CRONOGRAMA DE EJECUCION DE OBRA

PROYECTO: AMPLIACION DE REDES Y CONEXIONES DOMICILIARIAS DE AGUA Y ALCANTARILLADO EN LOS SECTORES B, C, y D de la URBANIZACION AGRICULTURA DE LA CIUDAD DE PUNO,

AVANCE FISICO FINANCIERO


% INCIDENCIA
PRIMER MES SEGUNDO MES TERCER MES TOTAL
CODIGO DESCRIPCION UND. COSTO S/. MES 1 MES2 FINANCIERO % FISICO FINANCIERO FINANCIERO % FISICO FINANCIERO
SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA 7 SEMANA 8 SEMANA 9 SEMANA 10 SEMANA 11 SEMANA 12 total
01 RED DE AGUA POTABLE 98092.91

01.01 TRABAJOS PRELIMINARES UN 2,467.80 2,467.80 2,467.80 100.00% 2467.8 100.00%

01.02 MOVIMIENTO DE TIERRAS UN 27,706.61 27,706.61 0.00% 27706.61 100.00%

01.03 SUMINISTRO DE TUBERIAS PVC UN 43,186.41 28,790.94 14,395.47 28,790.94 66.67% 14395.47 33.33% 43186.41 100.00%

01.04 SUMINISTRO DE ACCESORIOS UN 16,977.95 16,977.95 0.00 0.00% 16977.95 100.00% 16977.95 100.00%

01.05 INSTALACION DE ACCESORIOS PVC UN 934.96 934.96 0.00 0.00% 934.96 100.00% 934.96 100.00%

01.06 VARIOS 6,819.18 6,819.18 0.00 0.00% 6819.18 100.00% 6819.18 100.00%
01 RED DE ALCANTARILLADO 164,028.45

02.01 RED COLECTORA UN 93,676.85

02.01.01 TRABAJOS PRELIMINARES UN 5,232.22 5,232.22 5,232.22 100.00% 0.00 0.00% 5232.22 100.00%

02.01.02 MOVIMIENTO DE TIERRAS UN 35,619.34 35,619.34 35,619.34 100.00% 0.00 0.00% 35619.34 100.00%

02.01.03 SUMINISTRO DE TUBERIAS PVC UN 49,303.60 49,303.60 0.00 0.00% 49303.60 100.00% 49303.6 100.00%

02.01.04 PRUEBAS HIDRAULICAS UN 3,521.69 3,521.69 3,521.69 100.00% 0.00 0.00% 3521.69 100.00%

02.02 BUZONES RED COLECTORA UN 70,351.60 35,175.80 35,175.80 35,175.80 50.00% 35175.80 50.00% 70351.6 100.00%

03 CONEXIONES DOMICILIARIAS DE AGUA UN 31,781.40 31,781.40 0.00 0.00% 31781.40 100.00% 31781.4 100.00%

04 CONEXIONES DOMICILIARIAS DE ALCANTARILLADO UN 26,473.92 26,473.92 0.00 0.00% 26473.92 100.00% 26473.92 100.00%

05 CAPACITACIONES, EDUCACION SANITARIA UN 10,000.00 10,000.00 10000.00 100.00% 10000 100.00%


COSTO DIRECTO 330,376.68 110,807.79 191,862.28 138,514.40 41.93% 191,862.28 58.07% 330376.68 100.00%
GASTOS GENERALES 6.4% 20,688.50 8,673.90 12,014.60 8,673.90 41.93% 12,014.60 58.07%
GASTOS DE SUPERVISION 2.4% 7,789.44 3,265.82 4,523.62 3,265.82 41.93% 4,523.62 58.07%
GASTOS DE LIQUIDACION 1.13% 3,620.36 1,517.88 2,102.48 1,517.88 41.93% 2,102.48 58.07%
TOTAL PRESUPUESTO 362,474.98 124,265.39 210,502.98 151,971.99 41.93% 210,502.98 58.07% 362,474.98 100.00%