Вы находитесь на странице: 1из 9

Boracay Foundation, Inc. v.

Province of Aklan opposition to the reclamation project on environmental, socio-


G.R. No. 196870, June 26, 2012 economic and legal grounds.

Despite the opposition, the Province merely noted their


FACTS: objections and issued a notice to the contractor on December 1, 2010
Claiming that tourist arrivals to Boracay would reach 1 million to commence with the construction of the project. Thus, on June 1,
in the future, respondent Province of Aklan planned to expand the port 2011, BFI filed with the Supreme Court the instant Petition for
facilities at Barangay Caticlan, Municipality of Malay. Thus, on May Environmental Protection Order/Issuance of the Writ of
7, 2009, the Sangguniang Panlalawigan of Aklan Province issued a Continuing Mandamus. Thereafter, the Court issued a Temporary
resolution, authorizing Governor Carlito Marquez to file an application Environmental Protection Order (TEPO) and ordered the respondents
with respondent Philippine Reclamation Authority (PRA) to reclaim to file their respective comments to the petition.
the 2.64 hectares of foreshore area in Caticlan. In the same year, the
Province deliberated on the possible expansion from its original The Petition was premised on the following grounds, among
proposed reclamation area of 2.64 hectares to forty (40) hectares in others:
order to maximize the utilization of its resources. a) the Province failed to obtain the favorable endorsement of
After PRA’s approval, on April 27, 2010, respondent the LGU concerned;
Department of Environment and Natural Resources-Environmental b) the Province failed to conduct the required consultation
Management Bureau-Region VI (DENR-EMB RVI) issued to the procedures as required by the Local Government Code
Province Environmental Compliance Certificate-R6-1003-096-7100 (LGC).
(the questioned ECC) for Phase 1 of the Reclamation Project to the The Province responded by claiming that its compliance with
extent of 2.64 hectares to be done along the Caticlan side beside the the requirements of DENR-EMB RVI and PRA that led to the
existing jetty port. approval of the reclamation project by the said government agencies,
On May 17, 2010, the Province finally entered into a MOA as well as the recent enactments of the Barangay Council of Caticlan
with PRA which stated that the land use development of the and the Sangguniang Bayan of the Municipality of Malay favorably
reclamation project shall be for commercial, recreational and endorsing the said project, had “categorically addressed all the issues”
institutional and other applicable uses. It was at this point that the raised by the BFI in its Petition. It also considered the Petition to be
Province deemed it necessary to conduct a series of public consultation premature for lack of cause of action due to the failure of BFI to fully
meetings. exhaust the available administrative remedies even before seeking
judicial relief.
On the other hand, the Sangguniang Barangay of Caticlan, the
Sangguniang Bayan of the Municipality of Malay and petitioner
Boracay Foundation, Inc. (BFI), an organization composed of some ISSUES:
160 businessmen and residents in Boracay, expressed their strong
WON the petition is premature because petitioner failed to law rule or regulation or a right therein, xxx and there is no other plain,
exhaust administrative remedies before filing this case? speedy and adequate remedy in the ordinary course of law.” Such
proper court may be the Regional Trial Court exercising jurisdiction
WON there was proper, timely, and sufficient public over the territory where the actionable neglect or omission occurred,
consultation for the project? the Court of Appeals, or the Supreme Court.

Here, the Court found that BFI had no other plain, speedy, or
RULING: adequate remedy in the ordinary course of law to determine the
questions of unique national and local importance raised that pertain to
On the issue of prematurity due to failure to exhaust administrative laws and rules for environmental protection.
remedies
Moreover, the writ of continuing mandamus “permits the court
The Court held that the petition is not premature for failing to to retain jurisdiction after judgment in order to ensure the successful
exhaust administrative remedies and to observe the hierarchy of courts implementation of the reliefs mandated under the court’s decision”
as claimed by the respondents. and, in order to do this, “the court may compel the submission of
compliance reports from the respondent government agencies as well
The Court reiterated their ruling in Pagara v. Court of Appeals
as avail of other means to monitor compliance with its decision.”
where they clarified that the rule regarding exhaustion of
administrative remedies is not a hard and fast rule. It is not applicable
where, among others, there are circumstances indicating the urgency
of judicial intervention such as in the instant case. The rule may also On the issue of whether or not there was proper, timely, and
be disregarded when it does not provide a plain, speedy and adequate sufficient public consultation for the project
remedy or where the protestant has no other recourse. The Court found that there was no proper, timely, and
Meanwhile, the new Rules of Procedure for Environmental sufficient public consultation for the project.
Cases, A.M. No. 09-6-8-SC, provides a relief for petitioner under the The Local Government Code (LGC) establishes the duties of
writ of continuing mandamus, which is a special civil action that may national government agencies in the maintenance of ecological balance
be availed of “to compel the performance of an act specifically and requires them to secure prior public consultations and approval of
enjoined by law” and which provides for the issuance of a TEPO “as local government units. In Province of Rizal v. Executive Secretary,
an auxiliary remedy prior to the issuance of the writ itself.” the Court emphasized that, under the Local Government Code, two
The writ of continuing mandamus allows an aggrieved party to requisites must be met before a national project that affects the
file a verified petition in the proper court when any government environmental and ecological balance of local communities can be
agency or instrumentality or officer thereof “unlawfully neglects the implemented: (1) prior consultation with the affected local
performance of an act which the law specifically enjoins as a duty xxx communities, and (2) prior approval of the project by the appropriate
in connection with the enforcement or violation of an environmental
sanggunian. The absence of either of such mandatory requirements
will render the project’s implementation as illegal.

Here, the Court classified the reclamation project as a national


project since it affects the environmental and ecological balance of
local communities. In one ruling, the Court noted that such national
projects mentioned in Section 27 of the LGC include those that may
cause pollution and bring about climate change, among others, such as
the reclamation project in this case.

Also, DENR DAO 2003-30 provides that project proponents


should “initiate public consultations early in order to ensure that
environmentally relevant concerns of stakeholders are taken into
consideration in the EIA study and the formulation of the management
plan”.

Thus, the law requires the Province, being the delegate of the
PRA’s power to reclaim land in this case, to conduct prior
consultations and prior approval. However, the information
dissemination conducted months after the ECC had already been
issued was insufficient to comply with the requirements under the
LGC.

Furthermore, the lack of prior public consultation and approval


is not corrected by the subsequent endorsement of the reclamation
project by the Sangguniang Barangay of Caticlan and the Sangguniang
Bayan in 2012, which were both undoubtedly achieved at the urging
and insistence of the Province.
CASE DIGEST: BORACAY FOUNDATION, INC. v. THE expressed its strong opposition to the intended foreshore lease
PROVINCE OF AKLAN, et al. application, through Resolution No. 044, approved on July 22, 2009,
manifesting therein that respondent Provinces foreshore lease
FACTS: Boracay Island (Boracay), a tropical paradise located in the application was for business enterprise purposes for its benefit, at the
Western Visayas region of the Philippines and one of the countrys expense of the local government of Malay, which by statutory
most popular tourist destinations, was declared a tourist zone and provisions was the rightful entity to develop, utilize and reap benefits
marine reserve in 1973 under Presidential Proclamation No. 1801. The from the natural resources found within its jurisdiction.
island comprises the barangays of Manoc-manoc, Balabag, and Yapak,
all within the municipality of Malay, in the province of Aklan. In August 2009, a Preliminary Geohazard Assessmentfor the
enhancement/expansion of the existing Caticlan Jetty Port and
More than a decade ago, respondent Province built the Caticlan Jetty Passenger Terminal through beach zone restoration and Protective
Port and Passenger Terminal at Barangay Caticlan to be the main Marina Developments in Caticlan, Malay, Aklan was completed.
gateway to Boracay.It also built the corresponding Cagban Jetty Port
and Passenger Terminal to be the receiving end for tourists in Boracay. Thereafter, Governor Marquez submitted an Environmental
Respondent Province operates both ports to provide structural facilities Performance Report and Monitoring Program (EPRMP) to DENR-
suited for locals, tourists and guests and to provide safety and security EMB RVI, which he had attached to his letter dated September 19,
measures. 2009, as an initial step for securing an Environmental Compliance
Certificate (ECC). The letter reads in part:
Governor Marquez sent a letter to respondent PRA on March 12, 2009
expressing the interest of respondent Province to reclaim about 2.64 With the project expected to start its construction implementation next
hectares of land along the foreshores of Barangay Caticlan, month, the province hereby assures your good office that it will give
Municipality of Malay, Province of Aklan, pursuant to Resolution No. preferential attention to and shall comply with whatever comments
13, s. 2008 issued by the Sangguniang Barangay of Caticlan. that you may have on this EPRMP.

Sometime in April 2009, respondent Province entered into an Within the same month of October 2009, respondent Province
agreement with the Financial Advisor/Consultant that won in the deliberated on the possible expansion from its original proposed
bidding process held a month before, to conduct the necessary reclamation area of 2.64 hectares to forty (40) hectares.
feasibility study of the proposed project for the
Renovation/Rehabilitation of the Caticlan Passenger Terminal Respondent PRA approved the reclamation project on April 20, 2010
Building and Jetty Port, Enhancement and Recovery of Old Caticlan in its Resolution No. 4094and authorized its General Manager/Chief
Coastline, and Reclamation of a Portion of Foreshore for Commercial Executive Officer (CEO) to enter into a MOA with respondent
Purposes (the Marina Project), in Malay, Aklan. Province for the implementation of the reclamation project.

Subsequently, on May 7, 2009, the Sangguniang Panlalawigan of On April 27, 2010, DENR-EMB RVI issued to respondent Province
respondent Province issued Resolution No. 2009110, which authorized ECC-R6-1003-096-7100 (the questioned ECC) for Phase 1 of the
Governor Marquez to file an application to reclaim the 2.64 hectares of Reclamation Project to the extent of 2.64 hectares to be done along the
foreshore area in Caticlan, Malay, Aklan with respondent PRA. Caticlan side beside the existing jetty port.

Meanwhile, the Sangguniang Bayan of the Municipality of Malay On May 17, 2010, respondent Province entered into a MOA with
respondent PRA.
ISSUES:
In Resolution No. 046, Series of 2010, adopted on June 23, 2010, the
Malay Municipality reiterated its strong opposition to respondent [1] Whether or not the petition should be dismissed for having
Provinces project and denied its request for afavorableendorsement of been rendered moot and academic;
the Marina Project.
[2] Whether or not the petition is premature because petitioner
The Malay Municipality subsequently issued Resolution No. 016, failed to exhaust administrative remedies before filing this case;
Series of 2010, adopted on August 3, 2010, to request respondent PRA
not to grant reclamation permit and notice to proceed to the Marina [3] Whether or not respondent Province failed to perform a full
Project of the respondent Provincial Government of Aklan located at EIA as required by laws and regulations based on the scope and
Caticlan, Malay, Aklan. classification of the project;

In a letter dated October 12, 2010, petitioner informed respondent [4] Whether or not respondent Province complied with all the
PRA of its opposition to the reclamation project. requirements under the pertinent laws and regulations; and

Petitioner likewise transmitted its Resolution No. 001, Series of 2010, [5] Whether or not there was proper, timely, and sufficient public
registering its opposition to the reclamation project to respondent consultation for the project
Province, respondent PRA, respondent DENR-EMB, the National
Economic Development Authority Region VI, the Malay Municipality, HELD: A close reading of the two LGUs respective resolutions
and other concerned entities. would reveal that they are not sufficient to render the petition
moot and academic, as there are explicit conditions imposed that
Petitioner alleges that despite the Malay Municipalitys denial of must be complied with by respondent Province. In Resolution No.
respondent Provinces request for afavorableendorsement, as well as 003, series of 2012, of the Sangguniang Barangay of Caticlan it is
the strong opposition manifested both by Barangay Caticlan and stated that any vertical structures to be constructed shall be subject for
petitioner as an NGO, respondent Province still continued with the barangay endorsement. Clearly, what the barangay endorsed was the
implementation of the Reclamation Project. reclamation only, and not the entire project that includes the
construction of a commercial building and wellness center, and other
On June 1, 2011, petitioner filed the instant Petition for Environmental tourism-related facilities.Petitioners objections, as may be recalled,
Protection Order/Issuance of the Writ of Continuing Mandamus. On pertain not only to the reclamation per se, but also to the building to be
June 7, 2011, this Court issued a Temporary Environmental Protection constructed and the entire projects perceived ill effects to the
Order (TEPO) and ordered the respondents to file their respective surrounding environment.
comments to the petition.
The Sangguniang Bayan of Malay obviously imposed explicit
After receiving a copy of the TEPO on June 9, 2011, respondent conditions for respondent Province to comply with on pain of
Province immediately issued an order to the Provincial Engineering revocation of its endorsement of the project, including the need to
Office and the concerned contractor to cease and desist from conduct a comprehensive study on the environmental impact of the
conducting any construction activities until further orders from this reclamation project, which is the heart of the petition before us.
Court. Therefore, the contents of the two resolutions submitted by respondent
Province do not support its conclusion that the subsequent favorable
endorsement of the LGUs had already addressed all the issues raised The new Rules of Procedure for Environmental Cases, A.M. No. 09-6-
and rendered the instant petition moot and academic. 8-SC, provides a relief for petitioner under the writ of continuing
mandamus, which is a special civil action that may be availed of to
2) We do not agree with respondents appreciation of the compel the performance of an act specifically enjoined by law and
applicability of the rule on exhaustion of administrative remedies which provides for the issuance of a TEPO as an auxiliary remedy
in this case. We are reminded of our ruling in Pagara v. Court of prior to the issuance of the writ itself. The Rationale of the said Rules
Appeals, which summarized our earlier decisions on the procedural explains the writ in this wise:
requirement of exhaustion of administrative remedies, to wit:
The rule regarding exhaustion of administrative remedies is not a hard Environmental law highlights the shift in the focal-point from the
and fast rule. It is not applicable: (1) where the question in dispute is initiation of regulation by Congress to the implementation of
purely a legal one, or (2) where the controverted act is patently illegal regulatory programs by the appropriate government agencies.
or was performed without jurisdiction or in excess of jurisdiction; or
(3) where the respondent is a department secretary, whose acts as an Thus, a government agencys inaction, if any, has serious implications
alter ego of the President bear the implied or assumed approval of the on the future of environmental law enforcement. Private individuals, to
latter, unless actually disapproved by him, or (4) where there are the extent that they seek to change the scope of the regulatory process,
circumstances indicating the urgency of judicial intervention. will have to rely on such agencies to take the initial incentives, which
may require a judicial component. Accordingly, questions regarding
Said principle may also be disregarded when it does not provide a the propriety of an agencys action or inaction will need to be analyzed.
plain, speedy and adequate remedy, when there is no due process
observed, or where the protestant has no other recourse. This point is emphasized in the availability of the remedy of the writ
of mandamus, which allows for the enforcement of the conduct of the
tasks to which the writ pertains: the performance of a legal duty.
Although petitioner was not a party to the proceedings where the
decision to issue an ECC was rendered, it stands to be aggrieved by the The writ of continuing mandamus permits the court to retain
decision, because it claims that the reclamation of land on the Caticlan jurisdiction after judgment in order to ensure the successful
side would unavoidably adversely affect the Boracay side, where implementation of the reliefs mandated under the courts decision and,
petitioners members own establishments engaged in the tourism trade. in order to do this, the court may compel the submission of compliance
As noted earlier, petitioner contends that the declared objective of the reports from the respondent government agencies as well as avail of
reclamation project is to exploit Boracays tourism trade because the other means to monitor compliance with its decision.
project is intended to enhance support services thereto; however, this
objective would not be achieved since the white-sand beaches for Petitioner had three options where to file this case under the rule: the
which Boracay is famous might be negatively affected by the project. Regional Trial Court exercising jurisdiction over the territory where
Petitioners conclusion is that respondent Province, aided and abetted the actionable neglect or omission occurred, the Court of Appeals, or
by respondents PRA and DENR-EMB RVI, ignored the spirit and this Court.
letter of our environmental laws, and should thus be compelled to
perform their duties under said laws. Petitioner had no other plain, speedy, or adequate remedy in the
ordinary course of law to determine the questions of unique national
*** and local importance raised here that pertain to laws and rules for
environmental protection, thus it was justified in coming to this Court. ***

3) Being the administrator of the EIS System, respondent DENR-EMB The Local Government Code establishes the duties of national
RVIs submissions bear great weight in this case.However, the government agencies in the maintenance of ecological balance, and
following are the issues that put in question the wisdom of respondent requires them to secure prior public consultation and approval of local
DENR-EMB RVI in issuing the ECC: government units for the projects described therein.

[1] Its approval of respondent Provinces classification of the project as In the case before us, the national agency involved is respondent PRA.
a mere expansion of the existing jetty port in Caticlan, instead of Even if the project proponent is the local government of Aklan, it is
classifying it as a new project; respondent PRA which authorized the reclamation, being the exclusive
[2] Its classification of the reclamation project as a single instead of a agency of the government to undertake reclamation nationwide.
co-located project; Hence, it was necessary for respondent Province to go through
[3] The lack of prior public consultations and approval of local respondent PRA and to execute a MOA, wherein respondent PRAs
government agencies; and authority to reclaim was delegated to respondent Province. Respondent
[4] The lack of comprehensive studies regarding the impact of the DENR-EMB RVI, regional office of the DENR, is also a national
reclamation project to the environment. government institution which is tasked with the issuance of the ECC
that is a prerequisite to projects covered by environmental laws such as
As may be gleaned from the breakdown of the 2.64 hectares as the one at bar.
described by respondent Province above, a significant portion of the
reclaimed area would be devoted to the construction of a commercial This project can be classified as a national project that affects the
building, and the area to be utilized for the expansion of the jetty port environmental and ecological balance of local communities, and is
consists of a mere 3,000 square meters (sq. m). To be true to its covered by the requirements found in the Local Government Code
definition, the EIA report submitted by respondent Province should at provisions.
the very least predict the impact that the construction of the new
buildings on the reclaimed land would have on the surrounding Under the Local Government Code, therefore, two requisites must be
environment. These new constructions and their environmental effects met before a national project that affects the environmental and
were not covered by the old studies that respondent Province ecological balance of local communities can be implemented: prior
previously submitted for the construction of the original jetty port in consultationwith the affected local communities, and prior approval of
1999, and which it re-submitted in its application for ECC in this the project by the appropriate sanggunian. Absent either of these
alleged expansion, instead of conducting updated and more mandatory requirements, the projects implementation is illegal.
comprehensive studies.
Based on the above, therefore, prior consultations and prior approval
Any impact on the Boracay side cannot be totally ignored, as Caticlan are required by law to have been conducted and secured by the
and Boracay are separated only by a narrow strait. This becomes more respondent Province. Accordingly, the information dissemination
imperative because of the significant contributions of Boracays white- conducted months after the ECC had already been issued was
sand beach to the countrys tourism trade, which requires respondent insufficient to comply with this requirement under the Local
Province to proceed with utmost caution in implementing projects Government Code. Had they been conducted properly, the prior public
within its vicinity. consultation should have considered the ecological or environmental
concerns of the stakeholders and studied measures alternative to the
project, to avoid or minimize adverse environmental impact or environment, lest they kill the proverbial hen that lays the golden egg.
damage. In fact, respondent Province once tried to obtain the favorable At the beginning of this decision, we mentioned that there are common
endorsement of the Sangguniang Bayan of Malay, but this was denied goals of national significance that are very apparent from both the
by the latter. petitioners and the respondents respective pleadings and memoranda.

Moreover, DENR DAO 2003-30 provides: As shown by the above provisions of our laws and rules, the speedy
and smooth resolution of these issues would benefit all the parties.
5.3. ublic Hearing / Consultation Requirements Thus, respondent Provinces cooperation with respondent DENR-EMB
RVI in the Court-mandated review of the proper classification and
For projects under Category A-1, the conduct of public hearing as part environmental impact of the reclamation project is of utmost
of the EIS review is mandatory unless otherwise determined by EMB. importance.
For all other undertakings, a public hearing is not mandatory unless
specifically required by EMB. WHEREFORE, premises considered, the petition is hereby
PARTIALLY GRANTED. The TEPO issued by this Court is hereby
Proponents should initiate public consultations early in order to ensure converted into a writ of continuing mandamus specifically as follows:
that environmentally relevant concerns of stakeholders are taken into
consideration in the EIA study and the formulation of the management 1. Respondent Department of Environment and Natural Resources-
plan. All public consultations and public hearings conducted during Environmental Management Bureau Regional Office VI shall revisit
the EIA process are to be documented. The public hearing/consultation and review the following matters:
Process reportshall be validated by the EMB/EMB RD and shall
constitute part of the records of the EIA process. a. its classification of the reclamation project as a single instead of a
co-located project;
In essence, the above-quoted rule shows that in cases requiring public b. its approval of respondent Provinces classification of the project as a
consultations, the same should be initiated early so that concerns of mere expansion of the existing jetty port in Caticlan, instead of
stakeholders could be taken into consideration in the EIA study. In this classifying it as a new project; and
case, respondent Province had already filed its ECC application before c. the impact of the reclamation project to the environment based on
it met with the local government units of Malay and Caticlan. new, updated, and comprehensive studies, which should forthwith be
ordered by respondent DENR-EMB RVI.
The lack of prior public consultation and approval is not corrected by
the subsequent endorsement of the reclamation project by the 2. Respondent Province of Aklan shall perform the following:
Sangguniang Barangay of Caticlan on February 13, 2012, and the
Sangguniang Bayan of the Municipality of Malay onFebruary 28, a. fully cooperate with respondent DENR-EMB RVI in its review of
2012, which were both undoubtedly achieved at the urging and the reclamation project proposal and submit to the latter the
insistence of respondent Province. As we have established above, the appropriate report and study; and
respective resolutions issued by the LGUs concerned did not render b. secure approvals from local government units and hold proper
this petition moot and academic. consultations with non-governmental organizations and other
stakeholders and sectors concerned as required by Section 27 in
It is clear that both petitioner and respondent Province are interested in relation to Section 26 of the Local Government Code.
the promotion of tourism in Boracay and the protection of the
Respondent Philippine Reclamation Authority shall closely
monitor the submission by respondent Province of the
requirements to be issued by respondent DENR-EMB RVI in
connection to the environmental concerns raised by petitioner, and
shall coordinate with respondent Province in modifying the MOA,
if necessary, based on the findings of respondent DENR-EMB
RVI.

The petitioner Boracay Foundation, Inc. and the respondents The


Province of Aklan, represented by Governor Carlito S. Marquez,
The Philippine Reclamation Authority, and The DENR-EMB
(Region VI) are mandated to submit their respective reports to
this Court regarding their compliance with the requirements set
forth in this Decision no later than three (3) months from the date
of promulgation of this Decision.

In the meantime, the respondents, their concerned contractor/s,


and/or their agents, representatives or persons acting in their
place or stead, shall immediately cease and desist from continuing
the implementation of the project covered by ECC-R6-1003-096-
7100 until further orders from this Court. For this purpose, the
respondents shall report within five (5) days to this Court the
status of the project as of their receipt of this Decision, copy
furnished the petitioner.

Вам также может понравиться