Вы находитесь на странице: 1из 14

Journal of Natural Gas Science and Engineering 37 (2017) 234e247

Contents lists available at ScienceDirect

Journal of Natural Gas Science and Engineering


journal homepage: www.elsevier.com/locate/jngse

Effect of full-bore natural gas release on fire and individual risks: A


case study for an LNG-Fueled ship
Bongsik Chu, Daejun Chang*
Department of Mechanical Engineering, School of Mechanical, Aerospace and Systems Engineering, Korea Advanced Institute of Science and Technology, 291
Daehak-ro, Yuseong-gu, Daejeon 34141, Republic of Korea

a r t i c l e i n f o a b s t r a c t

Article history: This study investigated the significance of categorizing and selecting representative leak sizes in
Received 29 June 2016 Quantitative Risk Assessment (QRA) for estimating natural gas fire risks. In most fire QRA procedures, the
Received in revised form full-bore sizes of leaks have been overlooked even though they causes the catastrophic consequences
27 September 2016
with relatively high frequencies. So, in the present study, the effect of particular leak sizes on the in-
Accepted 19 November 2016
Available online 24 November 2016
dividual risks (IRs) were investigated through the fire risk assessment. As case studies, LNG (Liquefied
Natural Gas) fuel gas supply system for a large ship were considered with three different approaches.
Approach 1 considers only three categories of leak sizes; small, medium, and large. Approach 2 includes
Keywords:
Quantitative risk assessment
the full-bore leak in addition to categories of Approach 1, and Approach 3 reflects more categories of leak
Hydrocarbon fire sizes with every 1 mm increment in diameter. Compared with the total IR of Approach 3, the total IR of
Full-bore leak Approach 1 was two times lower, whereas Approach 2 resulted in the comparable total IR with an
Individual risk approximately 4% deviation. Admitting that Approach 3 should be close to the exact solution, Approach 2
LNG fuel gas supply system gave acceptable results, whereas Approach 1 unsatisfactorily underestimated the total IR. The results
indicated that full-bore leak accidents are critically important scenarios and omission of them can lead to
misjudgment in the risk-informed decision-making process. Taking the full-bore accidents into addi-
tional account to the conventional simplified QRA can reduce the time and effort for estimating the leak-
related risks without a significant loss of accuracy in the estimated risks.
© 2016 Published by Elsevier B.V.

1. Introduction accompanying catastrophic outcomes have occurred in the offshore


field over the last several decades (HSE, 2007).
To meet the increasing demands for energy and strict environ- To reduce the risk of such disasters, industries have made an
mental regulations, the consumption of natural gas is steadily incessant effort to provide a combination of prevention, detection,
expanding across the world (Economides and Wood, 2009; Wood, control and mitigation measures. The performance standards for
2012), presenting challenges to improve safety standards. One of these measures should be consolidated at the concept design stage,
the most important challenges to hydrocarbon systems is the during which design and operating philosophies, including those
management of fire and explosion risks because the combustible for fire and explosion safety, are established. Target systems or fa-
fluids are usually stored in bulk and used at high pressure or cilities should be designed to meet these philosophies and the
cryogenic conditions (Lee et al., 2016). Shipping and offshore in- acceptance criteria in normal engineering practice.
dustries that are additionally subject to extreme marine environ- Quantitative Risk Assessment (QRA) has been employed as a
ments have especially been intrinsically threatened by such rational and rigorous method to estimate the risks, including the
hazards, leading to disastrous consequences: injury or death of fire risk, and to evaluate the effectiveness of the implemented
operators, damage to assets, physical and biological degradation of measures. Although the term Formal Safety Assessment (FSA) is
facilities, interruption of operation and production, and disruption preferable to QRA in the shipping industry, there is no fundamental
of business (Spouge, 1999). A number of hydrocarbon accidents difference between them. QRA or FSA is used to quantify risks,
which are expressed as a combination of frequency and conse-
quences, and to provide input to a decision-making process. QRA
* Corresponding author. has made great advances in recent decades thanks to plentiful
E-mail address: djchang@kaist.ac.kr (D. Chang). theoretical and experimental investigations.

http://dx.doi.org/10.1016/j.jngse.2016.11.043
1875-5100/© 2016 Published by Elsevier B.V.
B. Chu, D. Chang / Journal of Natural Gas Science and Engineering 37 (2017) 234e247 235

Nomenclature F(d) frequency of holes exceeding size d (per meter year)


HP high pressure
a equipment constant HSE health and safety executive
ALARP as low as reasonably practicable IMO International Maritime Organization
A10% 10% of lethal area (m2) IR individual risk
A50% 50% of lethal area (m2) LNG liquefied natural gas
A100% 100% of lethal area (m2) m equipment constant
C equipment constant n equipment constant
Cn number of fatalities for nth accident scenario NOx nitrogen oxide
CO2 carbon dioxide OGP International Association of Oil and Gas Producers
D equipment diameter (mm) P&ID piping and instrumentation diagram
d hole diameter (mm) PBU pressure build-up
EER escape, evacuation and rescue PFD process flow diagram
ESD emergency shutdown PLL potential loss of life (per year)
ETA event tree analysis pignition
n ignition probability for nth accident scenario
FABIG Fire and Blast Information Group POBavg average annual number of people on board
FGSS fuel gas supply system Pr probit function
Fn fire frequency for nth accident scenario (per year) Q thermal radiation (kW/m2)
fnleak leak frequency for nth accident scenario (per year) QRA quantitative risk assessment
Frup additional rupture frequency (per meter year) SOx sulfur oxide
FSA formal safety assessment t exposure time (s)

Although the accuracy of QRA has been remarkably improved, QRA results of two different approaches to selecting representative
most QRA approaches have been influenced by inherent uncer- leak sizes and to determine the effects of a particular leak scenario
tainty, which reduces confidence in the results. The uncertainty is on the risk estimation.
especially significant for the QRA of hydrocarbon fire accidents.
Health and Safety Executive (HSE) defined several sources of un-
2. Theoretical background
certainty regarding fire accidents and paid attention to inaccuracy
and incompleteness by selecting representative scenarios (HSE,
2.1. Procedure of quantitative risk assessment of hydrocarbon fire
2006).
Accidents can occur through infinitely various scenarios. Thus, it
Fig. 1 presents the steps of the QRA procedure to estimate and
is infeasible to model all cases and possibilities due to limited time
control fire risks. The QRA procedure used to estimate hydrocarbon
and effort, especially during the initial design stage. The measured
fire risks includes various approaches and techniques that are in-
risks from frequency and consequence analysis are highly depen-
tegrated for one common aim: the quantification of frequency and
dent on the defined scenarios. Analysts may have the challenge of
consequences. There are three primary tasks to estimate and
selecting a limited number of scenarios that can represent all
manage the fire risks: the selection of representative scenarios, the
possible events with acceptable tolerance. In consequence, the se-
estimation of frequency, and the analysis of consequences.
lection of representative scenarios is one of the most important
tasks for an accurate assessment.
Selecting representative scenarios is also a formidable challenge 2.2. Selection of representative scenarios
for the QRA of hydrocarbon fire accidents because the frequency
and consequences of fire accidents can be affected by many factors. Hydrocarbon accidents can occur through innumerable sce-
The selection of representative leak sizes is a crucial task in the narios. As the first step of the QRA, analysts should choose a limited
selection of scenarios (Spouge, 1999). A hydrocarbon fire accident number of scenarios that represent all possible events. This step has
begins with a leak, and the results of frequency and consequence a significant influence on the estimates of fire frequency and con-
analysis are significantly affected by the leak sizes. For example, the sequences in the subsequent steps.
ignition probability of a leak is largely affected by the leak rate, How a leak can lead to accidents depends on whether it is
which is in turn a strong function of leak size. Although the se- ignited or not. The location, direction of leak and environmental
lection of leak sizes may give rise to one of the largest uncertainties conditions exert a combined effect on the hydrocarbon fire risks.
causing inaccuracy in QRA, there is no definite basis or criterion for For example, a leak located in the central part of the system has
choosing representative leak sizes. Most QRA approaches to hy- more detrimental potential than one occurring in the circumfer-
drocarbon accidents have classified leak sizes in three different ential part. However, in the case where the leak direction of the
categories without any sensitivity analysis (Ahmad et al., 2013; latter is toward the inside of the system, its consequences can be as
Badri et al., 2013; Bris et al., 2014; Dan et al., 2014; FABIG, 2010; severe as those of the former. Accordingly, the occurrence and
FABIG, 2014; Krueger and Smith, 2003; Moon et al., 2009; Paik escalation of hydrocarbon accidents are influenced by various pa-
et al., 2011; Yanlin and Jang, 2015). rameters, and scenarios are sequential combinations of those
This investigation identifies a limitation in the procedure of parameters.
selecting representative leak sizes for estimating hydrocarbon fire The Event Tree Analysis (ETA), which is as a systematic approach
risks. This study pays attention to a particular leak size that is to determining representative scenarios, is well developed and
frequently omitted or overlooked in existing QRA approaches, widely used (Spouge, 1999). An event tree is a diagram that shows
despite its importance. A case study is performed to compare the how an initial event evolves into its final states based on binary
reasoning through the evolution of the event, including the ignition
236 B. Chu, D. Chang / Journal of Natural Gas Science and Engineering 37 (2017) 234e247

Fig. 1. Steps of the QRA procedure for hydrocarbon fire accidents.

and operability of safety systems, together with the parameters of 2.3. Leak frequency function based on leak size
leak size and direction.
Defining representative leak sizes is a crucial task in selecting The dependence of the leak frequency on equipment can be
representative scenarios because the estimated risks are sensitive obtained from statistical data sources, which show a strong corre-
to the leak size (FABIG, 2010; FABIG, 2014; Spouge, 1999). Note that lation between the leak frequency and size. The HSE database is one
discrete leak sizes should be defined for QRA although real leak of the standard sources of leak frequency with a high quality and
sizes are arbitrary and continuous. QRA usually considers the hole quantity of data for offshore fields (DNV, 2007; Falck et al., 2009;
diameter range from 1 mm to the maximum or full-bore diameter Lee et al., 2015; OGP, 2010a; Pitblado et al., 2011; Spouge, 1999,
of pipe segments. In terms of the leak rate, only release rates 2005, 2006; Vinnem, 2007b). Spouge (2005) presented a set of
exceeding 0.1 kg/s are usually considered because small leaks lead analytical leak frequency functions based on the HSE database as
to an insignificant impact (Vinnem, 2007a). shown in Eq. (1). This generic leak frequency function has been
In most existing QRA methodologies, leak sizes are classified
into three size categories: small (minor), medium (significant), and
large (major). Typically, the median value of each leak size range is Table 1
used as a representative value. It is assumed that the values Example of categories of leak sizes and typical leak rate ranges.
selected for each category represent all possible leak accidents.
Leak size category Hole diameter range, mm Leak rate, kg/s
Table 1 shows an example of categories of hole diameter and their
typical leak rate ranges (Spouge, 1999). Of course, the leak rate is a Small 1e10 0.1e1
Medium 10e50 1e20
function of fluid properties as well as the hole diameter.
Large 50 ~ equipment diameter >20
B. Chu, D. Chang / Journal of Natural Gas Science and Engineering 37 (2017) 234e247 237

Fig. 2. Frequency of a process pipe segment with 1 m in length and 100 mm in diameter.

verified and developed to obtain credible and consistent leak fre- consequences.
quency for any leak size categories (Falck et al., 2009; OGP, 2010a; The reason for the high frequency of the full-bore leak is highly
Pitblado et al., 2011; Spouge, 2006). Besides, with this equation, related to the cause of rupture of the process equipment. Dropped
DNV has developed the commercial LEAK software which is object accidents onto the installation can damage equipment con-
frequently used in the industrial and academic fields (Celnik and taining hydrocarbons and may result in a full-bore release (DNV,
Bain, 2012; DNV, 2007; Lee et al., 2015; Reniers et al., 2006; 2010b; Mazzola, 2000; OGP, 2010a; Spouge, 1999). Several condi-
Vinnem, 2007b). tions should be satisfied for a dropped object to result in hydro-
carbon leaks; it should penetrate the deck or protection above the
equipment, if any, and then strike the equipment with sufficient
FðdÞ ¼ Cð1 þ aDn Þdm þ Frup (1) kinetic energy to fully cut off the piping. Table 2 presents the
This equation expresses the frequency of leaks as a function of probability of dropped objects per lift derived from the Worldwide
the hole diameter. Here, F(d) is the frequency of holes exceeding Offshore Accident Databanks and UK HSE's ORION databases (OGP,
size d, D is the equipment diameter, d is the hole diameter, and Frup 2010b). The frequency of objects dropped onto the installation can
is the additional rupture frequency. C, a, m, and n are constants for be estimated based on the probability of the dropped objects per
each equipment type. The rupture frequency and constants are lift and the number of annual lifts.
defined depending on the type of equipment and leak. The number of lifts per year depends on the types of units. For
All leaks in the HSE database are divided into three scenarios: example, in the case of a wellhead platform, the number of annual
zero pressure leaks, limited leaks, and full leaks. It is statistically loaded lifts that could cause full rupture is approximately 800 lifts
known that 10% of leak accidents are zero pressure leaks, 59% of per year. In this situation, the frequency of objects dropped onto the
leak accidents are limited leaks, and the remaining 31% are full installation is 0.01 per year. Even if all dropped object accidents
leaks (Spouge, 2005). The zero pressure leaks are normally would not lead to rupturing process equipment, this can certainly
excluded from QRA for hydrocarbon accidents because most of be considered a large number. Furthermore, full-bore leaks due to
them do not lead to significant consequences. Full leaks are pres- dropped objects could have high ignition probability as a result of a
surized leaks and always included in QRA. They may initiate serious large release rate and sparks on impact. Based on this reasoning,
accidents for personnel, structures and other safety functions. the full-bore hydrocarbon release seems to have the highest po-
Limited leaks include all other pressurized leaks. This type of leak tential risk, and the contribution to the hydrocarbon leak scenario
may have a limited leak duration or leak rate. Thus, this scenario is should not be neglected.
concerned with personnel risk rather than asset risk or global
structural failure (OGP, 2010a). 2.4. Comparative approaches with different leak size categories
Hole diameters vary from 1 mm to the full-bore diameter. Most
statistical data sources indicate that the smaller the size is, the Based on the reasoning, three approaches are conceivable for
larger its frequency is. Fig. 2 shows the total leak frequency, F(d), of QRA of the fire accidents:
a process pipe segment with 1 m in length and 100 mm in diameter,
derived from a general leak frequency function (DNV, 2007). Table 2
As shown in the graph, leak frequency exponentially diminishes Probability of dropped objects per lift.
with increasing hole diameter. However, a sudden peak in fre-
Drop onto: Installation Sea Vessel
quency is observed at the point of the largest hole diameter, or the
full-bore size. This study pays attention to this point because the Mobile units (per lift) 1.2E-05 1.4E-06 9.4E-07
Fixed installations (per lift) 1.4E-05 8.8E-07 1.6E-06
full-bore release may potentially lead to the most catastrophic
238 B. Chu, D. Chang / Journal of Natural Gas Science and Engineering 37 (2017) 234e247

Fig. 3. LNG fuel gas supply system for large oil tanker.
B. Chu, D. Chang / Journal of Natural Gas Science and Engineering 37 (2017) 234e247 239

Fig. 4. Process flow diagram of LNG-FGSS.

Table 3
Isolatable segments and major inventories for target system.

Segment Segment 1 ~ 8 e Gas Segment 1 ~ 8 e Liquid Segment 9 Segment 10 Segment 11

Description LNG Fuel Tank LNG Fuel Tank Suction Drum HP pump HP vaporizer
Mole fraction
Nitrogen 0.0287 0.0025 0.0287 0.0287 0.0287
Methane 0.9707 0.9394 0.9707 0.9707 0.9707
Ethane 0.0005 0.0480 0.0005 0.0005 0.0005
Propane 0.0000 0.0082 0.0000 0.0000 0.0000
n-Butane 0.0000 0.0020 0.0000 0.0000 0.0000
i-Butane 0.0000 0.0000 0.0000 0.0000 0.0000
Pressure, bara 5.0 5.0 5.0 300 300
Temperature,  C 137.4 137.4 137.4 116.6 45
Phase Gas Liquid Liquid Liquid Gas
Density, kg/m3 8.1 406.8 406.8 414.9 217.6

 Approach 1 considers only three categories of leak sizes: small, detrimental than the explosion risk. An explosion in open space is
medium, and large. unlikely to occur, and the overpressure even in the case of explo-
 Approach 2 considers four categories of leak sizes: small, me- sion is not considerable. In contrast, the fire risk due to cryogenic
dium, large, and full bore. LNG and high-pressure natural gas after evaporation may lead to
 Approach 3 considers more categories of leak sizes, for example, catastrophic consequences and should be addressed appropriately.
every hole diameter in increments of 1 mm. An LNG-FGSS for a large oil tanker, as shown in Fig. 3, is
considered for the case study.
Approach 1 has been employed by most conventional QRA This system mainly comprises eight LNG storage tanks of cy-
studies, whereas Approach 2 additionally considers the effect of the lindrical pressure vessels, a suction drum, a high-pressure (HP)
full bore leak. Approach 3 is highly costly in terms of effort and time pump, and an HP vaporizer, as shown in Fig. 4. A pressure build-up
and unreasonable to implement in usual QRA studies for large-scale (PBU) is installed with the storage tank to boost the internal pres-
hydrocarbon installations. However, the results of Approach 3 can sure. Alternatively, a submerged pump can be installed. The suction
be regarded as the exact solution to judge the accuracy of Ap- drum removes vapor that otherwise could enter the pump, leading
proaches 1 and 2. the mechanical damage. The pressurized LNG is evaporated in the
vaporizer and supplied to a main engine.
The case study conducts Approaches 1 and 2 to demonstrate the
3. Case study effects of a full-bore hydrocarbon leak on the estimated risk. As
described in Section 2.4, Approach 1 categorizes the leak sizes into
3.1. General three different ranges of small, medium, and large, in line with
most studies. In contrast, Approach 2 separates a full-bore leak
For compliance with emission regulations on SOX, NOX, partic- scenario from a large leak scenario. Thus, this approach contains
ulate matter and CO2 (Devanney, 2011; IMO, 2009a, b), a significant four categories of leak sizes: small, medium, large, and full-bore.
portion of oceangoing ships are expected to sail on natural gas. The The individual risk (IR) of the target system is estimated by the
use of natural gas as a fuel also has validity from the viewpoint of two different approaches to observe how the approaches affect the
economics (Li et al., 2015; Seo et al., 2016). Because fuel gas should risk estimation.
be stored in a liquefied form or LNG, a dedicated system, called the Approach 3 is also conducted to verify the results of Approach 1
LNG fuel gas supply system (FGSS), should be installed onboard. and Approach 2. In this approach, leak sizes are categorized every
The system should accompany subsystems for the storage and 1 mm, which requires leak scenarios to be subdivided as finely as
handling of pressurized LNG that surely present LNG-related risks. possible. It is obvious that Approach 3 is the most detailed analysis
When the LNG-FGSS is above the deck, the fire risk is more
240 B. Chu, D. Chang / Journal of Natural Gas Science and Engineering 37 (2017) 234e247

Table 4
Leak size categories and representative hole diameters for each segment and each approach.

Segment Approach Leak size category Hole diameter range, mm Representative hole diameter, mm

Segment 1 ~ 8 e Gas Approach 1 Small 10e20 15


Medium 20e50 35
Large 50e150 100
Approach 2 Small 10e20 15
Medium 20e50 35
Large 50e150 100
Full bore 150 150
Approach 3 10 mm 10 10
11 mm 11 11
« « «
149 mm 149 149
150 mm 150 150
Segment 1 ~ 8 e Liquid Approach 1 Small 5e15 10
Medium 15e50 32
Large 50e150 100
Approach 2 Small 5e15 10
Medium 15e50 32
Large 50e150 100
Full bore 150 150
Approach 3 5 mm 5 5
6 mm 6 6
« « «
149 mm 149 149
150 mm 150 150
Segment 9 Approach 1 Small 5e15 10
Medium 15e40 28
Large 40e100 70
Approach 2 Small 5e15 10
Medium 15e40 28
Large 40e100 70
Full bore 100 100
Approach 3 5 mm 5 5
6 mm 6 6
« « «
99 mm 99 99
100 mm 100 100
Segment 10 Approach 1 Small 3e5 4
Medium 5e30 18
Large 30e100 65
Approach 2 Small 3e5 4
Medium 5e30 18
Large 30e100 65
Full bore 100 100
Approach 3 3 mm 3 3
4 mm 4 4
« « «
99 mm 99 99
100 mm 100 100
Segment 11 Approach 1 Small 3e10 6
Medium 10e30 20
Large 30e80 55
Approach 2 Small 3e10 6
Medium 10e30 20
Large 30e80 55
Full bore 80 80
Approach 3 3 mm 3 3
4 mm 4 4
« « «
79 mm 79 79
80 mm 80 80

and may give the most accurate results among the three ap- leak in an isolatable segment, the ESD valves are closed, and the
proaches. The case study commonly follows the procedure pre- inventory in the isolatable segment is released to a safe location.
sented in Fig. 1. The isolatable segments and major inventories are listed in Table 3.
Note that Segments 1 to 8 correspond to the eight LNG fuel tanks.
3.2. Scenario selection The segment volume includes that of the process equipment and
piping segments.
The target process facility is divided into several isolatable Hydrocarbon fire risk analysis is performed on the basis of
segments by ESD (Emergency Shutdown) valves as shown in Fig. 4. representative leak size categories. The hole diameter ranges are
Typically, the inventory within an isolatable section is subject to bounded from the low end by the minimum with a 0.1 kg/s leak rate
practically identical pressure and temperature. In the event of a to the largest diameter of the pipe segment. The midpoints of hole
B. Chu, D. Chang / Journal of Natural Gas Science and Engineering 37 (2017) 234e247 241

Table 5
Summary of variables for accident scenarios.

Variables Description

Leak size  Approach 1: Classified into small, medium and large size categories
 Approach 2: Classified into small, medium, large and full-bore size categories
 Approach 3: Classified into hole diameter categories of every 1 mm
(the leak rate depends on the inventory condition and hole diameter)
Leak position  Located at the center of the target segment
Leak direction  Critical leak direction at each leak position
Ignition type  Immediate ignition: Early ignition to cause jet fires
Wind speed  1.5 m/s
Atmospheric condition (Pasquill stability class)  F (Stable)

Fig. 5. Ignition probability with leak rate.

diameter ranges are selected as representative hole diameters. It descriptions.


should be noted that the defined ranges of each segment vary with
the characteristics of the segment, including inventory conditions 3.3. Frequency analysis
and facility characteristics. Table 4 shows leak size categories and
representative hole diameters for each segment and each approach. The frequency analysis is carried out with a combination of ETA
Other variables should be identified for further fire risk analysis. and statistical data. The event is a hydrocarbon leak, and the leaked
It is assumed that the leakage position should be located at the inventory may be a fire or harmless depending on ignition. The fire
volumetric center of the defined segment. This study considers the frequency for the nth accident scenario Fn is calculated by multi-
most critical leak direction at each leak position to ensure conser- plication of the leak frequency and conditional probabilities of
vative results. ignition as shown in the following equation.
The leaked inventory may catch fire, explode, or cause no harm
ignition
depending on whether the leak is ignited or diluted out. There are Fn ¼ fnleak  pn (2)
two main types of ignition: immediate ignition and delayed igni-
tion. For defined inventory conditions, the leakage of liquid in- where fleak is the leak frequency and pignition is the ignition
ventory immediately becomes a spray of small droplets and could probability.
incur only jet fire upon ignition (Dan et al., 2014; Spouge, 1999). The leak frequency is obtained from the historical data and Eq.
Thus, pool fire is not considered in the case study. Delayed ignition (1) in Section 4. For the estimation of leak frequency, all equipment
of the flammable gas cloud results in explosion. Because flammable and piping elements of each segment are counted. Pressurized
gas clouds rarely form in the given condition, explosion is not leaks, including full leaks and limited leaks, are considered as the
considered in this case. Although an explosion can occur above the leak scenario. The ignition probability can be inferred from the
open deck, its impact or explosion overpressure are insignificant. simplified and sophisticated models based on historical data. The
The properties of fire also depend on the weather conditions on change in the ignition probability with the leak rate for gas and
the sea. To obtain conservative results, the atmospheric condition is liquid is shown in Fig. 5 (Cox et al., 1990; Mannan, 2014). The im-
assumed to be very stable with wind speed set as 1.5 m/s to mediate ignition probability is assumed to be 0.5 of the overall
consider a lower dispersion scenario (Dan et al., 2014). Table 5 ignition probability.
shows the summary of variables for the scenarios and their The results of the frequency estimation for each segment and
242 B. Chu, D. Chang / Journal of Natural Gas Science and Engineering 37 (2017) 234e247

Table 6
Results of frequency analysis.

Segment Approach Leak size category Leak freq., per year Ignition prob. Fire freq., per year

Segment 1 ~ 8 e Gas Approach 1 Small 3.721E-03 2.783E-03 1.035E-05


Medium 5.570E-04 8.264E-03 4.603E-06
Large 4.382E-05 3.183E-02 1.395E-06
Approach 2 Small 3.721E-03 2.783E-03 1.035E-05
Medium 5.570E-04 8.264E-03 4.603E-06
Large 2.788E-05 3.183E-02 8.875E-07
Full bore 1.594E-05 5.359E-02 8.545E-07
Approach 3 10 mm 3.313E-04 1.653E-03 5.476E-07
11 mm 2.799E-04 1.868E-03 5.230E-07
« « « «
149 mm 9.371E-08 5.313E-02 4.979E-09
150 mm 1.594E-05 5.359E-02 8.545E-07
Segment 1 ~ 8 e Liquid Approach 1 Small 3.266E-04 6.780E-03 3.266E-04
Medium 1.269E-04 3.021E-02 1.269E-04
Large 1.222E-04 1.306E-01 1.222E-04
Approach 2 Small 3.266E-04 6.780E-03 3.266E-04
Medium 1.269E-04 3.021E-02 1.269E-04
Large 4.607E-05 1.306E-01 4.607E-05
Full bore 7.613E-05 2.198E-01 7.613E-05
Approach 3 5 mm 7.267E-05 2.783E-03 2.023E-07
6 mm 5.390E-05 3.518E-03 1.896E-07
« « « «
149 mm 1.421E-07 2.179E-01 3.098E-08
150 mm 7.613E-05 2.198E-01 1.674E-05
Segment 9 Approach 1 Small 4.988E-04 6.780E-03 3.382E-06
Medium 1.788E-04 2.545E-02 4.551E-06
Large 1.946E-04 8.258E-02 1.607E-05
Approach 2 Small 4.988E-04 6.780E-03 3.382E-06
Medium 1.788E-04 2.545E-02 4.551E-06
Large 8.022E-05 8.258E-02 6.625E-06
Full bore 1.144E-04 1.306E-01 1.494E-05
Approach 3 5 mm 1.094E-04 2.783E-03 3.044E-07
6 mm 8.160E-05 3.518E-03 2.871E-07
« « « «
99 mm 5.422E-07 1.289E-01 6.989E-08
100 mm 1.144E-04 1.306E-01 1.494E-05
Segment 10 Approach 1 Small 1.292E-03 8.165E-03 1.055E-05
Medium 1.625E-03 5.637E-02 9.161E-05
Large 1.070E-03 2.934E-01 3.140E-04
Approach 2 Small 1.292E-03 8.165E-03 1.055E-05
Medium 1.625E-03 5.637E-02 9.161E-05
Large 5.131E-04 2.934E-01 1.505E-04
Full bore 5.572E-04 5.102E-01 2.843E-04
Approach 3 3 mm 5.988E-04 5.642E-03 3.378E-06
4 mm 4.014E-04 8.165E-03 3.278E-06
« « « «
99 mm 2.806E-06 5.037E-01 1.413E-06
100 mm 5.572E-04 5.102E-01 2.843E-04
Segment 11 Approach 1 Small 1.220E-03 1.024E-02 1.249E-05
Medium 3.617E-04 4.808E-02 1.739E-05
Large 3.712E-04 1.763E-01 6.545E-05
Approach 2 Small 1.220E-03 1.024E-02 1.249E-05
Medium 3.617E-04 4.808E-02 1.739E-05
Large 1.553E-04 1.763E-01 2.739E-05
Full bore 2.159E-04 2.853E-01 6.160E-05
Approach 3 3 mm 3.898E-04 4.203E-03 1.638E-06
4 mm 2.456E-04 6.082E-03 1.494E-06
« « « «
79 mm 1.164E-06 2.808E-01 3.268E-07
80 mm 2.159E-04 2.853E-01 6.160E-05

category are shown in Table 6. Frequency analysis of all approaches reason. The ignition probabilities of the large leak categories in
is carried out in the same way. Because Approach 1 and Approach 2 Approach 1 and Approach 2 are identical because representative
have the same small and medium leak categories, they have the hole diameters of them are same. Approach 2 separates a full-bore
same frequencies of leak, ignition, and fire among the leak cate- leak scenario from a large leak scenario and it has its own repre-
gories. However, the frequencies are different for the larger cate- sentative hole size. Since the fire frequency is the product of the
gories; the leak frequency of the large leak category in Approach 1 leak frequency and the ignition probability, the sum of the fire
is equal to the sum of the leak frequencies of the large and full-bore frequencies of the large and full-bore leak categories in Approach 2
leak categories in Approach 2. Note that this equality does not hold is not same with the fire frequency of the large leak category in
for the ignition probability and fire frequency due to the following Approach 1 as shown in Table 6.
B. Chu, D. Chang / Journal of Natural Gas Science and Engineering 37 (2017) 234e247 243

Table 7
Results of consequence analysis.

Segment Approach Leak size category Area of lethality level, m2

10% 50% 100%

Segment 1 ~ 8 e Gas Approach 1 Small 18.1 9.3 5.4


Medium 130.8 84.9 54.3
Large 1073.7 735.0 499.2
Approach 2 Small 18.1 9.3 5.4
Medium 130.8 84.9 54.3
Large 1073.7 735.0 499.2
Full bore 2359.4 1638.0 1124.8
Approach 3 10 mm 3.7 1.3 0.0
11 mm 6.2 1.5 0.9
« « « «
149 mm 2329.1 1616.6 1109.8
150 mm 2359.4 1638.0 1124.8
Segment 1 ~ 8 e Liquid Approach 1 Small 150.4 96.9 61.5
Medium 1563.5 1063.2 715.2
Large 9663.1 8876.6 6895.9
Approach 2 Small 150.4 96.9 61.5
Medium 1563.5 1063.2 715.2
Large 9663.1 8876.6 6895.9
Full bore 14772.8 13939.4 12940.9
Approach 3 5 mm 23.3 16.2 9.1
6 mm 42.8 28.1 16.7
« « « «
149 mm 14705.5 13868.5 12848.7
150 mm 14772.8 13939.4 12940.9
Segment 9 Approach 1 Small 150.4 96.9 61.5
Medium 1206.2 815.0 545.7
Large 7029.1 4947.7 3415.8
Approach 2 Small 150.4 96.9 61.5
Medium 1206.2 815.0 545.7
Large 7029.1 4947.7 3415.8
Full bore 9663.1 8876.6 6895.9
Approach 3 5 mm 23.3 16.2 9.1
6 mm 42.8 28.1 16.7
« « « «
99 mm 9617.3 8803.3 6761.3
100 mm 9663.1 8876.6 6895.9
Segment 10 Approach 1 Small 130.0 80.4 55.8
Medium 2612.3 1830.5 1260.9
Large 11978.8 10907.3 9359.6
Approach 2 Small 130.0 80.4 55.8
Medium 2612.3 1830.5 1260.9
Large 11978.8 10907.3 9359.6
Full bore 19980.0 17293.2 14319.4
Approach 3 3 mm 80.00 35.80 27.20
4 mm 130.0 80.4 55.8
« « « «
99 mm 19980.0 17176.1 14245.5
100 mm 19980.0 17293.2 14319.4
Segment 11 Approach 1 Small 79.3 45.7 21.1
Medium 1471.0 1000.1 671.9
Large 4880.8 4262.8 3902.1
Approach 2 Small 79.3 45.7 21.1
Medium 1471.0 1000.1 671.9
Large 4880.8 4262.8 3902.1
Full bore 7821.3 6637.8 6073.1
Approach 3 3 mm 0.35 0.00 0.00
4 mm 18.5 3.5 0.0
« « « «
79 mm 7722.6 6560.5 6005.6
80 mm 7821.3 6637.8 6073.1

3.4. Consequence analysis estimate the lethality of the accidents.


The radiation contours from the consequence modeling are
This section presents the physical impact of the fire on opera- used to estimate the fatality rate of personnel exposed to jet fires.
tors. Several models based on experimental data and commercial It is assumed that immediate fatality should be assumed for ra-
codes are available to estimate the fire results. In this case study, diation above 37.5 kW/m2. Delayed fatality depends on the radi-
consequence modeling is conducted by DNV PHAST, which is one of ation intensity and the exposure time between 12.5 kW/m2 and
the most commonly used commercial codes in the industry (DNV, 37.5 kW/m2 (Spouge, 1999). The lethality of the jet fire is esti-
2010a) and provides contours of thermal radiation levels to mated through two radiation criteria which are 12.5 kW/m2 and
244 B. Chu, D. Chang / Journal of Natural Gas Science and Engineering 37 (2017) 234e247

Table 8 exposed to thermal radiation over a given duration of time. It is


Number of fatalities for both approaches. assumed that the workers exposed to radiation should use escape
Segment Approach Leak size category No. Of fatalities routes and leave the area within 30 s. In other words, 30 s of
Segment 1 ~ 8 e Gas Approach 1 Small 0.0103
exposure time is considered to be the worst case. Incident radiation
Medium 0.0928 levels of 18.3 kW/m2 and 26.6 kW/m2 represent the 10 and 50%
Large 0.8145 lethality levels from a given probit function, respectively. Table 7
Approach 2 Small 0.0103 shows the results of the consequence analysis for each segment
Medium 0.0928
and category.
Large 0.8145
Full bore 1.8187 The number of fatalities for an accident scenario can be obtained
Approach 3 10 mm 0.0011 by considering the probability of death, the area of lethality level,
11 mm 0.0021 and the population density. The number of fatalities for the nth
« «
accident scenario Cn is defined as follows.
149 mm 1.7949
150 mm 1.8187
Segment 1 ~ 8 e Liquid Approach 1 Small 0.1058 Cn ¼ POBavg
Medium 1.1752
   
Large 9.9661
A100
n
% þ 0:5  A50 %  A100 % þ 0:1  A10 %  A50 %
n n n n
Approach 2 Small 0.1058

Deck Area
Medium 1.1752
Large 9.9661
(4)
Full bore 16.9213
Approach 3 5 mm 0.0167 where POBavg is the average annual number of people on board.
6 mm 0.0299 A100%, A50%, and A10% are the 100%, 50%, and 10% lethality levels,
« « respectively. It is assumed that the number of crew on deck is 25
149 mm 16.8197
and that the total deck area of the oil tanker is 19,980 m2. Table 8
150 mm 16.9213
Segment 9 Approach 1 Small 0.1058 shows the number of expected fatalities for each segment and ac-
Medium 0.9002 cident scenario. Note that both approaches have a number of fa-
Large 5.4929 talities for the small to large leak categories.
Approach 2 Small 0.1058
Medium 0.9002
Large 5.4929 3.5. Risk estimation
Full bore 9.9661
Approach 3 5 mm 0.0167
6 mm 0.0299
The risk to personnel is expressed by the IR, which states the
« « probability of fatalities per year for an individual worker. The IR is
99 mm 9.8394 expressed by the following equation (Vinnem, 2007b).
100 mm 9.9661
Segment 10 Approach 1 Small 0.0914 PLL
Medium 2.0319 IR ¼ 8760
(5)
Large 12.8135 POBavg $Exposed time ðHÞ
Approach 2 Small 0.0914
Medium 2.0319 where PLL is the potential loss of life, which is the annual number of
Large 12.8135
Full bore 20.1138
fatalities and can be calculated by multiplying the results of the
Approach 3 3 mm 0.0449 frequency and consequence analyses (Vinnem, 2007b).
4 mm 0.0914 X
« « PLL ¼ ðFn $Cn Þ (6)
99 mm 20.0090 n
100 mm 20.1138
Segment 11 Approach 1 Small 0.0460 For crews on board the oil tanker, it is assumed that the exposed
Medium 1.1049 time is 6 months per year, i.e., 4380 h per 8760 h.
Large 5.1855 Table 9 Summarizes the IR for crew members. Based on different
Approach 2 Small 0.0460
Medium 1.1049
representative leak categories, the results of the two approaches
Large 5.1855 produce different individual risks for the target system. The IR of
Full bore 8.1003 Approach 1 is 1.197E-04, whereas that of Approach 2 is 2.298E-04,
Approach 3 3 mm 0.0000 nearly two times higher than that of Approach 1. The IR of Approach
4 mm 0.0040
3 is 2.204E-04, which is relatively close to that of Approach 2. In
« «
79 mm 8.0071 consequence, Approach 1 considerably underestimates the IR in
80 mm 8.1003 comparison with Approach 2 or 3.

4. Results and discussion


37.5 kW/m2.
To predict the probability of delayed fatality from thermal ra- The case study demonstrated obvious difference in the IRs be-
diation, a probit function Pr is employed with thermal dose criteria tween Approaches 1 and 2. Compared with the IR of Approach 3,
(Eisenberg et al., 1975). Approach 1 provided a significantly underestimated IR, whereas
Approach 2 gave a relatively comparable IR with an approximately
 4  4% deviation. Regarding the results of Approach 3 as the most ac-
Pr ¼ 14:9 þ 2:56ln Q 3 t (3) curate solution, Approach 2 provides a more accurate result than
Approach 1 for the target system.
where Q is the thermal radiation, and t is the exposure time. Fig. 6 shows the contribution of each leak category to the IR in
The probit function estimates the fatality rate of personnel each approach. In Approach 1, the large leak size contributes 95.8%
B. Chu, D. Chang / Journal of Natural Gas Science and Engineering 37 (2017) 234e247 245

Table 9
IR for crew members.

Approach Segment IR, per year Total IR, per year Ratio of IR to Approach 3

Approach 1 Segment 1~ 8 e Gas 3.341E-08 1.197E-04 0.54


Segment 1~ 8e Liquid 3.275E-06
Segment 9 1.855E-06
Segment 10 8.421E-05
Segment 11 7.184E-06
Approach 2 Segment 1~ 8 e Gas 5.622E-08 2.298E-04 1.04
Segment 1~ 8e Liquid 6.958E-06
Segment 9 3.795E-06
Segment 10 1.567E-04
Segment 11 1.322E-05
Approach 3 Segment 1~ 8 e Gas 4.707E-08 2.204E-04 1.00
Segment 1~ 8e Liquid 6.611E-06
Segment 9 3.663E-06
Segment 10 1.509E-04
Segment 11 1.263E-05

Fig. 6. Contribution of each leak scenario to IR.

of the IR, followed by the medium leak size. The largest percentage the graph. Those outliers correspond to diameters of the piping
of the IR in Approaches 2 and 3 is the full-bore leak size. The small segments of the system. Within the segment, the full-bore leak size
leak size has little effect on the personnel risks in all three ap- has a much higher frequency than other large sizes of leaks. As
proaches. This means that the IR is governed by the larger sizes of mentioned in Section 4, the reason for this is related to the rupture
leaks that accompany a large amount of hydrocarbon release rather of the piping segment, which is caused by the dropped object ac-
than the smaller sizes of leaks. cidents onto the installation. With high frequency, this accident
Fig. 7 shows the contribution of each segment to the IR in each may accompany a large amount of hydrocarbon release, causing
approach. Although the IR of Approach 1 is distinguished in catastrophic consequences.
magnitude from those of Approaches 2 and 3, the relative contri- Table 10 shows the IRs depending on the piping diameter of the
butions of each segment to the IR remain similar for all three ap- target system. The IRs of Approaches 1 and 2 are different regard-
proaches. Segments 10 and 11 containing high-pressure inventory less of the piping segment diameter. The full-bore leak size has a
contribute the leading parts of the IR. Segment 10 contributes the decisive effect on the results over the whole range of piping di-
largest percentage of the IR because it contains the highest pressure ameters. In Approach 1, the underestimated IR results from
of liquid inventory, which may result in a large amount of hydro- ignoring the full-bore leak accidents that led to the most cata-
carbon release. This segment also has a relatively high leak fre- strophic consequences. The full-bore leak size is the most critical
quency, as shown in Table 6. one in terms of fire risks to personnel and should be treated as an
Fig. 8 shows a distribution of leak frequencies for all segments of individual scenario.
the target system. The distribution exponentially decays with The results of the case study also relate to the fact that the full-
increasing hole diameter, but there are several outliers as shown in bore leak size has comparatively high frequency. If a full-bore hole
246 B. Chu, D. Chang / Journal of Natural Gas Science and Engineering 37 (2017) 234e247

Fig. 7. Contribution of each segment to IR.

Fig. 8. Leak frequency for all segments.

diameter had the lowest frequency, unlike in the real situation, the affects the estimated risks because it accompanies the largest
distribution of leak frequencies would exponentially decay without consequence with relatively high frequency. Omission of the full-
the peak points at the full-bore hole diameters. Under this condi- bore leak size in the QRA leads to underestimation of the fire
tion, the full-bore leak size would have little influence on the risk risks. This may cause misjudgment in the risk-informed decision-
estimation, and both approaches would give practically the same making process. Therefore, the full-bore leak size should be
results. considered as one of representative scenarios in the QRA.
The effect of the full-bore leak size has been demonstrated by a
5. Conclusion case study. These accidents feature a high leak rate, which has a
great effect on the fatality risk. Although it is not fully revealed for
The full-bore leak size is the critical scenario that significantly other cases, the results concerning the personnel risk are not
B. Chu, D. Chang / Journal of Natural Gas Science and Engineering 37 (2017) 234e247 247

Table 10
IRs depending on piping diameters.

Approach IR, per year (Ratio to Approach 3)

<25 mm 80 mm 100 mm 150 mm

Approach 1 2.264E-08 (0.72) 7.184E-06 (0.57) 8.606E-05 (0.56) 2.639E-05 (0.50)


Approach 2 3.739E-08 (1.19) 1.321E-05 (1.05) 1.605E-04 (1.04) 5.603E-05 (1.05)
Approach 3 3.133E-08 1.263E-05 1.545E-04 5.323E-05

expected to differ significantly from those of the current case study. 137e75. Virginia.
Falck, A., Bain, B., Rodsaetre, L.K., 2009. Leak Frequency Modeling of Offshore QRA
Nevertheless, it is worthwhile to conduct comparative studies for
Based on the Hydrocarbon Release Database. IChemE Symposium Series No.
other cases. 155, UK.
Regarding the structure-related risk, the effect of neglecting the Fire and Blast Information Group (FABIG), 2010. Fire Loading and Structural
full-bore leak category is not as clear as in the case of the personnel Response. Technical Note 11. UK.
Fire and Blast Information Group (FABIG), 2014. Design Guidance for Hydrocarbon
risk. This is because of the intrinsic characteristics of the leak or the Fires. Technical Note 13. UK.
tradeoff between the high heat dose rate and the short duration of HSE, 2007. Accident Statistics for Floating Offshore Units on the UK Continental
the full-bore leak. Its risk to the structure will be largely affected by Shelf 1980‒2005. Research Report R567. Norway.
HSE, 2006. Guidance on Risk Assessment for Offshore Installations. Offshore In-
the safety systems, including emergency isolation, blowdown, and formation Sheet No. 3/2006. UK.
especially passive fire protection, on the structure. The first two IMO, 2009a. Regulations for the Prevention of Air Pollution from Ships (Revised
safety systems determine the duration of the leak and thermal MARPOL Annex VI).
IMO, 2009b. Interim Guidelines on Safety for Natural Gas-fuelled Engine In-
dose, whereas the last mitigates the rate of temperature rise in the stallations in Ships. Resolution MSC.285(86). ANNEX 11.
structure. Krueger, J., Smith, D., 2003. A practical approach to fire hazard analysis for offshore
It is clear that more scenarios are considered, the better accurate structures. J. Hazard Mater 104, 107e122.
Lee, S., Seo, S., Chang, D., 2015. Fire risk comparison of fuel gas supply systems for
estimates of the risk of hydrocarbon leak accidents can be obtained. LNG fuelled ships. J. Nat. Gas. Sci. Eng. 27, 1788e1795.
However, considering all the possible scenarios is a very-time Lee, S., Seo, Y., Lee, J., Chang, D., 2016. Economic evaluation of pressurized LNG
consuming task. This study indicates that taking the full-bore ac- supply chain. J. Nat. Gas. Sci. Eng. 33, 405e418.
Li, J., Wu, B., Mao, G., 2015. Research on the performance and emission character-
cidents into additional account to the conventional simplified QRA
istics of the LNG-diesel marine engine. J. Nat. Gas. Sci. Eng. 27, 945e954.
can reduce the time and effort for estimating the leak-related risks Mannan, S., 2014. Fire. In: Lees' Process Safety Essentials: Hazard Identification,
without a significant loss of accuracy in the estimated risks. Assessment and Control. Elsevier, UK, ISBN 978-1-85617-776-4, pp. 201e256.
Mazzola, A., 2000. A probabilistic methodology for the assessment of safety from
dropped loads in offshore engineering. Risk Anl. 20, 327e337.
Acknowledgements Moon, K., Song, S., Ballesio, J., Fitzgerald, G., Knight, G., 2009. Fire risk assessment of
gas turbine propulsion system for LNG carriers. J. Loss Prev. Process Ind. 22,
This research was supported by a grant from the LNG Plant R&D 908e914.
OGP, 2010a. Risk Assessment Data Directory: Process Release Frequencies. Report
Center funded by the Ministry of Land, Transportation and Mari- No. 434 e1. UK.
time Affairs (MLTM) of the Korean government (15CPTA-A058125- OGP, 2010b. Risk Assessment Data Directory: Mechanical Lifting Failures. Report No.
08). 434 e8. UK.
Paik, J.K., Czujko, J., Kim, B.J., Seo, J.K., Ryu, H.S., Ha, Y.C., Janiszewski, P., Musial, B.,
2011. Quantitative assessment of hydrocarbon explosion and fire risks in
References offshore installations. Mar. Struc 24, 73e96.
Pitblado, R., Bain, B., Falck, A., Litland, K., Spitzenberger, C., 2011. Frequency data and
Ahmad, A., Hassan, S.A., Ripin, A., Ali, M.W., Haron, S., 2013. A risk-based method for modification factors used in QRA studies. J. Loss Prv. Process Ind. 24, 249e258.
determining passive fire protection adequacy. Fire Saf. J. 58, 160e169. Reniers, G.L.L., Ale, B.J.M., Dullaert, W., Fourbert, B., 2006. Decision support systems
Badri, N., Rad, A., Kareshki, H., Abdolhamidzadeh, B., Parvizsedghy, R., for major accident prevention in the chemical process industry: a developers'
Rashtchian, D., 2013. A risk-based decision making approach to determine survey. J. Loss Prv. Process Ind. 19, 604e620.
fireproofing requirements against jet fires. J. Loss Prv. Process Ind. 26, 771e781. Seo, S., Chu, B., Noh, Y., Jang, W., Lee, S., Seo, Y., Chang, D., 2016. An economic
Bris, R., Medonos, S., Wilkins, C., Zdrahala, A., 2014. Time-dependent risk modeling evaluation of operating expenditures for LNG fuel gas supply systems onboard
of accidental events and responses in process industries. Reliab. Eng. Syst. Safe ocean-going ships considering availability. Ship Offsh. Struct. 11, 213e223.
125, 54e66. Spouge, J., 1999. A Guide to Quantitative Risk Assessment for Offshore Installations.
Celnik, M., Bain, B., 2012. A Simple Methodology to Assess Environmental Risk from DNV Technica, UK, ISBN 978-82-14-04830-8.
Offshore Operations. In: IChemE Symposium Series No. 158, UK. Spouge, J., 2005. New generic leak frequencies for process equipment. Process Saf.
Cox, A.W., Lees, F.P., Ang, M.L., 1990. Classification of Hazardous Locations. IIGCHL, Prog. 24, 249e257.
IChemE. Spouge, J., 2006. Leak Frequency from the Hydrocarbon Release Database. In:
Dan, S., Lee, C.J., Park, J., Shin, D., Yoon, E.S., 2014. Quantitative risk analysis of fire IChemE Symposium Series No. 151, UK.
and explosion on the top-side LNG-liquefaction process of LNG-FPSO. Process Vinnem, J.E., 2007a. Analysis techniques. In: Offshore Risk Assessment: Principles,
Saf. Environ. 92, 430e441. Modeling and Applications of QRA Studies, second ed. Springer, New Jersey,
Devanney, J., 2011. The impact of the energy efficiency design index on very large ISBN 978-1-84628-716-9, pp. 161e232.
crude carrier design and CO2 emissions. Ship Offsh. Struct. 6, 355e368. Vinnem, J.E., 2007b. Risk picture-definition and characteristics. In: Offshore Risk
DNV, 2007. DNV LEAK Version 3.21. Assessment: Principles, Modeling and Applications of QRA Studies, second ed.
DNV, 2010a. DNV PHAST Version 6.7. Springer, New Jersey, ISBN 978-1-84628-716-9, pp. 15e50.
DNV, 2010b. Risk Assessment of Pipeline Protection. DNV-RP-F107. Norway. Wood, D.A., 2012. A review and outlook for the global LNG trade. J. Nat. Gas. Sci.
Economides, M.J., Wood, D.A., 2009. The state of natural gas. J. Nat. Gas. Sci. Eng. 1, Eng. 9, 16e27.
1e13. Yanlin, J., Jang, J.B., 2015. Probabilistic fire risk analysis and structural safety
Eisenberg, N.A., Lynch, C.J., Breeding, R.J., 1975. Vulnerability Model: a Simulation assessment of FPSO topside module. Ocean. Eng. 104, 725e737.
System for Assessing Damage Resulting from Marine Spills. NTIS Report CG-D-

Вам также может понравиться