Вы находитесь на странице: 1из 142

117_prelims.

qxd 28/11/03 9:43 Page I

Renewable Energies series


117_prelims.qxd 28/11/03 9:43 Page III

UNESCO TOOLKIT OF LEARNING AND TEACHING MATERIALS

Solar Photovoltaic
Project Development

Herbert A. Wade

UNESCO PUBLISHING
117_prelims.qxd 28/11/03 9:43 Page IV

In the same series:


Geothermal energy
Solar detoxification
Solar photovoltaic systems: technical training manual

The designations employed and the presentation of material


throughout this publication do not imply the expression of any
opinion whatsoever on the part of UNESCO concerning the legal
status of any country, territory, city or area or of its authorities,
or concerning the delimitation of its frontiers or boundaries.

The author is responsible for the choice and the presentation of the
facts contained in this book and for the opinions expressed therein,
which are not necessarily those of UNESCO and do not commit the
Organization.

Published in 2003 by the United Nations Educational,


Scientific and Cultural Organization
7, place de Fontenoy F-75352 Paris 07 SP
Typeset by S R Nova Pvt. Ltd., Bangalore, India
Printed by Jouve

ISBN 92-3-103903-2
© UNESCO 2003
All rights reserved
Printed in France
117_prelims.qxd 28/11/03 9:43 Page V

Preface

Developing countries face an overall situation of limited introduction of PV household systems is the need for
energy resources and applications, particularly in rural suitable financial support systems. If the need for such
areas, and there is an urgent need to address this loan or rental arrangements is not recognized and
situation. Limited energy resources and applications pose addressed, the users will undoubtedly face additional
a serious constraint and barrier to social and economic burdens. Other forms of renewable energy also require
development, and present significant challenges and promotion as part of an overall approach to energy
opportunities for renewable energy. Renewable energy sustainability and poverty reduction. These include
sources include biomass, solar energy, wind and biomass stoves, ovens and related applications,
hydropower. Many of these energy sources have been solar drying, water heating, wind and hydropower — the
used for millennia — the sun and wind in drying and other form of energy chosen depending on the local situation.
direct or ‘passive’ applications, while biomass has been Measures to address the problems of global warming
the ‘active’ staple energy source since our ancestors and sea-level rise and promote sustainable development
discovered fire. Moreover, water and wind power have have been strongly advocated since the Earth Summit
been used as energy sources since the earliest driven in Rio in 1992, and have cited the development,
machinery. Most recently, the use of solar power in innovation and utilization of renewable energy
photovoltaic systems has become synonymous with technologies as an effective means of addressing these
renewable energy at the smaller household level. problems. There have been widespread calls for the
Renewable energy is also synonymous with sustainable reduction of greenhouse gas emissions, highlighting
development and has been linked, more recently, the importance of domestic actions and the benefits of
with poverty reduction. While the use of renewable encouraging renewable energy and energy efficiency.
energy is the epitome of sustainability, whether and to This was again a focus of the World Summit on Sustainable
what extent such applications will reduce poverty is a Development in Johannesburg in 2002, with renewable
more complex question. Solar PV systems are most energy forming a component of the WEHAB agenda.
applicable in rural and remote areas that have no access The challenge is to translate high-level political
to electricity grids — places that are often the habitats of commitments into concrete activities that are of benefit to
poor people in developing countries. But PV systems are the world as a whole. Fifty years from now,
very expensive for these people, who also have other few will doubt the important role that renewable energy
priorities such as water, housing and education. Although plays in sustainable development. The challenge is
there are undoubted benefits, a crucial issue in the how to move towards this future. This toolkit, consisting of
117_prelims.qxd 28/11/03 9:43 Page VI

vi Preface

two companion volumes — Solar Photovoltaic Systems: about, and Akio Suzuki, for the development of the
Technical Training Manual and Solar Photovoltaic UNESCO Renewable Energies series.
Project Development, will help us to move in this direction
in the field of household PV systems. Walter Erdelen
I would particularly like to thank Herbert Wade for the Assistant Director-General for the Natural Sciences
development of the toolkit. I would also like to thank my UNESCO
colleague, Tony Marjoram, for his role in bringing this
117_prelims.qxd 28/11/03 9:43 Page VII

Contents

Foreword xiii

Acknowledgements xv

Chapter 1 Development 1
Introduction 1
Development as change 1
Defining development 1
Requirements for economic development 1
Perceived value of development at international level 2
Perceived value of development at community level 2
Development and electrification policy 3

Chapter 2 Project design for photovoltaic electrification 5


Introduction 5
Pre-electrification or electrification 6
Assessing the needs of users 6
Economic assessment of projects 7
Technical design of installations 7
Choice of equipment 8
Installing PV systems 8
Maintenance organization and user education 9
Conclusion 10
Summary 10
117_prelims.qxd 28/11/03 9:43 Page VIII

viii Contents

Chapter 3 Rural electrification for developing countries 11


Introduction 11
Rural economic development considerations 11
Advantages of rural electrification in economic development 12
Rural electrification and development policy 13
Non-technical problems in rural electrification in developing countries 15
Organizing for rural electrification 16
Determining the mode of electrification 16
Basic criteria for rural electrification 16

Chapter 4 Development of rural electrification policy 19


Basic policy concepts 19
Basic requirements of a national rural electrification policy 20
Policy layers and policy stability 20
Developing policy 21
Bringing it all together 22
Policy considerations 23
Summary 26

Chapter 5 Basics of rural electrification project design 29


Introduction 29
Project quality 29
Determining goals 29
Goals and terms for rural electrification projects 30
Project goals 31
Project design 32
Determining available resources 32
Detailed design 33
Summary of project design basics 34

Chapter 6 User needs assessment through site surveys 35


Surveys as project design tools 35
Pre-survey data collection and analysis 35
Selecting surveyors 36
117_prelims.qxd 28/11/03 9:43 Page IX

Contents ix

Selecting units to be surveyed 37


Survey questions 38
Who supervises? 39
What questions are asked? 40
Analysing the results 42
Project decisions based on user surveys 44
Summary 44

Chapter 7 Forecasting rural demand for electricity 45


Importance of accurate forecasts of demand 45
Methods of forecasting demand 45
Your forecast will never be 100% accurate 47

Chapter 8 Project organization 49


The task 49
Skills required 49
Creating an effective organizational structure 50
Creating the organization 51
Changing the organization as the project develops 51
Institutional organization for rural electrification 54
Conclusions 56

Chapter 9 Obtaining and using consultants 57


What are consultants? 57
Why hire consultants? 57
Establishing consultancy specifications 58
Locating suitable consultants 58
Evaluating consultant responses 59
How do consultants set their fees? 60
How much do you pay? 60
Negotiating with consultants 61
When do you pay? 61
Working with consultants 62
117_prelims.qxd 28/11/03 9:43 Page X

x Contents

Chapter 10 Economic and financial analysis 63


Economic versus financial analysis 63
Absolute versus relative analysis 64
Financial analysis overview 65
Life cycle cost 67
Procedure for life cycle cost analysis 68
Analysis for decision-making 69
Sensitivity analysis 71

Chapter 11 Determining the best type of rural electricity system 73


The technology decision 73
Centralized power versus individual solar power systems 75
Disadvantages of individual solar PV systems over central power 77
Determining the mode of electrification 78
Fitting photovoltaics into rural electrification policy 79
Barriers to individual system implementation 79
Conclusions on solar power for rural electrification 81

Chapter 12 Funding for projects 83


External funding is usually needed 83
Sources of funds 83
Arranging combinations of funding 86
Finding the available funding agencies 88
Fitting the project proposal to the funding source 88
Funding agencies want to give money 89
Help in locating funding 89
Summary and conclusions 90
117_prelims.qxd 28/11/03 9:43 Page XI

Contents xi

Chapter 13 Preparation and submission of a proposal 91


Understand the approval process 91
Obtain pre-approval as much as possible 91
Appearance is important 91
Weight does not count 92
Contents of proposal 92
Who do you submit the proposal to? 93
Learn from successes and failures 93

Chapter 14 Technical design processes 95


Introduction 95
When is technical design done? 95
Who does the technical design? 95
Technical design cost 96
Technical design criteria 97
The completed design 97

Chapter 15 Budgeting 99
Why budget? 99
What to budget 99
Using budgets in project management 101

Chapter 16 Specifying and purchasing equipment 103


Direct purchase 103
Agency purchase 104
Competitive tendering 105
Open tender 106
Successful tendering 106
The tender process 106
Evaluating tenders 109
Who does the evaluation? 110
Making the final selection 111
Good tender evaluations follow good tender specifications 111
117_prelims.qxd 28/11/03 9:43 Page XII

xii Contents

Chapter 17 Keeping a PV project operating 113


What is maintenance? 113
Records 113
Preventive maintenance for solar electricity systems 114
Maintenance functions 114
Repairs 115
Checklist of maintenance activities 115
Summary 115

Chapter 18 Spare parts systems 117


Spare parts requirements 117
Obtaining historical data 118
Security 119

Chapter 19 Special considerations for solar utilities 121


What is a solar utility? 121
Service not solar 121
Sales versus rental (RESCO) 121
RESCO structure 123
Characteristics of a RESCO 124
Advantages of RESCO structure 124
Disadvantages of RESCO structure 125

Chapter 20 Solar utility management 127


Introduction 127
Comparing sales and RESCO approaches 127
Technical and customer monitoring 128
Life cycle cost, not first cost, should determine design 129
Fee collection 131
Customer records 134
Company records 136
Operations management 138
117_prelims.qxd 28/11/03 9:43 Page XIII

Foreword

A variety of smaller-scale solar and renewable energy resources. Solar photovoltaic home systems, mainly for
technology applications were developed and promoted in household lighting, are a particular area of interest.
the 1970s and 1980s. These include solar photovoltaic Many challenges, constraints and barriers remain,
systems for lighting, battery charging, refrigeration, however, to the use of renewable energy and promotion
communications and water pumping. Direct or ‘passive’ of associated technologies. These include awareness-
solar applications included water heating, crop drying raising, advocacy, information, communication,
and solar architecture. Wind, used over generations for management, maintenance and the development of
water pumping and power, was applied to electricity human and institutional resources. Policy and planning
generation. Hydropower was also developed at frameworks and instruments are required to promote
micro- and mini-hydro level. Improved cooking stoves institutional awareness and innovation of renewable
and ovens enhanced the efficiency and use of biomass energy systems in the public and private sectors.
resources. More recent technological applications include Awareness-raising and advocacy are necessary to
hybrid systems, energy cogeneration, small-scale promote renewable energy to policy-makers, planners, the
distribution systems and solar desalination. general public, the private sector, schools, the media and
With few models to follow and such a variety of other potential stakeholders and interested parties.
innovative technologies and approaches, it is not Advocacy activities include the need to promote solutions
surprising that success was equally varied. There was an to constraints and barriers. Renewable energy
emphasis on technological hardware rather than the technologies are innovations and require conventional and
‘software’ of innovation, operation and management that innovative approaches for promotion and support. This
was often supply-driven rather than demand- or user- includes demonstration pilot projects and the promotion
driven. In the case of relatively expensive photovoltaic of good practice through networking and centres of
solar home systems, for example, this included the excellence. The development and provision of appropriate
problems of affordability and the ‘front-end loading’ costs payment facilities for households, entrepreneurs and small
of PV systems — and the consequent need for financial businesses are vital in promoting the use of renewable
support through small loans or rental schemes. energy systems.
Lessons were learned and improved technology and Information and communication strategies include the
management systems developed. Many developing need to use ‘conventional’ materials, information and
countries are now looking to expand and enhance the use communication technologies (ICTs) and multimedia
of technology applications for solar and renewable energy approaches to serve an advocacy role in both promoting
117_prelims.qxd 28/11/03 9:43 Page XIV

xiv Foreword

renewable energy applications and providing learning The toolkit has comprehensive technical, educational
and teaching materials for education and training. and geographical coverage. It provides a complete course
Management and maintenance are required of in PV applications for rural electrification at three levels:
renewable energy systems in terms of monitoring and instructor, senior technician and field technician.
evaluation performance, maintenance needs and The toolkit is based on experience gained in the
durability. Maintenance and rehabilitation are required Pacific, where renewable energy was pioneered,
to promote efficiency and sustainability of existing and the islands served as a particular ‘laboratory’ for solar
renewable energy systems and the sustainability of new photovoltaics and rural electrification in the 1970s and
systems. 1980s. Pacific Island communities face particular problems
The development of human and institutional resources of small size, remoteness and isolation — by sea on
is essential to support this process, and education and smaller islands and by land on larger islands. Over 75% of
training at primary, secondary and tertiary levels are of Pacific islanders live in small, scattered communities in
particular importance to demonstrate and promote the rural areas and outer islands, and over 70% of islanders,
concept and use of renewable energy. This includes mainly those in rural areas and outer islands, have no
projects in science and technology teaching and the access to electricity. The Pacific Islands have a high
use of photovoltaic lighting and other equipment in dependency on imported hydrocarbon fuels — often the
‘solar schools’. Training in the application, installation and major import. As the islanders face threats of global
management of solar and renewable energy systems is warming and sea-level rise, it is appropriate that
also vital, as is the need for good learning and teaching recognition is given to the pioneers of renewable energy
materials in this area. in the Pacific and the small island states that have such a
The toolkit consists of two companion volumes — Solar particular interest and concern in the success of
Photovoltaic Solar Systems: Technical Training Manual renewable energy and sustainable development.
and Solar Photovoltaic Project Development. This toolkit is based on two excellent manuals of
The technical manual, in landscape format, has greater training materials produced in the 1980s by Herb Wade,
detail, text and graphics. Solar Photovoltaic Project a specialist in PV practice and applications then working
Development has no graphics and smaller font text, and with the Pacific Energy Development Programme. That
is intended more as a text for teachers both to support material has long been out of print and Herb has been
the technical training manual — making it easy to relate happy to revise and update it for wider publication and
student and teacher materials, and to discuss wider issues distribution, creating the attractive and useful toolkit we
relating to project development for solar photovoltaic see here. Herb Wade therefore deserves particular thanks
systems. and acknowledgement for the preparation and production
The overall objective of this toolkit is to provide of this toolkit, as does Gloria McConnaghy for the
comprehensive training material on the innovation, illustrations.
application, installation, operation, monitoring and Tony Marjoram
evaluation, management maintenance and rehabilitation Basic and Engineering Sciences
of PV systems as well as providing useful information for UNESCO
advocacy, awareness raising, innovation, policy and
planning.
117_prelims.qxd 28/11/03 9:43 Page XV

Acknowledgements

This text is a major revision of a 1980s teachers’ source The readability of this book is largely due to the efforts
book prepared by the author for a course sponsored by of Ms Caroline Lawrence who did a great job of translating
the South Pacific Institute for Renewable Energy in my English into the real thing and ensuring that the text is
Mahina, Tahiti, French Polynesia. The revisions are the consistent and accurate. I would also like to thank
benefit of twelve more years of PV rural electrification Mr David McDonald of UNESCO who was a genuine pleasure
experience by the author plus the expansion of that to work with in the publishing of this book.
experience to include many Asian and African projects. Particular thanks are due to Mr Tony Marjoram of
The book in its present form would therefore not be UNESCO, whose vision and support made possible the
possible without the specific support and assistance of PV revision and publication of the material.
project personnel from Bhutan,
the Cook Islands, Federated States of Micronesia, Fiji, Herbert Wade
India, Indonesia, Kiribati, Marshall Islands, Morocco, Palau, Bangkok, 2002
Papua New Guinea, the Philippines, Sri Lanka, Tahiti,
Thailand, Tonga, Tuvalu, Zambia and Zimbabwe.
Chapter-1.qxd 11/8/03 11:02 AM Page 1

Development 1 CHAPTER 1

Introduction Defining development


Rural electrification is a component of rural development. Rural development is most commonly defined in the
Several definitions of development are in common use economic sense. The goal of economic development
and one of the first considerations in designing rural programmes is basically to change economic patterns
electrification projects must be to decide what the from locally based barter and communal subsistence to
development goals are for the programme. a money-oriented economy with economic interactions
extending far beyond the local level.
Another valid definition of rural development is the
Development as change improvement of living conditions. This is usually achieved
through advances in housing, sanitation, water supply,
Development implies change. Whether the changes that health services and communications, and often referred
follow development are advantages or disadvantages to as social or quality of life development.
depends on the observer’s point of view. These two approaches to development philosophy are
Most governments consider a change to be for linked. Improving personal living conditions generally
the better if: produces conditions favourable to economic development
and economic development usually leads to an increased
· it results in better integration of the country into a cash flow in a community that is often used to improve
nation rather than just a loose conglomeration of living conditions. Programmes directed towards both
individual districts modes of development may be operating simultaneously,
· trade increases within the country with some emphasizing economic development and others
· the affected population wants the change to occur, social development.
i.e. it is politically popular
· the rate of rural migration to urban areas decreases
· the financial dependence of rural areas on urban areas
decreases
Requirements for
· social tension decreases in the affected district.
economic development
Some governments also consider a change to be an Which approach is used depends on the development
improvement if it increases Westernization, while other philosophy adopted by government and what it perceives
governments consider this a disadvantage. to be needed in rural districts. To succeed in economic
Chapter-1.qxd 11/8/03 11:02 AM Page 2

2 Solar Photovoltaic
Project Development

development, the following must be true of the Perceived value of development


development site:
at international level
· There is a production facility that can produce goods
for sale at an acceptable price. A goal of the governments of industrial nations and
· There are sufficient willing, trained people to operate developing countries is to lessen the gap in living
and administer the facility. standards that exists between the two groups of
· Local financial institutions are available so there is countries. The ‘North/South’ polarization that now exists
access to capital and easy money transactions. largely because of this development gap is recognized as
· There is a stable, long-term market for the goods that causing international stress and its reduction and ultimate
can continuously absorb the quantity produced at an elimination has resulted in such activities by the industrial
acceptable price. North nations as the Lomé series of development
· There is a stable, long-term source of raw materials agreements and the creation of numerous international
that can supply the quantity needed at an acceptable development organizations, as well as extensive
price. development plans on the part of the non-industrial
· There is transport available at a low enough price and South nations.
often enough to provide adequate access to suppliers Electrification is one of the factors in the disparity
and markets. between North and South. By making electricity available
· The project provides a profit to the community to the minimally developed rural areas of the South,
without a long-term subsidy from outside, though it national governments of developed and developing
may be reasonable to subsidize initial capitalization countries believe that there will be some closing of the
and sometimes even start-up operations. development gap.
· The project has the support of the community where Partly as a result of this international belief, rural
it is located. electrification has become a significant component of
· There is access to adequate supplies of economically developed country aid budgets and developing country
acceptable energy to operate the project. funding requests.

If any one of these factors is not present at a site,


economic development generally does not occur. Perceived value of development
Sites proposed for social development must also meet at community level
a set of criteria before success is possible:

· The proposed development project must be desired by In any social development project, the actual value of the
the recipients. project is in direct proportion to the value of the project
· The recipients must be willing and able to bear as perceived by the community. If a community really
preferably all, but at least a major portion of, the wants rural electrification, it will be much more likely to
recurring costs associated with the project. operate and maintain the system properly and pay the
· Adequate willing and trained labour must be available inevitable price for having electricity than a community
locally for operation and maintenance of project that sees electrification as a low priority. Unlike
hardware. grid-extension rural electrification, stand-alone electricity
· Adequate financial, administrative and technical systems must have the solid support of the community
support must be available. If not present within even when a national electricity agency owns, operates
the community, it must be made available from and maintains the system. Community-scale grid-based
outside. systems, such as micro-hydro or small diesel generators,
are very sensitive to the undisciplined use of high-load
Development through standard of living improvement can appliances such as electric frying pans and electric kettles.
be expected to succeed only if all these factors are Without community-wide cooperation in the use of
present. high-load appliances, system reliability suffers. In the case
Chapter-1.qxd 11/8/03 11:02 AM Page 3

Development 3

of individual home solar photovoltaic systems, community therefore not a major factor in deciding for or
discipline is also needed to ensure that systems are against development of these industries.
operated correctly and are not modified in ways that
Because electricity is a minor factor in rural economic
lower their reliability and lessen component life.
development, it is not cost-effective for government to
A reasonable measure of the genuine desire of a
allocate more than a minor amount of economic
community for rural electrification is its willingness to pay
development funding for rural electrification. A rural
for it both in terms of money and commitment in time and
electrification policy directed towards economic
effort. Rural electrification should not be considered an
development should not attempt to electrify rural areas
essential service such as sanitation and water supply, and
in the hope of attracting industry, rather the policy
should be installed only where communities provide
should be directed towards assisting industry by providing
adequate evidence of their willingness to accept significant
electricity at the industry site after the major problems of
financial and operational responsibility for the project.
raw material supply, capitalization, marketing and
transportation have been solved.
Development and
electrification policy Conclusions
The presence or absence of commercial electrical power
In designing rural electrification projects, both economic in a rural area generally has little effect on the
and socially-oriented development should be considered. economic development in that area. Providing electricity
For economic development, electrification policy should be has even been known to slow economic development of
designed to facilitate increased investment in commercial a rural community because community resources have
activity. For socially-oriented development, electrification been diverted to operating and maintaining the
programmes should aim to improve personal and community electrical system instead of being invested in productive
health and comfort through such things as better lighting, activities. While it is true that rural areas that are
food storage, entertainment, communications, education, economically developed usually have electrical power,
health services, sanitation and water supply. investigation usually shows that the presence of
commercial electrical power is usually a result of the
Role of rural electrification development and not the reason for it.
in economic development

Although electricity is often necessary for economic Role of rural electrification


development, there is no evidence that industry is in social development
attracted to rural areas simply because electricity is
available. The reasons behind this conclusion are: A summary of the relationships between social
development and rural electrification:
1) Other factors are more limiting. The relative
isolation of many rural districts is a major factor in Advantages
limiting economic development. The difficulties in 1) Electricity is desired by most rural dwellers.
obtaining supplies and transporting finished products As rural dwellers perceive electricity as an improvement
to market are far more limiting than the lack of an in the quality of life, it fills a social need.
electricity supply. 2) Gradual integration of rural areas into modern
2) Electricity is a small part of production cost. With technological systems. Rural electricity directly
the exception of some mineral-processing industries, affects individual households, bringing them into
electricity costs represent less than 10% of closer contact with modern technology. Most other
production costs for most rural industry. This means rural development is either low technology, such as
that any price differential between diesel community sanitation and water supply developments,
self-generation and commercial power usually has or high technology that only affects a specialized
little effect on the cost of production and is group of people at an industrial or government site.
Chapter-1.qxd 11/8/03 11:02 AM Page 4

4 Solar Photovoltaic
Project Development

3) Increased quality of public communications. The the community’s cash position, money must come in from
availability of rural electricity for telecommunications, outside through the sale of goods or services to urban
radio, television and video presentations can provide areas or other communities.
rural districts with more varied entertainment, better
1) Electrification may increase the migration of
national integration and improved public health and
young people to urban centres. There is a widely
safety.
believed development myth that providing electricity
4) Better-quality education. Improved home lighting for
reduces urban drift. In fact, electricity generally
study, electric lighting for school study rooms, the
increases urban drift — at least in the first few years
availability of electrically powered audiovisual
of service. In the early stages of rural development
equipment, computers, improved living conditions for
while little opportunity exists for making money in the
teachers and electrically powered office equipment to
area, young people may be sent by rural families to
support teacher efforts, can all help to achieve higher
urban areas to work for the money to pay for
standards of education in rural schools.
electrical services and appliances.
5) May encourage the return of migrants to urban
2) Other rural quality of life development may be
areas. There is reason to believe that those who have
slowed. The resources necessary for rural
migrated to urban areas for economic reasons are
electrification could often be used for other rural
more likely to ultimately return to their rural homes,
quality of life developments such as water supplies,
bringing their skills and wealth with them, when
health services, roads and sanitation.
electricity is available.
3) Increased dependence by rural areas on urban
areas. As more rural families become integrated into
Disadvantages the money economy, rural areas will become
It must always be remembered that rural electrification for increasingly dependent on urban areas for the supply
social development always reduces the amount of money of goods and services. Financial dependence is also
in a community because of the need to pay outside the increased as money is scarce in rural districts and
community for electrical service and appliances. Thus, it improvements in the rural quality of life will have to
may actually reduce the rate of economic development be largely financed by urban wealth passed down
because the loss of funds in the community will reduce the through family members living in urban areas.
funds available for capitalizing and operating productive 4) Social tensions resulting from change. The social
projects. Therefore any community selected to receive distance between young and old members of a rural
electricity should already have a substantial economic base community can be expected to markedly increase as
so that the addition of electricity does not reduce the change is demanded by the young and resisted by the
ability of the village to invest in projects that will make old. While these tensions have always existed, the
more money and allow future economic development. social change brought about by imported technology
There have been several cases in developing countries of is far greater and more easily introduced than the
electrification projects that substantially lowered the rate usual changes likely to be made in a static,
of economic development of villages because of this net subsistence-based, agrarian society. Thus the tensions
cash outflow. In one case known to the author, the village can be correspondingly greater.
ultimately abandoned the electrification because it was
bankrupting the village. For villages with little money Conclusions
available, electrification should be accompanied by projects Rural electrification offers significant social advantages
that will increase cash input to the community from and disadvantages. In general, government development
outside. Note that certain projects made possible by access goals will determine whether the advantages, which all
to electricity, such as providing films for the community, point towards increased Westernization of the economy,
organizing dances or community entertainment for a fee, or the disadvantages, which tend to be social disruptions
do not improve the community’s cash position, they only following increased Westernization, are considered the
move money around within the community. To improve most important.
Chapter-2.qxd 11/8/03 11:05 AM Page 5

Project design for


photovoltaic electrification
2CHAPTER 2

Introduction are often purchased without adequate consideration of


their integration into a system. Also, in an attempt to
Photovoltaic (PV) electrification is a relatively recent reduce first costs, components that do not have
innovation and much of the industry does not yet have adequate capacity or are of poor quality may be
extensive experience, nor is there a well-developed specified. RESCO systems need a different design
professional core of designers and installers. Most approach to systems intended for sale. Selling systems
projects have emphasized the sale of PV systems to users requires close attention to first costs so designs tend
although there is increasing use of the RESCO (system to provide the absolute minimum in component
rental, see Chapter 19) model for projects. Promoters of capability for the system to survive for the warranty
PV projects have usually been implementing such projects period, usually one year. With RESCO, the company has
for less than five years and have no long-term experience to live with the systems for the long term, so
with their designs. As a result, many projects have failed components must be selected on a life cycle basis, not
in the long term. a first cost basis.
The most frequent reasons for PV project failures are: 3) Incorrect installation. Incorrect panel placement
and orientation, incorrect wire size, poor-quality
1) Use of a design that is not appropriate to the
connections and incorrect battery placement leads to
need, resulting in poor customer satisfaction. Most
lowered reliability, shortened battery life and reduced
PV-based rural electrification projects have provided
system capacity. All installations should be checked
identical systems to all users, ignoring the desire of
before commissioning.
wealthy users to have greater service availability and
4) Inadequate arrangements for continuing
that of non-wealthy users for minimum service. The
maintenance. Without an adequate system for the
resulting poor customer satisfaction leads to
provision of spare parts, user training, PV technician
unauthorized addition of appliances, failure to pay
training and continuing financial support, long-term
user fees and lobbying for the replacement of PV
project success is impossible.
systems with another more ‘useful’ generating
technology. The RESCO model in particular needs If a PV project is to succeed, it must have a suitable
several options for users in order to meet different technical design and a suitable institutional design, it must
customer needs. be affordable and the users’ needs must be met. The
2) Incorrect component specification or selection. PV process of PV project design and implementation is one
systems are indeed systems. All components must be that, in a step-by-step fashion, determines users’ needs,
matched for the system to work properly. Components creates the technical and institutional designs, determines
Chapter-2.qxd 11/8/03 11:05 AM Page 6

6 Solar Photovoltaic
Project Development

the relative economics of the project, specifies and · High maintenance costs. The low-cost design with
purchases the necessary components and services to minimum panel capacity results in short battery life,
implement the project, and ensures that installation, lack of reliability and high maintenance cost. The
operation and system maintenance are carried out resulting poor reputation of PV as a medium for rural
correctly. electrification further lowers customer satisfaction.

Electrification
Pre-electrification or electrification
Where photovoltaic systems have been chosen to supply
Pre-electrification the needs of a rural community and there is no intention
of providing power from another source in the
In many countries, the demand for rural electrification is foreseeable future (10 years or more), pre-electrification
much greater than the ability of the electricity supply methods will not be acceptable. In this situation, the PV
system to extend the grid. Delays of five or more years systems should be designed to provide end service
are common between a request for electrical service and comparable in quality and quantity to that which would
its provision. One approach to reducing the political be provided by grid-based electricity delivery systems.
pressure from rural communities for grid extensions is to This requires individually designed systems to fit the
provide small photovoltaic systems for rural households varying requirements and ability to pay of each rural
unlikely to receive grid extensions within an acceptable user. A RESCO operation is specifically intended to be a
time. The aim is not to provide long-term electrical long-term electrification process and must be designed to
service from the solar PV systems but very basic service meet the actual needs of the customers, not just to
for five to ten years. provide minimum capacity while customers are waiting for
Because these pre-electrification solar units are a grid connection.
specifically intended to be just a temporary measure Adequate long-term maintenance requires an
with ‘real’ electrical service following a few years institutional structure that is comparable in complexity
later, they are designed as cheaply as possible with a and size to that of a grid-based electricity utility with a
‘one size fits all’ philosophy that generally only allows similar number of customers. This requires an institution
the use of one or two lights and a radio or small black that has adequate financial and personnel resources to
and white television. Minimum institutional support is maintain the systems indefinitely. It also requires
provided, with users often made responsible for competent management and a dedication to customer
maintenance. service.
Such systems may be accepted by rural customers as a
short-term solution but the limited system capacity and
low long-term reliability owing to inadequate
Assessing the needs of users
maintenance will give little satisfaction.
The systems to be installed must fulfill the desire of the
Pre-electrification projects usually cannot be logically
users for electrical service, to the extent of their
justified because:
financial capability to meet the costs involved.
· They are an inefficient use of development funds.
The funds expended on the pre-electrification projects Costs
would usually be better spent on improving market
access roads, sanitation and communications. In the case of private solar electricity, where the user
· Poor long-term customer satisfaction. Customer pays for both the initial installation and subsequent
satisfaction with the minimum electrification provided maintenance costs, system capacity is usually determined
by pre-electrification schemes is short-lived and the by the initial cost of the system. Operating and
return of pressure for grid extensions is delayed only maintenance costs are modest but tend to occur with
a few years. long periods between relatively large expenditures for
Chapter-2.qxd 11/8/03 11:05 AM Page 7

Project design for 7


photovoltaic electrification

battery replacement, making it difficult for the private developing countries is too limited to be able to afford
user to adequately budget for these expenses. solar projects that are not competitive with conventional
The most successful solar electrification projects are energy sources. The decision should be economic not
those that include some process for spreading the cost of financial, however. Financial factors must be weighed
the systems over a long period, usually through the against other factors such as:
collection of regular small amounts sufficient to cover the
· a desire for greater national energy independence
replacement of batteries and other costs of the systems.
· the reduction of continuing foreign expenditures for
The RESCO type of structure does this best. The customer
fuel
sees a predetermined, constant, acceptable cost and the
· continuity and reliability of the service supplied
variations in maintenance cost are absorbed by the
· preservation of the environment through lowered
company providing the service.
noise, lessened pollution, and improved aesthetics
· safety for the users (danger of electrocution, etc.).
Needs
A solar project may be higher in cost than a conventional
Assessing individual user needs is more important for project but nevertheless may be preferred if the
PV-based rural electrification than for grid-based systems. non-financial factors swing the balance to solar. The
This is because the PV systems are almost always individual difficulty faced in analysis is quantifying these other
systems and must be matched to each individual user’s factors as their weight varies according to the attitudes
needs. Diesel systems, local hydroelectric systems or other of the decision-making authority. It is up to the owner of
grid-delivered electrification schemes can be sized on the the project, whether private or public, to decide whether
basis of expected load for the entire community that can solar or another energy source provides the best overall
generally be estimated using load figures from comparable technical solution.
communities that have already been electrified.
The most common method for PV rural electrification
has been to install the same size of PV system on each Technical design of installations
house of an entire village or even in an entire country,
with no differentiation between the financial capability A project must be entirely conceived on paper before
and wishes of the different users. This is certainly the construction. Although it seems obvious, too many
simplest approach for project design but long-term projects have been carried out without completing
customer satisfaction suffers and such projects usually thorough designs that envision all aspects of the use of
have problems with unauthorized addition of appliances the system. This technical design leads to a complete and
and system abuse, resulting in shortened battery life and detailed technical specification that is used for purchasing
high maintenance costs for many customers. and installing the systems.
In areas more economically developed, where people Among the various errors of technical design, the
can afford and therefore desire more power-hungry following are particularly serious:
appliances such as colour televisions and videos, the size
1) Central instead of individual systems. For domestic
of the PV systems, and as a consequence the monthly
photovoltaic electrification, the temptation is great to
fee, must fit each user’s needs and ability to pay or the
design a centralized power station connected to a grid
electrification project will be considered a failure when
that connects the village homes, instead of building
compared with conventional grid supply.
individual systems for each house. A central power
station with its connecting grid is often much more
Economic assessment of projects costly, particularly if the housing is scattered. More
serious is the fact that over-consumption by a few
The second step in any solar electrification project is to users penalizes the entire community while with
assess its economic impact compared with that of other individual systems over-consumption only penalizes
generating technologies. The financial capability of the offending user.
Chapter-2.qxd 11/8/03 11:05 AM Page 8

8 Solar Photovoltaic
Project Development

2) Incorrect project sizing. Not only must the total 3) Excessive energy consumption. Some controllers
capacity of the installation fit the needs of the user require an excessive amount of energy for their own
but the various components, such as modules, operation. Such controllers reduce the amount of energy
batteries, controllers and wiring, must be correctly available to the user, which means increasing the
matched. Many sales representatives for PV systems, number of panels installed in order to meet user needs.
in an attempt to keep initial costs low, tend to
The appliances used with the PV system, such as lights,
recommend systems with capacities inadequate for the
televisions, pumps, etc., must also be selected for good
service required. This has been a particular problem
reliability and efficiency of operation. The appliances best
with systems including colour televisions and videos
used with PV systems are those designed to be connected
which are relatively large consumers of energy.
directly to the direct current from the system. They are
3) Inadequate battery specification. In order to save
not only as reliable as the more common ac mains
on capital cost, batteries are often undersized or of
equipment but are usually more efficient users of energy.
inadequate quality, leading to power outages and
Remember that providing high-quality and expensive
more frequent replacement of batteries with resulting
components for a PV system is a waste of money if the
higher ongoing costs.
appliances selected are not equally high in quality and
reliability. Often top-quality panels, controllers and
batteries are specified in a project but cheap, unreliable
Choice of equipment lights are fitted. The ability to use appliances is the sole
reason for installing a PV system. It makes good sense to
Even a well-engineered installation cannot function provide appliances that work efficiently and reliably.
properly with defective or unreliable components. The equipment intended for use in PV systems in the
Paradoxically, the difficulties do not arise from the tropics must have been proven through test or field
new technology, the PV modules. They are the most experience to meet technical specifications and reliability
reliable part of the system. Appliances, batteries and requirements for a difficult, hot, high-humidity,
controllers are the causes of most malfunctions. sometimes salt-laden environment. For this reason,
Batteries as delivered from manufacturers present two various organizations, such as the Florida Solar Energy
types of problem for the technical design: Center, the Asian Institute of Technology and the South
1) Lower than design capacity. Their storage capacity Pacific Institute for Renewable Energy (S.P.I.R.E.) have
in ampere-hours is almost always less than that stated conducted long-term, systematic tests of the main
by the manufacturer. components used for solar installations. This helps to
2) Their energy efficiency may be low. The energy provide the knowledge necessary to select the best
available from the battery is less than 85% of available components to ensure that installed systems will
the energy that comes from the panels. A low battery meet their design specifications.
energy efficiency may be offset only by increasing the
number of modules which is, of course, costly. Installing PV systems
Controllers can also pose problems:
An economically viable project, well designed and using
1) Poor reliability. If the controller fails, the user has a
the best available components, will still not function
tendency to bypass it and battery failures increase as
properly if the installation is poorly carried out.
there is no longer any protection against overcharge
The installation must be made in accordance with a
and excess discharge.
distinct technical specification that clearly defines the
2) Unstable operation. Controllers whose settings
process.
change over time create many system problems. Poor
Among the more common faults in installation are:
design that makes controller settings sensitive to
temperature, vibration, humidity or just ageing are not 1) Errors in positioning the solar panels. Many
unusual. installers attempt to orient the panels without
Chapter-2.qxd 11/8/03 11:05 AM Page 9

Project design for 9


photovoltaic electrification

reference to a compass and rely on their own in the system have been found to perform even the
guesswork or that of the local inhabitants for most basic preventive maintenance procedures a few
direction. Almost always, this leads to orientation months after installation. It is not a problem of
mistakes and therefore to lower power availability. inadequate training or the absence of written guidelines
The other mistake in location is inadequate for maintenance, it seems to be simply a lack of real
consideration of shade from vegetation or structures, interest. So long as the systems provide a reasonable
even from other solar modules in the same array. number of hours of light, nothing is done. By the time
2) Wiring mistakes. Reversing the polarity of a single they are no longer providing satisfactory service,
module in an array containing many modules is a problems have accumulated and battery life has been
common error that drastically reduces the power seriously shortened.
available from the array. This is a complex problem because of the interaction
3) Voltage loss due to poor connections or of economic, technical, political and social considerations.
undersized wire. The quality of the connections in a The solution is to create an organization that:
low-voltage PV system is much more important than
1) collects fees. There must be an organized system to
in 120 V or 240 V wiring. Poor connections tend to
collect regular payments from the users to cover the
cause contact heating and excessive voltage drops
operating and maintenance costs and, if required, the
that are detrimental to the performance of the
amortization of the capital and installation costs.
installation. Likewise, PV system wire sizes must be
2) provides preventive maintenance and repair. The
larger than those for ac mains use or excessive
organization must ensure, either directly or through
voltage drops result.
contracts, the periodic checking of the systems and
4) Incorrect protection and location of batteries. The
their repair when needed.
batteries should be placed in a locked, ventilated
enclosure inaccessible to children. This is important for A most important step to be taken by this organization
safety because there is some risk of accidental is to explain in clear detail what the users can expect
explosion of a battery and the acid is corrosive and from their systems and what fees will have to be paid.
dangerous. Before the system installation, the recipients should be
required to sign a contract describing their benefits and
At the time of acceptance of an installation, a
obligations. The contract should also define what the
commissioning inspection and report should be made. It
company will provide by way of services.
must be carried out according to a specific commissioning
Several types of structure are possible, using either a
procedure that gives the measurements and inspection
municipal organization or a company having a contract
steps necessary for acceptance and commissioning. This
with the community. At this point there will be no
ensures that the installation meets the technical
attempt to discuss this aspect in more detail, but its
specifications originally set out.
complexity and extreme importance is emphasized.

Maintenance organization and User education


user education
It is not necessary to give the users of a domestic solar
Organization installation extensive technical training. However, it is
important to clearly explain to them how to use the
Experience has shown that most rural domestic systems system properly, particularly the availability of power.
are not well maintained by the users and a centralized Many failures are caused by abuse of the system
maintenance system has to be organized. While it either by over-consuming energy or by carelessness.
is true that system maintenance is simple and could A permanently affixed plate should be included in the
theoretically be done by users, only a few households installation that clearly explains in the local language the
that happen to include a member with genuine interest capacity of the system and directions for its operation.
Chapter-2.qxd 11/8/03 11:05 AM Page 10

10 Solar Photovoltaic
Project Development

In particular, users should be advised of the need to technical specifications, without proper installation
conserve energy during and immediately after cloudy specifications, with equipment that has not been field
periods. tested, without meeting commissioning requirements and
Experience shows that installers rarely take the time without taking into consideration user instruction and
to provide instructions to users and as a result the later maintenance. Nevertheless, the rate of failures in
users have a tendency to tinker with the installation, even these installations is less than that of small diesel
sometimes causing serious damage. These instructions systems for community rural electrification. This is an
must be posted and explained verbally to users before indication of the basic soundness and reliability of
commissioning. photovoltaic technology and the technology is clearly
User instruction has also been found to work best a preferable for any installation where there is to be
few weeks after the installation. Giving detailed electrification of remote sites with low consumption
instructions at the time of installation does not work well requirements.
because users have no experience of the systems and When solar installations are made following the
many of the things explained will have no meaning until principles of good design and adequate follow-up
there is some practical experience. maintenance is performed, the number of satisfactory
installations and satisfied users will approach 100%.
Training of maintenance technicians
Summary
Technicians living near the installations should generally
be used for basic system maintenance. This allows Steps necessary but often ignored in carrying out
frequent, low-cost maintenance and rapid response to photovoltaic projects should include:
problems. While some complicated problems may have to
· An economic evaluation that must include
be solved by a well-trained technician external to the
non-financial factors such as energy independence,
community, the great majority of problems are easily
the reduction of continuing foreign expenditures,
solved and can be handled by a basically trained local
continuity and reliability of the service, preservation
technician. These maintenance technicians do not need to
of the environment and safety, as well as the usual
have extensive technical training, only the amount of
monetary considerations.
training necessary to maintain that specific type of
· A design phase including in particular the correct
installation.
sizing of the installation.
· Selection of the components with regard to reliability
Conclusion and energy efficiency.
· An installation phase that includes the definition of
Unfortunately we must recognize that there are very few the installation process to be followed and an
cases where all the steps described have actually been inspection upon completion.
carried out. Most solar installations have been made · Education of the users and organization of
without sufficient economic study, without adequate maintenance.
Chapter-3.qxd 11/8/03 11:07 AM Page 11

Rural electrification
for developing countries
3CHAPTER 3

Introduction rarely provides strong impetus to economic development.


For rural electrification to cause economic development,
The enormous economic success of rural electrification in all the many other factors necessary for economic
the United States is often cited to demonstrate that development must already be present. As this situation is
‘development follows electrification’. When carefully rare, rural electrification projects that have triggered
examined, the American experience actually demonstrates economic development are also rare.
that ‘electrification follows development’. In the 1920s
and 1930s, electrification was demanded by rural areas
Rural economic development
to support development already well under way. The
large US Government expenditures to capitalize rural
considerations
electrification during those years was not primarily to
One of the most basic reasons rural electrification does
provide electricity for remote areas that did not have
not by itself attract economic development is that it is
power, it was usually to provide lower-cost electricity to
but one of many factors that are necessary to a
rural communities already generating their own power
successful development project, and not even a very
using diesel engines. This was accomplished by a
important one at that.
combination of price subsidy and grid extensions from
Of the many factors that interact complexly in
efficient, large-scale power plants. While the availability
successful economic development projects, those that
of low-cost power certainly improved the profitability of
must all be present before success can be hoped
existing industries and allowed increased income for
for are:
formerly marginally profitable industries, it was and still is
a minor factor in the progress of rural economic · A stable market for the products of the project that is
development in the USA. strong enough to absorb output of the project
There is no doubt that the availability of electricity is without price depression.
an important factor in many economic development · Cost-effective and dependable transport adequate to
projects. Because it is important to development, it is meet the needs for transporting goods to market and
often perceived that the presence or absence of rural bringing items needed for production to the
electricity is a major determining factor in the rate of development site.
progress of rural economic development. In fact, · Adequate capital to fund the project and keep it going
worldwide experience has clearly demonstrated that during what is often a lengthy start-up period.
simply having electrical power available in a rural area · Sufficient skilled labour to operate the facility.
Chapter-3.qxd 11/8/03 11:07 AM Page 12

12 Solar Photovoltaic
Project Development

· A reliable supply of raw materials whose price is stable operating and maintenance costs — on the off-chance
enough not to rise as a result of increased demand by that it will attract development is usually unreasonable
the project. because of the additional cost and the uncertainty that
· A production facility that can economically produce development will in fact follow.
the items for sale.
· No requirement for long-term subsidies.
· Commitment on the part of the participating Availability of electricity at a rural site
community. usually provides little or no cost advantage
· Energy to run the project. to development projects

The only one of these factors that rural electrification It is common for the least-cost solution for rural
touches upon is energy. With so many factors that must development to have different electricity supply systems
be simultaneously present for a development project to for households and for industry and commerce. Typically,
succeed, it is poor development strategy to expend large diesel generation for the high, concentrated loads found
sums of money on general rural electrification when it is in industry and commerce combined with solar PV systems
only one aspect of development. Indeed, spending a for the low, dispersed loads of households will prove to
country’s limited development capital on broadly based be the least costly overall approach to off-grid
rural electrification reduces the capital available for electrification.
investment in other factors more important to economic Even in the case of projects located in urban areas,
development. for some countries with high generating costs, such as in
most of the smaller Pacific Island nations, there is usually
little difference in cost between project-generated power
Need for excess capacity and power purchased from the public grid (unless
to attract development subsidized by government) and it is not unusual for
hotels, industrial facilities and large commercial
Before development projects can be attracted to a rural enterprises to generate their own electricity owing to its
area by the availability of electrical power, there must be comparable cost and the often unreliable operation of
enough excess capacity available in the system for the the public supply.
development needs for at least a five-year period. When Most rural development projects are of a type that
general rural electrification is installed for social use little electricity per economic unit produced.
development, the generating equipment should have just Of existing development projects functioning profitably in
enough capacity to serve the people in the community. rural areas of developing countries, only mining devotes
If this same electrical system is intended to attract more than 15% of its operating costs to the use of
industry, then it must have enough extra capacity to electrical energy. The majority of rural economic
handle that industry as well as the community needs. development projects are agriculturally oriented and their
It is not at all unusual for a rural industry to need as energy costs are generally of the order of 5% of
much or more electricity for its operations as the entire production costs, certainly not a large enough percentage
community uses for household purposes. This means that for the difference in energy price between grid-delivered
the electricity delivery capacity installed in a rural district power and self-generation to be a major determining
with a view to attracting industry must be at least double factor in the decision to locate in a particular place.
the size of that needed just to service the households.
Where rural electrification is by means of urban grid
extensions, this is usually not a problem unless the Advantages of rural electrification
project’s energy needs are very large. However, in economic development
stand-alone electricity systems not interconnected with
an urban grid will often be necessary. For such systems, Although it is clear that the presence of electricity in
providing excess capacity — resulting in higher capital, a rural environment is not a requirement for economic
Chapter-3.qxd 11/8/03 11:07 AM Page 13

Rural electrification 13
for developing countries

development, rural areas that are electrified do have National integration


some advantages over non-electrified areas when
development finally comes. Creating a nation from many isolated communities
1) Community introduction to technology. The requires a good-quality two-way communications system
community will be accustomed to using devices whose that can be used by everyone. The national government
workings they do not really understand — a basic fact must be accessible to the rural population and the
of life in any technically oriented, i.e. developed, area population must be kept informed of matters of national
but an alien concept to most rural peoples of as well as local interest.
developing countries. At the present time, many unelectrified rural
2) Increase in technically oriented labour pool. In communities can access the national telephone system
general, the labour to be found in a community that through existing, usually solar-powered, radio-telephone
has electricity will be more familiar with technology units. Nevertheless, the majority of rural dwellers cannot
and will be quicker to become accustomed to working be said to have easy access to a national communications
with the machinery and modern tools of industry and system. Where rural electrification has occurred, almost
commerce. always a local radio-telephone installation is immediately
3) Introduction to financial systems. The periodic installed or follows shortly. This has obvious advantages
payments that are made for the electrical service and such as the ability to obtain emergency services more
the various commercial aspects of that service further rapidly, but also has the more subtle effect of closing
introduces people just emerging from a barter the gap between community and national awareness.
economy to the more complex concepts of the With electricity available, some improvement
money economy with its written contracts, the idea in personal communications may result, though in
of making money payments for having services general most households already have one or more
available rather than just payments for services battery-operated radios and electrification does not
already rendered, and many other small aspects of seem to have much effect on their number. Television,
the world of commerce not usually part of the however, is much more limited in rural areas as it requires
average developing country rural dweller’s life. more energy than is readily available from batteries
As economic development invariably includes many alone. Its increased availability could have a marked
commercial problems, this introduction through the affect on rural dwellers’ national awareness and the
commercial aspects of electrification improves nation’s system of communication. Rural electrification
villagers’ understanding of the problems and needs of by itself will not bring about a national television system
any development project. but is an essential part of any national, household-level
communication scheme.
The presence of rural electrification therefore usually
helps to prepare rural people for economic development,
Effect on migration to urban centres
but its cost cannot be justified on this basis or on its
limited advantages in economic development.
The argument that rural electrification helps to stop
people from migrating to urban areas is often made,
but no substantial evidence is available to support that
Rural electrification theory. Rather, the pattern has been for increasing levels
and development policy of development to increase rather than decrease
urbanization. The most economically and physically
Rural electrification has definite effects on rural society. developed countries of the world generally have the
Whether those effects are advantages or disadvantages highest levels of urbanization.
depends on the observer’s point of view. As the Certainly the effect of rural electrification on urban
decision-makers for development are generally drift varies from country to country and from
governments, it is their view that prevails. circumstance to circumstance. In general, however,
Chapter-3.qxd 11/8/03 11:07 AM Page 14

14 Solar Photovoltaic
Project Development

there is no hard statistical evidence that rural the dormitories and teachers’ dwellings can improve
electrification, by itself, has an impact on rural to urban students’ learning and instructor performance.
migration, but analysis of the effect of rural 4) Administrative improvements. The capability to use
electrification on the economy of isolated rural areas electrically powered office equipment, particularly
indicates that it probably tends to increase the migration copy machines and computers, can improve the quality
of young people to urban areas. The primary reason for of education by allowing the use of higher-quality
expecting this increased migration is the need for teaching materials and a wider range of educational
additional money in the electrified rural district to pay for source material.
electricity and appliances. It is common practice for rural
Unfortunately, though electrification can have the above
families to send their young people to urban areas to
beneficial effects on education, actual cases indicate that
make money to cover purchases that cannot be made
those benefits only appear where the administration
within the scope of the very limited money generated by
and teachers have the understanding, skills and
most rural communities. Though in many cases the young
particularly the desire to take advantage of the increased
people return to their rural homes when they have
educational capabilities that electricity provides. In those
earned enough for the immediate needs of their family,
schools where student test scores have risen following
they often do not.
electrification, the school staff have adapted their
On the other hand, there is reason to believe that the
teaching processes to take full advantage of electricity
presence of rural electricity increases the probability that
in improving education.
older urban dwellers will return to their ancestral home
in the rural districts later in life. Government employees
often retire in their late 40s or early 50s and move back
Effect on other development
to their community of birth. This is partly to be with the
The financial resources available to a nation for rural
family group, partly because they usually have land there
development are limited. Investment in electricity means
and partly because the small retirement income available
less investment in some other area of development.
to them goes much further in rural areas than in urban
Embarking on a massive rural electrification programme
centres. The primary disadvantage to returning is the
before the more basic health, sanitation, water supply
lower standard of living to be found in the rural
and road developments have been accomplished may
homeland and the presence or absence of electricity can
actually be detrimental to rural districts. Unless rural
be a positive factor in the decision to return.
electrification is integrated carefully into overall
development plans, any advantages that could be gained
Effect on education by electrification may not be realized owing to the lack of
other supporting development.
Electricity in rural schools can have a benefit on For electricity to be of maximum value to a community,
the quality of education in several ways. Advantages the community itself must provide the priority for
cited are: development. Forcing a community to accept electrification
1) Increased practicality of evening study. It is difficult when the community’s priorities place it below other
to obtain a high enough level of illumination for a types of development increases friction between the
study room using kerosene, even kerosene pressure community and national government that is counter to
lamps. the usual goals of development.
2) Availability of new teaching modes. Computers and
electrically powered audiovisual aids, particularly Effect on the economic development
video, can stimulate and improve education. of the community
3) Reduce student discomfort. As personal discomfort
is detrimental to learning, fans and better lighting There is a limited amount of money available in most
for classrooms and various electrical amenities in rural communities. For economic development to take
Chapter-3.qxd 11/8/03 11:07 AM Page 15

Rural electrification 15
for developing countries

place, that money has to be used to develop resources Non-technical problems in


and markets to increase the cash flow into the village.
The addition of rural electrification causes cash to flow
rural electrification in developing
away from the community and often reduces its ability to
countries
fund projects that improve cash flows into the
The technical problems of rural electrification are generally
community. Only villages that already have sufficient
well known but a number of non-technical problems
access to money to be able to pay the external costs of
have not received much attention. Some of the more
electrification — the operating fees and the purchase
important of these are:
of appliances — can be electrified without compromising
their ability to develop projects that bring more money 1) The cost of rural electrification is unknown. In very
into the community. few cases has the real cost of rural electrification
projects been recorded. As a result it is very difficult
to budget for rural electrification. Policy must be
Social tensions resulting flexible enough to allow for actual costs that are
from rural electrification significantly different from those projected initially.
2) Political pressures can be strong to electrify
Any change affecting a community introduces tensions certain areas or in certain ways. Rural electrification
and electrification is no exception. In most agrarian, policy should create a process for electrification as
subsistence-based economies, the political power resides independent of the political system as possible.
in a group of elders. Change is usually considered a Probably more solar projects have failed through
threat by older people and pressure for change usually political meddling than through any other cause.
comes from the younger members of the community. Forcing projects on recipients that do not have an
In the case of a technological development such as internal priority for electrification, or providing
electrification, the gap between young and old is even unrealistic, unsustainable subsidies, are two major
greater and the tensions more acute. political errors commonly found — both of which
Electrification of a community can create a technical ultimately lead to project failure.
hierarchy in parallel with the traditional one. This 3) Donor policies. Funding agencies often work outside
new hierarchy is based on technical training rather than country policy constraints and sometimes propose
on the experience gained by age. Often the youngest certain projects or certain technologies for rural
adult members of the community are the best trained electrification that may not be locally appropriate.
and stand highest in this technical hierarchy. Unless this Governments should not automatically accept funding
new hierarchy is well integrated into the traditional agency projects but should carefully evaluate them for
hierarchy, tensions can become so great that the social and technical appropriateness before approval.
electrical system may be abandoned rather than allow 4) Inadequate inter-agency linking. Government should
the community to become strongly polarized. This has create links between rural development agencies and
happened in several solar projects. The high rate of the rural electricity organization or an energy
failure of community operated rural electrification is authority to ensure interaction.
mainly due to inadequate training of operation and 5) The cost of rural electrification cannot be controlled
maintenance personnel but also can be the result of locally. Electrification costs can be too dependent on
the unwillingness of a community to accept the social foreign technology and foreign currency fluctuations.
changes and stresses that result from electrification. Wherever it is practical, locally available fuels, materials
For rural electrification to be a success, the technical and labour should be involved in rural electrification.
hierarchy that develops within the community must 6) Once electricity subsidies are put into effect, it is
clearly be subservient to the traditional leadership and very difficult to eliminate them. Subsidies should be
the traditional leadership of a community must genuinely limited to initial capitalization or contractually limited
be willing to accept the resulting social changes. in term at the time of inception. No subsidies should
Chapter-3.qxd 11/8/03 11:07 AM Page 16

16 Solar Photovoltaic
Project Development

be instituted for operating and maintenance costs of operating the stand-alone system should be weighed
systems installed for social development purposes, against the installation and maintenance cost of
and those for economic development should be for a extending the grid. Government subsidy will be
limited period only. involved in either task, as it is rarely possible for the
rural village itself to afford the investment necessary
to initially bring electricity to the community.
Organizing for rural electrification In addition, the source of funds must be considered.
Money may be readily available for grid extensions
While urban-based electricity authorities have successfully
but not for stand-alone power plants, or vice versa.
carried out the grid-extension type of rural electrification
2) The impact of adding this village on the ability of
in a number of countries, in most places urban electricity
the electricity supply agencies to provide service
authorities are not properly equipped, either
to existing customers. If the urban system is at the
administratively or technically, to deal with the large
limit of its capacity, adding more load through grid
number of small-scale power plants required for
extensions is not appropriate. If the rural electricity
remote-area rural electrification where grid interconnects
authority is having severe problems keeping its
are not practical. A separate organization specializing in
present inventory of power plants running, adding
stand-alone system rural electrification is therefore
another one to the system is unwise.
needed. In most cases, the off-grid rural electricity
3) The preference of the village involved. Although it
authority should consider contracting private organizations
probably should not be binding, the preference of the
for the support of remote electricity systems.
village should always be sought and, if this preference
The policy evolved for rural electrification in a country
cannot be allowed, a clear explanation of the reasons
must therefore deal with two interconnected but
for the government decision should be given.
separate electricity authorities — the urban authority with
4) The electrical load structure of the village. A large
its urban grid extensions to rural areas, and the rural
village with several commercial establishments or an
authority with its off-grid, stand-alone power plants.
industry likely to have significant electrical load would
A single government department should have both
usually be better served by a grid extension; while for
electricity authorities under its policy control. It is not
a small village with a small load that is mainly evening
appropriate, for example, to have a Rural Development
lighting, a stand-alone plant may be the better choice.
Ministry in charge of rural electrification and an Energy
Department in charge of urban electricity matters.
Basic criteria for rural electrification
Determining the mode
of electrification For national electrification to provide the maximum
development benefits with the minimum of initial cost
In those countries with many villages that can be and upkeep expense, rural electrification projects should
electrified either by stand-alone systems or by urban grid be designed in such a way that the operating costs of the
extensions, there must be a mechanism to determine electricity supply can be borne by the recipients, thereby
which electricity authority should provide services. Often requiring no ongoing subsidy.
the decision as to which form of electrification prevails is
one of chance and opportunity seized by competing
Capital subsidies, not continuing
grid-based and stand-alone-based electricity authorities.
operating subsidies
This should not be the case. The decision should be made
Capital costs occur once and can largely be borne by
by the government department overseeing the two
donor-country participation or soft loans. Operating
electricity authorities and should be based on a balanced
expenses continue indefinitely and can rarely be financed
consideration of several factors:
with aid or soft loans. For heavily urbanized countries, a
1) Relative life cycle cost of grid extension versus continuing subsidy for rural electricity may be economically
stand-alone generation. The cost of installing and acceptable as the strong urban economy can support
Chapter-3.qxd 11/8/03 11:07 AM Page 17

Rural electrification 17
for developing countries

a small rural subsidy for electricity. In most developing central stock of parts, transport to the remote site is
countries the majority of the population is in rural areas often slow. For rural electrification to meet the desired
so it may be possible to subsidize a few rural electrification social and economic development goals, the power must
projects, but the country’s urban population cannot be reliable. Long periods without power waiting for spare
reasonably subsidize the operating costs of a national rural parts can destroy the profitability of businesses
electrification programme. depending on that power and reduce the social value of
In the case of rural electrification for social rural electrification.
development, the people using the electricity should pay To meet these criteria, the rural electrification
for all operating costs (fuel, repairs, maintenance labour, programme should be designed around simple, standard
etc.). Where rural electrification is for economic generating modules as much as possible. Keeping an
development, the development project should be capable inventory of spare parts for a wide variety of different
of bearing the electricity system operating costs without generating systems is very costly. In general, photovoltaic
subsidy. Though a subsidy during the early years of power systems require the smallest spare parts inventory
operation may be appropriate, subsidies lasting longer while diesel systems require the largest.
than five years should not be required.
The best electricity system for a rural village would be
Services should meet the long-term
one with minimum operating costs. A diesel system may
requirements of users
have the lowest initial cost but the long-term cost can be
much higher than hydro, solar or biomass-fuelled power
Services initially provided must meet the immediate
systems.
needs and expectations of the rural population with the
capability of being expanded easily and at reasonable
Maintenance should be carried out locally incremental cost to meet increased power requirements
as development proceeds. If rural electricity installations
Day-to-day maintenance and operation of power systems do not meet the minimum expectations of the
must be the responsibility of local people with basic community, they will not be effective tools for either
technical training. A central pool of trained maintenance social or economic development. Neither will
staff located in a city can only service a few isolated rural installations that have little capacity for expansion to
electrification projects at high cost. The rural pool of meet increased needs. Many attempts at PV-based rural
well-trained electrical and mechanical maintenance electrification have provided only very basic lighting
technicians is small and its growth is slow. Either an with no provision for adding capacity to operate videos,
expensive, large-scale, long-term, technical training refrigerators or other electrical appliances. As time
programme must be included in a rural electrification passes and expectations change, these minimal systems
programme or the electrification scheme must allow for become inadequate and communities apply strong
maintenance by people with only basic training. pressure to change to other, more costly generating
Technically oriented development projects will often schemes in order to provide more services. Had the
include staff with the technical and management skills photovoltaic programme been designed with load
necessary to correctly operate and maintain a relatively growth in mind, the increased needs could have been
complex power-generating system. On the other hand, fully met at much lower cost than by conversion to
electricity systems for social development must be diesel or other more expensive generation. However,
capable of administration, maintenance and repair by it is not appropriate to initially oversize rural electrical
basically trained people. systems to allow for long-term load growth. Oversized
systems have higher initial costs, lower operating
Spare parts must be readily available efficiency and generally higher maintenance costs. It is
much better to provide systems that can be upgraded at
The availability of spare parts can be a major problem for modest incremental cost, with those costs mainly being
remote power system maintenance. Even with a large borne by the individuals requiring increased services.
chapter-4.qxd 11/8/03 11:08 AM Page 19

Development of rural
electrification policy
4CHAPTER 4

Basic policy concepts different technicians is an administrative mess and a


great waste of money and trained labour.
For there to be a direction to rural electrification, some
overall guidelines or policy must be established. Without Policy implementation
a policy backdrop, rural electrification becomes haphazard
and arbitrary. For any policy to be useful, it must be followed. This
means that the people who are expected to use the
Policy levels policy must know that the policy exists, be able to
interpret it as intended, and follow it.
Every level of government establishes policy. The Energy Knowledge. Rural electrification projects have been
Department may have a rural electrification policy and conceived, designed, funding located and carried to the
the Public Works Department may also have its own rural brink of implementation before the discovery is made
electrification policy. It is generally true that such that they are ‘against policy’. Besides being a waste of
departmental, or lower-level, policies apply only to effort, such cases demonstrate a breakdown of the most
that department. Thus in the case of rural electrification, basic rule of policy implementation: those affected by a
different policies may be established by the policy must be aware of its existence and content.
Energy Department, Public Works Department, Clarity. Even when a policy is known to exist, it may
Marine Department, Telecommunications Department, be vague, not quite applicable to the project in question
Health Department, Education Department, Rural or, worse, a policy that is unwritten and based on
Development Department and any other government precedents or discussions with high-ranking officials. Such
office that may require electricity at a rural facility informal ‘policies’ do not provide the stable guidelines
operated by that department. needed for long-term rural electrification development
For rural electrification to be manageable on any but and usually result in conditions not much better than
the smallest scale, it is important to establish a national, having a multitude of departmental policies. Such policies
rather than departmental, rural electrification policy that violate the rules that policies must be written, well
provides a common set of guidelines for the development defined and specific enough to keep interpretation within
of rural electrification for all departments. To have many reasonable limits.
solar installations in remote communities, each of which Enforcement. Even when a policy is clearly defined
is conceived differently, uses different equipment, has and widely published, projects that do not conform
different standards for installation and is serviced by can proceed if no one enforces the policy. For example,
chapter-4.qxd 11/8/03 11:08 AM Page 20

20 Solar Photovoltaic
Project Development

a policy that places all rural electrification responsibility that help to define the policy and limit its application to
with the Public Works Department will fail if the what is desired.
department ignores its responsibility and no one forces Policy example for a Pacific Island country: ‘Rural
its implementation. So the third rule of policy-making is electrification on all communities excepting the Capital
that policies must be enforced. There must be some Island is the responsibility of a Rural Electrification
agency with responsibility for enforcement, with Authority established under the Department of Energy
authority from the highest levels of government to carry who will provide specific guidelines to the authority for
out that task. implementation. All operational costs and at least 20% of
capital costs will be borne by recipients of electrical
Basic requirements of a national services provided by the Rural Electrification Authority.
Electrification will be carried out as requested by
rural electrification policy communities on a community-by-community basis as
resources become available. Should more communities
To be useful, a rural electrification policy must:
request electrification than there are available resources,
· fit the needs and capabilities of the country communities will be placed on a waiting list in the order
· be specific enough to keep projects within of receipt of 20% of the estimated capital cost of their
predetermined limits electrification project.’
· be general enough to allow for changing conditions The specifics in this sample policy are:
and differing needs in different parts of the country
· who is responsible: Rural Electrification Authority
· have the support of a high enough level in
· who has enforcement supervision: Department of
government to ensure enforcement.
Energy
· financing: at least 20% of capital and 100% of
Fitting the needs and capabilities operational costs come from the recipients with the
of the country rest inferred to come from outside sources
· who gets electrified: all rural communities not on the
Rural electrification policy must be in agreement with Capital Island may request electrification and if all
national development goals. The policy must provide for who apply cannot be serviced immediately, a waiting
the needs of the rural districts and their development list of communities in the order of their deposit of the
goals. The policy must be capable of implementation with 20% capital requirement will be established.
the trained labour and financial resources that are
available to the country. A beautifully designed policy General enough to meet changing
that cannot be carried out with the resources available conditions and different needs
is useless. in different parts of the country
‘All rural villages will be electrified within the next five
years’ would be a policy that probably violates both the Too restrictive a policy can be as unworkable as one that
rules of need and capability. Not all rural villages need or is too general. For example, it would be too restrictive for
want rural electrification and it would be impossible to a rural electrification policy in most countries to specify
find enough technicians or enough money to carry out the generating technology to be used. In some locations
such a massive project in such a short time. small hydro will be best, in others solar, in yet others
diesel. Thus a policy that restricts rural electrification
Specific enough to keep projects to diesel generation would usually not be a good one.
within limits
Policy layers and policy stability
Establishing who is responsible for carrying out the
policy, who enforces it, its geographical limits and how In practice, rural electrification policy is developed in
projects are to be financed are some of the specifications layers with national policy the topmost and each
chapter-4.qxd 11/8/03 11:08 AM Page 21

Development of rural 21
electrification policy

successive layer of authority below the national level One common approach to this rule is the use of a
having an increasingly detailed policy for its increasingly policy development committee with representatives from
narrow range of activities. each of the affected parties. This rarely works for policy
Each layer of policy has authority over all lower levels. development though committees do provide a good
Thus the national policy sets the limits of all other forum for airing the expectations of the represented
levels of policy. A ministry policy sets the limits of groups prior to policy development. A committee of
department policy that in turn sets the limits of divisional this type is most useful in the final stages of policy
policy and so on down the hierarchy of authority. development where it provides some assurance that
Proceeding down the hierarchy, each level has a each of the groups understands and agrees to the
narrower, more detailed range of activity than the one policy. During the actual development stage, however,
above. The policy to govern the actions at each level a committee is unworkable except possibly as a sounding
likewise becomes more detailed on the way down. For board for ideas.
example, the national policy may be that users pay the If progress is to be made, policy development must be
operating cost of their facility; ministerial policy then may handled by a single person or by a group of no more
be that each consumer of electricity pays according to than three. A larger group may serve to monitor the
the wattage of the appliances in use and, within that progress of policy development but when asked to do the
guideline, the departmental policy may be that for each actual development, larger groups invariably get bogged
kilowatt demand of installed appliances the consumer down in interpersonal disputes and seemingly insoluble
must pay US$30 per month. problems involving minute details, making progress slow
The more detailed the policy, the more likely it is that and the results, if any, generally weak and ineffective.
it will have to be changed due to changing conditions.
For this reason, we expect lower-level detailed policies to Policy development inputs
be frequently updated while top-level national policies
should remain intact for decades if they are to be Although it is possible to develop a comprehensive rural
effective for long-term development. electrification policy with little input beyond the
experience and capabilities of the people carrying out the
development, that approach will rarely provide the best
Developing policy results. The developers should seek information from a
number of sources and integrate it into their process of
Who develops policy? policy development. For rural electrification policy
development some useful inputs are:
As a policy is of no value unless implemented, and · National development goals and plans. What form
implementation depends on the cooperation of all of development is acceptable? What priority should
affected by the policy, it is very important that policy rural electrification have at the present stage of
development takes place in full view of all those who will national development?
be involved in its implementation. It will do no good to · Prior policies and precedents. Though there may not
establish policy that states that the urban electricity have been a national rural electrification policy,
agency will do all rural electrification if the management undoubtedly some rural electrification has taken place.
of that agency is not willing to take on the task. They What has been its governing policy? Have any
will find every possible excuse to limit their rural precedents been set that provide a good model? Have
electrification activity and even sabotage projects so that any precedents been set that must be specifically
they can say ‘it cannot be done’. rejected?
· Other affecting policies. There may be other
An important rule of policy development: government policies that will affect rural electrification
Involve all who will be affected by a policy in
and limit what can be achieved. For example, it may
the process of policy development.
be a policy of the national government to leave the
chapter-4.qxd 11/8/03 11:08 AM Page 22

22 Solar Photovoltaic
Project Development

final decision for rural development to local understanding of national development goals and of
governments. Such a policy would have to be included the road to reach these goals. While this ideal is
in a rural electrification policy. not always reached, they can still provide a lot of
· Using policies enacted by other countries. useful information about development projects, rural
The direct use of rural electrification policies development in general and national development
developed for other countries is unwise, but good goals.
ideas can be gleaned and problem areas illuminated · Surveys. As a method of determining attitudes and
by close examination of other countries’ experience predicting what people will do regarding rural
with rural electrification. electrification, surveys have not been very useful. As a
· The experience of other rural development method of learning what people actually are doing,
projects. By examining the problems and successes of they seem to work well. It is difficult for people who
other rural development projects, potential problems have never had electricity to predict what they will do
and solutions may become evident. If a particular type with it. On the other hand, surveys can tell reasonably
of problem, for example the collection of money from accurately what people are now using for lighting and
rural recipients, has occurred in other projects then electricity in the rural districts and this information is
the same problem will probably occur with rural useful as a predictor of minimum use.
electrification. If a rural project has proven particularly
successful, the design that led to its success may also Bringing it all together
fit rural electrification.
· Prior government and consultancy reports. In most Gathering the data and creating a rational, well-designed
countries, interest in rural electrification has existed rural electrification policy is a long and difficult task but
for a long time and often a search through piles of even when that is complete, the process of policy
old reports will yield useful information for policy development is far from over.
development, always adjusting for the age of the No matter how logically developed a policy may be, it
reports and the assumptions under which they were must fit the often illogical and hostile environment of
prepared. the real world. Powerful people or agencies can either
· New consultant and international agency reports. destroy or render ineffective the best policy man can
For a task as large in scope as rural electrification, devise. To be useful, a policy must have more powerful
funding for consultancies, either private or public, may supporters than detractors. In reality, for a policy to be
be available. Though outside consultants rarely have successful, everyone affected must grant at least
sufficient understanding of the rural situation in a grudging approval to the policy and not actively fight its
developing country to actually design a workable application.
policy, these consultants can often highlight problems Therefore, once the developers have produced what
and solutions that are overlooked by people without they feel is the best possible policy, then it has to
the breadth of international experience they can bring undergo the scrutiny of those it will affect and
to bear. negotiation take place with those parties at odds with
· Political and civic leaders. As rural electrification has the policy concepts. As modifications to suit one party
a direct effect on the majority of a nation’s population may make another party unhappy, this process is long,
and an indirect effect on the rest, everyone seems to involved and will require a great deal of diplomacy and
have an opinion on how it should take place. Informal tactful editing of the policy itself. The policy committee
talks with leaders from both rural and urban areas will referred to earlier can be a useful forum for this process,
help the policy developers to understand what people though it will be necessary to conduct much of the work
want in the rural districts and what the urban districts informally.
(where the money actually comes from) will support. If the final product is judged workable and has the
· Planning departments. Ideally, national planning support of the important groups that it affects, it is time
departments have the best knowledge and to place it on the table for written ratification at the
chapter-4.qxd 11/8/03 11:08 AM Page 23

Development of rural 23
electrification policy

highest level consistent with its purpose. If it is a national of government to provide subsidies should be linked
policy, it should be ratified by the senior executive to the willingness of the commercial enterprise to use
committee of government, often called the Cabinet. If it electricity efficiently. The fact that government is
is a ministerial policy, the minister should ratify it, a making lower-cost power available should not result
department policy should be ratified by the department in waste of power by the project. To receive a
head, and so on. subsidy, the project should be required to follow
energy-conservation guidelines provided by the rural
electricity authority.
Policy considerations Each site at which industrial development is
proposed will have different requirements for
Although policy must always be designed to fit the needs electrification and the policy should be flexible enough
of a particular set of conditions and a general policy to be of assistance in all cases.
cannot be designed to fit all circumstances, the following 2) Use flexible power systems for industrial and
are specific and general concepts that should be commercial development projects. High capital cost
considered in establishing a policy for rural electrification: power-generating facilities such as solar, hydro or
steam power are not recommended for new,
Policy concepts for rural electrification stand-alone industrial-development type electrification
with emphasis on economic development projects. They are recommended, if cost-effective,
only for industries with a history of five or more
1) Provision for development assistance for a specific years of successful operation.
term. The policy would allow the provision, where Experience with rural commercial and industrial
needed, of assistance in the development of an development has shown that projections for
electrical power-generating facility, and up to five long-term electricity needs are rarely accurate.
years of subsidy to offset some of the cost of local Furthermore, the failure rate for rural development
electricity production, for a rural industry that has projects is high. The installation of hydro, solar or
met the basic criteria for rural industrial development other high capital cost electricity-generating systems
of: adequate capitalization, labour, raw material is not recommended in the initial stages of an
supply, access to markets and transportation. The economic development project. It is more
amount and type of assistance should be determined cost-effective to subsidize the extra operating cost
on a site-by-site basis. of a diesel plant for the early years of operation of
Although electrical availability and cost is a factor the rural industry than to invest in a high-cost
in the profitability of rural industry, it is generally a generating facility that will probably prove to be the
minor factor except in the mining industry. Assistance wrong size or will not be needed at all because the
by government in development of electrical generation venture fails. Diesel plants are relatively low in cost,
at an industrial site should be viewed in the same vein can be moved to another site if a venture fails,
as short-term tax relief: a method of improving and changing the size of a diesel generating facility
profitability to increase the viability of the business is not difficult or prohibitively expensive. On the
during the difficult first years of its operation. It may other hand, hydro or steam-generating systems are
be reasonable to provide short-term assistance in the inflexible as to size and cannot usually be
development of an electricity supply as an added economically moved to another site.
incentive to commercial development, but long-term The effective life of a diesel facility is of the order
survival of the business is not closely linked to of 10 years and it is appropriate that as soon as a
electricity prices. Therefore government should not new industrial facility is operational, plans should
take on the long-term burden of a continuing be made for converting the diesel generating facility
electricity supply subsidy agreement as there will be to one that has a lower operating cost or uses
little benefit to overall development. The willingness indigenous fuel but that no actual installations should
chapter-4.qxd 11/8/03 11:08 AM Page 24

24 Solar Photovoltaic
Project Development

be made until the industrial venture has stabilized and subsidy each of the last two years. This phasing
realistic electricity use projections can be made. process reduces the fiscal shock of a sudden loss of
Though advantages may be obtained by combining subsidy and provides incentives for the gradual
electrification for a rural commercial project and improvement of plant facilities to more efficient
nearby rural homes, serious problems may arise: energy use.
4) Provide technical assistance for development. Rural
· If the commercial venture fails, either the difficult
electrification policy should include a provision for
political decision will have to be made to no longer
technical evaluation services and technical assistance
provide electrical power to the homes previously
to development projects to ensure that the project is
serviced, or the difficult financial decision of
designed for the most efficient use of electricity.
continuing to provide electricity from a plant much
Because electricity is not a major cost of
too large to efficiently provide power for the small
production for most rural development projects,
domestic load.
developers pay little attention to the need for
· If the commercial venture is very successful,
efficient energy use. If government is to subsidize the
increasing its load faster than expected, either the
power plant installation and up to five years of power
difficult political decision will have to be made to
production costs, the government energy agency
disconnect the domestic users thus freeing up
should take part in the project design at the earliest
capacity for the commercial venture, or the costly
possible stage to examine the energy needs of the
financial decision to immediately increase the
proposed facility and offer alternatives to
generating capacity of the plant just to service
the proposed design if they would result in the
low-profitability domestic loads.
more efficient use of energy.
Where possible, it is recommended that domestic The technical assistance should extend to preparing
users should not be integrated into a commercially operational guidelines for energy conservation
based rural electrical system until the commercial measures to ensure minimal waste of electrical power.
entity has stabilized to the point where accurate Subsidies for electricity production should be tied to
projections of energy use can be made. the project’s willingness to follow these energy
3) Limited subsidy life. It is recommended that any conservation guidelines and the correct operation and
subsidy towards the actual cost of electricity delivered maintenance of the generating equipment.
to a rural industrial facility should be for no more than 5) Ownership should not be local. Generating
five years and that the amount of subsidy should not equipment and associated wiring for the distribution
result in the cost of electricity to the user being lower of power should be owned by the rural electricity
than that paid by a similar industry in an urban area authority, not locally. The basic assumption underlying
of the country. this policy is that the majority, if not all, the capital
The goal of rural economic development policy for installation of rural generating equipment is from
should be to establish efficient, stable, economically public funds and public ownership can therefore be
sound businesses in rural areas. While it is reasonable to justified. If users or user groups such as village
provide incentives for the establishment of such cooperatives are given ownership of the generating
businesses, there is no indication that long-term equipment it will be impossible to control abuse of
subsidies for electrical power are effective in keeping the equipment or maintenance costs. If the generating
industry in a rural location. There is strong evidence that equipment is to be locally owned, then the only
long-term electrical power subsidies tend to encourage acceptable approach for maintenance is for the local
an increase in energy use without a commensurate owners to also be fully responsible. Experience shows
increase in productivity, resulting in a waste of energy clearly that this is rarely successful and the public
and of the government money used to subsidize power. funds used for the project are wasted.
It is recommended that power subsidies should be This policy is consistent with normal practice for
subjected to a gradual phasing out with a 33% cut in urban electrical systems where the electricity agency
chapter-4.qxd 11/8/03 11:08 AM Page 25

Development of rural 25
electrification policy

owns and maintains all generating and wiring This is not often practical, however, and service cost is
components up to the point of entry to the user’s site. applied in accordance with other demand factors such
as the size of appliances in service and their energy
Policy concepts for rural electrification requirements. In the case of individual home power
with emphasis on social development systems, such as solar PV systems, charges based on
the system capacity are appropriate.
1) Subsidies for the capitalization of domestic-type It is important that fees should be collected on
rural electrification projects should be provided as behalf of the rural electricity authority rather than the
required but the operating cost should not be village. Experience has clearly shown that funds
subsidized. A typical PV-based village electrification collected by a village for power use are rarely used for
project is to provide lighting power for 50 to maintenance of the generating systems. Pressure on
100 houses clustered in a small village. The cost of the village treasurer to make the collected funds
providing this service may exceed US$1,000 per house. available for other, more immediately urgent,
Most rural families do not have access to that much purposes appears to be overwhelming. In none of the
money. On the other hand, money is usually already many cases known to the author has a village fund
being spent on lighting, generally around US$5 per that was established specifically for maintaining the
month with many households spending over US$20 on electrical power system lasted longer than six months
lighting fuel and lantern maintenance, and considerably without having been diverted to other village uses.
more on dry cells for radios and torches. Fees collected should go to the authority or its agent
It is reasonable to provide a major capital subsidy and not be kept by the village, though actual
for the initial installation though there should still be collection by village administration may be
investment by the recipient to the greatest extent appropriate.
possible. It is recommended that no less than 20% of The authority must enforce payment by users
the total capital investment should be provided by the through service disconnection or other punitive
recipient village. This local investment increases the means. If the authority does not enforce payment,
capability of the country to provide electricity to experience clearly shows that payment will never be
more people but, more importantly, ensures that received from many users with the short-term result
recipients feel they have an investment in the system being heavy, unintentional subsidization of rural
and therefore some responsibility to see that it is electrification. The long-term result is an overall
correctly used. degeneration of rural electrification services as the
2) Periodic fees based on services rendered should be recurring costs are too high to be borne by the
collected. A system for collection that includes an authority.
authority outside the community should be provided. 3) Domestic-type rural electrification should be
Though capital funding in the form of grants and community oriented and should have community
soft loans may be readily available to governments, it involvement in system design, financing and
is difficult to obtain funding to cover recurrent costs maintenance. Electrification projects have the best
from outside sources. As there is an existing cost to success rate in communities that see electricity as a
villagers for energy in the form of kerosene or priority. Therefore, electrification should be provided
benzine fuel, it is reasonable to charge at least a only to those communities that clearly express a desire
comparable amount for the electrical service that for it and show that desire through payment of part of
eliminated the need for lanterns and their fuel. The the capital investment in the system.
total cost of operation and maintenance of the village The rural electricity authority should visit the site
electrical system should be borne by the village. and meet with villagers several times to ensure that a
Furthermore, the individual family cost should be full understanding is reached by both parties
assessed in direct accordance with the amount of concerning the requirements of the villagers for
services received. Ideally, power should be metered. service, the size of the system to be installed and the
chapter-4.qxd 11/8/03 11:08 AM Page 26

26 Solar Photovoltaic
Project Development

specific responsibilities of the authority and the up to the limit of the source or, in the case of a large
village in installation, maintenance and administration water source, up to twice the initial village load.
of the project. Again, the extra cost of increased pipe size is small
4) Continuing training programmes for system compared with the cost of replacement and system
installation and maintenance should be a part of efficiency is somewhat improved with the larger pipe.
rural electrification projects. Because it is impossible On the other hand, it is bad practice to install
to efficiently operate and maintain a large number of oversized diesel-generating equipment as fuel
small-scale rural electrification projects from a central efficiency is poor on a lightly loaded diesel and
location, a relatively large number of people from the maintenance costs higher per unit of power delivered.
rural districts will have to be trained in the installation, Oversizing turbines in a hydro plant also results in
operation, maintenance and repair of the systems. lowered efficiency of generation and is not
A training facility specifically to meet that need economically appropriate.
should be included as an integral part of a rural Biomass-fuelled steam-generating systems are
electrification effort. The facility should be controlled particularly inflexible and increasing their operating
by the rural electricity authority though it is reasonable capacity generally means adding another complete
for it to be part of an existing instructional institution. unit. Incremental increases in capacity are not usually
Training should also be provided to rural users of practical. For this reason, steam plants are best suited
electricity. That training should be designed to help to projects that have reached load maturity and
individuals understand what the electricity system can significant load growth is thus unlikely.
do and what it cannot. Users should be shown how to Individual solar photovoltaic systems are the most
make the best use of their appliances and how to get flexible power producers for changing load conditions.
the longest life from their system. Instruction in the Adding or subtracting panels and batteries is simple
safe use of electricity is also important. and no more costly per unit of power than the original
5) System design should allow for load growth installation.
through a cost-effective system expansion 6) Generating equipment and any associated wiring
process, not by initial oversizing. Although electrical for the distribution of power should be owned by
load growth in most rural districts has been much the rural electricity authority, not locally. The basic
lower than that of urban customers owing to the assumption is that the majority if not all the capital
limited money available for appliance purchase and fee for installation of rural generating equipment is from
payments, there is strong evidence that as more public funds and public ownership can therefore be
money becomes available in rural areas load growth justified. If users or user groups such as village
does occur. Therefore, rural electricity systems should cooperatives are given ownership of the generating
be designed to allow increased generating capacity equipment it will be impossible to control abuse of
that can provide power unit costs comparable to that the equipment or maintenance costs. If the generating
of the original installation. equipment is to be locally owned, then the only
In grid-reticulated systems, it is generally good acceptable approach for maintenance is for the local
practice to install distribution wiring of a size large owners to also be fully responsible. Experience shows
enough to handle at least double the initial village clearly that this is rarely successful and the public
needs. The extra cost of increased wire size is very funds used for the project are wasted.
small compared with the cost of wire replacement,
particularly if an underground reticulation system is
installed. The larger wire size also slightly increases
Summary
the efficiency of the power distribution system at the
The steps in producing a policy are as follows:
original, lighter loads.
In a small hydro system, it may be appropriate to · Establish a dialogue with the affected parties to
install a large enough penstock to permit water flows understand their positions, needs and restrictions.
chapter-4.qxd 11/8/03 11:08 AM Page 27

Development of rural 27
electrification policy

· Gather as much background data at home and abroad type of installation and the importance of electricity
as possible. to profitability of the project. A requirement for
· Draft the best policy you can. minimizing power waste through energy-conservation
· Negotiate the terms of the policy with those affected measures as directed by the supervising department
until the policy is acceptable to all parties. should be tied intimately to these subsidies.
· Have the policy ratified and proclaimed at the highest · Electrification for social development should have no
level consistent with its nature. subsidy for operation and only a partial subsidy for
· Enforce it. installation.
· The authority, not the user, should own the
To summarize the main concepts that are desirable in a
generating equipment and all wiring. The appliances
rural electrification policy:
using the electricity should be the responsibility of
· There should be provision for an independent rural the user, though they may be financed by the
electricity authority specializing in off-grid authority.
electrification that may share technical and physical · All those associated with administration, fee collection
resources with the urban electricity authority but has or system maintenance should be full employees of
separate administration and funding. The authority the rural electricity authority. A village cooperative
should be set up in such a way that it can seek may be set up to finance electrification but should not
finance from aid agencies or international provide administration or technical services.
development banks with minimum interaction with · The policy should state and the authority should
other government agencies or departments. enforce disciplinary measures against users that violate
· The same department that makes policy for rural their agreement to pay periodic fees or in some way
electrification should make policy for urban modify the system to its operational detriment.
electrification and should supervise both rural and · Community leaders, in the case of social development
urban authorities. electrification, or project management, in the case of
· The rural electricity authority should specialize in economic development projects, should be involved in
independent village-scale or individual-scale systems, all stages of system selection, design, financing and
while the urban authority should specialize in installation.
multi-village grid-delivered power systems. The · The technology used for rural electrification should
supervising department should decide which authority not be fixed but should vary according to the needs of
has jurisdiction in a service area. the user and the characteristics of the site.
· Electrification for economic development should be Technology selection should emphasize recurring
tied to specific economic development projects. costs, not initial cost. Different selection criteria
Subsidies for capitalization and plant operation during should be used for economic development and social
the early years should be made available based on the development electrification.
Chapter-5.qxd 11/8/03 11:09 AM Page 29

Basics of rural electrification


project design
5CHAPTER 5

Introduction designer must ask some questions:


1) How well does the project fit into established
The term ‘project design’ is very broad in scope and government policy for rural development? If not
covers everything that must be determined before a very well, does it go against any established
project can proceed. This includes establishing what government policy? ‘Good’ projects do not go against
the project is intended to accomplish, locating funding, established policy.
locating people to carry out the project, preparing the 2) Who are the most important participants and will
technical design, specifying and ordering materials, the project fit their idea of what a good project
organizing the project, scheduling, budgeting, auditing should be? Remember that the recipient of the
and management. The process of designing a project project is always one of the most important
can be broken into three subprocesses: (1) goal participants. In all cases, the attitude of the recipient
determination; (2) determination of resources available; can make or break a project. ‘Good’ projects meet the
and (3) detailed design of the project. requirements of the important participants.
3) Will the form of the project establish a precedent
that may prove to be a problem in the future? For
Project quality example, rural electrification ‘demonstrations’ where
power is provided with heavy subsidies may make it
We are all familiar with the terms ‘good project’ and politically impossible to develop or finance full-scale
‘bad project’ but it is not so easy when it comes to rural electrification without continuing the expensive
deciding what determines whether a project is good or subsidies. Thus the demonstration effectively destroys
bad. Every project has many different participants. the very concept it was intended to demonstrate.
Virtually everyone has some interest in a rural ‘Good’ projects will not create a long-term burden for
electrification project and can be considered a any of the important participants.
participant. Each participant will have a goal in mind for
the project and criteria of success or failure. A project Determining goals
may be considered bad by one participant and good
by another. Where do goals come from?
For the rural energy project designer to develop a
‘good’ project, there have to be some common criteria All projects inherently include some goal. The goal of the
for what is good and bad. To help decide, the project will be a major determinant of its form and the
Chapter-5.qxd 11/8/03 11:09 AM Page 30

30 Solar Photovoltaic
Project Development

design of the project is the direct result of its goal as set a video in a rural village community centre is ‘to increase
by the designer. The project designer may never actually the level of social interaction and to improve the quality
define a project goal but a project cannot come into of life in the village’. This goal is sufficiently worthy,
existence without the designer having some end result in idealistic and vague to satisfy all parties to the project
mind. Vague and formless goals often result in vague and but no one can design an actual project around this goal
formless projects, so it is important that the first step in because it is impossible to determine whether or not it
project design should be the formal determination of has been achieved until long after the project is
a project goal. completed. So many other factors enter into ‘quality of
Rarely, however, can the designer of a project decide on life’ and ‘social interaction’ that no reliable measurement
the goal of a project without responding to pressures from of goal achievement is possible. The most basic and
others whose idea of the appropriate goal for the project important characteristic that a design goal must have
may be very different. For example, in a project intended to is the possibility of immediate measured achievement.
provide some solar electrical services to a rural community, When the project is complete, we have to be able to
the goal of the aid agency providing the funds may be to say whether the goal has actually been reached or not.
have a highly visible, easily accessible project that can be a While some of the real design goals of a project may
showplace for their country’s products and for the aid seem crass, base or venal, they must still be determined if a
agency’s efforts. The goal of the politicians involved may be good design is to result. If the very real and immediate goal
to fulfill campaign promises to supply electricity to rural of a project is to finally silence a persistent parliamentarian
districts. The goal of the planning office may be to make who has been after your department for years to put a
another step towards completion of their five-year plan. solar-powered water pump in his home village, you as
The goal of the community receiving the project may be to project designer had better have that as an unwritten but
be as modern as the neighbouring village that already has definite goal for the project design. If you are competent,
electric lights. The goal of the implementing office may you will also strive to make the project fit into overall
be to do something reasonably useful with the money development policy and attempt to make it as useful as
offered by the aid agency while keeping the politicians, the possible to the recipients, but you must not forget that the
planning office and the recipients happy. All these goals are basic goal is to please the insistent parliamentarian.
reasonable and in fact all may be achieved in the course of
a project. Indeed, one valid measure of the success of a Goal testing
development project is how many of the different groups
that have some interest in it are happy with the results. The true test of project design goals are whether the
It is up to the project designer to recognize the larger goals can be met and, if so, whether you will know it in
set of interacting goals of all the direct and indirect time for the knowledge to be useful. Goals that cannot
participants in the project and to create a well be achieved are not a useful basis for project design.
defined — and achievable — set of goals that is the best Goals that are so vague that no one can tell whether or
overall compromise. not they have been achieved are equally useless for
project design. Goals that take more than five years to be
achieved are rarely useful for project design purposes.
Immediate design goals versus long-term
development goals
Goals and terms for rural
The goals we are talking about here are the real ones electrification projects
that directly affect how the project is carried out. It is
common to have vague and idealistic goals set out in What are the goals of those involved
project documents but to have rather different real goals in the project?
in mind when the project is designed and carried out.
For example, the project document may state that the Every group of people involved in a rural electrification
goal of a project that places electric lights and power for project has its own goals for the project. These can
Chapter-5.qxd 11/8/03 11:09 AM Page 31

Basics of rural electrification 31


project design

generally be categorized into four main classes: · a project that will look good to the home office
· recipients · a better way to spend the allocated project money
· funding agency than other projects proposed.
· elected government Elected government (politicians):
· civil service.
· sets no precedents for future projects that cannot be
These four classes rarely have the same goals. The main supported in the long term
task of the designer is to assign project goals that are · no recurring expenses that will be a future burden on
acceptable to the recipients, the funding agency, the government
politicians and the bureaucracy. · fulfills political promises or policy declarations
· provides a project for a district that has been ignored
Determining the goals of each group in the past
· provides a project for a district that is the home
It often seems like an exercise in mind reading to district of an important politician
determine the real goals for each of the four participant · will not be criticized by the electorate.
classes. Virtually everyone will say one thing but mean
Civil service (bureaucracy):
another. It is the job of the project designer to learn
what is really required. · can be easily administered with available resources
Each class has a set of goals, not a single goal, that · fits the plans developed by the bureaucracy for rural
the project is expected to achieve. Some of the goals are development
more important than others and the less important ones · does not conflict with other activities of the
may be ignored. It can safely be assumed that all groups bureaucracy
really do have as a goal the improvement of the life and · establishes no unacceptable precedents
wealth of the rural people receiving the project, but this · has a clear beginning and ending, with no
may not be the most important goal for some of the long-term, vague responsibility attached
groups. · has a reasonable chance of success.
In every situation, the different needs of the groups
This is a representative, if not exhaustive, list of goals.
lead to different project goals. Some of the likely goals
For each project the goals will change as attitudes and
for the different groups are:
resources change. What is important to the project
Recipients: designer is to know that a diverse set of goals must be
merged into the project if it is to receive the support of
· better lighting for night work
these four important groups. Without the support of each
· better lighting for children’s school work
of these groups, the project may go ahead if pressures
· less cash outlay through savings in kerosene and dry
are strong enough, but its long-term success is unlikely.
batteries
· a feeling of pride
· employment for villagers
· training for villagers Project goals
· access to television and video entertainment.
1) Design using your own goals. The first step is to
Funding agency:
roughly design the project to meet your goals.
· a high-visibility project to demonstrate that their Then examine this project design objectively, relating
money is doing something the project to what you believe to be the goals
· easy access of the recipients, funding agency, politicians and
· a project that tests new equipment in the field bureaucracy. Where your goals are in clear conflict
· a showplace for the products of a donor country in with what you believe to be the goals of the other
the hope that future sales will be generated groups, attempt to find a compromise that is
Chapter-5.qxd 11/8/03 11:09 AM Page 32

32 Solar Photovoltaic
Project Development

acceptable to you and you believe will be acceptable requirements correctly and that the compromise you have
to the others. worked out is acceptable to all parties.
2) Refine using your perception of others’ goals. These informal negotiations may require considerable
Once you have finished the above exercise, you should time and effort but the result is a project document that
have a draft project design that, if your estimate of has a reasonable guarantee of passing through the
the reactions of the other project participants is approval processes with minimal difficulty and delay. The
correct, will probably be approved. overall time required is usually far less than trying to
3) ‘Test fly’ the draft. Discuss the project with members salvage a formally submitted project document that has
of each of the four groups whom you feel to be been rejected or has become stalled on the desk of
important to the final approval of the project. If they someone who dislikes the project but is unwilling to come
clearly approve of your design, then you can right out and kill it.
reasonably assume that you have understood what
they require from the project and have met those
requirements with your draft design. Project design
It is likely, however, that you will find resistance to some The initial project document that is submitted for
of the terms of the project in one or more of your approval by government and funding agencies should
discussions. This means that your project draft has not have only sufficient detail to make it possible to estimate
met one or more of the goals that particular person results and costs. The detailed technical design and
considers important. Determining the real problem can operating budgets of time, money and labour are usually
require some detective work. A politician is not likely to prepared after the general project concept is approved.
admit the project is unsatisfactory because it is making a While it is possible to complete a detailed design before
rival politician look good. Sometimes you can simply ask approval is sought, the initial design will rarely be
‘well, what changes do you think I should make?’ and at accepted and in the process of negotiations with funding
least determine which aspect of the project is causing agencies, government officials and recipients so
the difficulty. Once that is understood then a series of many changes will be made in the concept that the
‘would it be acceptable if …’ questions can usually be implementation details will need complete revamping.
asked until a compromise is found. The approval of a project concept carries with it the
This first round is best handled verbally, not by written approval of the use of a certain amount of resources to
submissions. If you formally submit your draft for written carry out the project. However, just because approval is
comment, you are placed in the position of submitting granted does not always mean that the resources
what may be an unacceptable project, thereby starting approved for use are actually available. Before creating a
the approval process off on the wrong foot. First detailed project design the limits of the resources
informally iron out the major problems before submitting available to implement the project must therefore be
a formal draft for comment. In an informal discussion you clearly established.
have the opportunity to explain the reasons for particular
aspects of the project that you may not have made clear
in the written draft. Though your draft may seem Determining available resources
perfectly clear to you, it may not be to other people less
familiar with the ideas you wish to communicate. This first All projects require resources to accomplish. The three
verbal session helps to point out parts of your draft that basic resources are money, labour and time. Generally
are not clear and could be a source of misinterpretation the three are somewhat interchangeable so an excess of
or confusion in the final project document. time or labour may make up for a shortage of money.
If compromises are involved in the rewriting of the Shortage of labour can be partially overcome by
project, another round of informal discussions is additional money and time and lack of time can often be
necessary to ensure that you have read the participants’ surmounted by increased money or labour.
Chapter-5.qxd 11/8/03 11:09 AM Page 33

Basics of rural electrification 33


project design

To be feasible, the project design must work within support organization after the physical completion of
the limits of resource availability. The task of the project the project. Many, if not most, rural energy projects
designer before beginning the detailed design is to list fail through lack of adequate post-completion
the money, labour and time resources that might be support in the form of maintenance, fuel supply,
made available to the project together with their possible spare parts or training. The collection of fees for
sources. project services is often left to chance or the hope
At no point in the development of the project design that what amounts to voluntary donations by the
should the requirement for resources exceed those that user will suffice. It is the responsibility of the project
can be made available. This resource list is therefore designer to ensure that there is an adequate support
constantly referred to as the detailed project design is organization to run the project as well as the more
developed. When the requirement for one resource immediate need for an organization to carry out the
exceeds that available, the designer can consider design and construction.
increasing the use of other resources as a replacement. 4) Technical design. Who will do the actual hardware
Where replacement is not possible, the project design design for the installations? Who will check the
must be adjusted to stay within the available resources. designs to make sure that they fit the needs of the
project? If consultancies are needed, how will they
be chosen? Are there any restrictions placed by the
Detailed design funding agency on who can perform services on
the project?
Once project design goals are determined and a list has
5) Supply of materials and labour for the project.
been made of time, money and human resources available
The project design must include some process for
for the project, detailed project design can begin.
specifying and purchasing the components and
The principal items addressed in detailed project
services for the project. Does the recipient have to
design are:
provide any materials or labour? Is there a
1) Specific technical purpose of the project. What is requirement by the funding agency for purchasing
the project meant to achieve? For example, a from a particular source? If tendering is required,
reasonable purpose is to provide sufficient electrical who evaluates the tenders? Who writes the
power in a remote village to operate a video that specifications?
requires 150 W of power at 240 V, 50 Hz, for 4 hours 6) Budgeting resources (time, money and labour).
per week. As this purpose is the basis for the As resources are the constraints on the project,
technical design of the project, it must be clearly budgets of those resources are required as guides
and correctly determined. for their allocation. Budgets actually used for the
2) Recipients of the benefits of the project. Where project design should be as detailed and accurate as
are the project sites and who will be the recipients possible.
of the services provided by the project? This is 7) Preparation of a cash-flow estimate and sourcing
usually determined only after a great deal of of adequate and timely funds. Where do the funds
discussion and compromise. In many cases, the come from and how are they spent? Sometimes
recipients who would be most suitable for the funding is assured before a project is designed.
project will not be chosen owing to political, social Often the project is designed then money is sought.
and economic pressures. The project design must be In either case, the project designer has to ensure
geared specifically to the actual recipients rather that funding is sourced in amounts adequate to the
than to the ideal or average recipient. needs of the project and that the funds must be
3) Organization to design, administer, build and available when the expenditures have to be made.
operate the project. Obviously, there must be an 8) Arrangements for receiving materials from
adequate organization for building the project, but suppliers and shipping them to site. Will there
less obvious is the need for an administrative and be a need to test components when received? Will
Chapter-5.qxd 11/8/03 11:09 AM Page 34

34 Solar Photovoltaic
Project Development

there be a need to store materials between receipt the preparation of a very good project design in order to
from suppliers and shipment to the project site? foresee and avoid even more expensive problems during
What kind of storage will be needed at the project project implementation.
site and for how long?
9) Ownership of the project. Although very important,
the actual ownership of the project is often not
Summary of project design basics
specified in the project design. There has been at
Summary of general project design for rapid project
least one case where a village received an expensive
approval:
diesel rural electricity plant for their use — with most
of the cost borne by the government — and a short · Write the project to best fit what you think should be
time later sold the unit at a considerable profit and the goals.
equivalent loss to the government. There have been · Examine the resulting first draft in the light of what
a number of instances where solar panels and you believe to be the requirements of the recipients,
batteries installed as part of a rural electrification funding agency, politicians and bureaucrats.
project have been used for other things, with the · Modify the first draft to best fit the requirements of
excuse being that they belonged to the users rather the four participant groups.
than the government and they could therefore do as · Hold one or more rounds of informal talks with
they pleased with them. important (to your project) representatives of each of
10) Resolution of land questions. Obtaining land for the four groups and negotiate the terms to best fit
power-plant sites, power-line access rights, dam the real requirements of all the participant groups.
sites, release of land for flooding by hydro dams, · Write a final draft and submit it for approval.
the felling of trees to provide solar access, building Summary of factors to be considered for detailed
access roads and obtaining sand and stones for project design:
construction are typical requirements for a rural
electrification project. Ignoring these items during · specific technical purpose of the project
the project design phase can be either a money or · recipients of the benefits of the project
time budget disaster. If negotiations are not held · organization to design, administer, build and operate
until after much work has gone into the project the project
preparations, the cost of the land or rights being · technical design
purchased is likely to be much higher than if the · supply of materials and labour
negotiations take place in a leisurely fashion with · budgeting resources
little pressure on project management to bring them · cash-flow estimate to ensure funds will be available
to an early conclusion. when needed
· arrangements for shipping, receiving and storage of
A major determinant of the success or failure of a project components
is the quality of the detailed project design. It is · ownership of the project
worthwhile spending considerable effort and expense in · resolution of land questions.
Chapter-6.qxd 11/8/03 11:10 AM Page 35

User needs assessment


through site surveys
6 CHAPTER 6

Surveys as project design tools possible from sources in the country and from
international organizations prior to the actual survey.
One of the methods used to determine the size of a rural This information can also help in the survey design.
electrification project is to carry out a needs survey of Important pre-survey information that should be
the prospective recipients of the project. This survey gathered includes:
should be designed to determine several factors as · Access and infrastructure. Is there transport in and
accurately as possible: out of the site? What does it cost to reach the site
· the electricity needed to replace energy obtained from from the urban area in time and money?
other sources Are communications reliable and reasonable in cost?
· the desire of the recipients for additional electrical What other government officials and departments
energy for new purposes have facilities in the district?
· the relative importance to the recipients of lighting, · Demographic information. Population, per capita
radio, refrigeration, video, water pumping and other income, age distribution, percentage of rural citizens
common uses of electricity working elsewhere in the country or abroad.
· the ability of the recipients to pay the cost of · Meteorological data. Hours of sunshine, rainfall,
whatever system is installed cloud conditions, temperature, wind, humidity,
· any physical, cultural or economic constraints to the frequency and severity of storms.
installing an electricity system at the recipients’ site · Geographical. Shape and size of district, topography
· the relative importance of community versus individual that may cause problems with shading for PV systems
use of appliances such as irons, refrigerators and or with transmission and distribution wiring. The
videos topological and hydrological character of local streams.
· any other aspects specific to the recipients’ situation · Agricultural and fisheries development prospects.
that would affect the size and type of project What products are commercially produced? Will
required. electrical power be needed for agricultural or fish
processing? Are trees considered an important resource
Pre-survey data collection that should not be felled to provide shade-free solar
and analysis exposure or a right of way for transmission and
distribution lines?
As a survey visit to a remote rural site is costly and often · Past projects, existing projects and planned
difficult, it is important to collect as much information as projects for that district’s development. What is
Chapter-6.qxd 11/8/03 11:10 AM Page 36

36 Solar Photovoltaic
Project Development

the expected energy impact of the existing and Response bias is rendered unimportant when a
planned projects in the short and long term? foreigner is used to supervise survey staff, to collect
Assessment of the reality of planned projects, as data from written sources or to assist in analysing the
many are planned and few are implemented. What has collected data. On the other hand, sometimes
been the success rate for past development projects? the presence of a foreigner makes the survey seem
If they have failed, for what reasons? more important and increases the level of cooperation by
· Economic information. How do people in the rural the community. Foreigners are often equated with aid,
district obtain money? however, and there can be a tendency for people to
· Health and education information. The size and exaggerate their resources, their desire for development
type of facilities devoted to schools and health and their needs when a foreigner is a part of the survey
centres. The location, quality and availability of water team.
supplies. Response to national government officials from
· Politics. What administrative and social structure is outside the community. Although more likely to avoid
present in the rural districts? Are there community the language and cultural problems of the foreigner,
factions that may have a bearing on the project’s other problems bias their survey information.
success? Is it important to balance the project In some cultures, government officials from outside
resources among the factions? What organizations the district are viewed as gift givers. There is a
exist that might be used for local administration of tendency to inflate needs and to overstate the
the project? desire to receive development projects. Presumably the
expectation is that the person doing the survey has
Other resources that should be tapped include people
some control over the allocation of resources,
from the district currently living in the urban area and
so exaggerating needs increases the possibility that
government officials familiar with the district,
more will come to the community than otherwise.
its resources and any problems with projects there.
In other cultures, government officials are viewed with
suspicion and the opposite bias will occur. People hide
Selecting surveyors their resources and blatantly lie about what they believe
should be done about problems.
The goal is to obtain the genuine attitudes of the project Like foreigners, externally based government officials
recipients. Unfortunately, every person surveyed will have may be somewhat exotic and help to focus community
some bias towards the person doing the survey and every attention, but they are not usually good surveyors.
person surveying will have some bias to those surveyed. Response to local government officials. As local
The response of surveyed to surveyor changes with government officials are often selected on the basis of
culture so there are no general rules for preventing bias, political ability, they can be expected to have
but observations in many developing countries show considerable personal bias themselves when relating to
strong similarities in the way local people being surveyed the various sub-groups within the district population.
respond to different categories of surveyors. Likewise, the people being surveyed often have very
Response to a foreigner on the survey team. positive or very negative biases towards these local
Consultants, foreign volunteer workers or expatriate government officials. There is also a definite self-interest
government employees are rarely successful in collecting problem, as a survey bias that causes an increase in the
data through personal contact. Language barriers prevent level of development will also increase the power and
accurate surveys, a lack of intimate knowledge of the responsibility of local government officials.
cultural context limits their ability to ‘read between the The best use of local government officials is in
lines’ of responses and to probe for deeper meanings. arranging the logistics of the survey (transport, food,
Even without the language problems, responses are lodging, etc.) but not as surveyors.
usually strongly biased towards what the respondent Response to a young person as a surveyor. The
thinks the foreigner wants to hear. use of upper-secondary school students as surveyors has
Chapter-6.qxd 11/8/03 11:10 AM Page 37

User needs assessment 37


through site surveys

been tried several times with reasonable success. Though every unit in the survey area. The goal of any good
not always the case, people under the age of 20 are selection process is to select those to be surveyed in such
usually seen as too unimportant to lie to. They are not a way as to end up with the same survey results as if the
a threat nor are they seen as likely to be able to use entire population were surveyed. There are several
information given for the survey in a harmful manner. common methods of selection with this goal in mind but
Both young men and young women seem to do equally the most common for rural surveys is random selection.
well, though there is some sexual bias in that questions When all the surveys are similar in nature, in particular
relating to women’s activities will have more detailed when there is a very large number of them, random
answers when women are surveying while if a man is selection is the method usually chosen. First, the whole
surveying, men’s activities usually elicit more detailed group is numbered, laid out geographically or organized in
responses. some fashion, then the units to be surveyed are selected
Experience with rural energy and other types of by randomly picking out names, numbers, locations or
survey in many developing countries indicates that the some other identifier. In fact, any selection method that
least-biased survey interviews are usually obtained by ensures a genuinely random selection of survey recipients
sending a young (under 20) male/female team to each will be satisfactory. For this to be a valid method of
location and having the male surveyor interview the men selection it is important that (a) all the surveys are for
of the household and the female surveyor interview the the same thing (you cannot mix household surveys with
women. There are no data to indicate whether or not it surveys for commercial or community needs, for example);
is important that the surveyors are from the surveyed (b) survey units include about the same number of people
district, though that is likely to vary with the culture (you should not mix household units with six people
and particularly whether or not intercommunity rivalry or with extended family units of 30, for example);
distrust is involved. and (c) the selection is genuinely random.
For less than 1,000 units, the higher the percentage of
Summary the total population surveyed, the better the accuracy
of the results, but the accuracy improves most between
The survey team that is likely to obtain information 0% and 15%. Above 15% the accuracy still improves,
with the least bias will consist of teams of young men but more slowly. Also, the greater the number of units
and women supervised by government officials or surveyed, the better the accuracy, but the accuracy
foreigners. A local government official should be improves most dramatically up to about 20 units.
included for introductions and logistic support but Above about 20 surveyed units, the accuracy still
should not directly participate in the survey itself. improves, but more slowly. Thus as a general rule of
thumb for these types of small survey, no less than 15%
Selecting units to be surveyed of the total group should be surveyed and no less than
20 surveys should be taken when using this random
Random selection of survey units selection method.

Although energy surveys are almost always of people, RULE FOR SMALL RANDOMLY BASED SURVEYS:
No less than 15% of the total number of units,
the unit of survey may be several people, such as
or 20 units, whichever is larger, should be
a household, rather than an individual. So in discussing surveyed to obtain an acceptably accurate
who is surveyed, we use the term ‘survey unit’ instead of estimate of total needs.
person. In each survey unit, therefore, one or more
people are interviewed. In a community with 40 households, 15% of them is only
In some cases, no selection process is required: every six, so the minimum of 20 units should be surveyed,
unit is surveyed. Often, however, there are too many i.e. half (50%) of the households.
units, they are spread over too large an area or for some If there are fewer than 20 possible units to survey,
other reason there is not enough time or money to survey then all of them should be surveyed. For example,
Chapter-6.qxd 11/8/03 11:10 AM Page 38

38 Solar Photovoltaic
Project Development

if there are five secondary schools in the district being arbitrarily select one person from a survey unit of several
considered for a project, all five should be surveyed for persons and make no effort to gather information from
their needs. If the entire country is to be surveyed and the others.
there are 100 secondary schools in the country, at least The person or persons interviewed must not only have
20 should be surveyed. If there are 500 secondary the information the surveyor is interested in, there must
schools in the country being considered for the project, be a willingness to be interviewed. People who are very
at least 75 should be surveyed (15%). shy, who are junior members of the survey unit and are
These rules of thumb mainly apply to the relatively uncomfortable or forbidden to speak for the survey unit,
small surveys usually needed in isolated rural districts. who are embarrassed about having little education or are
When a few thousand units are involved, and the basic simply not interested in helping, will not be good sources
rules of uniformity and random selection apply, the of information.
percentage of units surveyed can be reduced without A significant problem with surveys of households is
seriously reducing the accuracy of the survey. However, to find people from the household who not only have
the quality of the survey design becomes increasingly the information but are willing to give it to the surveyor.
important. When such large surveys are required, The time of day that the survey is carried out may make
specialists in survey design should be employed. a difference. If a time is chosen when the only people
The implication of large surveys is that major economic left at home are the very young and very old members of
decisions affecting the lives of thousands are involved, the household, there may be many more problems
so attempting to save money on the survey may result in obtaining accurate information than at other times when
the wasting of larger sums later. the leading household members are available.

Selecting people with appropriate Survey questions


knowledge for survey
The survey is no better than the questions asked.
If the person being interviewed for the survey has no A series of questions can be devised that force the
knowledge of the subject of the interview, the results are results into almost any predetermined mould. Other sets
not going to be very useful. In the case where specialized of questions may yield results so random as to yield no
knowledge is required to make an intelligent response to useful information. The questions should be prepared by
the survey, people with that knowledge must be selected. someone who has intimate knowledge of the group being
For example, if the subject is the amount of firewood surveyed but who also has an intimate understanding of
needed for cooking, in most households the men will not the processes needed for analysis of the survey and the
be able to provide accurate estimates as the women effect the questions have on that analysis. Rarely will all
usually gather and use the wood. In most rural cultures, those skills be present in a single person. A team
it would be a poor-quality fuel-wood survey that was generally has to be involved to prepare the questions
based only on interviews of the senior male person in and the team should include someone from the culture
a household. being surveyed who clearly understands the goals of
To determine the amount of fish likely to be collected the survey, someone who understands the mechanics of
for freezing and resale, people who are currently in the surveying and of survey analysis, and someone who is
fish business are better survey subjects than those who knowledgeable on the subject of the survey.
only fish for their families. A group of fishermen of any For example, suppose we need to design a question
type would be better survey subjects than a group of for a survey that is intended to help forecast the change
people who have spent their lives growing yams. in firewood usage that would come about as a result of
Because a single survey unit may contain many people, wood stoves being provided for cooking. Someone who
it may be important to interview several people from each knows how firewood is used in the village is very
unit to cover all the areas of knowledge needed for an important. If a primary use of firewood is for
accurate survey response. It is poor survey practice to underground ovens, wood stoves will affect firewood
Chapter-6.qxd 11/8/03 11:10 AM Page 39

User needs assessment 39


through site surveys

usage differently than if most is used for cooking over surveyed. The main danger is that the other survey
open fires. was not a good one so yours will not be either.
Someone who has experience with other communities You must first judge the other survey and its results
and their reactions to the use of different types of wood and be convinced that it is appropriate for your use.
stoves will be important. What are the alternative fuels in 3) Refinements are included. If a very similar survey
the area that are not now being tapped but could be has been made a number of times and the
used in stoves, what about the different methods of organization creating and carrying out the survey is
cooking needed to take advantage of stoves, the reaction reasonably competent, the survey will be refined with
to different foods that may be prepared on stoves but each use. You will have the benefit of this experience
not on open fires, the reaction to different types of and refinement.
stoves, and many other considerations that will have an 4) The organization preparing the other surveys may
impact on the actual use of stoves if they are installed. be able to assist you in preparing and analysing
Finally, there must be someone who knows how to yours. It will have had considerable experience and
convert the answers to the questions into a form that can may be able to point out potential problems well in
be used for the purpose of the survey. That person will be advance so that they can be avoided.
mainly responsible for the form of the questions to ensure
A final, but important point: though the survey may
that the answers are definite enough to be useful.
initially be prepared in English or other metropolitan
Though general impressions are an important part of a
language, the questions actually used must be in the
survey, the actual data must be in a form that is either
local language. If they are not, the surveyor will have to
numerical or represents a very limited choice of responses.
translate and experience has clearly shown that this will
This sounds very complex, and it can be,
introduce major biases into the responses. The very
but realistically most surveys are based on other surveys.
careful wording of questions to eliminate bias will be
Once a set of reasonable survey questions and analysis
useless if the questions have to be explained by someone
methods has been found for surveying a particular
else in a different language. The translations should be
subject, the same general set can be adjusted to fit
carefully checked by people from the same cultural
the local situation and used again. There are many
background as those being surveyed. Someone who is
advantages in using the same or a very similar set of
fluent in the original metropolitan language as well as the
questions as used in other surveys. Some of
local language should translate them back to ensure that
the advantages are:
the intended meaning has been preserved.
1) Using survey questions that have worked
elsewhere increases the likelihood that they will
work for you. Once you are convinced that the other Who supervises?
survey was similar enough to yours in goals and in the
character of the place being surveyed, you can be Someone has to be in charge of the survey team. Usually,
fairly sure that the questions that were acceptable in the field representative of the organization paying for
the other survey will be usable in yours. the survey is in overall charge. If the representative is not
2) Your survey results can be directly compared with a national of the country being surveyed, the cultural and
those of the other survey. Few surveys have no language problems may make it impractical for that
meaning at all, the problem is trying to find out what person to be the direct supervisor of the people actually
the meaning is! If the same survey is used again and doing the survey. A responsible local person who can
again, in time a correlation between the results of effectively communicate both with the foreigner in
the survey and what actually happens can be made. charge and the local surveyors is a very important part of
The more times and places the survey is made, the survey team. That person should be the overall
the more correlation possibilities there are and the supervisor of the survey with the foreigner having the
more confidence you can have in the survey results authority to step in should there be a problem and be
providing a true understanding of the situation being the ultimate arbiter of disputes.
Chapter-6.qxd 11/8/03 11:10 AM Page 40

40 Solar Photovoltaic
Project Development

What questions are asked? · people with small generators of their own will have a
higher electricity use than people with no past history
It takes many questions to get one answer of electricity use
· people who are now buying 20 or 30 dry cells a month
It is usually not appropriate to come right out and ask to run radios and portable lights can be expected to
the very question that is most important to your survey. have higher electricity use than those buying
You must, instead, ask several related questions and very few.
determine the result from the combination of answers. Asking about the economic situation of the family is
There are several reasons for this ‘beating around the another subject area that supports the key question of
bush’ in surveying. energy use because it is known that families with a lot
1) People who are being surveyed usually think that of money tend to use more electricity than those with
what they say will have some impact on what they little. The number of people in the household is a relevant
will receive from the government. In most cases, question. The number and type of electrical devices
they are right. Unfortunately, they often strongly bias (cassette players, portable lights, etc.) is a relevant
their answers to questions in a manner that they think question. Questions relating to what people would be
will increase what they receive later. willing to pay for differing levels of electrical service help
2) In surveys relating to the introduction of new to indicate their real priorities for energy use.
technology in a rural environment, the survey is
Misdirection as a device to reduce bias
often related to things few people have
experienced. As a result their answers are based on
Ideally, the people surveyed should not know why they
imagination rather than experience. For example,
are being surveyed if unbiased answers are required.
if electrification of a rural village is being considered,
Sometimes surveys are deliberately misnamed or their
most of the people in the village will not be able to
purpose falsely stated in the hope that the real area of
accurately answer the question, ‘How much electricity
interest will seem incidental to the stated subject and the
will you use?’. They have no experience of electricity
responses will be unbiased. Another ruse used where
and their answer to that direct question will not be
the subject is already known to the people is to have two
very accurate.
questionnaires, one clearly about the subject with obvious
3) Even knowledgeable, experienced, unbiased people
straightforward questions but the other questionnaire,
usually have trouble answering questions about
claimed to be a survey that some other agency wanted
what they would do ‘if’ without considerable
done while the surveyors were in the area, contains the
thought. By asking a number of supporting, relevant
real detail with all the supporting and background
questions that are easy to answer, an answer can be
questions that will be the principal source of information
determined more accurately than if a straight
about the surveyed area. Note that the surveyors
‘what will you do if’ question is asked. It is definitely
themselves are told the same thing, so they are less likely
relevant to ask that direct question, but the
to ask leading questions or coach the respondents to give
supporting questions are no less important in the final
answers that the survey organizers want.
analysis and should be asked before the direct
Generally only about a quarter of the questions asked
question.
in a good survey are directly relevant to the subject.
Therefore suppose your real question is ‘How much The rest are of varying degrees of importance, with many
electricity will your household use if we electrify your questions being actually irrelevant but included to keep
village?’. Relevant but indirect questions that should be people from knowing which questions are really important
asked include questions about existing energy use and to provide some easy questions along with the
because difficult ones so people do not feel too intimidated.
· people who are used to many kerosene and pressure When instructing the surveyors, they should be
lights will also want many electric lights warned not to coach or instruct beyond the basic need to
Chapter-6.qxd 11/8/03 11:10 AM Page 41

User needs assessment 41


through site surveys

tell people what is wanted. It is important that the How the questions are asked
questions be clearly worded so that little or no assistance
is needed from the surveyor. The more the surveyor is How the questions are asked is almost as important as
involved in assisting, the more the answers become the questions themselves. The surveyor should ask all
biased towards the surveyor’s opinions instead of those questions in the same manner. There should be no clue
of the person being interviewed. For example, in a wood that any questions are more important than others. The
fuel survey one of the questions was to list the species questionnaire should not require a dialogue between
of trees that were used for fuel and about 10 blank lines the surveyor and the surveyed as the questions should all
were provided. When the results were tabulated there be multiple choice, yes/no or other types of question that
was a very strong correlation between the primary require little or no assistance from the surveyor.
species listed and the person asking the question. Estimates of numerical quantity are often poor
Apparently each surveyor had a favourite type of wood unless the respondent can visualize the quantity.
fuel which was usually written down as the answer given Questions that require a numerical answer, such as how
by the person being interviewed. It was so obvious many litres of kerosene are used per week, should be
that when, say, ironwood was given as an answer, based on sample sizes rather than just asking for a
one particular surveyor was sure to have been the one number. For example, to determine litres of kerosene
asking the question. When coconut fronds appeared on used per week, the person surveyed could be shown
the list, it was almost always another particular surveyor. several different sizes and types of containers and asked
Such biases make the answers useless. to identify how many are used per week. If the question
This example points to another important aspect of is how much wood is burned for cooking every day, then
the questions: use checklists or yes/no responses instead the respondent should be asked to make a pile of wood
of blanks to be filled in from memory. What should have about the same size as is used in a day and that pile
been done was to list the species known to be in the weighed by the surveyor.
area and the surveyor should have asked about each. Quality responses require a quality environment.
Another technique used to improve the accuracy of Placing the subject under stress by having more than two
survey questionnaires is to ask the same question several people visiting the site at a time, allowing the team to
times but in a different context or manner. For example, arrive at times that are inconvenient to the person being
people could be asked how many kerosene lights are interviewed, using a language that is foreign to the
kept lit and for how many hours a day. Later they could person being surveyed or in any way violating the local
be asked how much kerosene they use in lamps every concept of good manners, will all reduce the usefulness
week. Finally, they could be asked where each light is of the response. Always remember that the surveyors are
used in the household and how long each one is left literally guests of the people being interviewed and it is
burning. By asking the same thing in different ways you important that they follow the unwritten rules of custom
will learn whether or not the person being interviewed is that apply to guests. Although the surveyors should not
giving you useful data. If the answers are reasonably be encouraged to linger and take advantage of their
consistent, the answer is yes. If very inconsistent, no. guest status, they must still be allowed to stay the
Subjective information can be valuable if the same minimum time that is considered polite, have a cup of tea
person collects all the data. For example, the size and and a biscuit or whatever is the local custom in these
quality of the house and furnishings is an indicator of the circumstances. In many cultures it is impolite to come
economic situation of the household. As long as the same immediately to the point of a visit and considerable time
person reports on what they perceive as the relative may be spent in small talk before the actual purpose of
quality of the house and furnishings, there is some value the visit can be broached.
in that information. For any form of subjective In most cultures, it is appropriate to bring a small
information, however, no two people view the same gift when visiting. Most remote families appreciate
situation in the same way and subjective information from something from the outside and a small gift from a store
several people is not satisfactory for comparative analysis. in the city may be more appreciated than a large gift of
Chapter-6.qxd 11/8/03 11:10 AM Page 42

42 Solar Photovoltaic
Project Development

local produce. Find out from people knowledgeable of the 4) Questions that are consistently left unanswered or
culture what is appropriate and make arrangements well answered by the equivalent of ‘I don’t know’
in advance for gift giving if it is appropriate. In some indicate a problem with that question. The question
cultures a particular type of gift is always given for needs revision. The solution is not to instruct the
a particular type of visit, so always obtain the advice of surveyors to more fully explain the question.
someone from the area being surveyed as to what is This is almost certain to introduce major biases into
appropriate. the response so that the opinion of the surveyor will
Many village-based cultures also expect a formal be reflected in the response rather than that of the
ceremonial visit to be paid to the village governing person surveyed. The surveyors should not coach or
council, be they a formal group or an informal gathering other than minimally instruct the people being
of elders. Some cultures have quite strict rules of gift surveyed.
giving and conduct for these meetings, other cultures
In addition to checking the actual responses, the person
require little more than a handshake with the village chief.
in charge of the survey team should continuously tour
This initial formal meeting will set the tone for the entire
the survey area to ensure that the surveyors are in fact
visit so it is particularly important that no rules of custom
working in the right area and that there are no particular
be violated at this time. A local member of the team or
problems to be solved.
a trusted advisor who knows exactly what is expected
should make all arrangements and coach all the team
members on the proper conduct and the appropriate
ceremonial responses. For the foreign members of the
Analysing the results
group a rehearsal may be useful. Though the days appear
A survey is a closed circle. In order to create an
to be past when you might lose your head over a minor
appropriate set of questions, you must know in advance
customs breach, you may still lose your welcome and the
the methods that will be used for analysis. To find the
quality of your survey will be in jeopardy.
best methods for analysis, you must have some idea of
the responses that will result from the questions.
Checking daily As much analysis as possible should be undertaken in
the field so that if there are problems with specific parts
Every questionnaire should be checked at least daily by of the survey, they can be redone or at least the reasons
the person on the team with the most experience in for the problems can be determined. Once you leave the
survey work. The checker should look for: survey site, it is very difficult to work out why a particular
1) Wildly varying responses between respondents set of data is dramatically different from the rest or why
who are obviously similar. This usually indicates one question seems greatly at odds with others asking
a poorly asked question or one that has a strong essentially the same question. Doing much of the analysis
emotional impact. The question should be rephrased in the field always involves the possibility of yielding to
or eliminated. the temptation to try and ‘clean up the data’ by taking
2) Notable differences in the number of people all the data on the fringes of the main group and trying
questioned by the different surveyors. A surveyor to ‘find out what is wrong with them’. That is not the
doing an unusually large or small number in intention. All sets of data will have a few points at either
comparison with the others should be suspect. extreme. It is not the extremes but rather what is
3) Very consistent responses to questions asked by happening in the core group that reveals how good the
particular surveyors in comparison to the survey is. If the data are widely distributed with no
consistency of response found by other surveyors. particular concentration, there is reason to believe that
This indicates too much coaching or leading of the the question was not well phrased or it is not relevant
subjects by the surveyor. It can also mean that to the subject. That sort of data does not provide much
the question is not being asked at all and the surveyor information other than the fact that whatever was asked
is filling it in. does not seem to matter much. Relevant data will have
Chapter-6.qxd 11/8/03 11:10 AM Page 43

User needs assessment 43


through site surveys

one or more clear concentrations and the relative Also, where numerical accuracy in the presentation is
importance of the question (or else how well it was important, a tabular presentation is usually better than
phrased!) can be seen by how sharp the peak is. If a graphical one.
virtually everyone says that something is true, that is Graphical representations work best where data
strong evidence for assuming it is true in planning for variables are related and can be plotted side by side for
development. If half the people say that something is comparison. For example, plotting the size of different
true and the other half that it is false, considerably less age groups for a population sample will show at a glance
confidence can be placed in that question. whether the population is largely young, middle-aged or
old. Graphical presentations of data are almost always
Checking for questionable data easier to understand than tabular ones. Most people find
it much easier to relate to a graph than to raw numbers.
The first step in analysing the data from the survey is to For example, seeing the number 10 next to the number
locate questionable data and set them aside for special 1,000 is much less dramatic than a line 1 mm long next to
study. An attempt should be made to find out why the one 100 mm long. Correlation between different data
data are so unusual. The reason may be simply an error, items and the relative importance of different responses
poor reporting by the surveyor, or that the person are usually much more clearly represented graphically
surveyed did not understand the question and therefore than in a table.
gave a strange answer, but the reason may also relate to Map-based graphics can be very useful if the data
the survey analysis. No data should ever be actually vary according to location and location is significant to
discarded. Even those that are clearly absurd should be the end use of the survey.
noted and annotated even though they may not be used
in final data tabulations. Determining survey quality
After noting questionable data, which in a good
survey should never be more than 10% of the total The quality of a survey determines what level of
collected, the problem is to present the useful data in importance its results should have in project decisions.
a form that is easy to understand. While determining the quality of a survey is largely
a matter of judgement based on experience and training,
Correlating responses there are some indicators of quality that anyone
can use:
The correlation of different data items is an important 1) Answers are not clustered. Survey questions where
part of analysis. When preparing the questionnaire, the all the answers are about the same or the answers are
point was made that the same question should be asked fairly evenly distributed among the possible choices
in several different ways. In the analysis phase, those are probably not good ones. Good survey questions
questions should be compared to see if the answers are usually result in answers that tend to be clustered
consistent. The stronger the correlation, the more among a few responses but have some responses
confidence you can have in the correctness of the outside the cluster too. If the questions that are
response. If the correlation is very poor, the response relevant to the end use of the survey are not good
should not be used as a determining factor in the project. ones, then the survey is not good either.
2) Responses can be seen to vary according to who is
Presenting the data in usable form surveying. If one surveyor consistently has a
particular answer to a question on the response
The two most common formats are tabular and graphical. sheets but the other surveyors are different,
Tables are best suited to data with many unrelated the quality of that surveyor — and therefore of the
variables concerning one data subject. For example, the survey itself — is placed in doubt.
subject may be a person, the variables might be age, sex, 3) The sample size is small or not randomly selected.
educational level, number of children, height, weight, etc. In general, the larger the sample, the more reliable
Chapter-6.qxd 11/8/03 11:10 AM Page 44

44 Solar Photovoltaic
Project Development

the results when applied to the whole community. It is electricity is not likely to yield an accurate forecast of
reasonable to be suspicious of the quality of a survey how it will actually be used.
if the sample size is small or if there is reason to
believe that the sample used was not truly randomly
selected. Summary
4) The survey methodology or questions have not
been used before. With a particular set of survey Surveys play an important role in determining the
questions or mode of surveying it usually takes three probable uses of electricity in a rural district but they
or four tries, with modifications on each try, to obtain should not be the sole method used in deciding on the
high-quality results. There should be less confidence in type and size of a rural electrification project.
the results of a new set of survey questions or a new For a survey to be useful, the following points in
approach to a user survey than one that has been preparing and administering it should be remembered:
successfully used many times before.
· The survey sample must be large enough to be
relevant (over 20 units surveyed and over 10%
Project decisions based of the total units randomly selected).
on user surveys · The survey questions should be in the language
of the people being surveyed.
The primary use of a user survey is to determine what · The survey questions should be brief and not require
energy is being used and to help in determining how elaborate directions or long written responses.
much of this energy can reasonably be replaced by For best results, they should be answered by a check
electricity from a rural electrification project. from a list of possible responses.
Under the best of conditions, a user survey carried out · Surveyors should be selected to cause the least bias on
prior to electrification will provide a good basis for the part of both the units being surveyed and the
predicting the minimum use of electricity after surveyors themselves. To avoid sexual bias, survey teams
electrification. A rural electrification project can be with both male and female members should be used.
expected to replace most of the energy used for lighting · Constant checking should take place during the survey
and the energy used in operating personal generating to ensure that surveyors and survey questions are
equipment. A good survey should accurately determine satisfactory.
these two classes of use. · The resulting data must be placed in a form that
User surveys of this type should not be used to shows the relationships between responses and the
predict actual or maximum use of electricity. Some of the questions intended to be answered by the survey.
information, such as the economic situation of the users, · The weight the survey has in project decision-making
may be useful in forecasting the total demand for depends on the quality of the survey and the
electricity, but a survey of users who have never had availability of other information.
Chapter-7.qxd 11/8/03 11:13 AM Page 45

Forecasting rural demand


for electricity
7CHAPTER 7

Importance of accurate forecasts requirements then all appliance use estimates totalled to
obtain the overall village estimate.
of demand This approach is only as accurate as your knowledge
of what appliances will be used and how they will be
When designing any electrical system, whether for a single
used. In the case of solar photovoltaic electricity, this
house or a continent, there must be advance knowledge
method is almost always used because each house
of how much total energy (watt-hours) will be needed and
is a separate generating unit and has to be treated
the maximum power (watts) that will be required. Without
individually.
that knowledge, the size and type of the system needed
cannot be calculated.
The more accurate the estimate of the needs of the Top-down method
customer, the better the designer is able to provide a
system that will meet those needs without excess cost In the top-down approach, the estimate is made on
due to oversizing or customer dissatisfaction due to the basis of known use by comparable installations
undersizing. elsewhere. The basic assumption is that for similar groups
of users the individual use of electricity may differ
greatly but that of the group will be comparable to other
Methods of forecasting demand groups of similar size.
So if the task is to electrify a village of 50 houses and
There are two basic approaches to forecasting the data from another village of 75 houses are available, we
demand for electricity, top-down and bottom-up. can compute the per house use from the electrified village
(by dividing total village use by 75), then multiply the result
Bottom-up method by the 50 houses in the new project village to estimate its
total electricity needs.
The bottom-up method (sometimes called the build-up The accuracy of this approach depends on how
method) sums the estimates of a large number of small comparable the two villages really are. As many factors,
units into an overall estimate of total demand. For both economic and social, affect electricity use in a
example, in a small village, each appliance in the village village, finding two villages that have the same use
might be listed with an estimate of its individual electrical patterns is not easy.
Chapter-7.qxd 11/8/03 11:13 AM Page 46

46 Solar Photovoltaic
Project Development

To achieve the best forecast using the top-down the electrified village. If you need the number in
method, the following criteria for the project user group kilowatt-hours, simply divide the total watt-hours
and the comparison user group should be met as closely per day by 1,000. If you need the monthly average,
as possible: multiply the daily use by 30.
4) Divide that monthly electrical usage and peak watts by
1) Both groups should have similar per capita income
the number of houses in the village to find average
levels. Energy use is tied closely to income, so
monthly household use and average peak household
estimating the use of a poor village on the basis of
demand.
the use of a rich one will not provide an accurate use
5) Multiply the average monthly household use and the
forecast.
average peak household demand by the number of
2) Both groups should be culturally similar. Taking the
houses in the project village to estimate the monthly
use of an electrified suburban village inhabited by
electrical requirements for the project village.
workers with jobs in the urban areas to forecast the use
6) Add any special loads that will be connected to the
of a remote rural village will not be accurate. Neither
project village electrical system. Note that stores
will the usage figures from a village that depends on
supplying domestic needs such as food and clothing
agriculture for its subsistence necessarily result in a
are automatically included in the regular top-down
good estimate of electricity use in a fishing village.
estimate (as their load is approximately in proportion
3) Both groups should be similar in size. Use patterns
to the number of households served) and only special,
in large villages are often different to small ones.
non-domestic loads should be added to the figure
4) Both groups should have similar types of
obtained from the top-down method.
generating systems. Estimating use for a village that
is to receive a diesel system based on the use of a Where suitable comparable villages can be found and
village electrified from the grid may result in where the generating system is to serve an entire village,
inaccurate estimates. the top-down method generally yields the best estimate of
project village consumption. Where good comparisons are
These four criteria are listed in the approximate order of
not available or where individual generating systems for
their importance to an accurate forecast. Thus it is more
each home are to be installed (as with photovoltaics), this
important that the villages have a similar economic
method is not so good and the bottom-up method should
structure than that they get their electricity from similar
be used.
generators.
Note that this method automatically compensates for
If any special electrical loads must be connected in the
the fact that not all houses will connect to the electrical
project village that have no counterpart in the village
service by assuming the same percentage of connection
used for comparison, they should be added to the
as the comparable village. If there is reason to believe
top-down estimate. For example, a freezer is to be
that this will not be the case in the project village and a
installed for freezing fish before shipment to market. The
good estimate is possible of the number of households
freezer constitutes a significant special load that should
that will elect to receive electricity, a similar process of
be added to the general load of the houses that has
estimation may be carried out by just including electrified
been estimated by the top-down method.
houses in the villages rather than all houses. Stores and
commercial establishments must be added separately in
Making a top-down estimate for this case.
designing a village electrical system
Making a bottom-up estimate
1) Locate a village that is electrified and is comparable in
economic base, culture and size to the project village. As the electrical energy used by an appliance, as
2) Find the number of houses in both villages. measured in watt-hours, equals the number of watts an
3) Find the monthly electrical usage in kilowatt-hours appliance uses multiplied by the number of hours it
(kWh) and the peak demand in watts (peak watts) for operates, watt-hours per month (or day, week, etc.) is
Chapter-7.qxd 11/8/03 11:13 AM Page 47

Forecasting rural demand 47


for electricity

easily calculated if the appliance power requirements countries can yield useful information about how villagers
and hours of use per month (or day, week, etc.) are in your project village will respond to the new electrical
known. system.
The bottom-up method of estimating monthly In the bottom-up method, you will be in error if
electricity use for a village requires knowledge of you ignore special situations that change use patterns.
appliance power requirements and use patterns: For example, Saturday and Sunday may have completely
1) List all the appliances to be used in the project village different use patterns than the rest of the week. While
with their individual watt ratings and the number of these unusual but predictable variations in energy use are
hours each will be used per day. automatically taken care of in the top-down method, you
2) Multiply each of their wattage requirements by their must manually correct for them in the bottom-up
daily use in hours to find the watt-hour per day figure method.
for each appliance.
3) Total all the appliance watt-hours per day to find the Your forecast will never be
total village watt-hours per day. If you need the 100% accurate
number in kilowatt-hours (kWh), simply divide
the total watt-hours per day by 1,000. If you need the Remember that only a certain level of electricity use will
monthly average, multiply the daily use by 30. actually occur. The chances are very low of your forecast
With solar electricity, this calculation is best carried out corresponding exactly with that. What you are striving
for each house, rather than the village as a whole. for is a forecast that will not be so much smaller than
The accuracy of such a calculation is no better than reality as to cause hardship or strong complaints
the estimate of the appliances that will be used and the from the customers, or so much larger as to leave a
estimate of their period of use. Usually, at the time of significant part of the system (and its capital
initial installation of a rural electrification project, the investment) unused.
appliances to be used can be determined with good In solar PV installations at least, the error in
accuracy. With PV systems, the appliances are usually forecasting has usually been on the small side. People
installed at the same time as the solar panels and there is seem to use the systems more than they initially
no doubt about their number or characteristics. estimate. If money is available, it is a reasonable practice
The time of appliance use per month (or day or week) to assume at least a 15% greater electrical load than the
is much more difficult to estimate, however. If the forecast predicts.
prospective users are asked how many hours a day As a general observation, the demand for electricity
(week, or month) they will use the appliances, you may tends to increase with time, though that is not at all a
get an answer but remember that it is only a guess. The universal law. There have been a number of cases where
villagers have never had electricity before and they are the demand for electricity decreased after the initial
imagining how they will use it, not judging by past installation. This decrease has been attributed to the
experience. difficulty of obtaining money in a remote rural village
As with the top-down method of estimation, the use where an attempt is made to reduce cash outflow or
of comparables is valuable. If another similar village has where appliances have failed and the money to repair
received a similar electrification project, how appliances them is not available.
are used in that village can be a very valuable source What does seem to be almost universal is the increase
of information for estimating use in the project in energy use with an increase in the money available. If
village — usually better than the estimates made by the a village (or household) increases its prosperity, it tends
project village population. Even comparable users in other to increase its use of electricity and vice versa.
Chapter-8.qxd 11/8/03 11:15 AM Page 49

Project organization 8 CHAPTER 8

The task General project design. The skills to perform this


task include a good understanding of the socio-economic
Project management includes deciding what the project is situation of the recipients, knowledge of the bureaucracy
meant to accomplish, obtaining funding, obtaining people and what is needed to get a project approved,
to carry out the project, performing the technical design, understanding of the political situation, knowledge of
specifying and ordering materials, organizing the project, funding sources and their requirements, and broad
scheduling, budgeting, auditing, arranging for spare knowledge of rural development project successes and
parts, and organizing maintenance and fee collections. failures. This skill is needed primarily in the
For any project, even a small one, a team is required pre-implementation phase of project development.
and for large, complex projects, hundreds of people may Data gathering. Familiarity is required with data
be involved. resources in the country, with surveys and their analysis
Bringing that team together and working towards and with the basic statistical processes needed to analyse
the common goal of an operating project is what project numerical data. Computer skills will be useful and are
management means. increasingly a requirement as CDs and the Internet are
used for storing and distributing data. Data-gathering
skills are needed up to completion of the project design.
Skills required Economic and financial analysis. A clear
understanding of the costs and benefits of the project is
The organization will be required to perform many vitally important. This is necessary to compare costs of
technical and administrative functions, so the personnel different options, to provide cost analysis to funding
involved, and the organizational structure itself, must agencies, for project approval within government and for
reflect this requirement. To carry out the project, a determining the recurrent cost of the project to respond
number of skills must be available to the rural to subsidy and user fee requirements. This skill is also
electrification project organization: important in the pre-implementation phase of project
Management. This is the skill necessary to assemble a development.
project team, organize it, budget resources and keep Technical design. This is the ability to design the
the project on track within the resources of the team physical plant necessary to perform the project tasks, to
and the restrictions of the budget. After installation of specify components that must be purchased and to
the project, management must organize and administer estimate installation and maintenance requirements. This
fee collection and maintenance. Management skills are skill is mainly required at the actual time of technical
needed throughout the project period. design, though some technical input will be necessary in
Chapter-8.qxd 11/8/03 11:15 AM Page 50

50 Solar Photovoltaic
Project Development

the early general design stage. There is a minimal involved, particularly those near the top. So the first, and
requirement for design skills after the project installation probably most important, rule for creating an organization
has begun. is to fill the top positions with the most capable people
Purchasing. Knowledge of vendors, tender procedures, possible. Without good people in the guiding positions,
market prices for equipment of the type being purchased, no organization will perform well. Of course, having a
and skill in evaluating vendor responses is necessary here. workable organizational structure is going to help a good
Generally this skill is required only briefly when actually manager to do an excellent job and may be the
purchasing components. There is a minimal requirement difference between success and failure for an
for purchasing skills after project installation commences. organization with a mediocre manager.
Shipping and warehousing. Skills for this task include When structuring an organization, two basic rules
an understanding of the different relative advantages and should be observed to obtain the best results:
disadvantages of various shipping methods, knowledge of
Have no more than seven people and no less
the time required to move materials from one place to
than three reporting to one supervisor.
another, getting components through arrival processes
quickly and at minimum cost to the project, and a For decision-making in an organization, one
knowledge of the quality of storage necessary for person is best, but never more than three and
extended holding of components before installation. preferably not two.
This skill is generally little required before purchasing
commences and minimally after installation.
Training. An ability to train people with basic formal
Rule one — the rule of sevens
education to carry out installation and maintenance of
Long experience with many different kinds of
technical components is required after the technical
organization shows that one person cannot effectively
design is complete and periodically after the installation
supervise the work of more than about seven others.
is complete.
When more than seven people are assigned a manager
Installation. An understanding of the processes for
for supervision, either the quality of supervision falls
installing the rural electrification components is required,
dramatically and people become essentially
including the standards to be met. The ability to cope
self-supervising, or the supervisor keeps up the level of
with changing conditions is essential. This skill is required
supervision and the work pace falls dramatically because
when installation commences and sporadically after project
everyone is standing around waiting their turn for a
installation is complete.
decision. Seven also seems to be the maximum effective
Maintenance. Knowledge of the correct operation of
size for committees and other operating groups in an
the systems and the procedures for troubleshooting,
organization. If there are less than three people
repair and maintenance is required. This skill is needed
reporting to a supervisor, the supervisor’s job should
after the installations are complete.
probably be eliminated or merged with another.
Fee collection. Honesty and the ability to keep good
In effect, this means that increasing numbers of
records are the main requirements here, coupled with a
employees, say maintenance staff, at a particular level
friendly but firm attitude. There must be a willingness
will require increasing numbers of supervisors in the ratio
and ability to carry out unpopular tasks such as the
of seven employees to one supervisor.
disconnection of non-paying customers. This skill is
required continuously after project installation is complete.
Rule two — decision-making

Creating an effective Decision-making requires weighing all the available


organizational structure information and determining the right course of action.
As each person sees things differently, no two people will
The success of an organization is often much less come to exactly the same conclusion when given the
dependent on its physical structure than on the people same data. One person can come to a decision easily as
Chapter-8.qxd 11/8/03 11:15 AM Page 51

Project organization 51

no one is disagreeing with the weighting of the factors Categories 2 and 3 staff may be permanent employees
involved. If that person has experience, intelligence and temporarily assigned to the project or may be hired as
competence the decision will probably be satisfactory. temporary employees from the outside. For large
Three people will weigh the available information government projects, it is common practice to hire a
three different ways and will probably disagree on many commercial project management firm to provide all these
points, but generally two of the three can come to an short-term employees.
agreement and force the third into a consensus. For small projects, one person may take care of
Two people can easily become deadlocked and several (sometimes all) of the tasks. Typically, however,
outside arbitration (or dictates from above) may be specialized tasks such as technical design and economic
required to force a decision. More than three people analysis are carried out by consultants or specialists made
have so many different views of the same problems and available from other organizations for work on the
interact in so many different ways that it takes much project; while general tasks, such as project management
longer to reach a decision and often that decision and purchasing, would be carried out part-time by an
involves so many compromises that it is not a good one. existing employee.
For this reason, committees are not useful tools for
decision-making.
Putting this rule into practice, if the decision-making Changing the organization
(i.e. management) position can be filled by a as the project develops
well-qualified person with the respect and confidence
of others in the organization, do it. If not, have the An organization that is excellent for designing a project is
important decisions made by a triumvirate of managers. not usually good for operating it after completion. For
This last does not mean that you must hire three people any project, the organization should evolve along with
to do the job of one, rather it means that the person the project itself.
sitting in the manager’s seat has restricted authority and
must act together with two others in the organization to Initial organization: Phase 1
make decisions for actions beyond that authority.
The first task of project organization is to do a general
design of the project, obtain the necessary funding and
Creating the organization the approval and cooperation of the project participants. In
fact, this stage should probably be called the ‘pre-project’
There are three main categories of employment within an organization as an actual project does not exist until this
organization: phase ends.
To accomplish this task requires only a small team,
1) Long-term employees. Those who have terms often a single person. At this point, cost must be kept to
extending beyond the project period. Maintenance the minimum as no commitments of money or local
personnel are an example. support have yet been achieved. But the organization
2) Project employees. Those whose term ceases with must be strong enough to develop the project concepts
the acceptance of the completed project. The project and terms well enough to obtain funding and approval
manager is an example. commitments.
3) Temporary employees. Those with terms significantly The minimum project information usually required at
shorter than that of project employees. Technical this point includes:
designer would be one such job.
1) Intended class of recipient. General consumer, health
Category 1 staff, long-term employees, are generally centre, school, commercial establishment, industrial
hired specifically to work on the project and have no user, etc. Note that at this stage it is not necessary to
other responsibilities, though in the case of very small specify actual recipients, indeed providing such detail
projects they may share their time with other projects. may slow down or prevent approval.
Chapter-8.qxd 11/8/03 11:15 AM Page 52

52 Solar Photovoltaic
Project Development

2) General project development goals. What is the Detailed project design organization:
project meant to achieve? Phase 2
3) Scope of the project. How many of the designated
class of recipients will be served by the intended Detailed project design not only requires the technical
project? One village? All primary schools? capability to design the hardware aspects of the project,
4) General technical concepts. Is this to be a but also considerable negotiation with the various groups
photovoltaic, diesel, biomass or hydro project? A interested in the project to determine actual location,
central system or individualized power? List any specific recipients and the exact scale of the project
special technical aspects that may be important to to be implemented. Numerous administrative matters
either the funding agency or the approval committees, must be handled, such as detailed budgeting of money,
such as the ability to use the system for both time and personnel; determining procedures for
daytime commercial activities and nighttime domestic purchasing; preparing optimal shipping and warehousing
lighting. procedures; developing procedures for labour procurement;
5) Budgets. Reasonable estimates of money, time arranging for any special bank accounts needed for the
and personnel needed to do the project. Make sure project and arranging consultancies.
that between 10% and 15% of the total project For this phase, a project manager with two to three
cost is included for the process of detailed project people assigned to the project will usually suffice. The
design. three- or four-person team should include the necessary
6) Justification. How the project fulfills the needs of the technical, financial analysis and administrative skills to
recipients. How the project fits into development either directly carry out the tasks or to select the
plans. How the project meshes with other development necessary consultants. Though this organizational phase
projects being undertaken. should include site visits and some fieldwork, there is
Most rural electrification projects of the scale found in generally no requirement for personnel to be assigned in
smaller countries are initially designed by people in the field.
energy offices or electricity authorities who are not This phase is very important to the success of the
assigned full time to this task. There is generally no project. If adequate plans and budgets have been
justification in assembling a special project organization developed, the project administration becomes routine
or hiring people specifically for project development until and can proceed smoothly with management only having
a project concept is approved for funding and to respond to emergencies that are few and far between.
implementation. However, just because there is no formal If the detailed design is inadequate, the implementation
project organization does not mean that no organization phase will become one long emergency; an extended
exists. One person must, even at this stage, be series of crises with resulting inefficiencies destroying
designated ‘in charge’ of the project development and budgets and requiring many compromises to meet
must be given the resources and authority necessary to unplanned activities, all resulting in a poor quality
carry out this responsibility. project.
The director of the energy office, electricity
authority or company sponsoring the project should Project implementation: Phase 3
choose a project manager at this point who will be
capable — in terms of both skill and time — not only of Once detailed project planning has been completed
developing the project to the point of approval, but and the necessary approvals obtained for proceeding,
carrying it on to its successful completion. It is poor the actual implementation of the project can begin.
practice to have one person to design a project and The organizational structure needed for the project
another to implement it. There will be a strong desire immediately becomes more complex and requires careful
on the designer’s part to see that the concepts are design to maintain efficiency and minimal-cost operation.
carried out in the best possible fashion so that the Tendering, tender evaluation, purchasing, shipping,
design works. warehousing and testing of received components are the
Chapter-8.qxd 11/8/03 11:15 AM Page 53

Project organization 53

initial tasks, which are typically done in the office. Once manager, and if appropriate the technical advisors, should
materials are received, the focus of the project shifts to carefully inspect the project and ensure that all the
the field. installation has been properly carried out. If something is
The organization necessary for this phase shifts in not correctly installed at this time, the chances are that it
emphasis, as do the tasks. Initially the only field never will be. It is common for managers, in the press of
personnel to be hired will be those needed as field completion schedules, to decide to ‘fix those problems
supervisors — often only one person for projects being after the commissioning’ and then the job never quite
installed in a single location. Local labour for installation gets done. Always assume that the condition of the
will not be put on the payroll until just before project at the time of acceptance will be the best it will
construction starts, though it is important that field ever be.
personnel are selected and their commitment obtained as
soon as the need for them is established. If locating local
Project operation: Phase 5
labour is delayed until the last minute, either labour
availability or labour cost (usually both) may prove to be
The organization necessary to operate a project is
a problem.
generally very different from that needed to design and
Supervisors need direct access to the people being
construct it. Usually, a completely different team takes
supervised. Having a supervisor consistently out of
over after commissioning and provides for operation,
contact with those supervised is unworkable. If work
maintenance, spare parts control, fee collection and the
locations are widely separated, it will be necessary to
other tasks that continue as long as the project is
assign supervisory responsibility to a person in each of
operational.
the locations. No team should be put to work without
Experience with rural electrification projects shows
one person on that team having supervisory
that there is always a need for both field and home
responsibility.
office members of the operating organization. It is rarely
Prior to the actual start of construction, the field
successful for the complete maintenance, administration
supervisors should make final preparations for installation
and fee collection for a rural electrification project
and carefully check lists of materials to ensure that all
to be taken care of in the field. Technical assistance and
needed items are being shipped. When the materials arrive
spare parts are required from urban areas. To turn the
in the field, the field labour should be put on the payroll or
project over completely to a local government, village
under contract and the overall focus of the project shifted
cooperative or other wholly rural organization is to
to the field.
separate the project from its very roots: the technical
According to the type and size of the project, the
expertise and financial capabilities of an urban
project manager may remain in the home office or may
organization.
shift to the field at this stage. Generally, it is best
Even the most capable local organization will need
practice for the manager to shift to the field at least
technical support and the administrative ‘distance’ of an
until the installation process appears to be functioning
externally based parent. To ask members of a community
smoothly.
to act without prejudice against family members, close
As there is still a need for financial management and
friends, or for that matter traditional enemies, is asking
technical support, the project design team should usually
too much. The impartiality of an external organization
remain intact during the construction phase.
is needed when unpleasant tasks, such as service
disconnection, must be carried out or whenever impartial
Project acceptance: Phase 4 distribution of resources, such as spare parts, is required.
Although members of a community can deal with the
When the construction phase of the project is complete, practical aspects of such tasks, the responsibility and
acceptance by the various participating groups should authority must be located outside the community so that
take place. Before declaring the construction phase the local organization can properly claim an impartiality
complete and asking for acceptance, the project enforced from outside.
Chapter-8.qxd 11/8/03 11:15 AM Page 54

54 Solar Photovoltaic
Project Development

Institutional organization for village scale, management, technical and financial


skills may not be adequate to the task of
rural electrification electrification. Again, in a few cases there have been
successes, particularly in large communities, but as a
Although it is possible for a government Energy
general method for rural electrification the experience
Department or urban power authority to successfully
has not been good.
carry out a few rural electrification projects, any attempt
4) National or regional electricity cooperatives. Where
at large-scale rural electrification requires a specialist
the population being served goes beyond the
organization.
community and the size of the electrification project is
· The rural electricity organization must be capable of large enough to allow for the hiring of professional
managing the funding, installation, operation, managers and adequate technical support, this has
maintenance, repair and upgrading of large numbers been satisfactory. In this case, the basic approach is
of small power-generating systems. commercial and differs from a commercial utility only
· The organization must have a dispersed administrative in that the ownership is with the users and there is no
structure owing to the remote location of most of its profit motive. Abuses of financial responsibility have
plants. been common, however, and external audits and fiscal
· The organization must have the capability of training supervision are advisable.
large numbers of rural people having basic but 5) Independent rural electricity utilities. A rural utility
adequate technical knowledge of the installation, organization owns and maintains all generating and
operation and maintenance of remote power electrical distribution equipment using locally based
systems. technicians for maintenance. Payment is through fees
· The organization must have access to the financial charged for service rendered with customers being
and technical means to fund, design and repair the disconnected for non-payment of fees. This has been
systems. a particularly successful structure for solar PV-based
electrification. See Chapters 19 and 20 for more
Many different institutional approaches to rural
details.
electrification have been tried in developing countries.
The most common have been: An analysis of the relative successes and failures of the
different types of rural electricity organizational
1) Government-provided systems turned over to structures indicates that consistent success requires:
communities for operation and maintenance. This
has been generally unsatisfactory. While some 1) Professional management. Management skills for
communities do an excellent job of operation and technical projects are usually weak at community level.
maintenance, most do not and either government To attract good managers, the project level must be
must regularly provide additional, unbudgeted support at least regional in nature.
or the project fails. 2) Quality technicians, most of whom are locally
2) Government-provided systems maintained by based. Maintenance usually cannot be handled from an
government on a fee basis. In most cases this has urban location. Local technicians must be available and
not been successful. Government agencies are rarely adequately trained. Village-based owners can rarely
flexible enough to meet the changing demands of a arrange for continuing and adequate technical support.
rapidly growing rural electrification programme. 3) System disconnection for failure to pay fees. If
Village-based fee collections are not effective and there are no disconnections, fee payments will not be
transport of government technicians to the rural site regular or sufficient. A village administration usually
is expensive, so visits are not as frequent as good lacks the will to disconnect systems for non-payment.
maintenance requires. An external organization is necessary to enforce a
3) Village cooperatives. These have not generally been disconnection policy.
satisfactory. It has been difficult for villages to collect 4) An organization with a strong enough base to be
money from their own people consistently. At the able to finance expansion and modification as load
Chapter-8.qxd 11/8/03 11:15 AM Page 55

Project organization 55

structures change. Village-based electrification being served, they must be responsible only to the
schemes usually cannot raise the necessary money for rural electricity organization in their work. They should
system improvement or expansion. be formal employees and be paid directly by the
organization with no compensation from the
Therefore, a major rural electrification programme should
community itself.
be designed around an organizational structure equivalent
Without this administrative distance between the
to that of an urban electricity utility though it must be
organization’s representatives in the village and the
more decentralized. The following points are
village leadership, it will be impossible for them to
recommended for consideration in the institutional design:
disconnect systems for defaulting on payment or to
1) The organization should have links with the existing enforce regulations regarding safety and system
urban electricity authority and the government energy modifications.
agency, but financially and administratively independent. 6) The rural electricity organization should have
2) Developing countries rarely have the technical or operational administrative management dispersed to
financial resources to be able to afford duplication in the areas where service is concentrated. Central
rural and urban electricity organizations, but as the management should provide direction and supervision
administrative structure of the two is quite different, but day-to-day operations should be carried out in the
they cannot be effectively shared. Very few off-grid rural districts being served.
rural electrification projects have been successful The size of the administrative facility should be
when implemented by urban electricity authorities. related to the number of users serviced in that area.
3) The rural electricity organization should not duplicate A single village might have one technician both as a
physical resources already present in the existing representative of the rural electricity organization and
electricity supply system but should have access to to carry out maintenance, while a district with a large
them. Shared facilities, such as rural warehousing, is number of users might require a permanent office and
an example of possible physical links between the several technical and administrative employees.
urban and rural electricity agencies. These administrative centres should be fully
4) The rural electricity organization should have close responsible for the correct operation of the
formal links with other organizations relating to the rural generating systems in their district, the collection of
environment. Rural development agencies, development user fees in their district, appropriate preventive
banks, rural affairs bureaus, rural transport authorities maintenance of the systems under their jurisdiction
or any other organizations that directly relate to rural and the rapid repair of failed systems.
development should be represented on the board of The central office should provide policy directives,
directors, an advisory board or have some other formal support services for field offices, central accounting,
link with the organization. government interface and financial services. While the
5) Community representation by the rural electricity central office should provide direction and supervision,
organization at both technical and administrative levels the field offices should make all day-to-day decisions
should be full-time employees, paid by the authority relating to field installations and users. Disconnections,
rather than the community, and their independence however, are probably best ordered from the central
from the local political structure should be rigorously office.
maintained. 7) The rural electricity organization should have formal,
Though actual collections may be carried out by direct links with government offices obtaining and
the traditional community leadership, the rural disbursing aid and soft-loan capital funding.
electricity organization must have maintenance staff Large amounts of capital will be required for rural
operating within each electrified community and they electrification and if the organization does not have
must have the clear authority to disconnect users who direct access to those in government that negotiate
have not paid the established fees when so ordered for and distribute aid money, it will be unlikely to be
by the area manager. While these local maintenance able to obtain the sums necessary to expand
staff are expected to be members of the community services.
Chapter-8.qxd 11/8/03 11:15 AM Page 56

56 Solar Photovoltaic
Project Development

Usually this means having close ties to government Two distinct and very different organizational
Finance and Planning Departments. These close ties structures are required, the first being the organizational
can be horizontal through governing or advisory board structure necessary to design and build the project and
members, or vertical through the government the second the organizational structure needed to
department that has responsibility for supervising the operate it.
rural electricity organization. Of the two, the operating organization is much more
important. No matter how quickly and efficiently a
project is designed and installed, if it is not operated
Conclusions correctly the project is a failure. Unfortunately, the
organization that creates the project usually receives all
The organizational structure for a project changes the attention and the ultimate operation (and success)
continuously from project conception to final operation. of the project is left to chance.
Chapter-9.qxd 11/8/03 11:16 AM Page 57

Obtaining and
using consultants
9CHAPTER 9

What are consultants? for hiring a consultant, such as:

1) Requirements of the funding organization. Even


Basically, consultants sell knowledge. An architect hired though local staff may have more knowledge than any
to design a building is performing a professional service foreign consultant regarding the project, the funding
and is not a consultant. The same architect is however a agency may still require an external consultant. Many
consultant when hired to assist you in the selection of international funding sources such as the Asian
competing architectural designs. As a general rule, what Development Bank, the European Union and some
you get from a consultant is information. Admittedly country’s bilateral aid agencies commonly have such
there is considerable overlap between the concept of requirements written into project funding agreements.
professional services and a consultancy but the end result 2) Lack of confidence in local staff. There is always a
is the same: you pay for specialized knowledge. tendency to assume that an external expert is
There are consultants for just about everything somehow superior to someone local. Higher levels in
imaginable. Public-relations consultants for the politician, an organization may lack confidence in local
hair-replacement consultants for the balding, tennis capabilities and require external consultancies, even
consultants for the athlete. The type of consultant most though the local staff may be well qualified for the
likely to be involved in rural electrification projects are particular project envisioned.
technical consultants. They are simply people with 3) The need for someone external to the system to
sufficient knowledge in a technical field to be able to kill an unworkable project approved by higher
convince others to pay them for that knowledge. authority. Ill-defined and unworkable projects are
sometimes forced upon local staff for design and
Why hire consultants? implementation. An outside consultant may be able to
convince the project sponsors of its unworkable
The most common reason for hiring a consultant is that nature where local staff cannot. Remember that the
information or knowledge needed for designing or consultant’s recommendation cannot be defined in
implementing a project is not available to the project advance and the result may not be what you want.
staff and someone from the outside with that 4) The need for someone external to the system to
information or knowledge must be hired in order to recommend a good project rejected by higher
successfully complete the project. authority. Where a project is considered necessary
Even if the information or knowledge needed is and appropriate by local staff but government powers
available to the project staff, there may be other reasons at higher levels do not accept the concept, sometimes
Chapter-9.qxd 11/8/03 11:16 AM Page 58

58 Solar Photovoltaic
Project Development

positive recommendations from external consultants 4) Currency of response and of payment. You want all
will pave the way for implementation. Again, remember respondents to your consultancy tender to use the
that the consultant’s recommendation cannot be same currency in calculating their fees. Also in matters
defined in advance and the result may not be what of fee payment, it may cost you several extra percent
you want. to pay in a currency other than that of your home
country, so take that into consideration in your cost
determinations. Foreign consultants may not accept
Establishing consultancy payment in your local currency but your calculations
specifications have to be based locally. If a currency must be
converted, who pays the conversion fees may be one
Sometimes the person required for a consultancy is
of the negotiable points in the final contract.
known in advance and in that case negotiations can be
5) Unusual requirements and special hazards.
opened directly with that person. In other cases, what
Consultants should be prepared for normal situations in
amounts to a consultancy tender must be made and
their field. A hydro consultant hired to make a field
specifications for the consultancy must be written.
survey should expect to be hiking over rough ground
Specifying the services required from a consultant is a
and living in temporary camps. If that is the actual
similar process to specifying equipment for purchase.
case, then this need not be specified. But if an unusual
First you must decide what is required then express it in
situation exists, for example if the consultant will be
terms clear and specific enough to ensure valid
expected to parachute into the site and paddle a canoe
responses. These specifications are usually called the
out, it had better be specified. If the project entails
consultancy ‘terms of reference’ or TOR.
special hazards such as the requirement to enter a
It is not sufficient to ask for prices on ‘a solar panel’
zone of civil unrest, that should be spelled out also.
nor is it sufficient to ask for the cost of services to ‘design
6) Whose laws prevail in the case of contract
a solar house’. The term ‘specification’ includes the word
questions. Unless you specify where litigation will
specific and that is what you must be in order to elicit
take place if it is necessary, you may face the task of
meaningful responses from consultants. The consultancy
making a case in a court of law in the consultant’s
specification must include full details of what services are
home country instead of yours.
required, when they are required, where they are required
7) Penalties for non-performance. It is common for
and when and to whom a response should be made.
penalties to be charged if a consultant does not
Some of the items often overlooked in specifying for a
complete the task on schedule. Penalties can be
consultancy are:
applied for other areas of non-conformance but may
1) Special equipment to be provided by the be difficult to enforce. Meeting schedules, however, is
consultant. If someone is to be hired to evaluate a clear-cut and there are good precedents for enforcing
micro-hydro site, equipment to accurately determine penalties for late completion. Before actually
the vertical height between the source and the enforcing a penalty make sure that the tardiness on
turbine is necessary. If you expect the consultant to the part of the consultant cannot be traced directly to
bring it, you must include that in the specification. someone in the client country not fulfilling their part
Computers are increasingly considered a necessity of the consultancy agreement.
for consultants. What do you have available? Should
the consultant bring one? What about software? Locating suitable consultants
2) Report language. In what language do you want the
report? You may hire a German consultant to do the There is no publication or other simple method of
job but require the report to be submitted in English. advertising for consultants. It is usually necessary to
3) Measurement units. If you want metres, kilograms send consultancy tenders to individuals who are known
and litres you should say so. Otherwise you may get to have an interest in the type of consultancy proposed.
imperial gallons, pounds and feet. The problem is locating these individuals.
Chapter-9.qxd 11/8/03 11:16 AM Page 59

Obtaining and 59
using consultants

When there has been good prior experience with yes/no answer possible. If the answer is yes, then price is
consultants in a particular field, then it is reasonable to the determining factor. Evaluating consultancy tender
consider using them again. When no one is known to responses is generally more complex than evaluating
meet the requirements of the consultancy, then outside hardware purchase tenders.
advice is needed. Some sources of advice in locating Unless known to the evaluator, a consultant’s
consultants are: representation of his capability through a CV and job list
is all there is to go on. Poor consultants can sometimes
1) Government departments. Consultants that are
provide a very good CV and an impressive job list while a
familiar with your country and have some prior
consultant that is perfect for the job at hand may not
insight into the needs and cultural context of its
look so good on paper. If a consultant is not known to
people should be sought. This usually means
the evaluator, it is wise to call around to see if anyone
someone who has had a prior consultancy contract in
whose judgement you trust knows the person and can
your home country. One of the first places to seek
give an idea of the person’s capabilities and qualifications
names of possible consultants is in government
as applied to your project.
departments.
In evaluating consultancy tender responses, price is
2) Regional organizations. Knowledge of conditions in a
usually ignored until after completing the evaluation of
multi-country region is not as good as country-specific
the capabilities of the consultants responding. This is
experience but is better than no experience with
done by keeping prices separate from CVs and other
local conditions at all. Regional organizations, such
statements of qualifications. The respondents are
as United Nations regional projects, often use
grouped according to the evaluator’s estimate of the
consultants and would be willing to share information
suitability of their skills and experience to the project.
about those known to them.
One group will be excellent, another good, and so on
3) Professional organizations. Some fields, such as
down to the group who are ill-suited to your project and
architecture and medicine, have strong professional
should not be considered.
organizations that can assist you in locating
One approach to the price question is to then take
consultants within the profession. Some general
the respondents from the top group and see who is the
organizations, such as the International Solar Energy
lowest price in that group. This is an attempt to get
Society, maintain membership lists and sometimes
the best price from the best qualified. If you have a
actual lists of consultants and their specialities.
fixed budget, you may have to go down the levels of
4) Manufacturers and vendors. Used with caution,
competency to find someone within your budget. If no
manufacturers and vendors can assist in locating
respondents who have been judged as competent for the
competent consultants. You can reasonably expect a
project meet your budget, you will have to re-tender or
bias towards that company’s products, however.
enter into negotiations with one or more of the
5) Trade journals. Periodicals that specialize in a
respondents to try to bring the price down.
particular profession often carry advertisements or
Price should be viewed as definitely secondary
news relating to consultants in that profession.
to the quality of the consultant, however. A cheap but
6) Embassies. The commercial attaché at a foreign
poor-quality consultant may result in a project that
embassy generally will be able to assist in locating
costs far more to implement than one supported by a
consultants from that country. Sometimes lists are
more expensive but excellent consultant. As the final
published, sometimes the embassy is willing to make
project costs many times what is to be spent on the
limited enquiries for you.
consultancy, an error at the consultancy stage can cost
large sums at the implementation stage.
Evaluating consultant responses On the other hand, do not make the error of
believing that the most expensive consultant is the best
Whether or not a hardware item meets the tender one. As seen in the following section, the price charged by
specifications is usually a straightforward task with a consultants includes a premium for competence but many
Chapter-9.qxd 11/8/03 11:16 AM Page 60

60 Solar Photovoltaic
Project Development

other factors may enter into the pricing formula. A willing to work at a lower rate on a Pacific project to
consultant with excellent qualifications based in the region gain entry to the Pacific regional consultant’s market.
may charge far less than a consultant from a distant A consultant who suspects that a scapegoat may be
country who has never been to the region and knows little required should a marginal project fail may demand a
about dealing with the specific problems to be found higher fee to compensate for the professional risk.
there. 3) Time. The job may come at a time when there are no
other demands for the consultant’s services. A lower
How do consultants set their fees? price may be agreeable to fill the gap in the work
schedule. If the consultant’s schedule is nearly full, a
Consultants generally charge by the day. The cost of high price may be asked because your work is
using consultants is primarily determined by the market. competing with other work.
If everyone has plenty of hair, then hair-replacement 4) Where the consultant comes from. The market price
consultants are not much in demand and they are not for consultants in the same field is not the same all
expensive. If everyone’s hair is falling out, such over the world. European consultants tend to
consultants become quite expensive because they are in command higher fees than those with comparable
great demand. qualifications from Australia. Consultants from India
Besides being dependent on the demand for their are generally lower paid than those with comparable
services, the market price of a particular consultant is qualifications from North America. This reflects only
dependent on: the conditions of their home country market, not their
relative competence.
1) Qualifications. Those with long experience or
5) Side benefits. The consultant may be able to take
university degrees from top institutions tend to
care of other business on the trip to and from the
command higher market prices than those with lesser
client country and will accept a lower fee to help
qualifications.
attract your business. A lower fee may be acceptable
2) Success rate. A consultant that consistently solves a
to allow a consultant to look for more work in your
client’s problems will have a greater market value than
country, using your job as a springboard to increased
one with a lower success rate.
business in the future.
3) Prior fees received. Once a particular fee is received
6) Who is paying. Consultants may charge higher fees
from one client, that automatically becomes the
when the sponsor is an organization known for long
market value for that consultant and that fee can be
delays in payment or has complicated billing
expected to be asked from others.
requirements. Many international organizations take
In reality, it is not quite so straightforward as many other three to six months to make payment after billing.
factors enter into the final price quoted for consultant Employers known to be slow payers are often charged
services — though the market price is always a major more than those with rapid payment records.
factor. Some of the other factors are:
The meaning of all this is that consultancy fees vary. You
1) Personal. Does the particular consultant have a great should shop around if possible. Negotiation is appropriate
like (or dislike) for the organization doing the hiring? and expected. As timing often has something to do with
If a consultant particularly likes to work with the client price and availability of consultants, you should try to
organization or in the area of the project, or has keep the schedule as flexible as possible if you want the
friends and relatives there, a lower fee may be best price.
acceptable. If the consultant has had bad experiences
or simply dislikes working for the client organization, How much do you pay?
the fees may be greater than that set by the market.
2) Professional. Does the job have any professional Knowing the daily fee of a consultant is not enough to
benefits or potential problems? A consultant that has determine the total cost, even if the number of days is
never worked in the Pacific region but has excellent fixed. There are many opportunities for a consultant
qualifications from the Caribbean or Africa may be to add on other costs to the daily rate. Some of
Chapter-9.qxd 11/8/03 11:16 AM Page 61

Obtaining and 61
using consultants

these extra costs may be: and those that are flexible. Consultants have different
ideas of which terms are flexible and which are not. One
1) Payment of full daily fees during travel. Although the
consultant may absolutely insist on business-class airline
consultant is not actually providing you with services
tickets to the client country then take a taxi to the hotel
during his travel time, there may be a charge for time of
from the airport, while others will accept cut-rate economy
travel anyway. Some consultants do, some do not. At
tickets but demand to be picked up at the airport.
today’s rates for international consultants, this may
The negotiator also needs a clear idea of what
make several thousand dollars difference to your costs
the priorities are for the consultancy. In the heat of
when long or complex travel arrangements are involved.
negotiations for lowered cost, the goal of the
2) Payment of fees for calendar days rather than
consultancy must not be forgotten. For the best price,
working days. Some consultants charge on the basis
negotiations should be attempted, but remember that the
of a five-day working week, some on a six-day
quality of your final project — something that usually
working week, some on the seven-day calendar week.
costs some 10 times as much as the consultancy — is
3) Payment of expenses. The consultant may ask for a
directly dependent on the quality of the consultancy and
daily expense allowance, refund of bills receipted, or
saving a few dollars through hard negotiations may lower
expenses may be built into the daily fee. Refunding of
the quality of the consultant’s product and ultimately
bills receipted is dangerous because you have no control
cost much more due to problems with the project.
over what the consultant spends on hotels and food.
Enter into negotiations prepared to negotiate on
A daily allowance is safer, but you must know in
anything. Lower fees may be offered for schedule
advance what the actual rates are, so do not accept
changes favourable to the consultant. Consultants may
such phrases as ‘at internationally accepted Daily
make concessions for staged payments during the work
Subsistence Allowance (DSA) rates’ or some similar
instead of a lump sum at the end of the consultancy.
undefined amount. Note that the consultant may expect
Items, such as government-supplied ground transport,
different daily rates during travel or if there is to be
that cost you little may be seen as important and cause
work at different locations for your project.
the consultant to make important concessions in other,
4) Insurance. Although not common, some consultants
more costly, areas.
require countries to provide insurance during their stay.
From the consultant’s point of view, a reduction in the
Such insurance usually includes guarantees that the
length of the consultancy offers the best way to reduce
consultant will be provided air transport to a foreign
overall cost. This allows the consultant to maintain an
hospital if injured or seriously ill. Liability insurance to
acceptable daily fee structure and not make special fee
protect the consultant from civil proceedings during the
precedents just for your job, yet the goal of reducing the
performance of work may also be required.
overall cost to the client is attained. Do not hesitate to
5) Ground transport. Some consultants require
ask the consultant to offer suggestions for reducing
continuous access to client-paid ground transport.
the time needed in the client country through prior
This usually means a rental car. Others ask for
work by local people in collecting information needed
reimbursement for taxi or bus fares. Some are happy
for the consultant’s work, or the provision of local
with access to government transport when needed for
assistance during the work. Make sure of having a clear
specific tasks in the consultancy and take care of their
understanding of what the consultant expects to be done
personal transport out of daily fees.
before arrival and check that this preliminary work is
actually done beforehand.
Negotiating with consultants
When do you pay?
The response to a request to negotiate terms of a
consultancy varies from outright rejection to an open Before a consultancy begins, payment for transport
willingness to adjust everything from schedule to fees. to the consultancy site and return to the consultant’s
The negotiator must determine what aspects of home base is usually expected, in the form of prepaid
fees are important to the consultant (and therefore fixed) airline tickets. Some consultants require full or partial
Chapter-9.qxd 11/8/03 11:16 AM Page 62

62 Solar Photovoltaic
Project Development

prepayment of travel per diem and other incidental treat the consultant like a visiting dignitary, a better
costs of travel. Some require prepayment of a percentage job will be done for you if the consultant concentrates
of the expected total consultancy fee. As arranging on your work, not petty annoyances.
prepayments on contracts can be difficult, allow plenty of 3) Facilitate access to all relevant data sources. As
time for this task. the quality of the information provided to the
After arrival, a consultant may expect reimbursement consultant determines the quality of service, you
for expenses on a periodic basis (weekly, for example) if must make sure that the consultant has all the
the stay in the country is more than a few days. information needed and that it is as accurate and up
Fees are not generally billed until the consultancy is to date as possible. You should be willing to assist
complete and all requirements fulfilled by the consultant. the consultant in finding the way through your
This may not be the case in some longer consultancies government’s bureaucracy to locate specific
where progress is made in stages and bills for fees are information and reports.
presented at the completion of each stage. 4) Be as honest and candid as possible about
information relevant to the project. If you change
the facts to meet your own ideas of what they should
Working with consultants be, you might as well do the consultancy rather than
pay a large fee for a report that ends up as biased as
1) Smooth the way through arrival formalities. One the information you provided.
sure way to get a consultancy off on the wrong foot 5) Brief the overseas consultant new to your country
is to fail to make adequate preparations with customs on local culture and etiquette. While local people
and immigration for the consultant’s arrival. If a may forgive a foreigner for an inadvertent breach of
work permit or visa is required, make arrangements good social conduct, the consultant may not forgive
with immigration in advance. If the consultant will you for letting that sort of embarrassing situation
be bringing in special equipment that customs may occur.
consider holding for duty payment, make sure that 6) Give the consultant as private a place to work as
arrangements are made in advance with customs for possible. If the consultant can have an office with
clearance of the items. Be at the airport to help to phone, desk and computer so much the better. At
get through the formalities of arrival. least there should be a place where the consultant
2) Keep personal distractions to a minimum. Once can leave papers and work materials without fear of
the person is hired, it is up to you to use your them being disturbed before returning. You should
consultant’s rather expensive time in the most ensure reasonable access to office machines such as
efficient manner. As unhappy workers are not copiers, typewriters, computers, faxes, etc.
good workers, you should check that the consultant 7) Be flexible about work. There is no way you
is settled into satisfactory lodging, has access to can accurately predict what will be needed to
good food, and that adequate transport is available successfully complete a consultancy. Be prepared to
for getting to and from the place of work. Remember visit places or do things that were not anticipated in
that preferences in lodging and food differ widely the original consultancy plan. Likewise, where
from individual to individual. If the conversation the possible, let the consultant be flexible about work.
first day on the job includes a stream of complaints For report writing or reading background reports,
about the hotel, the meals served or difficulty in some consultants may work best at night in their
catching the right bus to get to the office, you have hotel, because of jet lag, others may prefer to work
not been doing your job. While it is not necessary to in the office after hours.
chapter-10.qxd 11/8/03 11:19 AM Page 63

Economic and
financial analysis
10 CHAPTER 10

Economic versus financial analysis electrification project are:


· Foreign exchange cost. This is the cost of using a
One of the most important aspects of making a decision country’s foreign exchange reserves to purchase
regarding which generating technology to use for rural components and services for the project from
electrification is relative cost. Two types of cost can be external sources. This is an economic cost because
considered. The first is money cost: those costs that can foreign exchange reserves are limited and using these
be directly accounted for by the exchange of money. The reserves for this project makes them unavailable for
second is economic cost. This is more subtle but no less other uses that could be of more value to the
important than the money cost. Economic cost includes country. There is also a cost if the exchange rate
the money cost but also considers the costs that are between the local currency and the external currency
not paid through money exchange. These are often is artificially maintained by government so that the
opportunity costs that result from using limited exchange rate is not the market value for the local
resources for a project thereby making them unavailable currency.
to others. · Trained labour limits. Technically trained personnel
Businesses usually use financial analysis when they are generally in short supply in developing countries.
want to compare the cost of different approaches to a When a technical project is put into service the
project. A business is interested mainly in cash flow and trained labour involved in that project is no longer
the non-money aspects of a project are generally not available for other projects, which may have to be
considered. Financial analysis is therefore usually all that delayed unless labour is obtained from outside the
is done. Public projects, however, rarely use money as country.
the sole criterion of success or failure and it is important · Release of untrained labour for other tasks.
that non-money aspects of a project be considered in Although rural electrification removes trained labour
addition to finances. from the market it often releases untrained labour for
For public projects, one way to look at the uses of the other uses. For example, electricity may be used for
two types of analysis is to say that the financial analysis pumping and moving water that may have been done
reveals whether we have enough money to do it or not. by hand before electrification. The people who were
The economic analysis reveals if the overall value of the pumping or carrying water can now work on other
project to the country is enough to make it worthwhile. tasks for the community. If that released labour is
A few examples of non-financial factors that used to the benefit of the community, there is a net
might be considered in an economic analysis of a rural economic income to the community. If the released
chapter-10.qxd 11/8/03 11:19 AM Page 64

64 Solar Photovoltaic
Project Development

labour is not useful for other tasks, then those people decision has been made to provide rural electrification
become a net economic drain on the community and but should the project use diesel or photovoltaics to
are a cost. produce the electricity. In this type of analysis, the
· Resulting changes in the money economy of the differences between the two technologies are important.
recipient group. When a community receives a rural This is a relative analysis because we are comparing one
electrification project, its use of money may increase, project to another to see what the differences are. The
decrease or stay the same. This change should be result is not the overall cost or benefit of the project but
considered in an economic analysis. If the net money rather the difference in cost between two approaches to
available to the community decreases because the same project.
of additional expenditures on fuel, labour, Relative analysis is generally easier and more accurate
maintenance and appliances, there is a cost to the than absolute analysis. This is simply because the
community. If the available money increases because number of costs that should be considered is lower
new sources of income are generated or productivity because many are the same and therefore do not need
of old sources improves, there is an economic income to be calculated.
to the community. For example, many of the vague, difficult to evaluate
· Opportunity cost of capital. The use of local capital economic changes that take place in a community as a
investment funds or aid money for the rural result of rural electrification will be the same whether
electrification project makes those funds unavailable photovoltaics or diesel generators are used to produce
for other projects that may be of more economic the electricity. These changes have to be considered in an
value to the country. absolute analysis, but not in a relative analysis where
· Environmental effects. There are environmental only differences are evaluated. In fact, only financial
costs to all projects. Some have greater effects than differences have to be considered in most relative
others and should be analysed specifically for the analyses because the non-financial factors are about the
project at hand. same for both approaches to the implementation of the
rural electrification project.
Many other non-financial costs and benefits could
When comparing technologies for a rural electrification
be considered in an economic analysis, ranging from
project, the economic factors are often converted to what
relatively easy to define changes in a community to
are considered equivalent money values so that they can
subtle, very difficult to evaluate social modifications that
be combined easily with money costs and benefits in an
result from rural electrification. Whether these items are
analysis. In some cases, such as foreign exchange costs,
considered in an economic analysis depends on the
this can be done with some justification. In other cases,
importance assigned to them by government and to the
such as the cost of cultural changes to a community or
level of impact caused by rural electrification projects.
the cost (or benefit) of the change in use of untrained
labour after rural electrification, cannot easily be equated
Absolute versus relative analysis with money. Such conversions are arbitrary and depend on
the point of view of the person making the conversion.
In analysing projects in either the financial or the Another approach to comparing the relative economic
economic sense, we can make an absolute analysis, cost of different technologies for a project is to make a
where the economic costs and benefits are calculated on numerical analysis for the financial part and then to make
the basis of a single project concept and all factors are a comparative list of non-monetary costs and benefits
considered. The end result of such an analysis should be that result from the use of the different technologies.
the net cost or benefit of the project. An absolute The financial analysis gives a numerical result that can
analysis is often made to decide whether or not to go be compared. The list of non-monetary costs and benefits
ahead with a project at all. is examined for major differences between the two
In other cases, the problem is to decide between technologies. Where costs and benefits do not differ, they
several possible approaches to a project. For example, the are ignored. Where there is a difference, some arbitrary
chapter-10.qxd 11/8/03 11:19 AM Page 65

Economic and 65
financial analysis

weight is given to the difference and an overall judgement they should pay something like the US$200 a month that
made of the importance of the differences in deciding on a I would have received if I had bought the house and
technology for rural electrification. rented it out.
For example, suppose that a rural community of 2,000 Generally, for financial analysis, interest is expressed
is to be electrified either by a stand-alone diesel system as a percentage. The word percent comes from the Latin
or by connection to a diesel-powered grid that already words per and cent, where per means ‘for each’ and cent
serves 250,000 people in urban areas. There probably will means ‘hundred’. So percent in financial terms means
be little difference in the non-financial results of the how many dollars are charged for each US$100 being
project and only the relative cost of the two approaches used for the period of time being considered. As a year is
to the project will have to be calculated. If the analysis usually the time period for expressing interest charges,
included individual solar units as one of the technologies percent usually means ‘the number of dollars charged for
proposed, then some non-financial factors would have to the use of US$100 for one year’. In formal financial
be considered such as the economic value of not having terms, this is ‘annual interest’.
recurring costs tied to foreign fuel prices. Imported fuel So if I want to borrow US$500 from a source that
may have to be used for both diesel and grid-generated charges an annual interest rate of six percent (usually
electricity, so if those were the only two technologies written 6%) then for every US$100 I borrow, I will have
being compared, the fuel requirement would be about to pay US$6 a year. I am borrowing US$500, so my
the same for either approach. If solar PV were one of the interest charge in one year will be 500 × US$6 = US$30.
options being compared, then imported fuel would not The term for this kind of interest is ‘simple interest’.
be needed for the PV but would be needed for the diesel, You just multiply the number of hundreds of dollars
so the economic cost to the country in foreign exchange (or whatever monetary unit you are using) by the interest
reserves and energy independence would have to be rate in percent, and you have the annual cost of using
included in the analysis. the money.
The term for the money being lent is the ‘principal’.
So if I borrow US$2,000 at 7% for one year and I am
Financial analysis overview charged US$140 in interest, the US$2,000 is the
principal, the 7% is the interest rate and the US$140 is
Interest the interest.
Note that what we are really doing to make the
A number of specialized terms are used by consultants calculation is to divide the total amount of money by
and professionals when discussing financial analysis. 100 then multiply that answer by the interest in
Probably the most important of these is ‘interest’. percent:
The concept of interest is a simple one. It is the same Borrowing US$2,000 for one year at 7% will
concept as rent. When a house is rented, the person cost what in interest?
using the house is expected to pay a sum for the use of
US$2,000 ÷ 100 = US$20 (there are
the house. Interest is nothing more than the rent charged
20 hundreds of dollars in US$2,000)
for the use of money. Just as the amount charged for
renting a house changes with time and the market US$20 × 7 = US$140 interest in a year.
conditions, so does the rental charged for the use of
When you look at books on financial analysis, you will
money. Interest is what is charged for not being able to
find that the usual way the calculation is made is to
use the money for something else.
divide the interest rate by 100 instead of the principal,
If I buy a house for US$20,000 and rent it to someone
and then multiply. The end result is the same, whichever
for US$200 a month, then my US$20,000 is making me
method you use:
money: US$200 a month less the cost of maintaining the
7 ÷ 100 = 0.07
house. The idea of interest is that if I lend someone else
the money that I could have used to buy the house, then US$2,000 × 0.07 = US$140 (simple interest).
chapter-10.qxd 11/8/03 11:19 AM Page 66

66 Solar Photovoltaic
Project Development

Compound interest To calculate future value you need to know:


1) the amount of the principal
Most of the actual interest calculations that are used 2) the interest rate
in financial analysis are not for simple interest but 3) the number of years to the time when future value is
for compound interest. As you may have suspected, to be calculated.
compound interest calculations are not so simple as
simple interest calculations. Present value
Suppose that I can lend money and receive 8% While future value determines the value of today’s money
interest on it. Suppose also that I own a house and have sometime in the future, present value says how much a
rented it to someone who pays US$200 a month. Every future sum of money is worth today.
month, I receive US$200 from the house rental. If Another way of explaining present value is that
every month I then take the US$200 and lend it to present value of a future sum of money is that amount
someone else, I will receive an additional 8% from that that must be invested today at the prevailing rate of
loan. So not only do I receive payment for the use of my interest to result in the amount needed in the future.
original US$20,000 that I used to buy the house that I Suppose I expect to have to replace US$960 worth
rent, but I can even make a little more by lending the of batteries in a PV system in five years. So five years
money I receive in rent. from now I will have to spend US$960. If I can get 4%
Compound interest assumes that as soon as any interest on my money over that five-year period, then I
money is received, then that money can be immediately will not need US$960 today in order to have US$960 in
lent and more interest received. In calculating compound my hands in five years. The present value of US$960
interest, you need to know how often the money is five years from now is therefore the amount of money I
received. In the house example, the money is received have to invest today in order to have US$960 in five
monthly, so the interest is said to be compounded years. Suppose that I have US$800 today and I invest it
monthly. at 4% for five years. How much money will I have in
five years?
Future value The simple interest received from US$800 at 4% will be
Because money can be lent and interest received, the US$32 per year (800 × 0.04) so over five years I will
amount available changes with time. If US$20,000 is lent receive US$160 (5 × 32) in interest and my total will be
at 9% for one year, at the end of the year when the loan the original US$800 plus US$160 in interest or US$960.
is paid back the lender will have US$20,000 plus interest The future value of US$800 invested at 4% simple
of 20,000 × 0.09 = US$1,800 or a total of US$21,800. interest for five years is therefore US$960. Also, the
This total amount that will be received one year in the present value of US$960 received five years in the future
future is called the future value of the money that is at 4% simple interest is US$800.
held today. Present value and future value are therefore two ends
If I have US$5,000 and I can lend it at 6% annual of the same process of having money at interest for a
interest, then the future value of my money after three period of time.
years will be (using simple interest calculations): One way to calculate the present value of a future
US$5,000 × 0.06 = US$300 (interest per year). sum of money is to try starting with different amounts
and seeing how much money will result in the future at
So, in three years, the total interest received will be:
the prevailing interest rate. When an amount is found
US$300 (interest per year) × 3 years = US$900
that results in the amount required in the future, you
(total interest).
have the present value.
Thus the future value in three years of US$5,000 lent at For example, we want to know how much we need
6% simple interest will be: today in order to pay US$1,000 for battery replacements
US$5,000 (principal) + US$900 (interest) = five years in the future. The highest interest we can get
US$5,900. on our money is 4%.
chapter-10.qxd 11/8/03 11:19 AM Page 67

Economic and 67
financial analysis

We know that the amount needed today Calculating when there is compound interest is much
will be less than the US$1,000 we need in more difficult. Fortunately a formula can be used to find
five years because the interest will add the exact present value of a future amount of money
money to our original amount. Pick a smaller placed in an account with compound interest:
number than US$1,000 and work out how present value = future value divided by the
much we will have at the end of five years. annual interest rate plus one raised to a
Try, say, US$600. power equal to the number of years;
Interest per year on US$600 at 4% will be or, in mathematical terms:
US$24. So in five years we will accumulate PV = FV/(1 + I)n
US$120, so the total at the end of five years
PV = present value
will be US$600 plus US$120 = US$720. We
need US$1,000, so US$600 is not enough to FV = future value
start with. Try US$800. I = annual interest rate (expressed as a
The interest per year on US$800 at 4% will be decimal, i.e. 4% = 0.04)
US$32, so at the end of five years we will n = number of years from the present to the
have US$160 in interest plus the original future date.
US$800 principal for a total of US$960. Still
not quite enough. So try US$900. This can be calculated with a computer or with a scientific
calculator.
Interest per year on US$900 at 4% is US$36. Doing the example problem of US$1,000 in five years
Over five years that will yield US$180. at 4%, the result is:
US$900 + US$180 = US$1,080, which is more PV = 1,000/(1 + 0.04)5
than we need. The actual amount will
therefore be between US$800 and US$900. PV = 1,000/(1.04)5
Try US$850. PV = 1,000/1.2763
Annual interest at 4% on US$850 = US$850 PV = US$821.93.
× 0.04 = US$34. Over five years that will total
US$170. So at the end of five years, the total So the present value of US$1,000 five years in the future
available to buy batteries would be US$850 with a 4% interest rate continuously compounded is
+ US$170 = US$1,020. Still not exactly right. US$821.93. This means that if I place US$821.93 in a
Note that this calculation means that the bank today at 4% compounded interest, when the time
future value of US$850 placed at 4% interest comes to buy batteries in five years, I will be able to
for five years will be US$1,020 and at the withdraw US$1,000 from the bank. Note that the actual
same time it means that the present value amount in the bank after five years will probably be a
of US$1,020 five years in the future with little less than US$1,000 because the bank may only
4% interest is US$850. compound the interest quarterly. The formula is still a
reasonable method to use as the difference is small and
We can try US$840 if we need to get even the overall accuracy of the estimate is good, given that
closer. other factors are also uncertain, particularly the interest
US$840 × 0.04 × 5 = US$168.00. rate which will probably change over the five-year period.
US$840 + US$168 = US$1,008. Still closer to
the goal of exactly US$1,000.
Life cycle cost
We can keep changing our trial number until the answer
is exactly US$1,000 but it may take a number of trials to When analysing a project either in the financial or the
find the exact amount. economic sense, it is not enough just to look at the initial
chapter-10.qxd 11/8/03 11:19 AM Page 68

68 Solar Photovoltaic
Project Development

cost of the project. In the future, there will be the cost to be similar for the different technologies being
of operating the project, repairing and maintaining the considered. As it is the differences, not the exact dollar
equipment and ultimately disposing of the remains when amount that we are interested in, these errors tend to
it wears out. Often these costs will be greater than the cancel and the result will still be useful in deciding which
initial cost of purchase. If these recurring or future costs technology to use.
are ignored when analysing a project, the analysis will Unfortunately, an absolute life cycle analysis has
not provide a true picture of the real cost of the project. to made in order to determine what to charge for
The method for analysis that includes all the costs rural electricity services. As the charge must equal the
associated with a project over its life is called life cycle cost, cost estimates have to be accurate if the
costing or LCC. charge — whether to the consumer or to the consumer
Simply put, a life cycle cost analysis is an attempt to plus a government subsidy account — is to cover the
produce today the set of project accounts that will exist actual cost of rural electrification. This is the most
when the project is finally disposed of at the end of its difficult part of analysing rural electrification projects and
useful life. We are placed in the position of predicting the will usually require frequent revision as the project ages
life of the project, estimating all the costs associated and more accurate data become available. For this
with it and forecasting when those costs will occur. As reason, fees usually have to change with time.
the result of the analysis is no better than the quality
of the ‘estimating’ ‘predicting’ and ‘forecasting’
mentioned above, whoever does a life cycle cost analysis Procedure for life cycle
must understand the project in detail, what it does and cost analysis
what will be required to keep it running.
To do an absolute life cycle analysis, where all the It is important that not only do all costs appear in the
costs must be exact in order to yield exact results, there analysis but that the timing of the costs is accurate.
must be an excellent understanding of the project Because of the time value of money, the present value
costs and how the project will be used, operated and of money is less and less the further in the future
maintained. Usually, such accurate cost information will an expenditure must be made. Thus, the effective
only be available for projects that duplicate others present-day cost of US$1,000 for batteries five years in
that have been in place for long periods of time. Grid the future with an interest rate of 4% we have already
extensions are of this type in most countries. Many rural determined to be US$821.93. If the battery life is eight
grid-extension projects have been carried out in past years instead of five, and the US$1,000 will not have to
years and it should be relatively easy to make an be spent until the project has been in operation for eight
accurate estimate of how much it will cost to install and years, then the present value (the equivalent present-day
operate another one. On the other hand, solar rural cost) will be:
electrification is not common enough in most countries PV = FV/(1 + I)n = 1,000/(1.04)8 = US$730.69
for there to be enough data to accurately predict future
instead of US$821.93. This is simply saying that it costs
costs for new projects.
less in a solar project if batteries last longer.
Fortunately, most of the analyses that must be made
A typical life cycle analysis for a rural electricity
for rural electrification projects require relative rather
system will include the following costs:
than absolute analysis. That is, we compare the life cycle
cost of two different types of installation and try to 1) Initial cost of installing the project. This includes
decide which would be better. In this case, a number of the cost of buying the components, shipping, storage,
factors are the same for each type of installation and labour, administration and any other costs incurred
therefore do not enter into the comparison. Only a few prior to the actual commencement of the project
major differences will exist that will have to be estimated. operation. These costs are usually lumped in year one
A further aspect of a relative analysis is that when of the project accounts even if it took over a year to
someone estimates costs, the errors in judging costs tend get the project running.
chapter-10.qxd 11/8/03 11:19 AM Page 69

Economic and 69
financial analysis

2) Replacement of components when they wear out. accountants and others who are not directly involved
All components wear out, though not all at the same with the operation or maintenance of the project are
rate. In a solar project, batteries are often assumed to part of administrative costs. If one manager oversees
have a five- to eight-year life, controllers seven to several projects, the manager’s salary should be
ten years and panels 15 to 20. If similar components divided among them. The cost of telephones, of
have been used in other projects, then there may be electricity for the office, office rent and other such
historical data as to their actual service life, otherwise expenses that are not directly incurred in operating
educated guesses are the best that can be made. the project come under this account heading.
3) Regular maintenance. This includes labour, travel
costs, administrative costs, the cost of storing spare Term for life cycle costing
parts, minor material costs and the various other
periodic costs that are part of regular maintenance. In making accounts for every year of the life of a project,
Do not forget to include such mundane but significant one of the first things to decide upon is the number of
things as power-house repairs. All maintenance costs years that the project is expected to be in operation
that can be predicted should be included. without major modification. Usually, this is the effective
4) System overhaul costs. In the case of some types life of the most expensive components or the period of
of rural electricity systems, the equipment must time that the project will be in use before being replaced
periodically receive special maintenance, often called by another.
an overhaul, in order to maintain system reliability. Photovoltaic projects are often analysed using a
For example, a diesel engine usually requires regular 15- to 20-year life, diesel 10 to 15 years, grid extensions
maintenance plus every five years or so it must be 20 to 30 years, hydro 15 to 20, and so on. There is no
stripped down and many worn parts replaced at specific rule that should be followed in deciding the
considerable cost. These overhaul costs should be useful life of a project, but the period chosen has a
listed as a separate item and placed in the accounts definite effect on the results so there should be some
at the time they are expected to be carried out. So rational reason for it. If the LCC analysis is to be used for
if an engine costs US$10,000 and the manufacturer securing an external loan, most lending agencies assume
(or local experience) indicates an overhaul cost of a 15-year effective life for electrification projects.
US$3,000 every five years and replacement after
fifteen years, then the LCC accounts should show the
initial cost of US$10,000 in the first year, additional
Analysis for decision-making
US$3,000 costs for overhaul in years 5 and 10 and
Once the LCC accounts are complete, an analysis can be
another US$10,000 replacement cost in year 15.
carried out to decide the best design for a project.
Note that this is in addition to the regular
For rural electrification projects, several key pieces of
maintenance costs for oil, replacement of minor
information can be obtained from the LCC accounts:
parts, labour, etc.
5) Operating costs. This is the cost of field personnel 1) Capital cost. This is generally the figure that begins the
operating the project and those field costs that may accounts. It is the cost of the project up to the point of
be directly allocated to the project, such as local commencing the delivery of electricity. Capital cost for
transport costs, local housing for employees, fuel and rural electrification projects is generally borne by either
oil for operating a diesel generator and local spare the utility company or the government — although the
parts storage costs. actual funds may be obtained through grants from
6) Administrative and overhead costs. Sometimes funding agencies.
lumped with either maintenance or operating costs, 2) Recurring cost. This is the cost per year of the project
the cost of administering the project once it is after it begins operation. Generally, this cost is borne
operating is best treated as a separate item in the LCC by the user, though part may be borne by the utility or
accounts. The salary of the manager, of secretaries, government if subsidies are involved. This figure will
chapter-10.qxd 11/8/03 11:19 AM Page 70

70 Solar Photovoltaic
Project Development

provide a means of determining how much money will Lotus 1-2-3 or other computer-based spreadsheet
have to be available from the user community to help programs allow the computation of NPV quickly,
to decide if the community actually has the necessary accurately and easily.
resources to pay for the electricity delivered.
3) Cost per unit served. For conventional power systems Effect of interest on analysis results
(grid-based central generation such as diesel or
hydro) this may be per unit of electricity, usually the If we use the NPV method of comparing project costs,
kilowatt-hour cost. For PV systems, kilowatt-hour the results will be affected by the interest rate used. In
costs are less meaningful and the costs for specific projects, the term ‘discount rate’ is often used instead of
services (such as lighting, refrigeration, pumping, etc.) interest rate. For our purposes they are the same thing.
are calculated. Also, per household cost or per person The term discount rate has a slightly broader definition
cost can be calculated and may be useful for than interest rate but for the purposes of analysis as
comparison purposes. defined here, the difference need not be considered.
4) Maximum funding requirement. As the LCC As a general guide, the discount rate used should not
accounts are made with at least annual — and be lower than the interest that local banks provide on
sometimes monthly — detail, it is easy to see the savings accounts nor higher than the interest charged for
maximum amount of money that will be needed at loans from the local development bank.
any one period over the life of the project. This is
useful because for most electrification schemes,
Effect of inflation on analysis results
particularly solar, the early years have very low
funding requirements. After five or so years,
Inflation means that, as time passes, it will cost more
however, major expenditures for replacing batteries
and more to purchase goods and services. What is
or engine overhaul become necessary and if funds
actually happening is that the value of money changes
are not available then the project fails. The LCC
with time. It is much like having interest charged on all
accounts are very useful in helping administration,
money in circulation. So an inflation rate of 5% per year
government and users avoid the common mistake of
means that things that cost US$100 will cost US$105 a
lowering electricity charges after a few years
year later.
because there is a large surplus in the account, then
In terms of project analysis, inflation and interest
when a major expenditure for battery replacement or
rates interact. For rough analysis — as here — the
engine overhaul is required, insufficient funds have
effective time value of money involved in the project will
been collected and the project cannot be repaired.
be the bank interest rate minus the inflation rate. When
In comparing projects, one method often used is to inflation is high, banks must charge high interest because
determine the total present value of each project. What money is losing its value over time and there are strong
this means is that the income and expenditures for each pressures to spend money today when it is worth more.
future year are converted to present value then totalled To convince someone to put aside money for a long time,
for a net present value (NPV) for each of the projects they must be convinced that despite the lowered value of
to be compared. The NPV gives a relative overall value money over time, that the interest is high enough to
for the project over its entire life. For this comparison cover that as well as provide a reasonable additional
to be appropriate, the analysis must use the same total amount.
life for all the technologies being compared, typically Inflation changes dramatically with changes in world
fifteen years. economic conditions, with changes in the local economy
As we have to separately calculate the present and sometimes seemingly for no reason at all. It is usually
value for the expenditures in each year of the life of impossible to accurately predict inflation rates years in
the project, when comparing several different projects advance and, as a result, analysis using inflation rate
each with a 15- or 20-year life, this becomes a adjustments are often inaccurate. Fortunately, there is a
time-consuming and error-prone manual task. Excel, way around this problem. Though inflation rates (and the
chapter-10.qxd 11/8/03 11:19 AM Page 71

Economic and 71
financial analysis

interest rates that occur at the same time) may change LCC account sheets and changing only the number of
radically over time, the difference between the inflation years between battery replacements will show how much
rate and interest rates is fairly constant. This usually is effect battery life has on overall project cost. If the
from 4% to 8%. So if inflation is rampant at 15%, interest project cost is particularly sensitive to changes in a
rates usually are around 20%. If inflation is low, say particular component cost, then that component should
2% per year, then interest rates are around 7%. be carefully selected for minimal cost and its interaction
Because we are making a relative analysis (comparing with other component costs considered.
the financial characteristics of different projects) we For example, PV system costs are very sensitive to
can ignore both the actual inflation rate and the actual changes in battery life. The life of a battery is sensitive
interest rate and use as the effective interest rate this to the average level of discharge taking place while in
4% to 8% difference. An interest rate of 6% is suggested service. This in turn is determined by the size of the
as one that is suitable for general use in the present solar panels charging the battery. Changing the cost of
value calculations for a comparative LCC analysis. the panels does not change the overall project cost as
rapidly as changing the life of the batteries. Thus by
Sensitivity analysis increasing the size of the panels (not a very sensitive
cost) the battery can be made to last longer (which is a
The result of the LCC analysis is a powerful tool to assist cost-sensitive factor) and the overall system LCC reduced.
the decision-maker in determining the best design for Creating just one LCC by hand is a slow process with
a project. It is a particularly useful tool when used to many opportunities for errors to creep in. To make
determine what aspects of a project have the most several, as is necessary for sensitivity analysis, becomes a
financial impact on its overall cost. The way to analyse task few people would be interested in undertaking
the sensitivity of project cost to changes in component manually. However, by using a computerized spreadsheet
costs is to create a number of LCC account sheets with representation of the LCC accounts, such changes can be
changing values for various items in the accounts. For made almost instantly and it is easy to find out what
example, what effect does the life of the battery have effect different parts of the cost picture have on the
on the overall LCC of a PV project? Creating several overall cost of the project.
Chapter-11.qxd 11/8/03 11:20 AM Page 73

Determining the best type


of rural electricity system
11 C H A P T E R 11

The technology decision Disadvantages:


· fuel often requires use of foreign exchange
Five major technology groups have been successfully used · generally there is foreign control over fuel price and
for rural electrification: (1) grid extensions; (2) small availability
hydro; (3) steam from biomass; (4) diesel; and (5) solar · noise, noxious smoke and smell
photovoltaics. Though wind, biogas, gasifier and ocean · fuel is toxic and may damage land and sea
energy systems have all been tried for rural electrification environment
at one time or another, their long-term success rate has · short useful life of fuel and machinery
been low and should be considered as still experimental · functions inefficiently and with higher
for the purpose of rural electrification. maintenance requirements at light loads
Each technology has advantages and disadvantages to · relatively high training and maintenance cost
the user and the installer. Following is a list of the · rural fuel availability is controlled by outside forces
principal advantages and disadvantages of each such as shipping schedules, labour availability,
technology for rural electrification: access to urban fuel stocks, etc.

Biomass-fuelled steam central system


Diesel central system
Advantages:
Advantages:
· locally supplied fuel
· lowest initial cost · moderate to low maintenance requirements
· fuel generally readily available though dependent on · exhaust heat sufficient for process heat use
shipping and external suppliers · quiet operation
· fuel easily stored and not bulky · fast response on load changes
· replacement parts readily available · mechanically simple
· rapid speed response on load changes · long useful life.
· short time between start and availability to system
Disadvantages:
· rapid, simple shutdown process
· moderate in bulk and weight · intermediate capital cost
· little operator training required. · smoke
Chapter-11.qxd 11/8/03 11:20 AM Page 74

74 Solar Photovoltaic
Project Development

· large space needed for fuel storage and drying Solar PV central generating system
· high labour requirement for operation and fuel handling
· long time (up to 1 hour) between start and availability Advantages:
to system
· no fuel requirements
· long time needed for shutdown (up to 1 hour)
· instantaneous response to load changes with excellent
· treated fresh water needed
voltage and frequency regulation
· bulky and heavy
· unattended operation
· limited availability of spare parts
· special appliances not required
· well-trained operators needed for safe operation
· no moving mechanical components
· inefficient at light loads
· low environmental impact.
· large fuel volume used can produce serious
environmental damage Disadvantages:
· use of biomass for power generation may reduce · high capital requirement
availability of fuel for households · power quality may not be good, causing problems with
· long-term availability and cost of fuel uncertain. some appliances
· highly trained electronic technician required for
Small hydro central system maintenance
· system reliability poorer than most other competing
Advantages: technologies
· long useful life · spare parts not readily available
· low maintenance · limited systems experience except in monitored
· unattended operation except at start-up and demonstration projects
shutdown · lowered efficiency at light loads
· no fuel requirements · requires a large, shade-free area
· quiet and no smoke · specialist engineering services required
· reasonably rapid response to load changes · power capacity is weather dependent.
· short time between start and availability of power
to system
Solar individual systems
· short shutdown time
· possible secondary use for water behind dam or at
Advantages:
turbine exit
· high percentage of local component in total cost · simple proven designs available
usually possible · easily serviced
· usually low environmental impact although water · components modular and few in number
diversion, civil works construction and water output · little training needed for installation and field
from the turbine may have a negative impact. maintenance
· size can be optimized to load
Disadvantages:
· moderate capital cost (high component cost but no
· long construction time grid cost)
· high capital cost · readily available spare parts
· poor replacement parts availability · all the advantages of individual systems over central
· availability of power tied to weather systems
· not many suitable sites · system easily modified to accommodate changed
· flood damage likely appliance mix
· specialists in design and supervision of construction · rapid installation possible
required. · no cost premium for 24-hour power availability
Chapter-11.qxd 11/8/03 11:20 AM Page 75

Determining the best type of rural 75


electricity system

· very low environmental impact cost, however, may be too high to be justified and
· no noise or smoke individual or community electricity supply systems will be
· little change in efficiency with load changes necessary.
· instantaneous response to load changes Where the grid extension is too costly and a
· simple design can be done locally stand-alone system must be installed, the primary choice
· no fuel required. is between central power and individual solar power.
Where the load is almost exclusively domestic, individual
Disadvantages:
power systems are clearly technically and socially superior
· power availability somewhat dependent on weather to any central system. Individual systems are usually also
· expensive low voltage appliances or expensive power financially superior unless the houses are very close
converters required together, a community grid already exists or a grid
· requires shade-free mounting location extension to that community can reasonably be expected
· requires more customer attention and training than to occur within five years of the initial installation.
other systems Where a significant industrial or commercial load exists
· maintenance personnel must always travel to within the community, the decision to interconnect all
customer’s site for service, carrying with them all consumers with a central power source or to keep the
necessary tools and parts. commercial and domestic loads separate must be made
on the basis of (1) the type of commercial load;
Conclusions (2) the timing of the commercial and domestic load
peaks; and (3) the relative scale of the commercial and
Combining advantages and disadvantages, we can rank
domestic loads. Cost analysis and experience indicate that
the power-generating technologies as follows:
unless the commercial load peaks are about equal to the
Individual systems domestic load peaks and occur at distinctly different
times, the best choice is usually to keep commercial
· Only solar photovoltaics should be considered. generation and domestic generation separate.
Again, individual systems for the domestic load are
Central systems
usually the most satisfactory though the commercial load
· Where cost competitive, small hydro provides may require diesel, hydro or steam central generation
the simplest, most reliable option. if it is over a few kilowatt-hours per day.
· Where a continuing, adequate supply of low-cost
biomass fuel is available, small steam systems should Centralized power versus individual
be considered. solar power systems
· Diesel systems should be considered if biomass or
hydro systems are shown to be technically or Of all stand-alone rural electrification technologies, only
economically inappropriate. solar offers an acceptable individual power system option.
· Central solar PV systems should be considered only There are substantial economic and social advantages to
after other technologies have been eliminated and individual power in remote, rural sites making solar an
then only for concentrated loads associated with important option for national-scale rural electrification.
important social or economic units such as When compared with stand-alone central systems,
government centres, telecommunications or the major advantages of individual systems are:
community water supplies, but not for general village
1) There is no power grid. The resulting cost savings,
electrification.
particularly for communities having widely separated
The first consideration for new rural electrification should houses, is often greater than the capital cost
be the extension of an existing grid. For reliability, power differential between diesel and solar power.
capacity and operating cost, grid supply is generally the The experience in the Pacific Islands is that for new
best of all rural electricity supply options. Initial capital rural electrification it is usually cheaper to provide
Chapter-11.qxd 11/8/03 11:20 AM Page 76

76 Solar Photovoltaic
Project Development

equivalent electrical services using individual solar 5) Appliances designed for low-voltage dc must be
than small diesel with a grid. used rather than standard mains appliances.
2) Individual systems can be sized to fit individual Although this may appear to be a disadvantage at
needs, making power cost truly proportional to first glance, it turns out to be a major advantage of
energy use. Wealthy families requiring refrigerators, individual systems. The primary advantage results
videos, fans and other capabilities beyond lighting from the higher efficiency of ‘solar’ type appliances
can have a system large enough for their needs, compared with standard commercial models. In the
while the family requiring only basic lighting need case of refrigerators, ‘solar’ units often have half
have only a small system at correspondingly lower the energy requirements of standard ac units for an
cost. In the case of a central system, the capacity equivalent amount of cooling. This directly translates
of the system is usually dictated by the demands of to requiring half as large a generating capacity.
a few affluent consumers who rarely pay their Furthermore, the ready availability of cheap,
proportionate share of the system cost. inefficient, high-demand appliances such as electric
3) Central systems are easily overloaded resulting in teapots, electric frying pans and immersion water
the loss of power to the entire community, while heaters makes it inevitable that consumers will buy
overloads of individual systems result in and attempt to use such devices on the low-capacity
individual loss of power. The activation of a single power systems used for stand-alone rural
large-demand appliance, such as an electric frying electrification. Such appliances are not available for
pan, during peak demand times can overload a small low-voltage dc applications and, even if they were,
village central system creating a power loss for the their use would not create a community-wide
entire community. It has proved very difficult to problem.
control the use of such appliances and the resulting 6) Centralized PV systems are less efficient.
friction within the community is not easily resolved. Distribution losses of 10% to 20% are usually
With individual PV systems, excess energy use results present. Additionally, if the central system is itself
in early loss of power only to the consumer powered by solar, there are extra inefficiency and
concerned and may result in friction between technical problems associated with power conversion
the power authority and the user but not within the from solar-generated dc to the high ac voltages
community itself. necessary for grid power distribution.
4) The power levels and technical complexity of 7) The location of houses is not fixed by a grid. It is
stand-alone PV systems are far less than central not unusual in many rural cultures to change house
systems. An individual PV system is comprised of locations regularly along with changes in the location
only a solar array, charge/discharge controller and of tilled land or for family reasons. Individual PV
batteries. The power levels are low and the systems are easily moved to the new location but
components simple. All three components are easily grid systems are costly to change once installed.
maintained and technicians do not require extensive 8) System size can be easily increased or decreased
training. Central systems, with much higher power according to changing needs. Central power
levels and a transmission/distribution system, require systems can provide increased capacity only by
a much higher level of technical competence for changing the entire generation, and sometimes
operation, maintenance and repair. Note that the distribution, system. The resulting change affects
higher the level of technical training someone the entire community. Individual PV systems can be
receives, the less likely they are to stay in a rural easily changed in size to meet changing family
environment. The turnover rate for people power requirements without affecting anyone but
sufficiently highly trained to operate and maintain the family concerned.
central power systems is likely to be far higher than 9) The practical limit to the maximum power
that for the person trained for individual PV system demand from individual PV systems is very high,
maintenance. while central systems are severely limited by
Chapter-11.qxd 11/8/03 11:20 AM Page 77

Determining the best type of rural 77


electricity system

generator and distribution capacity. Individual PV Disadvantages of individual solar


systems operating from lead-acid batteries can PV systems over central power
provide very high power levels and are limited by
watt-hours available rather than instantaneous watt Though the advantages of individual PV systems over
demands. Thus a small individual PV system having stand-alone central systems for domestic rural
only 120 W in peak panel (generation) capacity can electrification are impressive, there are disadvantages
power a movie projector drawing 1,500 W for a few as well:
hours per week while a central system must be sized
to generate and distribute the full 1,500 W no 1) Central systems can take advantage of load
matter how short a time the projector is to be diversity to allow smaller-sized installations.
operated. Individual PV systems must each have sufficient
10) Power is available 24 hours a day at no increase capacity to provide the maximum power requirements
in cost. Many rural central systems operate only of that user. As all customers on a central system are
a few peak demand hours per day as the cost of not simultaneously using all appliances, the system
operating during times of low demand is too great. can be smaller than the sum of all user’s maximum
Individual PV systems have continuous power power requirements. In the case of urban systems
available to the user so long as the use rates are with many diverse customer types, this saving can be
commensurate with system watt-hour capabilities. large. In the rural environment with customers who
11) Overall community power reliability is higher. have little diversity, the advantage is small.
The failure of a component in a central facility 2) Later interconnection to a larger grid is more
causes the loss of power to the entire community. expensive where individual PV systems have been
A similar failure in an individual system is limited to installed. If the community is near enough to be
one user. reached by a grid extension in five years or less, the
12) Maintaining a spare parts inventory is easier. cost advantage of the individual PV system is usually
Large numbers of essentially identical individual PV lost and a central system will be the best option.
systems require a spare-parts inventory comprised 3) In communities with a daytime commercial power
only of panels, batteries and controllers. Central demand comparable to night-time domestic
systems, particularly diesel or steam, must stock demand, central systems can often fill both needs
large numbers of different small parts to repair with little capital cost increase. If the night-time
engines, generators, switchgear and the distribution domestic load is comparable to the daytime
system. Furthermore, different-sized systems require commercial load, the same generating system may be
different sets of parts, making the spare parts used for the commercial and the domestic load with
management of a national-scale rural electricity little increase in capital cost, only operating cost.
system very complex. Central systems increase in capital cost with increased
13) Individual PV systems are safer. In order to power (watt) demand but do not increase with
distribute power efficiently, central system voltage increased energy (watt-hour) demand until the system
levels are high enough to be dangerous. Individual is fully utilized 24 hours per day. Solar PV systems,
systems are usually 12 V or 24 V and do not both central and individual, increase in capital cost
constitute a shock hazard. almost linearly with increased energy (watt-hour)
14) It is easy to add customers after the initial demand. For individual systems there is little capital
installation. With individual PV systems, there is cost penalty for quite large instantaneous power
little or no cost penalty for late installations. demand increases thanks to the low internal
With central power systems, particularly those with resistance of the lead-acid batteries used for storage.
underground grids, the cost of adding customers 4) Urban power authorities, which often manage
after the installation team and heavy equipment rural electrification programmes, are structured
have departed may be very high. around and understand central generation better
Chapter-11.qxd 11/8/03 11:20 AM Page 78

78 Solar Photovoltaic
Project Development

than individual generation. Different systems of Money may be readily available for grid extensions but
management and technical training are required for not for stand-alone power plants, or vice versa.
operating and maintaining individual PV systems than 2) The impact of adding this village on the ability of
for central systems. Where urban power authorities the electricity supply agencies to provide service
are also rural electricity managers, considerable effort to existing customers. If the urban system is at the
must be expended to provide the management, limit of its capacity, adding more load through grid
operation and maintenance structures necessary for extensions is not appropriate. If the rural electricity
large numbers of individual systems. The transition to authority is having severe problems keeping its
numerous small grid systems is less difficult. present inventory of power plants running,
5) As system size requirements increase, the cost adding another one to the system is unwise.
advantages of solar decrease. This is the result of 3) The preference of the village involved. The
decreasing marginal cost for increasing generating preference of the village should always be sought and,
capacity with non-solar systems but constant marginal if this preference cannot be allowed, a clear
cost for increasing generating capacity with solar. explanation of the reasons for the government
Typically, when the average energy use of individual decision should be given.
households is more than about 2 kWh per day, 4) The electrical load structure of the village. A large
conventional central systems begin to become more village with several commercial establishments or an
cost-effective than individual solar. industry likely to have significant electrical load would
6) In areas with dense vegetation, solar access can be usually be better served by a grid extension; while for
difficult and system costs increased. If it becomes a small village with a small load that is mainly evening
necessary to place the solar array at some distance lighting, a stand-alone plant may be the better choice.
from homes, the cost advantage of not having a grid
The primary constraints on grid extensions and multi-
is reduced.
village grid schemes are:
1) Economic. The cost of grid extensions often exceeds
US$10,000/km. As villages are usually separated by
Determining the mode several kilometres and total village loads can be 5 kW
of electrification or less, in many cases the life cycle cost of individual
systems is lower than that of a grid extension.
In those countries with two types of rural electricity
2) Geographic. Countries with rural districts consisting of
authorities, one serving off-grid systems and one with
many small islands cannot interconnect the islands.
extensions from an urban grid, a decision must be made
Countries with tropical rainforests and rugged interior
on which authority is to provide electricity for a specific
mountains have very high costs for transmission line
village. There must be a mechanism to determine which
extensions.
electricity authority should provide services. The decision
3) Climate. Many developing countries are troubled by
should be made by the government department
seasonal tropical storms. High temperatures and high
overseeing the rural electrification process and should be
humidity, also common in developing countries,
based on a balanced consideration of several factors:
create a very harsh environment for electrical
1) Relative life cycle cost of grid extension versus systems.
stand-alone generation. The cost of installing and 4) Social/Legal. Land rights are complex in many rural
operating the stand-alone system should be weighed areas where there is a mixture of traditional and
against the installation and maintenance cost of statutory land systems. Obtaining and retaining land
extending the grid. Government subsidy will be for power plants and a right of way for transmission
involved in either task, as it is rarely possible for the and distribution systems is often very difficult.
rural village itself to afford the investment necessary 5) Technical. The small number of adequately trained
to initially bring electricity to the community. technical staff limits the capability of a country to
In addition, the source of funds must be considered. expand and maintain grids.
Chapter-11.qxd 11/8/03 11:20 AM Page 79

Determining the best type of rural 79


electricity system

Generating and delivering electricity For large-scale rural electrification to be successful,


to rural areas the technology used must have an operating cost that
can be met by the consumers. Ongoing operational
Because many rural communities cannot be economically subsidies that are tied to uncontrollable market prices
connected to a large-scale grid, rural power systems will for fuel, spare parts and technical services cannot be
develop at scales ranging from individual households to maintained for the decades necessary for rural districts
multi-village grid. The mode of development will depend to become affluent enough to cover their own power
on the geographical, economic and social conditions costs.
specific to each rural district. On the other hand, one-off capital costs are easily
Solar PV is the only generating technology that can be budgeted in known, fixed dollar terms and capital funding
more economical in individual rather than central is much more easily obtained from funding agencies than
installations. Diesel, biomass-fired steam and small hydro recurrent cost funding.
are the other technically proven options for rural For these reasons, many governments consider high
electrification, but none can economically provide power capital cost, low operating cost technologies as the best
on an individual home basis. The basic choice that must choice for national-scale rural electrification, with low
be made is whether or not to provide power from operating costs receiving much more emphasis than
individual solar units or a central village generator fed capital costs.
through a small grid. Of the remaining four rural electrification
technologies, all have substantially higher first costs and
substantially lower operating costs than stand-alone
Fitting photovoltaics into diesel power. There are other constraints as well:
rural electrification policy nearness to the grid for line extensions, nearness to an
easy-to-develop site for small hydro, and the availability
Although the small diesel power plant has been used for of low-cost biomass fuel in sufficient quantity for
more stand-alone rural electricity systems than any other biomass steam plants. These constraints make it a
technology, these systems have a high operating cost and requirement that there be careful matching of these
a poor reliability record. The reasons for their popularity technologies to the rural site. On the other hand, solar
are basically their relatively low first cost and familiarity. photovoltaics has the least dependency on physical site
Their poor reliability stems primarily from the problems of characteristics and can be used virtually anywhere,
supplying remote rural communities with fuel of adequate though the capital cost will vary as the level of solar
quality, replacement parts and technical support for availability varies.
maintenance and repair. Where these materials and It is of interest to note that after careful examination
services have been adequately provided, system reliability of rural electricity options, at least one Pacific Island
is much improved. Unfortunately the cost of providing country has formally adopted photovoltaics as the sole
these materials and services has turned out to be much method for new, stand-alone, rural electrification,
higher than most governments initially estimated. while many other nations consider photovoltaics to be
A reliable stand-alone, village-scale diesel power system appropriate for rural electrification in remote areas
in a remote rural location places power costs, based on unlikely to be reached by a grid for one or more
operating costs alone, in the US$1 to US$2 per decades.
kilowatt-hour range and the total cost per unit is about
three to four times that found with urban systems based
on diesel generation. Barriers to individual system
While a small number of systems of such high implementation
operating cost can be supported, a national rural
electrification programme using small, stand-alone diesels Despite the clear advantages of individual solar over
can be a major financial burden that is impossible to central systems for much domestic rural electrification,
justify on economic grounds. only a few countries have embraced solar programmes
Chapter-11.qxd 11/8/03 11:20 AM Page 80

80 Solar Photovoltaic
Project Development

for rural electrification beyond the early trial stage. specifically designed for rural electrification rather
There are several reasons for this: than relying on existing urban power authorities.
1) Poor projects in the past. Many over-optimistic 4) Inadequate and inflexible designs. The most
promises followed by a few poorly conceived solar common mistake in rural electrification using
projects have damaged the credibility of solar in individual PV systems is to not make allowances for
general. In particular, in developing countries the differing needs of the people being served.
experimental projects using solar as a central power To date, virtually all solar rural electrification projects
generator have been installed with a high rate of have provided a single-design, minimum PV system for
failure. These demonstration projects have had a high all customers. What happens is that the wealthy,
capital cost and a low reliability and have been neither and often politically powerful, users who justifiably
an economic nor a technical success. expect electrification to allow them to use videos and
2) Poor systems support. A number of villages have other conveniences within their economic reach,
been provided with well-designed individual PV are frustrated by the inadequacy of the project,
systems and then the projects were essentially publicly deride the technology and often lobby for its
abandoned by the implementing agency without replacement by a government-subsidized central
providing access to parts or technical assistance. system. Had there been a mechanism available for
The result was, once again, failed projects and a loss these users to obtain a sufficiently large PV system to
of confidence in the technology. meet their expectations and perceived needs,
That individual PV systems can be installed, this problem would not have arisen. Even if the
operated and maintained in a fashion that yields purchase of this extra solar capacity is subsidized,
economic, technical and social advantages has been the end cost to government is almost always much
well demonstrated by projects in the Pacific Islands less than the cost of subsidies for equivalent central
that have been in operation 10 years and more with system purchase and operation.
continued good customer acceptance and no loss of 5) Limited genuine expertise is available. Although
enthusiasm for the future of the technology. almost every engineering firm contacted claims to be
This success has required the establishment of a capable of designing PV systems, the number of
specialist solar electricity organization, a long-term people with actual experience of designing and
commitment to the project and a great deal of implementing community-scale rural electricity systems
money. Exactly the ingredients of any successful using solar photovoltaics is very small. A great deal of
rural electrification project regardless of the trial and error is still going on and bad advice is much
generating technology. easier to come by than good. Seemingly intelligent
3) Technical and managerial inertia. The experts in and otherwise rational people have an amazing
electrification in any developing country are from tendency to treat others’ clear mistakes in project
the urban power sector. All their experience, design as flukes that will not cause trouble when
technical education and professional commitment repeated in their own projects.
revolve around centrally generated, grid-delivered 6) Promises of better things tomorrow. The continuing
power. Rural electrification using large numbers of claim that solar prices are going to fall dramatically in
stand-alone systems, whether village-scale central the future has a negative effect on the market today.
generation or individual solar installations, requires While it is probably true that panel prices will continue
different management, technical and support to fall, the cost of panels in the overall solar rural
structures. It is difficult for a government to overrule electrification equation is a minor one. A cost
their own electrical power experts and establish reduction of 50% in panel prices would result in less
different standards and structures for rural than 20% reduction in overall rural electrification
electrification. Note, however, that the most capital costs because of the unchanged cost of labour,
successful rural electrification projects are almost the balance of system costs, project overheads and
always characterized by a separate organization transport costs.
Chapter-11.qxd 11/8/03 11:20 AM Page 81

Determining the best type of rural 81


electricity system

Conclusions on solar power of large numbers of individual PV systems in remote


for rural electrification sites.
· The programme must be flexible enough to meet the
Sufficient experience has now been gained in the needs of consumers ranging from the one-light
large-scale implementation of individual PV systems for household up to at least that of lights, video and
domestic rural electrification to understand where the refrigerator.
technology best fits into national programmes. · Unless ever-spiralling subsidy costs can be handled
For successful rural electrification, the most significant in government budgets, fees covering operation and
problems have turned out to be ones of management and maintenance costs must be collected from
policy rather than of technology. Some of the important customers.
lessons learned are:
There is no single technical solution to rural
· With solar as the power source, only individual systems electrification. Any national programme must be flexible
should be considered. Where individual systems are not enough to deal with several generating technologies and
appropriate, do not use solar for rural electrification in philosophies. Solar electrification should be a part of any
developing countries. developing country’s national rural electrification
· There should be a decentralized organization programmes and should be considered for domestic rural
specifically designed and staffed to handle the special electricity at most sites unlikely to be connected to a grid
problems of installation, operation and maintenance system for the foreseeable future.
Chapter-12.qxd 11/8/03 11:21 AM Page 83

Funding for projects 12 C H A P T E R 12

External funding is usually needed Finally, requiring the district to share the cost helps to
ensure that there is a genuine desire and need for
Although rural electrification policy should be for the electrification, not merely a passive willingness to have
districts being electrified to pay for the operation and government provide a free project.
maintenance of the electricity system, few rural districts As the generating equipment should not belong to
have the financial resources necessary to make the initial the users, an appropriate charge for the installation of the
capital investment. Virtually all rural electrification rural electricity system is one that pays for those parts of
projects require external funding of some sort. the system that are not part of the generation and
distribution system but actually will belong to the user.
Such items are usually limited to house wiring, appliances
Sources of funds and labour for connecting buildings to the system. Usually,
for a village-scale scheme, those components of the project
A number of funding sources are available, though not all
will comprise between 10% and 20% of the overall cost.
may be available at the same time. Most projects use a
combination of funding sources. Often, different sources
are used for different stages of a project. Payments from government treasury

Payments from recipients In those governments where the priority for rural
of rural electricity system electrification is high enough to justify budgeting
treasury funds, a portion of the capital cost for rural
All rural electrification capital projects should have some electrification projects comes directly from government.
financial input from the recipients. If a rural district The actual source of the treasury funds may be taxes or
cannot afford a 10% to 30% investment in the project, may be external to the country, but the allocation is
then their ability to continue to pay the operating and made through the national budgetary process and does
maintenance cost is highly suspect. Furthermore, a rural not directly involve external funding agencies.
district with so little income will be unable to obtain the Rural electrification that involves government facilities,
appliances necessary to make full use of the available such as schools, health centres and government offices,
electricity. Also, if so little money is available then adding will usually be funded from the budgets of the respective
rural electrification is likely to slow development because departments responsible for the facilities. Sometimes,
it will take a high percentage of available money out of electricity produced for these facilities will be made
the village, leaving nothing for development. available to private citizens living nearby.
Chapter-12.qxd 11/8/03 11:21 AM Page 84

84 Solar Photovoltaic
Project Development

Urban electricity authority investment take years of negotiations before the money becomes
available.
Some electricity authorities are statutory
bodies — companies that are government owned but Soft loans
separate from normal government processes. Some are
government departments and some are privately owned. These are low-interest loans, often with very long
Most developing countries have electricity authorities that pay-back periods. Payment terms are much better than
are closely tied to government. Because rural extensions commercial loans.
of the grid rarely generate enough revenue to pay for Soft loans are usually provided by international
the investment, the decision to provide rural development banks, such as the Asian Development Bank
electrification through grid extensions is political rather (ADB) or World Bank, or by government banks in
than commercial. Government may directly subsidize relatively wealthy countries. The loans are generally given
these extensions through subsidies to the electricity to governments or, if given to an electricity authority,
authority specifically for rural electrification, or indirectly with a requirement that their payment be guaranteed by
through general subsidies to the electricity authority. government. These loans may have interest rates of only
It may also require the authority to ‘cross-subsidize’, a few percent and pay-back periods of several decades.
making the relatively wealthy urban customers pay higher However, they often require more than a year to obtain
rates to cover the cost of rural electrification in and may include a number of restrictions. Restrictions are
cash-poor areas of the country. requirements considered by the lender to be necessary to
It is important to realize that although the electricity ensure that the funds are correctly applied. These may
authority is making the rural electrification investment, include the requirement for lender-designated
the source of money for that investment is not from consultancies to determine the appropriate location,
charges made to rural districts but subsidies from budget and type of rural electrification for the country;
government, urban users or both. specific fee structures for users; particular organizational
structures for the rural electricity authority; onerous
periodic reporting requirements; or other terms that
Commercial loans
reduce the borrower’s flexibility in the use of the money.
These are loans obtained from commercial banks or
private lenders at rates and under conditions available to Loans from local development banks
general commercial-class borrowers such as businesses.
Typical commercial loans have interest rates between Most developing countries have a national development
10% and 20% and pay-back periods from five to ten bank. Their terms lie between commercial loans and soft
years. loans. Interest rates are usually a little better than
For rural electrification that involves industry, such as commercial rates but pay-back periods are usually much
a coconut-oil mill, or a major commercial activity, longer.
such as a tourist resort, the expected return on Local development banks are funded by governments,
investment may be great enough to pay back the capital often with external funding as a basis, and are usually
cost even at the relatively high interest and in the intended for economic development only. They would not
relatively short time associated with commercial loans. usually be a source of funds for domestic rural
This source of funding is usually considered the last electrification but might be for electricity related to
resort for a project as the cost of obtaining the money is a commercial or industrial project.
higher than that of other sources. Commercial loans do The quality of the project, in terms of its likely
have the advantage of generally being the easiest to economic success or failure, does not need to be as high
obtain, as long as the project is financially sound. as for a commercial loan. Borrowers, however, are usually
Arrangements for commercial loans can be completed in restricted to certain classes and uses of borrowed funds
a month or less while other, cheaper sources may literally are usually restricted to certain classes of projects.
Chapter-12.qxd 11/8/03 11:21 AM Page 85

Funding for projects 85

The time period for obtaining development bank loans Bilateral aid typically requires a year to two years of
is generally six months or more and considerable effort is negotiations, though some donor countries have small
usually needed to pass the application through the various grant programmes that can result in project funding in
levels of bank bureaucracy. The primary advantage is a less than six months.
longer pay-back period than commercial loans and, once Multilateral regional aid is provided by a country,
the loan is made, more flexibility in modifying payment an international agency such as the United Nations
structures to meet changing conditions. Development Programme (UNDP) or a group of countries
For rural electrification, the primary use will be for such as the European Union, to a group of designated
economic development of rural districts through industry recipient countries. Generally a specific amount is
or commerce. Unlike the usual commercial loans, provided for the entire region so an increase in project
however, domestic rural electrification sometimes may be funding for one country will reduce the amount available
included in a loan provided that the overall project is for to others in the region. Such aid is therefore negotiated
economic development. as a group, often with a regional intergovernmental
agency representing the recipient nations in
negotiations. Regional aid may have designated uses,
Bilateral or multilateral grants-in-aid
such as for energy development only, or may be
a general fund with no specific use designated in
This is funding from countries or international
advance and individual projects being negotiated after
organizations that is provided with no pay-back or
the funding is allocated.
interest requirements.
Regional aid is usually the slowest and most
Bilateral aid is negotiated directly between the donor and
cumbersome. Long negotiations between the recipient
the recipient country. Broad terms are usually set by the
and donor countries for the amount and type of aid,
donor government, but within those limits terms may vary
long negotiations between recipient countries to divide
considerably and must be negotiated on a case-by-case
up the aid, long project approval times and complex
basis. As aid terms change with donor government policies,
systems for project development, approval and
a change in government in the donor country may
implementation are common. Five years or more may pass
precipitate a major change in the amount and terms of aid
between initial negotiations and project implementation.
available to the recipient countries. Such changes may be
Terms for regional aid tend to be more stable than
sudden and a series of negotiations on a project may have
those for bilateral aid and the availability of the specified
to be started all over again following sudden changes in the
funding can be treated as certain. The best use for this
ground rules set by the donor country.
type of funding is long-term, non-critical projects whose
Bilateral aid funds may be provided for a specific
requirements are not likely to change over a five- to
project or may be part of a general aid package to
ten-year period. Domestic rural electrification often fits
government negotiated around a group of projects.
this category of project and can successfully use regional
The terms of bilateral aid vary. Some donor countries
funding to advantage.
restrict the use of the money to purchases from donor
country suppliers, while others have virtually no
restrictions on where the money is spent so long as it is Commercial aid
directed towards the completion of the approved project.
Though pay-back is not required, the donor country These are basically gifts from manufacturers or
usually expects the recipient government to maintain distributors. A manufacturer seeking to enter a market
a friendly attitude towards the donor government and for may donate components for a ‘demonstration’ project.
there to be some trade preference or commercial Such aid is rare and available only under very special
advantage to donor-country businesses. If these circumstances and then only in small amounts.
expectations are not met, it is common for bilateral aid to Such projects are rarely genuinely useful to the
become difficult to obtain or additional restrictions to be recipient and often involve considerable hidden costs in
applied to aid-funded projects. administrative overheads and unscheduled maintenance.
Chapter-12.qxd 11/8/03 11:21 AM Page 86

86 Solar Photovoltaic
Project Development

In a few specialized cases such aid can be useful, but the Arranging combinations of funding
recipient must constantly be aware that the donors are
providing the equipment to meet their own needs for Most rural electrification projects are funded from
commercial advantage and, for the project to be useful, a combination of sources. All rural electrification capital
those needs should not in any way conflict with the investment projects should have some funding input,
utility of the project to the recipient. no less than 10% and preferably more, from the
One of the most common requirements for a project recipients. Government often provides some input,
of this type is unlimited access for the donor company. at least in the form of project management and
The users of the equipment must be prepared to host sometimes as capital subsidies. The remainder of the
the donor company representatives and their clients at funding is most often obtained from aid sources or from
any time. Often government representatives are soft loans guaranteed by government. Commercial loans
expected to accompany client tours. The time spent or local development bank loans are little used for rural
hosting and touring with such groups can be a serious electrification projects and then only as a component of
problem and may end up costing more than the value of a much larger economic development project that can
the project. reasonably be expected to generate sufficient income to
Another type of project that is sometimes funded by pay back the loan on schedule.
a manufacturer is in reality a field trial for prototype
equipment. In this type of project, new components that Combining aid grants
seem to work at the manufacturer’s facility are placed in
the field to see if they work properly under actual use When putting together a funding package for a rural
conditions. This type of project is acceptable as long as electrification project, the lowest cost funding should be
everyone involved knows that it is in fact an experiment, sought first. That will be bilateral aid or regional aid
the manufacturer agrees to bear all the cost of funding that need not be paid back and has no interest
maintenance and the system is to be used in an charges. Typical sources are aid programmes of the
application where reliability is not essential. Unhappily, European Union, Japan, the United States and other
manufacturers often call such projects ‘pilot projects’ developed countries. Also, various UN organizations,
or ‘demonstrations’, implying that the technology is particularly the UNDP, have provided rural electrification
proven and reliable. Both the user who is the butt of development grants. The World Bank and regional
such an experiment and the government office that has development banks, such as the Asian Development Bank,
to try to keep it working may suffer. have provided technical assistance grants for rural
Energy planners should be aware that aid agencies of electrification development. Some of these sources have
donor countries sometimes offer such projects as aid wholly funded rural electrification projects, others have
rather than as the commercial field trials or funded components of projects such as specific hardware
manufacturer’s overstocks that in fact they really are. or consultancies. Diesel, hydro, photovoltaic, gasifier,
Energy officers should be wary of projects initiated by aid wind and biomass-fired steam systems as well as grid
agencies that are restricted to the use of a specific type extensions have all been funded from these sources.
of hardware, as these can be assistance to manufacturers To obtain grants from international sources, a project
in need of field trials disguised as assistance to prospectus should be given to some or all of the grant
developing countries. agencies operating in your country for examination.
When equipment is offered that has not been This should be followed up with a personal visit to their
successfully used elsewhere over a period of five years or offices to discuss the possibility of complete or partial
more, some form of sharing of the costs of replacing the funding of the project.
equipment should it prove inadequate over the life of Be aware that many grant agencies will not be
the project must be included in the project funding. interested in partially funding a project when other grant
The usual one-year warranty is not sufficient under these agencies are to provide another part of the funding.
circumstances. This is called co-financing and it is rarely successful.
Chapter-12.qxd 11/8/03 11:21 AM Page 87

Funding for projects 87

To overcome this problem, break the project into a group the loan, government must do so from other sources
of smaller projects each of which is funded differently. thereby effectively diverting money from other
Thus as an example of the division of a large rural development projects. If the government’s priority for rural
electrification project into smaller packages for joint electrification is high enough to justify a 30- or 50-year
funding, the United States might fund the electricity commitment to what amounts to a subsidy for rural
installation for rural schools, France the health centres, electrification, then a loan can be considered. It should be
the EU the domestic users and Japan the commercial users. noted that in most developing nations, there is little social
Another approach to packaging a project for multiple or economic justification for placing rural electrification
agency funding is to divide it into projects for higher in priority than the development of rural roads,
implementation at different times. Thus a pilot project for water supply and health services.
domestic solar electrification might be funded by Japan, Even if the recipients can pay back the cost of the
two years later there could be a first-stage project with loan, the payments by the recipients will take money out
basic PV lighting installations funded by the EU, of the rural economy that could slow the rate of local
then three to five years later an upgrade project by the development. Prior to accepting loans for rural
USA to increase the level of power available to the users electrification, implementing agencies must carefully
to allow for other appliances. weigh the options for development and make sure that
A third method is to divide up a large project the loan and interest payments made by either
geographically, one community to be funded by one government or recipients is money best spent on rural
agency, another community by a second agency and so electrification or on other forms of rural development.
on. This often leads to difficulties in maintaining If loans are to be sought, the objective is to have the
consistent technical designs, however, and should be rural electrification capital investment made with the
approached with caution. least overall cost to the receiving electrification agency
A fourth approach is to divide the project into or government. Some industrialized country governments
functions: one agency funds the design consultancy, a offer soft loans for development projects as a type of
second the hardware, another the training component, aid. Basically these are bank loans with the pay-back
a third the labour and so on. This approach sometimes guaranteed by the lending government and part of the
permits tapping sources that would be otherwise interest subsidized as well. If the recipient agency pays
unavailable. Also, it avoids the problem of retaining a back the loan as scheduled, the cost to the donor
consistent design for different installations as the entire country is much less than an outright grant and a donor
project design is done by one agency and the entire country’s aid budget can be stretched much further.
hardware procurement by another. This approach requires From the point of view of the receiver, these loans have
good-quality coordination and is perhaps the most similar interest rates and length of pay-back period to
difficult to make function efficiently. those of international development bank soft loans but
In each case where funding is divided among several usually are much less restrictive in their terms.
agencies, the technical design should be as unified as Often these soft loans have no more restrictions than
possible. You should not place yourself in a position aid grants, except for the important difference that they
where as many different types of equipment are being have to be paid back with interest. The procedure for
installed as there are funding agencies, which would applying for these soft loans is generally the same as for
make maintenance and spare parts control difficult. aid grants.
Soft loans from international development banks such
Loans for rural electrification as the World Bank have low interest rates and long
pay-back periods and are generally the first choice for
Before even considering a loan for rural electrification, borrowing capital for development projects if the less
the most basic question, ‘will the recipients of the project restrictive direct loans from donor governments cannot
be able to repay the capital plus interest’, must be be arranged. However, be aware that international
answered. If the recipients cannot be expected to pay back development bank loans often include requirements that
Chapter-12.qxd 11/8/03 11:21 AM Page 88

88 Solar Photovoltaic
Project Development

may add significantly to the effective cost of the loan. As with combining various grant sources for a
Complex accounting systems may have to be established project, though the funding is compartmentalized,
to meet reporting requirements. There may be the project itself should not be divided into
restrictions on the use of the capital even within the sub-projects but rather integrated into a general
scope of the project. There may be restrictions on rural electricity system.
the structure of the electricity agency implementing
the project. There may be minimum electricity rate
requirements, business profitability requirements and Finding the available
many other restrictions on the borrowing organization
that can raise the effective cost of the loan. Costly
funding agencies
consultancies may have to be carried out and paid from
In locating funding, you must think like a salesperson.
the loan. While most of the restrictions are intended to
One of the most important rules of selling is to know
ensure that the agency receiving the money uses it in
what the customer wants. You cannot prepare a good
a businesslike manner and for the purposes intended,
funding proposal unless you know what type of project
none the less the additional cost to the borrower must be
the funding agencies are looking for. You must know the
considered when using these sources.
usual terms and conditions of the funding agencies. It is
Local development banks and commercial banks are
important to make early contact with all the possible
rarely used for general rural electrification because their
sources of funds available for rural energy projects, get
loan periods are too short and their interest rates too
to know the people involved and learn the requirements
high for this type of project. They may be used,
for applying for funding, what size projects they prefer
however, when borrowing for the electricity supply
to fund, what terms you can expect from them, how long
system for a commercial or industrial project, where the
it usually takes to obtain a funding decision and any
bank can reasonably expect that the loan can be paid by
special conditions that are likely to be imposed.
the business without undue hardship. Usually, such
Part of this information can be obtained directly from
loans are negotiated with the project developers and
the funding agencies but much is best learned from others
energy planners are not involved directly other than
who have experience dealing with the agencies. By talking
sometimes as technical advisors and economic analysts.
with others who have had projects funded from the
agencies you are interested in, you can learn a great deal
Combining grant and loan funding about how the agency operates that you cannot learn
from the agency itself. It is particularly important to find
While loans usually should not be used to wholly finance out what projects have recently been funded by the
rural electrification when a project can be largely agencies. This will give insight into the current thinking of
capitalized by grants, the use of a soft loan to complete the agency regarding funding and, if you can study the
the project may be reasonable. To arrange such a documents for the projects that have been funded,
combination of funding will probably mean dividing the you will have a better idea of what the agency is looking
project into sub-projects as described above. The aid for in projects and in the way proposals are presented.
money is used for some sub-projects and the loan for It is also worthwhile to learn about projects that were
others. In general, it is often best to tie the loan submitted but rejected for funding to give you an idea of
component to the part of the project relating to what the agencies are not looking for.
government, commercial or industrial use, as these are Remember also that you will be dealing with specific
the type of users usually preferred by lending people at the agency and their personal requirements and
institutions. Thus a soft loan might be arranged to cover ideas about how projects should be submitted may differ
the electrification costs of rural public works facilities, from those of another person in the same agency.
government field offices, dispensaries, schools, Get to know the agency as an organization but, more
navigational aids, airports and harbour facilities; importantly, get to know the individuals you will have to
while grants are used for domestic electrification. deal with.
Chapter-12.qxd 11/8/03 11:21 AM Page 89

Funding for projects 89

Fitting the project proposal funding projects. By giving the agency a good-quality
project to fund you are doing it a favour, as the home
to the funding source office judges both by the quality of the projects funded
and whether or not the budgeted funding for your country
Once you have a good idea of the type of project that is
has been spent. If you can design a good project and
likely to be funded, you can prepare a project document
present it with terms that are at all acceptable to the
fitted to the agencies you are contacting. When dealing
funding agency, you will get the money.
with several funding agencies with very different
Some funding agencies will actually encourage
approaches to project funding, you can even prepare
increased project funding in order to help them to meet
several project dossiers, each tailored specifically to
a funding quota. Remember that the sole purpose of
a funding agency that you believe might fund the project.
development banks is to lend money to countries
This is not to recommend that you should modify the goals
for development. Regional development banks have been
of the project to fit funding agency requirements. The idea
known to encourage far greater investment in rural
is to modify aspects of the project that are unimportant to
electrification than is appropriate to the needs of the
meeting the goals in order to fit particular funding agency
receiving country in order to get their money into projects
requirements. Do not, however, modify the project to the
in developing countries. Design your project around the
point where its ultimate goals are not being realized. You
needs and capabilities of your country and only accept
may get the funding but end up with a poor project.
funding to the level needed. Remember that you must
In many cases, just changing the emphasis of parts of
have a balance of resources to carry out a project
the project document is sufficient. In the case of a
properly and money is only one of them. An excess of
donor-country aid agency, emphasizing the possible
money usually leads only to waste of that money and not
improvements to rural quality of life may be more
to an improved project. If you accept excess money for a
important than emphasizing fuel savings. In the case of
project from a granting agency, you are wasting money
a development bank, the document might emphasize the
that could have been used in your country for another
economic, rather than the social, development potential
project. If you take excess money offered by a bank, you
of the project. Sometimes, a funding agency will receive
are still wasting your country’s resources as it has to be
policy directives regarding particular features to look for
paid back from your government’s income.
in funding projects. For example, a few years ago, the US
Agency for International Development (USAID) was
emphasizing the concept of ‘privatization’ and projects Help in locating funding
that appeared to move economic endeavours away from
government and into private hands were looked upon While it is true that almost any good rural electrification
with special favour. Currently, there seems to be a lot of project can be funded through grants or soft loans,
political interest in ‘the environment’ and ‘poverty locating sources is not always easy. International and
alleviation’ so it would not be surprising to find that rural regional development organizations such as UNDP may be
energy project proposals that emphasize environmental able to direct you to a source of funding and may even
concerns and reducing poverty are more likely to be be willing to assist you in preparing the documents
funded than those that do not. necessary to obtain the money. Such organizations have
close contact with international development banks and
the aid organizations of the countries funding rural
Funding agencies want electrification projects. Provided you have a good project,
to give money they can arrange meetings, supply letters of introduction
or in other ways pave the way for you to meet the
Do not go into a funding agency with hat in hand and the appropriate funding agency officials.
feeling that you are begging for help. The funding agency As funding agencies often fund similar projects in
exists either as an arm of some government’s foreign different countries, it is useful to ask other country
policy or as a commercial enterprise just for the purpose of representatives who is currently funding their rural
Chapter-12.qxd 11/8/03 11:21 AM Page 90

90 Solar Photovoltaic
Project Development

electrification projects. Some funding agencies seem to Project requests provided in the format of the funding
prefer certain types of project. For example, Japan has agency, with supporting information, with clearly defined
funded many fishery-type projects in the Pacific. These project goals and showing that the means for their
‘specialities’ often change with governments and with accomplishment can be provided, will be much more likely
changes in the people administering the funding agencies to be funded than requests that are poorly prepared and
concerned, so you should not be discouraged if the incomplete.
funding sources readily available in your country do not There are many sources of funds for projects.
seem to have a history of funding projects such as yours. Although it is most convenient to have a single source,
the combination of a number of sources is often
Summary and conclusions necessary. The project may have to be divided into many
sub-projects, each funded by a different source,
The ease of obtaining funding for projects is usually in order to assemble sufficient funding.
directly related to the quality of the project request.
Chapter-13.qxd 11/8/03 11:23 AM Page 91

Preparation and submission


of a proposal
13 C H A P T E R 13

Understand the approval process Once the proposal has been submitted, try to keep
track of its progress and if it stalls along the way,
Before even starting to write a project proposal, be prepared to give it a push if necessary. In many cases,
you must understand the details of the approval process people who are continually reviewing project proposals
for the proposal. If delays or rejection are to be avoided, will give priority to proposals that have someone pushing
it is vitally important that the needs of every agency them while others will wait at the bottom of the pile.
involved in the approval process are provided for in the Sometimes proposals stall on someone’s desk because the
proposal. To do that, you must know what agencies are evaluator does not understand some aspect and requires
going to act on the proposal during its passage to final additional information. Though the request for that
approval or rejection. information will ultimately be sent to you, it may be much
Another important reason for determining the quicker if, when you learn that your proposal is spending
approval path before the project is submitted is so that an excessive time in one place, you drop in and ask
you can discuss the project with all parties to the pleasantly how the review is coming along and if you can
approval process in order to clear up problem areas be of any assistance.
before submission and to smooth the way through the
system. If you know the path the proposal will take Appearance is important
through the bureaucracy, you can keep track of its
progress and, should it halt along the way, it will be Although the submission of a proposal may be preceded
much easier to expedite if you can go directly to the by a long period of discussion and negotiation and you
person causing the problem. feel that the way has been well prepared for approval,
the actual document submitted has a great effect on how
Obtain pre-approval a proposed project is judged. A sloppy, confusing
as much as possible proposal will be more likely to be rejected or delayed
than one that is neat, complete and informative.
Once you know who will be examining your project Graphs, photographs, tables and other visual
proposal, try to discuss it with them before the components can be used to improve the appearance of
final proposal is written. This allows you to reduce the proposal and make it easier to understand. Just make
misunderstandings and to change those parts of the sure that the visual presentations are relevant and really
proposal that could pose a problem before submitting do add to comprehension. Also make absolutely sure that
the written proposal. tables and graphs agree with what is written.
Chapter-13.qxd 11/8/03 11:23 AM Page 92

92 Solar Photovoltaic
Project Development

It often happens that during the course of revisions of different goals. Some of the goals may be of
the proposal, numbers listed in tables or on graphs are importance to the agency receiving the proposal,
not changed when numbers in the text are revised. At others may not. In listing goals, emphasize those that
best this is confusing, at worst, the evaluator may use are important to the receiving agency, not just those
the wrong numbers and reach the wrong conclusions important to the proposer of the project. For example,
about the project. a goal such as ‘reducing greenhouse gas production’
may be better received by an environmentally oriented
agency than one that states as a goal ‘improving the
Weight does not count quality of life in rural districts’. Specific, measurable
To be approved, the proposal has to be read. An error goals such as ‘electrifying 3,500 rural homes’ should
frequently made in preparing project proposals is thinking be included as well as altruistic but vague goals such
that they must be long in order to be good. If they must as ‘poverty reduction’.
be long in order to tell their story properly, fair enough, 2) Justification for the project. Why should this project
but adding pages and pages of useless data to a project be carried out? What is its place in the overall
proposal will be annoying to the recipient and will lessen development plan of the country? How does it fit in
the chances of your proposal, not increase them. with other projects? For what reasons is this project
An aid agency may receive hundreds of proposals and needed? Why should resources be spent on this
an evaluator will appreciate proposals that are concise project instead of others? Why carry out the project
and to the point. Long rambling proposals with pages of now instead of later?
information not directly applicable will not be read 3) The agency responsible for the project. The proposal
beyond the first few pages before being deposited in the should list the agency responsible for the project and
‘do not fund’ pile. the contact persons in that agency. The address,
A general rule of thumb is to keep the proposal itself telephone, email and fax numbers for the contact
to 15 pages or less, although 10 pages is better. If more person should be included.
information is needed, put it in specialized annexes. If the 4) Location of the project. If the location is relevant to
proposal is more than 20 pages, it is wise to provide a the success of the project, be specific but otherwise
three- or four-page ‘Executive Summary’ as that will keep the location as general as possible to avoid
probably be read in its entirety while the lengthy having to justify location changes later. Sometimes
proposal may not. the location will be determined as part of the process,
after a rural needs assessment, for example.
5) Brief technical description of the project. What
Contents of proposal technology is being used? For rural electrification,
such factors as what type of generator is to be used,
The exact contents of a proposal document and the order
its generating capacity, the voltage of delivery to
they appear in the document will change slightly
users, hours of operation and total energy to be
according to the recipient, but certain items must be
provided should be stated.
present in almost all project proposals.
6) Mark the completion of the project. Every project
Unless the funding agency has a specific format to
should have a clearly defined beginning and an equally
follow, the proposal should follow that of a sales
clearly defined end.
brochure: a first section to catch the attention of the
7) Provisions for operating and maintaining the
reader (the goals and objectives), a central section to
project. Who will receive the project for operation
provide necessary details and specifications, and a last
and maintenance after its completion? Will any fees
section to say how much it will cost in money and time.
be charged? If so, who collects them and what is done
Typical contents include:
with the money? What about spare parts?
1) Goals of the project relevant to the agency 8) Time budget. Unless a specific date must be used,
receiving the proposal. Every project has many use the final approval date of the project
Chapter-13.qxd 11/8/03 11:23 AM Page 93

Preparation and submission 93


of a proposal

as the starting point and project the time for to the right one, but it also may be returned to you with
accomplishment of specific parts of the project as so a rejection letter. If you are not aware of the existence
many days, weeks, months or years after that initial of the other offices, you may assume, incorrectly,
approval date. Do not make an elaborate schedule of that the rejection from one prevents you from obtaining
exact dates for project activities, as the dates will funding from the entire agency. In fact, the rejection
almost always end up being wrong. from one office of a multi-office agency may have no
9) Financial budget. For some small projects, only a impact on how you are treated at another office.
total cost will have to be shown. Other projects will If you intend to submit proposals for approval,
need to have the cost broken down into several you need to know the organization and structure of
categories. Labour, materials, travel, communications, the funding agencies so that you can make sure that
consultancies, administration and overheads are you submit to the right place. Talk to other people who
several cost categories often required by funding have had projects approved by the agency concerned and
agencies. find out how they submitted their proposal and what
path it took in the approval process.
Include what is needed, leave out the rest Talk to several people in the funding agency
and obtain their advice on submissions and any special
The project proposal must be complete enough to meet problems that may arise in submitting proposals.
the requirements of the agency whose approval is being
sought, but remember that you will be expected to Use the correct format
implement the project in the fashion described in your
project document. The fewer details there are in that Some organizations require very specific formats for
document, the more flexibility you will have in carrying proposals, for example the Global Environment Facility
out the project. (GEF). Others have no special format but require
For example, if the funding agency does not require certain information to be included. Find out in advance
the actual installation site to be listed in the project what kind of format is required and use that format.
document, do not list one. If you list a site in the If specific forms must accompany the proposal, first fill
project document then later have to change the site, out a copy and find out if the way you did so is what
the funding agency may have to approve the was expected by the agency. Sometimes what is really
modification, losing time and possibly causing problems wanted on a submission form is not obvious from the
with other aspects of the project. Keep such details as form itself.
project site, material suppliers, time schedules, money
budgets and work assignments as general as possible yet
adequate for evaluation.
Learn from successes and failures
When a project is approved, try to find out what was
Who do you submit particularly liked about the proposal and use that
the proposal to? information in preparing the next one. If a proposal is
rejected, do your best to find out why and do not make
Although it is often obvious who should receive project the same mistakes again if the problem was within your
proposals, sometimes it is not. In particular, large aid power to resolve.
agencies and international agencies such as the United In addition to learning from the results of your own
Nations often maintain several types of office located in proposal submissions, learn from the experience of
different places. Each office may specialize in a others. Even submissions from other countries can help
particular category of assistance. If you send your you to find out what an agency likes and dislikes about
proposal to the wrong office, it may ultimately be sent proposals.
Chapter-14.qxd 11/8/03 11:24 AM Page 95

Technical design processes 14 C H A P T E R 14

Introduction they can be used as the actual technical design. In other


situations, the preliminary designs bear little resemblance
Technical design is primarily the sizing and determination to the final technical design.
of component requirements for a project. When the In most projects, the actual technical design is done
technical design is complete, it should be possible to after project approval and allocation of funds. Therefore
immediately specify the components needed and place it is best that the preliminary design is realistic. If the
orders or request tender submissions for purchasing. preliminary design is realistic and the funds allocated are
adequate, then the detailed technical design can be
carried forward based solely on the project requirements.
When is technical design done? On the other hand, if the preliminary design was
inadequate, there may not be sufficient funds for the
Prior to the technical design, estimates of materials full scope of the original project or corners may have to
requirements must be made in order to prepare cost be cut in the final design to lower the cost to an
estimates and operating budgets for the project proposal, acceptable level.
but the actual components needed for the project are
not usually specified until after the project is approved.
This is mainly because of the time and effort required
Who does the technical design?
for detailed technical design and the fact that outside
Technical design may be wholly or partly done by the
assistance in the form of consultancies is often required.
sponsoring department staff. Often for types of project
If the technical design is completed before a project is
that have not been done before, external consultants are
approved, there is always the chance that the concept
necessary.
will be changed or the project will be rejected and the
External technical design assistance may come from
design will have to be discarded and a new one prepared
several sources. The most common are:
at considerable additional cost.
In order to prepare the project budget, there must be 1) Aid agency consultants. It is not unusual for a
a preliminary design and a generalized component list project funded by an aid agency to include design
with approximate costs estimated. This preliminary design services. Sometimes, the agency requires its
is often nothing more than a copy of the design used in consultants to do the technical design. The quality and
a prior project. If the project management is experienced appropriateness of these services varies widely.
and has carried out similar projects in the recent past, Unfortunately the consultant may well be unfamiliar
these preliminary designs may require little change before with local conditions, have little understanding of the
Chapter-14.qxd 11/8/03 11:24 AM Page 96

96 Solar Photovoltaic
Project Development

needs of the community being electrified and be the consultant trying to meet design specifications
unwilling or unable to work closely with the local that are not well thought out or too vague.
agency. The resulting design will show this lack of 4) Public, external consultants. Design consultants are
understanding and sensitivity. Be very wary of such often available from the United Nations, international
arrangements and always seek an outside opinion banks, aid agencies and non-governmental
from a technical organization that you trust regarding organizations. It is sometimes possible to use a
the appropriateness of a design produced under these public consultant to create a design but this class of
conditions. consultant is best at reviewing someone else’s design.
2) Equipment manufacturers or sales organizations. As Usually little or no cost is involved and, as should be
the equipment manufacturer or sales organization expected with any no-cost programme, scheduling may
wants the equipment to work correctly, it is be difficult and the quality of service variable.
reasonable to consult them about designs to ensure Obtaining a timely response is often a problem,
that their equipment is capable of handling the though some agencies that specialize in energy
operating conditions. However, few manufacturers or problems can often provide a design review of a
sales organizations maintain a real capability to assist simple project in a matter of days.
in designs. Usually, design assistance is provided 5) Government employees of other departments and
haphazardly by staff whose primary responsibility local consultants. Local people working for other
is sales. They should not be relied upon for technical government departments, electricity authorities or
designs without a review by a competent technical private industry may have a better understanding of
organization. Also, vendors usually only recommend the technical design problems for a rural electrification
the products they sell, which may severely limit the project in your country than outside consultants. Even
choice and the quality of the resulting designs. if someone cannot be found locally who has the
3) Private, external consultants. There are good and specific technical knowledge necessary, a technical
bad consultants, as in any other profession, but in design team should include at least one local technical
general the private consultant is the most flexible and person who at the very least can help the external
most likely to provide a reasonable cost design that consultants to understand conditions at the site and
meets the project needs. Also, the private consultant the availability of labour and materials for
is most likely to agree to directly involve local agency construction and maintenance.
staff in the design process. The private consultant is
also usually the most expensive option as far as
consultancy costs are concerned, though the Technical design cost
high-quality design provided by good private
consultants may result in a project with lower overall As a general rule of thumb, the technical design of a
costs. The main advantage of the private consultant major rural electrification project should not cost more
is that, during the contract period, the consultant than about 10% of the hardware cost. Pilot projects
works for you and you alone. The other classes of involving few installations or complex designs will have
design consultants have you as a temporary boss and technical design costs that are a much larger percentage
another agency as a permanent boss. Their natural of total cost, sometimes exceeding the hardware costs,
reaction is to try to please both bosses but the but the expectation is that those designs will later be
permanent boss (not you!) will win in any conflicts repeated at several sites (assuming the pilot is successful
that arise. and the design is satisfactory) thereby sharing the cost
The private consultant depends on your good will over many installations. For example, a pilot project to
and satisfaction for future business and will usually install a two-panel solar-lighting installation on 20 rural
attempt to provide you with what you want in a homes might cost US$20,000 for the equipment but the
project technical design. If you know what you want, technical design may cost more than US$10,000 if
this works well. If not, a poor design may result from outside assistance is necessary. If the pilot is successful
Chapter-14.qxd 11/8/03 11:24 AM Page 97

Technical design processes 97

and a major rural electrification programme follows, there area but also the location of all sites that will be
will be several hundreds, if not thousands, of similar receiving electricity, identifying the type of user at
two-panel systems installed so that the design cost can each site.
be spread over so many future installations that the cost 4) Expected load for each user type. This is required
per system meets or is better than the 10% cost in peak watts per user and watt-hour usage per
guideline. month (or average energy use per day in the case
of solar).
5) Special requirements. This includes anything related
Technical design criteria to the project that will require the designer to include
restrictions imposed from outside. Some possible
No matter how good the designer, if the information
requirements are that the design must meet
provided for the basis of the design is wrong
installation standards set by an urban electricity
or inappropriate, the resulting design will also be
authority; the equipment may only be purchased from
inappropriate.
certain vendors or country sources; the wiring must all
It is the responsibility of the project manager to
be underground; or solar panels must be mounted on
ensure that the technical designer knows the technical
poles rather than on buildings.
goals of the project and has all the information needed
6) Project financial budget. A major design restriction
to carry out the design task properly.
is usually the amount of money available. The
For rural electrification projects, some of the important
designer must know how much money can be spent
design information that the technical designer requires is
on the system being designed if the result is to be
as follows:
practical. Often this aspect of the design is the
1) Number of households that will be receiving hardest to meet.
electricity. This should be broken down into classes
related to the appliances that households are
expected to use. For example, the designer must The completed design
know how many households are expected to have
refrigerators, how many will want to use videos, the When the technical design is complete, it should include a
number of lights to be installed in different houses, complete, detailed materials list divided into lists for each
and any other appliances that will have a significant individual system type and for the project as a whole.
effect on user loads. Detailed specifications for the purchase of individual
2) Number and type of other anticipated users of components should be included. Recommendations for
electricity. This includes stores, industries, government specific brand and models of components should be
offices, schools, dispensaries and all users that are not provided. Drawings showing the wiring and assembly of
domestic in nature. each different system should be provided. Preparation of
3) Detailed map. The project map should not only show a complete, detailed cost estimate should then be
the important topographical features of the project possible with little additional effort.
Chapter-15.qxd 11/8/03 11:25 AM Page 99

15
Budgeting
C H A P T E R 15

Why budget? of management can make the decisions needed to


keep the project on track. However, if something goes
A budget is an outline of the predicted allocation of over budget, then higher levels of management are
resources over the life of a project. As the resources called in for decision-making in order to get the
used in a rural electrification project are primarily project back on to an acceptable path. For this
personnel, time and money, there will almost always be process to work well, budgets must be realistic and
budgets for these items. Financial and personnel budgets should be prepared at the same level as will be used
will include entries for the time when resources will have for performance rating.
to be made available. · As a focusing device. Making money and personnel
There are several reasons for making budgets: budgets requires a detailed visualization of the project
from start to finish. Problem areas and possibilities for
· To estimate the need for resources. To obtain
savings are often realized because attention has been
funding and to determine the capability of available
focused on details of the project through the process
resources to carry out a project, the need must be
of budgeting.
estimated. This budget begins with the project
· As part of a project proposal. Budgets are usually
concept and goals and develops the requirement
required by funding agencies. A time budget and a
for funding and labour to make the project
money budget are almost always included in requests
possible.
for project funding. Additionally, personnel budgets
· To permit efficient management of resources. A
may be required for some projects.
budget allows management to predict what resources
will be needed and when. This allows advance
arrangements to be made to ensure that the What to budget
resources will in fact be available when needed.
· As part of ‘management by exception’. A powerful Any resource used in a project can be budgeted.
management tool that should be used is that Examples are money, labour, time, equipment,
of management by exception. This simply means that management resources, fuel and materials. Generally
top management decides in advance what acceptable (except in the case of time itself), the resource is
performance is and will allow subordinates to run the budgeted against time as well as quantity. When this
project as long as that performance is achieved. is done, it is immediately clear what, how many and
Budgets are the primary gauge of performance. As when resources are expected to be needed for
long as everything is going as budgeted, lower levels the project.
Chapter-15.qxd 11/8/03 11:25 AM Page 100

100 Solar Photovoltaic


Project Development

Time budget 6) Check all sub-projects shown on the time budget to


make sure that there is no interference and that enough
The time budget shows the start and stop times of project resources will be available to carry out the projects as
stages. As some stages can be carried out simultaneously budgeted. Make sure that everything is labelled and
(these are ‘parallel processes’ such as ordering equipment clear to a reader not already familiar with the project.
and preparing sites) some of the stages overlap in the The result is a budget of the time needed to do the
budget. Other stages depend on the completion of prior project in the most time-efficient manner.
stages (these are ‘serial processes’ such as wiring
following the purchase of wire) and the beginning of one
stage must be budgeted to start after the completion of a Financial budget
prior stage. In preparing time budgets, the goal is to be as
realistic as possible. A reasonable approach is to: A financial budget lists the financial requirements for
components of the project. For example, a simple
1) Divide the project into sub-projects that can each be financial budget for a PV installation might allocate
carried out as a unit. For example, ordering materials money for materials purchases, shipping, installation
can be considered a separate sub-project to doing labour, administrative costs, training, testing of
a technical design, even though one depends on completed systems, travel costs for technicians not living
the other. locally and an amount for contingencies. Each one of
2) Create a computer spreadsheet with columns these categories in the budget would be a money amount
corresponding to time. Short projects may use one that has been estimated to be sufficient to provide the
day per column, long ones months per column. Rows materials or services listed in that category.
should correspond to tasks. Money budgets may be developed top-down or
3) Colour the cells for each task that correspond to the bottom-up. The top-down approach starts with the total
time the task is carried out. For example, if orders are sum allocated to the project and the budget is developed
to be placed 30 days into the project and deliveries so that the sum of all the budgeted amounts equals
expected 60 days later, the columns corresponding to the allocation. The bottom-up approach starts with the
days 30—90 on the row for the task of materials budgeted amounts for the various tasks in the project
delivery should be coloured. and the project sum is the total of those component
4) Determine which sub-projects must follow others and amounts. It is reasonable to do a first draft of a budget
in what order. Decide how much time each stage takes using the bottom-up method to see if the total amount is
and lay out the tasks in the right order, allocating the greater than the amount allocated for the entire project.
estimated number of days to each. If any of the tasks This allows the project designer to first determine what
cannot start prior to a certain date, make sure that the level of funding is really needed for the project. If that
budget shows them starting later than that date. amount significantly exceeds the amount available, then
5) Determine which projects can be carried out it will be necessary to shrink the scope of the project,
simultaneously and locate them on the timeline at redesign parts of it so that less cost is involved, or seek
points where other resources are not limiting. An additional funding.
example of a limiting resource might be labour. Suppose
a project is to install PV systems on the houses in two
Time/money budgets
villages. While it is possible to install the systems on
houses in two villages at the same time, there may not
A combined time and money budget that shows at a
be enough trained people to do so. Then the two
glance how much and when money must be spent is very
villages will have to be treated as serial projects (one
useful. Making this budget is similar to making a time
after the other) rather than parallel (occurring at the
budget. A reasonable approach is to:
same time). The difference between this and what was
done in item four is that either activity can be carried 1) Break the project into sub-projects that can be
out first, they do not have to be in any special order. considered as one class of expenditure. Note that the
Chapter-15.qxd 11/8/03 11:25 AM Page 101

Budgeting 101

sub-projects considered here may be the same as, or installation site. The site managers are responsible for
different to, the sub-projects that were created for the installation. They are each briefed and given copies
the time budget. It is often more convenient if they of the budgets for their site. As long as they are able to
are the same but this is not essential. keep the project within the time and money allocated
2) Create a timeline chart for the duration of the project in the budgets, only periodic reports of progress are
like the one created for the time budget. required. The project manager in the capital city can
3) Mark the times when money is expected to be spend time in other areas of work instead of closely
received and show the amounts. monitoring or even personally managing the field projects.
4) List the sub-projects and note the amount of money Should overruns in cost or time seem likely, the site
needed for each of them. manager notifies the project manager in the city who will
5) Mark the times when the sub-projects have been then have to take action.
budgeted to take place. This comes from the original Of course, this system only works if the project as
time budget. designed and the budgets as constructed are realistic and
6) Determine the money required for the sub-projects to have a good chance of being carried out as intended.
be carried out between receipts of money. If the If the project has unrealistic budgets or is poorly
amount of money needed for the sub-projects during designed, the project manager will be constantly on call
a certain period exceeds the amount provided for because budgets are rarely met. In that case, the direct
the same period, then the time budget will have to control of the project manager is necessary and the
be modified to fit or more money must be allocated budgets and project plan as prepared are essentially
at points where there is a shortfall. useless for management.
The end result is a reconciliation and display of the two
most important resources needed for a project: time and Budget flexibility
money. The same process can be followed for budgeting
any resource such as labour or fuel. The requirement to meet budgeted amounts in carrying
out a project ranges from absolutely crucial to totally
irrelevant. When there is no flexibility, it is usually because
Using budgets the project has been constrained by outside forces that
in project management cannot be controlled by the project manager. For example,
a project that must install an electrical generator in
Although a budget may be developed wholly for inclusion time for a holiday festival has no flexibility in its time
in a project document and never used later, budgets are budgeted for completion. If it is not ready for the festival
very useful management tools. Time and money budgets on the date of the holiday, it is a failed project.
at least should be made for every project with the A money budget may be inflexible in its totals but
intention of using them to help to manage the project. flexible in its components. This is because the total
When a project has been well designed and budgets funding available is fixed, but the cost of different parts
of the important aspects of the project have been of the project can be juggled so that different parts are
developed, managers of parts of the project can be given allocated different amounts, so long as the total does not
considerable autonomy and the higher levels of the increase.
project management not brought in unless the budgets The fact that a project is far under budget for money
are in danger of being exceeded. or way ahead of schedule on a time budget is just as
For example, say that the project manager of a major much reason for the manager to step in as are overruns.
rural electrification project works from an office in the While the reason may be very efficient field managers or
capital city. The construction phase of the project has unrealistic budgets, it may also be that something has
been carefully planned and detailed budgets of time, been forgotten in the project and therefore less time and
time/money and money have been created for each money were needed than were budgeted.
Chapter-16.qxd 11/8/03 11:26 AM Page 103

Specifying and
purchasing equipment
16 C H A P T E R 16

Direct purchase be in stock, the whole purpose on the part of the vendor
being to get the order by offering a low quote and
For small lots of spare parts, replacement items and then switching to another item of lesser value at the
commodity goods such as wire, bolts or terminal blocks, same price.
simply contacting a supplier and making a direct purchase Abuses on the purchaser side of the system are also
is a reasonable practice. For replacement parts, there is common. For example, if a purchaser favours a particular
often no choice of vendor so a direct purchase is made vendor, other quotations can easily be obtained and the
even for items of relatively large value. favoured vendor given these prices so that a slightly
In general it is good practice to obtain price and lower price can be offered. Purchasers also soon learn
delivery quotations from several vendors for the same which vendors are consistently the most expensive so,
product. As the item is the same in all cases, the vendor when another vendor is favoured, only quotations from
with the best terms should receive the order. Price alone, the favoured vendor and from the most expensive
however, should not be the determining factor. Often a vendors are sought, almost guaranteeing that the
vendor will provide a lower price but cannot provide favoured vendor will be chosen.
the item in a reasonable time. Also, warranty service
varies between vendors and should be considered for Advantages of direct purchase
many items.
It is typical for purchase regulations to require three When a particular manufacturer or model of equipment is
or more quotations for an item and the lowest price must strongly preferred, direct purchase is the only sure way to
be chosen. While on the surface this appears to be a obtain exactly what is wanted. With a direct purchase, the
good system and should keep costs low, in fact there are purchaser has complete control over what is purchased
many opportunities for abuse. Product substitutions are and who supplies the item.
common, for example. In this case, the vendor gives a low With a direct purchase, factors other than price can
price for a specific item then, on receiving the order a sway the purchase decision. With solar equipment,
few weeks later, states that the item is now out of stock particularly controllers, low-voltage appliances and
and substitutes a lower-quality item. The purchaser batteries, the reliability of the component may be
usually will not want to go through the process of far more important than the lowest possible price.
changing the vendor and goes ahead with the purchase Particularly for installations that will be remotely located
of the lower-quality item. In reality, the item originally where maintenance visits are very expensive, it often
ordered may never have been in stock or may still makes sense to pay a substantial price premium for
Chapter-16.qxd 11/8/03 11:26 AM Page 104

104 Solar Photovoltaic


Project Development

high-quality components to ensure long, trouble-free particular type that happen to include the items
life. As reliability and inbuilt quality are notoriously sought by the project.
difficult to specify in a competitive tender situation,
One common arrangement, not usually considered as an
tender-based purchasing often forces the purchase of
agency purchase but effectively the same thing, is to ask
lower-cost, lower-reliability components than would be
a dealer in solar equipment to provide specific items
obtained through a knowledgeable direct purchase.
that are not normally part of the vendor’s catalogue of
available products. The dealer then purchases the item
Disadvantages of direct purchase
from another dealer or manufacturer and charges the
purchaser slightly higher than cost price, effectively
The primary disadvantage of direct purchase is the lack
adding an agency fee for that service.
of price competitiveness. The lowest possible price will
rarely be obtained through direct purchase.
Direct purchase also offers a great opportunity for
Advantages of purchasing
dishonesty. Special vendor arrangements with
through an agent
under-the-table payments to the purchaser, special
The greatest advantage of dealing through an agent is
treatment of purchasers by vendors, and other violations
convenience, particularly with foreign purchases. When a
of the trust placed in the purchaser and the vendor, are
number of different items are needed from different
common.
external suppliers, to arrange for their purchase is
A secondary disadvantage is that the quality of
complicated, time-consuming and expensive. An agent in
the item obtained is often a direct reflection of the
the other country can make the arrangements for
knowledge and capability of the purchaser, because
purchase quickly and simply, combine the purchases into
the purchase decision is essentially a personal one. If the
one shipment and take care of all the complexities of
purchaser is very knowledgeable and has the best
export licences, shipping and customs clearance.
interests of the project in mind, the resulting purchase
When the agent has superior technical knowledge
will be optimal. If the purchaser depends on advertising
about the products being purchased, it is an advantage
or the vendor’s recommendations to decide what item to
to use that knowledge to ensure the purchase of the
purchase, it is much more likely that a less than optimal
best components for the project. Some caution must be
item will be selected.
used, however, as agents are not paid on the basis of
providing the best components, but rather on the basis
Agency purchase of the cost of the components. So, rather than select
what is best for the project, an unscrupulous agent may
An agent is often engaged to purchase on behalf of the
obtain a particularly expensive component in order to
project. This decision is made because:
maximize the agent’s fee.
· The equipment is not available locally and it is In general, agency arrangements are based on
difficult to make arrangements for international a great deal of trust. Once an agent has proved to be
purchase — usually due to shipping, customs clearance trustworthy and competent, the value to the foreign
or foreign exchange problems — from the project purchaser can be much greater than the fee charged for
country. the service. Often the fee charged by the agent will be
· The project staff do not have the technical knowledge less than the external communications would have cost to
to make an informed selection of components so an place orders with many different foreign vendors.
agent with specialist technical knowledge may be
chosen to select the appropriate components and Disadvantages of purchasing
purchase on behalf of the project. through an agent
· There is a pre-existing arrangement with an external
agent by the government purchasing department and Agents charge fees. The fees are usually based on the
the agent is used for all foreign purchases of a type of materials being purchased, the complexity of the
Chapter-16.qxd 11/8/03 11:26 AM Page 105

Specifying and 105


purchasing equipment

order and the amount of money involved. The purchase lower than a specified amount and require tendering for
of large quantities of trade goods such as wire may incur purchases above that amount.
an agency fee of less than 5%, while the purchase of a
single dc/ac converter may result in a 20% agency fee. Restricted tender
The purchaser is also very much at the mercy of the
agent in negotiating prices with vendors. The agent does A tender that is open only to certain vendors is called a
not have much incentive to seek the lowest price as the restricted tender. In the most common type of restricted
agency fee is usually an add-on percentage of that price. tender, only vendors from a pre-approved list are allowed
Unless you are willing to do the price negotiations to submit prices and no other tenders will be accepted.
yourself (in which case you would probably be better off This type of tender is often used to supply spare
doing the purchasing too) you must depend on the parts or to add on to a previous lot of goods purchased
agent. Most agents are well aware that their long-term under tender. The organizations that supplied the earlier
success depends on customer satisfaction with both lot or the equipment that requires spare parts may be
service and price and generally attempt to get reasonable requested to tender for additional equipment or spare
prices from vendors. Rarely will they get the best parts. In some situations, the purchasing agency
price, however. maintains a list of ‘qualified’ vendors and only
While a good, trusted purchasing agent is valuable vendors on that list may submit tenders for goods.
and worth much more than the fee charged, a dishonest
or incompetent agent can be a disaster. When choosing Advantages of restricted tender
agents for long-term use, make sure that you fully The primary advantage is speed and ease of
investigate their capabilities in purchasing the type of administration. There is no need to advertise for
materials you want and their reputation for honesty and respondents, the tender is automatically sent to the list
competence. of selected vendors. The number of vendors is controlled
so there is no chance of receiving a very large number of
Competitive tendering tenders to evaluate, as can happen with open tenders.
By restricting the tender to those companies known to
While direct purchase and agent purchase arrangements supply the required items, the responses are comparable
have a number of advantages for small quantity and easier to evaluate. Additionally, you are reasonably
purchases, when larger quantities of goods and money assured that you will in fact receive qualified tenders
are involved, competitive purchase arrangements, often from companies providing the required goods. With an
called tendering or bidding, are generally used. open tender, this may not be the case.
The process of purchasing through tenders consists of Companies known to be reliable and to provide
six distinct steps: adequate after-sales service can be selected and
companies that may provide very low prices but are
1) determination of what is to be purchased and when unreliable may be left off the list.
it is needed
2) writing technical and procedural specifications
Disadvantages of restricted tender
3) distribution of tenders
The restricted tender process is more open to manipulation
4) tender evaluation
because it is not truly competitive. The person who selects
5) selection of vendor and purchasing
the companies who will be allowed to tender wields a
6) receiving test and acceptance.
considerable amount of power and is subject to many
The process of tendering can be expensive, so for temptations to abuse that power to personal advantage.
low-value purchasing the lower prices that can be Restricted tenders also do not usually provide the best
obtained through tendering may not save enough to prices. In particular, if a long-term ‘qualified company’ list
cover the cost of the tender process. Most government is used over and over, the tendency is for the companies
purchase regulations allow direct purchase for values to become less and less competitive over time.
Chapter-16.qxd 11/8/03 11:26 AM Page 106

106 Solar Photovoltaic


Project Development

Companies not on the tender list may complain small. Therefore, the tender responses may not include
bitterly, often applying considerable political pressure on equipment that would best fit the needs of the project.
the purchasing organization. For this reason, politically The quality of the product finally selected is directly
sensitive organizations tend to avoid the use of restricted related to the quality of the specifications. As price
tenders. is always a major issue in an open tender, if the
specifications are not written correctly, a low-cost,
low-reliability component may be approved for purchase.
Open tender One of the most common problems with solar projects is
that an inadequate set of tender specifications may result
This is open to any company wishing to submit a
in low-cost but also low-reliability equipment being
response. In fact it is often a form of restricted tender
purchased.
because there are geographical restrictions. For example,
bilateral aid projects often only allow the use of
equipment made in the donor country. However, any firm Successful tendering
within the stated geographical area may submit and be
considered. This form of tender is usually the most formal In general, a tender can be considered a success if the
and tightly structured. It is usually the form used for equipment ultimately supplied does the required job
high-value purchases. properly at an acceptable cost.
The technical specifications generally determine the
quality and appropriateness of the equipment purchased
Advantages of open tender therefore preparation is very important.
The cost of the supplied materials in relation to the
The process is generally considered the least likely to be amount budgeted for them will generally be determined
manipulated for personal gain. While there are abuses, if by the experience and capability of those doing the cost
administered correctly the open tender is the most likely estimates for the budget and those administering the
of the several purchasing methods to obtain a truly tender process. The cost of materials supplied by tender is
competitive price. often much greater than the project budget yet the prices
quoted are competitive within the market place. This is not
Disadvantages of open tender a fault of the tender process, rather it reflects on the
quality of the cost estimate used to develop the purchase
It is a costly, slow process. It is not uncommon for the budget. One relatively common reason for this is the fact
time between commencement of the tender process and that many larger projects, particularly within government,
the actual selection of vendors to be six months or more. have cost estimates prepared many years before the actual
It is costly for the tendering companies too. The strict project is implemented. Worse, these budgets may also be
structure of the open tender must be followed exactly based on costs incurred in an even earlier project. When
or the tender will be thrown out during the initial stages the tender is finally prepared, the cost figures are not
of qualification. Usually there are many requirements brought up to date and the budget is much too low to
for details about the product, the company and even allow purchase of the materials in the quantity specified.
company personnel that must be included in a very
specific format. The conditions of the tender are usually The tender process
complex and difficult to understand, often requiring a
specialist or lawyer to interpret. For this reason, small Determining what is to be purchased
companies are much less likely to submit a response than under tender
large companies with staff well experienced in the
complexities of open tenders. This can be a problem with For most projects, specific rules have been set by the
solar projects because the industry is not large and many government or the project financing agency that
of the companies supplying quality products are still determine what must be purchased under tender and
Chapter-16.qxd 11/8/03 11:26 AM Page 107

Specifying and 107


purchasing equipment

what can be purchased without tender. When this is not local service. The risk of tendering for such items is
the case, you should consider tendering for: that you may receive an offer that fully meets the
specifications at a lower cost but which is for an item
· high-cost speciality items. As these usually have
known to be inferior. While it is possible to write
relatively high profit margins, significant reductions in
tender specifications that exclude most unwanted
price can sometimes be obtained through competitive
items, you may have to accept an unwanted item
tender.
simply because it does in fact meet the specifications
· unusually large quantities.
and has a lower price.
· When you have not purchased the item
competitively for more than a year. If you do not
Writing technical specifications
know the competitive market price for an item, you
cannot know what price you should be paying.
For rural electrification projects, writing technical
Competitive tenders provide an arena for competition
specifications is the most critical step and the one where
in which true market prices may be found.
most problems originate. To obtain products that are
· When miscellaneous items are to be purchased as
satisfactory for your application you should follow these
a group rather than individually. For example, if you
guidelines:
wish to have suppliers provide a complete PV lighting
system, you will want them to assemble all the · Write specifications around equipment that has
components and state a price for a package, not the been proven in the field. Once you find a piece of
individual components. By tendering, you have better equipment that works reliably under your field
control over the specifications of the individual conditions, write detailed specifications around that
components and can take advantage of some vendors’ piece of equipment. Choose very specific details about
ability to supply many components and give a better that equipment that are not common to other,
overall price. less-acceptable equipment.
· If you are tendering for an item that has no field
You should consider not tendering for items when:
experience in the conditions of the project site,
· the items are peripheral to the project and represent seek assistance from those who do have field
a small part of the overall cost. For example, hand experience under those conditions. Never base
tools will probably be better purchased separately than tender specifications on manufacturer’s brochures or
as a part of a project tender. Generally the respondents advertisements. If you want to know how the unit
to the tender will be specialists in supplying the main works in the field, you must have access to actual
project items and will provide a competitive price but for field experience.
peripheral items not within that speciality, they will · Clearly state the environmental conditions that
simply purchase the equipment from other vendors and will be found at the project site. Equipment
increase the price to cover their costs plus their profit. intended to be mounted inside a Western-style frame
You can thus purchase at about the same price as the or masonry house may have serious problems if placed
supplier and can save much of the add-on cost. in a local-style house with open walls or walls made
· the items are commodities. A commodity is basically from woven bamboo or other materials that sun, dust
a standardized product produced and marketed in and rain can penetrate. Temperatures are especially
such large quantities by many manufacturers that the critical with electronic items. The presence of salt
market is already highly competitive. Wire and wall spray, dust and very high average humidity can
switches are two such commodity items. Indeed, such severely stress mechanical equipment and must be
items often end up costing more when priced by noted in the specifications.
tender than by quotation because the vendor has to · Use other tenders as models. If items of the type you
prepare a complicated tender response. wish to purchase have been received before in response
· you want to purchase very specific items because to a tender, use those tender specifications as the basis
of their long field experience or the availability of for your tender. But do not blindly copy other tenders,
Chapter-16.qxd 11/8/03 11:26 AM Page 108

108 Solar Photovoltaic


Project Development

especially if you do not know how successful the tender Shipping should usually be for CIF (Cost, Insurance and
was in obtaining the appropriate components. Freight — the sum of the cost of the item, freight to your
· Seek external, expert advice. If you are not familiar port of entry, offloading on to the dock and shipping
with writing tender specifications for the items being insurance). It is common for suppliers to quote FOB (Free
purchased, consider obtaining expert assistance. As On Board) their factory (FOB does not include shipping,
the expert can do the assistance without travel, the offloading or insurance) or FOB your port (does not
cost need not be high. In a major project the possible include insurance or offloading but does include shipping)
cost of having to use inadequate equipment can be that can make comparison of responses difficult. Tenders
very high and even fees amounting to several percent may even specify door-to-door shipping where every cost
of the tender value can often be justified. At the very incurred between the factory and your receiving point
least, send the technical specifications to someone is included. Use caution with specifying door-to-door
with experience and ask for comments. shipping, however. It may be very difficult for the foreign
· Use manufacturer tender specification sheets. If respondent to find out the real cost of delivery from the
you have a particular manufacturer’s product in mind dock to your site and the shipping cost may be inflated
that you specifically wish to purchase, ask the to cover that uncertainty.
manufacturer to send you a tender specification sheet Special conditions that apply just to the tender at
for that product. Many manufacturers prepare hand must be written to cover details such as the
technical specification sheets for tendering that are tendering address and acceptable method of delivery of
generally written in a manner intended to almost tenders, number of copies of tenders required, shipment
guarantee the purchase of their product. address for delivery of goods and other terms and
conditions that are not in the general conditions.
When there is no specific manufacturer’s product that
Also in the special conditions there often must be a
you wish to purchase, you must write the tender
section that modifies or supersedes some of the general
technical specifications with enough detail to guarantee
conditions that do not exactly apply to the tender at
a satisfactory product, without adding so much detail
hand. For example, the general conditions may state that
that no manufacturer can meet the specifications. A
full payment will be made for materials within 45 days
common mistake is to add specifications that are not
after receipt. For this tender, suppose you wish to pay
really necessary but you believe would be useful. For
90% upon receipt and withhold 10% until the warranty
example, in a PV charge controller specification you
expires, then you must include in the special conditions
might add the requirement for an indicator light to
a section that cancels that part of the general conditions
show when the battery is fully charged. If that light is
relating to payments and add the new conditions.
not very important to the functioning of the controller
in your application, do not include it in the tender
specification because an excellent controller that does Adding schedules and response
not include an indicator light will not then meet the format sheets
specification. Specify only those characteristics you
must have for the item to function correctly in your An important part of the evaluation process is the
application. inclusion of forms for the tender response that organize
the information in a way that simplifies comparisons
Adding general and special conditions between respondents. Without a standardized format,
every respondent will provide the required information in
General conditions typically apply to all tenders. Most a different way and it can be time-consuming to
offices that prepare many tenders will have created a set assemble the information for easy comparison.
of general conditions that are included with all tenders. In comparing technical specifications, it is particularly
These conditions will include such things as payment useful to provide a sheet for each component of
terms, warranty terms, shipping procedures, liability the technical specification, requiring the respondent
information and legal jurisdiction for disputes. to specifically state for each important aspect of the
Chapter-16.qxd 11/8/03 11:26 AM Page 109

Specifying and 109


purchasing equipment

specification the characteristics of the proposed product. in one or two periodicals, though that may be the
This ensures that the respondent clearly states whether minimum legal requirement. No publications serve a wide
or not the product is claimed to meet the individual enough geographical range of solar suppliers to make such
specifications, ensures that no important specifications an advertisement likely to bring in the wide range of
will be overlooked either by the respondent or in the respondents desired. Solar suppliers are often relatively
evaluation, and puts the information in a comparable small businesses and have neither the time nor the
format. money to subscribe to and carefully examine the many
publications in which international tenders are listed.
Setting a date for tender receipt For tender distribution to be successful, the tendering
agency must actively seek out companies that supply the
The amount of time needed between announcing the required products and encourage them to respond. As it is
availability of the tender and the cut-off time for receipt not a trivial task to locate manufacturers and suppliers of
of responses depends on the complexity of the tender, equipment, assistance should be sought from embassies,
whether it is a restricted or an open tender and trade associations, aid agencies, United Nations offices
the needs of the project. and others involved in purchasing similar equipment
The time needed is a combination of the time internationally.
necessary for the prospective respondents to learn of the
tender, the time needed to prepare the response and Providing clarification and amendments
the time needed to deliver the response. as required
· Time necessary for respondents to learn of the
It is not unusual that some sections of a tender are
availability of the tender. For a restricted tender
either completely wrong or are so difficult to understand
where the respondents are automatically provided
that many requests for clarification are received. If the
with the tender document, about two weeks should be
tender is essentially correct and a response should be
allowed for the tender to arrive at their place of
possible, then a direct clarification to the enquiring
business. For open international tenders, an additional
party may suffice. If there is an error or if important
four weeks are needed for respondents to learn of
information needed to respond properly has been left
the tender through advertisement and word of mouth
out, it may be necessary to issue an amendment to the
then request that a copy be sent.
tender. This has to be advertised in the same manner as
· Time necessary for response preparation. This varies
the original tender plus those firms that have requested
according to the item being sought and the complexity
clarification must be sent the amendment directly. Usually
of the tender. If the respondent is expected to provide
an amendment also changes the date of the required
one or two simple items, two weeks may be sufficient.
tender receipt by several weeks as the notification
If the respondent must assemble a number of items
process takes extra time.
into a combined package, several months may be
necessary. Typically, at least one month should be
allowed for response preparation.
Evaluating tenders
· Time necessary for response delivery. Unless your
Once tenders are received they must be evaluated. There
location is unusually poorly served by air transport,
are four separate steps in the evaluation process:
two weeks is generally sufficient for even
international open tender responses. 1) Procedural evaluation. Did the respondents do what
they were meant to do? Did they submit the tenders
Advising of availability of tender on time, are all the required papers included, is the
required form followed? Note any errors that could
A requirement for successful tendering is that the tender disqualify a respondent.
documents are sent to a wide range of probable 2) Technical evaluation. Do the items proposed in
respondents. It is rarely useful to simply advertise a tender the tender meet the specifications? Are there any
Chapter-16.qxd 11/8/03 11:26 AM Page 110

110 Solar Photovoltaic


Project Development

technical details missing or details that need International tenders in particular can be difficult
clarification? What are the technical problem areas because of foreign languages, terminology different from
and how serious are they? How do each respondent’s that used locally and units from a different system of
proposals for equipment compare with the others? measurement to that used in the specifications.
Note all specifications that are not met or that require For small purchases one person may have to do the
additional information from the vendor. complete evaluation, so the person who wrote the tender
3) Price evaluation. Do the prices quoted include documents is often the best choice. But if the technical
everything asked for in the tender? That is, were such evaluation is at all complex or if there are difficult choices
things as freight and insurance meant to be in the to make, it is important to obtain outside assistance. After
price quotation and if so, are they? Are all the prices all, the quality of the project can only be as good as the
in the proper currency and presented with the proper quality of the components and making the wrong choice
conditions? If not, they should be converted to the at the tender evaluation can condemn a project to failure.
correct format. How do the prices of the different
tenders compare? Note any prices that are incomplete Obtaining evaluation assistance
or whose form does not fit the requirements of
the tender. For large purchases, the best approach is to hire a
4) Overall evaluation. Taking the technical and specialist and funding is often set aside for that purpose.
the price evaluation together, which of the tenders For smaller purchases, the need for outside assistance
provides the best value? By definition, the lowest may be just as great but funding is not available. In that
priced response that meets all specifications is the case, there are several possibilities:
best value. If no one meets all specifications (true 1) An expert from another branch of government.
about 90% of the time for technical tenders) then There may be someone in another department that
the combination of price and the importance of has the experience and skills to assist. A competent
the specifications that are not met must be weighed person will require very little time to evaluate a small
to find the best value. The same is then done to set of tender responses and this can often be fitted in
determine which is next best, and so on. as an interdepartmental favour.
2) An expert from an international agency or
Who does the evaluation? institution. The United Nations, the regional
government associations, the European Union, the
Procedural evaluations can be performed by anyone Commonwealth Scientific and Industrial Research
who can follow instructions and is careful about details. Organization (CSIRO) and many other such
All that is required is an understanding of the exact organizations may be able to assist either by
requirements of the tender and the ability to check to see providing a staff expert to assist in the evaluation or
if the respondents have carried out those requirements. by putting you in contact with another organization.
The answer is usually yes or no and little judgement is For small jobs of this type, the task will usually be
required. The person who wrote the tender documents is done without fee, particularly if the organization is
ideal for this task because, if anyone knows what approached politely and asked to assist only in the
procedures should have been followed, the preparer will. part of the evaluation that cannot be properly done
Technical evaluations are more complex. Sometimes a by local staff.
clear yes or no decision can be made without much 3) An expert from a university. It is more difficult to
thought but often a good understanding of the obtain free evaluation services from universities as
technology and experience in judging what is and what is they usually have budget problems themselves, but it
not important comes into play. For a proper technical does no harm to try. When fees are charged, they
evaluation, you need one or more technically competent may be moderate enough to be acceptable.
people with experience of projects of the type Do not, however, make the mistake of taking advantage
being tendered. of these ‘free’ services when they are not genuinely
Chapter-16.qxd 11/8/03 11:26 AM Page 111

Specifying and 111


purchasing equipment

needed. If you get the reputation of continually farming lower-priced equipment. If you are tightly constrained
out your work to others, you will soon get refusals by time, the extra few months necessary to retender may
instead of assistance. Seek assistance only for those not be worth a small improvement in the quality of the
knotty problems that you cannot solve at home and put purchased goods. If the lowest-priced equipment is so
them into the simplest possible form first. bad that your project will suffer as a result, it may be
better to start again with better specifications than to
proceed with inferior equipment.
Making the final selection In most tender evaluations, tenders that provide
favourable terms to the buyer are rarely disqualified,
If the best value response also offers the lowest price,
even for fairly flagrant violations of the procedural terms
there should be no problem in selecting that vendor. If it
and sometimes of technical specifications as well. On the
is not the lowest price, and the tender regulations you
other hand, tenders are often disqualified on minor
have to use do not allow you to choose any but the
points when they offer poor-quality goods, even though
lowest-price vendor of the qualified respondent list, then
the price is very good. These practices are generally
you must see if you can disqualify the lower-priced but
ignored where the expenditure involved is not too great.
lower-value respondents.
Large-value tenders are usually handled with greater
It has been the experience of those doing tender
rigour because of the likelihood of close scrutiny by
evaluations for technical product purchases that, strictly
respondents that are not selected. There must be very
speaking, about 90% of all tender responses could
solid grounds for having selected one respondent who did
be disqualified on the basis of procedural errors or
not meet all the tender requirements rather than many
the fact that the products offered do not exactly meet
other respondents who also did not meet all the tender
specifications. It is far harder to qualify most vendors
requirements but did offer a lower price.
than it is to disqualify them.
If you wrote the specifications correctly, then the
response judged the best value should have no Good tender evaluations follow
lower-priced competition in the tender responses that good tender specifications
meet your specifications. If no respondent meets all the
specifications and the technical evaluator gives a Most of the problems of tender evaluation and justification
best-value response that is not the lowest price, then you of vendors offering the right equipment can be avoided if
must convince the agency that oversees the award of tender specifications are well written. Where high-quality
tenders that your choice is sufficiently better technically evaluations with clear choices between acceptable and
than the lower-priced offers to justify the additional cost. unacceptable vendors is necessary, as when large
If the agency cannot be convinced, as is often the case, purchases are involved, hiring specialists to assist in the
you have the option of retendering or of accepting the writing of the tender documents may save a great deal in
lowest-price response. This decision is wholly dependent the evaluation process and may avoid having to purchase
on the situation and the reasons for not wanting the goods of inferior quality simply because of their low price.
chapter-17.qxd 11/8/03 11:27 AM Page 113

Keeping a PV project operating 17 C H A P T E R 17

What is maintenance? 2) As-built plan. This is an accurate plan of the


installation as the system was actually built. It is not
The term ‘maintenance’ is often used to describe what is the same as the plan prepared before the installation.
in fact ‘repair’ — fixing something that has failed. For our The actual installation will normally differ in some
purposes, maintenance is used in the much broader sense respects from the original design and these changes
of keeping a system working at its optimum. Maintenance must be part of the plan kept for maintenance
includes repair but it also includes regular checks to purposes.
make sure that all the components of a rural electricity 3) Installation test records. To be able to tell when a
system are working the way they are intended to. It includes system is not performing correctly, it is first necessary
the regular replacement of materials that are consumed to know how it performs when it is working correctly.
in the operation of the system, such as battery water with At the time of installation, tests should be carried out
PV systems or engine oil with diesels. Most failures of PV on all the components and their results recorded. These
systems are not abrupt, dramatic failures but are the result tests not only prove that the components are working
of a long series of minor problems. If these problems are to specifications, they also provide a benchmark for
resolved instead of being allowed to accumulate, failures later tests when problems are encountered.
are much less likely and component life much longer. 4) Maintenance log. At the very least, a book with the
Periodic checking to ensure that minor problems are taken date of each maintenance visit, the name of the
care of before they become major problems is preventive technician, and a brief description of the scope of the
maintenance. Solar PV is a technology that benefits greatly maintenance and of anything unusual that was
from preventive maintenance. observed.
5) ‘Readings’ log. Where part of the maintenance
procedure includes reading voltages, temperatures or
Records any other meters, these should be written in a log to
indicate whether a slow but progressive change in
One of the most important but least observed maintenance
the readings is occurring. With PV systems, if battery
tasks is adequate record keeping. It is much easier to
hydrometer and voltage readings are logged at each
diagnose problems, obtain the right parts and make
visit, it is easy to see if problems with the battery are
satisfactory repairs when the following are available:
developing.
1) Component list. A complete record of the 6) Repair and change records. If components are
manufacturer, model and serial number of all parts replaced or changed, whether because of failure or in
installed at the site. order to modify the system, the manufacturer, model
chapter-17.qxd 11/8/03 11:27 AM Page 114

114 Solar Photovoltaic


Project Development

and serial number of each new component should Detecting problems early
be added to the component list. Any components
that have been replaced should be crossed off the As preventive maintenance is intended to resolve small
component list. Any changes to the as-built plan problems before they threaten the overall operation of
should be made if it is affected by the repair or the system, it is first necessary to recognize that problems
modification. exist. This requires a thorough understanding of how the
These records should be kept together in a water-resistant system should work. Maintenance technicians should be
package at the installation site as well as keeping an office very familiar with the signs that the system being
copy. Copies of the component list and the as-built plan maintained is working properly. They should know how to
should be kept in a file at the maintenance organization test the components for correct operation and know
offices and updated when changes are made to the which test values show good components, which indicate
installation. marginal components and which indicate problems.
As a technician only comes into contact with the
system once every month or two, it is essential to discuss
Preventive maintenance with the people using the system every day how it has
been working. The user of the PV system is most familiar
for solar electricity systems with how well it works. Just as when you are becoming ill
you notice changes in the way your body works, when a
It is always better to stop a boat from leaking by regular
PV system is beginning to have problems the user will
care instead of waiting until it sinks before fixing it. With
notice changes in the way it works. When the user starts
a rural electricity system, it is much better to regularly
to notice changes in the way the system works, it is
check everything and to resolve small problems before
time to do an exceptionally careful check. Even if no fault
they become major ones.
is found, the technician should always write down what
Because preventive maintenance of solar electricity
changes the user has noticed so that if a problem does
systems is so simple and so little seems to be done
develop there will be a record of how it started.
at each visit, it may seem unimportant. It is not
Changes in the way the system works, or in the
unimportant. Small problems, like minor cracks in a boat
behaviour of the components, indicate a potential
hull, soon become major problems if not resolved. By
problem. If the electrolyte level in the battery begins to
carrying out regular maintenance, major repairs are less
fall at a more rapid rate than before, the maintenance
likely to be needed.
technician should carefully check the controller, the
How often maintenance visits must be made depends
battery and the system usage to see if there is really a
on the type of equipment installed and the way it is used.
problem or if the battery is simply ageing. The ability to
For new photovoltaic projects, there is not usually much
identify changing conditions is important to preventive
point in scheduling maintenance visits more frequently
maintenance and is the point of good record keeping. No
than once a month, but neither should more than about
technician who has to maintain dozens of systems can
two months pass without a regular check. After a few
remember the hydrometer readings of each cell in a
years, the maintenance schedule can be adjusted. If little
battery. If the hydrometer readings are changing in a
maintenance is required for about three months at a time,
pattern that indicates problems, without prior records the
then a three-monthly schedule could be implemented. If
technician will not see that pattern or realize that a
problems frequently occur between maintenance visits,
problem exists until it has become so serious that it
then a more frequent schedule is indicated.
probably cannot be cured without battery replacement.

Maintenance functions Preventing problems

The goal of preventive maintenance is to prevent By inspecting all parts of the system during maintenance
situations from arising that will result in component visits, potential problem areas can be found. In addition,
failure. the simple but important task of keeping all operating
chapter-17.qxd 11/8/03 11:27 AM Page 115

Keeping a PV project operating 115

components clean and connections tight should be part 2) Every part of the solar PV system is checked
of every maintenance visit. The quality of connections for correct operation, cleanliness and good
and size of wiring in low-voltage systems are much more connections. There are few parts in a PV system, but
important than in ac mains power systems. A battery problems with any part will cause the entire system to
connection that looks correct but in fact has internal work poorly. In particular, problems with wiring, panels
corrosion or is loose can dramatically reduce the amount or the controller can damage the battery and greatly
of power that is stored from the panels or delivered to shorten its life. Dirt and corrosion always cause
the appliances. problems with electrical equipment. Loose or corroded
Unauthorized modifications can cause serious connections will cause problems. Every part should be
problems. Adding appliances, changing wires or relocating checked at every maintenance visit.
wires almost always creates problems with system 3) Components that are not in good condition are
reliability. Users should be allowed to have a system that repaired or replaced. If a component is not working
fits their requirements, but modifications must be made correctly, if it is not immediately repaired or replaced
by someone who understands the effect of those with a good unit, the system will not work well and
modifications on the system and can take steps to ensure other components, particularly the expensive battery,
that no component is damaged as a result. may be damaged.
Maintenance technicians should know how to detect 4) The system is checked to make sure that no
consistent excessive consumption of energy by the unauthorized changes have been made. It is
user and discuss with the user how to either reduce common for a user to add more appliances to a solar
consumption to an acceptable level or increase the PV system. Because the system has been carefully
capacity of the system to meet the higher load. If designed around the original set of appliances,
excessive use is suspected, the technician should check adding any new appliances will cause problems and
the charge level of the battery late in the afternoon shorten the battery life. If more appliances are
after a series of sunny days. If it is not at full charge, required, sufficient additional panels and a large
consumption probably exceeds the design value and will enough battery must be installed at the same time
have to be reduced, or panel capacity increased, for the as the new appliances otherwise the system will
unit to continue to produce electricity reliably. soon fail.
5) A record is made of any action taken during the
Repairs maintenance visit. Problems with PV systems often
develop slowly. If careful records are kept, it will be
Repairs should always be carried out using the correct much easier to see what repairs are required when
replacement components. One of the most serious the system finally does break down. Also, a record
problems with user maintenance is a strong tendency to of maintenance activities will point out particular
replace components with units that cannot provide the components that are not working properly and the
level of service needed, often because the appropriate manufacturers can be contacted for improved
parts are simply not available in rural areas. The models.
spare-parts system implemented under the project must
make these components available for repairs. Summary
Checklist of maintenance activities Preventing failure of a PV system is usually more
cost-effective than repairing a failed system. Good
1) The user is questioned about the operation of the preventive maintenance can dramatically increase the life
system to see if there are any problems. The user of the battery and keep user satisfaction at a high level.
of the PV system is most familiar with how well it Spare parts should be of comparable quality and
works. When changes in system operation are noticed specification to the original components otherwise the
by the user, it is time for an exceptionally careful system will not meet the performance level it was
check of the system. designed for.
Chapter-18.qxd 11/8/03 11:29 AM Page 117

Spare parts systems 18 C H A P T E R 18

Spare parts requirements essential for the operation of the project should probably
be stocked, even though they may sit on the shelf longer
When a project is first made operational, though there than three years. If there is a well-stocked dealer in the
will certainly be a need for spare parts for repairs, what country that can be depended on for a quick response to
parts will be needed or when those needs will arise may spare part needs, it may not be necessary to maintain a
not be easy to predict. diverse enough stock to meet 90% of repair needs.
If too large a stock of parts is initially provided, the
extra cost of purchasing and storing the parts will not be New project parts estimate — using
a good use of the project funds. Also, spare parts that estimated failure rates
remain in storage for a long time before use are often
corroded, damaged or lost. Also, there is always the As the need for parts is directly related to the rate of
possibility that someone in a fit of cleaning will throw out failure of the parts when in use, the first step in
all those ‘old bits and pieces’ that have been lying around estimating the number of parts to be kept in stock is
for so long. to estimate the life of those components in service.
If too small a stock of parts is provided, frequent Suppose a controller used in PV systems is estimated
purchase orders will have to be placed to obtain parts for by the manufacturer to have a life of 10 years without
what should be routine repairs. This can be costly both replacement. The project using the controller is new and
in the time and the money needed to expedite shipment you do not have any field experience with the controller.
of the parts. There are 100 controllers installed in the project. Assume
The goal of spare parts management should be to further that it takes three months to obtain replacement
have enough parts on hand so that a high percentage of parts from the supplier. How many controllers should be
all repair requirements can be met from that stock but in the parts inventory?
only a low percentage of the spare parts sit on the shelf A simplified approach is to assume that all the
for a long time. Reasonable goals for rural electrification controllers will fail sometime in the first 10 years and that
projects are for at least 90% of all parts needed for the failures are distributed evenly over that period. This
repairs to come from spare parts and less than 10% of means that with 100 controllers installed, 10 are estimated
the spare parts to stay in stock for longer than three to fail each year. As the lead time for obtaining controllers
years. Certainly, these goals are flexible and must be is three months, the minimum number would be the
adjusted for special circumstances. For example, parts number of controllers estimated to fail in a three-month
that are particularly difficult to obtain quickly but are period: 2½. Therefore three controllers would be required.
Chapter-18.qxd 11/8/03 11:29 AM Page 118

118 Solar Photovoltaic


Project Development

This simple system of estimating may be useful for the expected number of failures of that part in a day.
some types of parts but the assumption that the failures Multiply this fraction by the number of days that it takes
will be evenly distributed over the average life of the to obtain replacements from the supplier. The result is
components is usually not valid. the minimum stock that should be on hand.
Typically, there will be an early flurry of component For example, suppose there are 150 installations of
failures as those that work initially but have some solar lights in the project. Experience over the last five
weakness will fail. Then there will be a period with few years has shown that the bulbs have an average life of
failures up to the time when the age of the components is 90 days. It takes 60 days to receive a shipment from the
about 70% of their average life. When the age of the dealer of replacement bulbs. How many bulbs should be
components begins to approach their average life, failures kept on hand as spare parts?
will begin to increase, with most of them failing around Each installation will be expected to require four
the average life mark. After that the number of failures bulbs per year (365 ÷ 90). So 150 installations may need
will gradually fall until all units have been replaced. 600 bulbs a year. 600 ÷ 365 = 1.64 bulbs per day.
Hence it is wise to have a larger stock of parts initially It takes 60 days to obtain the bulbs from the supplier, so
available than the quantity predicted by the simplified 1.64 × 60 = 98.4 bulbs. The minimum number of bulbs to
method in order to cover the expected flurry of early have on hand at any one time would therefore be 99. If
failures. A suggested initial parts inventory is about the number on hand falls to 99 more should be
double that indicated by the simplified analysis. For the immediately ordered.
controller example, at first five or six would be stocked
instead of just three.
For a project that is old enough for there to have
Obtaining historical data
been three or four replacements of the component in
For spare parts management, the most important records
question, there will be a much more even distribution of
are those indicating when parts have been replaced.
failures because the average age of the components will
Without these records, it is difficult to predict what the
not all be the same, as it was when the project began.
failure rate will be.
This means that as the project ages and parts have gone
Records of parts usage are often kept for a spare-
through several replacement cycles, the simplified method
parts inventory, but not often for those parts purchased
will be closer to reality than when the project was new.
directly from suppliers as replacements. All replacement
of parts should be recorded. Each individual installation
Older project parts prediction — using should have a record sheet with full details of the
historical data operational and repair history of that installation. Ideally,
a copy should stay with the installation and another copy
Manufacturers’ predictions of component life are often be kept in the office of the administrator of the project.
too optimistic, but when the project is new they may be Whenever an old part is replaced by a new one — for
the only details available for predicting the use of spare whatever reason — details should be entered on the
parts. Once a project has been in place long enough installation record sheet. Not only is this important for
for a particular part to have been replaced two or three spare parts management, it will immediately indicate any
times, the actual service life of those components will be unusually high rates of failure for components of that
known. Also, by then, the time of replacement will have particular installation. Unusual failure rates often point to
become more and more random so the simple approach abuse of the system or design errors that have placed
of dividing the number of installations by the average under-rated or low-reliability components in the
life of the components in years will give a reasonable installation.
estimate of the number of those components that will be
used in a year. The time required to obtain the parts is Using historical data from other projects
determined and the number of parts to be used in that
time is predicted. First divide the number of parts When a project is new, historical data are not available. If
expected to fail in a year by 365. This decimal fraction is similar projects using some of the same components have
Chapter-18.qxd 11/8/03 11:29 AM Page 119

Spare parts systems 119

been installed elsewhere, it may be possible to obtain environmental conditions is unlikely to occur.
data on failure rates from that older project to help in Administrative procedures should also be in place to
determining the quantity of those components to stock ensure that someone is clearly responsible for the
as spare parts for the new project. The closer the other inventory of parts and that parts are regularly checked.
installation is to the design of the new one, the more It is particularly important that inventories are
accurate the information will be. regularly taken of the spare parts stock. A complete,
Often, component reliability data can be used from detailed inventory should be taken at least annually
projects using the same components in other developing and all records checked against the actual stock.
countries with similar field conditions. As long as the use Unannounced spot checks by supervisors every few
of the component is similar, such data are useful. months is also a good idea. This not only discourages the
Test data from organizations not associated with unauthorized use of spare parts by the local technicians,
manufacturers, such as S.P.I.R.E. and CSIRO, are useful in it also means that all parts are examined so that there is
estimating life and spare parts requirements as long as some guarantee that they are still usable and have not
the actual equipment tested is exactly the same as that been damaged while in store. All too often, spare parts
being used in your project. It is less useful to have test are found to be unusable due to corrosion, insect
data for even a slightly different component because damage or other reasons.
small changes can have a major impact on reliability. The person responsible for the parts should also be
trained to clean and maintain them where required. For
Security example, batteries shipped filled with electrolyte must be
kept in a fully charged condition if the batteries are to
Spare parts usually represent a considerable financial last a long time. Someone must therefore arrange for
investment. It is important that they be kept where battery charging at least every two months if the spares
theft or physical damage from rain, heat or other are to be kept in good condition.
Chapter-19.qxd 11/8/03 11:30 AM Page 121

Special considerations
for solar utilities
19 C H A P T E R 19

What is a solar utility? utility, RESCO or fee for service approach consists of
renting PV systems instead of selling them.
The ‘solar utility’ structure for PV electrification
originated in Fiji in 1983 when the Department of Energy Service not solar
installed three village PV electrification projects. The
users did not own or maintain the PV installations Rural households do not want solar PV systems, they
but paid a fixed fee every month for their use and want electrical services. People have been willing to pay
maintenance. Users had no responsibility for maintenance surprisingly high prices for reliable, adequate electrical
or any technical aspect of the project, only for the services and the successful projects have been those
intelligent use of the systems and the payment of the emphasizing long-term quality of service rather than the
fee. Although those early projects were unsuccessful sale of PV systems.
owing to both technical and structural flaws, the The development of the RESCO structure is
knowledge gained resulted in the successful development specifically to shift the emphasis of PV electrification
of solar utility concepts in other parts of the Pacific. The from encouraging people to buy solar systems to the
solar utility structure has recently been used in a number provision of electrical service to rural households.
of projects worldwide and has proved to be the most
consistently successful approach to PV-based rural
electrification in developing countries. When the concept Sales versus rental (RESCO)
was developed in the Pacific, the term ‘solar utility’
was coined but that has proved to have unfortunate Creating a RESCO can be difficult, complex and expensive.
associations in donor-analyst minds with large, monopoly Why should a RESCO be used instead of the much simpler
companies so the name RESCO (Renewable Energy Service sales approach? Essentially, it is because the sales
Company) has now been applied to the concept of a solar approach has not worked well in the long term. Few
utility, though technically an energy service company households can or will buy PV systems because the price is
does not always supply only electricity. While ‘solar too high and people’s confidence that they will get their
utility’ is actually more accurate and descriptive of the money’s worth is too low. With few households buying, it
concept, common usage of the term ESCO or RESCO is difficult for the selling company to provide
has made the term obsolete. Also popular in some cost-effective after-sales support. As time passes, systems
development circles is the term ‘fee for service’ (FFS). develop problems and customers learn that repairs are
They all mean the same. Whatever the name, the solar difficult and expensive. The service that people want is
Chapter-19.qxd 11/8/03 11:30 AM Page 122

122 Solar Photovoltaic


Project Development

not being provided, the word gets around and soon there life cycle considerations. Therefore systems sold are
are so few sales that the company fails. usually undersized in an attempt to keep the sales
How do the operating characteristics of sales cost as low as possible. This results in marginal
companies and RESCOs compare? performance, poor quality of service and low customer
· Market penetration and customer density satisfaction.
Sales : Cash sales in rural areas of developing countries RESCO : There is a strong incentive for a RESCO to
can typically be made to no more than 5% of design systems for minimum life cycle cost rather than
households. Providing credit terms for two or three first cost as it must operate and maintain the systems
years may increase this to more than 10% but there indefinitely. As long-term maintenance costs,
is still little benefit to the great majority of rural particularly battery replacement costs, are most
households. economically lowered by increasing panel capacity,
RESCO : Provides finance over the real life of the systems are likely to be designed with more than
systems, 15 to 20 years. This cannot be done by adequate capacity. This also increases system
direct commercial sales to individuals as no bank or reliability and quality of service, so customer
commercial lender is willing to finance a PV system for acceptance is high.
more than three to five years due to the risk and high · Installation quality
cost of servicing such a small account over such a long Sales : Installation is often poorly carried out, in
time. Long-term finance can be arranged, however, particular where customers are expected to do the
for the purchase of a large number of PV systems to installation, or where a local handyman is employed
be owned and installed by a company providing for the installation. Customers are rarely willing to pay
electrical service from the systems to fee-paying the cost of professional installation.
customers. Furthermore, thanks to the large RESCO : System performance is the responsibility of
purchasing power of such a company, the initial cost the company, not the individual user. Installations will
of the systems will probably be 30% or more below be carried out professionally as it is in the best
the cost paid by individual households, making it interest of the company to provide customers with
possible to further lower the cost to the user. optimal performance.
Experience has shown that where a sales company can · Replacement components
only expect to sell to less than 5% of rural Sales : With user ownership of systems, there is a
households, a RESCO can reach over 50%. strong tendency to purchase replacement batteries,
· Maintenance quality controllers, lights and other components on the basis
Sales : Because the market for selling PV systems is of lowest cost and immediate availability, rather than
such a small portion of the rural population, the attempting to match the operating characteristics
customers are spread thinly over a large geographical of the original equipment. The end result is usually
area. The cost of transport and time for moving degraded performance, reduced customer satisfaction
between these widely separated customers is high, and increased maintenance costs.
causing maintenance costs to be very high. As a RESCO : This approach automatically results in the right
result, few customers are willing to pay for replacements being made, as long-term profitability of
professional maintenance and rely on family members the RESCO depends on minimizing life cycle costs and
or local handymen to maintain the PV systems. maximizing customer satisfaction. For both to occur,
RESCO : The RESCO must provide all maintenance so replacement components of the correct size and
professional maintenance is assured. The maintenance quality must be provided.
cost is kept low by the high customer density made · System abuse
possible by the low rental fee. Sales : The argument is often made that people will
· System design take better care of PV systems they own than those
Sales : System purchases by households are almost provided as rentals. Experience has not backed up this
always based on first cost considerations rather than argument. Users who are owners feel no responsibility
Chapter-19.qxd 11/8/03 11:30 AM Page 123

Special considerations 123


for solar utilities

to anyone outside their own household because it be cost-effectively covered by a single field-based
is their own system to use or abuse as desired. When technician for monthly visits to all serviced households.
there is no external agency to impose discipline, users A district must have at least as many households
have a strong tendency to push their systems beyond accepting service as are needed to pay for a locally
design limits for their immediate benefit even though based technician visit every month. In most developing
they have been well informed of the probable countries, where labour rates in rural areas are quite
long-term adverse effects. low, this is about 75 systems. No installations are made
Solution: There is an external owner who may remove in a district until this minimum number of customers
the system or increase fees when abuse is found. agrees to accept service. A single technician can
To maintain profitability, a RESCO must perform adequately maintain about 150 systems (if the district
preventive maintenance. This requires periodic visits is compact in size) and this would be the maximum size
by a company technician who can see at first hand of a district. Note that these figures are assuming
if a household is abusing the system. The customer monthly preventive maintenance visits as usually
can then be penalized through increased fees or needed in the early years of a PV rural electrification
disconnection of the system. project. The figures can be doubled for a mature
· Perceived risk programme where bimonthly visits are adequate.
Sales: The decision to purchase a system is a Maintenance visits more than two months apart are
significant one for most rural households, even those unlikely to provide adequate service to customers.
of relative wealth. Households often fail to make the · Service contract. The RESCO contracts with users to
major investment in PV systems because they fear provide them with a specified level of electrical service
that they will not work well or that the grid may soon and to keep the electricity supply in satisfactory repair,
be extended to their area. replacing all failed parts at no additional cost to the
RESCO: The cost of receiving the use of a system is user except for user-owned house wiring, lights and
a modest one-off connection fee and the monthly appliances. Users contract to pay an installation fee
rental fee. If the system does not work well or if a usually consistent with the cost of wiring their house
better electricity source becomes available, the and after installation they agree by signing the service
household can at any time stop paying for the system contract not to tamper with any of the RESCO-owned
and the RESCO will move the system to another equipment, to maintain the panel area free of shade, to
customer’s house. So there is little risk to the allow RESCO technicians free access to the system, to
customer in taking a system. pay the periodic fee on time and to use the system in
accordance with published RESCO guidelines. Should the
user not conform with the agreed terms, the system
RESCO structure can be disconnected or removed by the RESCO. Should
the RESCO not meet its obligations, the customer can
Based on project experience, a successful RESCO has the
stop paying fees and return the system.
following characteristics:
· Periodic service fee. This is based on the actual cost
· Ownership of all major components of the system of operation and maintenance that is the sum of the
by the RESCO. Panels, controllers, batteries and costs of battery replacement, replacing the controller
wiring up to the load connection point are owned and at the end of its useful life, capital repayment and the
maintained by the RESCO. Appliances and house wiring operating cost of the RESCO. Fee collection methods
after the load connection are usually owned and must be adapted to the income characteristics of
maintained by the householder. the customers.
· Locally based service structure. The RESCO services · Field technician supervision. A few times a year,
small rural electrification districts, each covered by a a senior technician from the home office visits each
locally resident technician who is a full-time employee district and audits the field technician’s performance.
of the utility. A district is defined as the area that can Additionally, the senior technician is available on call
Chapter-19.qxd 11/8/03 11:30 AM Page 124

124 Solar Photovoltaic


Project Development

to assist field technicians in troubleshooting and Integration into a conventional utility will usually require
repairs that are beyond the level of their training and setting up a subsidiary organization specifically for the
experience. solar installations.
· Customer feedback. It has been found to be
important that the RESCO should have some method
for user feedback on service quality and the Characteristics of a RESCO
performance of the field technician in each district.
A district users’ committee consisting of five to However RESCO structures are referred to — ‘fee for
seven people elected by the users in that district is service’, ‘PV system rental company’ or ‘solar
the approach successfully used in one project. Local utility’ — their primary characteristic is an emphasis on
government representatives fulfil this purpose with the provision of electrical services, not on the provision
good results in another project. It is the responsibility of PV systems. In general a RESCO:
of the feedback system to carry complaints and · never gives up ownership of the PV systems. The
requests from users to the RESCO management and to RESCO usually retains ownership of at least the
communicate RESCO matters, mainly reasons for fee primary PV components including the panel, the
and service changes, to the users. There is also the controller and the battery.
possibility of arbitration through the feedback system · charges a fee that includes all maintenance and
in the case of proposed disconnections owing to repair services. Users are not allowed to participate
customer failure to pay fees. in the installation, maintenance or repair of PV
A problem with the RESCO system is the systems. These are all carried out by professional
impersonality and relative remoteness of the technicians under the control of the RESCO.
organization. A feedback system helps the community · disconnects or removes systems following failure
to keep the RESCO in focus as a community service to pay fees. Customers are expected to pay a
provider through developing good relations between predetermined fee at a specified time. Failure to do so
the parties and a high level of user service and results in disconnection and ultimately removal of the
therefore high level of fees collected on time. An area systems.
of particular friction between RESCOs and users is that · bases system designs on life cycle costs, not first
of disconnections for non-payment of fees. In rural costs. The RESCO is responsible not only for the initial
areas, income is often sporadic and a local arbitration investment in the PV system but also for all its
arrangement to determine whether a request for delay maintenance and repair costs. Therefore the design of
of payment is appropriate or not is essential for good the system needs to minimize the long-term costs, not
community relations. just the initial cost of the PV system.
· A system for continuing training and retraining of
all technicians is provided by the RESCO for its
technical employees. A common problem with the Advantages of RESCO structure
implementation of PV projects is inadequate training
opportunities for technical personnel after the first For users, there are three main advantages of the
few years of the project. Successful solar utilities RESCO approach:
provide at least annual training for all technicians.
· It requires the least annual cost outlay by users.
It has also been found that the turnover of field
Rural households usually cannot afford to purchase a
technicians is relatively high as the training provided
PV system, even under time credit terms, because the
is often sufficient to allow a technician to find a good
cash outlay is too great. The RESCO approach spreads
job in the city.
the cost of the system over 10 or more years thus
Clearly this structure has much in common with that making the payments much more affordable.
of a conventional utility, though there are significant · The user does not have to worry about repairs or
differences arising from the distributed generation base. maintenance. Experience has shown that rural users of
Chapter-19.qxd 11/8/03 11:30 AM Page 125

Special considerations 125


for solar utilities

PV systems have neither the interest nor the technical · The maintenance system for the RESCO can also
knowledge to effectively maintain PV systems. In most support PV sales. A major problem with specializing in
cases, users have a greater tendency to damage the sale of PV systems is the fact that it is costly to
systems than to maintain them. The RESCO approach provide an after-sales support system. When a company
takes maintenance out of user hands and provides has a RESCO operation, it can use the maintenance
trained technicians whose sole responsibility is to keep capability that has been established for the RESCO to
the PV systems operating at optimal level. This also support the highly profitable sales of PV systems to
means that users do not have to worry about a large wealthy households, non-governmental organizations
unbudgeted cost should a major part fail. The fee and governments.
charged by the RESCO operator covers replacement of
batteries, controllers and panels.
· There is little risk to the user. People in rural areas Disadvantages of RESCO structure
are hesitant about purchasing PV systems even if they
have sufficient money. They are worried that the For the user, there are no significant disadvantages. For
systems will not work as claimed, or that the grid the RESCO, certain problems must be resolved:
will soon become available and their investment in a
· It takes more capital than a sales approach. As
PV system will be wasted. The RESCO approach allows
users are paying the system cost back over 10 years
customers to return the systems to the operator at
or more, the company must be prepared to finance
any time they are not happy with the way they work
the systems for a much longer period than if they
or if another, more convenient electricity source
were to be sold to users.
becomes available to them.
One way around this has been for government to
The advantages of the RESCO structure for a purchase the PV systems then to lease them to the
PV company are: RESCOs, often at a heavily subsidized rate. This
removes the need for a RESCO to finance the capital
· There can be a greatly increased customer density. investment.
The lower monthly cost of the RESCO systems allows · Short-term profits may be low. Due to the high
more households in a region to take PV systems. investment required, it takes longer to develop profits
This often is an increase of four or five times the than is the case with direct sales of PV systems. Over
customer density that can be achieved by the sale of the long term, however, profits tend to be substantially
PV systems. This increased customer density allows better than with sales.
the company to provide maintenance at a much lower · Management is more complicated. There are many
cost and may even allow a local office to be created more customer transactions to handle and a wider
that further helps the company to develop its range of activities to manage than in the sales
customer services and marketing. organization. Where sales typically turn over every few
· Income is predictable and for a long term. PV sales months, management must deal with a 10 year or
vary greatly from year to year because customers are longer horizon when budgeting for a RESCO.
transient and the market volatile. The RESCO operator · Profitability requires many systems to be
has a fixed customer base that provides a predictable installed. While a profit may be made on the sale
and steady income in the long term. of just a few systems, a RESCO needs hundreds of
· There are far fewer technical problems with the systems installed before profitability can be
PV systems. As the design, installation and achieved. This is because operating costs change
maintenance is all carried out by the RESCO, technical little from just a few systems to a thousand or more
problems tend to be much less than when users install installations. So the more systems installed, the
and care for systems themselves. Fewer technical lower the management cost per system. RESCOs
problems means better acceptance of the technology typically have their break-even point between 1,000
by users and a more receptive market. and 2,000 systems.
Chapter-20.qxd 11/8/03 11:31 AM Page 127

Solar utility management 20 C H A P T E R 20

Introduction Comparing sales and RESCO


approaches
Providing the same group of customers with long-term
service is quite a different management problem to There are major differences between the sales model and
selling merchandise to a constantly changing customer the RESCO model for a business. The hire-purchase
group. The ‘fee for service’ company must look to the model has some characteristics of both models as it
long term. Decisions made today can affect operations effectively acts as a RESCO during the hire phase but,
for years to come and should be based on sound when the customer has paid the total cost of the system,
information, carefully considering how the company the customer becomes the owner of the system and
operations will be affected over both the short and the the relationship between the company and the customer
long term. becomes more like the sales model.

Sales-based operations RESCO operations


Short-term contact with customers Based on continuing, low-level customer contact
Transfer of goods Provision of service
Maintenance responsibility limited Maintenance responsibility complete
Limited activity away from company base Most activity away from company base
Operational feedback based on limited-term Operational feedback based on life cycle
warranty repairs performance
Requirements are usually expressed once Requirements change over time and are expressed
at the point of sale through continuing interaction
Sales fluctuate a great deal due to external Sales are relatively stable and predictable
market forces; not very predictable
Service support is needed and is important to Sales opportunities exist but are a minor part of
continuing sales, but is a minor component operations, though they may represent significant
of income income
Chapter-20.qxd 11/8/03 11:31 AM Page 128

128 Solar Photovoltaic


Project Development

Technical and customer monitoring requirements for the system and discourage the use of
appliances that exceed the capability of the system.
For a service company to be profitable, the customer
must receive the service required but the company must Payment patterns
also respond to changes in customer needs. Also there Every household has a unique pattern of income and a
must be some way of tracking the operation of the unique approach to paying bills. The company goal should
installed systems to ensure that the components selected be to adjust the payment schedule to match income
are adequate and the maintenance processes are working patterns. The ‘one size fits all’ approach does not work
properly. for either system design or for customer payments.
Where records show a repeated pattern of problems with
payments, that household can be targeted for discussions
Customer monitoring
about alternative payment methods or a change in the
payment schedule. To arbitrarily set a payment schedule
Patterns of energy use
and rigidly enforce it may alienate customers when there
How people use the electricity from a PV system is
are alternatives that would be agreeable both to the
important to both the design and the maintenance of the
customer and the company.
system. Customer satisfaction depends on reliable
electrical service in the amount and at the time needed.
Monitoring of battery charge levels and repeated Technical monitoring
customer interviews provide information about changes in
use patterns that may affect system performance and Spare parts requirements
service reliability. Records of the nature of customer To provide acceptable service, spare parts must be readily
complaints and records of the charge level of customer available to the field technicians for repairs. These spare
batteries relative to that of other customers are parts must however be closely controlled to ensure that
important in discovering changing demand for electricity. they are not being used for purposes other than those
In a RESCO project, the discharge controller should be intended. Periodic inventories and tracking through a
considered as an emergency disconnection and the continuous record for each major component for its full
system design be such that the load is only automatically operational life are usually considered the minimum
disconnected no more than once or twice a year. More requirements in monitoring spare parts use.
frequent automatic disconnections imply either a problem
with the charging of the battery or a problem with Battery life
increased use beyond the design level. Therefore it is A crucial cost factor in maintenance is the working life
important to keep records of low-voltage disconnections of the system battery. Leaving batteries for extended
both to ensure that the system is checked for correct periods at partial charge levels causes sulphation, a major
operation and that the customer is not increasing the cause of decreased life in batteries. Sulphation can often
demand for electricity. be reversed if caught early enough.
It is usually cost-effective to record battery operating
Appliance requirements parameters frequently and to statistically compare each
The most common cause of changes in service battery with other batteries in the service area. A
requirements is the addition or removal of appliances. A battery that is consistently lower in charge level than the
change from a system that only provides lighting to the norm for the service area indicates either a technical or
inclusion of television in a household may make a great a user problem that must be addressed. Sulphation is
difference to the way the system is used and may require easily detected by a comparison of the battery voltage
a change in components to make the adjustment. It is (when not connected to the panel or a load) and the
important to keep a record of ‘authorized’ appliances hydrometer reading. If a battery voltage reading
and implement some system for tracking changes in indicates a significantly higher level of charge than
appliances. This can both help to predict usage and is indicated by a hydrometer reading, sulphation
Chapter-20.qxd 11/8/03 11:31 AM Page 129

Solar utility management 129

probably has occurred. If a controlled overcharging Life cycle cost, not first cost,
process (equalizing charge) is carried out within a few
weeks of detection of sulphation, it can often be
should determine design
reversed. But if left without equalization, the battery life
Most conventional approaches to household PV-system
will probably be reduced.
design are intended to provide barely adequate
performance in order to offer the minimum purchase
Maintenance frequency cost. This is a direct result of designs being optimized
Another crucial cost factor is the frequency of service for selling systems where the first cost is the major
visits. It is clearly true that depending on customers to factor in purchase decision-making. Systems intended for
request maintenance may result in decreased battery RESCO applications need a different design approach
life. By the time a PV system has degraded to the point because the company will have to live with those
where a customer is experiencing problems, the battery systems for their entire life cycle. Selling a controller
has probably been damaged and its life reduced. Wide that fails in three years may not be a detriment to
experience has shown the value of scheduled, preventive continuing sales, but installing a controller in a RESCO
maintenance but the optimal frequency depends on the system that fails every three years may seriously reduce
system design, the cost of battery replacements and the profits. A panel size that is the minimum to provide
cost of the maintenance visits. Service visits that are acceptable service will stress the battery much more
more frequent than necessary will increase labour and than one that is comfortably oversized. The extension
travel costs and may annoy the customer. Service of battery life and the improved customer relations
visits that are too far apart may worsen customer from a more reliable system may prove to be worth a
relations through the accumulation of minor problems significant increase in panel cost over the conventional
and may shorten the life of batteries if technical design value.
problems are caught later than optimum. Only through For selling systems, even on credit terms, first cost is
careful analysis of maintenance and customer payment critical. Also attractive packaging, minor but interesting
records can the optimum frequency be determined. extra features such as an array of indicator lights, spikes
RESCO operators commonly hire someone living in the to discourage birds from perching on panels and indicator
local service area to provide preventive maintenance caps for battery cells may attract customers away from
services. This is particularly important when the service the competition. For the RESCO operator, the first cost is
area is isolated and access difficult or seasonal. In most a factor but the cost of continuing operation and
developing countries, the cost of hiring a local technician maintenance is of greater concern. The design goal must
to make frequent preventive maintenance visits is be to achieve the optimal balance between first cost and
modest and much more cost-effective than attempting operation and maintenance cost. A system that is cheap
to provide maintenance services from a distant urban in first cost may have high maintenance requirements,
area. Minimal training is required, as the primary tasks of while a highly reliable system may have low maintenance
the local technician are to take battery measurements, costs but too high a first cost.
replace lost battery water and clean connections and
components. In most cases these operations will keep The battery is the most expensive
serious problems to a minimum and a senior technician part of a system
will rarely be needed to perform more complex service
procedures. The PV panel may last more than 20 years. During that
Most project experience has indicated in the first year time there will be many battery replacements. So, when
or two of operation that a preventive maintenance visit considered on a life cycle basis and bearing in mind the
every month is required for best system performance and recent cost reductions in panels, the battery is likely to be
customer satisfaction. When customers are familiar with the most costly component. One of the principal reasons
the systems, use patterns stabilized and systems for preventive maintenance visits is to extend the life of
optimized, a visit every two months is often adequate. the battery through direct maintenance of the battery and
Chapter-20.qxd 11/8/03 11:31 AM Page 130

130 Solar Photovoltaic


Project Development

indirectly through optimizing other components in the but not cause water levels to fall too far within one to
system — including the user. two months.

Controller affects battery life Panel size affects battery life


While field experience does not show much difference Power reliability — a factor closely linked to customer
between exotic, highly technical controllers and basic satisfaction that in turn is closely linked to the need
controllers that simply turn charging on and off relative for frequent customer visits and fee collection
to battery conditions, it is clear that the control problems — increases rapidly when panel capacity is
set-points, the conditions under which charge and increased 20% to 30% above the minimum usually
discharge are established, are a major factor in battery considered acceptable in PV design calculations. Also,
life and in system reliability. Controls that are unstable the average battery charge level is usually much higher
or are set incorrectly can seriously shorten battery life. simply because the battery will much more frequently
A failed controller can markedly shorten battery life if come to a full charge. Batteries that have a high average
not repaired quickly. High reliability and stability seem level of charge, particularly batteries that are regularly
more important design parameters than the provision brought to full charge conditions, have a significantly
of complex control algorithms that attempt to fine-tune longer useful life than batteries operated for long
control to battery type. periods under partial charge conditions. With the falling
In particular, the charge cut-off (high-voltage cost of panels, it is becoming increasingly cost-effective
disconnect or HVD) setting has a major effect on battery to add panel capacity with the aim of lowering
life. Most commercial charge controllers are set at a maintenance costs through fewer maintenance visits and
voltage that minimizes water loss from the battery. This increased battery life.
is a good idea for systems that depend on users to
maintain the battery water level as it has been found Installation quality affects battery life
that users are unlikely to check battery water levels very With low-voltage dc systems, connection quality and
often. Unfortunately, in order to keep water loss very losses in wiring have a strong effect on system reliability
low, the HVD has to be set at a level that stops the and battery life. Wires that are too small or too long,
battery becoming fully charged. Most commercial charge using poor-quality switches, using connection methods
controllers only allow the battery to come to 90% of that introduce voltage drops, panel location and
full charge, not 100%. When 10% of the battery is not orientation can all lower system efficiency and the
charged, the result is early sulphation and shortened average level of charge of the battery, which in turn
battery life. While it is true that the battery life would be increases maintenance costs and lowers customer
even shorter if the water level fell too low, the battery satisfaction.
life is much less than optimum. In a RESCO operation
where frequent preventive maintenance is included, a Use patterns affect battery life
higher controller HVD setting allows the battery to come The customer is one of the major components of the
to full charge and the maintenance personnel ensure that PV system and needs as much or even more attention
the water level does not fall below the minimum. In that than the battery, panel or other components. This is
case, the battery may last for years longer than it would particularly true in the early months after the installation
with a lower controller voltage setting. when user habits are formed and the level of satisfaction
For this reason, only controllers with adjustable with the system is also established by the customer. First
set-points should be used in a RESCO system and the impressions are often lasting. Frequent visits by RESCO
set-points adjusted to the highest value possible without staff to discuss problems and to provide user advice have
causing so much water loss that the maintenance proved very worthwhile in the long term. Attempting to
technician cannot keep it at the correct level on the cut costs by visiting new customers only on demand has
preventive maintenance schedule. In most cases, a 14.4 V not been shown to be cost-effective in the long term, as
to 14.6 V HVD setting will allow full charge in the battery early customer satisfaction is often low through lack of
Chapter-20.qxd 11/8/03 11:31 AM Page 131

Solar utility management 131

understanding about how to best use the PV system, and where a customer area has not been visited for an
resulting in abuse of the system and the formation of a extended period, a special service visit is probably
costly, long-term adversary relationship with the RESCO warranted.
operator.
Fee collection
Battery type affects battery life
In some circumstances, low-cost batteries that are One of the most controversial aspects of the RESCO
replaced often may be the least costly solution, while in operation is the approach to fee collection. Many
sites where access is costly and battery supply irregular, different approaches have been tried with varying levels
high-quality deep-discharge batteries that last a decade of success, and two important points have emerged from
may be the most cost-effective over the life of the all this experience: (1) the customer must consider the
system. Experience indicates that in most rural areas of method of fee collection to be reasonable and have
developing countries, a mid-range, mid-cost battery with minimal intrinsic annoyances; and (2) the method has to
a five- to seven-year practical life provides the best fit the conditions that exist. These conditions include
compromise. Low-cost, locally made vehicle batteries such factors as income patterns, cultural issues, the
that must be replaced every two years or so may presence of other collection systems in the service area,
indicate the lowest life cycle cost when mathematically the remoteness of the site, the distance between
analysed. However the RESCO operator must consider serviced households, the ability of the company to
the gradually lowering reliability of the system as the disconnect customers that do not pay and many other
battery approaches the end of its life. This increases factors specific to a service area.
the number of calls for maintenance and the associated It is clearly a mistake to attempt a collection process
service costs. With hundreds of households in a service that is mainly intended to fit the convenience and needs
area having a battery replacement cycle of only two of the company. Successful collection schemes always
years, the operator could face a never-ending reliability consider the needs of the customer as a priority at least
problem and end up with such a high volume of service as high as those of the company. It is simply not good
calls that additional technicians have to be hired, business to annoy customers on a persistent basis.
reversing the cost saving expected from the use of a
cheap battery. Choose a fee-collection process
that fits customer and site
Maintenance frequency affects battery life
The minimum frequency for maintenance of a PV system Visiting households solely to collect fees can be
is related to the frequency of the need to check battery expensive, but if combined with scheduled service visits it
water. Theoretically, in a system with a sealed battery, may in the end be the cheapest approach. Where local
no preventive maintenance is necessary. However technicians are in place and the cost of frequent visits to
experience shows that scheduled preventive maintenance customers low, technical visits on a monthly basis may be
visits, even with sealed battery systems, can dramatically cost-effective and collecting fees during those visits may
increase battery life. This relates to the control of user be the least-cost method that also results in the minimum
actions and prevention of user abuse, to the periodic customer annoyance. The main problem with this
cleaning and tightening of connections that have approach is controlling the funds collected by technicians
gradually increased their voltage losses, and to the and their tendency to extend credit beyond acceptable
control of shading on panels as nearby plants grow. As a limits, especially for friends and family.
general practice, when a technician is in a service area At the other extreme is a service area that is
for a demand service call, a short visit is warranted to all expensive to service on an individual household basis
nearby customers both as a show of customer service and and systems are designed to require little preventive
to clean and adjust the systems to optimal efficiency. maintenance. Using contracted fee-collection services
Customer records should include such unscheduled visits through the sale of prepayment tokens or cards at a local
Chapter-20.qxd 11/8/03 11:31 AM Page 132

132 Solar Photovoltaic


Project Development

store, or payment through a local public agency, may to pay US$0.60 a day for the use of two 8 W lights
prove the most cost-effective. for a total of US$18 per month. But in other projects
providing similar services to households it proved very
Determining the appropriate difficult to collect even US$6 each month for that service.
payment period Because the income pattern tended to be the receipt of
a small amount each day for producing copra or selling
Because of the payment habits deeply ingrained in urban vegetables in the market, making payments in the same
areas — whose residents usually design rural projects — the pattern worked much better than trying to force people
monthly payment scheme is almost universally considered to follow the unaccustomed pattern of saving money for
as the way to collect money. In principle, this is a monthly payments, even though the total payment per
reasonable length of time as it is short enough to avoid month was much less.
heavy losses if payment is not received on time yet long
enough to avoid too much cost in making the collections. Prepaid tokens or cards for a fixed payment period
In rural areas there are few monthly pay cheques, The use of prepaid tokens, codes or smart cards can be
however, so customers may do better making payments on used to collect fees. While technically interesting, care
very different time scales. Some Pacific islanders have been must be taken that the extra complexity will not
successfully offered a daily payment scheme through introduce hidden costs of lowered system reliability and
purchase of tokens at the local store to provide power for distance the company from its customers too much.
24 hours (thereby emulating their habit of purchasing Results have been mixed and clearly depend a great deal
kerosene daily for the lights at night), while in Africa on the particular system and how well it meets the
commercial farmers prefer to pay in advance every six payment needs of the customer as well as the company.
months to coincide with crop sales. Technical ‘solutions’ to social problems risk creating
different social problems that may offset any expected
Long payment periods are risky unless advantages. And there is always an additional technical
collected in advance risk when complex technology is operated in remote
Long periods between payments minimize the number of rural areas.
collections per year but also increase the risk of long Confusion sometimes arises between prepayment
periods before non-payment is recognized and may cards or tokens offered by electricity utilities for rural
increase the probability that a household will be unable customers and the prepayment systems for RESCO PV.
to meet the full payment at the assigned time. Where The prepayment system for the utility company is based
payment is being made for services already rendered, on kilowatt-hour use, so a high-usage customer will
three months probably represents the longest period that run out of money before a low-usage customer. The
is generally acceptable. However, where advance payment prepayment approaches for RESCO PV are so far all based
for services is possible, longer periods are certainly on time period rather than energy use. Thus when
acceptable so long as periodic visits are made to ensure purchasing a prepayment card for utility service the
that systems are not being abused and are continuing to customer is buying energy, when purchasing a
work properly. Semiannual and annual payments in prepayment card for RESCO PV service, the customer is
advance are attractive enough to allow companies to buying time of use. The social and use effects can be
offer a discount over what would be paid for shorter quite different and caution should be exercised in
collection terms or for post-payment instead of transferring the experience of prepayment card use by
prepayment. utilities to RESCOs.

Shorter periods (and smaller payments) can make Payment is made by users for reliable,
payment easier for some adequate service
In the Pacific Island project where a 24-hour token was Customer visits during the early months of service
purchased daily at the local store, households were eager provision is usually very cost-effective because it helps
Chapter-20.qxd 11/8/03 11:31 AM Page 133

Solar utility management 133

the customer to understand the constraints of the limited service visit is made and a collection attempt made. To
service being provided and to understand how to be most effective in collection of defaulting payments,
prioritize use to fit these constraints. While initial user the customer should be informed by the company
training is necessary, experience indicates that only after representative that a default has occurred and an
actually using the system for some time can the customer attempt to collect made within days of the time of
really understand what the training meant. actual default. As the reason for defaulting is sometimes
Correct system sizing is also vital to customer a malfunction of the system, rapid response may also
satisfaction. No matter how cheap, if the services that are lower the risk of battery damage caused by a failed
the customer’s high priority are not met, payments will be system sitting for months without charge.
considered excessive. While it is true that every customer One particular advantage of collection by local agents
would like to operate a colour television, multiple fans and visiting the customer is the fact that the company
a refrigerator, they are probably not very high priority for knows right away when a default occurs and a promise
a rural dweller in a developing country. Some services are, for future payment can be extracted on the spot. With
however, considered essential and if they are not provided secondary payment systems, such as through a
by the RESCO, payment will be made only with the government office, the company is somewhat at the
greatest reluctance. It is very important to the success of mercy of the efficiency of the collection agent. Care
the RESCO that each customer has a system sized to meet should therefore be taken in setting up a collection
the very essential services as perceived by the customer. system to ensure rapid notification of payment defaults.
For one customer being able to operate only lights is Accurate payment records are also an important factor
essential. Others may consider four hours of television the in keeping customers paying on time. Customer records
absolute minimum of acceptable service. Field experience should show prior payment history as this both highlights
has generally been that people are quite realistic about problem payers and allows extra leeway to customers
paying for services that they consider essential and will who have irregular incomes but always pay when money
pay a surprisingly large percentage of their available is received.
money to receive those services — but will baulk at paying
anything for less.
Establish a reasonable disconnection
policy and stick with it
Payment records must be timely
and accurate The threat of disconnection is not enough, actually
disconnecting customers after prior warning is absolutely
It is almost always easier to arrange to collect late essential. The main advantage of prepayment cards is
payments soon after a default than later. While the that immediate disconnection for non-payment is
actual payment may have to wait until a specific income assured. The corollary disadvantage is that it allows no
transaction is made by the customer, if the customer is leeway at all and indicates a certain lack of regard for the
not faced with the problem of non-payment soon after customer on the part of the company and may cause
the default occurs, their priorities may shift to other the customer to rationalize abuse of the system.
more pressing debts that are likely to be accumulating In most rural cultures, it is difficult if not impossible
simultaneously. So payment records have to be updated for a local agent to perform disconnections. In such
very soon, preferably within a few days, after the cases, company officials from outside the community
scheduled collection time. With the distance, both should perform disconnections to avoid putting the local
cultural and physical, between the company and the agent in a socially untenable position. If the RESCO is
customer it is easy for payment records to take weeks to well managed and customer needs are being met,
reach the point where a manager can note a payment disconnections will generally be rare and the cost
default. As frequently a default is not even recognized minimal. Any need for disconnection should however be
until at least one payment period, typically one month, investigated by a company official, as it may indicate
has elapsed it may be two to three months before a deeper problems that should be addressed.
Chapter-20.qxd 11/8/03 11:31 AM Page 134

134 Solar Photovoltaic


Project Development

In any case, it is vital to ensure that the customer is Detailed list of components installed
aware of the disconnection policy and sees evidence that
it is enforced. Without clear objective evidence that In order to ensure adequate maintenance and local
the policy is carried out on the terms presented, availability of spare parts, as well as facilitating the
collection rates can be expected to fall and the cost of recovery of stolen components, a detailed list should be
collection rise. Not disconnecting promptly when a made of the components installed on each house with
payment default occurs is a major cause of loss of their model numbers and identifying codes. Batteries
income by fee for service companies. may be permanently marked with identification codes
by carefully using a soldering iron or engraving tool to
Customer records write on the plastic case. Controllers and panels
usually have identification labels but may be more
The 80—20 rule permanently marked by inscribing identity marks on
metal components.
A general rule for service companies is that 80% of the Many RESCO contracts limit the appliances that can
problems are from 20% of the customers. Harsh action be attached to the system and may specify that different
against the ‘good’ 80% customers because of the or additional appliances may only be used with the
problems caused by the ‘bad’ 20% is unjustified, nor does permission of the RESCO provider. In that case a list of
it result in good customer relations. Identifying the authorized appliances with their identification should be
problem customers allows them to be treated differently included.
from the customers that rarely have problems. According The installed components will change over time
to the reasons for the problems, this can improve as old components fail and are replaced or as system
customer relations where the problems are external or modifications are made. Components removed from
can reduce losses where the customer is a poor risk. service should be deleted from the list and new
components and their identification details added along
Service contract with the date the exchange is made.

Because the RESCO is entering into a long-term Maintenance records


relationship with the customer, the terms of
that relationship must be clearly spelled out in a contract. As the maintenance requirements of system components
In the contract, the services to be provided by the RESCO form a vital part of the company knowledge base,
must be defined as well as the responsibility of the whenever any maintenance is carried out that affects any
customer to prevent damage to the system and pay the of the components, a detailed record should be kept. For
required fees. In particular, a specific person should be preventive maintenance, a checklist is useful as the tasks
identified by each household as personally responsible are specific and repetitive. When repairs are needed, a
for the payments and that person should be the description of the problem and the action taken to carry
signatory to the contract. Also the specific house that out the repair should be entered. Quality maintenance
has the installation must be clearly identified in the records can be an invaluable source of information for
contract. Many rural areas have ill-defined addresses and selecting more cost-effective components and creating
local people rely on the relationship of the site to other better maintenance procedures. But to be of value the
landmarks. While the traditional approach for locating the records must be (1) systematic in content so that they
house should be used, if a different approach is used by can be statistically analysed; (2) completed by the
government agencies to locate a rural house, that should technicians at the time maintenance is carried out; and
also be included in the contract. (3) actually used as data by the management.
The disconnection policy and any penalties for damage Whenever a technician visits a house for any reason,
to the system or non-payment should be clearly spelled the preventive maintenance checklist should be
out in the contract. followed. This will typically include checks of
Chapter-20.qxd 11/8/03 11:31 AM Page 135

Solar utility management 135

connections, shading, cleanliness, battery water and can be cost-effective. However collecting battery data
measurements of important system parameters such as and never using them is a waste of time and resources;
battery voltage. benefit will only result if there is a system for using the
Customers should be required to sign any maintenance data to diagnose problems and if action is taken on
activity records because it helps to prove that the the result.
technician did carry out the maintenance, to ensure that
the maintenance records are created on the spot and not
Payment records
filled out later, and because the customer must be clearly
aware that maintenance service was provided.
The recording system must be such that a payment
can be easily matched with the household making the
Battery records payment. While this sounds very basic, in practice
payments are often received based on a person’s name
Because the battery is such a critical part of the or some other subjective identification. Providing the
system and is relatively easy to damage, records of household with payment coupons that include a customer
battery maintenance are potentially very useful in number, a customer identification card that is to be
cost-effective maintenance. Where open-cell batteries are presented with payment or devising some other means
used, a record of the amount of water used per cell since of positively identifying the household for which the
the last filling is useful information, particularly if some payment is being made, can greatly reduce problems
cells use a lot more water than others. when disputes about payments occur. Receipts that
In those cases where a field technician provides have a company-specific stamp or other unique
periodic preventive maintenance services, measurement identification should be used and always provided when
of battery voltage and cell hydrometer measurements payments are received.
can be of considerable value. Hydrometer measurements The accounting system should provide rapid
are the most accurate measure of level of charge for notification to management of the ageing of accounts
each cell and significant differences between cells is a and customers with arrears should be clearly identified
good indicator of potential battery problems. If caught along with the length of time the payment is overdue.
early, inequalities in cell charge can be equalized through Typically this is in the form of a list of customers in
deliberate, controlled overcharging but, if allowed to arrears provided a few days after the due date for
continue for months, permanent damage often results. payments. Where a customer makes a partial payment
The level of charge in the battery compared with that of on an arrears account this should be noted to show that
other batteries in the service area at similar times can the customer is making some effort to bring the
also be a good indicator of potential problems. A battery account up to date.
that shows a consistently low level of charge when
compared with other batteries operating under similar Disconnect/reconnect records
conditions may be the result of undercharging due to
system component problems, or over-discharge that When a system is disconnected, the agent doing the
is typically caused by the user. In either case, if left disconnection should provide the household with a
uncorrected, sulphation damage may progress more notification that states when the disconnection was made,
rapidly than it should and earlier failure may result. If why, and what the customer has to do to reconnect.
the problem is identified through the maintenance Temporarily leaving the house vacant to work elsewhere
records, correction is possible and early failure or visit relatives in a distant town may lead to
prevented. disconnections as well as simple non-payment of the bill.
Correlation between battery voltage and hydrometer The conditions at the house at the time of disconnection
readings helps to indicate the presence of sulphation in must be noted, as a system left on a vacant house should
the battery. As in many cases sulphation can be halted be treated differently to one installed with a reasonable
or reversed if caught early, these battery diagnostics expectation of a reconnection.
Chapter-20.qxd 11/8/03 11:31 AM Page 136

136 Solar Photovoltaic


Project Development

Removal records cost is associated with them and because they are a good
target for thieves and for misapplication by company
In cases where a household has been vacated or clearly employees.
will not require a reconnection, the system must be Effective spare parts control includes estimating the
removed and made available for installation elsewhere. failure rate of each component installed in service-area
The specific reason for ceasing to use the system systems and having sufficient spares to ensure that, during
should be determined and the household record closed. the time between using a part and restocking that part
As removal is expensive and disruptive, analysis of the from outside sources, there will be enough additional
reason should be carried out in each instance and some spares to cover additional failures. This is relatively easy
thought given to how to avoid it in future. A special for small, high-turnover items such as light bulbs but is
‘removal’ logbook devoted to such problems can be difficult for expensive, long-lived items such as batteries
of value. where a long time in storage may reduce the service life of
A common reason for the removal of systems is the battery after it is installed. PV panels rarely fail, so
the perception by the household that a competing keeping a local stock of spares may not be justified
electrical service provider offers better value than the because the risk of theft or misallocation is probably much
RESCO. Connection to a private grid or the purchase greater than the risk of a panel failing.
of a generator commonly occur in some countries There is no simple rule of thumb for controlling spare
and, in such cases, it is important to understand the parts, as each service area has different characteristics of
exact reasons for the shift in electrical suppliers. While access and parts use. In general, the easier the area is
the reason may seem to be price, often there are other to access, the less important it is to keep large local
reasons of perceived value or level of service. If the stocks of spares. Also, small components that have
customer is switching to a personal generator or a indefinite storage life, such as lights, controllers, switches
private grid, it may be through frustration with the and dc/dc converters are better candidates for local
service the RESCO has been providing rather than the storage than components that have a limited storage life,
cost or the level of power. such as batteries. High-value components with a low
failure rate, such as panels or inverters, are probably
System modification records better stocked in a regional site than locally.
‘Shrinkage’ of spare parts stocks can be a major
Moving a system to another site for the same customer cost. Periodic inventories at each stocking point and the
is not common but does happen. A record of the move creation of a paper trail for each part placed in stock
inserted in all the customer records and accounts is helps to reduce this to a low level. Certainly locked,
important to ensure continuity of customer records and secure storage is an important part of control. Those
to avoid confusion when maintenance visits are scheduled who have access to spare parts stores should be made
or collection stops made. directly responsible for accountability, but inventories
should be checked by someone else and transfer or use
records submitted periodically for comparison with
Company records inventory records.
A common method for field personnel to gain control
Spare parts control of components for their own use or private sale is to
claim that a part has failed on a system and has been
Having the correct spare parts available for rapid repair replaced, when in fact there has been no failure. All
of systems is very important to customer relations and failed components should be returned to the company for
timely payment of fees. This does not happen without identification, repair or disposal. This not only helps to
the implementation of a system to keep spare parts prevent fraud but also allows the company technical
in the right place and in adequate quantity. Furthermore, personnel to try to determine the reason for failure with
spare parts should be carefully controlled as considerable the hope of future prevention.
Chapter-20.qxd 11/8/03 11:31 AM Page 137

Solar utility management 137

Computerized customer accounts immediately clear that an error has been made. Also
codes that are related to service areas will allow the
While many small utilities in developing countries try to computer to generate a list of defaulting customers
manage several thousand customer accounts manually, in a particular service area. As an example, suppose
with more than a few hundred customers computerized there are four customers in the list named Kumar with
accounts can be an advantage, not because of the speed two in service area 1, one in service area 2 and one in
of entry of information which is not really much of a time service area 4. A coding system to serve our purpose
saver, but because of increased accuracy and the ability would use the service area number, a hyphen, part
of the computer to provide account summaries almost of the head of household name, and a final number
instantly. if more than one entry in that service area has the same
Most packaged business accounting programs can name:
handle thousands of customer accounts with little problem
1-Kumar1
and allow the customer accounts to be integrated with
1-Kumar2
the regular business accounts. If a business accounting
2-Kumar
program is not being used already, make sure that
4-Kumar.
the program selected can automatically add the periodic
charges to each customer’s bill at the appropriate time In creating a new customer account, all accounting
and can easily provide a receivables ageing report showing programs show an error if a new account has the same
which customers have not paid on time and how long name as an old one, so there is no difficulty in ensuring
payments are overdue. that unique customer codes are assigned.
Customer codes are essential to identify which
customer account is being accessed, as names on different Technician tool control
accounts may be the same or payments may be made
under different names for the same account. So when Field technicians need the correct tools and test
establishing the RESCO customer accounts, it is essential to equipment to do their job properly. But such equipment is
assign a unique code to each customer. expensive. Because tools are often difficult to find in a
For the system to work well, when payments rural village, company tools tend to be borrowed and then
are made the collection agent must use the customer disappear or are broken. Tools may be permanently
code. The speed of the computer is lost if the person marked as belonging to the RESCO, even painted a bright
entering the data has to look up the customer code. identifying colour to help in recovering borrowed or stolen
But at the time of payment the name and address tools. That will not help where a tool is broken through
of the payer should also be noted, as a mistake in misuse, however. For successful tool control, the field
writing the customer code will leave the company with technician should be made directly responsible for keeping
no possible way of determining who actually made the the company tools together and in good condition. A
payment. periodic inventory of technicians’ tools should be made by
In setting up a customer code, thought should be a senior technician and some mechanism of paying for at
given to reducing the chance of data entry error. Just least part of the replacement cost of damaged tools and
using a number is very prone to error as it is easy full replacement cost for lost tools should be imposed. For
for a payment to be allocated to the wrong account, this to be successful, each tool issued must be identified
something that can be difficult to locate afterwards. and tracked in an inventory. If a lost tool has to be
A customer code that uses part of the name of the replaced, the technician must be made fully responsible
head of the household is often used, as it is easy to for the purchase of a replacement and the money
remember and much less likely to be entered in deducted over time from salary payments. If the
error in a way that will result in the wrong account technician is made to pay only part of the replacement
receiving the money. The computer will fail to match cost, he may be tempted to become a discount tool
the code with any in the accounts and it will be salesman to friends and neighbours. For damaged or
Chapter-20.qxd 11/8/03 11:31 AM Page 138

138 Solar Photovoltaic


Project Development

broken tools, some consideration should be given for age Operations management
and the nature of the damage, but there should be at
least a nominal fine for any breakage that is clearly the For management to function properly, timely and
fault of the technician. appropriate information must be available. Too much
Various approaches to tool management have been information can, however, cause as many problems as too
tried with varying degrees of success. The provision of a little. While company data must be readily accessible on
lockable tool box is essential, though bear in mind that demand, because most company activities are routine and
the technician will be carrying the tools from place to repetitive only exceptional matters should be addressed in
place and one huge, heavy tool box may not be as regularly presented reports. The term ‘management by
practical as several smaller ones. exception’ has been coined for this process, where a range
Much of the damage to tools (and equipment) is the of acceptable conditions is established, for example a
result of incorrect use. The use of screwdrivers as pry bars budget, and as long as the operations are within this
and wrenches as hammers should be firmly discouraged. A acceptable range, no specific management decisions are
tool control system should always include training in the needed. As soon as some company operation goes outside
correct use of each tool provided. While it may seem trivial these limits, for example if a service area technician
to have a training session in the use of simple hand tools, exceeds his travel budget for the month, then the problem
observations of actual use has clearly shown that it is is brought to the immediate attention of management.
needed. In addition to these exceptional problems, status
reports created from timely information are needed. For
a RESCO, some important periodic operational status
Travel and communications cost records
reports for management would be:
Control of travel and communications costs is a problem · ageing of accounts by service area
for RESCO field operations and good, detailed records · disconnection and reconnection report
are essential. Budgeted cost control is important. If a · spare parts usage by service area
budget is prepared that assigns a reasonable level · system installation and removal report
of expenses to these categories, staff can be rewarded · customer complaint report
or penalized according to whether the actual amount · service call records and maintenance report
expended is under or over the budgeted amount. · operational expenditure report (communications,
Preparing a budget must, however, be an interactive travel, spare parts, operations, labour, etc.).
process with the staff involved to allow them to
Typically, these reports would be presented in a periodic
explain in detail what they think is an appropriate
management meeting by the managers responsible for each
communications and travel budget and why. Without
area of operation. Each report should include not only the
their agreement to the budget, their cooperation in
data for the reporting period but also information about
containing expenses within the budgeted amount
trends over the past year or more. RESCO operations are
will be difficult to obtain.
usually not characterized by rapid, highly disruptive changes
but by slow processes of change that may develop into
Personnel training records problems so unobtrusively that by the time they are
recognized in current activities, correction may be much
Continuing training of technical and administrative staff more difficult than if the trend had been recognized earlier.
is a vital part of RESCO operations. Training is not a
one-off thing. Each staff position should have a Operational communications
long-term training programme associated with it and
each staff member should have a record showing what With operating staff
training processes have been completed, when they The RESCO operation with a large, geographically dispersed
occurred and an evaluation of performance. customer base must somehow develop a fast and reliable
Chapter-20.qxd 11/8/03 11:31 AM Page 139

Solar utility management 139

communications system that allows queries and operations medium for disseminating information about fee changes,
data to flow quickly and accurately from the field and service changes and other actions that affect the
instructions and data to flow equally well to the field. customer directly.
Neither the field staff nor the customers should be
isolated from management. Where communications are Operational travel
poor, local staff may have to effectively form a small
company of their own and establish their own operating Transport costs can be the largest component of
procedures as RESCO management is difficult to reach field operations when the service area covers a wide
when decisions are needed. While this may work, most geographical area. A balance should be reached between
often it does not. The efficient use of rural radio-phones, the cost of adding field staff to service a small area
telephones, faxes and computer data links should be versus the cost of transport for existing staff to service a
integrated into company operating procedures wherever larger area. In any case, every effort should be made to
possible. Control over their use must be maintained as rural increase the customer base within a given service area
communications are often expensive, but without frequent rather than increasing the customer base by extending
and open communications, control of field operations the service area. The higher the customer density in a
becomes tenuous and may result in large costs service area, the more efficiently field staff can work.
accumulating in other areas. Marketing efforts should be directed towards increasing
the percentage of households with systems installed
With customers within a service area.
Some direct communications link should be arranged so Transport provided by the company should be of a
that customers can access management without going type common to the area and meet the need with
through the local operations staff. Without this link, minimum capital and operational cost. Where a bicycle
complaints about the activities of operating staff will will work well, do not provide staff with motorcycles. Use
never reach management. Service complaints delivered commercial transport such as buses or local trucking firms
directly to ‘the top’ make the customer feel less helpless where practical. Cost overruns in the use of company
and dependent on the local technician who may not be transport are common and very difficult to control.
universally liked. Renting transport services may seem expensive on a
To facilitate direct customer to management per unit basis but it will usually be much easier to
communications, a users’ committee may be formed with control than company transport, it will remove the
the responsibility of reporting to management problems costly and time-consuming problem of transport
that are not being resolved by the local operating staff. maintenance, and in the end it may well be much
This link can work the other way as a communication cheaper than providing company transport.

Вам также может понравиться