Plant - Time Phase - Discipline - Contract Time Phase - Plant - Discipline - Contract

WBS WBS Name WBS WBS Name


0 Project 0 Project
1 Building 1 1 Engineering
1.1 Engineering 1.1 Building 1
1.1.1 Civil 1.1.1 Civil
1.1.1.1 Company A 1.1.1.1 Company A
1.1.1.2 Company B 1.1.1.2 Company B
1.1.2 Mechanical 1.1.2 Mechanical
1.1.2.1 Company A 1.1.2.1 Company A
1.1.2.2 Company B 1.1.2.2 Company B
1.1.3 Electrical 1.1.3 Electrical
1.1.3.1 Company A 1.1.3.1 Company A
1.1.3.2 Company B 1.1.3.2 Company B
1.2 Procurement 1.2 Building 2
1.2.1 Civil 1.2.1 Civil
1.2.1.1 Company A 1.2.1.1 Company A
1.2.1.2 Company B 1.2.1.2 Company B
1.2.2 Mechanical 1.2.2 Mechanical
1.2.2.1 Company A 1.2.2.1 Company A
1.2.2.2 Company B 1.2.2.2 Company B
1.2.3 Electrical 1.2.3 Electrical
1.2.3.1 Company A 1.2.3.1 Company A
1.2.3.2 Company B 1.2.3.2 Company B
1.3 Construction 2 Procurement
1.3.1 Civil 2.1 Building 1
1.3.1.1 Company A 2.1.1 Civil
1.3.1.2 Company B 2.1.1.1 Company A
1.3.2 Mechanical 2.1.1.2 Company B
1.3.2.1 Company A 2.1.2 Mechanical
1.3.2.2 Company B 2.1.2.1 Company A
1.3.3 Electrical 2.1.2.2 Company B
1.3.3.1 Company A 2.1.3 Electrical
1.3.3.2 Company B 2.1.3.1 Company A
2 Building 2 2.1.3.2 Company B
2.1 Engineering 2.2 Building 2
2.1.1 Civil 2.2.1 Civil
2.1.1.1 Company A 2.2.1.1 Company A
2.1.1.2 Company B 2.2.1.2 Company B
2.1.2 Mechanical 2.2.2 Mechanical
2.1.2.1 Company A 2.2.2.1 Company A
2.1.2.2 Company B 2.2.2.2 Company B
2.1.3 Electrical 2.2.3 Electrical
2.1.3.1 Company A 2.2.3.1 Company A
2.1.3.2 Company B 2.2.3.2 Company B
2.2 Procurement 3 Procurement
2.2.1 Civil 3.1 Building 1
2.1.1.1 Company A 3.1.1 Civil
2.1.1.2 Company B 3.1.1.1 Company A
2.2.2 Mechanical 3.1.1.2 Company B
2.2.2.1 Company A 3.1.2 Mechanical
2.2.2.2 Company B 3.1.2.1 Company A
2.2.3 Electrical 3.1.2.2 Company B
2.2.3.1 Company A 3.1.3 Electrical
2.2.3.2 Company B 2.1.3.1 Company A
2.3 Construction 3.1.3.2 Company B
2.3.1 Civil 3.2 Building 2
2.3.1.1 Company A 3.2.1 Civil
2.3.1.2 Company B 3.2.1.1 Company A
2.3.2 Mechanical 3.2.1.2 Company B
2.3.2.1 Company A 3.2.2 Mechanical
2.3.2.2 Company B 3.2.2.1 Company A
2.3.3 Electrical 3.2.2.2 Company B
2.3.3.1 Company A 3.2.3 Electrical
2.3.3.2 Company B 3.2.3.1 Company A
3.2.3.2 Company B
Contract - Time Phase - Discipline - Plant Discipline - Plant - Contract - Time Phase
WBS WBS Name WBS
0 Project 0
1 Company A 1
1.1 Engineering 1.1
1.1.1 Civil 1.1.1
1.1.1.1 Building 1 1.1.1.1
1.1.1.2 Building 2 1.1.1.2
1.1.2 Mechanical 1.1.1.3
1.1.2.1 Building 1 1.1.2
1.1.2.2 Building 2 1.1.2.1
1.1.3 Electrical 1.1.2.2
1.1.3.1 Building 1 1.1.2.3
1.1.3.2 Building 2 1.2
1.2 Procurement 1.2.1
1.2.1 Civil 1.2.1.1
1.2.1.1 Building 1 1.2.1.2
1.2.1.2 Building 2 1.2.1.3
1.2.2 Mechanical 1.2.2
1.2.2.1 Building 1 1.2.2.1
1.2.2.2 Building 2 1.2.2.2
1.2.3 Electrical 1.2.2.3
1.2.3.1 Building 1 2
1.2.3.2 Building 2 2.1
2 Company B 2.1.1
2.1 Construction 2.1.1.1
2.1.1 Civil 2.1.1.2
2.1.1.1 Building 1 2.1.1.3
2.1.1.2 Building 2 2.1.2
2.1.2 Mechanical 2.1.2.1
2.1.2.1 Building 1 2.1.2.2
2.1.2.2 Building 2 2.1.2.3
2.1.3 Electrical 2.2
2.1.3.1 Building 1 2.2.1
2.1.3.2 Building 2 2.2.1.1
2.2.1.2
2.2.1.3
2.2.2
2.2.2.1
2.2.2.2
2.2.2.3
3
3.1
3.1.1
3.1.1.1
3.1.1.2
3.1.1.3
3.1.2
3.1.2.1
3.1.2.2
3.1.2.3
3.2
3.2.1
3.2.1.1
3.2.1.2
3.2.1.3
3.2.2
3.2.2.1
3.2.2.2
3.2.2.3
Discipline - Plant - Contract - Time Phase
WBS Name
Project
Civil
Building 1
Company A
Engineering
Procurement
Construction
Company B
Engineering
Procurement
Construction
Building 2
Company A
Engineering
Procurement
Construction
Company B
Engineering
Procurement
Construction
Mechanical
Building 1
Company A
Engineering
Procurement
Construction
Company B
Engineering
Procurement
Construction
Building 2
Company A
Engineering
Procurement
Construction
Company B
Engineering
Procurement
Construction
Electrical
Building 1
Company A
Engineering
Procurement
Construction
Company B
Engineering
Procurement
Construction
Building 2
Company A
Engineering
Procurement
Construction
Company B
Engineering
Procurement
Construction