Академический Документы
Профессиональный Документы
Культура Документы
Providing and laying mild steel reinforcement bars (G-60) with and including the cost of straightening,removing twists, cutting, bending, binding,wastage
such overlaps as are not shown over the drawings, placing in position on cement concrete complete in all respects.
Base
4'-8"
6''
1 Main Bars #3 9'' 2 13 26 5.68 ' 147.680
6''
2 Distribution Bars #3 9'' 2 7 14 10.68 ' 149.520 9'-8"
Slab
4'-8"
6''
1 Main Bars #3 9'' 2 13 26 5.68 ' 147.680
6''
2 Distribution Bars #3 9'' 2 7 14 10.68 ' 149.520 9'-8"
Horizontal Bars
9'-8"
6''
1 Long walls #3 9'' 2 7 14 10.68 ' 149.520
5'-8"
6''
2 Short walls #3 9'' 2 7 14 6.68 ' 93.520
Vertical Bars
5'-11"
6''
1 Long walls #4 6'' 2 18 36 6.93 ' 249.480
5'-11"
6''
2 Short walls #4 6'' 2 10 20 6.93 ' 138.600
Total Quantity = ( Rft ) 837.44 388.08 0.00 0.00
Weight per Rft in Kgs 0.170 0.303 0.473 0.682
WEIGHT OF BARS 0.260 Ton
Weight of Bars Dia Wise Kgs 142.36 117.59 0.00 0.00
Total Weight of Bars in Kgs 259.95
Page 3 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
Base
4'-8"
6''
1 Main Bars #3 9'' 2 13 26 5.68 ' 147.680
6''
2 Distribution Bars #3 9'' 2 7 14 10.68 ' 149.520 9'-8"
Slab
4'-8"
6''
1 Main Bars #3 9'' 2 13 26 5.68 ' 147.680
6''
2 Distribution Bars #3 9'' 2 7 14 10.68 ' 149.520 9'-8"
Horizontal Bars
9'-8"
6''
1 Long walls #3 9'' 2 7 14 10.68 ' 149.520
5'-8"
6''
2 Short walls #3 9'' 2 7 14 6.68 ' 93.520
Vertical Bars
5'-11"
6''
1 Long walls #4 6'' 2 18 36 6.93 ' 249.480
5'-11"
6''
2 Short walls #4 6'' 2 10 20 6.93 ' 138.600
Total Quantity = ( Rft ) 837.44 388.08 0.00 0.00
Weight per Rft in Kgs 0.170 0.303 0.473 0.682
WEIGHT OF BARS 0.260 Ton
Weight of Bars Dia Wise Kgs 142.36 117.59 0.00 0.00
Page 4 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
3 U.G.W. Tank
Base
5'-8"
6''
1 Main Bars #3 9'' 2 11 22 6.68 ' 146.960
6''
2 Distribution Bars #3 9'' 2 7 14 9.68 ' 135.520 8'-8"
Slab
5'-8"
6''
1 Main Bars #3 9'' 2 11 22 6.68 ' 146.960
6''
2 Distribution Bars #3 9'' 2 7 14 9.68 ' 135.520 8'-8"
Horizontal Bars
8'-8"
6''
1 Long walls #3 9'' 2 10 20 9.68 ' 193.600
5'-8"
6''
2 Short walls #3 9'' 10 0 6.68 ' -
Vertical Bars
6'-11"
6''
1 Long walls #4 6'' 2 16 32 7.93 ' 253.760
Page 5 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
6'-11"
6''
2 Short walls #4 6'' 2 12 24 7.93 ' 190.320
Total Quantity = ( Rft ) 758.56 444.08 0.00 0.00
Weight per Rft in Kgs 0.17 0.30 0.47 0.68
WEIGHT OF BARS 0.264 Ton
Weight of Bars Dia Wise Kgs 128.96 134.56 0.00 0.00
Total Weight of Bars in Kgs 263.51
4 O.H.W. Tank
Base
4'-8"
6''
1 Main Bars #3 9'' 2 10 20 5.68 ' 113.600
Page 6 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
6''
2 Distribution Bars #3 9'' 2 7 14 7.68 ' 107.520 6'-8"
Slab
4'-8"
6''
1 Main Bars #3 9'' 2 10 20 5.68 ' 113.600
6''
2 Distribution Bars #3 9'' 2 7 14 7.68 ' 107.520 6'-8"
Horizontal Bars
6'-8"
6''
1 Long walls #3 9'' 2 6 12 7.68 ' 92.160
4'-8"
6''
2 Short walls #3 9'' 2 6 12 5.68 ' 68.160
Vertical Bars
4'-11"
6''
1 Long walls #4 6'' 2 14 28 5.93 ' 166.040
4'-11"
6''
2 Short walls #4 6'' 2 10 20 5.93 ' 118.600
Total Quantity = ( Rft ) 602.56 284.64 0.00 0.00
Weight per Rft in Kgs 0.17 0.30 0.47 0.68
WEIGHT OF BARS 0.189 Ton
Weight of Bars Dia Wise Kgs 102.44 86.25 0.00 0.00
Total Weight of Bars in Kgs 188.68
Rain Water Tank of
5 B.F
Base
3'-8"
6''
1 Main Bars #3 9'' 2 13 26 5.68 ' 147.680
6''
2 Distribution Bars #3 9'' 2 6 12 10.68 ' 128.160 9'-8"
Slab
3'-8"
6''
1 Main Bars #3 9'' 2 13 26 5.68 ' 147.680
6''
1 Distribution Bars #3 9'' 2 6 12 10.68 ' 128.160 9'-8"
Horizontal Bars
9'-8"
6''
1 Long walls #3 9'' 2 7 14 10.68 ' 149.520
5'-8"
6''
2 Short walls #3 9'' 2 7 14 6.68 ' 93.520
Vertical Bars
4'-11"
6''
1 Long walls #4 6'' 2 18 36 5.93 ' 213.480
4'-11"
6''
2 Short walls #4 6'' 2 10 20 5.93 ' 118.600
Total Quantity = ( Rft ) 794.72 332.08 0.00 0.00
Weight per Rft in Kgs 0.17 0.30 0.47 0.68
WEIGHT OF BARS 0.236 Ton
Weight of Bars Dia Wise Kgs 135.10 100.62 0.00 0.00
Total Weight of Bars in Kgs 235.72
Page 8 of 111
PLOT# 49, SEC-1, PHASE(VIII)
BAR SHAPE
4'-8" 6''
6''
9'-8"
4'-8" 6''
6''
9'-8"
9'-8" 6''
5'-8" 6''
Page 9 of 111
ULE OF SECOND FLOOR SLAB
BAR SHAPE
5'-11" 6''
5'-11" 6''
0.260 Ton
Page 10 of 111
ULE OF SECOND FLOOR SLAB
BAR SHAPE
4'-8" 6''
6''
9'-8"
4'-8" 6''
6''
9'-8"
9'-8" 6''
5'-8" 6''
5'-11" 6''
5'-11" 6''
0.260 Ton
Page 11 of 111
ULE OF SECOND FLOOR SLAB
BAR SHAPE
0.260 Ton
5'-8" 6''
6''
8'-8"
5'-8" 6''
6''
8'-8"
8'-8" 6''
5'-8" 6''
6'-11" 6''
Page 12 of 111
ULE OF SECOND FLOOR SLAB
BAR SHAPE
6'-11" 6''
0.264 Ton
4'-8" 6''
Page 13 of 111
ULE OF SECOND FLOOR SLAB
BAR SHAPE
6''
6'-8"
4'-8" 6''
6''
6'-8"
6'-8" 6''
4'-8" 6''
4'-11" 6''
4'-11" 6''
0.189 Ton
Page 14 of 111
ULE OF SECOND FLOOR SLAB
BAR SHAPE
3'-8" 6''
6''
9'-8"
3'-8" 6''
6''
9'-8"
9'-8" 6''
5'-8" 6''
4'-11" 6''
4'-11" 6''
0.236 Ton
Page 15 of 111
CONSTRUCTION OF PLOT# 49, SEC-1, PHASE(VIII)
Discription of item.
Providing and laying mild steel reinforcement bars (G-60) with and including the cost of straightening,removing twists, cutting, bending, binding,wastage,
overlaps as are not shown over the drawings, placing in position on cement concrete complete in all respects.
Basement Floor
A Foundation
1 Piles
12''
1 Dowels #4 25 8 200 0.00 38'
3"
2 Stirrups #3 6'' 2 81 162 0.00
Total Quantity = ( Rft ) 0.00 0.00 0.00 0.00
Weight per Rft in Kgs 0.17 0.30 0.47 0.68
WEIGHT OF BARS Weight of Bars Dia Wise Kgs 0.00 0.00 0.00 0.00 0.000 T
Total Weight of Bars in Kgs 0.00
2 Bottom Bars
1 X-Direction Bars
25'
6''
1 Main bars at A'-B/4-8 #4 9'' 1 9 9 26.00 ' 234.00
39'-8"
6''
2 Main bars at B-D/4-10 #4 9'' 1 9 9 40.75 ' 366.75
61'-6"
6''
3 Main bars at D-F/1'-10 #4 9'' 1 18 Page 16 of18
111 62.50 ' 1125.00
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
54'-6"
6''
4 Main bars at F-L/1'-9 #4 9'' 1 43 43 55.50 ' 2386.50
25'
6''
5 Main bars at L-N'/5-9 #4 9'' 1 14 14 26.00 ' 364.00
2 Y-Direction Bars
46'-10"
6''
1 Main bars at D-K/1'-4 #4 9'' 1 28 28 47.83 ' 1339.24
55'
6''
2 Main bars at A'-L/4-5 #4 9'' 1 12 12 56.00 ' 672.00
65'-7"
6''
3 Main bars at A'-N'/5-8 #4 9'' 1 24 24 66.58 ' 1597.92
61'-6"
6''
4 Main bars at B-N'/8-9 #4 9'' 1 11 11 62.50 ' 687.50
18'-3"
6''
5 Main bars at B-F/9-10 #4 9'' 1 11 11 19.25 ' 211.75
TOP BARS
1 X-Direction Bars
25'
6''
1 Main bars at A'-B/4-8 #3 9'' 1 9 9 26.00 ' 234.00
39'-8"
6''
2 Main bars at B-D/4-10 #3 9'' 1 9 9 40.75 ' 366.75
61'-6"
6''
3 Main bars at D-F/1'-10 #3 9'' 1 18 18 62.50 ' 1125.00
Page 17 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
54'-6"
6''
4 Main bars at F-L/1'-9 #3 9'' 1 43 43 55.50 ' 2386.50
25'
6''
5 Main bars at L-N'/5-9 #3 9'' 1 14 14 26.00 ' 364.00
2 Y-Direction Bars
46'-10"
6''
1 Main bars at D-K/1'-4 #3 9'' 1 28 28 47.83 ' 1339.24
55'
6''
2 Main bars at A'-L/4-5 #3 9'' 1 12 12 56.00 ' 672.00
65'-7"
6''
3 Main bars at A'-N'/5-8 #3 9'' 1 24 24 66.58 ' 1597.92
61'-6"
6''
4 Main bars at B-N'/8-9 #3 9'' 1 11 11 62.50 ' 687.50
18'-3"
6''
5 Main bars at B-F/9-10 #3 9'' 1 11 11 19.25 ' 211.75
Stair Dowels
3'-6"
6''
1 Horizontal Bars #3 8'' 1 7 7 4.50 ' 31.50
3'-9"
6''
2 Vertical Bars #4 6'' 1 8 8 4.25 ' 34.00
Total Quantity = ( Rft ) 9016.16 9018.66 0.00 0.00
Weight per Rft in Kgs 0.17 0.30 0.47 0.68
WEIGHT OF BARS Weight of Bars Dia Wise Kgs 1532.75 2732.65 0.00 0.00 4.265 T
Total Weight of Bars in Kgs 4265.40
3 Footing Beam
12'' 13'-7.5
1 Bottom Bars #4 2 0 15.63 ' 0.00
12'' 13'-7.5
2 Top Bars #4 3 0 15.63 ' 0.00
12''
3 Top Bars #6 2 0 15.63 ' 0.00 13'-7.5
3"
4 Stirrups #3 9'' 19 0 5.00 ' 0.00
12'' 17'-4"
1 Bottom Bars #4 2 0 19.33 ' 0.00
12'' 52'
2 Curtailment Bars #4 3 0 19.33 ' 0.00
12''
3 Top Bars #6 2 0 19.33 ' 0.00 54'
3"
4 Stirrups #3 9'' 25 0 5.00 ' 0.00
3 F.B at B-H/3
12'' 55'-10.5
1 Bottom Bars #4 2 0 57.88 ' 0.00
12'' 20'-9"
2 Curtailment Bars #4 3 0 22.75 ' 0.00
12''
3 Top Bars #6 2 Page 19 of 0111 22.75 ' 0.00
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
3"
4 Stirrups #3 9'' 71 0 5.00 ' 0.00
Total Quantity = ( Rft ) 0.00 0.00 0.00 0.00
Weight per Rft in Kgs 0.17 0.30 0.47 0.68
WEIGHT OF BARS Weight of Bars Dia Wise Kgs 0.00 0.00 0.00 0.00 0.000 T
Total Weight of Bars in Kgs 0.00
4 R.C.C WALL
Horizontal Bars
263'
6''
1 Horizontal Bars #3 9'' 1 17 17 264.60 ' 4498.20
Vertical Bars
12'-5"
6''
1 Dowel bars #4 6'' 1 502 502 13.43 ' 6741.86
Stirrups
3"
2 Stirrups #3 6'' 12 23 276 3.00 ' 828.00
Total Quantity = ( Rft ) 5326.20 6741.86 0.00 0.00
Weight per Rft in Kgs 0.17 0.30 0.47 0.68
WEIGHT OF BARS Weight of Bars Dia Wise Kgs 905.45 2042.78 0.00 0.00 2.948 T
Total Weight of Bars in Kgs 2948.24
5 Column
Page 20 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
1 Typical Column
14'-7"
1 Vertical Bars #4 10 4 40 15.59 ' 623.60
3"
2 Stirrups #3 6'' 10 25 250 3.00 ' 750.00
1 C-3
14'-7"
1 Vertical Bars #4 4 2 8 15.59 ' 124.72
14'-7"
2 Vertical Bars #6 4 8 32 15.59 ' 498.88
3"
3 Stirrups #3 6'' 4 25 100 3.00 ' 300.00
3"
4 Stirrups #3 6'' 4 25 100 4.00 ' 400.00
3"
5 Hook #3 6'' 4 25 100 1.75 ' 175.00
Total Quantity = ( Rft ) 875.00 0.00 0.00 498.88
Weight per Rft in Kgs 0.17 0.30 0.47 0.68
WEIGHT OF BARS Weight of Bars Dia Wise Kgs 148.75 0.00 0.00 340.24 0.489 T
Total Weight of Bars in Kgs 488.99
WEIGHT OF TOTAL Weight of Bars Dia Wise Kgs 2586.9512 4775.4376 0.0000 340.2362
7.703 T
BARS Total Weight of Bars in Kgs 7702.62
Page 21 of 111
PLOT# 49, SEC-1, PHASE(VIII)
BAR SHAPE
12''
38'
6" x 21"
3"
0.000 Ton
25' 6''
39'-8" 6''
61'-6" 6''
Page 22 of 111
ULE OF SECOND FLOOR SLAB
BAR SHAPE
54'-6" 6''
25' 6''
46'-10" 6''
55' 6''
65'-7" 6''
61'-6" 6''
18'-3" 6''
25' 6''
39'-8" 6''
61'-6" 6''
Page 23 of 111
ULE OF SECOND FLOOR SLAB
BAR SHAPE
54'-6" 6''
25' 6''
46'-10" 6''
55' 6''
65'-7" 6''
61'-6" 6''
18'-3" 6''
3'-6" 6''
3'-9"
4.265 Ton
Page 24 of 111
ULE OF SECOND FLOOR SLAB
BAR SHAPE
13'-7.5" 12''
13'-7.5" 12''
12''
13'-7.5"
6" x 21"
3"
17'-4" 12''
52' 12''
12''
54'
6" x 21"
3"
55'-10.5" 12''
20'-9" 12''
12''
Page 25 of 111
ULE OF SECOND FLOOR SLAB
BAR SHAPE
20'-9"
6" x 21"
3"
0.000 Ton
263' 6''
12'-5" 6''
6" x 6"
3"
2.948 Ton
Page 26 of 111
ULE OF SECOND FLOOR SLAB
BAR SHAPE
14'-7" 12''
6" x 6"
3"
14'-7" 12''
14'-7" 12''
6" x 6"
3"
15" x 6"
3"
3"
0.489 Ton
7.703 Ton
Page 27 of 111
CONSTRUCTION OF PLOT# 49, SEC-1, PHASE(VIII)
Discription of item.
Providing and laying mild steel reinforcement bars (G-60) with and including the cost of straightening,removing twists, cutting, bending, binding,wastage
such overlaps as are not shown over the drawings, placing in position on cement concrete complete in all respects.
X - DIRECTION REINFORCEMENT
1 9" Wall
287'
6''
1 Bottom Bars #4 1 2 2 288.00 ' 576.000
287'
6''
2 Top Bars #4 1 2 2 288.00 ' 576.000
3"
3 Stirrups #3 9'' 1 366 366 2.50 ' 915.000
2 4.5" Wall
38'
6''
1 Bottom Bars #4 1 2 2 39.00 ' 78.000
38'
6''
2 Top Bars #4 1 2 2 39.00 ' 78.000
3"
3 Stirrups #3 9'' 1 54 54 1.75 ' 94.500
Total Quantity = ( Rft ) 1009.50 1308.00 0.00 0.00
Page 29 of 111
PLOT# 49, SEC-1, PHASE(VIII)
BAR SHAPE
287' 6''
287' 6''
6" x 6"
3"
38' 6''
38' 6''
6" x 1.5"
3"
Page 30 of 111
0.568 Ton
ULE OF SECOND FLOOR SLAB
BAR SHAPE
0.568 Ton
Page 31 of 111
CONSTRUCTION OF PLOT# 49, SEC-1, PHASE(VIII)
Discription of item.
Providing and laying mild steel reinforcement bars (G-60) with and including the cost of straightening,removing twists, cutting, bending, binding,wastage,
overlaps as are not shown over the drawings, placing in position on cement concrete complete in all respects.
X - DIRECTION
1 REINFORCEMENT
20'-6"
1 Main bars at D-G/1'-4 #3 8'' 1 26 26 20.50 ' 533.00
8'-6"
2 Main bars at C-G/4-5 #3 8'' 1 29 29 8.50 ' 246.50
6'-6"
3 Main bars at B'-E/5-8 #3 6'' 1 36 36 6.50 ' 234.00
15'-3"
4 Main bars at B-F/8-10 #3 6'' 1 27 27 15.25 ' 411.75
17'-6"
5 Main bars at E'-H/5-8 #3 6'' 1 43 43 17.50 ' 752.50
13'
6 Main bars at G-H/1'-3 #3 9'' 1 21 21 13.00 ' 273.00
8'-3"
7 Main bars at F-I/8-9 #3 8'' 1 37 37 8.25 ' 305.25
Page 32 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
20'-6"
8 Main bars at H-K/1'-4 #3 9'' 1 24 24 20.50 ' 492.00
8'-6"
9 Main bars at H-L/4-5 #3 8'' 1 32 32 8.50 ' 272.00
18'-3"
10 Main bars at H-M/5-8 #4 6'' 1 43 43 18.25 ' 784.75
7'-6"
11 Main bars at J-N/8-9 #3 9'' 1 21 21 7.50 ' 157.50
Page 33 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
9'
1 Main bars at C-G/2 #4 6'' 1 35 35 9.25 ' 323.75
15'-9"
2 Main bars at G-H/2 #4 8'' 1 24 24 16.00 ' 384.00
9'
3 Main bars at B'/3-5 #4 9'' 1 21 21 9.25 ' 194.25
8'-3"
4 Main bars at D-G/4 #4 9'' 1 24 24 8.25 ' 198.00
8'-3"
5 Main bars at H-L/4 #4 9'' 1 24 24 8.25 ' 198.00
2'-6"
6 Main bars at C-G/5 #3 9'' 1 26 26 2.75 ' 71.50
8'-6"
7 Main bars at G-H/5 #4 8'' 1 17 17 8.75 ' 148.75
8'-6"
8 Main bars at H-M/5 #4 6'' 1 30 30 8.50 ' 255.00
13'-6"
9 Main bars at D-H/8 #4 6'' 1 34 34 13.75 ' 467.50
13'-1"
10 Main bars at H-M/8 #4 6'' 1 34 34 13.33 ' 453.22
4'-6"
11 Main bars at B-F/10 #3 8'' 1 28 28 4.75 ' 133.00
2 Y - DIRECTION REINFORCEMENT
Y - DIRECTION
1 REINFORCEMENT
17'
1 Main bars at D-G/1'-4 #3 8'' 1 31 31 17.00 ' 527.00
Page 34 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
16'
2 Main bars at F-H/1'-3 #3 9'' 1 18 18 16.00 ' 288.00
17'
3 Main bars at H-K/1'-4 #3 8'' 1 32 32 17.00 ' 544.00
21'
4 Main bars at C-G/4-5 #3 8'' 1 14 14 21.00 ' 294.00
21'
2 Main bars at H-L/4-5 #3 9'' 1 14 14 21.00 ' 294.00
6'-6"
3 Main bars at B'-E/5-8 #4 6'' 1 27 27 6.50 ' 175.50
21'
4 Main bars at E'-H/5-8 #3 8'' 1 27 27 21.00 ' 567.00
23'
2 Main bars at H-M/5-8 #4 6'' 1 28 28 23.00 ' 644.00
18'-3"
3 Main bars at C-F/8-10 #3 8'' 1 24 24 18.25 ' 438.00
24'-4.5"
4 Main bars at F-I/8-9 #3 9'' 1 14 14 24.38 ' 341.25
13'
2 Main bars at I-N/8-9 #3 9'' 1 12 12 13.00 ' 156.00
4'-6"
1 Main bars at D/1'-5 #3 9'' 1 43 43 4.75 ' 204.25
13'
3''
2 Main bars at D/8'-10 #4 8'' 1 24 24 13.50 ' 324.00
8'-9"
3 Main bars at G/1'-5 #4 9'' 1 43Page 35 of 43
111 8.75 ' 376.25
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
25'-6"
4 Main bars at F/8-9 #4 6'' 1 18 18 25.75 ' 463.50
9'-1"
5 Main bars at H/1'-5 #4 9'' 1 43 43 9.08 ' 390.44
14'
6 Main bars at H/5-8 #4 6'' 1 38 38 14.00 ' 532.00
11'-3.5"
2 Main bars at I/8-9 #4 9'' 1 12 12 11.30 ' 135.54
4'-9"
3 Main bars at K/1'-4 #3 8'' 1 32 32 5.00 ' 160.00
5'-6"
4 Main bars at L/4-6 #3 9'' 1 27 27 5.75 ' 155.25
6'-6"
5 Main bars at M/6-9 #4 7'' 1 29 29 6.75 ' 195.75
A Stair
3'' 4'
1 Main Bars #4 6'' 1 63 63 4.44 ' 279.72
3'' 34'-6"
2 Distribution Bars #3 8'' 1 7 7 35.00 ' 245.00
Total Quantity = ( Rft ) 8095.75 6923.92 0.00 0.00
Weight per Rft in Kgs 0.17 0.30 0.47 0.68
WEIGHT OF BARS Weight of Bars Dia Wise Kgs 1376.28 2097.95 0.00 0.00 3.474 To
Total Weight of Bars in Kgs 3474.23
Basement Floor Slab
A Beam
Page 36 of 111
1 B-1 at E'/5-8
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
1 B-1 at E'/5-8
12'' 17'
1 Bottom Bars #6 1 3 3 19.25 ' 57.75
12''
2 Top Bars #6 1 3 3 19.25 ' 57.75 17'
3"
3 Stirrups #3 6'' 1 36 36 4.00 ' 144.00
2 B-1 at H-K/6
12'' 15'-1"
1 Bottom Bars #6 1 3 3 17.08 ' 51.24
12''
2 Top Bars #4 1 3 3 17.08 ' 51.24 15'-1"
3"
3 Stirrups #3 6'' 1 31 31 4.00 ' 124.00
3 B-1 at D/9-10
4'' 9'-10"
1 Bottom Bars #6 1 3 3 11.83 ' 35.49
4''
2 Top Bars #4 1 3 3 11.83 ' 35.49 9'-10"
3"
3 Stirrups #3 6'' 1 21 21 4.00 ' 84.00
4 B-2 at E'-H/9
Page 37 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
12'' 20'-9"
1 Bottom Bars #6 1 5 5 22.75 ' 113.75
12''
2 Top Bars #6 1 4 4 22.75 ' 91.00 20'-9"
3"
3 Stirrups #3 6'' 1 43 43 4.50 ' 193.50
5 S.B-1
6'' 99'
1 Bottom Bars #4 1 2 2 100.75 ' 201.50
6'' 99'
2 Top Bars #4 1 2 2 100.75 ' 201.50
3"
3 Stirrups #3 6'' 1 203 203 2.50 ' 507.50
6 UB-3
12'' 7'-3"
1 Bottom Bars #6 1 3 3 9.25 ' 27.75
12''
2 Top Bars #4 1 2 2 9.25 ' 18.50 7'-3"
3"
3 Stirrups #3 6'' 1 16 16 3.50 ' 56.00
7 UB-6
12'' 11'
1 Bottom Bars #6 1 4 4 13.00 ' 52.00
Page 38 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
12''
2 Top Bars #4 1 2 2 13.00 ' 26.00 11'
3"
3 Stirrups #3 6'' 1 23 23 3.50 ' 80.50
8 C B-1
4'' 57'-9"
1 Bottom Bars #6 1 3 3 58.41 ' 175.23
4''
2 Top Bars #4 1 3 3 58.41 ' 175.23 57'-9"
3"
3 Stirrups #3 6'' 1 117 117 3.50 ' 409.50
9 CB-2
4'' 15'
1 Bottom Bars #6 1 6 6 15.66 ' 93.96
4''
2 Top Bars #4 1 6 6 15.66 ' 93.96 15'
3"
3 Stirrups #3 6'' 1 31 31 5.00 ' 155.00
10 CB-3
4'' 10'-3"
1 Bottom Bars #6 3 6 18 10.91 ' 196.38
4''
2 Top Bars #4 3 6 18 10.91 ' 196.38 10'-3"
Page 39 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
3"
3 Stirrups #3 6'' 3 22 66 5.50 ' 363.00
11 CB-4
4'' 9'-3"
1 Bottom Bars #6 1 5 5 9.91 ' 49.55
4''
2 Top Bars #4 1 5 5 9.91 ' 49.55 9'-3"
3"
3 Stirrups #3 6'' 1 20 20 4.00 ' 80.00
Total Quantity = ( Rft ) 2197.00 1049.35 0.00 1001.85
Weight per Rft in Kgs 0.17 0.30 0.47 0.68
WEIGHT OF BARS
Weight of Bars Dia Wise Kgs 373.49 317.95 0.00 683.26
1.375 To
Total Weight of Bars in Kgs 1374.70
Weight of Bars Dia Wise Kgs 1749.77 2415.90 0.00 683.26
WEIGHT OF TOTAL BARS 4.849 To
Total Weight of Bars in Kgs 4848.93
Page 40 of 111
PLOT# 49, SEC-1, PHASE(VIII)
BAR SHAPE
20'-6"
8'-6"
6'-6"
15'-3"
17'-6"
13'
8'-3"
Page 41 of 111
DULE OF SECOND FLOOR SLAB
BAR SHAPE
20'-6"
8'-6"
18'-3"
7'-6"
Page 42 of 111
DULE OF SECOND FLOOR SLAB
BAR SHAPE
9' 3''
15'-9" 3''
9' 3''
8'-3"
8'-3"
2'-6" 3''
8'-6" 3''
8'-6"
13'-6" 3''
13'-1" 3''
4'-6" 3''
17'
Page 43 of 111
DULE OF SECOND FLOOR SLAB
BAR SHAPE
16'
17'
21'
21'
6'-6"
21'
23'
18'-3"
24'-4.5"
13'
4'-6" 3''
13' 3''
8'-9"
Page 44 of 111
DULE OF SECOND FLOOR SLAB
BAR SHAPE
8'-9"
25'-6" 3''
9'-1"
14'
11'-3.5"
4'-9" 3''
5'-6" 3''
6'-6" 3''
4' 3''
34'-6" 3''
3.474 Ton
Page 45 of 111
DULE OF SECOND FLOOR SLAB
BAR SHAPE
17' 12''
12''
17'
6" x 15"
3"
15'-1" 12''
12''
15'-1"
6" x 15"
3"
9'-10" 4''
4''
9'-10"
6"x15"
3"
Page 46 of 111
DULE OF SECOND FLOOR SLAB
BAR SHAPE
20'-9" 12''
12''
20'-9"
6" x 18"
3"
99' 6''
99' 6''
6" x 6"
3"
7'-3" 12''
12''
7'-3"
6"x12"
3"
11' 12''
Page 47 of 111
DULE OF SECOND FLOOR SLAB
BAR SHAPE
12''
11'
6" x 12"
3"
57'-9" 4''
4''
57'-9"
12" x 6"
3"
15' 4''
4''
15'
21" x 6"
3"
10'-3" 4''
4''
10'-3"
Page 48 of 111
DULE OF SECOND FLOOR SLAB
BAR SHAPE
10'-3"
24" x 6"
3"
9'-3" 4''
4''
9'-3"
15" x 6"
3"
1.375 Ton
4.849 Ton
Page 49 of 111
CONSTRUCTION OF PLOT# 49, SEC-1, PHASE(VIII)
Discription of item.
Providing and laying mild steel reinforcement bars (G-60) with and including the cost of straightening,removing twists, cutting, bending, binding,wastage,
overlaps as are not shown over the drawings, placing in position on cement concrete complete in all respects.
Ground Floor
A Foundation
Foundation
1 F1 Footing
4'-8"
9''
1 Main Bars #4 8'' 1 8 8 6.18 ' 49.44
4'-8"
9''
2 Distribution Bars #4 8'' 1 8 8 6.18 ' 49.44
2 F2 Footing
3'-8"
9''
1 Main Bars #4 8'' 2 8 16 5.18 ' 82.88
4'-8"
9''
2 Distribution Bars #4 8'' 2 6 12 6.18 ' 74.16
3 F3 Footing
3'-8"
9''
1 Main Bars #4 8'' 2 6 12 5.18 ' 62.16
3'-8"
9''
2 Distribution Bars #4 8'' 2 6 Page 50 of12
111 5.18 ' 62.16
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
Page 51 of 111
PLOT# 49, SEC-1, PHASE(VIII)
BAR SHAPE
4'-8" 9''
4'-8" 9''
3'-8" 9''
4'-8" 9''
3'-8" 9''
3'-8" 9''
Page 52 of 111
ULE OF SECOND FLOOR SLAB
BAR SHAPE
0.115 Ton
Page 53 of 111
CONSTRUCTION OF PLOT# 49, SEC-1, PHASE(VIII)
Discription of item.
Providing and laying mild steel reinforcement bars (G-60) with and including the cost of straightening,removing twists, cutting, bending, binding,wastage
such overlaps as are not shown over the drawings, placing in position on cement concrete complete in all respects.
X - DIRECTION REINFORCEMENT
1 Column
1 Typical Column
13'
1 Vertical Bars #4 25 4 100 13.00 ' 1300.00
3"
2 Stirrups #3 6'' 25 23 575 3.00 ' 1725.00
2 C1 Column
14'
12''
1 Vertical Bars #6 3 10 30 16.00 ' 480.00
1'-3"
3"
2 Hook #3 6'' 3 28 84 1.75 ' 147.00
3"
3 Stirrups #3 6'' 3 29 87 3.00 ' 261.00
3"
Page 54 of 111
4 Stirrups #3 6'' 3 29 87 4.50 ' 391.50
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
3 C2 Column
11'
12''
1 Vertical Bars #6 2 8 16 13.00 ' 208.00
3"
2 Stirrups #3 6'' 2 23 46 3.00 ' 138.00
3"
3 Stirrups #3 6'' 2 23 46 5.50 ' 253.00
4 C3 Column
14'-3"
1 Vertical Bars #6 4 8 32 14.25 ' 456.00
14'-3"
2 Vertical Bars #4 4 2 8 14.25 ' 114.00
1'-3"
3"
3 Hook #3 6'' 4 22 88 1.75 ' 154.00
3"
4 Stirrups #3 6'' 4 23 92 2.50 ' 230.00
3"
5 Stirrups #3 6'' 4 23 92 4.00 ' 368.00
Total Quantity = ( Rft ) 3667.50 1414.00 0.00 1144.00
Weight per Rft in Kgs 0.170 0.303 0.473 0.682
WEIGHT OF BARS Weight of Bars Dia Wise Kgs 623.48 428.44 0.00 780.21 1.832 Ton
Total Weight of Bars in Kgs 1832.13
Page 55 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
1 9" Wall
279'
6''
1 Bottom Bars #4 1 2 2 280.00 ' 560.000
279'
6''
2 Top Bars #4 1 2 2 281.00 ' 562.000
3"
3 Stirrups #3 9'' 1 361 361 2.50 ' 902.500
2 4.5" Wall
39'
6''
1 Bottom Bars #4 1 2 2 40.00 ' 80.000
39'
6''
2 Top Bars #4 1 2 2 40.00 ' 80.000
3"
3 Stirrups #3 9'' 1 59 59 1.75 ' 103.250
Total Quantity = ( Rft ) 1005.75 1282.00 0.00 0.00
Weight per Rft in Kgs 0.170 0.303 0.473 0.682
WEIGHT OF BARS Weight of Bars Dia Wise Kgs 170.98 388.45 0.00 0.00 0.559 Ton
Total Weight of Bars in Kgs 559.42
Weight of Bars Dia Wise Kgs 794.45 816.89 0.00 780.21
WEIGHT OF TOTAL BARS 2.392 Ton
Total Weight of Bars in Kgs 2391.55
Page 56 of 111
PLOT# 49, SEC-1, PHASE(VIII)
BAR SHAPE
13'
6" x 6"
3"
14' 12''
1'-3" 3"
6" x 9"
3"
9"x15"
3"
Page 57 of 111
ULE OF SECOND FLOOR SLAB
BAR SHAPE
9"x15"
11' 12''
9" x 9"
3"
15" x 15"
3"
14'-3"
14'-3"
1'-3" 3"
6" x 6"
3"
6" x 15"
3"
1.832 Ton
Page 58 of 111
ULE OF SECOND FLOOR SLAB
BAR SHAPE
279' 6''
279' 6''
6" x 6"
3"
39' 6''
39' 6''
6" x 1.5"
3"
0.559 Ton
2.392 Ton
Page 59 of 111
CONSTRUCTION OF PLOT# 49, SEC-1, PHASE(VIII)
Discription of item.
Providing and laying mild steel reinforcement bars (G-60) with and including the cost of straightening,removing twists, cutting, bending, binding,wastage,
overlaps as are not shown over the drawings, placing in position on cement concrete complete in all respects.
X - DIRECTION REINFORCEMENT
X - DIRECTION
1 REINFORCEMENT
20'-6"
1 Main bars at D-G/1'-4 #3 8'' 1 26 26 20.50 ' 533.00
8'-6"
2 Main bars at C-G/4-5 #3 8'' 1 29 29 8.50 ' 246.50
17'-6"
3 Main bars at B-H/5-8 #3 8'' 1 48 48 17.50 ' 840.00
10'
4 Main bars at D-F/9-10 #3 6'' 1 29 29 10.00 ' 290.00
15'
5 Main bars at A-F/10-11' #4 6'' 1 55 55 15.00 ' 825.00
28'-3"
6 Main bars at G-H/1'-5 #3 8'' 1 17 17 28.25 ' 480.25
22'
7 Main bars at F-I/9-11 #4 8'' 1 42 42 22.00 ' 924.00
Page 60 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
19'
8 Main bars at H-K/1'-4 #3 9'' 1 24 24 19.00 ' 456.00
8'-6"
9 Main bars at H-N/4-5 #3 8'' 1 34 34 8.50 ' 289.00
8'-9"
10 Main bars at H-N/5-6 #3 6'' 1 45 45 8.75 ' 393.75
8'-9"
11 Main bars at G-H'/6-8 #3 6'' 1 47 47 8.75 ' 411.25
8'
12 Main bars at E'-N/8-9 #3 8'' 1 59 59 8.00 ' 472.00
Page 61 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
9'
1 Main bars at D-G/2 #4 6'' 1 35 35 9.25 ' 323.75
13'
2 Main bars at G-H/2' #4 6'' 1 22 22 13.25 ' 291.50
7'-6"
3 Main bars at H-K/2 #4 6'' 1 35 35 7.75 ' 271.25
21'
4 Main bars at C-G/4 #4 8'' 1 29 29 21.00 ' 609.00
8'-3"
5 Main bars at H-L/4 #4 9'' 1 26 26 8.25 ' 214.50
13'-6"
6 Main bars at G-L/5 #4 8'' 1 17 17 13.50 ' 229.50
20'-6"
7 Main bars at H-L/5 #4 6'' 1 44 44 20.50 ' 902.00
8'-3"
8 Main bars at D-H/8 #4 8'' 1 40 40 8.25 ' 330.00
7'-9"
9 Main bars at F-N/9 #4 8'' 1 53 53 7.75 ' 410.75
4'
10 Main bars at A'-F/10 #4 8'' 1 39 39 4.25 ' 165.75
14'-3"
11 Main bars at F-I/11 #4 4'' 1 84 84 14.50 ' 1218.00
Y - DIRECTION REINFORCEMENT
Y - DIRECTION
1 REINFORCEMENT
17'
1 Main bars at D-G/1'-4 #3 8'' 1 31 31 17.00 ' 527.00
Page 62 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
19'
2 Main bars at C-G/4-5 #3 8'' 1 14 14 19.00 ' 266.00
32'
3 Main bars at B-H/5-8 #3 8'' 1 28 28 32.00 ' 896.00
13'
4 Main bars at E-F/9-10 #3 5'' 1 25 25 13.00 ' 325.00
27'
5 Main bars at A'-F/10-11' #4 8'' 1 23 23 27.00 ' 621.00
10'-6"
6 Main bars at G-H/1'-5 #3 6'' 1 59 59 10.50 ' 619.50
28'
7 Main bars at F-I/9-11 #3 9'' 1 30 30 28.00 ' 840.00
29'
8 Main bars at E'-I/8-9 #3 9'' 1 12 12 29.00 ' 348.00
17'
9 Main bars at H-K/1'-4 #3 8'' 1 29 29 17.00 ' 493.00
22'
10 Main bars at H-N/4-5 #3 9'' 1 12 12 22.00 ' 264.00
22'
11 Main bars at H-N/5-6 #3 8'' 1 14 14 22.00 ' 308.00
23'
12 Main bars at H-N/6-7 #3 8'' 1 15 15 23.00 ' 345.00
11'-3"
13 Main bars at I-N/8-9 #3 8'' 1 17 17 11.25 ' 191.25
Page 63 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
5'
1 Main bars at E/1'-5 #3 9'' 1 39 39 5.25 ' 204.75
11'-1"
2 Main bars at B/5-8 #4 4'' 1 56 56 11.33 ' 634.48
18'-9"
3 Main bars at D/9-10 #4 9'' 1 14 14 19.00 ' 266.00
7'
4 Main bars at A & F/10-11 #4 9'' 1 21 21 7.25 ' 152.25
10'
5 Main bars at G/2-5 #4 9'' 1 35 35 10.00 ' 350.00
10'
6 Main bars at H/2-5 #4 9'' 1 35 35 10.00 ' 350.00
15'-3"
7 Main bars at H/5-8 #4 9'' 1 24 24 15.25 ' 366.00
5'-6"
8 Main bars at K/2-4 #3 9'' 1 26 26 5.50 ' 143.00
9'-6"
9 Main bars at L/4-6 #4 8'' 1 28 28 9.75 ' 273.00
5'-6"
10 Main bars at N/6-9 #3 8'' 1 31 31 5.75 ' 178.25
STAIR
3'' 3'-11"
1 Main Bars #4 6'' 1 52 52 4.44 ' 230.88
3'' 29'-6"
2 Distribution Bars #3 8'' 1 6 6 30.00 ' 180.00
Total Quantity = ( Rft ) 10540.50 9958.61 0.00 0.00
Weight per Rft in Kgs 0.17 0.30 0.47 0.68
WEIGHT OF BARS 4.809 To
Page 64 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
1 B-1 at E'/5-8
12'' 17'
1 Bottom Bars #6 1 3 3 19.25 ' 57.75
12''
2 Top Bars #6 1 3 3 19.25 ' 57.75 17'
3"
3 Stirrups #3 6'' 1 36 36 4.00 ' 144.00
2 B-1 at H-K/6
Page 65 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
12'' 15'-1"
1 Bottom Bars #6 1 3 3 17.08 ' 51.24
12''
2 Top Bars #4 1 3 3 17.08 ' 51.24 15'-1"
3"
3 Stirrups #3 6'' 1 31 31 4.00 ' 124.00
3 B-1 at D/9-10
12'' 9'-10"
1 Bottom Bars #6 1 3 3 11.83 ' 35.49
12''
2 Top Bars #4 1 3 3 11.83 ' 35.49 9'-10"
3"
3 Stirrups #3 6'' 1 21 21 4.00 ' 84.00
4 B-2 at E'-H/9
12'' 20'-9"
1 Bottom Bars #6 1 5 5 22.75 ' 113.75
12''
2 Top Bars #6 1 4 4 22.75 ' 91.00 20'-9"
3"
3 Stirrups #3 6'' 1 43 43 4.50 ' 193.50
5 S.B-1
6'' 99'
1 Bottom Bars #4 1 2 2 100.75 ' 201.50
Page 66 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
6'' 99'
2 Top Bars #4 1 2 2 100.75 ' 201.50
3"
3 Stirrups #3 6'' 1 203 203 2.50 ' 507.50
6 B-4
Page 67 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
6 B-4
12'' 24'-1.5"
1 Bottom Bars #6 1 8 8 26.13 ' 209.00
12''
2 Curtailment Bars #4 1 4 4 26.13 ' 104.50 24'-1.5"
12''
3 Top Bars #4 1 3 3 26.13 ' 78.38 24'-1.5"
3"
4 Stirrups #3 6'' 1 49 49 5.00 ' 245.00
7 UB-1
12'' 26'-9"
1 Bottom Bars #6 1 5 5 28.75 ' 143.75
12''
2 Curtailment Bars #4 1 4 4 28.75 ' 115.00 26'-9"
12''
3 Top Bars #6 1 4 4 28.75 ' 115.00 26'-9"
3"
4 Stirrups #3 6'' 1 55 55 5.00 ' 275.00
8 UB-2
12'' 26'-9"
1 Bottom Bars #6 1 3 3 28.75 ' 86.25
12''
2 Curtailment Bars #4 1 4 4 28.75 ' 115.00 26'-9"
Page 68 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
12''
2 Top Bars #6 1 5 5 28.75 ' 143.75 26'-9"
3"
3 Stirrups #3 6'' 1 51 51 3.50 ' 178.50
9 UB-3
12'' 7'-9"
1 Bottom Bars #6 1 3 3 9.75 ' 29.25
12''
2 Top Bars #4 1 2 2 9.75 ' 19.50 7'-9"
3"
3 Stirrups #3 6'' 1 19 19 3.50 ' 66.50
10 CB-1
4'' 16'-9"
1 Bottom Bars #6 1 3 3 17.41 ' 52.23
4''
2 Top Bars #4 1 3 3 17.41 ' 52.23 16'-9"
3"
3 Stirrups #3 6'' 1 35 35 3.50 ' 122.50
11 CB-2
4'' 15'
1 Bottom Bars #6 1 6 6 15.66 ' 93.96
4''
2 Top Bars #4 1 6 6 15.66 ' 93.96 15'
Page 69 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
3"
3 Stirrups #3 6'' 1 31 31 5.00 ' 155.00
12 CB-4
4'' 10'-2"
1 Bottom Bars #6 2 5 10 10.91 ' 109.10
4''
2 Top Bars #4 2 5 10 10.91 ' 109.10 10'-2"
3"
3 Stirrups #3 6'' 2 23 46 4.00 ' 184.00
Total Quantity = ( Rft ) 2279.50 1177.40 0.00 1389.27
Weight per Rft in Kgs 0.17 0.30 0.47 0.68
WEIGHT OF BARS
Weight of Bars Dia Wise Kgs 387.52 356.75 0.00 947.48
1.692 To
Total Weight of Bars in Kgs 1691.75
Weight of Bars Dia Wise Kgs 2179.40 3374.21 0.00 947.48
WEIGHT OF TOTAL Bars 6.501 To
Total Weight of Bars in Kgs 6501.09
Page 70 of 111
PLOT# 49, SEC-1, PHASE(VIII)
BAR SHAPE
20'-6"
8'-6"
17'-6"
10'
15'
28'-3"
22'
Page 71 of 111
DULE OF SECOND FLOOR SLAB
BAR SHAPE
19'
8'-6"
8'-9"
8'-9"
8'
Page 72 of 111
DULE OF SECOND FLOOR SLAB
BAR SHAPE
9' 3''
13' 3''
7'-6" 3''
21'
8'-3"
13'-6"
20'-6"
8'-3"
7'-9"
4' 3''
14'-3" 3''
17'
Page 73 of 111
DULE OF SECOND FLOOR SLAB
BAR SHAPE
19'
32'
13'
27'
10'-6"
28'
29'
17'
22'
22'
23'
11'-3"
Page 74 of 111
DULE OF SECOND FLOOR SLAB
BAR SHAPE
5' 3''
11'-1" 3''
18'-9" 3''
7' 3''
10'
10'
15'-3"
5'-6" 3''
9'-6" 3''
5'-6" 3''
3'-11" 3''
29'-6" 3''
4.809 Ton
Page 75 of 111
DULE OF SECOND FLOOR SLAB
BAR SHAPE
4.809 Ton
17' 12''
12''
17'
6" x 15"
3"
Page 76 of 111
DULE OF SECOND FLOOR SLAB
BAR SHAPE
15'-1" 12''
12''
15'-1"
6" x 15"
3"
9'-10" 12''
12''
9'-10"
3" 6"x15"
20'-9" 12''
12''
20'-9"
6" x 18"
3"
99' 6''
Page 77 of 111
DULE OF SECOND FLOOR SLAB
BAR SHAPE
99' 6''
6" x 6"
3"
Page 78 of 111
DULE OF SECOND FLOOR SLAB
BAR SHAPE
24'-1.5" 12''
12''
24'-1.5"
12''
24'-1.5"
6"x21"
3"
26'-9" 12''
12''
26'-9"
12''
26'-9"
6" x 21"
3"
26'-9" 12''
12''
26'-9"
Page 79 of 111
DULE OF SECOND FLOOR SLAB
BAR SHAPE
12''
26'-9"
6"x12"
3"
7'-9" 12''
12''
7'-9"
6" x 12"
3"
16'-9" 4''
4''
16'-9"
12" x 6"
3"
15' 4''
4''
15'
Page 80 of 111
DULE OF SECOND FLOOR SLAB
BAR SHAPE
15'
21" x 6"
3"
10'-2" 4''
4''
10'-2"
15" x 6"
6.501 Ton
Page 81 of 111
CONSTRUCTION OF PLOT# 49, SEC-1, PHASE(VIII)
Discription of item.
Providing and laying mild steel reinforcement bars (G-60) with and including the cost of straightening,removing twists, cutting, bending, binding,wastage, and such overlap
not shown over the drawings, placing in position on cement concrete complete in all respects.
1 C3 Column
12'
6''
1 Vertical Bars #6 3 8 24 12.50 ' 300.00
12'
6''
2 Vertical Bars #4 3 2 6 12.50 ' 75.00
1'-3"
3"
3 Hook #3 6'' 3 22 66 1.75 ' 115.50
3"
4 Stirrups #3 6'' 3 23 69 2.50 ' 172.50
3"
5 Stirrups #3 6'' 3 23 69 4.00 ' 276.00
3"
2 Stirrups #3 6'' 3 23 69 5.10 ' 351.90
1 Typical Column
12'
6''
1 Vertical Bars #4 25 4 100 12.50 ' 1250.00
Page 82 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
3"
2 Stirrups #3 6'' 25 23 575 2.50 ' 1437.50
Total Quantity = ( Rft ) 2353.40 1325.00 0.00 300.00
Weight per Rft in Kgs 0.170 0.303 0.473 0.682
WEIGHT OF BARS Weight of Bars Dia Wise Kgs 400.08 401.48 0.00 204.60 1.006 Ton
Total Weight of Bars in Kgs 1006.15
2 LB-2
7'-6"
12''
1 Bottom Bars #6 1 5 5 9.50 ' 47.500
12''
2 Top Bars #6 1 2 2 9.50 ' 19.000 7'-6"
3"
3 Stirrups #3 6'' 1 17 17 4.00 ' 68.000
7 9" Wall
467'-6"
6''
1 Bottom Bars #4 1 2 2 468.50 ' 937.000
6''
2 Top Bars #4 1 2 2 288.00 ' 576.000 467'-6"
3"
3 Stirrups #3 9'' 1 414 414 2.50 ' 1,035.000
8 4.5" Wall
69'
6''
1 Bottom Bars #4 1 2 2 70.00 ' 140.000
Page 83 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
6''
2 Top Bars #4 1 2 2 70.00 ' 140.000 69'
3"
3 Stirrups #3 9'' 1 81 81 1.75 ' 141.750
Total Quantity = ( Rft ) 1244.75 1793.00 0.00 66.50
Weight per Rft in Kgs 0.170 0.303 0.473 0.682
WEIGHT OF BARS Weight of Bars Dia Wise Kgs 211.61 543.28 0.00 45.35 0.800 Ton
Total Weight of Bars in Kgs 800.24
Weight of Bars Dia Wise Kgs 611.6855 944.7540 0.0000 249.9530
WEIGHT OF TOTAL BARS 1.806 Ton
Total Weight of Bars in Kgs 1806.39
Page 84 of 111
PLOT# 49, SEC-1, PHASE(VIII)
BAR SHAPE
12'
12'
1'-3" 3"
6" x 6"
3"
6" x 15"
3"
6" x 15"
3"
12'
Page 85 of 111
ULE OF SECOND FLOOR SLAB
BAR SHAPE
6" x 6"
3"
1.006 Ton
7'-6" 12''
12''
7'-6"
467'-6" 6''
6''
467'-6"
6" x 6"
3"
69' 6''
Page 86 of 111
ULE OF SECOND FLOOR SLAB
BAR SHAPE
6''
69'
6" x 1.5"
3"
0.800 Ton
1.806 Ton
Page 87 of 111
CONSTRUCTION OF PLOT# 49, SEC-1, PHASE(VIII)
Discription of item.
Providing and laying mild steel reinforcement bars (G-60) with and including the cost of straightening,removing twists, cutting, bending, binding,wastage
such overlaps as are not shown over the drawings, placing in position on cement concrete complete in all respects.
X - DIRECTION
1 REINFORCEMENT
17'-6"
1 Main bars at D-G/2-4 #3 9'' 1 24 24 17.50 ' 420.00
8'-6"
2 Main bars at C-G/4-5 #3 9'' 1 26 26 8.50 ' 221.00
17'-6"
3 Main bars at B-H/5-8 #4 6'' 1 65 65 17.50 ' 1137.50
11'
4 Main bars at B-F/9-10 #3 8'' 1 28 28 11.00 ' 308.00
7'-6"
5 Main bars at E'-N/8-9 #3 6'' 1 79 79 7.50 ' 592.50
28'-3"
6 Main bars at G-H/1'-5 #3 9'' 1 15 15 28.25 ' 423.75
14'
7 Main bars at F-J1/9-10A #4 6'' 1 55 55 14.00 ' 770.00
19'
8 Main bars at H-K/2-4 #3 9'' 1 24 24 19.00 ' 456.00
Page 88 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
8'-6"
9 Main bars at H-L/4-5 #3 9'' 1 26 26 8.50 ' 221.00
19'
10 Main bars at H-N/5-8 #4 6'' 1 45 45 19.00 ' 855.00
9'-6"
12 Main bars at I-N/8-9' #3 6'' 1 25 25 9.50 ' 237.50
6'
1 Main bars at D-G/2 #4 9'' 1 24 24 6.25 ' 150.00
14'-9"
2 Main bars at G-H/2 #4 6'' 1 22 22 15.00 ' 330.00
Page 89 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
6'-6"
3 Main bars at H-K/2 #4 9'' 1 24 24 6.75 ' 162.00
8'-3"
4 Main bars at C-G/4 #4 9'' 1 26 26 8.25 ' 214.50
8'-3"
5 Main bars at H-L/4 #4 9'' 1 26 26 8.25 ' 214.50
12'-6"
6 Main bars at B-H/5 #4 8'' 1 49 49 12.50 ' 612.50
8'-3"
7 Main bars at H-L/5 #4 6'' 1 44 44 8.25 ' 363.00
17'-3"
8 Main bars at B-H/5 #4 8'' 1 49 49 17.25 ' 845.25
12'-3"
9 Main bars at H-J1/8 #4 6'' 1 29 29 12.25 ' 355.25
15'
10 Main bars at J1-N/8 #4 6'' 1 19 19 15.25 ' 289.75
11'
11 Main bars at B-E/10 #4 9'' 1 26 26 11.25 ' 292.50
5'-6"
12 Main bars at F-J1/10a #4 9'' 1 36 36 5.75 ' 207.00
Y - DIRECTION REINFORCEMENT
Y - DIRECTION
1 REINFORCEMENT
17'
1 Main bars at D-G/2-4 #3 8'' 1 31 31 17.00 ' 527.00
19'
2 Main bars at C-G/4-5 #3 9'' 1 13 13 19.00 ' 247.00
Page 90 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
32'
3 Main bars at B-H/5-8 #3 8'' 1 28 28 32.00 ' 896.00
18'-3"
4 Main bars at B-F/9-10 #3 8'' 1 17 17 18.25 ' 310.25
10'-6"
5 Main bars at G-H/1'-5 #3 8'' 1 44 44 10.50 ' 462.00
28'
6 Main bars at F-I/9-10a #3 8'' 1 20 20 28.00 ' 560.00
39'
7 Main bars at E'-N/8-9 #3 8'' 1 12 12 39.00 ' 468.00
17'
8 Main bars at H-K/1'-4 #3 8'' 1 29 29 17.00 ' 493.00
19'
9 Main bars at H-N/4-5 #3 9'' 1 12 12 19.00 ' 228.00
22'
10 Main bars at H-N/5-8 #4 6'' 1 39 39 22.00 ' 858.00
Page 91 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
5'
1 Main bars at E/1'-5 #3 9'' 1 39 39 5.25 ' 204.75
11'-1"
2 Main bars at B/5-8 #4 4'' 1 56 56 11.33 ' 634.48
5'
3 Main bars at D/9-10 #3 9'' 1 14 14 5.25 ' 73.50
12'
4 Main bars at F/9-10a #4 9'' 1 21 21 12.00 ' 252.00
9'
5 Main bars at G/2-5 #4 9'' 1 35 35 9.00 ' 315.00
9'
6 Main bars at H/2-5 #4 9'' 1 39 39 9.00 ' 351.00
15'-6"
7 Main bars at H/5-8 #4 6'' 1 36 36 15.50 ' 558.00
10'-3"
8 Main bars at I/9-10a #4 4'' 1 43 43 10.50 ' 451.50
9'-6"
9 Main bars at L/4-6 #4 8'' 1 28 28 9.75 ' 273.00
5'-6"
10 Main bars at N/6-9 #3 8'' 1 31 31 5.75 ' 178.25
5'
11 Main bars at B-H/1 #3 8'' 1 80 80 5.25 ' 420.00
10'
12 Main bars at B-D/3 #4 6'' 1 44 44 10.00 ' 440.00
Page 92 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
STAIR
3'' 3'-11"
1 Main Bars #4 6'' 1 52 52 4.44 ' 230.88
3'' 29'-6"
2 Distribution Bars #3 8'' 1 6 6 30.00 ' 180.00
Total Quantity = ( Rft ) 8127.50 11162.61 0.00 0.00
Weight per Rft in Kgs 0.17 0.30 0.47 0.68
WEIGHT OF BARS Weight of Bars Dia Wise Kgs 1381.68 3382.27 0.00 0.00 4.764 Ton
Total Weight of Bars in Kgs 4763.95
Ground Floor Slab
A Beam
1 B-1
12'' 17'-3"
1 Bottom Bars #6 1 3 3 19.25 ' 57.75
12''
2 Top Bars #6 1 3 3 19.25 ' 57.75 17'-3"
6"x
3"
3 Stirrups #3 6'' 1 36 36 4.00 ' 144.00
2 B-2
12'' 22'-9"
1 Bottom Bars #6 1 5 5 24.75 ' 123.75
12''
2 Top Bars #4 1 4 4 24.75 ' 99.00 22'-9"
3"
6" x
3 Stirrups #3 6'' 1 47 47 4.50 ' 211.50
Page 93 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
3 B-3
12'' 24'-1.5"
1 Bottom Bars #6 1 5 5 26.13 ' 130.63
12''
2 Top Bars #6 1 2 2 26.13 ' 52.25 24'-1.5"
6" x
3"
3 Stirrups #3 6'' 1 49 49 4.50 ' 220.50
4 UB-5
12'' 18'
1 Bottom Bars #6 1 5 5 20.00 ' 100.00
12''
2 Curtailment Bars #4 1 4 4 20.00 ' 80.00 18'
12''
2 Top Bars #6 1 3 3 20.00 ' 60.00 18'
Page 94 of 111
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
6" x
3"
3 Stirrups #3 6'' 1 37 37 5.00 ' 185.00
5 CB-1
4'' 13'-4.5"
1 Bottom Bars #6 1 7 7 14.04 ' 98.25
4'' 13'-4.5"
2 Top Bars #4 1 6 6 14.04 ' 84.21
12"
3"
3 Stirrups #3 6'' 1 28 28 3.50 ' 98.00
6 CB-4
4'' 12'-5"
1 Bottom Bars #6 1 7 7 31.41 ' 219.87
4'' 12'-5"
2 Top Bars #4 1 6 6 31.41 ' 188.46
15"
3"
3 Stirrups #3 6'' 1 61 61 4.00 ' 244.00
7 CB-5
4'' 27'
1 Bottom Bars #6 1 7 7 27.66 ' 193.62
4'' 27'
2 Top Bars #4 1 6 6 27.66 ' 165.96
27"
3"
3 Stirrups #3 6'' 1 55 55 of 111 6.00 '
Page 95 330.00
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
18"
3"
4 Stirrups #3 6'' 1 55 55 4.00 ' 220.00
Total Quantity = ( Rft ) 1653.00 617.63 0.00 1093.86
Weight per Rft in Kgs 0.17 0.30 0.47 0.68
WEIGHT OF BARS Weight of Bars Dia Wise Kgs 281.01 187.14 0.00 746.01 1.214 Ton
Total Weight of Bars in Kgs 1214.16
PARAPET WALL
3'' 4'-4.5"
1 Vertical Bars #4 6'' 1 441 441 4.88 ' 2152.08
3'' 249'-6"
1 Horizontal Bars #3 8'' 1 6 6 250.00 ' 1500.00
Total Quantity = ( Rft ) 1500.00 2152.08 0.00 0.00
Weight per Rft in Kgs 0.17 0.30 0.47 0.68
WEIGHT OF BARS
Weight of Bars Dia Wise Kgs 255.00 652.08 0.00 0.00
0.907 Ton
Total Weight of Bars in Kgs 907.08
WEIGHT OF TOTAL Weight of Bars Dia Wise Kgs 1917.68500 4221.49296 0.00000 746.01252
6.885 Ton
BARS Total Weight of Bars in Kgs 6885.19
Page 96 of 111
PLOT# 49, SEC-1, PHASE(VIII)
BAR SHAPE
Page 97 of 111
DULE OF SECOND FLOOR SLAB
BAR SHAPE
3''
3''
Page 98 of 111
DULE OF SECOND FLOOR SLAB
BAR SHAPE
3''
3''
3''
3''
Page 99 of 111
DULE OF SECOND FLOOR SLAB
BAR SHAPE
BAR SHAPE
3''
3''
3''
3''
3''
3''
3''
BAR SHAPE
3''
3''
4.764 Ton
12''
12''
6"x15"
3"
12''
12''
3"
6" x 18"
BAR SHAPE
12''
12''
6" x 18"
3"
12''
12''
12''
BAR SHAPE
6" x 21"
3"
4''
4''
12" x 6"
3"
4''
4''
15" x 6"
3"
4''
4''
27" x 6"
3"
BAR SHAPE
18" x6"
3"
1.214 Ton
3''
3''
0.907 Ton
6.885 Ton
Providing and laying mild steel reinforcement bars (G-60) with and including the cost of straightening,removing twists, cutting, bending, binding,wastage,
overlaps as are not shown over the drawings, placing in position on cement concrete complete in all respects.
14'-6"
2 Distribution Bars #3 9'' 1 17 17 14.50 ' 246.50
11'-6"
3 Main Bars #3 9'' 1 25 25 11.50 ' 287.50
18'-1.5"
4 Distribution Bars #4 9'' 1 16 16 18.13 ' 290.00
3'' 5-9"
7 Extras Horz. #4 9'' 1 17 17 6.00 ' 102.00
7'-9"
8 Extras Horz. #4 9'' 1 25 25 7.75 ' 193.75
3'' 4'-9"
9 Extras Horz. #4 9'' 1 25 25 5.00 ' 125.00
3'' 5'-4"
10 Extras Ver. #4 9'' 2 Page 106 of38
19 111 5.58 ' 212.04
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
3'' 6'-9"
11 Extras Ver. #4 9'' 2 16 32 7.00 ' 224.00
Total Quantity = ( Rft ) 803.50 1146.79 0.00 0.00
Weight per Rft in Kgs 0.17 0.30 0.47 0.68
WEIGHT OF BARS Weight of Bars Dia Wise Kgs 136.60 347.48 0.00 0.00 0.484 To
Total Weight of Bars in Kgs 484.07
Beam
1 9" Wall
6'' 99'
1 Bottom Bars #4 1 2 2 100.00 ' 200.00
6''
2 Top Bars #4 1 2 2 100.00 ' 200.00 99'
3"
3 Stirrups #3 9'' 1 121 121 2.50 ' 302.500
2 4.5" Wall
6'' 19'
1 Bottom Bars #4 1 2 2 20.00 ' 40.00
6''
2 Top Bars #4 1 2 2 20.00 ' 40.00 19'
3"
Page 107 of 111
3 Stirrups #3 9'' 1 27 27 1.75 ' 47.250
BAR BENDING SCHEDULE OF SECOND FLOOR SLAB
BAR SHAPE
12'-3"
14'-6"
11'-6"
18'-1.5"
5-9"
7'-9"
4'-9"
5'-4"
Page 109 of 111
DULE OF SECOND FLOOR SLAB
BAR SHAPE
6'-9"
0.484 Ton
99' 6''
6''
99'
3"
6" x 6"
19' 6''
6''
19'
3"
6" x 1.5"
Page 110 of 111
DULE OF SECOND FLOOR SLAB
BAR SHAPE
6" x 1.5"
0.205 Ton
0.689 Ton