Вы находитесь на странице: 1из 3

CRONOGRAMA DE DESEMBOLSOS

Obra MEJORAMIENTO DEL C.V. SAN ISIDRO - PUERTO SAN ANTONIO - HUALLHUAPAMPA Departamento HUANCAVELICA
DISTRITO DE TINTAYPUNCU, PROV. TAYACAJA, HUANCAVELICA Provincia TAYACAJA
Distritos TINTAYPUNCU
Fecha 24/11/2019
Nº PARTIDA UND METRADO PRECIO PARCIAL 1º MES 2º MES 3º MES
UNITARIO % AVANCE MONTO % AVANCE MONTO % AVANCE MONTO
01.00 OBRAS PRELIMINARES
01.01 CARTEL DE OBRA 2.40x4.80 m UND 2.00 1,586.61 3,173.22 100.00% 3,173.22
01.02 CAMPAMENTO PROVISIONAL DE OBRA M2 200.00 27.77 5,554.00 100.00% 5,554.00
01.03 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 43784.93 43,784.93 50.00% 21,892.47 50.00% 21,892.47
01.04 TRAZO,NIVELACION Y REPLANTEO KM 15.66 497.88 7,796.80 100.00% 7,796.80
01.05 TRAZO Y NIVELACION DE OBRAS DE ARTE M2 833.65 10.77 8,978.41 100.00% 8,978.41
01.06 DESBROCE Y LIMPIEZA HA 8.02 978.42 7,846.93 100.00% 7,846.93
01.07 FLETE TERRESTRE LIMA SAN ISIDRO GLB 1.00 41352.12 41,352.12 100.00% 41,352.12
02.00 MOVIMIENTO DE TIERRAS
02.01 CORTE EN MATERIAL SUELTO M3 10,611.80 4.07 43,190.03 75.00% 32,392.52 25.00% 10,797.51
02.02 CORTE EN ROCA SUELTA M3 2,425.15 15.10 36,619.77 100.00% 36,619.77
02.03 CORTE EN ROCA FIJA M3 2275.15 27.29 62,088.84 100.00% 62,088.84
02.04 RELLENO CON MATERIAL PROPIO M3 3713.73 8.01 29,746.98 100.00% 29,746.98
03.00 PAVIMENTOS
03.01 PERFILADO Y COMPACTADO EN ZONAS DE CORTE M2 57,550.50 1.36 78,268.68 100.00% 78,268.68
03.02 AFIRMADO M3 7,193.81 19.76 142,149.69 50.00% 71,074.85 50.00% 71,074.85
04.00 OBRAS DE ARTE Y DRENAJE
04.01 CUNETAS
04.01.01 CONFORMACION Y PERFILADO DE CUNETAS M 15,830.00 1.31 20,737.30 100.00% 20,737.30
04.02 ALCANTARILLAS DE CONCRETO
04.02.01 EXCAVACION MANUAL PARA ESTRUCTURAS M3 1,326.60 47.34 62,801.24 25.00% 15,700.31 75.00% 47,100.93
04.02.02 RELLENO DE ESTRUCTURAS M3 420.06 68.94 28,958.94 100.00% 28,958.94
04.02.03 NIVELACION Y COMPACTADO CON MATERIAL GRANULAR E= M2 325.95 8.45 2,754.28 75.00% 2,065.71 25.00% 688.57
04.02.04 CONCRETO CICLOPEO FC=175kg/cm2+30% PIEDRA GRAND M3 36.94 353.77 13,068.26 100.00% 13,068.26
04.02.05 CONCRETO F´c= 175 KG/CM2 M3 65.66 480.98 31,581.15 75.00% 23,685.86 25.00% 7,895.29
04.02.06 CONCRETO FC=210KG/CM2 M3 50.89 503.42 25,619.04 75.00% 19,214.28 25.00% 6,404.76
04.02.07 ENCOFRADO Y DESENCOFRADO M2 942.00 43.72 41,184.24 100.00% 41,184.24
04.02.08 ACERO FY = 4200 KG/CM2 KG 5,985.69 3.76 22,506.19 15.00% 3,375.93 85.00% 19,130.26
04.02.09 REVESTIMIENTO CON PIEDRA EMBOQUILLADA C/A 1:4 M3 77.94 253.00 19,718.82 15.00% 2,957.82 85.00% 16,761.00
04.03 BADENES
CRONOGRAMA DE DESEMBOLSOS
Obra MEJORAMIENTO DEL C.V. SAN ISIDRO - PUERTO SAN ANTONIO - HUALLHUAPAMPA Departamento HUANCAVELICA
DISTRITO DE TINTAYPUNCU, PROV. TAYACAJA, HUANCAVELICA Provincia TAYACAJA
Distritos TINTAYPUNCU
Fecha 24/11/2019
Nº PARTIDA UND METRADO PRECIO PARCIAL 1º MES 2º MES 3º MES
UNITARIO % AVANCE MONTO % AVANCE MONTO % AVANCE MONTO
04.03.01 LOSA DE BADEN DE MAMPOSTERIA DE PIEDRA E=0.30m M2 229.50 131.17 30,103.52 25.00% 7,525.88 75.00% 22,577.64
04.03.02 UÑAS DE BADEN SE MAMPOSTERIA DE PIEDRA M 139.00 121.88 16,941.32 25.00% 4,235.33 75.00% 12,705.99
04.03.03 EMBOQUILLADO DE PIEDRA E=0.20m M2 118.50 109.31 12,953.24 25.00% 3,238.31 75.00% 9,714.93
04.04 MUROS
04.04.01 EXCAVACION MANUAL PARA ESTRUCTURAS M3 700.67 47.34 33,169.72 15.00% 4,975.46 85.00% 28,194.26
04.04.02 RELLENO CON MATERIAL PROPIO M3 497.64 16.19 8,056.79 15.00% 1,208.52 85.00% 6,848.27
04.04.03 CONCRETO CICLOPEO FC=175kg/cm2+30% PIEDRA GRAND M3 364.15 353.77 128,825.35 15.00% 19,323.80 85.00% 109,501.55
04.04.04 TUBO DE DESAGUE PERFORADO DE 8" M 60.00 87.92 5,275.20 100.00% 5,275.20
04.05 PONTONES
04.05.01 EXCAVACION MANUAL PARA ESTRUCTURAS M3 47.12 47.34 2,230.66 85.00% 1,896.06 15.00% 334.60
04.05.02 RELLENO CON MATERIAL DE PRESTAMO M3 849.20 9.77 8,296.68 85.00% 7,052.18 15.00% 1,244.50
04.05.03 ENCAUSAMIENTO DE CURSOS DE AGUA RENDIMIENTO=300 M3 216.00 10.79 2,330.64 85.00% 1,981.04 15.00% 349.60
04.05.04 CONCRETO CICLOPEO FC=175kg/cm2+30% PIEDRA GRAND M3 113.01 353.77 39,979.55 85.00% 33,982.62 15.00% 5,996.93
04.05.05 CONCRETO FC=210 KG/CM2 PARA LOSAS MACIZAS M3 24.12 484.22 11,679.39 85.00% 9,927.48 15.00% 1,751.91
04.05.06 CONCRETO FC= 210 KG/CM2 PARA VIGAS M3 11.72 484.22 5,675.06 85.00% 4,823.80 15.00% 851.26
04.05.07 ENCOFRADO Y DESENCOFRADO DE ESTRIBOS. M2 348.87 43.72 15,252.60 85.00% 12,964.71 15.00% 2,287.89
04.05.08 ENCOFRADO Y DESENCOFRADO DE VIGAS M2 44.64 60.01 2,678.85 85.00% 2,277.02 15.00% 401.83
04.05.09 ENCOFRADO Y DESENCOFRADO DE LOSAS. M2 13.61 65.41 890.23 85.00% 756.70 15.00% 133.53
04.05.10 ACERO FY = 4200 KG/CM2 KG 2,640.21 3.76 9,927.19 85.00% 8,438.11 15.00% 1,489.08
04.05.11 JUNTAS DE DILATACION METALICA UND 4.00 163.64 654.56 100.00% 654.56
04.05.12 APOYO FIJO UND 2.00 465.41 930.82 100.00% 930.82
04.05.13 APOYO MOVIL UND 2.00 425.41 850.82 100.00% 850.82
04.05.14 BARANDA DE TUBO NEGRO PESADO 3" M 44.48 99.43 4,422.65 100.00% 4,422.65
05.00 SEÑALIZACION
05.01 SEÑAL INFORMATIVA UND 3.00 1,129.70 3,389.10 100.00% 3,389.10
05.02 SEÑAL PREVENTIVA UND 127.00 183.53 23,308.31 100.00% 23,308.31
05.03 POSTES KILOMETRICOS UND 17.00 180.30 3,065.10 100.00% 3,065.10
06.00 TRANSPORTE
06.01 TRANSPORTE DE MAT. GRANULAR HASTA 1KM M3K 6,132.89 15.02 92,116.01 50.00% 46,058.01 50.00% 46,058.01
06.02 TRANSPORTE DE MAT. GRANULAR>1KM M3K 27,863.57 2.84 79,132.54 50.00% 39,566.27 50.00% 39,566.27
CRONOGRAMA DE DESEMBOLSOS
Obra MEJORAMIENTO DEL C.V. SAN ISIDRO - PUERTO SAN ANTONIO - HUALLHUAPAMPA Departamento HUANCAVELICA
DISTRITO DE TINTAYPUNCU, PROV. TAYACAJA, HUANCAVELICA Provincia TAYACAJA
Distritos TINTAYPUNCU
Fecha 24/11/2019
Nº PARTIDA UND METRADO PRECIO PARCIAL 1º MES 2º MES 3º MES
UNITARIO % AVANCE MONTO % AVANCE MONTO % AVANCE MONTO
06.03 TRANSPORTE DE MATERIAL EXCEDENTE < 1KM M3K 11,191.52 8.34 93,337.28 50.00% 46,668.64 50.00% 46,668.64
06.04 TRANSPORTE DE MATERIAL EXCEDENTE > 1K M3K 17,129.52 2.98 51,045.97 50.00% 25,522.99 50.00% 25,522.99
07.00 IMPACTO AMBIENTAL
07.01 RESTAURACION DE CANTERA M2 1,800.00 0.71 1,278.00 100.00% 1,278.00
07.02 RESTAURACION DE PATIO DE MAQUINAS Y CAMPAMENTO M2 1,200.00 0.72 864.00 100.00% 864.00
07.03 ACONDICIONAMIENTO DE DEPOSITO DE MATERIALES EX M2 2,500.00 2.18 5,450.00 100.00% 5,450.00
07.04 REVEGETACION HA 0.52 8,123.71 4,224.33 100.00% 4,224.33
COSTO DIRECTO 1,477,815.34 406,578.59 737,302.23 333,934.52
GASTOS GENERALES 8.00% 118,225.26 32,526.30 58,984.19 26,714.77
UTILIDAD 7.00% 103447.07 28460.50 51611.16 23375.42
SUB TOTAL 1,699,487.67 467,565.39 847,897.58 384,024.70
IGV 18% 305,907.78 84,161.77 152,621.56 69,124.45
TOTAL 2,005,395.45 551,727.16 ### ###
% DE AVANCE 27.51% 49.89% 22.60%
% DE AVANCE ACUMULADO 27.51% 77.40% 100.00%