Академический Документы
Профессиональный Документы
Культура Документы
1 4 5
Keystone´s cross-over
Keystone’s
A detailed review of Keystone Cement’s SF
Cross-BarTM Cooler
cross-over
Pennsylvania.
by Robert This new cooler concept had Engineer Manager of Pyroprocessing
K
eystone Cement Company is a sub- E Shenk Senior Process
sidiary of Giant Cement Holding, Technology, FLSmidth Inc
Inc and along with its sister plant
(Giant Cement) is owned by the A wet process plant operating in today’s competitive cement market must
Spanish group Cementos Portland, SA. continually look at its operations for any possible ways to maximise avail-
Keystone Cement has been an integral part ability at the highest possible efficiency to compete with the more effi-
of the Lehigh Valley’s cement manufactur- cient dry process kilns. In doing so, wet process kiln owners must keep
ing scene since 1928.
abreast of the latest technology. One such plant was looking at spending
The original plant consisted of four
state of the art wet process kilns supported over half a million US dollars in 1997 to overhaul their traditional grate
by four raw mills and four finish mills. cooler originally supplied in 1965. At the same time a cement equipment
Today, the cement manufacturing facility supplier was introducing a revolutionary new clinker cooler concept to the
consists of two wet kiln systems: Kiln#1 marketplace. This paper will focus on this cement plant’s decision to
(2.9m diameter x 106.7m long) and Kiln#2 install the very latest in clinker cooling technology as well as the results
(4.57m diameter x 167.6m long). Each kiln
and experiences after four years of operation.
was originally supplied with a traditional
grate cooler. Two (2) raw mills from 1928,
as well as a new raw mill installed in 1999, been successfully operating for almost
are used to support the two kiln lines. A six months by the time Keystone was
modern cement mill with high efficiency thinking about their 1998 budget.
classifier is utilised to produce the final After receiving the rather large
cement product. inquiry for spare parts for the existing
Keystone began utilising waste derived cooler, the equipment supplier reasoned
fuels in 1976 to offset the high fuel costs that it may be more feasible for
inherent within the wet process. By having Keystone to consider the installation of a
state-of-the-art testing, unloading, and new cooler rather than overhaul an out
storage facilities for waste fuels, Keystone dated piece of machinery. The equipment
is able to supplement upwards of 50 per supplier introduced the new clinker
cent of the fossil fuels utilised with waste cooler concept to Keystone Cement and
derived fuels in kiln #2. took them on a plant visit to the proto-
type cooler. The new cooler
Decision making process concept was a revolutionary Figure 1: comparison of conveying mechanism for traditional
During the summer of 1997, Keystone design when compared to both grate cooler (top) versus Cross-Bar Cooler, bottom
Cement was establishing its budget for fis- Keystone’s traditional grate
cal year 1998. During this time, it was cooler and the generally
foreseen that at least US$500,000 worth of accepted cooler design at the
repairs would be required for the 32-year- time (air-beam style). The new
old traditional grate cooler for Kiln #2 dur- clinker cooler design is here-
ing the annual outage in 1998. Keystone with referred to as a cross-bar
had contacted its local equipment supplier cooler due to one of its four
to insure the necessary parts would be innovative design features.
available in time for the outage. When compared to existing
In early 1997, the same equipment clinker cooling technology, the
supplier had installed the proto-type ver- cross-bar cooler introduced
sion of its revolutionary new clinker cooler four new and innovative design
concept at a cement plant in Western features:
Process comparison
Keystone’s decision
After considering the new cross-bar cooler
opens to compensate for an increase in the profile can be created through the clinker design, visiting the proto-type installation,
resistance (fine clinker or thick clinker bed, which maximises the heat transfer and the favourable ‘Lease to Own
bed) or closes to compensate for a and the heat recuperation to the kiln Option”’provided by the equipment sup-
decrease in the resistance (coarse clinker system. plier, Keystone Cement decided to install
or thin clinker bed). The MFR, thus, con- the revolutionary new cooler design rather
trols the amount of cooling air to each Modular design than overhaul its existing cooler system.
individual grate plate. It is like having an The entire cross-bar cooler is constructed The new cross-bar cooler was installed in
individual cooling air fan for every grate as a modular system with a fixed inlet March 1998, and was easily installed dur-
plate in the cooler, except that the airflow module (1.3m wide x 2.0m long or 4 x 5 ing the annual outage, due to the modular
distribution is automatically taken care of grates) followed by standard cross-bar design of the new cooler.
with the MFR rather than constant manual modules (1.3m wide x 4.2m long or 4 x 14 The cooler supplied and installed at
adjustments. Figure 5 depicts the action of grates). The standard modules are pre- Keystone was two (2) modules wide by
the MFR when faced with varying bed resis- assembled in the workshop to ensure high three (3) modules long with a two (2)
tance.
Figure 7: fixed inlet module Figure 8: Cross-Bar module
The distribution of cooling air through
the clinker bed is most important within
the recuperation zone of the clinker cooler.
On traditional grate and air-beam style
coolers, where there is not finite distribu-
tion of cooling airflow, the cooling airflow
takes the path of least resistance as it
passes through the clinker bed. With little
control of where the cooling airflow is
going through the clinker bed, an uneven
velocity profile is created through the
clinker bed, which adversely effects heat
transfer and heat recuperation back into
the kiln (refer to Figure 6). However, when
finite control of airflow is realised, by the
use of MFRs, an even velocity
Maintenance results
In addition to the substantial process
Figure 9: modular delivery and installation of fixed inlet module results achieved by the installation of the
cross-bar cooler, Keystone has realised sig-
consistently utilise waste nificant maintenance benefits as well.
fuel and has a more stable When directly compared to the traditional
burning zone than previous grate cooler on an annual maintenance
to the cross-bar cooler cost basis, Keystone is realising annual
installation. The high sec- savings of US$100,000 (minimum) on parts
ondary air temperature alone. Additional savings are also realised
helps to negate the highly due to the decreased labour cost required
variable moisture content of on the cross-bar cooler during the annual
the waste fuel. outage.
The equipment supplier The characteristics of the wear compo-
recently conducted an audit nents at Keystone Cement have been well
to evaluate the cooler per- documented over the last four years. The
Figure 10: delivery & installation of Cross-Bar modules formance over time. Figure equipment supplier and Keystone have had
12 reflects the comparison a close working relationship to continually
module wide fixed inlet. Figure 9 shows the of the performance test (1998) and the improve the design of the wear compo-
delivery and installation of the fixed inlet recent audit some four years later. This nents to a point such that it is expected
module, while Figure 10 shows the delivery comparison truly reflects the capability of that all wear components will last for two
and installation of the third cross-bar mod- the cross-bar cooler to maintain a high campaigns before requiring replacement.
ule. The total grate area of the new cooler level of efficiency over time due to the Such long wearlife is achieved due to the
is 37m2 and at a nominal kiln production of
Figure 11: performance test results
1500tpd, the cooler loading is 41tpd/m2.
Conclusion
Over the four years since the installation of
the cross-bar cooler, Keystone Cement has
realised all of the equipment supplier’s
claims for the revolutionary clinker cooler:
decreased maintenance costs, increased
thermal efficiency, decreased specific
power consumption, and increased kiln
system availability. In many areas, actual
Figure 15: kiln operational percentage with Cross-Bar cooler since installation results have exceeded expectations. This is
especially apparent when looking at the
average monthly kiln operational percent-
age of 95.9 per cent (exclusive of annual
outages). The cross-bar cooler has signifi-
cantly raised the secondary air temperature
to such an extent that Keystone can max-
imise the utilisation of waste derived fuels,
while still maintaining a stable burning
zone ensuring long refractory lifetime.
Keystone Cement’s decision to ‘Lease to
Own’ a revolutionary new cooler rather
than overhaul an outdated piece of equip-
ment has ensured themselves higher
operating margins and has positioned
themselves more competitively within the
marketplace. ______________________❒
DENMARK
F.L.Smidth
Vigerslev Allé 77
DK-2500 Valby
Copenhagen
Tel: +45 - 36 18 10 00
Fax: +45 - 36 30 18 20
Environmentally certified according to DS/EN ISO 14001 Richard Larsen Grafisk A/S
E-mail: info@flsmidth.com
INDIA
Fuller India Limited
Capital Towers
180, Kodambakkam High Road
Nungambakkam
Chennai 600 034
Tel: +91 - 44-252-191234
Fax: +91 - 44-2827-9393
E-mail: fil@fullerindia.co.in
USA
F.L.Smidth Inc.
2040 Avenue C
Bethlehem, PA 18017-2188
Tel: +1 - 610-264-6011
Tel: +1 - 800-523-9482 KN
ING 02
2
MILJØMÆR
KSAG
Fax: +1 - 610-264-6170
TRY
SK
41
DI 5
NOR
E-mail: info@flsmidth.com
www.flsmidth.com