Академический Документы
Профессиональный Документы
Культура Документы
BPD 31003
CONSTRUCTION
COST
ESTIMATION
Ts. Dr. Norliana Sarpin
norliana@uthm.edu.my
CONCRETE WORK
+
CONCRETE WORKS
+
CONTENT
1. Introduction
2. Materials
3. Methods of Mixing
4. Price Factors
5. Site Transportation & Placing
6. Sub-contractors’ Responsibilities
7. In-situ Concrete
8. Production Method
+
CONTENT
9. Concrete Mixture
10. Calculation : Examples 1 & 2
11. Formwork
12. Calculation : Examples 3
13. References
+
INTRODUCTION
a) Materials
b) Method of mixing
c) Site transportation & placing
+
Materials
a) Portland Cement
50kg/bag.
The density varies between 1250kg/m 3 & 1420 kg/m3.
Allowance of 1 hour should be included for unloading
& placing in storage.
+ Materials
1. Ordinary Portland Cement delivered to site in bags per
1000kg
Material:
Cement = RM18.00/bag & 1 bag = 50kg
1000kg/50kg = 20 bag
20 bag x RM18.00 per bag = RM360.00
Labour:
Unskilled labour = RM40.00/day & 1 day = 8hr
Assume: 1000kg cement require 1 labour for
1 hour
RM40.00 x 1 hour / 8 hour = RM 5.00
Total price per tonne = RM365.00
+ Materials
b) Sand
Sold in tonne / m3.
The density may be taken as 1600kg/m3
c)Coarse Aggregate
Sold in tonne / m3.
The density may be taken as 1400kg/m3 vary
according to the particular material & moisture content
d) Water
Water requirement for concrete will be covered in
project overheads.
+
Materials
a) Hand mixing
For very small quantities.
Average output to mix the concrete is 2.0 hours/m3.
Labour output for hoisting & placing of concrete by
hand.
+ Methods of Mixing
Labour output for hoisting & placing of concrete by hand
c) Ready-mix
Quotation given would be used & placing allowed for
in addition.
+
Price Factors
Clarification:
1:2:4 – 20mm means:
1 = cement volume (m 3)
2 = sand volume (m 3)
4 = aggregate volume (m 3)
20mm = size of aggregate (diameter)
+
Example 1: In-situ Concrete
Find cost per m 3 for:
Concrete Grade 15 (1:3:6) in footing per m3 (using a 10/7 runner,
continuously). A 10/7 mixer takes 10 m3 of dry materials and
produces 7 m3 of concrete per mix. Working continuously at the rate
of 16.25 mixes per hour, this produces approximately 3.25m3 of
mixed concrete in an hour.
Assumptions:
Cost of mixer (rental) = RM 130.00 per day
Cost of diesel for mixer = RM 24.00 per day
Cost of lubricator for mixer = RM 11.20 per day
Labour wages = RM 40.00 per day
No. of labour = 6 persons (2 fillers, 2 wheelers, 2
spreaders)
+
Example 1: In-situ Concrete
Cost of Ordinary Portland Cement (50kg) = RM 18.00 per bag
Cost of unloading = RM 1.00 per bag
Cost of sand = RM 120.00 per tonne
Cost of coarse aggregate = RM 150.00 per tonne
Density of Ordinary Portland Cement = 1420kg/m 3
Density of sand = 1600kg/m 3
Density of coarse aggregate = 1400kg/m 3
Consolidation and wastage = 50%
Profit and overhead = 10%
8 hour working per day
+ Example 1: In-situ Concrete
RM RM RM/
m3
Material Cost
(a) 1 m3 Ordinary Portland Cement
Cement per tonne = 1000kg = (1000kg/50kg) = 20
bags
1 tonne cement = (RM18.00 per bag x 20 bags) = 360.00
Unloading = (RM1.00 per bag x 20 bags) = 20.00
Total cement price per tonne = 380.00
(b) 3 m3 Sand
1 m3 sand 1600kg/m3 at RM120.00 per tonne
= [(3m3 x 1600kg) / 1000kg ] x RM120.00/tonne = 576.00
Labour Cost
6 labourer at RM40.00 per day:
= 6 labourer x (RM40.00 / 8 hour)
= RM30.00 per hour
Assumptions:
Cost of 7/5 diesel concrete mixer (rental) = RM 150.00 per day
(inclusive diesel)
Labour wages = RM 40.00 per day
No. of labour = 6 persons (2 fillers, 2
wheelers, 2 spreaders)
+
Example 2: In-situ Concrete
(b) 2 m3 Sand
1 m3 sand 1600kg/m3 at RM120.00 per tonne
= [(2m3 x 1600kg/m3) / 1000kg ] x RM120.00/tonne = 384.00
Labour Cost
6 labourer at RM40.00 per day:
= 2 fillers + 2 wheelers +2 spreaders
= 6 labourer x (RM40.00 / 8 hour)
= RM30.00 per hour
FORMWORK
+
Formwork
For thick floors and for vibrated work, increase the labour
constants by 20%
+
Example 3: Formwork
Question:
Find the unit rate per m2 for:
Formwork to horizontal soffit of suspended floor slab not
exceeding 3.50m high.
Assumptions:
12mm thick plywood = RM 15.00 per m2
Timber per tonne = RM 900.00 (1.40m3)
Usage of formwork to floor soffit = 6 times uses
Timber in support required per m2 of floor soffit = 0.06m3
Cost per m3 of timber in support = RM 450.00
Allow for mould oil, nails and bolts per use per m2 = 15%
Wastage for materials per use = 10%
+
Example 3: Formwork
Assumptions (Cont’):
Carpenter preparing and erecting of floor soffit per m2 = 1.00 hour
Labour dismantling and keeping of floor soffit per m2 = 0.75 hour
Wages of Carpenter = RM 60.00 per day
Wages of General worker 8 hours working per day = RM 40.00 per day
Profit and Overhead = 10%
+
Example 3: Formwork
RM RM RM/m2
Material Cost
(a)12mm thick plywood = 15.00
(b)Timber in support per m2 = (0.06m3 x RM900.00 / = 38.57
1.40 per m3)
Cost of timber based on 6 uses = 53.57
Therefore, 1 use = (RM53.57 / 6 times) = 8.93
Thank you
norliana@uthm.edu.my
+
NEXT LECTURE
Brick Works
+
Example 4: Formwork
Question:
Formwork to horizontal suspended beam size 300mm x
600mm x 10m long. It will take 1 carpenter, assisted by 2
labours about 22.50 hours to erect and dismantle of 1
member of this formwork to beam. Find:
a)The unit rate per m2
b)Cost per number of suspended beam
+ Example 4: Formwork
Assumptions:
Usage of formwork to sides and soffit of beam = 4 times uses
12mm Thick plywood = RM 15.00 per m2
Strutting timber required per m2 = 0.05 m3
Cost per m3 of strutting timber in support = RM 450.00
Allow for nails and bolts per use per m2 = 0.20kg at RM4.50 per kg
Allow for mould oil per use per m2 = RM 0.30
Wastage for materials per use = 10%
Wages of labourer = Carpenter at RM 60.00day,
General worker at RM 40.00/
day
Working hour per day
= 8 hours
Profit and Overhead
= 10%
+
Example 4: Formwork
a) Cost per m2
RM RM
Material Cost RM/m2
(a) 1 m2 of 12mm thick plywood = 15.00
(b) Timber in support per m2 = (0.05m3 x = 22.50
RM450.00/m3)
Cost of timber per m2 based on 4 uses = 37.50
RM RM RM/m2
b) Find cost per no. of suspended beam