You have the approval on the architecture project, including the following observations:
2. HVAC installations:
i. The connection with counter of the commercial center is not shown on the
plan.
ii. The connection for smoke exhaust and foul air is not shown on the plan, as
it was transmitted to the connection plan.
iii. The connection for the condensation of the heat pump is not shown on the
plan.
iv. The position of the display from Zenner’s counter is not shown on the plan.
This one has to be placed next to the electrical metering one.
v. The thermal counter and the heat pump must be wired for their
integration in the BMS’s commercial center, the cables being left in the
false ceiling, above the advertising, in 2 different batches marked "BMS
PC" and "BMS Thermal Counter" with type JY (St) Y 2x2x0,8 cable.
Thank you,
0722382673