Вы находитесь на странице: 1из 12

GLOBAL

CONSTRUCTION
DISPUTES REPORT
MIDDLE EAST

2016
DON’T GET LEFT BEHIND

Contract Solutions
DON’T
GET LEFT
BEHIND
With uncertainty reigning in markets around
the world and projects more complicated than
ever before, disputes are taking longer to resolve
which can have far reaching consequences
CONTENTS

INTRODUCTION 6-7

THE WORLD ECONOMY IN 2015 8-9

OVERALL FINDINGS 10 - 13

MIDDLE EAST 14 - 15

SUMMARY 16 - 17

METHODOLOGY 18

CONTRACT SOLUTIONS EXPERTISE 19

CONTACT 20 - 21
INTRODUCTION
Welcome to the Sixth We have taken an in-depth, data- • to keep the respective delivery natural resources markets and
driven review of our projects and teams focused on delivering the some of the major Engineering,
Annual Arcadis Global disputes globally in 2015 and project; and Procurement and Construction
focused on five key areas: the (EPC) contracts have run into
Construction Disputes length of disputes, average value,
• to avoid a cumulative effect of
some substantial disputes, with
minor issues being aggregated
Report 2016, which common causes, most popular
into large disputes.
billions of US dollars in contention.
resolution methods and region- There has also been a rise in the
reveals key themes specific nuances. This report number of insolvent companies
These reasons are largely self-
Mike Allen and insights into the also includes an overview of the evident, and it is aspirational to and terminated contracts, which
macroeconomic market position suggest that all disputes can or are no doubt linked to the current
Global Leader global construction and goes on to provide insight need to be settled quickly. Even economic environment.
of Contract
Solutions disputes market. Any into the Middle East in a regional so, we must continue to embrace
In the last year we have also had
commentary. the many initiatives that are
Arcadis dispute is case specific, being deployed by construction
two cases which provide helpful
It is commonly known in the guidance on important aspects of
so to endeavour to industry that a substantial
professionals, lawyers and the
construction dispute resolution.
judiciary across the globe, and
group causes and percentage of disputes are settled
do all we can to facilitate the
The first related to the application
before they become formalized. of Liquidated Damages, and the
develop averages can In the unlikely case a dispute is to
settlement of such disputes. This
other an important reminder to
means that effective dispute
risk omitting critical materialize formally, both parties
avoidance mechanisms need to
us all that being an experienced
involved could see themselves construction professional doesn’t
information related to in a situation where differing
be actively deployed as early as
necessary qualify you to be an
possible within a project, and
views and interests could prolong expert in this field. Both of these
the overall nature of the dispute. Setting aside the
involvement of the right expertise
cases are discussed in more detail
and support at the right time is
the dispute. However different drivers and motives
critical.
in the summary.
of both parties involved, it is
given our range and generally agreed that a speedy We hope that you enjoy this
In 2015 the construction industry
depth of the coverage, settlement of any dispute is edition, and if you have any
faced head winds in particular with
desired, but why? feedback or insight that you wish
commodity and currency volatility.
dispute trends, both This resulted in many projects
to share please contact me.
• To use current and available
globally and regionally, people and documents, which
and programs being faced with a
very different economic business
are indicative of market are directly relevant;
case than had been planned,
trends. • to maintain cash flow within the which contributed to some of
supply chain; the issues and disputes that have
materialized. In particular the
• to maintain party relationships;

6 7
THE WORLD
ECONOMY
IN 2015 led economy towards a more
sustainable path based on
consumption and services. In the
meantime, Chinese developers and
contractors have been diversifying
complete without a mention of
Brexit1. Brexit fears appear to be
having an impact on investment
decisions, but the direct impact of
either outcome of the referendum

The economic trends that away from home markets. While


they have shown themselves to
on construction is likely to be more
limited. However, given that so

impacted disputes
be adept at operating in overseas much of the debate in connection
markets, these organizations with the referendum concerns
are challenged to adapt to the free-movement of labor, it is
business cultures and construction conceivable that any changes to
practices of mature developed labor market rules could affect
The global recovery from the 2008 Much like the aftermath of the markets. Two unexpected spill- the ability of contractors to meet
financial crash continued in 2015, financial crash of 2008, the over effects of China’s slowdown long-term project commitments.
but at an ever slowing pace. Future loss of growth momentum in in international markets could This is a long-term risk, but as
prospects are looking increasingly some markets including Russia be an increase in competition for skills shortages are such a big
fragile. The baseline projection for and Brazil is likely to impact work – resulting in lower entry issue in many markets, the ability
global growth in 2016 is a modest on construction volumes, prices – and an increase in disputes of designers and contractors
3.2% according to the International leading to disputes surrounding as new entrants to markets align to find the abilities to deliver
Monetary Fund, which is broadly the cancellation, suspension, themselves to established ways of projects to cost, time and quality
in line with 2015, but a 0.2% termination or restructuring of working. expectations, could turn out to
downward revision from January projects. Elsewhere in markets be a significant trigger for project
As previously stated, turbulence problems and possible disputes
2016. Recovery is projected to that are seeing some recovery in in commodity and currency over the next few years.
strengthen in 2017 and beyond, demand such as mainland Europe, markets over the past 12 months
driven primarily by developing persistently low background may have exposed clients and On the bright side, despite the
economies as conditions in these inflation can be expected to affect their contractors to unexpected global slowdown impacting
stressed markets gradually contractors’ ability to secure financial outcomes that could on economies worldwide, one
normalize. However, there are big expected levels of returns on potentially trigger problems on a benefit is likely to be interest
risks in the forecasts and some projects. project. Crude oil was priced at $44 rates remaining low, as countries
turbulence is expected in markets,
A major cause of the global a barrel in April 2016, down 32% continue to apply fiscal stimulus.
which could, in turn, affect the
economic slowdown has been a year on year, but up by over 50% in We are therefore unlikely to see
level of construction disputes.
fall in investment demand. This the first quarter from the low point a reduction in viability due to
The end of 2015 and beginning has been the case particularly for of the cycle. Similar movement increases in the cost of finance.
of 2016 saw renewed episodes commodity exporting countries has been seen in currencies. These
wild fluctuations are likely to affect All together these factors will
of global asset market volatility. whose terms of trade have
some parties in a supply chain if contribute to a challenging
Commodity and currency prices collapsed. If the forward pipeline
appropriate price hedging has not economic environment over the
have also fluctuated a great deal, of construction-related projects
been put in place. Currencies and next year both in emerging and
increasing the levels of uncertainty further weakens in these countries,
commodities are likely to remain developed economies.
underpinning commercial those involved in construction
arrangements. Despite an projects may focus efforts on unstable and could well trigger
improvement in market sentiment maximizing returns from existing wider problems on projects going
during the first quarter of this projects through disputes rather forwards.
year, business conditions remain than pursuing future projects. Finally, in 2016, no review which
challenging, highlighted by weak
China is navigating a complex includes the UK and Continental
financial data from China and
transition away from a high European markets would be
further loosening of fiscal policy in
Europe and Japan. growth, investment and export-

1.
The referendum vote on whether the UK will withdraw from the European Union.

8 9
OVERALL FINDINGS
We define a ‘dispute’ as a situation where two parties typically differ in
the assertion of a contractual right, resulting in a decision being given
REGION DISPUTE VALUES (US$ MILLIONS) LENGTH OF DISPUTE (MONTHS)
• The global average value of under the contract, which in turn becomes a formal dispute. 2010 2011 2012 2013 2014 2015 2010 2011 2012 2013 2014 2015
disputes was US$46million. The value of a dispute is the additional entitlement to that included in Middle East 56.3 112.5 65 40.9 76.7 82 8.3 9 14.6 13.9 15.1 15.2
the contract, for the additional work or event which is being claimed. The
• The global average length of a dispute is the period between when it becomes formalized Asia 64.5 53.1 39.7 41.9 85.6 67 11.4 12.4 14.3 14 12 19.5
length of disputes was under the contract, and the time of settlement or the conclusion of the
North America 64.5 10.5 9 34.3 29.6 25 11.4 14.4 11.9 13.7 16.2 13.5
15.5months. hearing.

The results below show that disputes globally have marginally reduced,
UK 7.5 10.2 27 27.9 27 25 6.8 8.7 12.9 7.9 10 10.7
• The highest value dispute but the durations have markedly increased. The increased length of Continental Europe 33.3 35.1 25 27.5 38.3 25 10 11.7 6 6.5 18 18.5
handled by the team in disputes will have multiple effects for both parties and are likely to,
2015 was worth US$2.5bn. ultimately, have a negative impact on the construction industry. GLOBAL AVERAGE 35.1 32.2 31.7 32.1 51 46 9.1 10.6 12.8 11.8 13.2 15.5

10 11
Dispute causes – poor contract Resolving disputes – let’s talk
administration most common
2015 RANK METHOD OF ALTERNATIVE DISPUTE RESOLUTION 2014 RANK

2015 RANK CAUSE 2014 RANK 1 Party to party negotiation 1

1 Failure to properly administer the contract 1 2 Mediation 2

2 Poorly drafted or incomplete and unsubstantiated claims 2 3 Arbitration 3

3 Errors and/or omissions in the contract document 3


The most important activities in helping to avoid a We have found that these trends are symptomatic
4 Incomplete design information or employer requirements New dispute were considered the following: of the work that we have undertaken, and provides a
(for Design and Build) helpful insight into global trends.
1 Proper contract administration
5 Employer/contractor/subcontractor failing to understand and/or 4 2 Fair and appropriate risk and balances in contract Programs of work are being aggregated into various
comply with its contractual obligations delivery models, at a time when key features are
3 Accurate contract documents evident in the global market, and may well be of
a direct contributory relevance to the disputes
In addition to this, one feature that was also discussed
themselves, including:
A new cause in the rankings is related to incomplete within the key inputs to avoiding a dispute was the
design information, which is considered to be linked
generally to the poor quality of design information,
25.5% of Joint role (and perhaps return) of the need for a truly
independent certifier.
• Commodity and currency volatility;

Ventures (JVs)
• legacy effects of tenders priced in the immediate
and a proportionate increase globally in the use
In reviewing the overall findings we find that, when aftermath of the financial crisis and the ensuing
of design and construct forms of contract. The

ended in dispute. compared to previous years, we gain the following economic recession;
implementation of EPC forms of contract have been
particularly problematic in certain industries. headline insights into global disputes: • rising global cost base and strain upon the supply
chain;
The property/real estate sector had the most • They have decreased marginally in value;
disputes. This was closely followed by the social • scarcity of labor and professional staff;
• they have increased in duration;
infrastructure/public sector, albeit the natural • significant reduction in the oil and natural resources
resources sector has some of the largest disputes. • the most common cause is still a failure to
price that has caused a radical rethink of strategy
administer the contract;
and delivery across the major programs.
• 1 in 4 JV’s still end up in dispute; and
Beneath the headline data of our research, many of
• party to party negotiation is still the most common these factors have also proved to be a contributory
form of resolving disputes. feature within the dispute environment and are
considered to be key factors in ensuring that you
“Don’t get left behind”.
12 13
MIDDLE EAST
The three most common methods of Alternative Mediation and Adjudication instead of the traditionally
DISPUTE VALUES (US$ MILLIONS) LENGTH OF DISPUTE (MONTHS)
Dispute Resolution that were used during 2015 in ME contracted Litigation/Arbitration methods. All
2010 2011 2012 2013 2014 2015 2010 2011 2012 2013 2014 2015 were: parties embrace the added value that an impartial
professional judgement/recommendation brings
Middle 56.3 112.5 65 40.9 76.7 82 8.3 9 14.6 13.9 15.1 15.2 1 Party to party negotiation to the settlement of disputes, which is not only
East 2 Arbitration cheaper and more expeditious, but also transfers
decision-making to external agents, thereby assisting
3 Mediation with state audit compliance. The market is further
The Middle East region saw its dispute values increase, once more, to their highest value since 2011. In an economic environment impacted by the oil increasingly utilizing design and build contracting
However, the amount of time taken to resolve disputes remained more-or-less static. price, the market continues to see a restriction in models and has even experimented with the New
decision-making within the industry. This drives a lack Engineering Contract (NEC) suite. Public-private
of appropriate delegation to project management partnerships are also growing in popularity as
2015 RANK CAUSE 2014 RANK
consultants and client representatives, thereby inward investment is coveted to mitigate budget
1 A failure to properly administer the contract 1 prolonging critical commercial decisions and deficits generated by low oil prices. This shift in
generating cash flow issues related to instructed strategic procurement can only be beneficial to
2 Poorly drafted or incomplete and unsubstantiated claims 2 variations. Some clients are looking to spread cash the continued growth of construction in the Middle
obligations by prolonging commercial payments and East and maintain its attractiveness to international
3 Incomplete design information or employer requirements New negotiations. Additionally, the tendency to utilize a contractors and consultants.
(for Design and Build) traditional contracting strategy is ill-suited to the
While the region is experiencing a challenging
continuing size and complexity of the programs. This
period, the opportunities and potential rewards
A failure to properly administer the contract In the Middle East, where a JV is in place, the is exacerbated by the propensity of clients to transfer
for contractors and consultants remain. As better
remained the most common cause of dispute in the proportion of disputes caused by a JV-related issue the majority of project risk to contractors.
compliance and cost optimization initiatives are
region, followed by poorly drafted or incomplete dropped in 2015, moving down almost ten percent to However, there is a desire from all parties to better introduced by private operators and governmental
and unsubstantiated claims which, once again, 32.3% streamline formal dispute processes, reduce entities, the market will improve as an environment
demonstrates the need to get the basics right from administrative burden and create a fairer contracting within which both domestic and international
the very start. model. There is a noticeable shift in the use of organizations can thrive.

14 15
SUMMARY
Our regional commentary gives some insight into the common causes and features of disputes
in the Middle East. We consider that these themes provide a helpful reference point to typical
trends both regionally and globally. It is evident that the natural resources market is now
operating against a very different economic backdrop. The business case assumptions that
were likely used to endorse projects and programs have therefore changed, presenting a huge
challenge to the project and entity risk profiles. The disputes in this sector have been a material
feature in the last 12 months and will continue to be evident in the coming year.

We have established that globally resolve issues as they materialize. • adjudication or some forms This year, consistent with last the actual loss. The Court made it considered in the context of the
the following key dispute themes Furthermore, if a claim then does of ADR in some regions is not year, we have noted the following clear that delay damages will only widely referenced ‘Ikarian Reefer’
have prevailed: progress into a formalized dispute, providing a solution that is additional features, which include: be considered to be penal, and so case and guidelines.
actively deploying key support acceptable to the parties. unenforceable, if the damages are
• The average value has and expertise, effective strategies • Mega disputes, with the largest extravagant to the point of being Thank you and I hope that you
marginally reduced to US$46m. Some interesting features of dispute we have been engaged have enjoyed this year’s edition.
and the active use of Alternative unconscionable.
the regional overviews have in this year exceeding US$2.5bn;
• The average length has Dispute Resolution (ADR) will
highlighted the following trends in and The second case is worthy of note
increased to 15.5 months. assist in reducing the time it takes
some or all of the markets: on two fronts, because it provides a Mike Allen
to resolve the dispute. • a notable increase in the volume
• The most common cause is very helpful reminder and checklist Global Leader
• The effect of the global of arbitrations. of Contract
still the failure to properly Considering why the length of of what is required of an Expert
commodity and currency Solutions
administer the contract. disputes has increased is likely to The majority of construction Witness, and also because the
volatility;
be a mix of the following factors: disputes are resolved privately other expert in this case who was Arcadis
A continuing trend over the last
• the earlier deployment of and so we tend to have very few used as a reference point of what
six years is that, on average, • An increase in the size of dispute avoidance mechanisms; reported cases, however in 2016 should have been undertaken was
disputes have increased in value disputes that Arcadis has been there were amongst others two Gary Kitt (UK Leader of Arcadis
and duration, with the notable instructed to act; • the increasing use of mediation,
cases which merit a mention. The Contract Solutions). The case
increase this year in the length and refinement of other forms of
• an increase in the number of first is Cavendish Square Holdings was Van Oord UK Limited & Sicim
of time taken to resolve disputes. ADR; and
large and complex EPC disputes; BV –v- El Makdessi and Parking Roadbridge Limited –v- Allseas UK
Therefore our theme this year
• a reliance from public or quasi- Eye Ltd –v- Beavis [2015] UKSC67, Limited [2015] EWHC 3074 (TCC),
of “Don’t get left behind” is • the disputes that are formalized public bodies to require third in which the notion of a liability in which the Court clearly set out
focused around making sure are including multiple or whole party decisions, to assist in for delay damages might be 12 rules of what is required of an
that in recognizing what causes contract issues, rather than retaining complete ‘arm’s length’ challenged if the rate of damages expert, and it is suggested that the
disputes, avoidance mechanisms referring discrete claims; and decision making. is not a genuine pre-estimate of full judgement should be read and
can be actively deployed to

16 17
METHODOLOGY CONTRACT
SOLUTIONS
This research was conducted by the
Arcadis Contract Solutions experts EXPERTISE
and is based on construction
disputes handled by the team in
2015. Arcadis’ Contract Solutions teams
help clients avoid, mitigate and
Arcadis is the leading global Design resolve disputes. The team is based
& Consultancy firm for natural around the globe and encompasses
and built assets. Applying our one of the industry’s largest pool
deep market sector insights and of procurement, contract, risk
collective design, consultancy, management and also quantum,
engineering, project and delay, project management,
management services we work engineering defects and building
in partnership with our clients to surveying experts.
deliver exceptional and sustainable
outcomes throughout the lifecycle The team provides procurement,
of their natural and built assets. contract and dispute avoidance
We are 27,000 people active in over and management strategies,
70 countries that generate €3.4 management expertise as well
billion in revenues. We support as dispute resolution and expert
UN-Habitat with knowledge witness services. This is delivered
and expertise to improve the through a blend of technical
quality of life in rapidly growing expertise, commercialism, sector
cities around the world insight and the use of live project
www.arcadis.com.  data, combined with a multi-
disciplined and professional focus.
Arcadis
Improving quality of life.

18 19
CONTACTS:
Craig Beeson
Head of Contract Solutions,
Middle East
T: +974 4424 5000
Email: craig.beeson@arcadis.com

20 21
Arcadis

@arcadisglobal

www.arcadis.com Contract Solutions

Вам также может понравиться