Академический Документы
Профессиональный Документы
Культура Документы
[1]
ABSTRACT
INTRODUCTION
programmed to be built. Usually, the small projects and several large hydro-
projects as well, are located at ungaged sites and either their scale does not
justify or the inaccessibility of their location does not permit a pre-project
data acquisition at the site. Thus, the hydrologic design of these projects
must be based on information spatially transferred from other gaged sites.
The majority of the potential water resources development sites of the area
studied are remote from existing hydrometeorologic stations so that the
transfer of hydrologic information, especially of runoff characteristics, by
using regression analysis (rainfall--runoff analysis, etc.) has been proved
untenable in most of the cases. The only m e t h o d which seems to be appro-
priate in such cases is to attempt the spatial transfer of information through
regionalization (Mimikou, 1982, 1984).
It is well known that the hydropower potential at a certain site depends
on the water availability and on the hydraulic head. Thus, a hydrologic
concern in the design is to estimate the flow availability at the site, which
is readily expressed by the flow duration curve. Although the latter does not
give the sequence of flows, that is provided by the complete hydrograph, it
yields a quick indication of the need for a storage reservoir at a certain river
site where a given flow is to be maintained and gives information needed for
the estimation of the hydropower potential at the site. It is thus a usefull
tool in preliminary hydroelectric energy studies. The curve gives hydrologic
information needed, as well in water supply studies and in water quality
studies.
Basic scope of the paper is to develop a simple technique for estimating
water availability at ungaged sites or generally at sites where data is scarce.
The regionalization of m o n t h l y flow duration characteristics in western and
northwestern Greece is presented. The technique is successfully applied in
estimating synthetic flow duration curves at ungaged sites of the area studied,
by using as input information morphoclimatic characteristics of the drainage
basins. Conclusions are drawn for the accuracy and the usefulness of the
technique, and a comparative reference to other related studies on the same
subject (Singh, 1971; Quimpo et al., 1983) is undertaken.
DATA USED
l
\ SCALE
\
0 " 50
\
I
N
f
f
\ Y U G O $ L A V I A
\ /
J
•\ /-
ALBANIA %" ~ ~ " . . . . . . . . k,. r . ~' "
...-.:i
~ ~ ~='::::::':"":
/ ?o i!~i~iiii!~
, P L A K A ST.
STE R EA
HEL L A S
tAVLAKI ST.
PE LO PON N E S U S
TABLE 1
Characteristics of the measuring stations
TABLE 2
M o r p h o c l i m a t i c characteristics
The flow duration curve is a plot of discharge Q versus the percent of time
D during the period of the record in which the particular discharge is equaled
or exceeded. It is a well known and widely used graph and details of the
procedure for the development of the curve can be found in introductory
hydrology books (Linsley and Franzini, 1972). Because of the numerical
procedure followed, the time interval used in the derivation affects the shape
of the curve. In this study m o n t h l y flow values have been used for the deri-
vation of the duration curves. This is due to the needs of the design of the
hydropower and other hydraulic installations of the area.
Following the definition of the flow duration curve, it is apparent that the
analytical expression of the curve depends on the serial correlation structure
of the flow time series. For series with statistically insignificant serial correla-
tion, the flow duration characteristics could be modelled with a probability
distribution model (gaussian, log-normal, etc.), as it is c o m m o n practice
when dealing with statistical data (Yevjevich, 1972). Nevertheless, in most of
the cases the flow series are autocorrelated (Kashyap and Rao, 1976) and
this is why the flow duration curve procedure differs from a probability
distribution approach. The serial dependence of the m o n t h l y flow series at
the 11 sites used in this study has been checked by using the autocorrelation
analysis and the Portmanteau check for testing the significance of the first-
order autocorrelation coefficient (Box and Jenkins, 1970). It was found that
all series exhibit a statistically significant first-order autocorrelation structure
at the 95% confidence level.
Various mathematical models for the flow duration curve have been used
in the literature. Singh (1971} conducted a research on flow duration curves
82
ILARION SIATISTA
20[ - Calculated curve
- Calculated curve
200I • Real value • Real va~ue
2
v
150 15(
TION CALIBRATION
~00 100
50 .
o o
0 O0 0 25 0 50 075 1 O0 o.0o 025 050 075 100
D - P e r c e n t of tqme O is equaled or exceeded D - P e r c e n t of trine Q ~ equaled or exceeded
A~LAN I
QREVENA - C a l c u l a t e d CUrve
200
- Calculated curve • Real v a l u e
• Real ~alue ~.~ 2 0 0 I
150
150
CALIBRATION
CALIBRATION
cl cl
100 100
50 50
".°
o1~
000 025 050 075
D - P e r c e n t of tqme O is equa~ed
....
100
or exceeded
0
O0 025 050 075
D - Percent of brae O 15 equaled
100
or exceeded
Fig. 2. Flow duration curves at the Ilarion, Siatista, Grevena and Avlaki measuring
stations.
PLA•A TSInOUO
2O0 - Calculated curve -Calculated curve
o • Real value 2001 • Real value
g ~
150 150
CALI BRAT I,qN u CALIBRATION
0 l
100 ; ,ool
50
000 025 050 075 100 o.00 025 050 075 100
D~ Percent of t,me O ,s equaled or exceeded D-Percent of time O ,S equaled or exceeded
KONITSA
GOGOS 20C,~I - Calculated curve
2 oo Calculated curve
o - • Real value
• Real value
~Z
v g
L
~ 150
15C
CALIBRATION
CALIBRATION
~3
100
100
50
o
o
0o0 025 050 075 100
ooo 025 050 075 100
D- Percent of t,me 0 is equaled or exceeded
D- Percent of t~me Q ps equaled or exceeded
Fig. 3. Flow duration curves at the Plaka, Tsimovo, Gogos and Konitsa measuring
stations.
daily flow duration model (Quimpo et al., 1983) and the monthly one esti-
mated herein cannot be safely justified because of the differences due to the
incorporation into the former of the drainage area as an additional implicit
85
VOVOUSSA VROSSINA
A 200 20O - Calculated curve
- Calculated curve
• Real value • Real value
~ 15C 15(
CALIBRATION CALIBRATION
cl
10C 100
5O 50
50ULOPOLILO
200
-Calculated curve
• Real value
'~ 15C
CALIBRATION
100
5o!
0.00 0.25 0 50 0.75 IO 0
D - P e r c e n t of t~me Q m5 equaled or exceeded
Fig. 4. Flow duration curves at the Vovoussa, Vrossina and Soulopoulo measuring
stations.
V = boPb'Ab:Hb~Lb4 (9)
where V is the dependent variable representing the parameters a, b, c, d and
b0, bl, b2, b3, b 4 are constants. The multiple regression analysis was per-
formed aceording to standard statistical texts (Haan, 1977; Middlebrooks,
1979). The model in eqn. (9) has been proved to be the one with the lesser
sum of squares of residuals for all parameters. Therefore, it has been selected
to be the best regional model to explain the spatial variation of the para-
meters of the flow durations curve. The regional models for all parameters,
fitted on the parameter values as given in Table 3, and their correlation
coefficients r are the following:
a = 0.011pO'S26A°-6OSHO'OOTLOaS3 r = 0, 87 (10)
b = 0.053 P°'S11A°'684H-°'lSlL °'27s r = 0, 87 (11)
c = 0.010 P°'7°SA°'952H-°'31SL°'°73 r = 0, 84 (12)
87
TABLE 3
Parameters and correlation coefficients of the regression equations
a b c d r
TABLE 4
F-test -- confidence levels
TABLE 5
Coefficients of determination r 2
H 0.009 0.012
L, H 0.524 0.254
P, L, H 0.567 0.311
A, P, L, H 0.757 0.687
L 0.506 0.337
H, L 0.531 0.439
P, H, L 0.563 0.478
A, P, H, L 0.748 0.712
APPLICATION -- VERIFICATION
The regional models in eqns. (10)--(13) can be used to estimate the flow
duration characteristics a, b, c and d and therefore, to construct a synthetic
flow duration curve of the cubic form of eqn. (5) for any other remote
ungaged site for hydropower or any other water resources development site
within the hydrologically homogeneous region of western and northwestern
Greece. The flow duration curve doesn't give information on the sequence of
flows, a fact that limits its usefulness in the design. Nevertheless, it readily
expresses the water availability and gives information needed for the esti-
mation of the h y d r o p o w e r potential (the latter being proportional to the
product of the discharge and the hydraulic head) at a certain site. It is thus
useful in preliminary hydro-electric energy studies, especially for small hydro-
power plants, where due to the small scale of the design, the requirements of
the study can be m e t by the type of flow information provided by the duration
curve, until sufficient data become available to warrant more sophisticated
techniques of analysis. It is also useful in assessing energy production at run-
of-river plants. It has also application in water supply and water quality
studies, where the duration of flows is basic hydrologic information for
the design. For example, the duration of low flows is strongly affecting the
solution of various pollution problems.
In order to verify the developed regional technique and to estimate the
accuracy for constructing synthetic flow duration curves at other locations
of the area, two other sites, which have not been used in the calibration
procedure, the Piges and the Kioteki stations on the Aoos and the Kalamas
rivers respectively, have been used. The characteristics of the stations and the
morphoclimatic characteristics of their drainage basins are given in Tables
1 and 2. The latter characteristics have been used in eqns. (10)--(13) and the
parameters a, b, c and d of the synthetic flow duration curves at both sites
have been estimated. Then eqn. (5) has been used to construct the curves
as shown in Fig. 5. Each of the two synthetic curves (dotted line) is given
along with the corresponding real curve (solid line) which is eye-fitted and
connects the points obtained from 25 pairs of discharge Q versus the time
of exceedance D. The (Q, D) pairs have been estimated from the available
monthly records at both sites by following the procedure previously descri-
bed. The fitting of the synthetic curves to the real ones appears to be very
good, especially at the Piges site.
90
IE E
g g
t_ L
~ 15£ 15C
UERIF]CATION UERIF ICATIOrb
c3 cl
q,,
10C 10C
50 50
Fig. 5. Synthetic flow duration curves at the Piges and Kioteki measuring stations.
where Qi is the real discharge, ~)i is the estimated one at the time D = i
of the abscissa and i ranges from 1 to N. The discharge values finally used
in eqn. (14) are the ones corresponding to the N = 25 pairs previously
selected and plotted in Fig. 5. The estimated accuracy is satisfactory and
equal to: e = 3% for the Piges station and e = 10% for the Kioteki station.
CONCLUSIONS
(3) The developed regional technique can be easily and successfully used
in estimating synthetic flow duration curves at ungaged sites within the
hydrologically homogeneous region of the study in western and north-
western Greece. It is usefull in estimating water availability for hydropower
at ungaged sites (especially for small hydropower plants, for run-of-river
plants), or for other water resources development (water supply, water
quality projects).
ACKNOWLEDGEMENTS
The authors wish to thank the Public Power Corporation of Greece for
providing the data used in the study.
REFERENCES
Box, G.P. and Jenkins, G.M., 1970. Time Series Analysis -- Forecasting and Control.
Holden-Day, San Francisco, Calif., 553 pp.
Haan, T.C., 1977. Statistical Methods in Hydrology. Iowa State University Press, Ames,
Iowa, 378 pp.
Kashyap, K.L. and Rao, A.R., 1976. Dynamic Stochastic Models from Empirical Data.
(Mathematics in Science and Engineering, 122) Academic Press, New York, N.Y.,
334 pp.
Linsley, R.K. and Franzini, J.B., 1972. Water resources Engineering. McGraw-Hill, New
York, N.Y., 690 pp.
Middlebrooks, F.J., 1979. Statistical Calculations. Ann Arbor Science, Ann Arbor, Mich.,
525 pp.
Mimikou, M., 1982. An investigation of suspended sediment rating curve in western and
northern Greece, Hydrol. Sci. J., 27 (3, 9): 369--383.
Mimikou, M., 1984. Regional relationships between basin size and runoff characteristics.
Hydrol. Sc. J., 29(1, 3): 63--73.
Quimpo, R.G., Alejandrino, A.A. and McNally, T.A., 1983. Regionalized flow duration
for Philippines. J. Water Resour. Plann. Manage., 109(4): 320--330.
Singh, K.P., 1971. Model flow duration and stream flow variability. Water Resour. Res.,
AGU, 7(4) : 1031--1036.
U.S.G.S. (U.S. Geol. Surv.), 1959. Flow Duration Curves, Manual of Hydrology: Part 2,
Low-Flow Techniques. Water Supply Pap. 1542-A, U.S. Gov. Print. Off., Washington,
D.C.
Yevjevich, V., 1972. Probability and Statistics in Hydrology. Water Resour. Publ., Fort
Collins, Colo., 302 pp.