Академический Документы
Профессиональный Документы
Культура Документы
DESIGN BUIL
AB
BANCAY,, APURÍM
MAC, PERÚ.
95% DE
ESIGN STAGE
S
ELECT
TRICAL
L DESIG
GN ANA
ALYSIS
HA
AP # 218
836
US ARMY
A CO
ORPS OF
F ENGINE
EERS
O
ORIGINA
AL
AUGUST, 2018
2
ELECTRICAL DESIGN ANALYSIS NARRATIVE
1. OVERVIEW
1. OVERVIEW
1.2.LOCATION The project site is located next to the Mariño River, in the city of
Abancay– Peru. Abancay is the capital of the Apurimac department, Peru. The city is
located at 13° 38′ 00.00′′ South Latitude and 72° 53′ 00.00′′ West Latitude at an
approximate elevation of 2377 meters above the sea level and has an approximate
population of 120.000 habitants. It has a dry and temperate weather most of the
year with temperatures about 4 and 20oC (39 to 68°F). Abancay is the agricultural
and industrial center of Apurimac’s department; there are also copper mines in the
area.
2. OBJETIVO
The objective of this project is to design medium and low voltage electrical
networks, connection to an existing overhead primary, grounding connection,
panelboard, lighting systems, general and dedicated outlets for specific uses,
stabilized outlets, voice and data telecommunication outlets; configuring in this way
a reliable, safe system for people, easy operation maintenance for the
"CONSTRUCTION OF WAREHOUSES IN THE CENTER OF REGIONAL
EMERGENCY OPERATIONS COER- APURIMAC", complying with the normative
and legal standards.
The project includes the design of Interior and exterior electrical installations for the
CONSTRUCTION OF THE “EMERGENCY OPERATIONS CENTER AND
DISASTER RELIEF WAREHOUSE EOC-DRW ABANCAY,” which is presented
next:
• Independent supply networks, one for the General TG panelboards and the
other for the fire suppression panelboard TF-1. These networks are supplied
from the two-pole mounted transformer substation of 75KVA, 10-22.9KV/0.38-
023KV. This substation shall be exclusively used for the EOC-DRW Abancay.
The project has been developed based on the architecture and respective
equipment drawings.
5. PROJECT DESCRIPTION
For the interior installations, it has been considered everything related to lighting
circuits, average outlet boxes and suppliers to different equipments considered
on the design drawings, including conductors, conduit system and luminaires.
5.3. Emergency Power System
This system has been designed having in consideration the load size of Maximum
Demand and special loads. The system is composed by a Diesel Generator and
an Automatic Transfer Switch (ATS ), which will be supplied in case of energy cut
by the mentioned 60KW/ 75 KVA. Diesel Generator.
This system will function 10 seconds after the average energy supplier system is
suspended and the 75 KVA. Diesel Generator is automatically activated, which
will supply energy to the entire system.
The wiring for the Telecommunications system will be carried by a wire mesh
cable tray and it is derived in EMT pipe to the work station and for the areas with
many work stations the wiring was designed with surface metal raceways.
• Adaptability
It shall allow the future technologies and their developments (e.g. video,
high speed data transmission, voice and multimedia applicative).
• Flexibility
It shall be the same distribution network for every communication
application in order to make it easier the possible displacement of the
system equipment.
• Transparency
• The system shall meet every telephone, data and video standards.
• The distribution of the communication exits (data, voice, audio, video and
other services) in the different levels of the building, control areas,
storage, for an efficient use of the institution resources.
A 500 Lux lighting has been estimated for offices areas. The considered lighting
is normal type and fluorescent T-5 lamps of 14, 28 and 54 watts have been
selected with electronic devices. The considered lighting levels, according to the
norm EM.010 from the National Edifications following:
The energy supply will be three-phase type with a neutral line of 380/220 V., 60
Hz. and shall be supplied from a two-pole mounted transformer substation of
75KVA. Electrical feeder from the General Panelboard TG and the Fire
Suppression Panelboard TF-1, conductors will be NHX-80 and these will be
installed in concrete ducts and/or PVC-P pipes, covered in concrete as it is
indicated on the drawings.
It is necessary to carry out tests to the electrical system, among which are
included Insulation of the conductors, Voltage level at full load, load balancing,
continuity, operation of the power plant and its transfers, measurement of the
earthing resistance. These tests must be carried out with qualified personnel
and the results must comply with the minimum requirements indicated in the
National Electricity Code.
For the project, a grounding system will be designed that will include a
grounding grid for the substation grounding, for the isolated ground system and
for the lightning system. These systems will be joined together. The value of the
ground resistance must not be greater than 25 Ohms, in case of values higher
than the established maximum, it will be necessary to apply artificial soil, to
decrease the value of the grounding resistance. The measurement must be
made in a time greater than two days after the rain has occurred.
Lighting levels tests shall be executed with the use of a lux meter to verify the
proposed lighting levels in plans.
6.4. EMERGENCY LIGHTING OPERATIONAL TEST
Emergency lighting operation tests shall be executed simulating local power
outages. There shall be a one-hour duration battery system according to the
National Edifications Regulation (art. 41 norm. A.130).
Tests shall be executed for the operation of the UPS provided by the user after
doing the maintenance, which means:
1. OVERVIEW
The calculations of current, voltage drop, panelboards schedule are shown in this
numeral and the designs of the Ground System, Lightning and interior and exterior
lighting, with their respective simulation are delivered as annexes.
2. STANDARD REFERENCE
• Código Nacional de Electricidad- Utilización – 2006.
• Reglamento Nacional de Edificaciones- 2006.
• EM.010 del R.N.E-2006
3. RATINGS
• Nominal Voltage : 380V
• Phases :3 + Neutral Conductor
• Frecuencia : 60Hz.
• Frequency : 60Hz.
• Power Factor :0,85
• Diversity Factor : variable
• Spare Capacity :20 %
a) Ampacity Calculation
MDTOTAL
I=
KxVx cos j
Where:
K= 1.73 for Three Phase Circuit
K= 1 For Single Phase Circuit
é rxL ù
LV = KxI ê ú x cos j
ë S û
Donde:
I : Nominal Current
V : Nominal Voltage
MDTOTAL : Peak Demand in Watts.
Cos f : Power Factor, 0.85
DV : Total Drop Voltage, 4% (2.5% + 1.5%) in Volts.
L : Length in m.
r : Specific Resistance or Copper Resistivity Coefficient
: = 0.01785 Ohm-mm2/m.
S : Section in mm2
K : Constant depending of the system type, 1.73 for
Three Phase Circuits, 2 for Single Phase Circuits
The voltage drop calculations results are indicated in the following table.
6. GROUND RESSISTANCE AND LIGHTNING DESIGN
Resistividad (con probabilidad del 70% de no ser superada) es: 263,16 W.m
GRÁFICO DE RESISTIVIDADES
600
RESISTIVIDAD DEL TERRENO Wm
500
400
Sentido N-S
300
Sentido E-O
200 BOX-COX
Promedio
100
0
0 0,5 1 1,5 2 2,5 3 3,5 4 4,5
SEPARACIÓN ENTRE ELECTRODOS (m)
CALCULO RESISTENCIA DE PUESTA A TIERRA SISTEMA GENERAL
PROYECTO:ABANCAY
Tipo:
Conductividad: 97 % respecto al cobre puro
Tipo de Union:
Temp Max de la Union: 450 ºC
Ta: 30 ºC (temperatura ambiente)
Akcmil: 6,15 kcmil
Características mínimas del conductor
Area minima: 3,11 mm2 de tierra
Diámetro mínimo: 0,0020 mm
Conductor de diseño:
área: 33,63 mm2
diámetro: 0,0065 mm
Electrodos Verticales
Resistividad del suelo: 263,16 [Ωm]
Longitud del electrodo: 2,4 [m]
Radio del electrodo: 0,00635 [m]
Separación (D): 0 [m]
R Sistema de electrodos
Building Dimensions
(for a rectangular structure in meters)
Length = 40 m
Width = 35 m
Height = 12,9 m