GC3 – The Health and Safety Practical Application

Candidate and course provider declarations:

For completion by the candidate:

I declare that the work submitted for this practical application assessment ie. the completed observation sheets
and the report to management, is my own work. I recognise that contravention of this statement constitutes
malpractice and may result in my being subject to the penalties set out in the NEBOSH Malpractice policy.

Name (Print) SUMITH M

Signature _______________________________

Date 15/10/2018

For completion by a course provider representative (eg internal practical assessor):

I declare that the work marked is identical to that received from the candidate. I recognise that contravention of
this statement constitutes malpractice and may result in my being subject to the penalties set out in the NEBOSH
Malpractice policy.

Name (Print) _______________________________

Signature _______________________________

Date _______________________________

For completion by the course provider’s internal practical assessor:

I declare that I have marked this work and am both qualified and approved by NEBOSH to do so. I recognise
that contravention of this statement constitutes malpractice and may result in my being subject to the penalties
set out in the NEBOSH Malpractice policy.

Name (Print) _______________________________

Signature _______________________________

Date _______________________________

NB: This declaration must be completed in full, submitted and retained with the
candidate’s script. If this declaration is not submitted the candidate’s result may be
declared void.

F:\final project.igc3.doc
GC3 – THE HEALTH AND Candidate’s observation
SAFETY PRACTICAL APPLICATION sheet

Sheet number 2 of 20

Student name SUMITH M Student number 00452075

Place inspected LIMS CONSTRUCTIONS Date of inspection 09/10/2018

Observations Control measures Timescale


Hazards and consequences Immediate and longer term actions

1.HAZARD:Observed vehicle moving  The excavation area should Immediately


around a excavated pit at high speed be barricaded
where no barricade in place.  There should proper warning
signage in area where Immediately
CONSEQUENCE: Vehicles may get excavation going on
trapped in excavated pit and people  There should be speed hump
and speed breaker to reduce Within 1 week
working in the excavation area may
the speed
get injured or even fatality occurs.  Traffic management system
should be in place to control Within 1 month
the vehicle movement
 Banks man should be there Within 3 week
for giving signal

Regularly
2.HAZARD:Observed people working  Frequent breaks and job
in hazardous area where cement dust rotation should be provided
and chemical particles present.  Health surveillance of
Within 1 month
workers exposed to hazard
area
CONSEQUENCE: Lung problem like
 Appropriate PPE should be Immediately
black lung disease through inhalation provided like RPE
and skin irritant caused by absorption.

3.HAZARD: Observed trailing cable of  Reposition of the cable wire Within 1 week
drilling machine on pathway where  Adequate lightning should be Immediately
workers are walking. provided in workplace
 Appropriate warning signage
can be given so people will Immediately
CONSEQUENCE: It can lead to trip have awareness about it.
hazard which can cause serious injury  Good housekeeping by
like head injury and bone fracture or providing suitable storage Within 1 month
even head hit against sharp edge can area for storage, clear
lead to fatality. obstacles from pathway.

F:\final project.igc3.doc
 The generator should be
repositioned from area where Within 1 week
4.HAZARD: Observed two person doing
workers are performing their
electrical work near power generator job
without any hearing protection.  Replace high noise generator Within 1 month
with a low noise one
CONSEQUENCE:The sound generated  Provide ear defender or ear
by the power generator could lead to plug to workers working in Immediately
hearing loss and non auditory disease noisy environment
like fatigue and stress.  Frequent break or job rotation
should be provided Regularly

 Make strict policy from Within 1 month


5.HAZARD: Observed a worker lifting
management side that a
cement bag which is approximately worker should not take more
50kg. than 20 kg weight
 Automate the process by Within 3 week
CONSEQUENCE: Which can lead to using machine like boom
MSD which causes back pain, neck crane
pain, and muscle cramp.  Frequent break or job rotation Regularly
given to worker
 Proper PPE should be
Immediately
provided like safety boots,
hard hat and RPE

 Routine inspection should be


6.HAZARD: Observed a man working Within 1 week
done by the supervisor
on a bench top grinder machine which  Adequate PPE to protect eye Immediately
is not protected by guard. and ear as they are exposed
to materials that come from
CONSEQUENCE: Which can lead to machine
entanglement as he is wearing loose  A fixed enclosing guard Within 3 week
clothes and with no adequate PPE. The should be placed around
ejected parts from machine can also motor and abrasive wheel
cause injury.  LEV should be installed to Within 1 month
control dust

 The management should Within 4 week


7.HAZARD: Observed a person who is provide proper platform like
carrying on welding operation in an scaffold
improper platform of approximately 5 m  Working at height should be Within 3 days
height . done with PTW
 Fall arrest equipment like
CONSEQUENCE: The person may fall harnesses and lanyard Immediately
which result in bone fracture or even should be provided
fatality, material may also fall causing  Safety net or soft landing Immediately
should be provided
damage of property.

F:\final project.igc3.doc
8.HAZARD: Observed stagnation of  Routine inspection should be
done in construction site to Within 1 week
water near to construction site where ensure prevention of stagnant
workers doing drilling operation. water
 Appoint pest control contractor
CONSEQUENCE: The workers may by management to prevent Within 1 month
get exposed by absorption or inhalation disease spread on work place
of harmful bacteria and virus may lead  Stagnant water should be
to disease like leptospirosis, hepatitis B drained through pump Immediately
etc

 Repair/Replace the electrical Within 1 week


9.HAZARD: Observed workers carrying
equipment
out maintenance work on faulty
 Double insulation should be
electrical equipment . provided Within 1 week
 ELCB must be installed Within 3 week
CONSEQUENCE: Electric shock and  Adequate PPE(gloves and
skin burn may occur to technicians due eye protection goggle should Immediately
to lack of adequate PPE . be provided)

10.HAZARD: Observed the flammable


chemical substance stored together  There should be separate Within 1 month
with other combustible materials near to storage area according to
workplace. their flammable property
 There should be proper
CONSEQUENCE: It can lead to fire and signage near to area of Immediately
explosion ,chemical exposure to skin flammable materials stored
may cause skin cancer ,irritating and  Training and supervision
lung cancer. should be given to workers Within 1 month
for the safe handling and
storage of flammable’s.

11.HAZARD: Observed a person using  Pre use inspection should


a ladder , the ladder is being placed on be done on ladder Immediately
a soft ground and he is climbing ladder  A stand by man should be
Regularly
with some object in hand without present near by
adequate PPE  Proper PPE to be provided Immediately
with hard hat , safety boots
CONSEQUENCE: As ladder is placed and aprons for safety
on soft ground the ladder may topple as  Training and supervision
a result person and the object will fall should be given to worker Within 1 month
which leads to injury, property damage to use ladder on workplace
or even fatality

F:\final project.igc3.doc
12.HAZARD: Had observed a driver  While reversing banks man Within 3 week
reversing fork lift truck without any with suitable clothing must
safety alarm on area where pedestrians give instruction to driver
are walking.  Proper maintenance should Within 1 week
be done by supervisor
CONSEQUENCE: Vehicle may hit the  Instead of reversing adapt Within 1 month
people or object which leads to damage around about system
of property ,injury to people or even  Vehicle free zone and
fatality. Within 3 week
Pedestrian free zone must
be marked separately

13.HAZARD: Observed person working  Confined space should be Within 2 days


in a confined space(tank) without any authorized by PTW
assistance.  Lightning should be
Immediately
adequate with a proper
CONSEQUENCE: Asphyxiation arising ventilation
from gas vapour or fume or lack of  Fire fighting equipment is to
oxygen, loss of consciousness as a Immediately
be placed near to confined
result of high air temperature space
 Atmospheric gas test must Within 2 week
be done before entering to
a confined space

 Always stack the material Regularly


14.HAZARD: Had Observed heavy
according to its weight that
materials used in construction were not
is the material should be
stacked sequentially and placed at top
stacked at bottom of rack.
of storage area.
 Clear the obstacles from
the pathway. Immediately

CONSEQUENCE: The materials may  Training and supervision to


Within 1 month
topple and workers may be seriously be given to worker for safe
injured and property damage occurs. handling and storage .

 Housekeeping should be
authorised by organisation Within 3 week
 Clean up the spill at
15.HAZARD: Observed workplace with appropriate interval
Immediately
oil spillage on floor were workers are  Proper lightning should be
doing machine maintenance activity provided Immediately
 Proper maintenance of
machine should be done in Within 1 week
CONSEQUENCE: Slip hazard which regular interval
lead to head injury, bruises.  Adequate PPE that is foot
wear with increased floor
resistance should be given Immediately
to workers

F:\final project.igc3.doc
 Select right tool for the right
Immediately
job

 Substandard tool must be


16.HAZARD: Observed a person using replaced with standard tool Within 2 week
cutting player to pound nail into wood.
 Proper PPE should be
CONSEQUENCE: Using wrong tool for provided like hand gloves Immediately
the job may hurt his hand or finger. The while performing job
person instead of hammer he used
cutting player which shows lack of  Training and supervision to Within 1 month
awareness . be given to worker on
selection of right tool for
the job

 Strict policy should be


Within 1 month
implemented by the
17.HAZARD: Observed a person who is management , that is drug
smoking near to a fuel storage area and smoking is strictly
prohibited during working
CONSEQUENCE: It may lead to fire hours
and explosion as the person may leave  Proper warning/signage is Immediately
cigarette near to storage area to be placed near to fuel
storage area
 An employer should be
Within 1 week
given responsibility to take
action against the people
who are misusing the
substance

 Minimum of 2 escape rote


18.HAZARD: Observed that there is Within 3 week
should be there in work
only1 emergency evacuation route at
place
the work site. The escape route and
 Fire marshals should be
assembly point were not marked
appointed by organisation Within 1 month
to take necessary action in
CONSEQUENCE: The workers may
time of emergency
get tensed in that situation due to lack
of unawareness ,this congested  Disabled workers should be
given special assistance in Immediately
situation may lead to injury or even
fatality time of emergency
 Lift or escalator should not Immediately
be used at emergency

F:\final project.igc3.doc
 Machine should be replace Within 4 week
with less vibrant one
 Training and supervision
19.HAZARD: Observed a worker using should be given to workers Within 3 week
drilling machine continuously for while using vibrating
prolong hours to bark the concrete equipment
 Frequent break and job
CONSEQUENCE: Due to transmission rotation should be given to Regularly
of vibration to body leads to hand arm workers
vibration. It can also tendons, muscle  Appropriate PPE should be
joints and nervous system provided like goggles,
Immediately
RPE, safety boot and hard
hat

 Gas cylinder to be
20.HAZARD: Observed gas cylinder is repositioned away from the Within 1 week
placed near to welding activity workplace
 Warning signage or symbol Immediately
CONSEQUENCE: Welding operation should be provided
spark hot slag may cause leakage of  Training and supervision
gas when regular area in contact with should be given to workers Within 1 month
cylinder valve, which lead to fire and during welding
explosion.

 Provision of LEV system Within 3 week


21.HAZARD: Observed a worker cutting
fitted to wood cutting
wood without any respiratory protection
machine
 Health surveillance adopted Within 1 month
CONSEQUENCE: Inhalation of wood
for workers
dust may lead to asthma and other
respiratory diseases  Provide PPE like mask or Immediately
RPE

 Cabin must be of adequate Within 1 month


22.HAZARD: Observed the watchman space
cabin having limited space with normal  Should provide chair with Within 2 week
chair proper back rest and foot
rest
CONSEQUENCE: It may lead to MSD  Should give training about
Within 1 month
due to poor working posture, symptoms the hazard present in
are back pain neck pain and slip disc workplace
 Should provide break and Regularly
job rotation

F:\final project.igc3.doc
 Train and supervise them
Within 1 month
23.HAZARD: Observed an young boy more than other workers
entering the work premises for implant  Provide a senior worker to Immediately
training, curious about the activities mentor them and keep a
going on in excavation area. close eye on their activities
 Do not expose them to Immediately
CONSEQUENCE: As boy is immature radiation
due to peer pressure he may risk his  Provide specific health
life. Within 3 week
surveillance

24.HAZARD: Observed a worker who is  A banks man with suitable


standing close to a suspended load of clothing should give proper Within 2 week
crane signalling to crane operator
 Training and supervision
CONSEQUENCE: The load may fall should be given to crane
due to lack of unawareness of crane Within 1 month
operator
operator which may lead to injury or  Proper warning/signage is
fatality. to be given to area were Immediately
loading and unloading take
place
25.HAZARD: Observed only one fire
extinguisher on the entire construction
site
 A fire extinguisher of
minimum 1 should be
CONSEQUENCE: It is not practicable Within 1 month
placed per 200sqm
in an emergency situation, were fire
 Fire extinguisher should be
may spread leads to loss of human life
placed at 30m distance Within a week
and damage to property.
travel
SAFE WORKING PRACTISE:  Appropriate fire extinguisher
for the appropriate hazard Within a week
1.Observed an employer in consultation should be in place
with worker regarding the working
procedure which will raise the worker
morale and enthusiasm. The feedback
from the worker would be helpful for the
management to improve the Health and Good Practise Continue
Safety of organisation

2.Observed welfare facilities such as


drinking water, sanitary conveniences,
resting and eating facilities, washing
facilities, accommodation for clothing
are provided according to number of
workforce present and maintained in
hygienic condition. Good Practise Continue

F:\final project.igc3.doc
UNIT GC3 – THE HEALTH AND Candidate report template
SAFETY PRACTICAL APPLICATION

Student number 00452075

Location LIMS CONSRUCTIONS, ERNAKULAM Date of review 07/01/2019

Introduction including overview of area inspected and activities taking place

The Health and Safety inspection was carried out by me on 9th October 2018
between 9:30 am to 11:30 am at area of work under LIMS constructions. The site is
approximately covered of 3 acre. The scope of the inspection is to highlight area of concern
of serious accidents and near misses in past month.

During time of inspection around 400 workers including engineer, supervisor


and other managerial staff were seen inside the work site. The several activities were
observed in construction site like excavation procedure, transportation of bricks and other
materials, carpentry works, machinery operation, workers at height, welding operation and
drilling operation. The workers are using equipments like hammer, chisel, electric disc cutter,
cement mixer and ladder as part of their work and lifting equipments like crane, forklift were
also observed.

Inspection has been conducted based on visual inspection, interviewing the


workforce and checking various records like investigation report of previous accident that
had happen in the workplace, whether the high risk activity are going on under PTW system,
SSOW document to overview the Health and Safety culture of the organisation.

F:\final project.igc3.doc
UNIT GC3 – THE HEALTH AND Candidate report template
SAFETY PRACTICAL APPLICATION

Student number 00452075

Location LIMS CONSTRUCTIONS Date of review 07/01/2019

Executive Summary

The main objective of this inspection was to identify major hazards that
result in incidents in a work site for past month. During inspection following job were being
undertaken excavation work , drilling operation, welding activity, carpentry works, concrete
work, transportation of materials, and other machinery operation.
The inspection clearly indicates that there are many hazards which are
not taken seriously by management.
1) VEHICLE HAZARD: The vehicles travelling close to excavation region at high speed.
Due to lack of barricade in place , lack of supervision, no proper warning signage the
vehicle may fall into excavation region causing serious injury or even fatality to
workers.
2) WORKING AT HEIGHT: A person carrying out welding operation at approximately
5m height in an improper platform, the person may fall which result in serious injury
like bone fracture or even fatality.
3) ELECTRICITY HAZARD: The workers carrying out maintenance activity on a faulty
electrical equipment, as a result electric shock or shock burn may occur to electrician
which leads to serious injuries or even fatality.
4) FLAMMABLE CHEMICALS HAZARD: The flammable chemical substance stored
with other combustible materials near to work place were machinery operation is
going on, as a result sudden explosion may occur which leads to fatality.
5) MACHINERY HAZARD: A man working on a bench top grinder with unprotected
guard, which result in serious injury like cuts, amputation, and entanglement.
As per ILO C167 Health and Safety in Construction Convention 1988 and
Indian Factory Act 1948, implementation of control measures to reduce accidents in
work place have been recommended. The management have the moral responsibility
to take care of their workers under SSOW, give training and supervision to protect
people from serious injury as far as reasonably practicable. The management should
comply with legal laws to ensure that they don’t suffer from financial loss and to show
a positive health and safety culture.

F:\final project.igc3.doc
UNIT GC3 – THE HEALTH AND Candidate report template
SAFETY PRACTICAL APPLICATION

Student number 00452075

Location LIMS CONSTRUCTIONS, ERNAKULAM Date of review 07/01/2019

Main findings of the inspection

1.OBSERVATION 1 (Vehicles moving around a excavation region at high speed):

Many vehicles are moving around an excavation area at high speed where no barricade in
place. The area is under a supervision of inspector, but he is not accessing the condition.
The workers were also busy in their on activity. The vehicles following an east route for
reaching the work site. The vehicles may be trapped in excavation region or there is a
possibility of skidding which result in serious injury or even fatality to people working in that
region. It may also lead to damage to underground buried service during the excavation
work causing explosion and flooding.

Legal Breaches are:


 Motor Vehicle Act 1988.
 Article 16, C167- Safety and Health in Construction Convention, 1988(No.167)
 Article 19, C167- Safety and Health in Construction Convention, 1988(No.167)
According to ILO convention 167 Article 16, all the vehicles should be maintained in good
working condition. Traffic management should be organised and controlled as to secure their
safe operation. Speed limit should be given by management in workplace.
According to ILO Convention 167 Article 19, there should be a proper barricade in place
where excavation is going on. The risk should be avoided to workers arising from possible
under ground dangers such as circulation of fluids or presence of gases, by undertaking
appropriate investigation to locate them.

If the management failed to comply with this law, then they will face financial loss, legal
issues, and moreover workers morale will be lost. The loss of worker morale which impacts
productivity and quality. The financial loss that occurs to company due to accident and
property damage. The legal issues is to be faced like enforcement action that result in fines
and imprisonment or even both. It is recommended that management should give training
and warn driver to reduce speed near excavation region. Arrange a speed breaker and
hump to reduce speed, appoint a banks man for giving proper signal to driver. Provide a
prohibition signal board for vehicle .

The estimated cost for providing a speed breaker and hump is approximately Rs 40000,
otherwise management will face financial loss of Rs 2000

F:\final project.igc3.doc
2.OBSERVATION 7 (A person working at height in a improper platform ):

The worker at approximately 5m height carrying out welding activity in an improper platform.
The person is not noticed by anyone as he is working alone. At the ground level concrete
works have been going on. The person may fall due to any adverse environmental
conditions like wind , health condition or due to unawareness. As a result he will be seriously
injured or even fatality occurs. The workers at ground level can also be effected by fall from
height.

Legal Breaches are:


 Indian Factory Act 1948, Article 32, section 4
 Article 18 ,C 167- Safety and Health in Construction Convention 1988(No.167)
According to Indian Factory Act , when any person have to work at height from where he is
likely to fall, provision shall be made, so far as reasonably practicable, by fencing or
otherwise, to ensure safety of person.
According to ILO Convention 167 Article 18, it is necessary to guard against danger and
preventive measures to be taken falling of person or object.

If the organisation failed to comply with the law, then they will face financial loss,
enforcement action. The workers trust towards management will be lost. The financial loss
due to fall from height or property damage. The legal issues that result in criminal offence,
civil claim, imprisonment and fine.

It is recommended that organisation should provide proper working platform like scaffold with
SWL, guard rails and toe board. The working at height should be undergone under PTW
system .The management should also provide adequate PPE like fall arrest equipment and
safety net to reduce consequence of fall.

The estimated cost for providing a scaffold as temporary working platform is Rs 60000,
otherwise the company will have a financial loss of Rs 300000.

F:\final project.igc3.doc
3.OBSERVATION 9 (Maintenance activity on faulty electrical equipment):

The workers carrying out maintenance activity on faulty electrical equipment which cause
electric shock and burns from contact with live parts and result in serious injury or even
fatality can occur when in contact with high voltage source. The workers were rushing to do
their job due to pressure from the supervisor. ELCB is not provided to incoming power
circuits to main electrical panel. The electrical equipment is not of double insulation.

The Legal Breaches are:


 Article 26, C167- Safety and Health in Construction Convention 1988(No.167)
 Indian Factory Act 1948 , Article 24 ,section 4

According to ILO Convention 167 Article 26, all the electrical equipment and installations
shall be constructed, installed, and maintained by a competent person, and so used to guard
against danger. The laying and maintenance of electrical cables and apparatus on
construction site to be governed by standard applied at national level.
In the Indian Factory Act 1948, Article 24 states that in every construction site there should
be suitable devices for cutting of power in case of emergencies.

If the management failed to comply with the law, then they will face economic loss, legal
issues and moreover there will be high staff turnover. So it is recommended that
management should install ELCB and the electrical cable wire should be of double
insulation. The management should give training while accessing electrical equipment.
Proper PPE should be given to workers like gloves, goggles while working with electrical
equipment.

The estimated cost for providing ELCB is Rs15000, if management failed to provide then
they will have a financial loss of Rs 200000.

F:\final project.igc3.doc
4.OBSERVATION 10 (Flammable chemical substance stored near to workplace):

The flammable chemical substance stored together with other combustible materials near to
which the workers are doing machinery operation. Also observed lack of ventilation in the
room where these flammables are stored. The storage room was not given any signage or
warning. The flammable substance of different types are stored in single room. The room is
not provided with fire extinguisher near to it. As a result sudden explosion may occur or
chemical exposure to skin can cause skin cancer and lung cancer.

The Legal Breaches are:


 Article 2, C170- Chemical Convention,1990(No.170)
 Article 27,C167- Safety and Health in Construction Convention,1988(No.167)
 The Indian Factory Act 1948, Article 37,section 4
According to Article 2, C170 states the how the flammable chemicals may get exposed
through storage and handling, transportation and disposal of chemicals and their control
measures.
According to Article 27, C167 states that the flammable chemicals which are explosive in
nature shall not be stored, transported, or handled except under condition prescribed by
national laws or regulation.
According to Indian Factory Act Article37, states exclusion or effective enclosure of all
possible sources of ignition.

If the management violates the law then they will face financial loss as a result of fire and
explosion. The worker will not feel safe, and they move to other organisations. The company
also face enforcement action that will result in fines, imprisonment or both.

It is recommended that hazardous flammable chemical substances not to be stored at high


temperature. It should not be stored with other materials. Always the storage area should be
with proper ventilation. There should be separate store room to keep different flammable
chemical substance. These are the ways in which the management can improve standards
of H and S.

The estimated cost for the store room with proper ventilation to separate different
flammables is 150000, if not provided by the company can lead to financial loss of Rs
500000.

F:\final project.igc3.doc
5.OBSERVATION 6 (Bench top grinder with unprotected guard):

A man is working on a Bench top grinder, which is used to grind down sharp edges and
remove burrs from processed metals. Beside him different operations are going on. The
person was wearing loose clothe with inadequate PPE. The Bench top grinder is not
protected by guard, which can lead to contact with rotating wheel, drawing into the trap
between tool rest and wheel, also parts may get ejected from machine. As the person is
wearing loose clothes entanglement may occur which result in serious injury like cuts
amputation may occur. Also non mechanical hazard like noise, ergonomics, vibration,
electricity may occur.

The Legal Breaches are:


 Article 17,C167 – Safety and Health in Construction Convention,1988(No.167)
 The Indian Factory Act 1948, Article 21, section 4
According to Article 17,C167 states that the machinery or equipment should be maintained
in good working condition, to be operated by workers who had undergone training.
According to Indian Factory Act 1948, Article 21, states every dangerous part of machine
shall be securely fenced by safe guard.

If the management failed to comply with the law , severe actions would be faced like legal
issues that is enforcement notice that result in civil claim, criminal offence, fines and
imprisonment or eve both. The financial loss like compensation pay out to worker,
hospitalisation cost, first aid treatment arises. The loss of staff morale as they realise that
employer is not providing safe place to work or SSOW.

It is recommended that the company should provide fixed enclosing guards around motor
and abrasive wheel. Also LEV should be installed to control dust. Routine maintenance
should be be done to ensure safe working condition, also ensure that competent person
should be given the right to work

The estimated cost for providing fixed guard and LEV is approximately 40000, if
management failed to provide they will economic loss of 200000.

F:\final project.igc3.doc
UNIT GC3 – THE HEALTH AND Candidate report template
SAFETY PRACTICAL APPLICATION

Student number 00452075

Location LIMS CONSTRUCTIONS ,ERNAKULAM Date of review 07/01/2019

Conclusions:

I sincerely thank the management of LIMS CONSTRUCTIONS for giving me an opportunity


to inspect the ongoing construction site. The inspection was part of my project and scope of
the project is to find out major hazard that lead to fatality for past month. During inspection
several good practises were observed that is welfare facilities like sanitary convenience ,
wash room, accommodation for clothing, place to eat and rest were in good hygiene
condition. An employer consulting with the worker regarding the work procedure also helps
the organisation to improve its standard on health and safety.

The activities on the construction site were of more high risk factor and some low risk factor.
The company is violating several safety laws and regulations that are stated in The Indian
Factory Act ,1948 and ILO- C167-Safety and Health in Construction Convention,1988.

The major findings that has been observed in the construction site were:
 The vehicles moving at high speed close to excavation area which is not barricaded.
The vehicle may get trapped in the area or due to over speed the vehicle may skid
and workers who are working in that excavation region will be seriously injured or
even fatality occurs. It may also cause damage to buried service cable resulting in
explosion or flooding.

The control measures that could be taken by management to control this incidence is
first of all the excavated are should be barricaded, drivers should undergo a training
session, speed breaker and hump should be installed by management to reduce over
speed, speed limit to be set by organisation, proper warning signage should be there
near to high risk work.

 A person carrying out welding activity at approximately 5m height in an improper


platform. As a result person may fall or object may fall resulting in bone fracture or
even fatality.

F:\final project.igc3.doc
The control measures to be taken are the worker should be provided a scaffold as
temporary working platform with SWL. The work at height should be done with PTW.
The management should provide adequate PPE like fall arrest equipment and safety
net to reduce consequence of fall.

 The workers carrying out maintenance activity on faulty electrical equipment. The
workers may get electric shock from high voltage source.

ELCB must be installed and double insulation to be provided, Also competent person
should be allowed to work, IITS to be provided to workers who were newly appointed
are the control measures to be taken by management.

 The flammable chemical substances stored together with other combustible materials
near to work place. As a result explosion may occur or even chemical exposure to
skin may lead to skin cancer.

There should be separate storage area for flammable materials and to be far away
from work place. Proper warning signage to be placed near to flammables. There
should be proper lighting and ventilation in storage area. Only authorised person
should have right to go to storage place. These are measures to be taken by the
management.

 A man is working on a Bench top grinder with unprotected guard, which can lead to
cuts, amputation, and entanglement.

The control measure to be by management is to provide a fixed guard between motor


and abrasive wheel, LEV to be installed to collect dust, provide adequate PPE like
goggles , gloves, aprons, and hard hat. Proper training and supervision should be
given to workers doing machinery operation.

The five critical issues may lead the organisation to suffer from decreasing of
production rate, high insurance premium, uninsured cost and reduce morale of
workers. So by implementing corrective measures stated in recommendation table it
will help the company to reduce accidents in work site. It also help to increase the
productivity and reduce staff turnover. The recommendation to be taken within 4
months time period. It is also advised to review the report in upcoming HSE
management meeting, so that we can ensure a positive health and safety culture in
the organisation.

F:\final project.igc3.doc
UNIT GC3 – THE HEALTH AND Candidate report template
SAFETY PRACTICAL APPLICATION

Student number 00452075

Location LIMS CONSTRUCTIONS Date of review 07/01/2019

Recommendations – include as a table in the following format:

Recommendation Likely resource implications Priority Target


date

VEHICLE HAZARD: Immediate action:


 Speed breaker and hump should  The excavation region
be provided to avoid over speed to be barricade with HIGH 11/10/2018
 The excavation area should be proper warning board
barricaded with proper warning and signage.
signage so that vehicles and Estimated cost is Rs:5000
workers will be have an awareness Long term action:
about the hazard.  Install speed breaker HIGH 21/10/2018
and hump.
 Provide IITS by a
competent person. LOW 2/11/2018
Estimated cost is Rs: 40000

F:\final project.igc3.doc
WORKING AT HEIGHT: Immediate action:
 As the worker is doing welding  Proper PPE should be
activity in an improper platform, a provided like fall arrest HIGH 13/10/2018
scaffold with SWL should be equipment and safety
provided by management. nets or safety landings
 Adequate PPE should be provided to reduce consequence
to reduce consequence of fall. of fall.
 PTW should be authorised by  PTW should be issued
management. by organisation. HIGH 14/10/2018
Estimated cost is Rs 30000
Long term action:
 Scaffold should be
erected HIGH 3/11/2018
 IITS should be given to
workers by a competent LOW 1/11/2018
person.
Estimated cost is Rs 70000

ELECTRICITY HAZARD: Immediate action:


 ELCB and electrical cable wire with  Adequate PPE like HIGH 11/10/2018
double insulation to be provided. gloves should be
 Proper training should be given to provided
workers by a competent person.  Double insulation wire
should be provided MEDIUM 13/10/2018
 Adequate supervision
should be done. LOW 10/10/2018
Estimated cost is Rs 20000
Long term action:
 ELCB must be installed
by management. HIGH 4/11/2018
 Proper training should
be given to workers. MEDIUM 6/11/2018
Estimated cost is Rs 30000

F:\final project.igc3.doc
FLAMMABLE CHEMICAL HAZARD: Immediate action:
 Separate storage area for  Warning signage to be
flammable chemical substance. placed near flammable MEDIUM 11/10/2018
 Warning signs to be placed near chemical substance.
storage area.  Ventilation and lightning
 Proper ventilation and lightning to be provided in HIGH 14/10/2018
should be provided. storage area.
Estimated cost is Rs 25000
Long term action:
 Storage area should be
placed away from work HIGH 10/11/2018
place for different type
of flammables.
Estimated cost is Rs 80000.

MACHINERY HAZARD:
 Fixed guard should be installed by Immediate action:
the management.  PPE should be provided
 LEV to be provided for collecting like goggles, hard hat HIGH 12/10/2018
dust from machinery. and aprons.
 Adequate PPE and IITS to be Estimated cost is Rs 20000
provided by management Long term action:
 A fixed guard to be
placed b/w motor and HIGH 25/10/2018
abrasive wheel
 LEV to be installed by
management MEDIUM 29/10/2018
 IITS should be provided
by management MEDIUM 6/11/2018
Estimated cost is Rs 70000

F:\final project.igc3.doc