Академический Документы
Профессиональный Документы
Культура Документы
x--------------------------------------------------------------------------------- x
RESOLUTION
TINGA, J.:
On 5 June 2006, the two cases, G.R. Nos. 161957 and 167994, were
consolidated upon the recommendation of the Assistant Division
Clerk of Court since the cases are rooted in the same Addendum
Contract.
We first tackle the more recent case which is G.R. No. 167994. It
stemmed from the petition to compel arbitration filed by respondent
Climax-Arimco before the RTC of Makati City on 31 March 2000 while
the complaint for the nullification of the Addendum Contract was
pending before the DENR Panel of Arbitrators. On 23 March 2000,
Climax-Arimco had sent Gonzales a Demand for Arbitration pursuant
to Clause 19.111 of the Addendum Contract and also in accordance
with Sec. 5 of R.A. No. 876. The petition for arbitration was
subsequently filed and Climax-Arimco sought an order to compel the
parties to arbitrate pursuant to the said arbitration clause. The case,
docketed as Civil Case No. 00-444, was initially raffled to Br. 132 of
the RTC of Makati City, with Judge Herminio I. Benito as Presiding
Judge. Respondent Climax-Arimco filed on 5 April 2000 a motion to
set the application to compel arbitration for hearing.
On 31 May 2000, Gonzales asked the RTC to set the case for pre-
trial.14 This the RTC denied on 16 June 2000, holding that the petition
for arbitration is a special proceeding that is summary in
nature.15 However, on 7 July 2000, the RTC granted Gonzales’s
motion for reconsideration of the 16 June 2000 Order and set the
case for pre-trial on 10 August 2000, it being of the view that
Gonzales had raised in his answer the issue of the making of the
arbitration agreement.16
Climax-Arimco then filed a motion to resolve its pending motion to
compel arbitration. The RTC denied the same in its 24 July 2000
order.
Gonzales thus filed the Rule 65 petition assailing the Orders dated 13
February 2001 and 7 March 2005 of Judge Pimentel. Gonzales
contends that public respondent Judge Pimentel acted with grave
abuse of discretion in immediately ordering the parties to proceed
with arbitration despite the proper, valid, and timely raised argument
in his Answer with Counterclaim that the Addendum Contract,
containing the arbitration clause, is null and void. Gonzales has also
sought a temporary restraining order to prevent the enforcement of
the assailed orders directing the parties to arbitrate, and to direct
Judge Pimentel to hold a pre-trial conference and the necessary
hearings on the determination of the nullity of the Addendum
Contract.
The court shall decide all motions, petitions or applications filed under
the provisions of this Act, within ten (10) days after such motions,
petitions, or applications have been heard by it.
Thus, the main issue raised in the Petition for Certiorari is whether it
was proper for the RTC, in the proceeding to compel arbitration under
R.A. No. 876, to order the parties to arbitrate even though the
defendant therein has raised the twin issues of validity and nullity of
the Addendum Contract and, consequently, of the arbitration clause
therein as well. The resolution of both Climax-Arimco’s Motion for
Partial Reconsideration and/or Clarification in G.R. No. 161957 and
Gonzales’s Petition for Certiorari in G.R. No. 167994 essentially turns
on whether the question of validity of the Addendum Contract bears
upon the applicability or enforceability of the arbitration clause
contained therein. The two pending matters shall thus be jointly
resolved.
We address the Rule 65 petition in G.R. No. 167994 first from the
remedial law perspective. It deserves to be dismissed on procedural
grounds, as it was filed in lieu of appeal which is the prescribed
remedy and at that far beyond the reglementary period. It is
elementary in remedial law that the use of an erroneous mode of
appeal is cause for dismissal of the petition for certiorari and it has
been repeatedly stressed that a petition for certiorari is not a
substitute for a lost appeal. As its nature, a petition for certiorari lies
only where there is "no appeal," and "no plain, speedy and adequate
remedy in the ordinary course of law."25 The Arbitration Law
specifically provides for an appeal by certiorari, i.e., a petition for
review under certiorari under Rule 45 of the Rules of Court that raises
pure questions of law.26 There is no merit to Gonzales’s argument
that the use of the permissive term "may" in Sec. 29, R.A. No. 876 in
the filing of appeals does not prohibit nor discount the filing of a
petition for certiorari under Rule 65.27 Proper interpretation of the
aforesaid provision of law shows that the term "may" refers only to
the filing of an appeal, not to the mode of review to be employed.
Indeed, the use of "may" merely reiterates the principle that the right
to appeal is not part of due process of law but is a mere statutory
privilege to be exercised only in the manner and in accordance with
law.
The special proceeding under Sec. 6 of R.A. No. 876 recognizes the
contractual nature of arbitration clauses or agreements. It provides:
The court shall decide all motions, petitions or applications filed under
the provisions of this Act, within ten days after such motions,
petitions, or applications have been heard by it. [Emphasis added.]
The separability doctrine was dwelt upon at length in the U.S. case of
Prima Paint Corp. v. Flood & Conklin Manufacturing Co.49 In that
case, Prima Paint and Flood and Conklin (F & C) entered into a
consulting agreement whereby F & C undertook to act as consultant
to Prima Paint for six years, sold to Prima Paint a list of its customers
and promised not to sell paint to these customers during the same
period. The consulting agreement contained an arbitration clause.
Prima Paint did not make payments as provided in the consulting
agreement, contending that F & C had fraudulently misrepresented
that it was solvent and able for perform its contract when in fact it was
not and had even intended to file for bankruptcy after executing the
consultancy agreement. Thus, F & C served Prima Paint with a notice
of intention to arbitrate. Prima Paint sued in court for rescission of the
consulting agreement on the ground of fraudulent misrepresentation
and asked for the issuance of an order enjoining F & C from
proceeding with arbitration. F & C moved to stay the suit pending
arbitration. The trial court granted F & C’s motion, and the U.S.
Supreme Court affirmed.
The U.S. Supreme Court did not address Prima Paint’s argument that
it had been fraudulently induced by F & C to sign the consulting
agreement and held that no court should address this argument.
Relying on Sec. 4 of the Federal Arbitration Act—which provides that
"if a party [claims to be] aggrieved by the alleged failure x x x of
another to arbitrate x x x, [t]he court shall hear the parties, and upon
being satisfied that the making of the agreement for arbitration or the
failure to comply therewith is not in issue, the court shall make an
order directing the parties to proceed to arbitration x x x. If the making
of the arbitration agreement or the failure, neglect, or refusal to
perform the same be in issue, the court shall proceed summarily to
the trial thereof"—the U.S. High Court held that the court should not
order the parties to arbitrate if the making of the arbitration agreement
is in issue. The parties should be ordered to arbitration if, and only if,
they have contracted to submit to arbitration. Prima Paint was not
entitled to trial on the question of whether an arbitration agreement
was made because its allegations of fraudulent inducement were not
directed to the arbitration clause itself, but only to the consulting
agreement which contained the arbitration agreement.50 Prima Paint
held that "arbitration clauses are ‘separable’ from the contracts in
which they are embedded, and that where no claim is made that
fraud was directed to the arbitration clause itself, a broad arbitration
clause will be held to encompass arbitration of the claim that the
contract itself was induced by fraud."51
These are the same issues that Gonzales raised in his Rule 45
petition in G.R. No. 161957 which were resolved against him in the
Decision of 28 February 2005. Gonzales does not raise any new
argument that would sway the Court even a bit to alter its holding that
the complaint filed before the DENR Panel of Arbitrators involves
judicial issues which should properly be resolved by the regular
courts. He alleged fraud or misrepresentation in the execution of the
Addendum Contract which is a ground for the annulment of a
voidable contract. Clearly, such allegations entail legal questions
which are within the jurisdiction of the courts.
The question of whether Gonzales had ceded his claims over the
mineral deposits in the Addendum Area of Influence is a factual
question which is not proper for determination before this Court. At all
events, moreover, the question is irrelevant to the issue of jurisdiction
of the DENR Panel of Arbitrators. It should be pointed out that the
DENR Panel of Arbitrators made a factual finding in its Order dated
18 October 2001, which it reiterated in its Order dated 25 June 2002,
that Gonzales had, "through the various agreements, assigned his
interest over the mineral claims all in favor of [Climax-Arimco]" as well
as that without the complainant [Gonzales] assigning his interest over
the mineral claims in favor of [Climax-Arimco], there would be no
FTAA to speak of."52 This finding was affirmed by the Court of
Appeals in its Decision dated 30 July 2003 resolving the petition for
certiorari filed by Climax-Arimco in regard to the 18 October 2001
Order of the DENR Panel.53
SO ORDERED.
DANTE O. TINGA
Associate Justice
WE CONCUR:
DECISION
PERALTA, J.:
ARBITRATION
Any dispute which the Buyer and Seller may not be able to settle by
mutual agreement shall be settled by arbitration in the City of New
York before the American Arbitration Association. The Arbitration
Award shall be final and binding on both parties.5
that respondent must first comply with the arbitration clause before
resorting to court, thus, the RTC must either dismiss the case or
suspend the proceedings and direct the parties to proceed with
arbitration, pursuant to Sections 66 and 77 of Republic Act (R.A.) No.
876, or the Arbitration Law.
In denying the motion, the RTC found that there was no clear basis
for petitioner's plea to dismiss the case, pursuant to Section 7 of the
Arbitration Law. The RTC said that the provision directed the court
concerned only to stay the action or proceeding brought upon an
issue arising out of an agreement providing for the arbitration thereof,
but did not impose the sanction of dismissal. However, the RTC did
not find the suspension of the proceedings warranted, since the
Arbitration Law contemplates an arbitration proceeding that must be
conducted in the Philippines under the jurisdiction and control of the
RTC; and before an arbitrator who resides in the country; and that the
arbitral award is subject to court approval, disapproval and
modification, and that there must be an appeal from the judgment of
the RTC. The RTC found that the arbitration clause in question
contravened these procedures, i.e., the arbitration clause
contemplated an arbitration proceeding in New York before a non-
resident arbitrator (American Arbitration Association); that the arbitral
award shall be final and binding on both parties. The RTC said that to
apply Section 7 of the Arbitration Law to such an agreement would
result in disregarding the other sections of the same law and
rendered them useless and mere surplusages.
Petitioner filed its Motion for Reconsideration, which the RTC denied
in an Order10 dated November 25, 1998.
Petitioner filed a petition for certiorari with the CA raising the sole
issue that the RTC acted in excess of jurisdiction or with grave abuse
of discretion in refusing to dismiss or at least suspend the
proceedings a quo, despite the fact that the party's agreement to
arbitrate had not been complied with.
Respondent filed its Comment and Reply. The parties were then
required to file their respective Memoranda.
On July 31, 2006, the CA rendered its assailed Decision denying the
petition and affirming the RTC Orders.
Notwithstanding such findings, the CA still held that the case cannot
be brought under the Arbitration Law for the purpose of suspending
the proceedings before the RTC, since in its Motion to
Dismiss/Suspend proceedings, petitioner alleged, as one of the
grounds thereof, that the subject contract between the parties did not
exist or it was invalid; that the said contract bearing the arbitration
clause was never consummated by the parties, thus, it was proper
that such issue be first resolved by the court through an appropriate
trial; that the issue involved a question of fact that the RTC should
first resolve. Arbitration is not proper when one of the parties
repudiated the existence or validity of the contract.
defenses are inconsistent with each other; and (d) the complaint filed
by respondent with the trial court is premature.
Section 29.
In this case, petitioner raises before the CA the issue that the
respondent Judge acted in excess of jurisdiction or with grave abuse
of discretion in refusing to dismiss, or at least suspend, the
proceedings a quo, despite the fact that the party’s agreement to
arbitrate had not been complied with. Notably, the RTC found the
existence of the arbitration clause, since it said in its decision that
"hardly disputed is the fact that the arbitration clause in question
contravenes several provisions of the Arbitration Law x x x and to
apply Section 7 of the Arbitration Law to such an agreement would
result in the disregard of the afore-cited sections of the Arbitration
Law and render them useless and mere surplusages." However,
notwithstanding the finding that an arbitration agreement existed, the
RTC denied petitioner's motion and directed petitioner to file an
answer.
ARBITRATION
Any dispute which the Buyer and Seller may not be able to settle by
mutual agreement shall be settled by arbitration in the City of New
York before the American Arbitration Association, The Arbitration
Award shall be final and binding on both parties.
We found that since the complaint filed before the DENR Panel of
Arbitrators charged respondents with disregarding and ignoring the
addendum contract, and acting in a fraudulent and oppressive
manner against petitioner, the complaint filed before the Panel was
not a dispute involving rights to mining areas, or was it a dispute
involving claimholders or concessionaires, but essentially judicial
issues. We then said that the Panel of Arbitrators did not have
jurisdiction over such issue, since it does not involve the application
of technical knowledge and expertise relating to mining. It is in this
context that we said that:
Arbitration before the Panel of Arbitrators is proper only when there is
a disagreement between the parties as to some provisions of the
contract between them, which needs the interpretation and the
application of that particular knowledge and expertise possessed by
members of that Panel. It is not proper when one of the parties
repudiates the existence or validity of such contract or agreement on
the ground of fraud or oppression as in this case. The validity of the
contract cannot be subject of arbitration proceedings. Allegations of
fraud and duress in the execution of a contract are matters within the
jurisdiction of the ordinary courts of law. These questions are legal in
nature and require the application and interpretation of laws and
jurisprudence which is necessarily a judicial function.29
SO ORDERED.
DIOSDADO M. PERALTA
Associate Justice
WE CONCUR:
G.R. No. 120105 March 27, 1998
BF CORPORATION, petitioner,
vs.
COURT OF APPEALS, SHANGRI-LA PROPERTIES, INC., RUFO
B. COLAYCO, ALFREDO C. RAMOS, MAXIMO G. LICAUCO III
and BENJAMIN C. RAMOS, respondents.
ROMERO, J.:
Barely two days later or on July 14, 1993, petitioner filed with the
Regional Trial Court of Pasig a complaint for collection of the balance
due under the construction agreement. Named defendants therein
were SPI and members of its board of directors namely, Alfredo C.
Ramos, Rufo B. Calayco, Antonio B. Olbes, Gerardo O. Lanuza, Jr.,
Maximo G. Licauco III and Benjamin C. Ramos.
3. Contract Document.
The lower court then ruled that, assuming that the arbitration clause
was valid and binding, still, it was "too late in the day for defendants
to invoke arbitration." It quoted the following provision of the
arbitration clause:
Notice of the demand for arbitration of a dispute shall be
filed in writing with the other party to the contract and a
copy filed with the Project Manager. The demand for
arbitration shall be made within a reasonable time after
the dispute has arisen and attempts to settle amicably
have failed; in no case, however, shall the demand he
made be later than the time of final payment except as
otherwise expressly stipulated in the contract.
Against the above backdrop, the lower court found that per the May
30, 1991 agreement, the project was to be completed by October 31,
1991. Thereafter, the contractor would pay P80,000 for each day of
delay counted from November 1, 1991 with "liquified (sic) damages
up to a maximum of 5% of the total contract price."
The lower court also found that after the project was completed in
accordance with the agreement that contained a provision on
"progress payment billing," SPI "took possession and started
operations thereof by opening the same to the public in November,
1991." SPI, having failed to pay for the works, petitioner billed SPI in
the total amount of P110,883,101.52, contained in a demand letter
sent by it to SPI on February 17, 1993. Instead of paying the amount
demanded, SPI set up its own claim of P220,000,000.00 and
scheduled a conference on that claim for July 12, 1993. The
conference took place but it proved futile.
The lower court denied SPI's motion for reconsideration for lack of
merit and directed it and the other defendants to file their responsive
pleading or answer within fifteen (15) days from notice.
Hence, this petition before this Court. Petitioner assigns the following
errors:
A
THE COURT OF APPEALS ERRED IN ISSUING THE
EXTRAORDINARY WRIT OF CERTIORARIALTHOUGH
THE REMEDY OF APPEAL WAS AVAILABLE TO
RESPONDENTS.
On the first assigned error, petitioner contends that the Order of the
lower court denying the motion to suspend proceedings "is a
resolution of an incident on the merits." As such, upon the
continuation of the proceedings, the lower court would appreciate the
evidence adduced in their totality and thereafter render a decision on
the merits that may or may not sustain the existence of an arbitration
clause. A decision containing a finding that the contract has no
arbitration clause can then be elevated to a higher court "in an
ordinary appeal" where an adequate remedy could be obtained.
Hence, to petitioner, the Court of Appeals should have dismissed the
petition for certioraribecause the remedy of appeal would still be
available to private respondents at the proper time.7
The rule that the special civil action of certiorari may not be invoked
as a substitute for the remedy of appeal is succinctly reiterated
in Ongsitco v. Court of Appeals8 as follows:
. . . . Countless times in the past, this Court has held that
"where appeal is the proper remedy, certiorariwill not lie."
The writs of certiorari and prohibition are remedies to
correct lack or excess of jurisdiction or grave abuse of
discretion equivalent to lack of jurisdiction committed by a
lower court. "Where the proper remedy is appeal, the
action for certiorari will not be entertained. . . . Certiorari is
not a remedy for errors of judgment. Errors of judgment
are correctible by appeal, errors of jurisdiction are
reviewable by certiorari."
The Court has likewise ruled that "certiorari will not be issued to cure
errors in proceedings or correct erroneous conclusions of law or fact.
As long as a court acts within its jurisdiction, any alleged errors
committed in the exercise of its jurisdiction will amount to nothing
more than errors of judgment which are reviewable by timely appeal
and not by a special civil action of certiorari."9
This is not exactly so in the instant case. While this Court does not
deny the eventual jurisdiction of the lower court over the controversy,
the issue posed basically is whether the lower court prematurely
assumed jurisdiction over it. If the lower court indeed prematurely
assumed jurisdiction over the case, then it becomes an error of
jurisdiction which is a proper subject of a petition for certiorari before
the Court of Appeals. And if the lower court does not have jurisdiction
over the controversy, then any decision or order it may render may be
annulled and set aside by the appellate court.
In the same vein, this Court holds that the question of the
existence of the arbitration clause in the contract between
petitioner and private respondents is a legal issue that must be
determined in this petition for review on certiorari.
The Court finds that, upon a scrutiny of the records of this case,
these requisites were complied with in the contract in question.
The Articles of Agreement, which incorporates all the other
contracts and agreements between the parties, was signed by
representatives of both parties and duly notarized. The failure of
the private respondent's representative to initial the "Conditions
of Contract" would therefor not affect compliance with the
formal requirements for arbitration agreements because that
particular portion of the covenants between the parties was
included by reference in the Articles of Agreement.
Petitioner's contention that there was no arbitration clause
because the contract incorporating said provision is part of a
"hodge-podge" document, is therefore untenable. A contract
need not be contained in a single writing. It may be collected
from several different writings which do not conflict with each
other and which, when connected, show the parties, subject
matter, terms and consideration, as in contracts entered into by
correspondence. 13 A contract may be encompassed in several
instruments even though every instrument is not signed by the
parties, since it is sufficient if the unsigned instruments are
clearly identified or referred to and made part of the signed
instrument or instruments. Similarly, a written agreement of
which there are two copies, one signed by each of the parties, is
binding on both to the same extent as though there had been
only one copy of the agreement and both had signed it. 14
This Court likewise does not find that the Court of Appeals erred
in ruling that private respondents were not in default in invoking
the provisions of the arbitration clause which states that "(t)he
demand for arbitration shall be made within a reasonable time
after the dispute has arisen and attempts to settle amicably had
failed." Under the factual milieu, private respondent SPI should
have paid its liabilities tinder the contract in accordance with its
terms. However, misunderstandings appeared to have cropped
up between the parties ostensibly brought about by either delay
in the completion of the construction work or by force majeure
or the fire that partially gutted the project. The almost two-year
delay in paying its liabilities may not therefore be wholly
ascribed to private respondent SPI.
In this connection, it bears stressing that the lower court has not
lost its jurisdiction over the case. Section 7 of Republic Act No.
876 provides that proceedings therein have only been stayed.
After the special proceeding of arbitration 16 has been pursued
and completed, then the lower court may confirm the
award 17made by the arbitrator.
It should be noted that in this jurisdiction, arbitration has been
held valid and constitutional. Even before the approval on June
19, 1953 of Republic Act No. 876, this Court has countenanced
the settlement of disputes through arbitration. 18 Republic Act
No. 876 was adopted to supplement the New Civil Code's
provisions on arbitration. 19 Its potentials as one of the
alternative dispute resolution methods that are now rightfully
vaunted as "the wave of the future" in international relations, is
recognized worldwide. To brush aside a contractual agreement
calling for arbitration in case of disagreement between the
parties would therefore be a step backward.
SO ORDERED.