Sr. No.

Reception and Conference Room 11/10/2019


1.1 Reception Door Handle is loose. Sat/Sun
1.2 Grids in Reception ceiling are not aligned. Sat/Sun
1.3 Translucent film design and placement on Reception Glass Door/Partition. Done
1.4 Skirting levelling in Reception, Under the red Cabinet. Done
1.5 Reception table & Cable management, supply and installation. Will update by eod
Electrical Point for Fire Panel in the reception cabinet is missing, Fire system not working post occupancy,
1.6
building administration issued a warning for the same. Done
1.7 Magnetic Locks for the Red Cabinet in the reception area. Done
1.8 Floor separation plates in flooring transition for reception and Conference room. Done
Conference room glass partition translucent sheets pattern is not as per design- it is completely opaque. Sample
1.9
never approved by BDP. Please suggest alternate. Done
1.1 Conference Room Door Handle yet to be supplied and installed. Door frame to be re finished. Done
Done : White silicone matching lacqured
1.11 Silicon Glue filling and cleaning for the socket placed on lacquered glass in conference room. as discussed with girjesh to be done over
weekend.
1.12 Glass partition frame needs to be painted and finished, it has multiple scratches, and exposed surfaces. Done
1.13 Wall panelling with laminate over the storage in Conference room to match the laminate top edge is pending.
Done
1.14 Cove Light in Conference Room missing. Sat/Sun
1.15 Red Wall photo frame installation pending. Done
1.16 Cracks in Conference Room wall. Sat/Sun
2 Server Room 07/10/2019
2.1 Camera Lan Configuration pending. Done
2.2 Heat Alarm Installation Pending. Done
Sat/Sun Floor leveling as discuused with
2.3 Floor Hatch, Raceways Cover pending in server room, the floor needs to be finished.
grijesh.
3 Office Floor Area 07/10/2019
3.1 Laminate Change on the Switch panel Boxing in Red Pod Area Done
3.2 Ceiling, Partition Cracks in the Pod Area. Done
3.3 Polishing, Touching up Window sill, partition. Done
Done : table top to be changed matching
3.4 Storage dimensions not matching the drawing for PS1, to be updated. Top to match Site.
the wall profile.
3.5 Corner Table extension missing, for the seat next to the window Will update by eod
Done , fixing of table Is pending.
3.6 Discussion Area Table supply, Installation pending. Electrical points along with the table on
wall pending.
3.7 Cove damaged over the Storage/Shelf. Done
3.8 Cable Management for all Workstations: Discussed With Girijesh. Done
Printer Table Top to be made out of MDF, Particle board not taking the weight of the printer, please take the
3.9
proper dimension from site. Will update by eod
Done, There are Tiles broken and dirty,
3.1 Ceiling tiles replacement, damaged and dirty tiles.
Grijesh is told about these.
3.11 2 no’s Table top Damaged, not right size to be replaced. Will update by eod
3.12 Fasteners, Hooks for the pelmet for hanging planters missing. Sat/Sun
This is still a dispute, we have installed
3.13 Key Board Trays Missing the older ones since a few people needed
them urgently.
3.14 Floor not levelled in places, please review with us on site, raceway covers also pending in some places Sat/Sun
Open storage for desks along the windows need to be fixed, Box files not getting accommodated. Skirting needs
3.15
to be removed and more height to be given between shelves Will update by eod
Shelves in the long storage against the side wall are sagging because they are in particle board instead of MDF,
3.16
please check on site and replace the required ones Will update by eod
3.17 AC adjustment and checking the FCU with dripping water problem. Sat/Sun
Changing the mentioned shelves to Pre-laminated Board, instead of particle board since they aren’t taking up the
3.18
weight of stuff kept and sagging. Will update by eod
4 Pantry 07/10/2019
4.1 Wall tiles missing from sink side and coffee machine side- please install. Will update by eod
4.2 Plumbing Work, including alterations to avoid the seepage, repairing the Corridor wall as well. Sat/Sun
Done, Installation of fan due, Exposed
4.3 RO Shifting, Fan installation, Moving conduits from over the wall to inside the wall. conduite to be changed, grijesh Is
informed about this.
4.4 Skirting missing from Pantry and office floor Transition. Done
4.5 Tiles around Switch Boards in pantry Broken/ Cracked. Will update by eod
4.6 Magnet Closers in pantry Storage missing. Done
4.7 Painting of pantry shaft door and addition of magnet/ locking mechanism. Sat/Sun
4.8 Ventilation system for Pantry. Sat/Sun
5 New/ additional items 07/10/2019
5.4 Increasing the Number of lights in the gypsum Ceiling along the windows. Done
Additionally there is a skirting in the Corridor which has to be repaired, this hasn’t been actioned since a long
5.5
time and the building admin is behind us to get it done ASAP. Please look into this as well. Done
Electrical point on discussion table for light .
Deep Cleaning of the carpet flooring.
Pantry ceiling Tiles are still damaged
Confernce Room AC/Overall Air purification system.