Detailed Engineering of Air Seperation Unit - SATORP

Detailed Engineering of Air Seperation Unit - SATORP


100.00%

90.00%

80.00%

70.00%

60.00%

50.00%

40.00%

30.00%

20.00%

10.00%

0.00%
9-De c-17 16-De c-17 23-De c-17 30-Dec-17 6-Jan-18 13-Jan-18 20-Jan-18 27-Jan-18 3-Feb-18 10-Fe b-18 17-Feb-18 24-Feb-18 3-Ma r-18 10-Ma r-18 17-Mar-18 24-Mar-18 31-Mar-18 7-Apr-18 14-Apr-18 21-Apr-18 28-Apr-18 5-May-18 12-May-18 19-May-18

Cum Pl anned Progres s (Bas eline) % Cum Actua l Progres s Cum Pla nned Progre s s (Rev-1)%

As per Baseline Schedule FEED Verification 60% Design Stage & Submittal (28th Jan 18) 90% Design Stage & Submittal (19th Mar 18) 90% Design Review IFC Submittal (24th Apr 18)
As per Schedule (Rev-1) FEED Verification 60% Design Stage & Submittal (20th Feb 18) 90% Design Stage & Submittal (11th April 18) 90% Design Review IFC Submittal (17th May 18)
Week No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Week Ending 9-Dec-17 16-Dec-17 23-Dec-17 30-Dec-17 6-Jan-18 13-Jan-18 20-Jan-18 27-Jan-18 3-Feb-18 10-Feb-18 17-Feb-18 24-Feb-18 3-Mar-18 10-Mar-18 17-Mar-18 24-Mar-18 31-Mar-18 7-Apr-18 14-Apr-18 21-Apr-18 28-Apr-18 5-May-18 12-May-18 19-May-18
Planned Progress % (As per Baseline) 0.50% 1.00% 3.00% 4.00% 4.00% 6.00% 6.00% 8.00% 4.00% 4.00% 6.00% 7.00% 9.00% 9.00% 8.00% 6.00% 5.00% 3.00% 3.00% 2.00% 1.50%
Cumm Planned Progress (Baseline) % 0.50% 1.50% 4.50% 8.50% 12.50% 18.50% 24.50% 32.50% 36.50% 40.50% 46.50% 53.50% 62.50% 71.50% 79.50% 85.50% 90.50% 93.50% 96.50% 98.50% 100.00%
Planned Progress % (As per Rev-1) 5.30% 4.70% 6.00% 6.00% 6.00% 4.00% 4.00% 4.00% 5.50% 6.00% 8.00% 8.00% 6.00% 6.00% 6.00% 4.00% 4.00% 3.00% 2.00% 1.50%
Cumm Planned Progress (Rev-1) % 5.30% 10.00% 16.00% 22.00% 28.00% 32.00% 36.00% 40.00% 45.50% 51.50% 59.50% 67.50% 73.50% 79.50% 85.50% 89.50% 93.50% 96.50% 98.50% 100.00%
Actual Progress % 0.70% 0.80% 0.70% 1.30% 1.80%
Cumm Actual Progress % 0.70% 1.50% 2.20% 3.50% 5.30%