• The project is estimated to cost Rs.250 million


• As of February 2011, the company has been directed the project prepare a detailed Environmental Management Plan / Environ-
ment Impact Assessment Report and submit the same for Environment Clearance.

Contact Address :Airan Metaliks (P) Limited, Kailash Bhavan, Carona Chowk, Sadar Bazar, Bilaspur - 495001
Ph: 07752- 324830, 324930 Fax: 07752- 401627 E-mail: airansteel@gmail.com

Balmukund Sponge & Iron to expand capacity

Sub Sector :Steel


Project Cost (in Rs.million) 314
Project Capacity :39,000 TPA
Project State :Jharkhand
Current Status :Environment Clearance Awaited

Project Details :

• Balmukund Sponge & Iron is planning to expand its iron plant to 39,000 TPA by installation of Ferro Alloys (10,500 TPA), MS
Ingot / Billets (36,000 TPA) & Sinter (27,000 TPA) at Manjhaladih in Giridih district of Jharkhand.
• The project is estimated to cost Rs.314 million
• As of February 2011, Ministry of Environment and Forests has directed the company to prepare a detailed Environmental Man-
agement Plan / Environment Impact Assessment Report and submit the same to the state pollution control authorities for con-
ducting public hearing.

Contact Address :Balmukund Sponge & Iron Limited, 603, Shanti Kunj Apartment, Chajju Bagh, Patna - 800 001 Ph: 0612-
3294794 E-mail: shreyase@sancharnet.in

Ambika Alloys to expand capacity

Sub Sector :Steel


Project Cost (in Rs.million) 85.6
Project Capacity :24,300 MTPA to 41,400 MTPA
Project State :Himachal Pradesh
Current Status :Environment Clearance Awaited

Project Details :

• Ambika Alloys to expand its Steel manufacturing unit.


• Ambika Alloys is planning to expand its Steel manufacturing unit
• The project involves increasing the capacity of M.S. Ingots 24,300 MTPA to 41,400 MTPA, Structural Steel 23,085 MTPA to
39,600 MTPA) at Kala Amb in Nahan in Sirmour district of Himachal Pradesh.
• The project is estimated to cost Rs.85.6 million
• As of February 2011, the company has been directed the project prepare a detailed Environmental Management Plan / Environ-
ment Impact Assessment Report and submit the same for Environment Clearance.

Contact Address : Ambika Alloys, Plot No. 5, Industrial Area, Village Kala Amb, Tehsil Nahan, District Sirmour - 173 030, Himachal
Pradesh Fax: 01702-238924 E-mail: jainbharathp@rediffmail.com

Surya Vijaynagar Steel & Power Plans New Steel Plant

Sub Sector :Steel


Project Cost (in Rs.million) 31645
Project Capacity :6.0 MTPA
Project State :Karnataka
Current Status :Environment Clearance Awaited

Project Details :

• Surya Vijaynagar Steel & Power is planning to set up a 6.0 MTPA Integrated Steel Plant along with 520 MW CPP at Kirasur,
Magalalli, Kadlimatti, Mudapaljivi, Achanur, Hallur & Bhagavati in Bagalkot district of Karnataka.
• The project is estimated to cost Rs.31645 million