Вы находитесь на странице: 1из 9

ENGINEER - Vol. XXXVIII, No. 02, pp.

65-73,2005
© T h e Institution of Engineers, Sri Lanka

An Overview of the Recent Design and Construction of


High Voltage Transmission Lines in Sri Lanka
G. R. V. Perera

Abstract: The construction of high voltage overhead transmission systems is a key element in electricity
infrastructure development in any country. With about 45% of the homes in Sri Lanka yet to be electrified
and the high demand growth in the areas already electrified, we will invariably have many electricity
system development projects in our national electricity network in the near future. Construction of long
lengths of high and medium voltage transmission lines and a large number of grid substations will be an
integral part of this development process.

The development of local expertise in this field of design, manufacturing and construction of high voltage
transmission lines and related electricity transmission and distribution systems and the turnkey
construction of these projects, entirely by Sri Lankan Companies in recent years, have become a great
advantage to the power sector of the nation. Maximizing similar local inputs into power sector
development activities need to be encouraged by the authorities in order to reduce costs and keep
electricity prices down.

1. Introduction In this context, this paper confines its discussions


to the design and constructional aspects of high
Sri Lankan engineers have been involved in the voltage electricity transmission lines in Sri Lanka.
design and construction of major power projects
including generation projects (both hydro and
2. The need for high voltage
thermal), transmission and grid systems, and
transmission lines. '
distribution networks over the past several
decades. Originally, they worked as counterparts Virtually, all the hydropower-generating schemes
for foreign contractors (For example -ABB are located far away from the main load centres
(Germany/Norway), Betonmast As (Germany), of the country. They are located, for obvious
Sri-U thone (Thailand), KEC (India), Hyundai reasons, in the central hills of the country, where
(Korea), etc.) but, during the last few years, water resources are naturally found. The power
several such projects have been designed and
generated in these remote places is transmitted
constructed entirely by the Sri Lankan engineers
to load centres, which are invariably in and
(From LTL Projects (Pvt.) limited (Sri Lanka))
around the major cities.
utilizing their own technical know-how, past
experience, knowledge and expertise. They were Though, theoretically, the thermal power schemes
able to successfully compete in a number of can be located anywhere in the country, certain
international tenders. Therefore, the capability of constraints such as the cost of fuel transport, the
Sri Lankan engineers or their knowledge and need to m i n i m i z e transmission losses and
expertise in handling major power projects are environmental concerns, have restricted them too
not in question any more. to pre-identified areas in the island and the power
will have to be transmitted from such locations
We have two main hydropower-generating to the load centers. ( F o r example - Two 100MW
complexes (Laxapana and Mahaweli) and a diesel power plants are recently under
number of thermal power plants. In addition, Sri construction at Puttalam and Embilipitiya)
Lanka has an interconnected grid system that
operates at 220 kV and 132 kV. Around 90% of The interconnected grid system of the country is
the total 1700 km of the transmission network designed and developed to achieve optimum
operates at 132 kV. The distribution network results with concerns for minimizing generation
consists of over 15,000 km of 33 kV and 2500 km
of 11 kV lines; the total length of the low voltage
(400 kV) distribution system exceeds 56,000 km. Eng. G. R. V. Perera, BSc. Eng, C.Eng. MIE(SL), Presently
working as a Project Engineer at Lanka Transformers
Limited -

65
costs, and reducing transmission and distribution Also to minimize the c o n s t r u c t i o n and
losses. operational cost,

For minimizing the transmission losses of power • Length of the Transmission line should
during long distance power transmissions, be minimized.
appropriate voltage levels for transmission have • Cost of c o n s t r u c t i o n s should be
to be selected. The level of voltage will vary minimized.
according to the requirements, such as distance
to be delivered, capacity of transmission line, cost But, to maximize the energy delivering capacity,
of constructions, etc. However, l l k V , 33kV,
• Cross sectional area (Size) of the
132kV and 220kV voltage levels are used in the
conductor can be increased
national electricity power transmission and
distribution network in Sri Lanka. • Higher voltage levels can be used.

During the preliminary design steps, designers


3. Design of transnussion lines and ifs try to reach a balance between the aforesaid
profile or arrangements. different requirements, which are counter to each
other and try to get the most practical solutions
3.1 Preliminary design with optimal results. However, in the next detail
designing stage all these solutions will be
The prime purpose of having high voltage
reconsidered and modified to accommodate
transmission lines is to transmit electricity energy
safety requirements, environmental concerns, and
from one place to another as economically and
also to conform and comply with the relevant
reliably as possible. Therefore, the concept behind
public regulations and laws of the country.
the p r e l i m i n a r y d e s i g n i n g p r o c e s s also is
transmitting the maximum energy between two
3.2 Profile design of the conductors.
points within reasonable cost and appropriate
safety margins. The construction and maintenance The main requirement of this process is to ensure
of high voltage transmission lines is a high cost that the live conductors are kept at an acceptably
operation. It must be realized that at the end of safe distance away from other structures, ground,
the day all the above construction, maintenance etc. These minimum distances (clearances) to be
and operational costs of transmission and maintained are different to each category of
distribution systems will be passed on to the structures and they are clearly defined in the
customer. But, from the point of power related regulations, and in the specifications too.
transmission, the tower structures are non­
productive items. The general breakdown of the
installed cost of a typical 132kV line in Sri Lanka
is as follows,

Productive cost
Conductors 30 - 40 %

Non-productive cost
Foundations 10 - 20%
Towers 30 - 45%
Fittings, insulators, earth wire, etc. 5 -15%
Land compensations, etc 10 - 1 5 %
Therefore, the non-productive costs are much
higher than the productive cost of the conductor
and the towers and foundations constitute the
major component of the non-productive cost. This
Figue (61)- Selecting a profit of conductor
underlines the importance of cost effective,
optimum designs and construction work, without
compromising on the safety and reliability of the
transmission lines.

66
For example, some main clearances that need to a growing need for higher power density and
be taken care of are as follows, compact lines and due to the greater emphasis
being laid on preservation of natural environment
1. M i n i m u m c l e a r a n c e b e t w e e n live many innovative configurations like guyed
conductors and ground, roads, roofs, towers and chainette towers are also available.
buildings, etc.
2. Minimum clearance between two live
conductors in the same line
3. M i n i m u m c l e a r a n c e b e t w e e n live
conductor and other structural parts in
the transmission line itself (such as cross
arms, etc.)
4. Safety of the personnel engaged on
maintenance work.

After preliminary assessments of the path of the


proposed transmission line and level of voltage,
capacity, arrangement of conductors, etc. the The design of transmission line structures
detailed survey works are started. From this involves careful optimization between reliability
survey details, decisions and conclusions are and economy, that is, getting the structure at the
made with regard to the land surface profile and least cost with m a x i m u m reliability. T h e
the heights of the existing structures (Buildings, structural design of the towers is mainly governed
LT line, Telephone line crossing, etc.) and other by the combination of wind load and the other
obstacles in the path of the proposed transmission loads due to conductors, line deviations, broken
line. wire c o n d i t i o n s , c a s c a d i n g , erection and
maintenance. The stress calculations in self-
However, as a first step, designers will draw the supported steel lattice towers are usually based
calculated profile of the c o n d u c t o r for the on conventional linear elastic analysis and this is
maximum design sag condition. (For example, 75 generally found to be adequate, as the deflections
degree/ 350m wind span / No wind conditions). are small in most cases.
Thereafter, the towers will be located in the given
surveyed land profile d r a w i n g , using the Historically, the steel transmission line tower
aforesaid calculated profile of conductors and design has been based on truss modeling where
keeping the lowermost conductor in accordance the angle members only carry compression and/
with the required ground clearances, etc. During or tension loads. These axial forces are then
this trial and error process of locating towers, the compared with calculated strengths based on
span between each tower, height and location of standards such as ASCE-10 (Standard code of
tower, etc., are determined. practice for design of lattice steel transmission
structures published by The American Society of
Most o f the present day transmission line Civil Engineers). This design method has been
designers are using special computer programs proven fairly accurate when compared with full-
for this profile designing work. These computer scale testing.
programs give more flexibility to try various
sensitivity c h e c k s on p o s s i b l e different However, the present design of members of the
arrangements and select the most economical towers is based on the u l t i m a t e strength
arrangement of the towers for the proposed approach. The specific loads are multiplied by
transmission line. appropriate load / safety factors according to the
specifications. The most important step in the
design of towers is the calculation of the buckling
5. Design of related structures such as
stress, which depends on the effective lengths of
steel lattice structures, pylons, etc.
various members. Even though guidelines are
Traditionally, the transmission line towers were available in the a b o v e design codes, right
self-supporting (free s t a n d i n g ) type of understanding and experience are required to use
configuration. However, more recently, there is the guidelines appropriately and to detail the

67
structure a c c o r d i n g l y s o that it w o u l d b e h a v e in
Figure (OJ)
the w a y it is e x p e c t e d in the design.

The prime purpose of the c o n d u c t o r is for efficient


p o w e r t r a n s m i s s i o n a n d t h e e a r t h w i r e is
protecting the a b o v e line c o n d u c t o r s from over
v o l t a g e s c a u s e d by l i g h t i n g , by s c r e e n i n g or
s h i e l d i n g t h e m . B u t , the a r r a n g e m e n t o r t h e
architecture of self-supporting towers d e p e n d s on
the various requirements. Therefore, the
a r r a n g e m e n t of c o n d u c t o r s and earth wire also
can be c h a n g e d a c c o r d i n g l y .

D u r i n g the structural designing, all the towers • S u s p e n s i o n t o w e r s - T h e s e s t r u c t u r e s are


h a v e to satisfy t w o s e t s of d e s i g n c o n d i t i o n s , designed o n l y to c a r r y the w e i g h t of
" N o r m a l c o n d i t i o n " , w h e n all the c o n d u c t o r s are c o n d u c t o r s in s t r a i g h t - l i n e p o s i t i o n s o f
loaded to tower as per basic design a r r a n g e m e n t s transmission line. Therefore, all the
or service conditions. " B r o k e n w i r e c o n d i t i o n " , c o n d u c t o r c a b l e s c o n t i n u o u s l y run through
w h e n any one or m o r e c o n d u c t o r s are broken, these towers
then, b r o k e n w i r e c o n d i t i o n i n v o l v e s w o r k i n g
• Tension t o w e r s - T h e s e towers are designed
through a n u m b e r of alternatives. Different safety
to terminate the c o n d u c t o r s at each cross arm
m a r g i n s will be e m p l o y e d for t h e a b o v e t w o
of the t o w e r and therefore they can take the
different conditions. (Refer Table (01)).
tension load of the cables too. T h e continuity
T a b l e (01) of the cable for electricity p o w e r transmission
G e n e r a l safety f a c t o r s for different loading will be provided by a s e p a r a t e j u m p e r loop.
conditions Tension towers are generally used for
Condition Safety factor turning points and for the section separating
l o c a t i o n s (in the s t r a i g h t s e c t i o n s ) in the
1 Normal condition 2.5 to 3.0
transmission lines.
2 Broken w i r e c o n d i t i o n 1.25 to 1.5
T h e piece of line from one tension tower to the
In Sri L a n k a , a b o v e the 33 k V v o l t a g e level, steel next is called a section. T h e length of the single
lattice structures ( s t e e l p y l o n s / t o w e r s ) only are section mainly d e p e n d s on the land profile All
used. W h e n c o n s i d e r i n g the single transmission t h e o t h e r t o w e r s in b e t w e e n t h e t w o t e n s i o n
line, it will consist of m a n y different types and t o w e r s will b e s u s p e n s i o n t o w e r s . T h e m o s t
configurations of steel lattice structures. But there economical and lightweight structures in
are two main types of steel lattice structures in transmission lines are s u s p e n s i o n towers. M o r e
any transmission lines, (Refer Figure (04)). than 6 0 % of towers will be s u s p e n s i o n towers in
any transmission line.

Basically, there are different types of tension and


suspension towers available during the designing
of n e w p o w e r transmission lines. (Refer Table-
(02))

T o w e r s of different heights can be obtained by


t.l ("I M
using b o d y e x t e n s i o n s to the s t a n d a r d h e i g h t
t o w e r s . Also, using different leg e x t e n s i o n s to
each leg can c o m p e n s a t e for different levels in the
t o w e r b a s e (Refer Figure (07)). During the
d e s i g n i n g of t o w e r s , three different s p a n s a r e
usually e m p l o y e d . Basic span for c o m p u t i n g the
m a x i m u m sag b e t w e e n t w o towers: W i n d span
N I M - I W k V -,vi.- • m e a n s half the wind load on the s p a n s on either
side of a t o w e r that should be taken by
Table (02)
Approximate steel weight of towers.

Item Type of tower Notation Approximate steel weight


(for basic wind span=360m) of single tower
(ZEBRA conductor)
1 Suspension tower (or Line tower) TDL 4.0 ton
2 0 - 1 0 degree tension towers. TD1 6.0 ton
3 10 - 30 degree tension towers TD3 7.5 ton
4 30- 60 degree tension towers TD6 12.0 ton
5 Terminal towers TDT 15.0 ton
6 Special towers such as river crossing 20 - 200 ton
towers, etc

Table (03)
General wind & weight spans for each type of tower

Type of Basic wind span - Allowable maximum weight span (in metres)
tower at normal
condition Normal condition Broken wire condition
(in metres) Maximum Minimum Maximum Minimum

TDL 360 600 - 450 -


TD1 360 900 -300 675 -200
TD3 360 900 -300 675 -200
TD6 360 900 -300 675 -200
TDT 360 450 - 300 -

the tower. Therefore the wind span is the main data is taken from the recently completed
deciding factor of the span between any two transmission line, which links one of the hydro
towers in the transmission line. Weight span power generating projects to the national
refers to the total weight of conductor on both electricity grid system in Sri Lanka.
sides that may occur to each of the towers. This
will change according to the profile of the land. When the ordinary suspension (TDL) towers are
[Refer Figure (05)) not strong enough to take the specific wind span
in a transmission line, one of above tension towers
BakSt ( Refer Figure-(06) ) can be used as a heavy
Wind Spoil suspension tower for that location after rechecking
and confirming the design calculations. This type
TtmC of situation frequently arises during the designing
of transmission lines in steep mountainous
terrains.

The transmission line profile designers use towers


of different heights for inclusion in different
locations according to the available land profile.
Therefore the tower designers initially design
each tower (TDL, TD3, etc.) to it's maximum
height (Approx 40 - 50 m) and
Apart from the above data (Table (03)) for basic
weight span and angle of towers, we can utilize
above towers as described in figure 06 too. This

69
Figuer 06 - Wind span vs Angle of 6. Mantifacturing of steel lattice
riiviatinn,
structures / pylons and cables

6.1 Manufacturing and testing of towers

After the completion of the designing process, the


fabrication drawings are prepared. The
fabrication e n g i n e e r must have a s o u n d
knowledge of the total design and construction
aspects such as Structural designs, Profile designs,
Materials and Fabrication, Transport and Tower
erection p r o c e d u r e s , C a b l e s t r i n g i n g and
the architecture of those towers are arranged with tensioning and the behavior of the towers during
flexibility to reduce their height steo by step (For the actual site loading conditions, etc.
Example - Reducing body extensions by 3.0 m
The fabrication of tower parts, in lattice towers,
steps) according to the site requirements. All
generally involves a large volume of repetitive
towers with reduced heights/body extensions
work. T h e r e f o r e , the use of n u m e r i c a l by
will be re-checked with the design calculations
controlled punching; drilling, and hard stamping
before use. One such architecture of the tower is
machines are very common features in the
shown in figure (07).(This is a locally designed
modern steel fabricating industry. By the use of
steel lattice tower arrangement /architecture
such high tech machines the quality as well as
which has been used in the Kukule - Matugama
the speed of the manufacturing process are
132kV transmission line)
enhanced.

The fabrication tolerances, also, are of prime


Figure:(07)
Body extensions importance. Therefore, it is a normal practice to
and Ijea. extensions specify the tolerances required at the initial stages
itself. These tolerances would cover such aspects
as hole diameter, edge distance, end distances,
hole center, length of bars, straightness, etc.
Note:

The required tower heights Basic Tower As a first step of fabrication, a prototype structure
can be obtained by ItO tower)
must be fabricated and erected in the fabrication
using different body . 28.0 m height I
extensions accordingly. factory premises under the design and fabrication
engineers' direct supervision. During this process
(Eg:-l\0^}.+6.+9,U2)\
almost all the fabrication and erection difficulties
and problems can be solved. Then the prototype
tower should be tested and verified for the
various loads and the combinations of loads that
are considered during the designing process.
•6m body
extensk) These full-scale tests are essential not only to
12m body
extension verify the design, but also to check the quality of
different leg
extensions materials, detailing, quality of fabrication,
-1m leg assembly and erection. The testing facility and
-Om leg
•1m leg procedures adopted should give confidence to the
•2m teg 1m H
•3m leg Int. designer, fabricator and the user agency.

This type of testing can be done in testing bays


The structural analysis and design of structural
available in India or Thailand. However the "art"
members of the above lattice structures are also
in tower design, that is not readily available in
done with the help of computer programs in
textbooks, can be a c h i e v e d only through
recent times. Therefore, the structural engineers
experience. This experience is essential to avoid
can a c h i e v e the m o s t a c c u r a t e as well as
certain pitfalls, which, in practice, are found to
economical results without difficulties.
cause premature failures. But this type of mistakes

70
cannot be detected by c a l c u l a t i o n s alone and can T h e optical fiber i n c o r p o r a t e d c o n d u c t o r s and
only be verified in full scale tests. H o w e v e r , the e a r t h w i r e s a r c a l s o u s e d in h i g h voltage
m a s s s c a l e t o w e r p a r t m a n u f a c t u r i n g will b e transmission line s y s t e m s recently. This is found
started only after all these tests are satisfactorily to be a very efficient s y s t e m for c o m m u n i c a t i o n s
completed. b e c a u s e optical fibers do not have electro
magnetic induction and, as a result, there is little
A l m o s t all the structures for transmission lines, or n o interference to s i g n a l s / d a t a resulting from
are invariably hot dip galvanized after fabrication electro m a g n e t i c induction.
to provide maximum protection against
corrosion.
8. Construction of foundations and
erection of steel structures.
7. Conductors and earth wires
;
T h e f o u n d a t o n reactions are generally not high
Economically, the c o n d u c t o r and earth wire
for the com.mon lattice structures in this field.
cables represent b e t w e e n 20 to 4 0 % of the total
T h e r e f o r e , the i n d i v i d u a l pad foundations for
cost of line. T h e r e f o r e , the selection of c o n d u c t o r
each leg are the c o m m o n practice for the a b o v e
and earth w i r e is o f p r i m e i m p o r t a n c e and the
structures and the construction is also a simple
whole concept of electricity transmission and
process. Only where extremely poor soil
distribution also r e v o l v e s a r o u n d the c o n d u c t o r s
conditions are found at t o w e r locations, pre cast
and earth wires.
concrete and pile driving will b e c o m e necessary.

Although c o p p e r w a s m a i n l y used as material for


Erection of these lattice structures needs s o m e
o v e r h e a d line c o n d u c t o r s in the early days, the
skilled personnel and supervisory staff. Although
aluminum-based c o n d u c t o r s are n o w w i d e l y
m a n y different tower erection m e t h o d s are
used d u e to m a n y r e a s o n s such as price, weight,
practiced in the world, the selection of an erection
availability, etc.
m e t h o d d e p e n d s on v a r i o u s p a r a m e t e r s such as
AAC - All a l u m i n u m c o n d u c t o r s the adaptability of selected m e t h o d to each site
conditions, time and the cost, etc. H e a v y cranes
ACSR - A l u m i n u m c o n d u c t o r steel reinforced
or such o t h e r h e a v y e q u i p m e n t cannot be used
A A A C - All a l u m i n u m alloy c o n d u c t o r
in most of the transmission t o w e r locations in Sri
A C A R - A l u m i n u m c o n d u c t o r alloy reinforced L a n k a . T h e r e f o r e , a p i e c e by p i e c e e r e c t i n g
p r o c e s s ( Refer Figure-(09) ) is still t.ie only cost
The first two types are very c o m m o n in Sri Lanka,
effective m e t h o d , available to Sri Lanka.
but the other t w o types are rarely used d u e to the
high cost of materials. (Refer Figure (08)).

Figure (08) - Different types of conductores

01«CI« KIUAC P I W I I

Figure (09) - Erection of lattice tower

9. Cable installations (cable stringing


The basic selection p a r a m e t e r s for c o n d u c t o r s are and clipping)
their electromechanical p a r a m e t e r s and the price.
Earth wires differ from c o n d u c t o r s only by their After erection of the lattice structures, the cable

function, and from the point of v i e w of lightning, stringing will be c o m m e n c e d . T h i s is a special


the material is of no i m p o r t a n c e . H e n c e , in m a n y p r o c e s s , w h i c h n e e d s h i g h l y skilled l i n e s m e n ,
lines, g a l v a n i z e d steel w i r e s a r e used as earth supervisors, tools and machineries. These

wires. specialized tools and e q u i p m e n t are very costly


i t e m s a n d t h e r e f o r e o n l y s p e c i a l i z e d foreign

71
companies were involved in this type of projects twisting must be avoided because it can
until recent times. very easily cause d a m a g e s to the
aluminum conductors as well as to the
Although this process slightly differs from site to
pilot wires.
site, the main idea behind the process is as
6. The above lightweight pilot wire can be
follows:
replaced by a heavy duty (steel) pilot wire
1. The cable-stringing programme and by the process of pulling and releasing the
schedule of cable drum usage is to be two winches at the same speed. (Puller
prepared. The conductor cables are the and Tensioner ) . This operation is to be
most costly item in these constructions. done without* the wire touching the
Therefore, cable w a s t a g e s must be ground.(Refer Figure (10). The aluminum
minimized during this process. Cable c o n d u c t o r c a b l e s are also strung
jointing, transporting of heavy winches following the same procedure using the
and cable drums, temporary anchoring of heavy-d.ity pilot wires.
towers, etc. are to be considered and the
locations and m e t h o d o f stringing
Tension
carefully selected. All these items must be Suspension T o m

included in the final schedule of drum


utility.
2. Then the two (temporary) end towers are
to be well anchored to the ground and
their cross arms are also to be anchored
to the body ( As extra reinforcement for
the heavy dynamic loads that might occur
during the cable stringing operations.).
Also, the two cable stringing winches and
cable drum jacks are to be well anchored
to the g r o u n d and p r e p a r e d for
operations. 7. Thereafter, special come-along clamps
that are designed for specific conductor
3. The special cable stringing pulleys with
sizes for avoiding d a m a g e s due to
rubber sleeves (To avoid damage to the
slipping or over c o m p r e s s i o n of
aluminum conductor when the cable runs
a l u m i n u m c o n d u c t o r until it .is
through it) will be hung on the cross arms
permanently jointed will temporarily
of the towers. The special anti-twisting
clamp the conductor cable. Well-trained
and lightweight pilot wire will be kept (on
skilled workmen do the cable jointing and
the ground) along the line of towers and
termination by the process of cold-
this pilot wire will be put trough the
welding. P o r t a b l e pressing tools
above rubber-sleeved pulleys on the cross
(hydraulic or electric) are used to do this
arms of the towers.
operation.
4. Thereafter, the lightweight pilot wire
8. The final adjustment of the profile of the
should be w o u n d to the two cable
cable (Sagging) is done before final fitting
stringing winches at both ends and
of the cable" ends in section towers. The
tensioned until the lightweight pilot wire
long-term c r e e p a g e is also to be
comes well above the ground.
considered during this final sagging
5. Then the heavy duty, anti-twisting, steel operation. After sagging the conductors,
pilot wire will be attached to the above the two ends of the conductors are fitted.
light weight pilot wire. The jointing Thereafter, the rubber sleeved pulleys on
device (swivel joint) of these two wires is the suspension towers are replaced by
specially designed for releasing any suspension clamps and reinforcing rods.
twisting force accumulated in either wire Finally the vibration dampers and jumper
when r u n n i n g though the pulleys, loops will be fitted as may be necessary.
capstan wheels of winches, etc. Excessive

72
10. Testing prior to energizing the new These major developments in the fields of
transmission line engineering and manufacturing in Sri Lanka have
resulted in huge savings to the country in addition
The newly constructed transmission line has to to providing employment opportunities and
be subjected to a series of tests and inspections other benefits to the nation. Encouragement of
before the initial energizing. These tests include the d e v e l o p m e n t of i n d i g e n o u s skills and
visual inspection of cables, cable joints, insulators, expertise, similarly, in other activities in the
getting measurements such as the arcing horn power sector will greatly help to contain the
distances, resistance of j u m p e r loops, line escalation of electricity tariff.
c l e a r a n c e s and w a y l e a v e s , c h e c k i n g the
continuity of total transmission line, etc. These References
types of tests are of prime importance for the high
voltage transmission lines, because any simple 1. American Society of Civil Engineers, "Design
mistake or error can lead to serious accidents as of lattice steel transmission structures" (
well as c o s t l y d a m a g e s during the initial ASCE 10 - 9 7 ) , 1801, Alexander Bell Drive,
energizing. Reston, Virginia, 20191-4400.
2. Dan E. Jakman, "Electrical transmission in
11. Summary and Conclusions the new age" American Society of Civil
Engineers, 1 8 0 1 , Alexander Bell Drive,
The construction of a high voltage overhead Reston, Virginia, 20191-4400.
transmission s y s t e m is a special field of
3. A m e r i c a n S o c i e t y of Civil Engineers,
construction. The construction of transmission
"Guidelines for electrical transmission line
networks in the developed countries has almost
structural loading" (0ASCE Manual No. 74),
reached the saturation point. As a result, there is
1801, Alexander Bell Drive, Reston, Virginia,
a decline in the availability of specialized
20191-4400.
designers, consultants and contractors in this field
4. J . Varnakulasinghe, "132 kV transmission
on an international scale and consequently the
lines - design view points", technical paper
competitiveness has reduced. In the past, these
presented to IESL, Sri L a n k a on 10th
high voltage lines and grid substations were
September 1970.
designed and constructed for us by specialized
foreign companies, and, because of the reasons 5. J. Varnakulasinghe, "A 132kV transmission
stated above, the cost of transmission systems had network" - the paper presented to IESL, Sri
been relatively high.. Lanka on 13th March 1974.
6. P.J. Ryle, "Steel tower economics" paper
The development of local expertise in this field
published in the IEE Journal Vol 93, Part II,
of designing and construction of high voltage
No. 33 and No. 361946.
transmission lines and related e l e c t r i c i t y
7. J.F- Adam, "Overhead lines - some aspects
transmission and distribution systems in recent
of design and construction" paper published
years has come as a great advantage to the power
in the IEE Journal Vol 131, Part I, No. 5,1984.
sector of the nation. S i m u l t a n e o u s l y , the
development of the capability of manufacturing 8. Course document, "Advance course on steel
most of the necessary high voltage conductors, t r a n s m i s s i o n line and c o m m u n i c a t i o n
galvanized steel lattice towers, steel structures, towers", Structural Engineering Research
and other accessories in local factories have Centre, CSIR Campus, Chennai on December
further enhanced the advantages. 2000.
9. John McCombe and F.R. Haigh, "Overhead
The Ceylon Electricity Board has used locally
line practice".
manufactured galvanized steel structures, and
10. S.S. M u r t h y and A . R . S a n t h a k u m a r ,
high voltage aluminum (ACSR) conductors for
"Transmission line structures" McGraw-hill
several 132kV, transmission lines that were
Book Co, New Delhi, India.'
constructed in recent years. (For example, 132kV
t r a n s m i s s i o n line from K u k u l e G a n g a
Hydropower project to Mathugama, Newly
constructed B a l a n g o d a - Ratnapura 132kV
Transmission line, etc.).

73

Вам также может понравиться