PT.

SULINDO PUTRA TIMUR

MONITORING PROGRESS TUNNEL DIVERSION


OUTLET TUNNEL
PERIODE APRIL 2019

Realisasi
STA.
Tanggal Jarak Rib (m') Panjang Galian Sisa Galian
Siang Malam (m') (m') Siang Malam
1 0 0.7 0.7 594.6 1,549.60
2 0.7 0 0.7 593.9 1,548.90 1,548.90
3 0 0 0 593.9 1,548.90 1,548.90
4 0 0 0 593.9 1,548.90 1,548.90
5 0.7 0 0.7 593.2 1,548.20 1,548.20
6 0 0 0 593.2 1,548.20 1,548.20
7 0 0 0 593.2 1,548.20 1,548.20
8 0 0 0 593.2 1,548.20 1,548.20

9 0 0.5 592.7 1,548.20 1,547.70


0.5
10 0.5 0.5 1.0 591.7 1,547.20 1,546.70

0.5 0.5 1.0


11 590.7 1,546.20 1,545.70
12 0 0.5 0.5 590.2 1,545.70 1,545.20

13 0.5 0.5 1.0 589.2 1,544.70 1,544.20

14 0.5 0.5 1.0 588.2 1,543.70 1,543.20

15 0.6 0.7 1.3 586.9 1,542.60 1,541.90


16 0.7 0.7 1.4 585.5 1,541.20 1,540.50
17 0 0.7 0.7 584.8 1,540.50 1,539.80
18 0 0 0 584.8 1,539.80 1,539.80
19 0 0 0 584.8 1,539.80 1,539.80
20 0 0 0 584.8 1,539.80 1,539.80
21 0 0 0 584.8 1,539.80 1,539.80
22 0 0.7 0.7 584.1 1,539.80 1,539.10
23 0.7 0.7 1.4 582.7 1,538.40 1,537.70
24 0.5 0.5 1.0 581.7 1,537.20 1,536.70
25 0.5 0.5 1.0 580.7 1,536.20 1,535.70
26 0 0 0 580.7 1,535.70 1,535.70
27 0.5 0 0.5 580.2 1,535.20 1,535.20
28 0 1.4 1.4 578.8 1,535.20 1,533.80
29 0.7 0.7 1.4 577.4 1,533.10 1,532.40

30 1 0 1.0 576.4 1,531.40 1,531.40


Panjang galian s/d saat ini 18.90 m'
Rata-rata galian per hari 0.63 m'/hr (2 shieft)
Target s/d saat ini 100.80 m' *) Target excavation April 2019 = 100.8 mtr, 28 days eff
Deviasi dari rencana -81.90 m'
Panjang total galian s/d saat ini 93.95 m' *) Awal outlet STA. 1+625,35
VERSION

Keterangan

Lahan belum free


Lahan belum free
Lahan belum free
Grouting injection
Grouting injection
Menunggu umur grouting
Menunggu umur grouting

Lahan belum free


Lahan belum free
Lahan belum free
Lahan belum free
Lahan belum free

Instal girder, jml. Rib


Concrete slab girder 1
Overshieft, (install 2 st.rib@0.7m) 2
2
Collapse 1
6

on April 2019 = 100.8 mtr, 28 days effective

A. 1+625,35

262.8 14,500,000.00 3,810,600,000.00


18.9 14,500,000.00 274,050,000.00
4,084,650,000.00
54,150,404,741.52
7.54%

576.4 595.30
PT. SULINDO PUTRA TIMUR

MONITORING PROGRESS TUNNEL DIVERSION


OUTLET TUNNEL
PERIODE MEI 2019

Realisasi
STA.
Tanggal Jarak Rib (m') Panjang Galian Sisa Galian
Siang Malam (m') (m') Siang Malam
1 0 0 0 576.4 1,531.40
2 1 1 2 574.4 1,530.40 1,529.40
3 1 0 1 573.4 1,528.40 1,528.40
4 0 1 1 572.4 1,528.40 1,527.40
5 1 1 2 570.4 1,526.40 1,525.40
6 1.2 1.2 2.4 568.0 1,524.20 1,523.00
7 1.2 1.2 2.4 565.6 1,521.80 1,520.60
8 1.2 1.2 2.4 563.2 1,519.40 1,518.20

9 1 0 1 562.2 1,517.20 1,517.20

10 0 1.2 1.2 561.0 1,517.20 1,516.00

11 0 0 0 561.0 1,516.00 1,516.00

12 0 0 0 561.0 1,516.00 1,516.00

13 0 0 0 561.0 1,516.00 1,516.00

14 1.2 1.2 2.4 558.6 1,514.80 1,513.60

15 1.2 1.2 2.4 556.2 1,512.40 1,511.20

16 1.2 0 1.2 555.0 1,510.00 1,510.00

17 0 1.2 1.2 553.8 1,510.00 1,508.80


18 1.2 1.2 2.4 551.4 1,507.60 1,506.40
19 0 0 0 551.4 1,506.40 1,506.40
20 0 0 0 551.4 1,506.40 1,506.40

21 0 0 0 551.4 1,506.40 1,506.40

22 0 0.8 0.8 550.6 1,506.40 1,505.60


23 0.7 0.8 1.5 549.1 1,504.90 1,504.10
24 0.8 0.8 1.6 547.5 1,503.30 1,502.50
25 1.1 1.1 2.2 545.3 1,501.40 1,500.30
26 0 0.9 0.9 544.4 1,500.30 1,499.40
27 0.8 0.9 1.7 542.7 1,498.60 1,497.70
28 0 0.7 0.7 542.0 1,497.70 1,497.00
29 0.8 0.8 1.6 540.4 1,496.20 1,495.40
30 1 1 1 3.0 537.4 1,494.40 1,492.40
31 1 0.9 0.9 2.8 534.6 1,491.40 1,489.60

Panjang galian s/d saat ini 41.80 m'


Rata-rata galian per hari 1.35 m'/hr (2 shieft)
Target s/d saat ini 44.11 m' *) Target excavation Mei 2019 = 65 mtr, 28 days ef
Deviasi dari rencana -2.31 m'
Realisasi Pjg galian s/d saat ini 135.75 m' *) STA. Awal Outlet : 1+625,35
RSION

Mei 2019
No Item Pekerjaan
Keterangan 19 20 21 22 23 24
1 Persiapan

Libur (STA. Awal Mei 1+531,4) 2 Savety shotcrete


1 3 Backfill untuk counterweight

Collapse wall sisi kanan, deform rib 1 4 Perkuatan steel rib

Penanganan Collapse 1 5 Shotcrete permukaan counteweight


1 6 Install Steel Pipe 2" For Grouting

2 7 Injection Grouting & Standby Umur Grouting


2 8 Lanjut Excavation
2
Terdapat boulder massive, diperlukan
blasting 1
Shotcrete savety, drilling, blasting 1
Shotcrete row, drilling hole + blasting (ada
boulder massive)
Overshieft, mucking

STA. after blasting 1+514,2, & 2nd


blasting pukul 02.30 dini hari, STA. face
1+512,76)
Install steel rib STA.1+514,8 dan
STA.1+513,6. Kondisi geologi kembali ke
poor rock 2 ###
STA. face 1+511.83, ada aliran air
dengan debit cukup besar mengalir
melalui face, perlu sub drain 2 ###
STA. face 1+509.36, sigunit
1 ###
Pasang pipa dewatering outside portal 1
2
Colapse Pkl.15.35 (STA. 1+505,40)
Penanganan Collapse, grouting
Shotcrete additional pada rongga,
STA.1+517,2
1
2
2
2
1
2 0.8 0.9
1 0.7
2 0.8 0.8
3 1 1 1
3 1 0.9 0.9
39

n Mei 2019 = 65 mtr, 28 days effective

: 1+625,35
9
25

ur Grouting
PT. SULINDO PUTRA TIMUR

MONITORING PROGRESS TUNNEL DIVERSION


OUTLET TUNNEL
PERIODE JUNI 2019

Realisasi
STA.
Tanggal Jarak Rib (m') Pjg. Galian Sisa Galian
Siang Malam (m') (m') Siang Malam
1 0.8 0 0 0 0.8 532.8 1,488.80 1,488.80

2 0 0 0 0 0 532.8 1,488.80 1,488.80


3 0 0 0 0 0 532.8 1,488.80 1,488.80
4 0 0 0 0 0 532.8 1,488.80 1,488.80
5 0 0 0 0 0 532.8 1,488.80 1,488.80
6 0 0 0 0 0 532.8 1,488.80 1,488.80
7 0 0 0 0 0 532.8 1,488.80 1,488.80
8 0 0 0 0 0 532.8 1,488.80 1,488.80
9 0 0 0 0 0 532.8 1,488.80 1,488.80
10 0 0 0.8 0 0.8 532.0 1,488.80 1,488.00
11 0.8 0 0.8 1.0 2.6 529.4 1,487.20 1,485.40
12 1 0 1 1.2 3.2 526.2 1,484.40 1,482.20
13 1 0 1 1.1 3.1 523.1 1,481.20 1,479.10
14 1 0 1 1 3.0 520.1 1,478.10 1,476.10
15 1 1 1.1 1.1 4.2 515.9 1,474.10 1,471.90
16 1 1 0 2.0 513.9 1,469.90 1,469.90
17 1 1.1 1.1 0.9 4.1 509.8 1,467.80 1,465.80
18 1 1 1 1 4.0 505.8 1,463.80 1,461.80
19 1 0.9 0 0 1.9 503.9 1,459.90 1,459.90
20 0.8 0.9 0.9 0.8 3.4 500.5 1,458.20 1,456.50

21 0.8 0.8 0.8 0.8 3.2 497.3 1,454.90 1,453.30

22 0.8 0.8 0.8 0 2.4 494.9 1,451.70 1,450.90

23 0 0 1.1 2.1 3.2 491.7 1,450.90 1,447.70


24 0 1 1 2 4 487.7 1,446.70 1,443.70
25 0.8 1 0.9 0.9 3.6 484.1 1,441.90 1,440.10
26 0 1.1 2.1 1 4.2 479.9 1,439.00 1,435.90

27 3.3 476.6 1,433.60 1,432.60


1.2 1.1 0 1
28 1 0 1 1 3 473.6 1,431.60 1,429.60

29 3 470.6 1,428.60 1,426.60


1 0 1 1
30 0 1 1 1 3 467.6 1,425.60 1,423.60
Panjang galian s/d saat ini 66.00 m'
Rata-rata galian per hari 3.10 m'/hr (2 shieft) Start Evaluasi 10 Jun s/d 30 Jun 2019
Target s/d saat ini 62.00 m' *) Target excavation Juni 2019 = 62 mtr, 28 days effect
Deviasi dari rencana 4.00 m' *) STA. Awal Outlet : 1+625,35
Realisasi Pjg galian s/d saat ini 201.65 m'
Estimate Breaktrough 27-Nop-2019 Tercepat 15-Des-19
VERSION

Mei 2019
No Item Pekerjaan
Keterangan 19 20 21 22 23 24
1 Persiapan

Shieft Malam Savety Shotcrete 1 2 Savety shotcrete

Cleaning Peralatan, Pers. Cuti Idul Fitri 3 Backfill untuk counterweight

Cuti Idul Fitri 1440 H 4 Perkuatan steel rib

Cuti Idul Fitri 1440 H 5 Shotcrete permukaan counteweight

Cuti Idul Fitri 1440 H 6 Install Steel Pipe 2" For Grouting

Cuti Idul Fitri 1440 H 7 Injection Grouting & Standby Umur Grouting

Cuti Idul Fitri 1440 H 8 Lanjut Excavation

Persiapan Alat Kerja


Persiapan Alat Kerja
1
3
3
3
3 ###
4 ###
3 ###
4
4
Collapse Pkl. 02.30 (Dinihari), Shotcrete
Mucking, Shotcrete, Install Rib
Kondisi Geologi : RMR 20, sisi kiri adanya
pengisian slit pada rongga joint

Collapse PKL. 10.49, Safety Shotcrete,


Kondisi Geologi masih rawan longsor
OS, Install 3 Steel Rib, 1-1-1,1
Intall 4 stell Rib @1,0 m

Install 4 Stell RIB, (1,1)-(1,1)-(1,0)-(1,0)


Batuan Arc lepas, menunggu kondisi geologi
aman, Savety Shotcrete

kondisi geologi unsave (runtuh), Safety


shotcrete
komdisi batuan runtuh-runtuh area circle.
29 74

un s/d 30 Jun 2019


n Juni 2019 = 62 mtr, 28 days effective 2.3214
: 1+625,35

Paling Lambat
9
25

ur Grouting
PT. SULINDO PUTRA TIMUR

MONITORING PROGRESS TUNNEL DIVERSION


OUTLET TUNNEL
PERIODE JULI 2019

Realisasi
STA.
Tanggal Jarak Rib (m') Pjg. Galian Sisa Galian
Siang Malam (m') (m') Siang Malam
1 1.1 0 0 1 2.1 465.5 1,422.50 1,421.50

2 1 0 1 0 2 463.5 1,420.50 1,419.50

3 1 0 0 0 1 462.5 1,418.50 1,418.50


4 1.2 0 1 0 2.2 460.3 1,417.30 1,416.30
5 1.2 0 1.1 0 2.3 458 1,415.10 1,414.00
6 1.1 0 1.5 0 2.6 455.4 1,412.90 1,411.40

7 0 0 0 0 0 455.4 1,411.40 1,411.40

8 1.5 1.3 1.5 0 4.3 451.1 1,408.60 1,407.10


9 1.5 0 1.6 0 3.1 448.0 1,405.60 1,404.00
10 1.5 0 1.3 0 2.8 445.2 1,402.50 1,401.20
11 1.3 0 1 0.0 2.3 442.9 1,399.90 1,398.90
12 1 1.1 1 0 3.1 439.8 1,396.80 1,395.80
13 1 1.1 1 0 3.1 436.7 1,393.70 1,392.70
14 1 1.1 1 0 3.1 433.6 1,390.60 1,389.60
15 1 1.1 1.1 1.1 4.3 429.3 1,387.50 1,385.30
16 1.1 1.2 1 1 4.3 425.0 1,383.00 1,381.00

17 0 425.0 1,381.00 1,381.00


0 0 0 0

18 4.5 420.5 1,378.10 1,376.50


1.5 1.4 1.6 0

19 1.5 1.2 1.2 1 4.9 415.6 1,373.80 1,371.60

20 0 0 2 1.4 3.4 412.2 1,371.60 1,368.20

21 0 0 1.5 0 1.5 410.7 1,368.20 1,366.70

22 1.5 0 1.5 0 3 407.7 1,365.20 1,363.70

23 0 0 1.5 0 1.5 406.2 1,363.70 1,362.20

24 1.5 1.2 1.3 1.3 5.3 400.9 1,359.50 1,356.90


25 0 0 1.6 0 1.6 399.3 1,356.90 1,355.30
26 1.5 0 1.4 0 2.9 396.4 1,353.80 1,352.40

27 2.6 393.8 1,352.40 1,349.80


0 0 1.2 1.4
28 0 1.6 1.1 1.1 3.8 390.0 1,348.20 1,346.00

29 0 1.5 1.2 1.1 3.8 386.2 1,344.50 1,342.20

30 0 1.3 1 1.1 3.4 382.8 1,340.90 1,338.80


31 1.5 0 1.3 1 3.8 379.0 1,337.30 1,335.00

Panjang galian s/d saat ini 88.60 m' *) Progres per tanggal 7/7 = 22.4 m', Minus 12 m'
Rata-rata galian per hari 2.86 m'/hr (2 shieft) Start Evaluasi 1 Jul s/d 31 Jul 2019
Target s/d bulan ini 100.00 m' *) Target excavation Juli 2019 = 100 mtr, 31 days effective
Deviasi dari rencana -11.40 m' *) STA. Awal Outlet : 1+625,35
Realisasi Pjg galian s/d saat ini 286.45 m'
Estimate Breaktrough 27-Nop-2019 Tercepat 15-Des-19
SION

Keterangan

STA awal 1+423.60


Breaker Face Kondisi geologi Batu keras
Memperbaiki Nozel Selang dan ban Loader
Bocor

Bleasting 14 hole jam 23.35 wib (sisi kiri)


Overshift/ breaker bottom terdapat batuan
masif, driling for Blasting
Shift Siang Bleasting 15 hole jam 14.37

Kondisi Geologi batuan masif, driling for


blasting

Blasting pkl. 06.00 23 hole (sisi sprin line to


bottom
Batuan massive jenis metabatu pasir, RMR
29 (Fair Rock)
Batuan massive jenis metabatu pasir, RMR
29 ; pada bottom very hard ;rib ke-2 install
pkl.05.00

Overshit ; Install Steel Rib pkl.04.30

Wheel Loader pecah house, aliva rusak

Shift siang terkandala ban loader pecah

Shift Siang Safety Shotcrete 6 steel rib

Shift siang excavation batuan keras


7 = 22.4 m', Minus 12 m'
1 Jul 2019
2019 = 100 mtr, 31 days effective
25,35

Paling Lambat
PT. SULINDO PUTRA TIMUR

MONITORING PROGRESS TUNNEL DIVERSION


OUTLET TUNNEL
PERIODE JULI 2019

Realisasi
STA.
Tanggal Jarak Rib (m') Pjg. Galian Sisa Galian Keterangan
Siang Malam (m') (m') Siang Malam
1 0 0 1.2 1.2 2.4 465.2 1,335.00 1,332.60 STA awal 1+335.00
Operator exca shift day sedang
sakit/berobat, operator penggantinya
2 0 0 1.3 1.2 2.5 462.7 1,332.60 1,330.10 kesulitan saat breaker

3 1.1 1 1.4 0 3.5 459.2 1,328.00 1,326.60


4 0 0 0 1.5 0 459.2 1,326.60 1,325.10 Overshift/Shift malam pasang 1 Steel Rib
Pek.Drilling Angkur Rockbolt D22 and
5 0 0 0 0 0 459.2 1,325.10 1,325.10 welding Angkur to Steel Rib Adit Tunnel
6 1.2 0 0 0 1.2 458.0 1,323.90 1,323.90 Instal Steel Rib Turn Adit (1.2 dan 1.5 m)

Continue breaker turn adit and install Steel


7 0 0 0 0 0 458.0 1,323.90 1,323.90 Support. Shift malam continue breaker face
and breaker bottom turn adit.

Continue breaker turn adit + install pipa +


safety shotcrete/ Sfiht malam breaker face,
safety shotcrete turn adit not mucking
8 0 0 0 0 0 458.0 1,323.90 1,323.90 because Rubber Pucking leak.
9 0 0 1.3 1.5 1.3 456.7 1,323.90 1,321.10
10 1.5 0 1.2 1.5 2.7 454.0 1,319.60 1,316.90
11 0 0 0 0.0 0 454.0 1,316.90 1,316.90 Libur Hari Raya Idul Adha
12 0 1.2 0 1.2 2.4 451.6 1,315.70 1,314.50
13 0 0 0 0 0 451.6 1,314.50 1,314.50
14 0 0 0 0 0.0 451.6 1,314.50 1,314.50
15 0 0 0 0 0 451.6 1,314.50 1,314.50
16 0 0 0 0 0.0 451.6 1,314.50 1,314.50
17 0 0 0 0 0 451.6 1,314.50 1,314.50
18 0 0 0 0 0.0 451.6 1,314.50 1,314.50

19 0 0 0 0 0 451.6 1,314.50 1,314.50

20 0 0 0 0 0 451.6 1,314.50 1,314.50


21 0 0 0 0 0 451.6 1,314.50 1,314.50

22 0 0 0 0 0 451.6 1,314.50 1,314.50

23 0 0 0 0 0 451.6 1,314.50 1,314.50

24 0 0 0 0 0 451.6 1,314.50 1,314.50


25 0 0 0 0 0 451.6 1,314.50 1,314.50
26 0 0 0 0 0 451.6 1,314.50 1,314.50

27 0 451.6 1,314.50 1,314.50


0 0 0 0
28 0 0 0 0 0 451.6 1,314.50 1,314.50

29 0 0 0 0 0 451.6 1,314.50 1,314.50

30 0 0 0 0 0 451.6 1,314.50 1,314.50


31 0 0 0.0 0 0 451.6 1,314.50 1,314.50

*Progres dari invoice terakhir tanggal 30 Juli s/d 12 Agustus=23.2 m'


Panjang galian s/d saat ini 16.00 m'

Rata-rata galian per hari 0.67 m'/hr (2 shieft) Start Evaluasi 31 Juli /d 31 Agustus 2019
Target s/d bulan ini 100.00 m' *) Target excavation Agustus 2019 = 100 mtr, 31 days effective
Deviasi dari rencana -84.00 m' *) STA. Awal Outlet : 1+625,35
Realisasi Pjg galian s/d saat ini 310.75 m'
Estimate Breaktrough 27-Nop-2019 Tercepat 15-Des-19 Paling Lambat
PT. SULINDO PUTRA TIMUR
PROYEK PLTM LAU GUNUNG 2X5 MW

PROGRES INLET TUNNEL


PEK. PEMASANGAN FORM WORK
PERIODE 01 AGUSTUS - 15 AGUSTUS

STA Volume Jlh. Man Power


Tanggal Shif Keterangan
Start Finish Pek. (m) MN TK H
D
1
N
D
2
N
D
3
N
D
4
N
D
5
N
D
6
N
D
7
N
D
8
N
D
9
N
D
10
N
D
11
N
D
12
N
D
13
N
D
14
N
D
15
N
PT. SULINDO PUTRA TIMUR
PROYEK PLTM LAU GUNUNG 2x5 MW KAB. DAIRI, SUMATERA UTARA

MONITORING PROGRESS TUNNEL DIVERSION


INLET TUNNEL
ACTION PLAN PERIODE JULI 2019

PERIODE (MINGGU KE - 1 S/D MINGGU KE-2) Realisasi Target Deviasi


Tanggal
1 2 3 4 5 6 7 8 9 10 11 12 13 14 s/d mggu ini s/d mggu ini s/d mgg ini
Shieft D N D N D N D N D N D N D N D N D N D N D N D N D N D N (m') (m') (m')
Lean Concrete & Pipe Drain
STA.
Install Besi
STA.
Concrete Invert
STA.
Concrete Wall
STA.
Shotcrete Layer-2
STA.
Keterangan :

PERIODE (MINGGU KE - 3 S/ MINGGU KE-4) Realisasi Target Deviasi


Tanggal
15 16 17 18 19 20 21 22 23 24 25 26 27 28 s/d mggu ini s/d mggu ini s/d mgg ini
Shieft D N D N D N D N D N D N D N D N D N D N D N D N D N D N (m') (m') (m')
Lean Concrete & Pipe Drain
STA.
Install Besi
STA.
Concrete Invert
STA.
Concrete Wall
STA.
Shotcrete Layer-2
STA.

PERIODE (WEEK 3rd ~ 4th WEEK) Realisasi Target Deviasi


Tanggal
29 30 31 s/d mggu ini s/d mggu ini s/d mgg ini
Shieft D N D N D N (m') (m') (m')
Lean Concrete & Pipe Drain
STA.
Install Besi
STA.
Concrete Invert
STA.
Concrete Wall
STA.
Shotcrete Layer-2
STA.
1

target per hr target 2 w


150 5 75

120 4 81

120 7

180

200 7
PT. SULINDO PUTRA TIMUR
PROYEK PLTM LAU GUNUNG 2x5 MW KAB. DAIRI, SUMATERA UTARA

MONITORING PROGRESS TUNNEL DIVERSION


INLET TUNNEL
PERIODE MEI 2019

PERIODE (1st WEEK ~ 2nd WEEK) Realisasi Target Deviasi


Tanggal
1 2 3 4 5 6 7 8 9 10 11 12 13 14 s/d mggu ini s/d mggu ini s/d mgg ini
Shieft D N D N D N D N D N D N D N D N D N D N D N D N D N D N (m') (m') (m')
Lean Concrete & Pipe Drain
65 75.0 (10.0)
STA. 905 ~ 865 865 ~ 840
Install Besi
12 38.57 (26.6)
STA. 893 ~ 881
Concrete Invert
11 63.5 (52.5)
STA. 895 ~ 884
Concrete Wall
1
0 0 0.0
STA.
Shotcrete Layer-2
75 100 (25.0)
STA. 905 ~ 830
Keterangan : = Joint inspection & Install Pipe Drain → 08 Mei 2019 ~ rakor Medan SPT-IME-TGP
= Joint inspection top level invert → 13 Mei 2019 ~ rakor Jakarta SPT-IME-TGP

PERIODE (3rd WEEK ~ 4th WEEK) Realisasi Target Deviasi


Tanggal
15 16 17 18 19 20 21 22 23 24 25 12 27 28 s/d mggu ini s/d mggu ini s/d mgg ini
Shieft D N D N D N D N D N D N D N D N D N D N D N D N D N D N (m') (m') (m')
Lean Concrete & Pipe Drain
100 101.8 (1.8)
STA. 840~820 820~805
Install Besi
36 60.0 (24.0)
STA. 907~893 881 ~ 869
Concrete Invert
36 98.8 (62.8)
STA. 907~895 884 ~ 871
Concrete Wall
0 0 0.0
STA. 2 3
Shotcrete Layer-2
114 135.7 (21.7)
STA. 830 ~ 810 810 ~ 791

PERIODE (WEEK 3rd ~ 4th WEEK) Realisasi Target Deviasi


Tanggal
29 30 31 s/d mggu ini s/d mggu ini s/d mgg ini
Shieft D N D N D N (m') (m') (m')
Lean Concrete & Pipe Drain
150.0
STA.
Install Besi
120.0
STA.
Concrete Invert
120.0
STA.
Concrete Wall
0.0
STA.
Shotcrete Layer-2
200.0
STA.
target per hr target 2 w
150 5 75

120 4 81

120 7

180

200 7

15
PT. SULINDO PUTRA TIMUR
PROYEK PLTM LAU GUNUNG 2x5 MW KAB. DAIRI, SUMATERA UTARA

MONITORING PROGRESS TUNNEL DIVERSION


INLET TUNNEL
ACTION PLAN PERIODE JUNI 2019

PERIODE (MINGGU KE - 1 S/D MINGGU KE-2) Realisasi Target Deviasi


Tanggal
1 2 3 4 5 6 7 8 9 10 11 12 13 14 s/d mggu ini s/d mggu ini s/d mgg ini
Shieft D N D N D N D N D N D N D N D N D N D N D N D N D N D N (m') (m') (m')
Lean Concrete & Pipe Drain
STA.
Install Besi
STA.
Concrete Invert
STA.
Concrete Wall
STA.
Shotcrete Layer-2
STA.
Keterangan :

PERIODE (MINGGU KE - 3 S/ MINGGU KE-4) Realisasi Target Deviasi


Tanggal
15 16 17 18 19 20 21 22 23 24 25 26 27 28 s/d mggu ini s/d mggu ini s/d mgg ini
Shieft D N D N D N D N D N D N D N D N D N D N D N D N D N D N (m') (m') (m')
Lean Concrete & Pipe Drain
STA.
Install Besi
STA.
Concrete Invert
STA.
Concrete Wall
STA.
Shotcrete Layer-2
STA.

PERIODE (WEEK 3rd ~ 4th WEEK) Realisasi Target Deviasi


Tanggal
29 30 s/d mggu ini s/d mggu ini s/d mgg ini
Shieft D N D N (m') (m') (m')
Lean Concrete & Pipe Drain
STA.
Install Besi
STA.
Concrete Invert
STA.
Concrete Wall
STA.
Shotcrete Layer-2
STA.
1

target per hr target 2 w


150 5 75

120 4 81

120 7

180

200 7
Mei 2019
No Item Pekerjaan
19 20 21 22 23
1 Persiapan

2 Savety shotcrete

3 Backfill untuk counterweight

4 Perkuatan steel rib

5 Shotcrete permukaan counteweight

6 Install Steel Pipe 2" For Grouting

7 Injection Grouting & Standby Umur Grouting

8 Lanjut Excavation
019
24 25