Manpower Rates (1 day = 8-10 manhours)

Item Gang / Crew Unit Daily Rate


Sub-Structure
Excavation (sand or clay) Loader + 2 Trucks + Drivers m3 500-600
Excavation (rock) Dozer + Excavator (Jack hammer) m3 100-150
Scrap disposal Loader + Trucks m3 -
Plain Concrete
Isolated Carpenter + Assist. m3 5
Raft 4 Carpenter + 4 Assist. m3 50
Reinf. Concrete
Isolated Carpenter + Assist. m3 2
Steel fixer - footing m3 6
Steel fixer - tie beam m3 1
Steel fixer - average m3 3.5
Raft Steel fixer m3 15
Waterproofing
Painting Bitumen Skilled Labor m2 40
hl. membrane Skilled Labor m2 65
vl. membrane Skilled Labor m2 36
fiber board Skilled Labor m2 200
block protection mason + assistant m2 14
Solidblock to backfill ‫ﻗﺼﺔ ردم‬ mason + assistant ‫ﻋﻤﺎﻟﺔ ﺗﺸﻮﻳﻦ وﻋﺠﺎن ﻟﻠﻤﻮﻧﺔ‬ m3 3-4
Backfill & Compaction 2 Loader + Plate compactor + 10 labors m3 200
Super-Structure
R.C. Columns/Walls
form work Carpenter + Assist. ‫ ﻓﻚ‬، ‫ ﺗﻘﻔﻴﻞ‬، ‫ ﺗﺠﻠﻴﺪ‬، ‫ﺗﺨﺸﻴﺐ‬ m3 1
steel fixing Steel fixer + Assist. m3 1
Slab on Grade (one layer mesh) 4 Steel fixer + 1 Carpenter (15cm thick.) m2 300
Concreting (Pouning/Casting) Pump+Truck mixers+Vibrator+4 labors m3 200
R.C. Slab
form work Carpenter + Assist. ‫ ﺗﻘﻮﻳﺔ‬، ‫ ﺗﻄﺒﻴﻖ‬، ‫ﻗﻴﻌﺎن‬+‫ ﺗﻌﺮﻳﻖ‬، ‫ﺗﺨﺸﻴﺐ‬ m2 8
steel fixing Steel fixer + Assist. m2 25
Finishing
Block Work
1000 block = 2.25 m3 mason + assistant (25cm thick.) m3 4
1000 block = 16.0 m2 mason + assistant (12cm thick.) m2 14
Plaster
mortar ‫اﻟﺒﻴﺎض ﻗﺒﻞ اﻷرﺿﻴﺎت‬ plasterer + assistant m2 25-30
Artificial rock ‫ﺣﺠﺮ ﺻﻨﺎﻋﻲ‬ plasterer + assistant ‫ﺑﻄﺎﻧﺔ وﺿﻬﺎرة ودق‬ m2 8-10
Rock ‫ﺣﺠﺮ ﻣﻴﻜﺎ أو هﺎﺷﻤﻪ‬ plasterer + assistant m2 20
Gypsum Cornice plasterer + assistant m.l. 15
Ceramic tiles mason + assistants m2 25-35
Parquet flooring m2
Marble or Granite (pieces 0.8x1m) (‫ ﻣﻴﻜﺎﻧﻴﻜﻲ )ﺷﺎﺳﻴﻪ ﺣﺪﻳﺪ وﺗﺮﺑﻴﻂ ﺑﺪون ﻣﻮﻧﺔ‬- (‫ﺳﻘﺎﻳﺔ ﻣﻮﻧﺔ‬+‫ﺟﺒﺲ‬+‫آﺎﻧﺎت‬+‫ﻳﺪوي )وزن‬
vl. Fixing mason + 2 assistants m2 20
hl. Fixing mason + 2 assistants m2 40
Clay tiles ‫ﻗﺮﻣﻴﺪ‬
on concrete or ‫ﺗﺴﻠﻴﺦ ﻣﻮﻧﺔ ﻋﻠﻰ ﺳﻠﻚ ﺷﺒﻚ‬ mason + assistants m2 40
steel structure ‫وﺧﺸﺐ‬ labors for prepration m2 8
Painting painter ‫دهﺎن‬2+‫ﺑﻄﺎﻧﺔ‬+‫ﺗﻠﻘﻴﻂ‬1+‫ﻣﻌﺠﻮن وﺻﻨﻔﺮة‬2+‫وﺟﻪ ﺑﺮاﻳﻤﺮ‬ m2 6
Staircase /Sills - marble mason for 1.5m width stair 10
Roof
heat insulation Skilled Labor + assistant m2 400
foam concrete-screed 8cm Skilled Labor m2 100
Finishing sequence
dry area + conduits&boxes ‫ ﺧﺮاﻃﻴﻢ وﻋﻠﺐ‬+subframes ‫ ﺣﻠﻮق‬+1st stage ‫ ﻃﺮﻃﺸﺔ وﺑﺆج‬+ ‫ﻣﺒﺎﻧﻲ‬
painting layers ‫ دهﺎﻧﺎت‬+ ‫ أرﺿﻴﺎت‬+ wiring ‫ ﺳﻠﻚ‬+ ‫أﺑﻮاب وﺷﺒﺎﺑﻴﻚ‬+ 2nd stage ‫ﺑﻴﺎض‬
final coat ‫ دهﺎن وﺟﻪ أﺧﻴﺮ‬+ electical fixtures ‫وﺷﻮش آﻬﺮﺑﺎء‬
wet area ‫ﺣﻮاﺋﻂ ﺳﻴﺮاﻣﻴﻚ‬+ ‫ ﺑﻴﺎض اﻟﺴﻘﻒ‬+ plumbing ‫ ﺳﺒﺎآﺔ وﺻﺤﻲ‬+ ‫ ﻋﺰل‬+ ‫ﻣﺒﺎﻧﻲ‬
sanitary ware ‫ اﻷﺟﻬﺰة اﻟﺼﺤﻴﺔ‬+ ‫ دهﺎن اﻟﺴﻘﻒ‬+ ‫أرﺿﻴﺎت ﺳﻴﺮاﻣﻴﻚ‬