Академический Документы
Профессиональный Документы
Культура Документы
www.biztrans.in
Introduction
Project
Introduction
Project is a series of related jobs usually directed
towards some major output and requiring a
significant period of time to perform.
Functional project
Functional Project
A functional project is housed within a
functional division
President
Research and
Engineering Manufacturing
Development
Functional project
Matrix project
Matrix Project Organization Structure
President
Research and
Engineering Manufacturing Marketing
Development
Manager
Project A
Manager
Project B
Manager
Project C
Matrix: Advantages
Pinpointed responsibility
1 Project 1 Project 2
Vertical Axis:
Always Activities Horizontal bars used to denote length
or Jobs of time for each activity or job.
Activity 1
Activity 2
Activity 3
Activity 4
Activity 5
Activity 6
Time-Cost Models
Used when cost trade-off information is a major consideration in
planning
Used to determine the least cost in reducing total project time
Steps in the CPM/PERT with Single Time Estimate
Activity Identification
• ES : Earliest start
• EF : Earliest finish
EF = ES + activity time
• LS : Latest start
• LF : Latest finish
LS = LF – activity time
• S: Slack
S=LS-ES or LF-EF
CPM with Single Time Estimate
A None 2
B A 1
C B 1
D C 2
E C 5
F D,E 5
D(2)
G F 1
E(5)
Determine early starts and early finish times
ES=4
EF=6
LS=4
LF=9
Critical Path & Slack
ES=4
Slack=(7-4)=(9-6)= 3 Wks
EF=6
Variance σ2 = [(b-a)/6]2
Activity Preceding activity a m b
1-2 - 6 8 10
1-3 - 3 6 9
1-4 - 1 3 5
2-5 1-2 0 0 0
2-6 1-2 2 4 12
3-5 1-3 2 3 4
4-5 1-4 3 4 5
4-8 1-4 2 2 2
5-7 3-5 3 7 11
5-8 3-5 2 4 6
8-7 4-8, 5-8 0 0 0
6-9 2-6 1 4 7
7-9 5-7 1 10 13
PERT or AOA diagram
5
2 6
4
8
6 3 7 9
1 3 5 7 9
4 4
3
2
4 8
Activity a m b t σ2
1-2 6 8 10 8 .44
1-3 3 6 9 6 1
1-4 1 3 5 3 .44
2-5 0 0 0 0 0
2-6 2 4 12 5 2.78
3-5 2 3 4 3 .11
4-5 3 4 5 4 .11
4-8 2 2 2 2 0
5-7 3 7 11 7 1.78
5-8 2 4 6 4 .44
8-7 0 0 0 0 0
6-9 1 4 7 4 1
7-9 1 10 13 9 4
Activity t σ2 ES EF LS LF S
1-2 8 .44 0 8 1 9 1
1-3 6 1 0 6 0 6 0
1-4 3 .44 0 3 2 5 2
2-5 0 0 8 8 9 9 1
2-6 5 2.78 8 13 16 21 8
3-5 3 .11 6 9 6 9 0
4-5 4 .11 3 7 5 9 2
4-8 2 0 3 5 14 16 11
5-7 7 1.78 9 16 9 16 0
5-8 4 .44 9 13 12 16 3
8-7 0 0 13 13 16 16 3
6-9 4 1 13 17 21 25 8
7-9 9 4 16 25 16 25 0
Computerisation of order processing system
Project variance: It’s the sum of variances on the critical
path
σ2=σ213+σ235+σ257+σ279
=1+.11+1.78+4
= 6.89 weeks
Probabilistic Network analysis
Basic assumptions in network analysis:
- activity times are statistically independent
- network mean and variance are normally distributed
Z = x-µ/σ
= 30-25/2.62 = 1.91
Z = 22-25/2.62
= -1.14
1. Find out the cost of crashing the maximum period possible and the total
project cost after crashing