to furnish the same
1996, CRSI.
reinforcing bars to inch-pound construction proj-
Structural Welding Code—Reinforcing Steel ects as well as to metric construction projects,
(ANSI/ AWS D1.4-98), American Welding and eliminates the need for the steel mills and
Society, Miami, Florida. fabricators to maintain a dual inventory. Thus,
Uniform Building Code, 1997, International USA-produced reinforcing bars furnished to any
Conference of Building Officials, Whittier, construction project most likely will be soft metric.
California.

7
Designations of Bar Sizes. The sizes of soft ric bar, which is the counterpart of an inch-pound
metric reinforcing bars are physically the same #8, Grade 60 bar. Regarding the bar size and
as the corresponding sizes of inch-pound bars. grade, the ASTM specifications require the num-
Soft metric bar sizes, which are designated #10, ber “25” to be rolled onto the surface of the met-
#13, #16, and so on, correspond to inch-pound ric bar to indicate its size. For identifying or des-
bar sizes #3, #4, #5, and so on. The metric bar ignating the yield strength or grade, the ASTM
designations are simply a re-labeling of the inch- specifications provide an option. A mill can
pound bar designations. The following table choose to roll a “4” (the first digit in the grade
shows the one-to-one correspondence of the soft number) onto the bar, or roll an additional longi-
metric bar sizes to the inch-pound bar sizes. tudinal rib or grade line to indicate Grade 420.
Soft Metric Bar Sizes vs. Inch-Pound Chapter 1 in the CRSI Manual of Standard
Bar Sizes Practice includes a detailed presentation of the
inch-pound and metric requirements in the ASTM
Soft Metric Bar Inch-Pound Bar specifications for reinforcing bars. Appendix A in
Size Designation Size Designation the Manual shows the bar marks used by USA
producers to identify Grade 420 soft metric bars.
#10 #3
#13 #4 More information about soft metric reinforcing
#16 #5 bars is also provided in Engineering Data Report
No. 42, “Using Soft Metric Reinforcing Bars in
#19 #6 Non-Metric Construction Projects”. EDR No. 42
#22 #7 can be found on CRSI’s Website at
#25 #8 www.crsi.org.
#29 #9
#32 #10 CRSI Website
#36 #11 Readers of this report are also encouraged to
#43 #14 visit the CRSI Website for:
#57 #18 • Descriptions of CRSI publications and soft-
ware, and ordering information
Minimum Yield Strengths or Grades. Virtually
all steel mills in the USA are currently producing • Institute documents available for download-
reinforcing bars to meet the metric requirements ing
for tensile properties in the ASTM specifications. • Technical information on epoxy-coated rein-
Minimum yield strengths in metric units are 300, forcing bars
350, 420 and 520 MPa (megapascals), which are
equivalent to 40,000, 50,000, 60,000 and 75,000 • Technical information on continuously rein-
psi, respectively. Metric Grade 420 is the coun- forced concrete pavement
terpart of standard Grade 60. • Membership in CRSI and member web
Bar Marking. Soft metric reinforcing bars are links
required to be identified with the producer’s mill • General information on the CRSI
designation, bar size, type of steel, and minimum Foundation
yield strength or grade. For example, consider the
marking requirements for a #25, Grade 420 met- • Information on the CRSI Design Awards
competition

This report No. 49 replaces EDR No. 36.

CONCRETE REINFORCING STEEL INSTITUTE


933 N. Plum Grove Road, Schaumburg, Illinois 60173-4758
Phone: 847/517-1200 Fax: 847/517-1206
www.crsi.org
This publication is intended for the use of professionals competent to evaluate the significance and limita-
tions of its contents and who will accept responsibility for the application of the material it contains. The
Concrete Reinforcing Steel Institute reports the foregoing material as a matter of information and, there-
fore, disclaims any and all responsibility for application of the stated principles or for the accuracy of the
sources other than material developed by the Institute.

DPG ALF 1001 28M 8 Printed in U.S.A.

Вам также может понравиться