Task... Task Name Duration Start End Predec... Compl...

Priority Resources Work Cost

1 Construction Project 91 days? 1/3/2019 5/9/2019 0% 500 6464 hrs $0.00 Construction Project
2 1. General Conditions 17 days 1/3/2019 1/25/2019 0% 500 488 hrs $0.00 General Conditions

3 1.1 Receive notice to proceed and sign contract 3 days 1/3/2019 1/7/2019 0% 500 G.C. General M... 24 hrs $0.00 Receive notice to proceed and sign contract G.C. General Management
4 1.2 Submit bond and insurance documents 2 days 1/8/2019 1/9/2019 3 0% 500 G.C. Project Ma... 32 hrs $0.00 Submit bond and insurance documents G.C. Project Management;G.C. General Management
5 1.3 Prepare and submit project schedule 2 days 1/10/2019 1/11/2019 4 0% 500 G.C. Project Ma... 32 hrs $0.00 Prepare and submit project schedule G.C. Project Management;G.C. Scheduler
6 1.4 Prepare and submit schedule of values 2 days 1/14/2019 1/15/2019 5 0% 500 G.C. General M... 32 hrs $0.00 Prepare and submit schedule of values G.C. General Management;G.C. Project Management
7 1.5 Obtain building permits 4 days 1/8/2019 1/11/2019 3 0% 500 G.C. Project Ma... 64 hrs $0.00 Obtain building permits G.C. Project Management;G.C. Procurement
8 1.6 Submit preliminary shop drawings 2 wks 1/14/2019 1/25/2019 7 0% 500 G.C. Project Ma... 160 hrs $0.00 Submit preliminary shop drawings G.C. Project Management;G.C. Procurement
9 1.7 Submit monthly requests for payment 1 day 1/8/2019 1/8/2019 3 0% 500 0 hrs $0.00 Submit monthly requests for payment
10 1.8 Site Grading and Utilities 10 days 1/3/2019 1/16/2019 0% 500 144 hrs $0.00 Site Grading and Utilities
11 1.8.1 Clear and grub site 3 days 1/3/2019 1/7/2019 0% 500 Site Grading Co... 24 hrs $0.00 Clear and grub site Site Grading Contractor
12 1.8.2 Install underground utilities 1 day 1/4/2019 1/4/2019 13 0% 500 0 hrs $0.00 Install underground utilities
13 1.8.3 Install temporary power service 1 day 1/3/2019 1/3/2019 0% 500 0 hrs $0.00 Install temporary power service
14 1.8.4 Install exterior fire line and building fire riser 2 wks 1/3/2019 1/16/2019 0% 500 Plumbing Contra...80 hrs $0.00 Install exterior fire line and building fire riser Plumbing Contractor
15 1.8.5 Erect building batter boards and layout building 1 wk 1/3/2019 1/9/2019 0% 500 G.C. Survey Cr... 40 hrs $0.00 Erect building batter boards and layout building G.C. Survey Crew
16 2. Foundations 45 days? 1/3/2019 3/6/2019 0% 500 768 hrs $0.00 Foundations
17 2.1 Excavate foundations 2 wks 1/10/2019 1/23/2019 15 0% 500 Site Grading Co... 80 hrs $0.00 Excavate foundations Site Grading Contractor
18 2.2 Excavate elevator pit 2 days 1/10/2019 1/11/2019 15 0% 500 Site Grading Co... 16 hrs $0.00 Excavate elevator pit Site Grading Contractor
19 2.3 Form column piers and spread foundations 4 days 1/24/2019 1/29/2019 17 0% 500 G.C. Rough Car... 32 hrs $0.00 Form column piers and spread foundations G.C. Rough Carpenter Crew
20 2.4 Rough-in electric and plumbing in elevator 4 days 1/14/2019 1/17/2019 18 0% 500 Plumbing Contra...64 hrs $0.00 Rough-in electric and plumbing in elevator Plumbing Contractor;Electric Contractor
21 2.5 Form elevator pit walls 4 days 1/18/2019 1/23/2019 20 0% 500 G.C. Rough Car... 32 hrs $0.00 Form elevator pit walls G.C. Rough Carpenter Crew
22 2.6 Pour column piers, foundations and walls 1 day? 1/3/2019 1/3/2019 0% 500 G.C. Concrete ... 8 hrs $0.00 Pour column piers, foundations and walls G.C. Concrete Crew
23 2.7 Cure 7 days 1/3/2019 1/11/2019 0% 500 G.C. Labor Crew 56 hrs $0.00 Cure G.C. Labor Crew
24 2.8 Strip forms 1 day 1/14/2019 1/14/2019 23 0% 500 G.C. Labor Crew 8 hrs $0.00 Strip forms G.C. Labor Crew
25 2.9 Install pneumatic tube in elevator pit 3 days 1/15/2019 1/17/2019 24 0% 500 Elevator Contra... 24 hrs $0.00 Install pneumatic tube in elevator pit Elevator Contractor
26 2.10 Prepare and pour concrete floor in elevator pit 1 day 1/18/2019 1/18/2019 25 0% 500 G.C. Concrete ... 8 hrs $0.00 Prepare and pour concrete floor in elevator pit G.C. Concrete Crew
27 2.11 Steel erection 45 days 1/3/2019 3/6/2019 0% 500 440 hrs $0.00 Steel erection
28 2.11.1 Erect steel columns, beams and joist - 1st and 2nd floors 2 wks 1/3/2019 1/16/2019 0% 500 Steel Erection C... 80 hrs $0.00 Erect steel columns, beams and joist - 1st and 2nd floors Steel Erection Contractor
29 2.11.2 Erect steel columns, beams and joist - 3rd floor and roof 2 wks 1/17/2019 1/30/2019 28 0% 500 Steel Erection C... 80 hrs $0.00 Erect steel columns, beams and joist - 3rd floor and roof Steel Erection Contractor
30 2.11.3 Install miscellaneous iron and bracing - 1st and 2nd floors 2 wks 1/17/2019 1/30/2019 28 0% 500 Steel Erection C... 80 hrs $0.00 Install miscellaneous iron and bracing - 1st and 2nd floors Steel Erection Contractor
31 2.11.4 Install miscellaneous iron and bracing - 3rd floor and roof 2 wks 1/31/2019 2/13/2019 29 0% 500 Steel Erection C... 80 hrs $0.00 Install miscellaneous iron and bracing - 3rd floor and roof Steel Erection Contractor
32 2.11.5 Install stairs and miscellaneous iron railing 2 wks 2/14/2019 2/27/2019 31 0% 500 Steel Erection C... 80 hrs $0.00 Install stairs and miscellaneous iron railing Steel Erection Contractor
33 2.11.6 Touch-up paint on steel 1 wk 2/28/2019 3/6/2019 32 0% 500 Steel Erection C... 40 hrs $0.00 Touch-up paint on steel Steel Erection Contractor
34 3. Form and Pour Concrete - Floors and Roof 16 days 1/3/2019 1/24/2019 0% 500 480 hrs $0.00 Form and Pour Concrete - Floors and Roof
35 3.1 Install rebar and in-floor utilities (including mechanical, electrical, plumbing)5 days 1/17/2019 1/23/2019 28 0% 500 G.C. Labor Cre... 120 hrs $0.00 Install rebar and in-floor utilities (including mechanical, electrical, plumbing) G.C. Labor Crew;Plumbing Contractor;Electric Contractor
36 3.2 Pour separate floors 4 days 1/3/2019 1/8/2019 0% 500 G.C. Concrete ... 32 hrs $0.00 Pour separate floors G.C. Concrete Crew
37 3.3 Cure separate floors 7 days 1/9/2019 1/17/2019 36 0% 500 G.C. Labor Crew 56 hrs $0.00 Cure separate floors G.C. Labor Crew
38 3.4 Strip forms 2 days 1/18/2019 1/21/2019 37 0% 500 G.C. Labor Crew 16 hrs $0.00 Strip forms G.C. Labor Crew
39 3.5 Form roof slab including all floor openings 5 days 1/18/2019 1/24/2019 37 0% 500 G.C. Rough Car... 80 hrs $0.00 Form roof slab including all floor openings G.C. Rough Carpenter Crew;G.C. Labor Crew
40 3.6 Install electrical underground 1 wk 1/3/2019 1/9/2019 0% 500 Electric Contrac... 40 hrs $0.00 Install electrical underground Electric Contractor
41 3.7 Install plumbing underground 1 wk 1/3/2019 1/9/2019 0% 500 Plumbing Contra...40 hrs $0.00 Install plumbing underground Plumbing Contractor
42 3.8 Install rebar and in-floor utilities 4 days 1/3/2019 1/8/2019 0% 500 G.C. Labor Cre... 96 hrs $0.00 Install rebar and in-floor utilities G.C. Labor Crew;Plumbing Contractor;Electric Contractor
43 4. Masonry Work 56 days 1/3/2019 3/21/2019 0% 500 824 hrs $0.00 Masonry Work
44 4.1 Rough-in plumbing at toilets and masonry walls 4 wks 1/3/2019 1/30/2019 0% 500 Plumbing Contra...160 hrs $0.00 Rough-in plumbing at toilets and masonry walls Plumbing Contractor
45 4.2 Lay masonry at core, mechanical, and toilets 4 wks 2/14/2019 3/13/2019 30;31 0% 500 Masonry Contra... 160 hrs $0.00 Lay masonry at core, mechanical, and toilets Masonry Contractor
46 4.3 Install exterior masonry work 5 wks 1/3/2019 2/6/2019 0% 500 Masonry Contra... 200 hrs $0.00 Install exterior masonry work Masonry Contractor
47 4.4 Install roof drains 2 days 2/7/2019 2/8/2019 46 0% 500 Roofing Contra... 16 hrs $0.00 Install roof drains Roofing Contractor
48 4.5 Install tile in toilet rooms 2 wks 1/31/2019 2/13/2019 44 0% 500 Tile Contractor 80 hrs $0.00 Install tile in toilet rooms Tile Contractor
49 4.6 Roofing 31 days 2/7/2019 3/21/2019 0% 500 208 hrs $0.00 Roofing
50 4.6.1 Install flashing at parapet walls 4 days 2/7/2019 2/12/2019 46 0% 500 Roofing Contra... 32 hrs $0.00 Install flashing at parapet walls Roofing Contractor
51 4.6.2 Pour lightweight concrete roof fill 2 days 2/13/2019 2/14/2019 47;50 0% 500 Roofing Contra... 16 hrs $0.00 Pour lightweight concrete roof fill Roofing Contractor
52 4.6.3 Install seamless roofing material 5 days 2/22/2019 2/28/2019 51FS+5... 0% 500 Roofing Contra... 40 hrs $0.00 Install seamless roofing material Roofing Contractor
53 4.6.4 Spread stone ballast on seamless roof 5 days 3/1/2019 3/7/2019 52 0% 500 Roofing Contra... 40 hrs $0.00 Spread stone ballast on seamless roof Roofing Contractor
54 4.6.5 Set rooftop equipment 2 wks 3/8/2019 3/21/2019 53 0% 500 HVAC Contractor 80 hrs $0.00 Set rooftop equipment HVAC Contractor
55 5. Building Finishes 55 days 1/3/2019 3/20/2019 0% 500 1200 hrs $0.00 Building Finishes
56 5.1 Install millwork and wood trim 3 wks 1/3/2019 1/23/2019 0% 500 G.C. Finish Car... 120 hrs $0.00 Install millwork and wood trim G.C. Finish Carpenter Crew
57 5.2 Paint walls and woodwork 4 wks 1/24/2019 2/20/2019 56 0% 500 Painting Contra... 160 hrs $0.00 Paint walls and woodwork Painting Contractor
58 5.3 Install conduit at ceiling plenum space 3 wks 1/3/2019 1/23/2019 0% 500 Electric Contrac... 120 hrs $0.00 Install conduit at ceiling plenum space Electric Contractor
59 5.4 Install duct in ceiling plenum space 3 wks 1/24/2019 2/13/2019 58 0% 500 HVAC Contractor 120 hrs $0.00 Install duct in ceiling plenum space HVAC Contractor
60 5.5 Install ceiling grid 2 wks 2/14/2019 2/27/2019 59 0% 500 Drywall Contra... 80 hrs $0.00 Install ceiling grid Drywall Contractor
61 5.6 Install ceiling tile 2 wks 2/28/2019 3/13/2019 60 0% 500 Drywall Contra... 80 hrs $0.00 Install ceiling tile Drywall Contractor
62 5.7 Hang wallpaper 2 wks 2/28/2019 3/13/2019 60 0% 500 Painting Contra... 80 hrs $0.00 Hang wallpaper Painting Contractor
63 5.8 Install building carpet 4 wks 2/21/2019 3/20/2019 57 0% 500 Carpet Contractor 160 hrs $0.00 Install building carpet Carpet Contractor
64 5.9 Install hardware and accessories 3 wks 2/21/2019 3/13/2019 57 0% 500 G.C. Finish Car... 120 hrs $0.00 Install hardware and accessories G.C. Finish Carpenter Crew
65 5.10 Complete interior and exterior sod and plantings 2 wks 2/21/2019 3/6/2019 57 0% 500 Landscape Con... 80 hrs $0.00 Complete interior and exterior sod and plantings Landscape Contractor
66 5.11 Pave, curb, and stripe parking lot 2 wks 3/7/2019 3/20/2019 65 0% 500 Paving Contractor 80 hrs $0.00 Pave, curb, and stripe parking lot Paving Contractor
67 6. Plumbing 45 days 1/3/2019 3/6/2019 0% 500 440 hrs $0.00 Plumbing
68 6.1 Rough-in plumbing in drywall walls 4 wks 1/3/2019 1/30/2019 0% 500 Plumbing Contra...160 hrs $0.00 Rough-in plumbing in drywall walls Plumbing Contractor
69 6.2 Tie-in fire line riser and set valves 2 wks 1/3/2019 1/16/2019 0% 500 Plumbing Contra...80 hrs $0.00 Tie-in fire line riser and set valves Plumbing Contractor
70 6.3 Set plumbing fixtures and trim 3 wks 1/31/2019 2/20/2019 68;44 0% 500 Plumbing Contra...120 hrs $0.00 Set plumbing fixtures and trim Plumbing Contractor
71 6.4 Flush, test, and clean piping and fixtures 2 wks 2/21/2019 3/6/2019 57;69;70 0% 500 Plumbing Contra...80 hrs $0.00 Flush, test, and clean piping and fixtures Plumbing Contractor
72 7. Electrical 91 days 1/3/2019 5/9/2019 0% 500 1360 hrs $0.00 Electrical
73 7.1 Rough-in electrical in masonry walls 4 wks 1/3/2019 1/30/2019 0% 500 Electric Contrac... 160 hrs $0.00 Rough-in electrical in masonry walls Electric Contractor
74 7.2 Rough-in electrical in drywall walls 4 wks 1/3/2019 1/30/2019 0% 500 Electric Contrac... 160 hrs $0.00 Rough-in electrical in drywall walls Electric Contractor
75 7.3 Pull wire in conduit and set area transformers 3 wks 1/31/2019 2/20/2019 73;58 0% 500 Electric Contrac... 120 hrs $0.00 Pull wire in conduit and set area transformers Electric Contractor
76 7.4 Install and terminate electrical devices 3 wks 2/21/2019 3/13/2019 75;74 0% 500 Electric Contrac... 120 hrs $0.00 Install and terminate electrical devices Electric Contractor
77 7.5 Make electrical terminations for HVAC equipment 35 days 3/22/2019 5/9/2019 75;54 0% 500 Electric Contr... 720 hrs $0.00 Make electrical terminations for HVAC equipment Electric Contractor
78 7.5.1 Heating and Ventilating - AC 20 days 3/22/2019 4/18/2019 0% 500 0 hrs $0.00 Heating and Ventilating - AC
79 7.5.2 Set equipment in mechanical room 2 wks 3/22/2019 4/4/2019 45 0% 500 HVAC Contractor 80 hrs $0.00 Set equipment in mechanical room HVAC Contractor
80 7.5.3 Rough-in mechanical in masonry walls 4 wks 3/22/2019 4/18/2019 0% 500 HVAC Contractor 160 hrs $0.00 Rough-in mechanical in masonry walls HVAC Contractor
81 7.5.4 Rough-in mechanical in drywall walls 2 wks 3/22/2019 4/4/2019 0% 500 HVAC Contractor 80 hrs $0.00 Rough-in mechanical in drywall walls HVAC Contractor
82 7.5.5 Install duct in building chase 3 wks 4/19/2019 5/9/2019 79;80 0% 500 HVAC Contractor 120 hrs $0.00 Install duct in building chase HVAC Contractor
83 7.6 Install light fixtures - test and clean 2 wks 3/14/2019 3/27/2019 60;76 0% 500 Electric Contrac... 80 hrs $0.00 Install light fixtures - test and clean Electric Contractor
84 8. Complete Final Inspections 80 days 1/3/2019 4/24/2019 0% 500 904 hrs $0.00 Complete Final Inspections
85 8.1 Complete elevator inspection and certification 3 days 4/3/2019 4/5/2019 92 0% 500 Elevator Contra... 24 hrs $0.00 Complete elevator inspection and certification Elevator Contractor
86 8.2 Perform architect's inspection 1 day 4/8/2019 4/8/2019 92;66;85 0% 500 G.C. Superinten... 16 hrs $0.00 Perform architect's inspection G.C. Superintendent;G.C. Project Management
87 8.3 Perform local building agency inspection 1 day 4/9/2019 4/9/2019 86 0% 500 G.C. Project Ma... 16 hrs $0.00 Perform local building agency inspection G.C. Project Management;G.C. Superintendent
88 8.4 Perform Fire Marshal's inspection 1 day 4/10/2019 4/10/2019 87 0% 500 G.C. Superinten... 16 hrs $0.00 Perform Fire Marshal's inspection G.C. Superintendent;G.C. Project Management
89 8.5 Final Clean-up and Occupancy 65 days 1/3/2019 4/3/2019 0% 500 112 hrs $0.00 Final Clean-up and Occupancy
90 8.5.1 Install hard tile flooring in common areas 1 wk 1/3/2019 1/9/2019 0% 500 Tile Contractor 40 hrs $0.00 Install hard tile flooring in common areas Tile Contractor
91 8.5.2 Clean hard tile floors 4 days 1/10/2019 1/15/2019 90 0% 500 Tile Contractor 32 hrs $0.00 Clean hard tile floors Tile Contractor
92 8.5.3 Remove debris from building and do final clean-up 4 days 3/28/2019 4/2/2019 63;62;6... 0% 500 G.C. Labor Crew 32 hrs $0.00 Remove debris from building and do final clean-up G.C. Labor Crew
93 8.5.4 Substantial completion date 1 day 4/3/2019 4/3/2019 92 0% 500 G.C. Superinten... 8 hrs $0.00 Substantial completion date G.C. Superintendent
94 8.6 Complete punch list items from all inspections 2 wks 4/11/2019 4/24/2019 88 0% 500 G.C. Superinten... 720 hrs $0.00 Complete punch list items from all inspections G.C. Superintendent;G.C. Labor Crew;Plumbing Contractor;Electric Contractor;HVAC Contractor;Drywall Contractor;Carpet Contractor;Paving Contractor;Painting Contractor