Вы находитесь на странице: 1из 28

Ras Tanura Integrated Project (RTIP) Document No: RT-6-1CS

KBR Project No. A554 Revision: 3


MATERIAL AND EQUIPMENT PROTECTION
AND PRESERVATION PLAN Issue Purpose: IFD

SUMMARY OF DOCUMENT REVISIONS


Rev. Date Section
No. Revised Revised Revision Description
0 26 Jun 08 New This is a new RTIP Specification

1 25 Jan 10 General Authorization for revision covered by A554-RFV-PRG-336. This


applies to EPC.
1 Added additional details to scope
1.1.1 Clarified responsibilities
1.1.3 Added purchaser/ buyer responsibilities
1.3 Added contractors/ purchasers plan
2.1 Added scope to cover shipping and transport
2.2.9 Added requirements for appropriate utilities to support protection
3.2 Added additional document
ATTACHMENT Added RTIP JMP Reliability & Maintenance Equipment and Material
1 Protection Plan Work Process (Documentum No: RT-6-1CS Rev. 1
Attachment 1)

ATTACHMENT Added Equipment and Material Protection Plan Work Process


2 spread sheet (Documentum No.: RT-6-1CS Rev. 1, Attachment 2)

2 26 July 10 General Authorization for revision covered by A554-RFV-PRG-567


Table of Deleted Attachment 1 and 2
Contents
Table 1 Added Note 2
2.14 Revise source for procedure
2.3.2 Deleted ref. to IPMS module
2.5.1 Deleted ref. to SMC1106
2.7.4.a/b Deleted ref. to IPMS module
3.1 Revised source for manual
3.2 Revised source for manual
Revised reference to Equipment and Material Protection Plan Work
Process
Added reference to spread sheet

This applies to EPC

3 22 Oct 10 1 Added note that this spec should be used in conjunction with
Schedules G and Q.

Table 1, 2.5 Added note to maintain vapour seals

Contains Confidential Information of both Dow and Saudi Aramco


Page 2 of 28
Ras Tanura Integrated Project (RTIP) Document No: RT-6-1CS
KBR Project No. A554 Revision: 3
MATERIAL AND EQUIPMENT PROTECTION
AND PRESERVATION PLAN Issue Purpose: IFD

SUMMARY OF DOCUMENT REVISIONS


Rev. Date Section
No. Revised Revised Revision Description
Table 1, 2.12.4 Added note the HVAC equipment should be hooked – up and
operated in analyser shelters before the shelters are installed.

Table 1, 2.19.1 Added note that piping should be placed on cribs when stored in the
field.
Table 1,2.19.15 Added cautionary note about nuts and bolts

Appendix 1, 2 Changed meaning of IH to “HVAC Controlled”

Contains Confidential Information of both Dow and Saudi Aramco


Page 3 of 28
Ras Tanura Integrated Project (RTIP) Document No: RT-6-1CS
KBR Project No. A554 Revision: 3
MATERIAL AND EQUIPMENT PROTECTION
AND PRESERVATION PLAN Issue Purpose: IFD

TABLE OF CONTENTS

Section Title Page No.


1. GENERAL..............................................................................................................4
1.1 Responsibilities ......................................................................................................4
1.2 Statutory Requirements .........................................................................................5
1.3 Industry Standards .................................................................................................5
2. EQUIPMENT PROTECTION DURING CONSTRUCTION AT JOBSITE ..............5
2.1 Scope .....................................................................................................................5
2.2 General Requirements ...........................................................................................5
2.3 Documentation .......................................................................................................6
2.4 Use and Application of Rust Preventives, Preservatives and Desiccants..............7
2.5 Examination of Equipment on Arrival at Jobsite.....................................................8
2.6 Machinery...............................................................................................................9
2.7 Motors and Generators ........................................................................................11
2.8 Transformers........................................................................................................12
2.9 Switchgear, Starters and Control Equipment .......................................................13
2.10 Cables ..................................................................................................................14
2.11 Storage Batteries .................................................................................................14
2.12 Instruments ..........................................................................................................14
2.13 Valves ..................................................................................................................15
2.14 Welding Consumables .........................................................................................16
2.15 Stainless Steel .....................................................................................................16
2.16 Flange Facings.....................................................................................................16
2.17 Vessels and Exchangers......................................................................................17
2.18 Computers, Telecommunications and Associated Equipment.............................18
2.19 Piping ...................................................................................................................18
3. QUALITY CONTROL PROCEDURES ................................................................22
3.1 General ................................................................................................................22
3.2 Relevant Documents............................................................................................22
4. MATERIAL CONTROL PROCEDURES .............................................................22

APPENDIX 1: ACTIVITY NUMBER CODES AND STORAGE LETTER CODES ..............23


APPENDIX 2: EQUIPMENT PRESERVATION AND MAINTENANCE LOG SUMMARY ..24
APPENDIX 3: CONSTRUCTION ENGINEERING MAINTENANCE LOG SHEETS (3
SHEETS)............................................................................................... 25-27

R2

R2

Contains Confidential Information of both Dow and Saudi Aramco


Page 4 of 28
Ras Tanura Integrated Project (RTIP) Document No: RT-6-1CS
KBR Project No. A554 Revision: 3
MATERIAL AND EQUIPMENT PROTECTION
AND PRESERVATION PLAN Issue Purpose: IFD

1. GENERAL SCOPE

R3 The intent of this document is to outline the minimum requirement in developing the
specific RTIP material and equipment protection/preservation plan by the Contractor
and/or the Purchaser, and should be used in conjunction with Schedule G and Q requirements.
This includes the appropriate coordination with the principles such as the Owner’s team
and the supplier/vendor to support the applicable warranty and life expectancy.
The Plan (s) must cover Equipment and Material Protection from the time the item is
being prepared for shipping at the source (by the Manufacturer or at Vendor Shop),
through shipping, site delivery/storage, and installation and/or the warehousing. The
Contractor and/or the Purchaser shall remain responsible for the proper execution of the
Equipment and Material Protection and Preservation Plan (Plan) until the Owner’s formal
written acceptance of the installation and/or turnover of the facility. The Plan shall
conform to Engineering Design and manufacturer’s requirements for storage and
preservation.

1.1 Responsibilities

1.1.1 RTIP Site Material Control Manager may oversee implementation of the Material
and Equipment Protection and Preservation Plan, including the roles and responsibilities
as indicated in the Equipment and Materials Protection Plan Work Process, employing
the appropriate equipment, piping, and bulk materials maintenance and preservation
procedures defined in this Plan.

1.1.2 Procurement / buyers are responsible for conveying information to suppliers


relative to site climatic and other conditions affecting equipment storage and preservation
and ensuring that suppliers respond with appropriate preservation requirements.

1.1.3 Purchaser / buyer such as the contractor is responsible for the proper development
and execution of the Plan to support and provide the appropriate information for the Site
Material Handling/Storage as well as the Owner’s Maintenance and Warehousing
approach such as the data management software. The data management software shall
be able to deliver the data in a format for upload into the Owner’s Equipment
Maintenance System and Asset Management System.

1.1.4 Statutory Requirements: The Purchaser / Supplier shall mutually determine and
properly communicate the measures that must be taken to comply with all applicable
governmental codes, regulations, ordinances and rules which shall be applied as a first
precedence.

1.1.5 Purchaser’s equipment and/or material Work Group Leader (WGL) as the
Engineer of the record is responsible for requesting and reviewing equipment storage,
maintenance, and protection requirements provided by equipment suppliers. The
Equipment Preservation and Maintenance Log Summary (Appendix 2) or Supplier's
equivalent log shall be used by each WGL to document agreed requirements.

1.1.6 To avoid an unreasonable deferment of the requirements to the downstream


principles and shifting of the cost/responsibilities, the Purchaser must economically

Contains Confidential Information of both Dow and Saudi Aramco


Page 5 of 28
Ras Tanura Integrated Project (RTIP) Document No: RT-6-1CS
KBR Project No. A554 Revision: 3
MATERIAL AND EQUIPMENT PROTECTION
AND PRESERVATION PLAN Issue Purpose: IFD

and/or technically justify the deferment of the engineering controls and shall obtain the
Owner’s concurrence. The Owner’s review and/or comment may also flag this upfront
design consideration and must be addressed appropriately.

1.1.7 Purchaser Site QA/QC Manager is responsible for reviewing the maintenance and
preservation procedures and performing the appropriate surveillances during the
implementation of this Material and Equipment Protection and Preservation Plan.

1.2 Statutory Requirements

The Purchaser and Supplier shall mutually determine the measures that must be taken to
comply with all applicable governmental codes, regulations, ordinances and rules which
shall be applied as the first precedence.

1.3 Industry Standards

The Contractor / Purchaser’s Plan must list the appropriate industry standards which may
apply to the equipment and material. As an example, the following document is
referenced herein and forms part of the standards. Current edition of the industry
standard shall apply unless otherwise indicated.

AMERICAN PETROLEUM INSTITUTE (API)


API 686, Recommended Practices for Machinery Installation and Installation Design,
Chapter 3 – Jobsite Receiving and Protection

2. EQUIPMENT PROTECTION DURING CONSTRUCTION AT JOBSITE

2.1 Scope

This section outlines the technical requirements for protection of equipment and
associated materials at the jobsite during the construction phase of the project. Jobsite
is defined as the temporary warehouse facilities (heated and unheated), lay down yard or
outside sheltered storage as well as the permanent equipment installation location.
The Contractor / Purchaser must include the other elements of the equipment and
material protection requirements in the Plan such as the requirements during the
shipping/transport.

2.2 General Requirements

2.2.1 These procedures are generally aligned with API 686 recommended practices, if
applicable, for jobsite protection and preservation for equipment, piping, and bulk
materials.

2.2.2 All maintenance/preservation activities have been abbreviated by means of a code


number that is used with Equipment Maintenance Log Sheets and Equipment
Preservation and Maintenance Log Summary. These codes may be found in
Appendix 1.

Contains Confidential Information of both Dow and Saudi Aramco


Page 6 of 28
Ras Tanura Integrated Project (RTIP) Document No: RT-6-1CS
KBR Project No. A554 Revision: 3
MATERIAL AND EQUIPMENT PROTECTION
AND PRESERVATION PLAN Issue Purpose: IFD

2.2.3 Additional or special protection procedures will be utilized on an individual item


basis as deemed necessary jointly by Purchaser and the Client. Purchaser’s Site
Material Control Manager will notify Purchaser Engineering and the Client when
packaged equipment or complex equipment arrives on site. Purchaser Engineering and
the Client will jointly agree in advance on any special preservation requirements to be
followed for the equipment.

2.2.4 Equipment manufacturers recommended storage and preservation procedures


shall be reviewed by Engineering WGL’s and incorporated into this plan as they are
received from Suppliers. In general, equipment manufacturer recommendations take
precedence over specific preservation requirements contained in this plan. Any
deviations from equipment manufacturer’s recommendations must be approved by
Purchaser Site Material Control Manager and agreed in writing with the Supplier to
ensure equipment warranties are not invalidated.

2.2.5 Storage and lay down areas shall be designed so that they are well drained. All
bulks stored outside shall be elevated above the ground and above the maximum water
run-off.

2.2.6 Protective covers and tarps are used to prevent contamination from blowing sand
and debris and shall be used in a manner that allows free air circulation around the bulks.
Covers or tarps shall not be sealed against the ground. Ventilation is needed to allow
moisture evaporation. Plastic tarps shall be used when appropriate with care to avoid
trapping moisture within the tarp and thus causing corrosion. This is especially sensitive
with rotating equipment. Woven or fabric moisture resistant tarps with impregnated vapor
corrosion inhibitors (VCI) are preferred.
2.2.7 Fibrous and other materials that can absorb moisture (e.g., pressed board,
cardboard, softwood, etc.) shall not be used as supports, spacers, separators, or covers.
Fibrous materials used in shipping crates and containers shall be removed and replaced
with suitable materials or the materials removed and suitably stored.

2.2.8 Materials shall not be stored outdoors in non-drainable positions. Components,


such as ells and bends, shall be stored in a horizontal position so that moisture and
condensation does not collect on the inside.

2.2.9 Arrangement for appropriate utilities must be in place for safe keeping of the
equipment such as the purge gas, heater power, etc.

2.2.10 Material identification markings shall be maintained.

2.2.11 All damaged and/or corroded materials shall be stored separately from
undamaged materials until corrective action is applied.

2.3 Documentation

2.3.1 Basic preservation and storage location requirements for individual equipment
items are outlined in the Equipment Preservation and Maintenance Log Summary
(Appendix 2). Preservation and storage location of auxiliary equipment and

Contains Confidential Information of both Dow and Saudi Aramco


Page 7 of 28
Ras Tanura Integrated Project (RTIP) Document No: RT-6-1CS
KBR Project No. A554 Revision: 3
MATERIAL AND EQUIPMENT PROTECTION
AND PRESERVATION PLAN Issue Purpose: IFD

instrumentation that is shipped loose shall follow the requirements contained in this plan,
depending upon how the auxiliaries are categorized.

R2 2.3.2 Evidence of the implementation of the Equipment Protection Plan shall be


documented using the “Construction Engineering Maintenance Log Sheets"
(Appendix 3). A log sheet shall be completed for each equipment item or package
requiring preservation and used to record preservation activities as they occur.

2.3.3 For each equipment item, the type of preservation performed, the date each
activity was performed and the individual performing the preservation activity shall be
recorded. The original documentation will be maintained by the Purchaser Site Material
Control Manager and ultimately turned over to the Client with the project quality records.

2.3.4 Special storage and preventive maintenance activities as required for maintaining
extended warranties, if required, shall be included on the Construction Engineering
Maintenance Log Sheet (Appendix 3). The items for which this is required are identified
in the notes column of the Equipment Preservation and Maintenance Log Summary
(Appendix 2).

2.4 Use and Application of Rust Preventives, Preservatives, and Desiccants

2.4.1 All interior and exterior surfaces shall be cleaned and dried as required before any
rust preventive materials are applied.

2.4.2 For interior surfaces of bearing housings, the preservative of choice is provided by
Cortec, who provides a vapor phase inhibitor product (VPI) with characteristics that will
maintain a lubricated and protected surface during cold weather conditions and for
extended periods. Most suppliers will agree to furnish their equipment with the
appropriate VPI product prior to leaving the shop if specified in the Purchase Order.

2.4.3 Mineral spirits such as Varsol or any Stoddard solvent, as applicable, shall be used
for cleaning exterior surfaces prior to application of any rust preventive compounds.
Kerosene or gasoline shall not be used as cleaning agents.

2.4.4 API Type D asphaltic preservatives should be avoided, as most asphaltic films are
very difficult to remove. Non-asphaltic inhibitors such as Cortec 368 provide excellent
long term storage protection.

2.4.5 The rust preventives to be used are defined below, based upon required usage.
Equivalent rust preventatives may be used with prior approval.

Contains Confidential Information of both Dow and Saudi Aramco


Page 8 of 28
Ras Tanura Integrated Project (RTIP) Document No: RT-6-1CS
KBR Project No. A554 Revision: 3
MATERIAL AND EQUIPMENT PROTECTION
AND PRESERVATION PLAN Issue Purpose: IFD

TABLE I: SAMPLE RUST PREVENTATIVES


Preservative Activity (2) Application Typical
Type Products (3)
Use as an additive to lubricants for protection of bearings
Lube Compatible #8 & #14 and internal surfaces. Compatible with mineral oil Cortec VCI-326
lubricants.
Use on exterior unpainted iron and carbon steel surfaces
Exterior #5 & #6 Cortec VCI-368
exposed to the weather.
Use on exterior unpainted iron and carbon steel surfaces Cortec VCI-368,
Storage #5 & #6 stored under a roof and sheltered from direct effects of VCI-369 and/or
the weather. Cor-Pak Film
Use as an additive to hydraulic systems for protecting
Hydraulic #Special ferrous and non-ferrous metals from corrosion due to Cortec VCI-326
moisture.
Use for filling seal chambers of double mechanical seals Consult machinery
Mechanical Seal #2
to prevent contamination of internal seal components. engineer
Consult machinery
Grease #12 Refer to the machinery lubrication schedule
engineer
Use in cast iron, carbon steel and aluminum equipment
casings were accumulation of moisture could cause
corrosion.
Desiccant #15 DRI-BOX (1)
• Not to be used with Vapor Phase Inhibitors.
• Not be used to protect stainless steel or components
with rubber parts.
Weldable #6 For use on ferrous weld bevels Deoxaluminite
Use on machined ferrous surfaces such as flange gasket
Petroleum Soluble #5 & #6 Cortec VCI-368
seating surfaces
Use to protect internal surfaces of equipment from
Vapor Phase
#15 corrosion. Cortec 307
Inhibitor
• Not to be used with desiccants.
Use to protect threaded ferrous and alloy surfaces, such
Anti-Seize #6 Jet-Lube 550
as valve stems, from corrosion.
Wax Cloth Tape #19 Use to protect exposed surfaces of shafts Denso Densyl Tape
Cortec VpCI 426
Rust Remover #20 Use to remove corrosion from carbon and stainless steel
and VpCI 426 Gel

Note 1 DRI-BOX is a transparent regeneratable dehydrating cartridge with color


indicating silica gel that turns from blue to pink when it can no longer pick-up
moisture
R2 Note 2 See Appendix 1
R2 Note 3 Products must be reviewed for process compatibility. Final product list to be
approved by Owner prior to shipment of equipment.

2.5 Examination of Equipment on Arrival at Jobsite

R3 2.5.1 The following receiving inspection activities relate to preservation.

Contains Confidential Information of both Dow and Saudi Aramco


Page 9 of 28
Ras Tanura Integrated Project (RTIP) Document No: RT-6-1CS
KBR Project No. A554 Revision: 3
MATERIAL AND EQUIPMENT PROTECTION
AND PRESERVATION PLAN Issue Purpose: IFD

2.5.2 All equipment shipped with protective covers or plugs over openings, and applied
rust preventive coatings on exterior machined and threaded surfaces, shall be examined
on arrival at the jobsite:

2.5.3 After Supplier approval, the covers with their full-face gaskets will be removed,
inspected, and reinstalled.

a. Protective covers, plugs, and coatings, shall be renewed if not intact (Appendix
1Activity #3, #4). Length of time that covers and plugs are removed shall be kept to
a minimum.

b. If water or dirt has entered the equipment through damaged or improperly secured
covers and plugs, the equipment shall be cleaned and preserved before covers,
plugs, and coatings are restored (Activity #10).

c. If vapor phase inhibitors or desiccants are used to protect the interiors of mechanical
equipment, the seals shall be examined when the equipment is received at the
jobsite. Any damaged vapor seals shall be repaired or replaced, and the inhibitor or
desiccant renewed if necessary (Activity #15).

d. Vapor seals shall be protected and maintained until the equipment is serviced for
startup. Any damage to seals prior to such time shall be immediately repaired
(Activity #15).

e. Equipment that is shipped in export crating and designated for outdoor covered (OC)
storage may remain in the original crating for a maximum period of 4 months unless
otherwise specified by the manufacturer. Following the 4 month period, preventive
maintenance shall commence.

2.6 Machinery

a. The shafts of all mechanical equipment shall be rotated as specified in the


Equipment Preservation and Maintenance Log Summary (Appendix 1) (Activity #1).

b. After installation at their final service location, rotating equipment such as turbines
and expanders, fans, gear unit cases, agitators, pumps, blowers, and centrifugal
compressors shall be protected as follows:

1. Continue to maintain all internal surfaces of bearing housings and gear unit
cases using the specified (Manufacturer/Brand) preservative. Vent and drain
connections shall be plugged, capped, or blinded, as applicable, using steel
fittings. Blinds shall be gasketed. The preservative oil level shall be checked at
bi-weekly intervals and topped up to manufacturer’s specification
(Activity #8, #11, #14).

2. Clean shaft couplings and exposed machined surfaces and coat them with
EXTERIOR preservative (Activity #5, #6).

Contains Confidential Information of both Dow and Saudi Aramco


Page 10 of 28
Ras Tanura Integrated Project (RTIP) Document No: RT-6-1CS
KBR Project No. A554 Revision: 3
MATERIAL AND EQUIPMENT PROTECTION
AND PRESERVATION PLAN Issue Purpose: IFD

3. Cover the suction and discharge nozzles of centrifugal compressors, pumps, and
blowers with leak tight metal closures (or blinds), which shall remain in place until
hydrostatic testing, and flushing of connecting piping is completed. Blinds are to
have tabs, which clearly identify the blind's presence in the line (Activity #4).

4. If a pump is shipped with double mechanical seals installed, fill the entire seal
cavity with mechanical seal type lubricant (Activity #2).

5. Spare rotating elements shall be stored indoors and per the manufacturer's
recommendations.

6. Equipment seal pots, pressurization piston assemblies, and related


instrumentation that are shipped loose shall be preserved, wrapped, and stored
indoors.

7. After installation at their final service location, reciprocating pumps and


compressors shall be protected as follows:

i. For reciprocating compressors the following shall be performed; Metal flange


covers with gaskets shall be installed on all compressor openings. A
nitrogen blanket shall be kept inside the machine frame to prevent moisture
and contaminants from entering the equipment. The nitrogen blanket (kept
at 5 psig (35 kPa(g)) or as specified by supplier) shall be checked and
maintained if necessary on a bi-weekly basis. Exposed machined surfaces
shall be coated with EXTERIOR preservative. When applicable, reseal
enclosures if opened by Customs. Cover filters or remove (Activity #3, #4,
#9).

ii For proportioning and metering pumps the drive mechanism (gearbox) shall
be filled with LUBE COMPATIBLE preservative. The equipment shall be
checked at bi-weekly intervals to ensure the drive mechanism and hydraulic
mechanisms are filled with the preservative.

c. Other mechanical equipment not specifically covered herein shall be protected as


follows:

1. Fill the oil lubricated bearing housings and gear unit cases with specified
(Manufacturer/Brand) preservative (Activity #8, #11, #14).

2. Apply a coating of EXTERIOR preservative to all shafts, couplings, and exposed-


machined surfaces with (Manufacturer/Brand). Cover if required (Activity #5, #6).

3. Remove all exposed drive chains. Clean chains with solvent, coat with
STORAGE type preservative, and wrap them in Kraft paper. Label each
wrapped chain to provide the proper identification, and store with accessories.

2.7 Motors and Generators

Contains Confidential Information of both Dow and Saudi Aramco


Page 11 of 28
Ras Tanura Integrated Project (RTIP) Document No: RT-6-1CS
KBR Project No. A554 Revision: 3
MATERIAL AND EQUIPMENT PROTECTION
AND PRESERVATION PLAN Issue Purpose: IFD

2.7.1 Indoor storage is required for all motors, except for motors designed for outdoor
use, which may be stored outdoors without protective covering if exposed shaft and
coupling are preserved.

2.7.2 For motors and electric motor operated valve actuators stored outdoors without
protective cover, the following shall be observed:

a. All enclosure openings not intended to be open during operation of the equipment,
such as conduit and cable entrance in terminal boxes, shall be closed with watertight
plugs. Temporary shipping plugs shall be replaced with permanent storage plugs
(Activity #3).

b. All motors and valve actuators shall be stored in their normal operating position, e.g.,
vertical motors in an upright position with their shaft extension downward. Inspect
and preserve seats.

c. If space heaters are furnished within the units, they shall be connected to a
continuous supply of power of the proper rating (Activity #17).

d. Insulation resistance values of each winding shall be measured and recorded on the
Construction Engineering Equipment Maintenance Log Sheet. This shall be done as
soon as possible after a unit arrives at the jobsite (Activity #18). If readings are low,
dry out the insulation using a method approved by supplier/manufacturer. Retest
periodically.

2.7.3 After installation at the final service location, motors with oil lubricated bearings
shall be protected as follows:

a. Maintain all internal surfaces of bearing housing with specified (Manufacturer/Brand)


preservative. Vent and drain connections shall be plugged, capped, or blinded, as
applicable, using steel fittings. Preservative oil level shall be checked at bi-weekly
intervals (Activity #3, #8, #11).

b. Every three months, measure and record insulation resistance values (Activity #18)
of each winding of units rated 2300 volts and higher on the Construction Engineering
Equipment Maintenance Log Sheet. Record temperature and weather conditions at
time of reading. If resistance is low and cables have been connected, disconnect the
cables and repeat the measurements. If resistance of winding insulation only is low,
dry out leads in unit's terminal box by removing the cover and exposing to dry, clear
weather, or by placing an electric lamp or heater in the terminal box. If this does not
result in acceptable insulation resistance values, dry out the windings by an
approved method until acceptable values are obtained.

c. Six weeks before commissioning, measure and record insulation resistance values of
each winding of all units on the Construction Engineering Equipment Maintenance
Log Sheet. Record temperature and weather conditions at time of reading. If
resistance is low, proceed per Paragraph 2.7.3.b.

Contains Confidential Information of both Dow and Saudi Aramco


Page 12 of 28
Ras Tanura Integrated Project (RTIP) Document No: RT-6-1CS
KBR Project No. A554 Revision: 3
MATERIAL AND EQUIPMENT PROTECTION
AND PRESERVATION PLAN Issue Purpose: IFD

d. Immediately before commissioning measure and record insulation values of all units
with cables disconnected. If readings are low, dry out before starting.

2.7.4 After installation at the final service location, motors with grease lubricated
bearings shall be protected as follows:

R2 a. Every three months, measure and record insulation resistance values (Activity #18)
of each winding of units rated 2300 volts and higher on the Construction Engineering
Maintenance Log Sheet (Appendix 3). Record temperature and weather conditions
at time of reading. If resistance is low and cables have been connected, disconnect
the cables and repeat the measurements. If resistance of winding insulation only is
low, dry out leads in unit’s terminal box by removing cover and exposing to dry, clear
weather, or by placing an electric lamp or heater in the terminal box. If this does not
result in acceptable insulation resistance values, dry out the windings by an
approved method until acceptable values are obtained.

R2 b. Six weeks before commissioning, measure and record insulation resistance values of
each winding of all units on the Construction Engineering Maintenance Log Sheet
(Appendix 3). Record temperature and weather conditions at time of reading. If
resistance is low, proceed per Paragraph 2.7.4 a.

c. For periods over 4 months, bearings shall be re-lubricated, if required, in accordance


with Manufacturer’s Recommendations and Instructions. If grease lubricated units
are at Work Site more than one year from the date of shipment from the factory
without having been operated, inspect the bearing grease (this does not apply to
“Sealed Bearings”). If there has been any visible deterioration of the lubricating
properties of the grease, clean it out and repack the bearings per manufacturer’s
recommendations (Activity #12).

d. Immediately before commissioning, measure and record insulation values of all units
with cables disconnected. If readings are low, dry out before starting.

2.8 Transformers

2.8.1 Indoor storage is required for all transformers except the following:

a. Transformers intended for outdoor installation may be stored outdoors without


protective covering. See the Equipment Preservation and Maintenance Log
Summary (Appendix 2) for storage categories.

b. Large indoor units may be stored outdoors if raised above grade to prevent any
damage from surface water and if a shed roof and tarpaulin siding (or equivalent) is
provided. See the Equipment Preservation and Maintenance Log Summary
(Appendix 2) for storage categories.

c. Drums of insulating liquid stored outdoors shall be laid on their side with the large
bung at about a 45 degree angle from the bottom center position and above grade.

Contains Confidential Information of both Dow and Saudi Aramco


Page 13 of 28
Ras Tanura Integrated Project (RTIP) Document No: RT-6-1CS
KBR Project No. A554 Revision: 3
MATERIAL AND EQUIPMENT PROTECTION
AND PRESERVATION PLAN Issue Purpose: IFD

d. Transformers filled with insulating liquid

If a transformer is shipped with its main tank filled with insulating liquid (except for
expansion space), measure and record the level of the liquid and the ambient
temperature when the unit arrives on Site, and every month thereafter. If the level
falls, repair leaks and add insulating liquid to keep the level within tolerances.

e. Gas under pressure

If a transformer is shipped with its main tank filled with insulating liquid and blanketed
with gas under pressure (or filled with gas under pressure), measure and record the
gas pressure and the ambient temperature when the unit arrives at site. Measure
and record the gas pressure and the ambient temperature every month thereafter. If
the pressure falls, repair leaks and add gas to keep the pressure within tolerances.

f. Primary disconnect switches

Primary disconnect switches shall be handled per the requirements for switchgear,
starters, and control equipment.

2.9 Switchgear, Starters and Control Equipment

2.9.1 Equipment shall be stored indoors in a dry, warm place where condensation of
water vapor cannot occur, and as follows:

a. There shall be good ventilation of the warehouse.

b. If high relative humidity or large, rapid changes in temperature are experienced,


heaters shall be used to maintain the temperature at a level approximately 10 oF
(6 oC) above minimum daily temperature.

c. If space heaters are furnished within the equipment, they shall be connected to a
continuous source of power of the proper rating upon arrival at Jobsite.

d. Free-standing metal enclosed equipment shall be stored in an upright position.

e. Oil immersed starters, circuit breakers, and similar items, which are shipped dry,
shall be stored indoors, or shall be filled with insulating liquid as soon as they are
received at site. Units filled with liquid may be stored outdoors if raised above grade
to prevent any damage from surface water and if a shed roof and tarpaulin, siding (or
equivalent) is provided.

f. Insulation resistance values of such parts as operating coils shall be spot checked
every (Select Time Frame). If any readings are low, the affected parts shall be dried
out before they are placed in operation.

2.10 Cables

Contains Confidential Information of both Dow and Saudi Aramco


Page 14 of 28
Ras Tanura Integrated Project (RTIP) Document No: RT-6-1CS
KBR Project No. A554 Revision: 3
MATERIAL AND EQUIPMENT PROTECTION
AND PRESERVATION PLAN Issue Purpose: IFD

2.10.1 Reels of paper insulated lead sheathed cable shall be rotated 90o every (Select
Time Frame).

2.10.2 Low-pressure gas filled cable shall be handled as follows:

a. Gas pressure shall be measured and recorded when the cable is received at site,
and every month thereafter. The pressure should be between 5 and 13 psig (35 and
90 kPa). If falling pressure indicates a leak in the cable, connect a cylinder of dry
nitrogen to the cable to maintain pressure until the leak is located and sealed.

b. Nitrogen used to maintain pressure during storage, if required, shall be per ASTM
D1933, Type I, II or III (Type III is preferred, if available). Manufacturer's
recommendations shall be followed during installation and operation of any nitrogen
cylinders.

2.11 Storage Batteries

2.11.1 All batteries shall be stored indoors, in a dry place.

2.11.2 Batteries that have been shipped dry and sealed shall have the seals inspected
when they are received at site. Any seals that are damaged shall be renewed per the
manufacturer's instructions.

2.11.3 Lead-acid batteries that have been shipped wet shall be handled as follows:

a. Electrolyte level shall be inspected when batteries are received at site. Electrolyte
shall be added to the proper level, if any has been lost.

b. Three months after date of shipment from the factory, and every 3 months thereafter,
batteries shall be given a freshening charge to restore the voltage to 2.15 volts per
cell and the specific gravity to 1.21 at 77 oF (25 oC). The charging rate shall not
exceed the manufacturer's recommended value; batteries shall not be overcharged.

c. Other type batteries that have been shipped wet shall be handled per the
manufacturer's instructions.

2.12 Instruments

2.12.1 Satellite Buildings (Remote Instrument Enclosures) with DCS, SIS or other
sensitive or computer-based instrument hardware should not be shipped to jobsites
where high temperatures or humidity are encountered, until permanent or temporary
power can be connected and air conditioning units can be run.

2.12.2 DCS, SIS, or other sensitive or computer-based hardware shipped loose should
not be shipped to the jobsite until it can be installed or stored in its final building, i.e.,
control building, satellite building, rack room, etc., or other indoor air conditioned area.

Contains Confidential Information of both Dow and Saudi Aramco


Page 15 of 28
Ras Tanura Integrated Project (RTIP) Document No: RT-6-1CS
KBR Project No. A554 Revision: 3
MATERIAL AND EQUIPMENT PROTECTION
AND PRESERVATION PLAN Issue Purpose: IFD

2.12.3 DCS hardware, such as field-bus racks, multiplexers, remote I/O modules, etc.
which will ultimately be installed in the field may be installed indoors, where heat and
humidity are limited, however they need not be stored in control room or satellite building
areas.

R3 2.12.4 Analyzer shelters and complex analyzers shall be stored per the
recommendations of the Suppliers. HVAC units shall be hooked up and operated to
maintain equipment inside the shelter.

2.12.5 All instruments requiring a temperature controlled environment shall be stored


indoors and as follows:

a. Temperature shall be controlled to prevent the condensation of humidity.

b. Prefabricated panel boards shall be left in their shipping cases until moved into the
control house or other location.

c. Potentiometers shall never be exposed to temperatures below 32 oF (0 oC) or above


125 oF (52 oC).

d. Instruments including control valve and motor actuators installed at outdoor locations
shall be protected from the weather and mechanical damage. Wood covers over
glass fronts may be used.

e. Control valves actuators shall be protected from severe shock and extreme
temperatures as they may contain electronic hardware. Conduit openings shall
remain with plastic plugs or other devices to inhibit rain, snow, and dust from entering
these enclosures until conduit or cable glands can be installed.

f. Motor actuators shall be protected in the same manner as motors.

2.13 Valves

2.13.1 Indoor storage shall be provided for all valves except the following:

a. Manually operated valves Size NPS 4 (100 mm) or larger may be stored outdoors on
a paved area (or pallets), with the valve stem upright. Valves stored outdoors must
be protected from blowing sand and salt spray.

b. Large automatic control valves such as slide valves and motor operated valves may
be stored outdoors on a paved area, or on pallets, if a shed roof and tarpaulin siding
(or equivalent) are provided. Actuators on control valves and motor operated valves
shall be protected against mechanical damage. All conduit connections shall be
covered to prevent water entry.

c. Valves shall be stored in the closed position, unless they have a spring actuator,
then the valve should be stored in the position such that the spring is in a relaxed
state.

Contains Confidential Information of both Dow and Saudi Aramco


Page 16 of 28
Ras Tanura Integrated Project (RTIP) Document No: RT-6-1CS
KBR Project No. A554 Revision: 3
MATERIAL AND EQUIPMENT PROTECTION
AND PRESERVATION PLAN Issue Purpose: IFD

d. Flange protectors shall be left on until the valve is ready to be installed (See Section
2.16).
e. Control valves shall be stored in accordance with the manufacturer’s storage
procedures and requirements.

2.14 Welding Consumables


R2 All bulk covered electrodes, SAW flux, spooled or straight length solid bare and flux and
metal cored wire shall be stored in a clean, warm (70 °F/21 °C minimum) and dry location
(70% maximum relative humidity) and shall be placed on wooden pallets or suitable
cribbing to eliminate contact with the floor. Procurement and management of welding
consumables should be in accordance with Engineering Procurement Contractor’s(EPC)
procedure for Welding Filler Metal and Electrode Procurement and Management.

2.15 Stainless Steel


2.15.1 Stainless steel (alloys containing more than 10% chromium) equipment,
components, and materials shall be protected as follows:
a. Undercover. (Protective coatings are acceptable alternatives to covered storage.)
b. Not in contact with the soil or with porous supports such as raw wood. The
preservation procedures must reflect the potential for environmental conditions to
create contact between the stainless steel and a potential corrosive (e.g., blowing
sand).
c. In addition, austenitic stainless steels shall not be exposed to salt water or salt spray.
d. Shall be stored segregated from ferrous materials.
e. Where there are large extremes between day and nighttime temperatures, care must
be taken to avoid collection of dew point condensation on stainless steel equipment
and materials.

2.16 Flange Facings


2.16.1 Flange facings on all piping and equipment shall be protected at all times during
fabrication and construction. The use of mechanical flange protectors should be
maximized, in addition to coating with the appropriate preservative.

2.16.2 All high-pressure flanges (Class 1500 and higher) shall be fitted with robust metal
protective caps during shipment and storage onsite. RTIP QA/QC must witness and
document that every high pressure joint is clean, undamaged and properly assembled
when the final closure is made. Such documentation shall be included in the turnover
packages for that system.

Contains Confidential Information of both Dow and Saudi Aramco


Page 17 of 28
Ras Tanura Integrated Project (RTIP) Document No: RT-6-1CS
KBR Project No. A554 Revision: 3
MATERIAL AND EQUIPMENT PROTECTION
AND PRESERVATION PLAN Issue Purpose: IFD

2.17 Vessels and Exchangers

2.17.1 Vessels and exchangers shall be stored and preserved in accordance with the
requirements set forth on the Equipment Preservation and Maintenance Log Summary
(Appendix 2) for storage categories.

2.17.2 Equipment maintenance and protection quality records shall be kept on the
Construction Engineering Maintenance Log Sheet (Appendix 3).

2.17.3 Special storage requirements as detailed in the Suppliers’ data books and
instruction manuals shall be adhered to.

2.17.4 Electric heaters shall have vapor phase inhibitor bags or desiccant bags on the
heater element side in order to prevent the absorption of moisture by the element
(Activity #15).

2.17.5 Air cooler fans should be prevented from rotating during storage, either by
restraining the fan blades, or by restraining the driven sprocket. Motors and belts should
be left in the shipping packaging as long as possible, and stored in a dry place at
moderate temperatures. Gear drives should be filled with lubricant. If storage lasts more
than three months, fan and motor shafts should be manually rotated at least 15
revolutions once a month, and should have grease added once every six months
according to the following table:

NEMA Frame Size (IEC) Vol. (mL)

182 – 215 (112 - 132) 8


254 – 286 (160 – 180) 16
324 – 365 (200 – 225) 24
404 – 449 (250 – 280) 40

Fan Bearings 75

After manual rotation of motor shafts, packaging should be returned to original state, and
desiccant should be added. Fans should be re-secured, and any covering replaced.

2.17.6 Louvers should be in the closed position. Carbon steel tubes with extruded fins
should have the exposed ends sprayed with oil every three months and the tube bundle
should be covered with plastic or canvas. If the exposed tube ends are painted with
epoxy paint, spraying with oil is unnecessary. For carbon steel tubes with embedded
fins, the entire length of the tubes should be sprayed with light oil every three months,
and the bundles covered. Machined surfaces of sprockets should be coated with grease.
For bundles with a nitrogen purge, pressure should be monitored, and nitrogen replaced
as necessary.

2.17.7 When air coolers are put in service, grease lines should be disconnected from
bearing housings, and lines should be purged with new grease. Lines should then be
reconnected, and bearing grease chambers should be purged with new grease, with

Contains Confidential Information of both Dow and Saudi Aramco


Page 18 of 28
Ras Tanura Integrated Project (RTIP) Document No: RT-6-1CS
KBR Project No. A554 Revision: 3
MATERIAL AND EQUIPMENT PROTECTION
AND PRESERVATION PLAN Issue Purpose: IFD

bearing drain plugs removed. Motors should be started and run for 5 to 10 minutes
before drain plugs are re-tightened.

2.18 Computers, Telecommunications and Associated Equipment

(Also, see Paragraphs 2.12.1 and 2.12.2)

All computer, telecommunication and associated equipment will be stored and


maintained in accordance with the manufacturer’s specified requirements. All sensitive
electronic equipment items shall be stored in environmentally controlled, indoor storage
locations. Only qualified personnel shall perform preventive maintenance for such
equipment.

2.19 Piping

2.19.1 General

R3 Piping should be placed on cribs in the field. Pipe and piping materials arrive at the site in
various forms of fabrication including fabricated spools, assemblies, random lengths of
pipe, and bulks. All materials shall be suitably stored and protected from the site
conditions. Materials subject to sea spray, blowing dust and sand, freezing or elevated
temperatures may require special storage precautions. Piping and piping assemblies
intended for lube oil service shall be kept clean, dry and sealed to minimize the risk of oil
contamination and lengthy flushing time during commissioning.

2.19.2 Damage

Damaged materials shall be documented, photographed and reported. Report shall


indicate the reason for the condition of the materials. The receiving inspector shall
record condition of materials on the material receiving record so that the Materials
personnel can take necessary corrective measures. All damaged materials shall be
stored separately from undamaged materials.

2.19.3 Corrosion Protection

All materials shall be inspected for corrosion. Corrosion shall be removed by methods
that do not damage the machined surfaces (Activity #20) and the cleaned surfaces
coated with a suitable rust inhibitor (Activity #5, #6). Inhibitors shall be inspected
routinely and renewed if there are any breaks in the film or signs of corrosion.

a. Threaded surfaces shall be coated with an anti-seize rust inhibitor.


b. Machined surfaces shall be coated with a petroleum soluble rust inhibitor.
c. Ferrous weld bevels shall be coated with a weldable rust inhibitor.

2.19.4 Mechanical End Protection

Protective seals (e.g., covers, plugs, caps, etc.) shall be inspected and if found to be
ineffective shall be restored or replaced (Activity #3, #4).

Contains Confidential Information of both Dow and Saudi Aramco


Page 19 of 28
Ras Tanura Integrated Project (RTIP) Document No: RT-6-1CS
KBR Project No. A554 Revision: 3
MATERIAL AND EQUIPMENT PROTECTION
AND PRESERVATION PLAN Issue Purpose: IFD

a. All openings shall be fully capped, plugged or covered to prevent damage and
ingress of moisture and foreign matter.
b. Wood covers may be used on flanges provided an impervious membrane is placed
between the wood and greased flange face.
c. Threaded ends shall be protected with high impact plastic wedge type protectors.

2.19.5 Internals

Internals shall be clear of debris and free of foreign matter. Internals protected with
desiccants, vapor corrosion inhibitors, or purges shall be tagged or marked to indicate
type of preservative used, when replaced, and when last inspected. Desiccants shall not
be used to protect stainless steel or high alloy materials, or components with rubber
internals. Silica gel used as desiccant shall be of the indicating type (blue-active) and
packaged to allow viewing of the material. The approximate volume to be used shall be
0.12 lb/ft3 (2 kg/m3). Purge items require internal inspection only when the purge is lost
(Activity #9, #15).

2.19.6 Shipping Containers

Materials may be stored in their original shipping container provided the container has
not been damaged and the container, and its internal dunnage, has been determined to
be suitable for the site storage conditions. Shipping containers determined to be suitable
for storage shall be resealed after receiving and inspection. Materials stored in shipping
containers shall be routinely inspected for corrosion.

2.19.7 Dunnage

All materials shall be stored on suitable dunnage to keep them clear of the ground and to
provide ventilation around materials to allow moisture evaporation. Fibrous dunnage
materials that can absorb moisture (e.g., pressed board, cardboard, softwood, etc.) shall
not be used to support or separate materials. Any fibrous dunnage materials located
shall be removed and replaced with suitable dunnage.

2.19.8 Traceability

Materials shall be inspected for proper markings in accordance with project standards
and the purchase order. Material traceability must be maintained at all times.

a. Alloy verified material should be segregated at all times from other materials.
b. Impacted tested carbon steel (ITCS) materials shall be color coded and segregated
from normal materials during storage.

2.19.9 Stainless Steel and High Alloy Materials

If site conditions dictate, uncoated SS and high alloy materials shall be stored under
cover or under tarps with adequate ventilation. The purpose of the cover is to prevent
contamination from airborne contaminants, blowing dust or sand, and iron-contamination

Contains Confidential Information of both Dow and Saudi Aramco


Page 20 of 28
Ras Tanura Integrated Project (RTIP) Document No: RT-6-1CS
KBR Project No. A554 Revision: 3
MATERIAL AND EQUIPMENT PROTECTION
AND PRESERVATION PLAN Issue Purpose: IFD

from grinding, welding and fabrication operations. Stainless steel and high alloy
materials shall not be:

a. Stored with, or come into contact with any ferrous materials.


b. Stored in contact with porous or moisture retaining supports on the ground.
c. Exposed to salt water or sea spray.
d. Marked with any markers other than low chloride markers.
e. Sealed with any type of tape or adhesive.
f. Protected from moisture by the use of desiccants.

2.19.10 Non-Metallics

Non-metallic materials shall be handled, stored, and protected in accordance with the
Suppliers recommended procedures and the following:

a. Exposed rubber parts shall be wrapped in opaque plastic covers secured with tape
or otherwise sealed.
b. Desiccants shall not be used to protect rubber or components with rubber parts.
c. Non-metallic materials shall be protection from UV exposure, high temperature and
mechanical abuse.
d. Openings shall be protected from mechanical damage by end caps.
e. Non-metallics shall be protected from impact against hard objects.

2.19.11 Special Protection Requirements

Manufacturer’s data shall be reviewed to determine if any special storage or preventative


maintenance procedures are required to maintain Suppliers' warranties.

2.19.12 Deficiency in Protection

Storage and protection methods shall be suitable for the site conditions. Some materials,
such as machined ferrous surfaces, are more sensitive to the environmental conditions
and require more frequent preventative maintenance. If the method of storage or level of
protection provided is not sufficient, then a deficiency exists and the materials shall be
marked for corrective action.

a. Storage and lay down areas shall be designed so that they are well drained.
b. All bulks stored outside shall be elevated above the ground and above the maximum
water run-off.
c. Bulks shall be stored in a manner that facilitates routine inspection and preventative
maintenance.
d. Storage methods shall protect materials from infiltration of water, dust, dirt, vermin,
insects, etc.
e. Materials shall not be stored in non-drainable positions, which will trap water.
f. Sensitive materials, such as stainless steel and non-metallics, are properly stored
and protected.
g. Materials subject to sea spray, blowing dust or sand, freezing or elevated
temperatures require additional protection.

Contains Confidential Information of both Dow and Saudi Aramco


Page 21 of 28
Ras Tanura Integrated Project (RTIP) Document No: RT-6-1CS
KBR Project No. A554 Revision: 3
MATERIAL AND EQUIPMENT PROTECTION
AND PRESERVATION PLAN Issue Purpose: IFD

2.19.13 Valves

a. Plug and ball valves shall be stored in the opened position.


b. Valves with a spring actuator shall be stored in the position that the spring is in a
relaxed position.
c. All other valves shall be stored in the closed position.
d. Valves shall have the interior coated with light oil.
e. Valve stems shall be coated with an anti-seize corrosion inhibitor.
f. Hand wheels that have been removed shall be securely strapped to the valve.
g. Safety relief valves shall be stored upright with lifting levers strapped to the body of
the valve.
h. Actuators on motor operated valves shall be protected against mechanical damage.

2.19.14 Pre-Insulated pipe Supports

a. Pipe supports with insulation shall be stored in a covered location in original sealed
containers or bags.
b. Cold pipe supports shall be sleeved in polyethylene and heat-sealed in waterproof
packages.
c. Insulation shall be protected from UV degradation and moisture.

2.19.15 Nuts, Bolts, and Gaskets

a. Nuts, bolts and washers shall be kept in sealed watertight containers if stored
outside.
b. Gaskets shall be sleeved in polyethylene and heat-sealed or maintained in
waterproof vapor barrier packages if stored outside.
R3 c. Contractor shall take care as to not misplace nuts and bolts.

2.19.16 Pipe

a. Pipe stored in the storage yard shall be placed on level timbers or pallets providing
good ground clearance.
b. Pipe openings shall be protected from entry of rain and foreign matter until closure
welds are made.
c. Internal spiders shall be maintained on large diameter thin wall piping to prevent out-
of-roundness.

2.19.17 Fabricated Pipe and Assemblies

a. Fabricated pipe shall be placed on level timbers or pallets providing good ground
clearance.
b. Pipe openings shall be protected from entry of rain and foreign matter until closure
welds are made.
c. Fabricated assemblies shall be maintained in shipping packages to prevent
mechanical damage.

Contains Confidential Information of both Dow and Saudi Aramco


Page 22 of 28
Ras Tanura Integrated Project (RTIP) Document No: RT-6-1CS
KBR Project No. A554 Revision: 3
MATERIAL AND EQUIPMENT PROTECTION
AND PRESERVATION PLAN Issue Purpose: IFD

d. Expansion joints shall be secured in a fixed position to prevent deflection during


handling, transport and storage.
e. Fabricated items and components shall not be stored outdoors in non-drainable
positions.

3. QUALITY CONTROL PROCEDURES

3.1 General

R2 This section references the Quality Control Procedures relevant to equipment protection
on the project. These procedures (and associated forms) may be found in the
Engineering Procurement Contractors (EPC) Construction Quality Control Procedures
Manual for the Program (Client), and/or the Project.

3.2 Relevant Document

R2 Construction Quality Manual: To be provided by Engineering Procurement Contractor


(EPC)

R2 RT-6-1-CSA Equipment and Material Protection Plan Work Process

R2 A554-K-PRG-CE-GEN-FRM-001 Equipment and Material Protection Plan work Process


Spreadsheet

4. MATERIAL CONTROL PROCEDURES

Refer to Engineering Procurement Contractor (EPC) Material Control Receiving


Procedures relevant to equipment receipt.

Contains Confidential Information of both Dow and Saudi Aramco


Page 23 of 28
Ras Tanura Integrated Project (RTIP) Document No: RT-6-1CS
KBR Project No. A554 Revision: 3
MATERIAL AND EQUIPMENT PROTECTION
AND PRESERVATION PLAN Issue Purpose: IFD

APPENDIX 1
ACTIVITY NUMBER CODES AND STORAGE LETTER CODES

1. ACTIVITY NUMBER CODES

1 Rotate shaft 2 1/4 turns


2 Fill double and tandem mechanical oil seal with seal oil
3 Plug or cap any openings
4 Cover and protect all equipment nozzles
Spray shafts and hubs with preservative and protect exposed shafts with wax
5
cloth wrap as required
6 Inspect machined surfaces and coat with preservative
7 Protect oil and level gauges as required
8 Check preservation oil level
9 Check nitrogen blanket pressure and add nitrogen as required
10 Inspect for presence of moisture
11 Fill bearing housings with oil as required
12 Purge and grease bearings (once every four months)
13 Preserve internals of lube and seal oil system
14 Fill gear box with lubricant as required
15 Check and add desiccant or vapor phase inhibitor as required
16 Operate lube oil system as required
17 Verify space heaters are operational as required
18 Measure insulation resistance as required
19 Protect exposed shafts with wax cloth wrap as required
20 Remove rust prior to application of preservative

2. STORAGE LETTER CODES

I Indoor storage - Unheated


O Outdoor storage/Lay down - Unprotected
R3 IH Indoor storage – HVAC controlled.
OC Outdoor storage - Covered

Contains Confidential Information of both Dow and Saudi Aramco


Page 24 of 28
Ras Tanura Integrated Project (RTIP) Document No: RT-6-1CS
KBR Project No. A554 Revision: 3
MATERIAL AND EQUIPMENT PROTECTION
AND PRESERVATION PLAN Issue Purpose: IFD

APPENDIX 2
(Client)(Site) Project - EQUIPMENT PRESERVATION AND MAINTENANCE LOG
SUMMARY (SAMPLE COPY)

Note. This form should be reviewed to ensure that sufficient room is provided on the form to allow pertinent information
and instructions to be recorded. As a minimum, the actual form should be size 11x17 (A3).

Contains Confidential Information of both Dow and Saudi Aramco


Page 25 of 28
Ras Tanura Integrated Project (RTIP) Document No: RT-6-1CS
KBR Project No. A554 Revision: 3
MATERIAL AND EQUIPMENT PROTECTION
AND PRESERVATION PLAN Issue Purpose: IFD

APPENDIX 3
CONSTRUCTION ENGINEERING MAINTENANCE LOG SHEET (1 OF 3)
JOB NO.:
CLIENT: CONSTRUCTION ENGINEERING
CONT’D ON
LOCATION: EQUIPMENT MAINTENANCE LOG SHEET PAGE 1
PAGE 2
TYPE EQUIP.: ITEM NO.:
MFGR.: S/N:

MOTOR INSULATION RESISTANCE CHECK


TECHNICIAN
DATE T1 T2 T3 Q.C. Initials
INITIALS

ACTIVITY
ACTIVITY DESCRIPTION SCHEDULE
NUMBER B
W W
M SP

1 Rotate shaft 2 1/4 turns


2 Fill double and tandem mechanical oil seal with seal oil
3 Plug or cap any openings
4 Cover and Protect all equipment nozzles
5 Spray shafts and hubs with preservative and protect exposed shafts
with wax cloth wrap as required
6 Inspect machined surfaces and coat with preservative
7 Protect oil view ports and level gauges as required
8 Check preservation oil level
9 Check nitrogen blanket pressure and add nitrogen as required
10 Inspect for presence of moisture
11 Fill bearing housings with oil as required
12 Purge and grease bearings (once every four months)
13 Preserve internals of lube and seal oil system
14 Fill gear box with lubricant as required
15 Check and add desiccant or vapor phase inhibitor as required
16 Operate lube oil system as required
17 Verify space heaters are operational as required
18 Measure insulation resistance as required
19 Protect exposed shafts with wax cloth wrap as required
20 Remove rust prior to application of preservative
DATE Tech. QC
ACTIVITY NUMBER Init. Init.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

W = WEEKLY; BW = BIWEEKLY; M = MONTHLY; SP = SPECIAL PERIOD: ITEM NO.

Contains Confidential Information of both Dow and Saudi Aramco


Page 26 of 28
Ras Tanura Integrated Project (RTIP) Document No: RT-6-1CS
KBR Project No. A554 Revision: 3
MATERIAL AND EQUIPMENT PROTECTION
AND PRESERVATION PLAN Issue Purpose: IFD

APPENDIX 3
CONSTRUCTION ENGINEERING MAINTENANCE LOG SHEET (2 OF 3)
JOB NO.:
CLIENT: CONSTRUCTION ENGINEERING

CONT’D ON
LOCATION: PAGE 2
EQUIPMENT MAINTENANCE PAGE 3
LOG SHEET
TYPE EQUIP.: ITEM NO.:
MFGR.: S/N:
DATE RECEIVED: DATE INSTALLED:
Tech. Q.C.
DATE
ACTIVITY NUMBER Initial Initial
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

W = WEEKLY, BW = BIWEEKLY, M = MONTHLY SP = SPECIAL PERIOD ITEM NO.:

Contains Confidential Information of both Dow and Saudi Aramco


Page 27 of 28
Ras Tanura Integrated Project (RTIP) Document No: RT-6-1CS
KBR Project No. A554 Revision: 3
MATERIAL AND EQUIPMENT PROTECTION
AND PRESERVATION PLAN Issue Purpose: IFD

APPENDIX 3
CONSTRUCTION ENGINEERING MAINTENANCE LOG SHEET (3 OF 3)
CLIENT: CONSTRUCTION ENGINEERING JOB NO.:
EQUIPMENT MAINTENANCE LOG
LOCATION: SHEET PAGE 3 LAST PAGE

TYPE EQUIP.: ITEM NO.:


MFGR.: S/N:
DATE NOTES (Record special precautions taken) Tech Q.C.
Initial Initial

W = WEEKLY, BW = BIWEEKLY, M = MONTHLY, SP = SPECIAL PERIOD ITEM NO.:

Contains Confidential Information of both Dow and Saudi Aramco


Page 28 of 28

Вам также может понравиться