Академический Документы
Профессиональный Документы
Культура Документы
TESIS
INGENIERO DE MINAS
ELABORADO POR:
ASESOR
LIMA-PERU
2015
Para mis padres por su interminable
CAPITULO I: GENERALIDADES
7.1 ANALISIS
7.2MEJORA EN LOS INDICADORES DE PRODUCTIVIDAD
CONCLUSIONES
REFERENCIAS BIBLIOGRAFICAS
LISTA DE TABLAS
mejora de la productividad.
Con el análisis realizado y las alternativas propuestas para la reducción del costo,
From 2011 to the operating cost in Minera Bateas SAC, increased by a 30.7%. A
The increase in the operating cost in 8.9% in 2014 regarding the budget of that year,
The analysis activities would identify the main impacts on the operating cost during
the 2014; being controlled administration that took place by the change of
power generation.
With the analysis and the alternatives proposed for the reduction of the cost, is
proposed to reduce spending operating den US $ 2,200,841 for 2015; which would
INTRODUCCIÓN
La actividad minera enfrenta, desde hace unos años, una situación más que compleja,
estables o en descenso, mientras que los precios de los insumos utilizados para
generarlos, crecen. Esta es una situación que domina la actividad en todo el mundo. Y
que está forzando a las empresas del sector a reformular sus diversos sistemas –
país en los últimos años, ahora se enfrenta a la incertidumbre de no saber lo que pasará
estos tiempos de alta fluctuación del precio de los metales en el mercado, el control
13
Como se mencionó antes, una variable importante es el precio de los metales, el cual
no depende de las empresas mineras; es por tal motivo que como objetivo se busca
2,011 a US $ 43.92/t en el 2,014. Es por ello que este estudio busca realizar un análisis
márgenes de beneficio.
METAS Y OBJETIVOS
Objetivo General
464,100 ton.
14
Objetivos específicos
Bateas.
Adoptar como única forma de pago: T-Km, para el transporte de relave con
volquete.
hidráulico
PROBLEMÁTICA DE INVESTIGACIÓN
A nivel global a pesar de los menores precios de los commodities, los costos siguen en
aumento. Como resultado, los precios de las acciones, los ingresos y las ganancias
sólo la primera vez en mucho tiempo, lo que significa que son pocas las empresas
es ajena a esta realidad, ya que su costo operativo tiene una tendencia a seguir
15
mejoras.
HIPOTESIS
METODOLOGIA DE LA INVESTIGACIÓN
identificar las oportunidades de mejora para luego plantear las alternativas para la
figura 1
CAPITULO I
GENERALIDADES
(31-s).
17
Características Geográficas.
Temperatura : de -14 a 21 ºC
Humedad relativa : de 65 a 75 %
Mina
Bateas
minero
Caylloma de 225 Km. aprox. pasando por el cruce de acceso a la Mina Arcata.
Lima-Arequipa : 1005 Km
Arequipa-Caylloma : 225 Km
Caylloma-Mina : 14 km
El valle es del tipo glacial. Esto se observa fácilmente por la forma del valle en
“U”. La altitud oscila entre los 4500 msnm a los 5000 msnm.
Los pastos naturales están constituidos por gramineasas esencialmente que son
las que confieren alguna utilidad de pastoreo a los sectores de las pampas y
los niveles más bajos del área de la formación ecológica; mientras que en los
1.2.2 Clima
de fuertes granizadas que cubren de nieve toda la zona. Durante los meses de
heladas.
1.3 HISTORIA
Caylloma es una de las minas más antiguas del Perú. Es conocía desde el
incanato y trabajaba casi desde forma continua desde la época Colonial (año
Uno de los periodos más activos, se inició en 1880, cuando un grupo sueco-
cantidad de los clavos mineralizados de alta ley de las vetas. El Toro, San Pedro
y Bateas. Luego se trasladó a la veta San Cristobal, que permitió que las
Después del año 1906, un grupo chilenos se hizo cargo de la mina e instalo una
mina a lo largo de 20 años, siendo la última dirigida por L.J Rosenshine que
instalo una planta de flotación con una capacidad de 30 Tpd en San Ignacio,
Luego la mina fue operada por el Grupo Hoschild a una capacidad de 500 tpd.
22
Inc) inicialmente se trataron 500 tpd, en la actualidad se trata más de 1250 tpd.
23
en el 2007 hasta las 1,350 tpd en el año 2014. Los gráficos siguientes muestran
CAPITULO II
GEOLOGÍA
Las rocas más antiguas aflorando en el área son sedimentitas de edad jurásica, las que
axiales subhorizontales.
La secuencia volcánica está integrada por paquetes de 20 hasta 100 metros de lavas
intercaladas con rocas volcanicoclásticas. Allí, se observan dos tipos de lavas la que
podemos reconocer como: Andesitas porfiríticas y andesitas finas, casi afaníticas con
Las rocas volcanicoclásticas están formadas en su mayoría por brechas matriz sostén,
26
volcánicas porfirícas.
Las rocas volcánicas suelen presentar en la extensión del distrito una alteración
hidrotermal suave caracterizada por una leve propilitización y una piritización dada
volcánica se encuentra intruída por cuerpo dómicos y sus flujos lávicos asociados de
composición ácida. Estos son riolitas que presentan una marcada fluidalidad, con
La fluidalidad está dada por filetes de variada coloración (rojiza y blanca), atribuida a
plagioclasas y piroxenos
28
variable entre decenas y cientos de metros, con una extensión vertical del orden
Las vetas poseen potencias desde 1 hasta 5 metros, con medias en alrededor de
estériles.
mayor ley. Las brechas consisten en clastos angulosos de roca de caja hasta
de las vetas mientras que los estadios más jóvenes se encuentran hacia el centro
de las vetas. Los minerales de ganga principales que forman la mayor parte del
diseminado en la ganga.
rodonita y bandas formadas casi exclusivamente por sulfuros que poseen desde
pulsos es principalmente simétrica, con los estadios más jóvenes ocupando las
volcanoclásticas.
La alteración cuarzo adularia está restringida a los márgenes de las vetas, siendo
En las zonas superiores del sistema la zona de cuarzo-adularia está ausente. Allí
Nota: El presenta capítulo está basado en los informes del área de Geología de
Minera Bateas.
33
CAPITULO III
Las reservas de mineral probadas y probables a Diciembre del 2014 son las que se
detallan a continuación.
34
cuadro siguiente.
35
CAPITULO IV
CAPITULO V
A fin del año del 2014, se realizó un análisis del costo operativo por
5.2.1 Supervisión
empleados del área de Mina, los EPP del personal empleado, el combustible
5.2.2 Preparación
rampas, etc. Para un mejor análisis del costo por metro de avance, se hizo una
compañía.
5.2.3 Explotación
Del cuadro podemos observar que el costo fue mayor en 2.17 US $/t que el
tareas son las actividades que tuvieron mayor incidencia en servicios varios.
son los que tuvieron la mayor incidencia. La siguiente tabla muestra el resumen:
5.2.4 Acarreo
compañía.
mayor gasto. El cuadro siguiente muestra el resumen del costo de acarreo. Para
5.2.5 Sostenimiento
contratistas.
47
sobre gasto menor. El Anexo 4 muestra información para el cálculo del costo
a detalle.
5.2.6 Relleno
transportado por los scooptram hacia los tajos que culminaron su explotación y
el relleno hidráulico que es el relave mas el agua, transportado como una pulpa
muestra el resumen:
50
de relave por ton/Km tuvo un impacto mínimo.El transporte de relave por Horas
5.2.7 Transporte
desde interior mina a tolva de gruesos realizado por los volquetes y dumper.
53
húmedas transportadas.
alimentación.
labores de avance.
54
combustible.
alimentación.
locomotoras.
parrillas.
56
etc.
rodillo, niveladora, cisterna, etc. En servicios varios se gasto mas por mayor
trabajos de servicios que se paga a las ECM y el mayor impacto fue por
materiales.
equipos
adicionales y reintegros.
adicionales y reintegros.
adicionales y reintegros.
60
y reintegros.
5.2.9 Energía
CAPITULO VI
OPORTUNIDADES DE MEJORA
convencional.
relave.
I. Situación
0.75 Yd de capacidad los cuales trasladan el material roto desde el tajo a los
echaderos.
II. Operaciones
mes en preparaciones.
Esta veta se caracteriza por tener dimensiones entre 0.50 a 1.0 m de ancho de
esta actividad.
de 50m.
cual es alimentado por bombeo. Así también el desmonte producto del descaje
o Servicios Auxiliares:
1,200 CFM
del 2,014. Para un mejor análisis se han disgregado los costos en:
sostenimiento explotación.
68
camino y con equipos cautivos. Las dimensiones de block a minar tienen las
de 50m.
de acceso hacia los tajos, por donde circula el personal y los materiales-
siguientes labores:
69
ventanas de acceso, pero incluye 3 chimeneas camino hacia los extremos del
rampas y las ventanas de acceso, pero incluye 3 chimeneas camino hacia los
extremos del tajo para acceso de personal y materiales, así también cabe indicar
que el Ore Pass será llevado dentro del tajo para lo cual deberá emplearse
un costo de US $ 2,300.
I. Costo de Preparación
servicios y GG/CF.
73
de minado, para los 2 primeros métodos se contempla el uso de Split set y malla,
longitudinal
Para el caso del método de minado mecanizado los mayores ciclos de trabajo
de método.
77
Se contaba con 5 parejas para las 14 ‘alas’ programadas, fue necesario contar
con una pareja más. Para el cambio de método a minado convencional con
winche fue necesario completar una pareja para los tajos y 2 parejas adicionales
VIII. Conclusiones
$ 1,355,040 .
ejecución (13 guardias), aparte de producir una doble influencia por voladura
en la misma zona.
IX. Recomendaciones
nuevo método de explotación con winche (tajos 290 y 390 en el nivel 11).
Los tajos 400, 500 y 600 deberán continuar con su método actual hasta
llegar a la cota del Nv-11, debido a que se tienen realizadas las labores de
conveniente trabajar las vetas que tienen potencias menores a 1.4m a través de
bombas marca KSB, modelo WL100, potencia de motor de 100 Hp, la tubería
bombeo del Nivel 9 Interior Mina, cuenta con una bomba Hidrostal modelo 40-
133,000 litros, recibe agua de la Estación del Nivel 9 Interior Mina. La Cámara
de bombeo del Nivel 7 , cuenta con una bomba Hidrostal modelo 40- 250,
25,000 litros, recibe agua de la Estación de bombeo del Nivel 7 Interior Mina,
cuenta con una bomba Hidrostal modelo 65-200, motor de potencia 60 Hp,
actualmente esta estación no cuenta con operador ya que cuenta con una boya
con un tanque de 140,000 litros, recibe agua de la Estación de bombeo del Nivel
5 1/2 Interior Mina, este es el punto final del sistema de bombeo de la Veta
Hidráulico
Objetivos
automáticamente.
apagado automático.
de bombeo.
- Sistema de comunicación.
rotura de la tubería.
una falla.
equipos de comunicación.
comunicación Ethernet Industrial, todas las radios son de uso industrial, para
bajos las normas del estándar de comunicación industrial RS485, para una
manualmente
N° DE BOMBEROS
PU TAREAS TOTAL $ / DIA TOTAL $ / MES
COSTO MANO DE OBRA /TURNO
3 70.87 3.75 532 15,946
PRECIO
DESCRIPCIÓN US$
Servicios 17,700
a. Evaluación de la inversión
b. Conclusiones
c. Recomendaciones
fallas en el sistema.
entre las canchas del Nv.8, Nv.9, tolva de gruesos e interior mina; lo que
producción diaria.
Objetivos.- Reducir los costos por rotura de bancos, eliminando la rotura por
plasteo:
i. Impacto en equipos
gruesos)
propias de la zona.
88
Análisis económico
39,000
b. Resultados
c. Conclusiones
d. Recomendaciones
TRANSPORTE DE RELAVE
que realizan este trabajo y cada una tiene contrato diferente con la minera.
Análisis económico.-
En los últimos seis meses el costo promedio del transporte de relave en la forma
Conclusiones.-
Recomendaciones.-
Reformular las tarifas y la forma de pago por T-Km hacia las empresas
contratistas.
MINA
manual.
operadores.
94
Evitar que el personal este expuesto en una vía con transito continuo de
vehículos y volquetes.
Flujo económico.-
B. Resultados
meses
C. Conclusiones
Al cavo del primer año el VAN será de US $ 119,977 y el TIR en cinco años
será de US $ 760,927.
D. Recomendaciones
A. Relleno detrítico:
preparación y de los batidos de las ventanas, hacia los tajos que entraron
en la etapa de relleno.
$ 10.38/m3.
B. Relleno hidráulico:
15.03 US $ / m3.
Si bien es cierto que se gastaría más en relleno detrítico, este gasto de mas
E. Conclusiones
F. Recomendaciones
relleno.
COMPAÑIA.
El cargador frontal de plata cuenta con operadores para las tres guardias, el
Se plantea que con la contratación de un operador más para mina-de esta forma
año.
diferentes trabajos en mina es de 600 Hr, con los dos operadores de compañía
Conclusiones-
El ahorro anual completando los tres operadores para el cargador frontal de cia
Recomendaciones-
CAPITULO VII
7.1 ANALISIS
Anual
Descripción Real Ahorro Dif Dif%
Supervisión Mina 910,427 - 910,427 0%
Preparación 1,990,201 871,183 1,119,018 44%
Explotación 6,772,931 668,266 6,104,665 10%
Acarreo y Carguío 346,528 16,704 329,824 5%
Sostenimiento 2,626,785 - 2,626,785 0%
Relleno 2,422,453 390,667 2,031,786 16%
Transportes 1,572,816 39,520 1,533,296 3%
Servicios Auxiliares 2,199,543 214,478 1,985,065 10%
Energía 1,185,845 - 1,185,845 0%
Total 20,027,528 2,200,818 17,826,710 11%
convencional:
un 38%.
104
Ratios Ejecutados
Tipo de explosivo Cantidad US $ t Kg/t US $/t
Anfo (Kg) 310,880 287,687 440,938 0.71 0.65
Emulnor (Kg) 60,737 141,597 440,938 0.14 0.32
Accesorios 345,592 440,938 0.78
Total 371,617 774,876 440,938 0.84 1.76
Ratios Proyectados
Tipo de explosivo Cantidad US $ t Kg/t US $/t
Anfo (Kg) 230,573 213,805 440,938 0.52 0.48
Emulnor (Kg) 56,276 130,800 440,938 0.13 0.30
Accesorios 287,480 440,938 0.65
Total 286,848 632,085 440,938 0.65 1.43
menor uso de equipos y mano de obra que requiere los trabajos de plasteo de
relave:
relave es más beneficioso para la empresa, que un pago en base al alquiler por
datos de campo.
Tabla 7.7 Cuadro comparativo del pago por T-Km y el pago por Hr.
Se concluye que el pago por T-Km tiene un mayor rendimiento y eficiencia que
el pago por hora. Se genera un ahorro de 0.38 $/t por cada tonelada de relave
un máximo.
cargador frontal de compañía, de tal forma que este equipo trabaje en todas
109
concepto.
Actual Propuesto
Descripción
US $ Hr $/Hr US $ Hr $/Hr
Costo alquiler ECM 16,704 249 67.08 8,242 123 67.01
Costo equipos Cía 18,441 351 52.54 25,584 477 53.64
Total 35,145 600 58.58 33,826 600 56.38
$16,704.
110
CONCLUSIONES
cabo de un año. A los cinco años el VAN será de US $ 466,536 y el TIR 588%.
tendría un VAN de US $ 119, 977 al primer año. En Los próximos cinco años
390,667 al año.
REFERENCIAS BIBLIOGRAFICAS
2006.
NOMENCLATURA
CH: Chimenea
D2: Petróleo
T-Km: Tonelada-Kilometro
Total 16,142 17.03 274,943 Total 14,400 16.49 237,509 37,434 15,343 -6,645 28,736
Los +1,742 m3 impactan x PU $+15,343; por Cantidad $-6,645 y por efecto MIX $+28,736.
Adicionales/Reintegros/Descuentos
Ejecutado Programado
Dif($)
Descripción Glb PU Total ($) Descripción Glb PU Total $
Alimentación $ 1,292 1 1,292 Alimentación $ 219.5 1 219 1,073
Camioneta $ 1 0 Camioneta $ 216.9 1 217 -217
Servicios Subreparto $ 3,373 1 3,373 Servicios Subreparto $ 0 0 3,373
Flete $ 16,932 1 16,932 Flete $ 0 16,932
Contingencia presupuesto $ 1 0 Contingencia presupuesto 367 1 367 -367
Servicios médicos $ 115 1 115 Servicios médicos $ 17 1 17 97
Serv Mantto $ 6,405 1 6,405 Serv Mantto $ 396 1 396 6,009
Demora desmovilización(Carta 1 635 1 635 Demora desmovilización(Carta 193-GG-13) $ 0 635
Traslado de materiales(Carta 193 78 1 78 Traslado de materiales(Carta 193-GG-13) $ 0 78
Reint x equipos(Carta 193-GG-13 3,963 1 3,963 Reint x equipos(Carta 193-GG-13) $ 0 3,963
Reint(DM,Paternidad,Alimentac 10,123 1 10,123 Reint(DM,Paternidad,Alimentación) $ 0 10,123
Reint. X Cargador de ANFO $ 3,278 1 3,278 Reint. X Cargador de ANFO $ 0 3,278
Reint x Manguera antiestatica 262 1 262 Reint x Manguera antiestatica 262
Ampliación labores x mixer $ 7,953 1 7,953 Ampliación labores x mixer $ 0 7,953
Reint. X incremento Chimenero s 1,048 1 1,048 Reint. X incremento Chimeneros $ 0 1,048
Reint x Dif PU CONGEMIN $ 5,614 1 5,614 Reint x Dif PU CONGEMIN $ 0 5,614
Reint x Dif PU MCEISA $ 24,788 1 24,788 Reint x Dif PU MCEISA $ 0 24,788
Reint x improductivos $ 10,498 1 10,498 Reint x improductivos $ 0 10,498
Retribución extraordinaría $ 24,203 1 24,203 Retribución extraordinaría 14,255 1 14,255 9,947
Reint x movilización (CONGEMIN 5,372 1 5,372 Reint x movilización (CONGEMIN) $ 0 5,372
Reint varios $ 107 1 107 Reint varios $ 0 107
Dscto x TC $ -1,730 1 -1,730 Dscto x TC $ 0 -1,730
Dscto. Jumbo Cía $ -28,634 1 -28,634 Dscto. Jumbo Cía $ 0 -28,634
Dscto. Scoop Cía $ -5,720 1 -5,720 Dscto. Scoop Cía $ 0 -5,720
Dscto CF+GG $ -11,908 1 -11,908 Dscto CF+GG $ 0 -11,908
Dscto x reparación jumbo cía $ -904 1 -904 Dscto x reparación jumbo cía $ 0 -904
Dscto x aceros $ -967 1 -967 Dscto x aceros $ 0 -967
Dscto.X Mat. entregados $ -426 1 -426 Dscto.X Mat. entregados $ 0 -426
Dscto x Dif precio de materiales -3,331 1 -3,331 Dscto x Dif precio de materiales $ 0 -3,331
Total $ 72,418 Total 15,473 56,946
Servicios Varios Ejecut. Program. Dif ($)
Inst. alcayatas $ 11,458 14,953 -3,494
Inst.Barrera $ 5,259 9,967 -4,708
Puntal de linea $(**) 3,216 0 3,216
Alquiler bomba $ 692 0 692
Tareas Operación $ 6,034 4,856 1,178
Tareas Operador Scoop $(*) 9,686 0 9,686
Alquiler de Scoop $ 11,348 0 11,348
Dumper 23.22 0 23
Inst. malla $ 505 0 505
Plataforma $(**) 532 0 532
Parrilla $(**) 378 0 378
Escalera y descanso $(**) 2,229 0 2,229
Guardacabeza 283 0 283
Inst. pie perforado 2,856 0 2,856
Ranfla 1419.88 0 1,420
Entablado $(**) 7,771 0 7,771
Total $ 63,691 29,775 33,915
Anexo Nº 2
Las -23,162 tms impactan x PU US $+558,181; por cantidad US $-252,446 y por efecto MIX US $-5,864.
Adicionales/Reintegros y Descuentos
Ejecutado Programado
Dif ($)
Descripción Cant. PU Total $ Descripción Cant. PU Total $
Alimentación mina $ 9686 1 9,686 Alimentación mina $ 174 1 174 9,513
Camioneta $ 1 0 Camioneta $ 172 1 172 -172
Servicios medicos $ 765 1 765 Servicios medicos $ 14 1 14 751
Contingencia Presupuesto $ 1 0 Contingencia Presupuesto $ 1748 1 1,748 -1,748
Servicio Equipos Cía $ 33415 1 33,415 Servicio Equipos Cía $ 1 0 33,415
Servicios Subreparto $ 19001 1 19,001 Servicios Subreparto $ 2233.944 1 2,234 16,767
Alq. Vehículo (Carta 193-GG-13)$ 357 1 357 Alq. Vehículo (Carta 193-GG-13)$ 0 357
Demora desmovilización(Carta 193-GG-13)$ 2912 1 2,912 Demora desmovilización(Carta 193-GG-13)$ 0 2,912
Pago x horas equipo(Carta 193-GG-13)$ 18178 1 18,178 Pago x horas equipo(Carta 193-GG-13)$ 0 18,178
Reint (DM, AM,Alimentación)$ 7764 1 7,764 Reint (DM, AM,Alimentación)$ 0 7,764
Improductivos $ 4755 1 4,755 Improductivos $ 0 4,755
Instalación y desintalación servicios batidos $ 2197 1 2,197 Instalación y desintalación servicios batidos $ 0 2,197
Movilización (CONGEMIN) $ 5688 1 5,688 Movilización (CONGEMIN) $ 0 5,688
Cuadrilla shotcrete $ 2140 1 2,140 Cuadrilla shotcrete $ 0 2,140
Personal productividad $ 2943 1 2,943 Personal productividad $ 0 2,943
Reint x Cargador Anfo $ 3278 1 3,278 Reint x Cargador Anfo $ 0 3,278
Reint x Manguera antiestatica 611 1 611 Reint x Manguera antiestatica 611
Flete $ 50,498 1 50,498 Flete $ 0 50,498
Estudio Vibraciones $ 19,500 1 19,500 Estudio Vibraciones $ 0 19,500
Bono extraordinarío $ 60,073 1 60,073 Bono extraordinarío $ 54,380 1 54,380 5,693
Desmovilización $ 7,800 1 7,800 Desmovilización $ 0 7,800
Camion utilitario $ 10,007 1 10,007 Camion utilitario $ 0 10,007
Otros servicios $ 250 1 250 Otros servicios $ 0 250
Reint x Dif PU (CONGEMIN) $ 77,190 1 77,190 Reint x Dif PU (CONGEMIN) $ 0 77,190
Reint x elecciones $ 2,341 1 2,341 Reint x elecciones $ 0 2,341
Reint x GG+CF $ 1,343 1 1,343 Reint x GG+CF $ 0 1,343
Dscto x medidores de GAS(CONGEMIN) $ -1,357 1 -1,357 Dscto x medidores de GAS(CONGEMIN) $ 0 -1,357
Dscto X Dif precio de materiales $ -17,022 1 -17,022 Dscto X Dif precio de materiales $ 0 -17,022
Dscto x aceros $ -6,343 1 -6,343 Dscto x aceros $ 0 -6,343
Dscto x herramientas $ -878 1 -878 Dscto x herramientas $ 0 -878
Dscto x Raparación jumbo $ -5,770 1 -5,770 Dscto x Raparación jumbo $ 0 -5,770
Dscto TC $ -28,470 1 -28,470 Dscto TC $ 0 -28,470
Dscto. Alq. jumbo Cía $ -34,696 1 -34,696 Dscto. Alq. jumbo Cía $ 0 -34,696
Dscto x Rev. CF+GG $ -44,721 1 -44,721 Dscto x Rev. CF+GG $ 0 -44,721
Dscto alq. Scoop cía $ -54,434 1 -54,434 Dscto alq. Scoop cía $ 0 -54,434
Total 149,000 Total 58,721 90,279
Adicionales/Reintegros/Descuentos
Ejecutado Programado
Dif ($)
Descripción Cantidad PU Total $ Descripción Glb PU Total $
Conting. Presto. $ 1 0 Conting. Presto. $ 1011 1 1011 -1,011
Alimentación $ 1774.06 1 1,774 Alimentación $ 1447 1 1447 328
Alq. Camioneta $ 1 0 Alq. Camioneta $ 1461 1 1461 -1,461
Servicios médicos $ 117.31 1 117 Servicios médicos $ 117 1 117 -0
Mantto. Reparación $ 13107.4 1 13,107 Mantto. Reparación $ 3338 1 3338 9,769
Servicios subreparto $ 11,064 1 11,064 Servicios subreparto $ 0 0 11,064
Retibución extraordinaría $ 1,060 1 1,060 Retibución extraordinaría $ 65 1 65 995
Movilización equipos (CONGEMIN) $ 16,598 1 16,598 Movilización equipos (CONGEMIN) $ 0 16,598
Reintegros varios CIS $ 11,623 1 11,623 Reintegros varios CIS $ 0 11,623
Pago x Carta 193-GG-13 $ 628 1 628 Pago x Carta 193-GG-13 $ 0 628
Otros reintegros $ 159 1 159 Otros reintegros $ 0 159
Reint x Dif PU $ 1,800 1 1,800 Reint x Dif PU $ 0 1,800
Dumper $ 584 1 584 Dumper $ 0 584
Transnel 931 1 931 Transnel 0 931
Volquete $ 157 1 157 Volquete $ 0 157
Dscto x TC $ -22 1 -22 Dscto x TC $ 0 -22
Dscto x Dif precio materiales $ -205 1 -205 Dscto x Dif precio materiales $ 0 -205
Dscto CF y GG $ -585 1 -585 Dscto CF y GG $ 0 0 -585
Dscto. Scoop Cía $ (*) -48,551 1 -48,551 Dscto. Scoop Cía $ (*) 1 0 -48,551
Total 10,241 Total 7,439 2,802
Anexo Nº4
Los-645 pernos impacta x PU $-15,112, por cantidad en $-14,658 y por efecto MIX $+16,176.
Shotcrete Preparación
Ejecutado Programado Efectos al Detalle (US$)
MES Dif ($)
Descripción m2 ($/m2) Total ($) Descripción ($/m2) Total ($) PU Cantidad Efecto MIX
ENE Shotcrete Vía seca 2" 371 21.04 7,802 Shotcrete Vía seca 2" 39.16 11,356 -3,554 -5,255 3,165 -1,464
FEB Shotcrete Vía seca 2"(CONGEMIN) 269.21 41.07 11,056 Shotcrete Vía seca 2" 39.16 18,993 -7,936 926 -8,450 -412
MAR Shotcrete Vía seca 2"(CONGEMIN) 662 41.07 27,178 Shotcrete Vía seca 2" 39.16 20,676 6,501 1,008 5,237 255
MAR Shotcrete Vía Humeda (Supermix) 165.76 41.40 6,863 6,863 0 6,491 372
ABR Shotcrete Vía seca 2"(CONGEMIN) 118.08 41.07 4,850 Shotcrete Vía seca 2" 39.16 26,276 -21,427 1,282 -21,652 -1,056
ABR Shotcrete Vía Humeda (Supermix) 346.32 35.49 12,292 12,292 0 13,562 -1,270
MAY Shotcrete Vía seca 2" 0 Shotcrete Vía seca 2" 39.16 24,984 -24,984 -24,984 0
MAY Shotcrete Vía Humeda (Supermix) 1166.12 34.20 39,881 39,881 0 45,665 -5,784
JUN Shotcrete Vía seca 2" 0 Shotcrete Vía seca 2" 39.16 26,081 -26,081 -26,081 0
JUN Shotcrete Vía Humeda (Supermix) 663.04 35.58 23,592 23,592 0 25,965 -2,373
JUL Shotcrete Vía seca 2" 0 Shotcrete Vía seca 2" 39.16 20,676 -20,676 -20,676 0
JUL Shotcrete Vía Humeda (Supermix) 728.16 33.84 24,644 24,644 0 28,515 -3,871
AGO Shotcrete Vía seca 2" 0 Shotcrete Vía seca 2" 39.16 24,867 -24,867 -24,867 0
AGO Shotcrete Vía Humeda (Supermix) 36 30.43 1,081 1,081 0 1,391 -310
AGO Shotcrete Vía Humeda (Supermix) 1,125 35.03 39,402 39,402 0 44,047 -4,645
SET Shotcrete Vía seca 2" 0 Shotcrete Vía seca 2" 39.16 18,053 -18,053 -18,053 0
SET Shotcrete Vía Humeda (Supermix) 355.2 30.43 10,808 10,808 0 13,910 -3,101
SET Shotcrete Vía Humeda (Supermix) 467.7 32.62 15,254 15,254 0 18,314 -3,060
OCT Shotcrete Vía seca 2" 0 Shotcrete Vía seca 2" 39.16 15,037 -15,037 -15,037 0
OCT Shotcrete Vía Humeda (Supermix) 918 31.99 29,352 29,352 0 35,933 -6,582
NOV Shotcrete Vía seca 2" 0 Shotcrete Vía seca 2" 39.16 6,775 -6,775 -6,775 0
NOV Shotcrete Vía Humeda (Supermix) 1,131 32.01 36,194 36,194 0 44,279 -8,085
DIC Shotcrete Vía seca 2" 0 Shotcrete Vía seca 2" 39.16 8,067 -8,067 -8,067 0
DIC Shotcrete Vía Humeda (Supermix) 675 36.83 24,856 24,856 0 26,428 -1,572
Total 9,196 34.27 315,104 Total 39.16 221,841 93,263 -2,038 138,260 -42,959
Los +3,530 m2 impacta x PU-2,038; por cantidad en $+138,260 y por efecto MIX $-42,959.
(*) Ratio en explotación 11.84 m2/m3 fuente Geomecanica
Enmaderado Explotación
Ejecutado Programado Efectos al Detalle (US$)
MES Dif ($)
Descripción Und ($/Und) Total ($) Descripción ($/Und) Total ($) PU Cantidad Efecto MIX
ENE Plantillas BA (ETRAMIN) 222 4.41 979 Plantillas BA 3.13 413 566 169 534 -137
ENE Plantillas AN (CIS) 277 3.13 867 Plantillas AN 3.13 1,158 -291 0 -552 261
ENE Puntal BA (ETRAMIN) 150 27.93 4,190 Puntal BA 19.08 1,526 2,663 708 416 1,539
ENE Puntal AN (CIS) 0 Puntal AN 19.08 363 -363 -113 -250
ENE Guardacabeza AN (CIS) 0 Guardacabeza AN 47.70 143 -143 -18 -125
ENE Guardacabeza BA (ETRAMIN) 2 69.47 139 Guardacabeza BA 47.70 239 -100 109 -18 -191
FEB Plantillas BA (ETRAMIN) 181 4.41 798 Plantillas BA 3.13 410 388 168 297 -76
FEB Plantillas AN (CONGEMIN) 249 3.34 832 Plantillas AN 3.13 1,086 -254 73 -582 255
FEB Puntal BA (ETRAMIN) 154 27.93 4,301 Puntal BA 19.08 1,526 2,775 708 439 1,627
FEB Puntal AN (CONGEMIN) 29 20.30 589 Puntal AN 19.08 363 226 23 59 144
FEB Guardacabeza AN (CONGEMIN) 5 50.76 254 Guardacabeza AN 47.70 143 111 9 12 90
FEB Guardacabeza BA (ETRAMIN) 18 69.47 1,250 Guardacabeza BA 47.70 239 1,012 109 77 826
MAR Plantillas BA (ETRAMIN) 31 4.41 137 Plantillas BA 3.13 610 -474 250 -974 251
MAR Plantillas AN (CONGEMIN) 154 3.34 514 Plantillas AN 3.13 1,243 -728 83 -1,443 631
MAR Puntal BA (ETRAMIN) 138 27.93 3,854 Puntal BA 19.08 1,240 2,614 575 433 1,605
MAR Puntal AN (CONGEMIN) 16 20.30 325 Puntal AN 19.08 363 -38 23 -18 -43
MAR Guardacabeza AN (CONGEMIN) 50.76 0 Guardacabeza AN 47.70 143 -143 -18 -125
MAR Guardacabeza BA (ETRAMIN) 4 69.47 278 Guardacabeza BA 47.70 239 39 109 -6 -64
ABR Plantillas BA (ETRAMIN) 55 4.41 243 Plantillas BA 3.13 613 -371 251 -837 215
ABR Plantillas AN (CONGEMIN) 252 3.34 842 Plantillas AN 3.13 1,070 -229 72 -534 234
ABR Puntal BA (ETRAMIN) 138 27.93 3,854 Puntal BA 19.08 1,317 2,538 611 410 1,517
ABR Puntal AN (CONGEMIN) 1 20.30 20 Puntal AN 19.08 363 -342 23 -107 -259
ABR Puntal Linea BA (ETRAMIN) 14 55.57 778 778 0 83 695
ABR Guardacabeza AN (CONGEMIN) 50.76 0 Guardacabeza AN 47.70 143 -143 -18 -125
ABR Guardacabeza BA (ETRAMIN) 7 69.47 486 Guardacabeza BA 47.70 239 248 109 12 127
MAY Plantillas BA (ETRAMIN) 54 4.41 238 Plantillas BA 3.13 639 -400 261 -891 229
MAY Plantillas AN (CONGEMIN) 208 3.34 695 Plantillas AN 3.13 1,321 -626 89 -1,271 556
MAY Puntal BA (ETRAMIN) 82 27.93 2,290 Puntal BA 19.08 1,507 783 699 18 66
MAY Puntal AN (CONGEMIN) 9 20.30 183 Puntal AN 19.08 363 -180 23 -59 -144
MAY Guardacabeza AN (CONGEMIN) 50.76 0 Guardacabeza AN 47.70 143 -143 -18 -125
MAY Guardacabeza BA (ETRAMIN) 8.5 69.47 590 Guardacabeza BA 47.70 239 352 109 21 222
JUN Plantillas BA (ETRAMIN) 111 4.41 490 Plantillas BA 3.13 629 -140 257 -534 137
JUN Plantillas AN (CONGEMIN) 253 3.34 845 Plantillas AN 3.13 1,230 -385 83 -831 364
JUN Puntal BA (ETRAMIN) 88 27.93 2,458 Puntal BA 19.08 1,393 1,065 646 89 330
JUN Puntal AN (CONGEMIN) 20.30 0 Puntal AN 19.08 420 -420 -131 -289
JUN Guardacabeza AN (CONGEMIN) 50.76 0 Guardacabeza AN 47.70 191 -191 -24 -167
JUN Guardacabeza BA (ETRAMIN) 6 69.47 417 Guardacabeza BA 47.70 239 178 109 6 64
JUL Plantillas BA (ETRAMIN) 76 4.41 335 Plantillas BA 3.13 604 -269 247 -695 179
JUL Plantillas AN (CONGEMIN) 268 3.12 836 Plantillas AN 3.13 1,239 -403 -4 -760 361
JUL Puntal BA (ETRAMIN) 137 27.93 3,826 Puntal BA 19.08 1,412 2,414 655 374 1,386
JUL Puntal AN (CONGEMIN) 20.30 0 Puntal AN 19.08 363 -363 -113 -250
JUL Guardacabeza AN (CONGEMIN) 50.76 0 Guardacabeza AN 47.70 191 -191 -24 -167
JUL Guardacabeza BA (ETRAMIN) 17 69.47 1,181 Guardacabeza BA 47.70 239 942 109 71 762
AGO Plantillas BA (ETRAMIN) 192 4.41 847 Plantillas BA 3.13 563 283 230 71 -18
AGO Plantillas AN (MCEISA) 335.00 3.49 1,169 Plantillas AN 3.13 1,415 -246 163 -695 286
AGO Puntal BA (ETRAMIN) 101 27.93 2,821 Puntal BA 19.08 1,317 1,504 611 190 704
AGO Puntal AN (MCEISA) 11 20.44 225 Puntal AN 19.08 420 -195 30 -65 -160
AGO Guardacabeza AN (MCEISA) 0 Guardacabeza AN 47.70 191 -191 -24 -167
AGO Guardacabeza BA (ETRAMIN) 15 69.47 1,042 Guardacabeza BA 47.70 239 804 109 59 635
SET Plantillas BA (ETRAMIN) 171 4.41 754 Plantillas BA 3.13 548 206 224 -24 6
SET Plantillas AN (MCEISA) 301 3.49 1,050 Plantillas AN 3.13 1,202 -151 138 -493 203
SET Puntal BA (ETRAMIN) 138 27.93 3,854 Puntal BA 19.08 1,393 2,462 646 386 1,429
SET Puntal AN (MCEISA) 20.44 0 Puntal AN 19.08 439 -439 -137 -302
SET Guardacabeza AN (MCEISA) 0 Guardacabeza AN 47.70 191 -191 -24 -167
SET Guardacabeza BA (ETRAMIN) 8 69.47 556 Guardacabeza BA 47.70 239 317 109 18 191
OCT Plantillas BA (ETRAMIN) 137 4.41 604 Plantillas BA 3.13 513 91 210 -160 41
OCT Plantillas AN (MCEISA) 325 3.49 1,134 Plantillas AN 3.13 1,180 -46 136 -309 127
OCT Puntal BA (ETRAMIN) 81 27.93 2,262 Puntal BA 19.08 1,336 927 620 65 242
OCT Puntal AN (MCEISA) 20.44 0 Puntal AN 19.08 420 -420 -131 -289
OCT Guardacabeza AN (MCEISA) 0 Guardacabeza AN 47.70 191 -191 -24 -167
OCT Guardacabeza BA (ETRAMIN) 31 69.47 2,154 Guardacabeza BA 47.70 239 1,915 109 154 1,652
OCT Cuadro BA (ETRAMIN) 4 217.70 871 871 0 24 847
NOV Plantillas BA (ETRAMIN) 112 4.41 494 Plantillas BA 3.13 501 -7 205 -285 73
NOV Plantillas AN (MCEISA) 397 3.49 1,386 Plantillas AN 3.13 1,283 102 148 -77 32
NOV Puntal BA (ETRAMIN) 85 27.93 2,374 Puntal BA 19.08 1,355 1,019 628 83 308
NOV Puntal AN (MCEISA) 0 Puntal AN 19.08 363 -363 -113 -250
NOV Guardacabeza AN (MCEISA) 0 Guardacabeza AN 47.70 191 -191 -24 -167
NOV Guardacabeza BA (ETRAMIN) 21 69.47 1,459 Guardacabeza BA 47.70 239 1,220 109 95 1,017
NOV Cribing BA (ETRAMIN) 12 34.73 417 0 417 0 71 346
DIC Plantillas BA (ETRAMIN) 167 4.41 736 Plantillas BA 3.13 541 195 221 -36 9
DIC Plantillas AN (MCEISA) 165 3.49 576 Plantillas AN 3.13 1,208 -632 139 -1,312 541
DIC Puntal BA (ETRAMIN) 118 27.93 3,296 Puntal BA 19.08 1,412 1,884 655 261 968
DIC Puntal AN (MCEISA) 6 20.44 123 Puntal AN 19.08 363 -240 26 -77 -189
DIC Guardacabeza AN (MCEISA) 0 Guardacabeza AN 47.70 191 -191 -24 -167
DIC Guardacabeza BA (ETRAMIN) 31 69.47 2,154 Guardacabeza BA 47.70 286 1,867 131 148 1,588
Total 6,379 11.33 72,271 Total 5.94 47,514 24,757 13,059 -9,640 21,338
Los -1,624 elementos de sostenimiento impacta x PU en $+13,059; por cantidad $-9,640 y por efecto MIX $+21,338.
Empernado Explotación
MES
Ejecutado Programado
Dif ($)
Efectos al Detalle (US$)
Descripción Und ($/Und) Total ($) Descripción ($/Und) Total ($) PU Cantidad Efecto MIX
ENE Split set 4' BA ( ETRAMIN ) 234 28.95 6,774 Split set 4' BA 18.59 3,718 3,056 2,072 925 59
ENE Split set 5' BA ( ETAMIN ) 228 34.12 7,779 Split set 5' BA 21.7 2,170 5,609 1,242 3,483 885
ENE Split set 5' AN ( CIS ) 91 11.09 1,009 Split set 5' AN 21.7 3,103 -2,094 -1,517 -1,415 838
ENE Split set 7' AN ( CIS ) 668 12.5 8,350 Split set 7' AN 26.13 17,246 -8,896 -8,996 218 -118
ENE Split set AN 10' (CIS) 5 20.17 101 Split set 10' AN 38.3 421 -320 -199 -163 42
ENE Hidrabolt 5' 0 Hidrabolt 5' BA 30.84 432 -432 -381 -51
ENE Hidrabolt 5' AN (CIS) 28 11.28 316 Hidrabolt 5' AN 30.84 524 -208 -333 299 -175
ENE Hidrabolt 7' AN (CIS) 512 14.05 7,194 Hidrabolt 7 ' AN 39.95 17,099 -9,905 -11,085 2,286 -1,105
ENE Hidrabolt 10' AN (CIS) 4 17.55 70 Hidrabolt 10' AN 55.42 111 -41 -76 54 -19
ENE Helicoidal 7' AN (CIS) 37 13.22 489 489 0 1,007 -518
ENE Malla BA ( ETRAMIN) 104.92 25.35 2,660 Malla BA 16.95 1,407 1,253 697 596 -41
ENE Malla AN (CIS) 3.6 10.27 37 Malla AN 16.95 356 -319 -140 -473 295
FEB Split set 4' BA ( ETRAMIN ) 192 28.95 5,558 Split set 4' BA 18.59 3,755 1,803 2,093 -272 -17
FEB Split set 5' BA ( ETAMIN ) 165 32.64 5,386 Split set 5' BA 21.7 2,148 3,237 1,083 1,796 358
FEB Split set 5' AN ( CONGEMIN ) 246 22.13 5,444 Split set 5' AN 21.7 2,995 2,449 59 2,939 -549
FEB Split set 7' AN ( CONGEMIN ) 613 26.6 16,306 Split set 7' AN 26.13 16,384 -78 295 -381 9
FEB Split set AN 10' (CONGEMIN) 0 Split set 10' AN 38.3 383 -383 -272 -111
FEB Hidrabolt 5' 0 Hidrabolt 5' BA 30.84 432 -432 -381 -51
FEB Hidrabolt 5' AN (CONGEMIN) 0 Hidrabolt 5' AN 30.84 493 -493 -435 -58
FEB Hidrabolt 7' AN (CONGEMIN) 497 41.66 20,705 Hidrabolt 7 ' AN 39.95 16,220 4,485 694 2,476 1,315
FEB Hidrabolt 10' AN (CONGEMIN) 0 Hidrabolt 10' AN 55.42 111 -111 -54 -56
FEB Malla BA ( ETRAMIN) 48.6 25.36 1,232 Malla BA 16.95 1,407 -174 698 -936 64
FEB Malla AN (CONGEMIN) 12.8 17.96 230 Malla AN 16.95 339 -109 20 -196 67
MAR Split set 4' BA ( ETRAMIN ) 192 28.95 5,558 Split set 4' BA 18.59 3,960 1,599 2,207 -571 -37
MAR Split set 5' BA ( ETAMIN ) 14 32.64 457 Split set 5' BA 21.7 3,949 -3,492 1,991 -4,571 -912
MAR Split set 5' AN ( CONGEMIN ) 394 22.13 8,719 Split set 5' AN 21.7 3,277 5,443 65 6,612 -1,234
MAR Split set 7' AN ( CONGEMIN ) 663 26.6 17,636 Split set 7' AN 26.13 19,127 -1,491 344 -1,877 42
MAR Split set AN 10' (CONGEMIN) 0 Split set 10' AN 38.3 421 -421 -299 -122
MAR Hidrabolt 5' 0 Hidrabolt 5' BA 30.84 802 -802 -707 -94
MAR Hidrabolt 5' AN (CONGEMIN) 0 Hidrabolt 5' AN 30.84 524 -524 -463 -62
MAR Hidrabolt 7' AN (CONGEMIN) 459 41.66 19,122 Hidrabolt 7 ' AN 39.95 18,337 785 785 0 0
MAR Hidrabolt 10' AN (CONGEMIN) 7 63.35 443 Hidrabolt 10' AN 55.42 111 333 16 136 181
MAR Malla BA ( ETRAMIN) 44.4 25.36 1,126 Malla BA 16.95 2,729 -1,603 1,354 -3,173 216
MAR Malla AN (CONGEMIN) 20 17.96 359 Malla AN 16.95 356 3 21 -27 9
ABR Split set 4' BA ( ETRAMIN ) 181 28.95 5,240 Split set 4' BA 18.59 3,811 1,429 2,124 -653 -42
ABR Split set 5' BA ( ETAMIN ) 35 32.64 1,142 Split set 5' BA 21.7 3,971 -2,829 2,002 -4,027 -804
ABR Split set 5' AN ( CONGEMIN ) 282 22.13 6,241 Split set 5' AN 21.7 3,277 2,964 65 3,564 -665
ABR Split set 7' AN ( CONGEMIN ) 441 26.6 11,731 Split set 7' AN 26.13 16,671 -4,940 300 -5,360 120
ABR Split set AN 10' (CONGEMIN) 0 Split set 10' AN 38.3 383 -383 -272 -111
ABR Hidrabolt 5' 0 Hidrabolt 5' BA 30.84 802 -802 -707 -94
ABR Hidrabolt 5' AN (CONGEMIN) 7 34.56 242 Hidrabolt 5' AN 30.84 524 -282 63 -272 -74
ABR Hidrabolt 7' AN (CONGEMIN) 395 41.66 16,456 Hidrabolt 7 ' AN 39.95 15,660 795 670 82 43
ABR Hidrabolt 10' AN (CONGEMIN) 3 63.35 190 Hidrabolt 10' AN 55.42 111 79 16 27 36
ABR Malla BA ( ETRAMIN) 24.25 25.36 615 Malla BA 16.95 2,729 -2,114 1,354 -3,721 253
ABR Malla AN (CONGEMIN) 17.96 0 Malla AN 16.95 373 -373 -599 226
MAY Split set 4' BA ( ETRAMIN ) 185 28.95 5,356 Split set 4' BA 18.59 3,792 1,563 2,113 -517 -33
MAY Split set 5' BA ( ETAMIN ) 123 32.64 4,015 Split set 5' BA 21.7 4,362 -347 2,199 -2,122 -424
MAY Split set 5' AN ( CONGEMIN ) 41 22.13 907 Split set 5' AN 21.7 3,798 -2,890 75 -3,646 681
MAY Split set 7' AN ( CONGEMIN ) 871 26.6 23,169 Split set 7' AN 26.13 19,075 4,094 343 3,836 -86
MAY Split set AN 10' (CONGEMIN) 0 Split set 10' AN 38.3 460 -460 -327 -133
MAY Hidrabolt 5' 0 Hidrabolt 5' BA 30.84 864 -864 -762 -102
MAY Hidrabolt 5' AN (CONGEMIN) 9 34.56 311 Hidrabolt 5' AN 30.84 617 -306 74 -299 -81
MAY Hidrabolt 7' AN (CONGEMIN) 327 41.66 13,623 Hidrabolt 7 ' AN 39.95 19,815 -6,192 848 -4,598 -2,442
MAY Hidrabolt 10' AN (CONGEMIN) 63.35 0 Hidrabolt 10' AN 55.42 111 -111 -54 -56
MAY Malla BA ( ETRAMIN) 25.36 0 Malla BA 16.95 2,898 -2,898 -4,653 1,754
MAY Malla AN (CONGEMIN) 17.96 0 Malla AN 16.95 339 -339 -544 205
JUN Split set 4' BA ( ETRAMIN ) 254 28.95 7,353 Split set 4' BA 18.59 3,941 3,412 2,196 1,143 73
JUN Split set 5' BA ( ETAMIN ) 185 32.64 6,038 Split set 5' BA 21.7 4,340 1,698 2,188 -408 -81
JUN Split set 5' AN ( CONGEMIN ) 148 22.13 3,275 Split set 5' AN 21.7 4,297 -1,021 85 -1,360 254
JUN Split set 7' AN ( CONGEMIN ) 635 26.6 16,891 Split set 7' AN 26.13 18,605 -1,714 335 -2,095 47
JUN Split set AN 10' (CONGEMIN) 0 Split set 10' AN 38.3 460 -460 -327 -133
JUN Hidrabolt 5' 0 Hidrabolt 5' BA 30.84 894 -894 -789 -105
JUN Hidrabolt 5' AN (CONGEMIN) 18 34.56 622 Hidrabolt 5' AN 30.84 586 36 71 -27 -7
JUN Hidrabolt 7' AN (CONGEMIN) 335 41.66 13,956 Hidrabolt 7 ' AN 39.95 18,137 -4,181 776 -3,238 -1,720
JUN Hidrabolt 10' AN (CONGEMIN) 63.35 0 Hidrabolt 10' AN 55.42 111 -111 -54 -56
JUN Malla BA ( ETRAMIN) 23.4 25.36 593 Malla BA 16.95 2,898 -2,305 1,438 -4,016 273
JUN Malla AN (CONGEMIN) 21.2 17.96 381 Malla AN 16.95 373 8 22 -22 7
JUL Split set 4' BA ( ETRAMIN ) 477 28.95 13,809 Split set 4' BA 18.59 3,960 9,849 2,207 7,183 460
JUL Split set 5' BA ( ETAMIN ) 76 32.64 2,481 Split set 5' BA 21.7 4,101 -1,621 2,068 -3,075 -614
JUL Split set 5' AN ( CONGEMIN ) 157 11.3 1,774 Split set 5' AN 21.7 3,884 -2,110 -1,862 -599 350
JUL Split set 7' AN ( CONGEMIN ) 789 13.11 10,344 Split set 7' AN 26.13 18,918 -8,574 -9,426 1,769 -916
JUL Split set AN 10' (CONGEMIN) 0 Split set 10' AN 38.3 460 -460 -327 -133
JUL Hidrabolt 5' 0 Hidrabolt 5' BA 30.84 833 -833 -735 -98
JUL Hidrabolt 5' AN (CONGEMIN) 51 11.84 604 Hidrabolt 5' AN 30.84 586 18 -361 871 -492
JUL Hidrabolt 7' AN (CONGEMIN) 397 14.74 5,852 Hidrabolt 7 ' AN 39.95 17,778 -11,926 -11,218 -1,306 599
JUL Hidrabolt 10' AN (CONGEMIN) 63.35 0 Hidrabolt 10' AN 55.42 111 -111 -54 -56
JUL Malla BA ( ETRAMIN) 22.6 25.36 573 Malla BA 16.95 2,729 -2,156 1,354 -3,766 256
JUL Malla AN (CONGEMIN) 45.6 11.63 530 Malla AN 16.95 322 208 -101 724 -414
AGO Split set 4' BA ( ETRAMIN ) 642 28.95 18,586 Split set 4' BA 18.59 3,625 14,961 2,020 12,162 778
AGO Split set 5' BA ( ETAMIN ) 22 32.64 718 Split set 5' BA 21.7 3,863 -3,145 1,947 -4,245 -847
AGO Split set 5' AN ( MCEISA ) 115 18.42 2,118 Split set 5' AN 21.7 4,969 -2,851 -751 -3,102 1,002
AGO Split set 7' AN ( MCEISA ) 552 22.78 12,575 Split set 7' AN 26.13 20,643 -8,068 -2,647 -6,476 1,054
AGO Split set AN 10' (MCEISA) 0 Split set 10' AN 38.3 460 -460 -327 -133
AGO Hidrabolt 5' 0 Hidrabolt 5' BA 30.84 771 -771 -680 -91
AGO Hidrabolt 5' AN (MCEISA) 6 29.44 177 Hidrabolt 5' AN 30.84 709 -533 -32 -463 -38
AGO Hidrabolt 7' AN (MCEISA) 518 35.67 18,477 Hidrabolt 7 ' AN 39.95 19,056 -579 -2,042 1,116 347
AGO Hidrabolt 10' AN (MCEISA) 0 Hidrabolt 10' AN 55.42 166 -166 -82 -85
AGO Malla BA ( ETRAMIN) 12.2 25.36 309 Malla BA 16.95 2,559 -2,250 1,270 -3,777 257
AGO Malla AN (MCEISA) 0 Malla AN 16.95 373 -373 -599 226
SET Split set 4' BA ( ETRAMIN ) 578 28.95 16,733 Split set 4' BA 18.59 3,718 13,015 2,072 10,285 658
SET Split set 5' BA ( ETAMIN ) 17 32.64 555 Split set 5' BA 21.7 3,689 -3,134 1,860 -4,163 -831
SET Split set 5' AN ( MCEISA ) 94 18.42 1,731 Split set 5' AN 21.7 3,949 -2,218 -597 -2,394 773
SET Split set 7' AN ( MCEISA ) 557 22.78 12,688 Split set 7' AN 26.13 19,598 -6,909 -2,513 -5,251 855
SET Split set AN 10' (MCEISA) 0 Split set 10' AN 38.3 460 -460 -327 -133
SET Hidrabolt 5' 0 Hidrabolt 5' BA 30.84 740 -740 -653 -87
SET Hidrabolt 5' AN (MCEISA) 49 29.44 1,443 Hidrabolt 5' AN 30.84 617 826 -28 789 65
SET Hidrabolt 7' AN (MCEISA) 474 35.67 16,908 Hidrabolt 7 ' AN 39.95 17,978 -1,070 -1,926 653 203
SET Hidrabolt 10' AN (MCEISA) 1 57.76 58 Hidrabolt 10' AN 55.42 111 -53 5 -27 -31
SET Malla BA ( ETRAMIN) 4 25.36 101 Malla BA 16.95 2,407 -2,305 1,194 -3,755 255
SET Malla AN (MCEISA) 5.4 17.55 95 Malla AN 16.95 322 -227 11 -370 131
OCT Split set 4' BA ( ETRAMIN ) 502 28.95 14,533 Split set 4' BA 18.59 3,495 11,038 1,948 8,544 547
OCT Split set 5' BA ( ETAMIN ) 137 32.64 4,472 Split set 5' BA 21.7 3,450 1,021 1,739 -599 -119
OCT Split set 5' AN ( MCEISA ) 141 18.42 2,597 Split set 5' AN 21.7 3,971 -1,374 -600 -1,143 369
OCT Split set 7' AN ( MCEISA ) 736 22.78 16,766 Split set 7' AN 26.13 18,291 -1,525 -2,345 980 -159
OCT Split set AN 10' (MCEISA) 0 Split set 10' AN 38.3 460 -460 -327 -133
OCT Hidrabolt 5' 0 Hidrabolt 5' BA 30.84 678 -678 -599 -80
OCT Hidrabolt 5' AN (MCEISA) 37 29.44 1,089 Hidrabolt 5' AN 30.84 586 503 -27 490 40
OCT Hidrabolt 7' AN (MCEISA) 444 35.67 15,837 Hidrabolt 7 ' AN 39.95 17,218 -1,381 -1,845 354 110
OCT Hidrabolt 10' AN (MCEISA) 57.76 0 Hidrabolt 10' AN 55.42 111 -111 -54 -56
OCT Malla BA ( ETRAMIN) 25.36 0 Malla BA 16.95 2,237 -2,237 -3,592 1,354
OCT Malla AN (MCEISA) 17.55 0 Malla AN 16.95 322 -322 -517 195
NOV Split set 4' BA ( ETRAMIN ) 562 28.95 16,270 Split set 4' BA 18.59 3,495 12,775 1,948 10,176 651
NOV Split set 5' BA ( ETAMIN ) 115 32.64 3,754 Split set 5' BA 21.7 3,385 368 1,707 -1,116 -223
NOV Split set 5' AN ( MCEISA ) 197 18.42 3,629 Split set 5' AN 21.7 3,819 -190 -577 571 -185
NOV Split set 7' AN ( MCEISA ) 793 22.78 18,065 Split set 7' AN 26.13 18,944 -880 -2,429 1,850 -301
NOV Split set AN 10' (MCEISA) 0 Split set 10' AN 38.3 460 -460 -327 -133
NOV Hidrabolt 5' 0 Hidrabolt 5' BA 30.84 678 -678 -599 -80
NOV Hidrabolt 5' AN (MCEISA) 7 29.44 206 Hidrabolt 5' AN 30.84 555 -349 -25 -299 -25
NOV Hidrabolt 7' AN (MCEISA) 545 35.67 19,440 Hidrabolt 7 ' AN 39.95 18,936 504 -2,029 1,932 601
NOV Hidrabolt 10' AN (MCEISA) 57.76 0 Hidrabolt 10' AN 55.42 111 -111 -54 -56
NOV Malla BA ( ETRAMIN) 228.2 25.36 5,787 Malla BA 16.95 2,170 3,618 1,076 2,726 -185
NOV Malla AN (MCEISA) 18.6 17.55 326 Malla AN 16.95 322 4 11 -11 4
DIC Split set 4' BA ( ETRAMIN ) 764 28.95 22,118 Split set 4' BA 18.59 3,718 18,400 2,072 15,346 982
DIC Split set 5' BA ( ETAMIN ) 81 32.64 2,644 Split set 5' BA 21.7 3,646 -1,002 1,838 -2,367 -472
DIC Split set 5' AN ( MCEISA ) 234 18.42 4,310 Split set 5' AN 21.7 4,253 57 -643 1,034 -334
DIC Split set 7' AN ( MCEISA ) 544 22.78 12,392 Split set 7' AN 26.13 19,232 -6,839 -2,466 -5,224 850
DIC Split set AN 10' (MCEISA) 0 Split set 10' AN 38.3 460 -460 -327 -133
DIC Hidrabolt 5' 0 Hidrabolt 5' BA 30.84 709 -709 -626 -84
DIC Hidrabolt 5' AN (MCEISA) 20 29.44 589 Hidrabolt 5' AN 30.84 586 3 -27 27 2
DIC Hidrabolt 7' AN (MCEISA) 308 35.67 10,986 Hidrabolt 7 ' AN 39.95 17,898 -6,911 -1,917 -3,809 -1,185
DIC Hidrabolt 10' AN (MCEISA) 7 57.76 404 Hidrabolt 10' AN 55.42 111 293 5 136 153
DIC Malla BA ( ETRAMIN) 143.8 25.36 3,647 Malla BA 16.95 2,356 1,291 1,169 131 -9
DIC Malla AN (MCEISA) 9.6 17.55 168 Malla AN 16.95 373 -204 13 -337 120
Total 22,263 26.98 600,677 Total 27.21 625,429 -24,752 -6,150 -19,668 1,065
Los -723 elementos de sostenimiento impactan x PU $-6,150; por Cantidad $-19,668 y por efecto MIX $+1,065.
Shotcrete Explotación
Ejecutado Programado Efectos al Detalle (US$)
MES Dif ($)
Descripción m2 ($/m2) Total ($) Descripción ($/m2) Total ($) PU Cantidad Efecto MIX
ENE Shotcrete (Vía seca) 2,433 24.05 58,518 Shotcrete (vía seca) 45.23 95,435 -36,917 -44,690 14,618 -6,845
FEB Shotcrete (Vía seca) 1,722 47.29 81,417 Shotcrete (vía seca) 45.23 86,344 -4,927 3,933 -8,474 -386
MAR Shotcrete (Vía seca) 1,771 47.29 83,740 Shotcrete (vía seca) 45.23 99,777 -16,038 4,544 -19,685 -897
MAR Shotcrete (Vía humeda) 478 41.06 19,609 Shotcrete (Vía humeda) 19,609 0 21,602 -1,993
ABR Shotcrete (Vía seca) 107 47.29 5,048 Shotcrete (vía seca) 45.23 86,208 -81,161 3,926 -81,381 -3,706
ABR Shotcrete (Vía humeda) 3,262 35.19 114,806 Shotcrete (Vía humeda) 114,806 0 147,541 -32,734
MAY Shotcrete (vía seca) Shotcrete (vía seca) 45.23 100,592 -100,592 -100,592 0
MAY Shotcrete (Vía humeda) 3,237 33.91 109,771 Shotcrete (Vía humeda) 109,771 0 146,401 -36,630
JUN Shotcrete (vía seca) Shotcrete (vía seca) 45.23 91,229 -91,229 -91,229 0
JUN Shotcrete (Vía humeda) 2,364 35.28 83,413 Shotcrete (Vía humeda) 83,413 0 106,929 -23,516
JUL Shotcrete (vía seca) Shotcrete (vía seca) 45.23 91,546 -91,546 -91,546 0
JUL Shotcrete (Vía humeda) 3,875 33.56 130,033 Shotcrete (Vía humeda) 130,033 0 175,245 -45,212
AGO Shotcrete (vía seca) Shotcrete (vía seca) 45.23 101,044 -101,044 -101,044 0
AGO Shotcrete (Vía humeda) 2,943 34.74 102,239 Shotcrete (Vía humeda) 102,239 0 133,121 -30,882
SET Shotcrete (vía seca) Shotcrete (vía seca) 45.23 92,948 -92,948 -92,948 0
SET Shotcrete (Vía humeda) 1,851 30.17 55,843 Shotcrete (Vía humeda) 55,843 0 83,707 -27,864
SET Shotcrete (Vía humeda) 1,540 32.34 49,818 Shotcrete (Vía humeda) 49,818 0 69,666 -19,848
OCT Shotcrete (vía seca) Shotcrete (vía seca) 45.23 87,339 -87,339 -87,339 0
OCT Shotcrete (Vía humeda) 2,997 31.72 95,061 Shotcrete (Vía humeda) 95,061 0 135,552 -40,490
NOV Shotcrete (vía seca) Shotcrete (vía seca) 45.23 96,249 -96,249 -96,249 0
NOV Shotcrete (Vía humeda) 2,197 31.74 69,734 Shotcrete (Vía humeda) 0 69,734 0 99,369 -29,634
DIC Shotcrete (vía seca) 0 Shotcrete (vía seca) 45.23 92,676 -92,676 -92,676 0
DIC Shotcrete (Vía humeda) 1,887 36.52 68,900 Shotcrete (Vía humeda) 0 68,900 0 85,327 -16,427
Total 32,662 34.53 1,127,950 Total 45.23 1,121,387 6,563 -32,287 355,916 -317,066
(*) Ratio en explotación 11.94 m2/m3 fuente Geomecanica
Los +7,869 m2 impacta x PU $-32,287; por cantidad $+355,916 y por efecto MIX $-317,066.
Servicios varios
Ejecutado Programado
Dif ($)
Descripción Und ($/Und) Total ($) Descripción Und ($/Und) Total ($)
Alquiler CF 430 67 28,837 Alquiler CF 32.5 67 2,178 26,659
Etramin Obras 1,062 1 1,062 Etramin Obras 0 1,062
Alquiler Scoop 8571.09 1 8,571 Alquiler Scoop 0 8,571
Alquiler shotcretera Vía seca 19,218 1 19,218 Alquiler shotcretera Vía seca 0 19,218
Alquiler volquete 23,758 1 23,758 Alquiler volquete 183 47.05 8,619 15,140
Trasnporte de hormigon 77,976 1 77,976 Trasnporte de hormigon 3,471 16 53,993 23,982
Tareas 11,610 1 11,610 Tareas 266 104 27,820 -16,210
Dispocición de residuos 1,674 1 1,674 Dispocición de residuos 0 1,674
Dumper 348.26 1 348 Dumper 0 348
Total 173,054 Total 92,610 80,444
Adicionales/Reintegros/Descuentos
Ejecutado Programado
Dif ($)
Descripción Glb PU Total $ Descripción Glb PU Total $
Alimentación $ 26,984 1 26,984 Alimentación $ 730 1 730 26,254
Serv. Medicos $ 69 1 69 Serv. Medicos $ 58 1 58 11
Alquiler camioneta $ 0 0 Alquiler camioneta $ 722 1 722 -722
Servisios Subreparto $ 587 1 587 Servisios Subreparto $ 1 0 587
Mantto y reparación $ 1,236 1 1,236 Mantto y reparación $ 249 1 249 986
Pago cemento $ 686 1 686 Pago cemento $ 0 686
Contingencia Presupuesto $ 1 0 Contingencia Presupuesto $ 264 1 264 -264
Sobredistancia 4 4,665 1 4,665 Sobredistancia 4 4,665
Fiscalización minera $ 10,919 1 10,919 Fiscalización minera $ 10,919
Reit. Varios $ 124 1 124 Reit. Varios $ 124
Flete $ 4,572 1 4,572 Flete $ 4,572
Cuadrilla shotcrete $ 18,530 1 18,530 Cuadrilla shotcrete $ 18,530
Estudio(Extracción de muestras) $ 1,721 1 1,721 Estudio(Extracción de muestras) $ 0 1,721
Reint x Dif PU $ 12,687 1 12,687 Reint x Dif PU $ 0 12,687
Retribución extraordinaría $ 15,579 1 15,579 Retribución extraordinaría $ 23,067 1 23,067 -7,488
Personal productividad $ 519 1 519 Personal productividad $ 519
Dscto x Dif Precio materiales $ -3,331 1 -3,331 Dscto x Dif Precio materiales $ 0 -3,331
Dscto TC $ -4,304 1 -4,304 Dscto TC $ 0 -4,304
Dscto. GG+CF $ -8,097 1 -8,097 Dscto. GG+CF $ 0 -8,097
Dscto Scoop $ -3,929 1 -3,929 Dscto Scoop $ -3,929
Otros descuentos $ -984 1 -984 Otros descuentos $ 0 1 0 -984
Total 78,234 Total 25,091 53,143
Anexo Nº 5
Desquinche
Adicionales/Reintegros/Descuentos
Ejecutado Programado
Dif ($)
Descripción Cantidad PU Total ($) Descripción Cantidad PU Total ($)
Alimentación mina $ 690 1 690 Alimentación mina $ 7.0 1 7.0 682.9
Servicios medicos $ 14 1 14 Servicios medicos $ 0.6 1 0.6 13.6
Camioneta $ 1 0 Camioneta $ 6.9 1 6.9 -6.9
Mantto y Reparación 926 Mantto y Reparación 90.3 1 90.3 -90.3
Contingencia Presupuesto $ 0 0 Contingencia Presupuesto $ 70.6 1 70.6 -70.6
Servicios Subreparto $ 746 1 746 Servicios Subreparto $ 1 0.0 746.0
Transnel 1029 1 1,029 Transnel 1,029.0
Flete $ 2280 1 2,280 Flete $ 2,280.0
Carg. Frontal 15 67 1,025 Carg. Frontal 1,025.1
Dumper $ 4545 1 4,545 Dumper $ 0.0 4,545.5
Tareas 5422 1 5,422 Tareas 5,422.0
Volquete 654 1 654 Volquete 653.8
Reint CIS $ 5106 1 5,106 Reint CIS $ 5,106.0
Remuneración Extraordinaria $ 1388 1 1,388 Remuneración Extraordinaria $ 521.9 1 521.9 865.7
Otro descuento -98 1 -98 Otro descuento -97.8
Dscto x GG+CF -533 1 -533 Dscto x GG+CF -532.6
Dscto TC -550 1 -550 Dscto TC -550.0
Dscto. Scoop Cía $ -11768 1 -11,768 Dscto. Scoop Cía $ 1 0.0 -11,767.5
Total 9,951 Total 697 9,254
Anexo Nº 6
Servicios Adicionales
Ejecutado Programado
Dif ($)
Descripción Und ($/Und) Total ($) Descripción Und ($/Und) Total ($)
Tarea Servicios 38.3 70.87 2,711 Tarea Servicios 120 94.2 11,308 -8,597
Tarea Operaciones 2.5 76.65 192 Tarea Operaciones 192
Tarea Operaaciones 24.5 111.3 3,193 Tarea Operaaciones 3,193
Inst. zangría 536.1 1.0 536 Inst. zangría 536
Tub 6" Ø (m) 465.4 1.0 465 Tub 6" Ø (m) 465
Tub 4" Ø (m) 58,795 1.00 58,795 Tub 4" Ø (m) 42000 2.7 111,300 -52,505
Tub 2" Ø (m) 1,320 1.00 1,320 Tub 2" Ø (m) 1,320
Mant. Linea Cauville (m) 704.95 1.0 705 Mant. Linea Cauville (m 1440 8.4 12,154 -11,449
Recup. Linea cauville 306.8 1.0 307 Recup. Linea cauville 307
Recup. Tub 4" Ø 23,769 1.0 23,769 Recup. Tub 4" Ø 9600 2.1 20,352 3,417
Barrera (ETRAMIN) 71278 1.0 71,278 Barrera (ETRAMIN) 375 83.1 31,146 40,132
Barrera 15,487 1.0 15,487 Barrera 3000 18.5 55,362 -39,875
Limp.Cuneta 81,932 1.00 81,932 Limp.Cuneta 0.0 0 81,932
Bomberos 28,678 1.00 28,678 Bomberos 28,678
Total 289,367 Total 241,622 47,746
Adicionales/Reintegros/Descuentos
Ejecutado Programado
Dif ($)
Descripción Glb ($/Glb) Total ($) Descripción Glb ($/Glb) Total ($)
Servicios medicos $ 361 1.00 361 º 141 1.00 141 220
Alim. Mina $ 5281 1.00 5,281 Alim. Mina $ 1508 1.00 1,508 3,772
Serv. Mina junio 2013 $ 0.00 0 Serv. Mina junio 2013 $ 12000 1.00 12,000 -12,000
Alquiler camioneta $ 0.00 0 Alquiler camioneta $ 1491 1.00 1,491 -1,491
Conti. Presu $ 0.00 0 Conti. Presu $ 4,003 1.00 4,003 -4,003
Otros $ 10181 1.00 10,181 Otros $ 0.00 0 10,181
Servicios Subreparto $ 12303 1.00 12,303 Servicios Subreparto $ 0.00 0 12,303
Mantto. Reparación $ 3066 1.00 3,066 Mantto. Reparación $ 20001 1.00 20,001 -16,934
Central telefonica 4377 1.00 4,377 Central telefonica 4,377
Transnel $ 515 1.00 515 Transnel $ 515
Flete 3456 1.00 3,456 Flete 3,456
Alquiler dumper $ 98 1.00 98 Alquiler dumper $ 98
IGV 391 1.00 391 IGV 1.00 0 391
Reint x Dif PU $ (*) 6,454 1.00 6,454 Reint x Dif PU $ (*) 6,454
Retribución extraordinaría $ 12556 1.00 12,556 Retribución extraordinaría $ 8,147 1.00 8,147 4,409
Reint x sobredistancia 2512 1.00 2,512 Reint x sobredistancia 2,512
Reint CIS 4901 1.00 4,901 Reint CIS 4,901
Reint varios 2413 1.00 2,413 Reint varios 2,413
Reint. GG+CF $ 8,817 1.00 8,817 Reint. GG+CF $ 8,817
Alquiler bomba flyght 5,653 1.00 5,653 Alquiler bomba flyght 5,653
Alquiler volquete 15,392 1.00 15,392 Alquiler volquete 15,392
Dscto x herramientas $ -131 1.00 -131 Dscto x herramientas $ 1.00 0 -131
Dscto x Dif precio de materiales $ -713 1.00 -713 Dscto x Dif precio de materiales $ -713
Dscto x TC $ -2,461 1.00 -2,461 Dscto x TC $ 1.00 0 -2,461
Dscto x GG+CF $ -5,420 1.00 -5,420 Dscto x GG+CF $ 0 -5,420
Dscto x herror valorización -13,451 1.00 -13,451 Dscto x herror valorización -13,451
Dscto Equipos Cía -590 1.00 -590 Dscto Equipos Cía -590
Total 75,960 Total 47,291 28,669
(*)Reint. X Dif PU ( Nuevo contrato CONGEMIN)
Anexo Nº7
Las -11,747 tmh impactan x PU en $-119,481; Por Cantidad en $-21,427 y por efecto MIX $+127,872.
Equipos
Ejecutado Programado Efectos al Detalle (US$)
Dif ($)
Descripción Hr PU Total ($) Descripción Hr PU Total ($) PU Cantidad Efecto MIX
Alquiler volquete 374 47.05 17,616 Alquiler volquete 684 47.05 32,182 -14,566 0 -24,734 10,168
Alquiler dumper 2,092 88.81 185,793 Alquiler dumper 2,520 88.81 223,801 -38,008 0 -34,193 -3,815
Alquiler dumper 1,125 77.40 87,067 Alquiler dumper 88.81 0 87,067 0 89,874 -2,807
Cargador Frontal 32 67.00 2,144 Cargador Frontal 2,144 0 2,557 -413
Sub total 3,623 80.76 292,621 Sub total 3,204 79.89 255,983 36,637 0 33,504 3,134
Las -310 Hr de Volquete impacta x PU $+0; por cantidad $-24,734 y por efecto MIX $+
Las +697 Hr de dumper impactan x PU $+0; por cantidad $+55,680 y por efecto mix $-6,622.
Las +32 Hr de Carg. Frontal impactan x PU $+0; por cantidad $+2,557 y por efecto MIX $-413.
Transporte de desmonte
Ejecutado Programado
Dif ($)
Descripción Hr PU Total ($) Descripción Hr PU Total ($)
Volquete 2,397 47.05 112,777 Volquete 2,200 47.05 103,510 9,267
Sub total Hr 47.05 112,777 Sub total Hr 47.05 103,510 9,267
Alquiler dumper 19 77.4 1,455 Alquiler dumper 88.81 0 1,455
Alquiler dumper 42 88.81 3,715 Alquiler dumper 360 88.81 31,972 -28,256
Sub total Cantidad 85.27 5,170 Sub total 360 88.81 31,972 -26,801
MO 399 1.00 399 MO 167 1.00 167 232
Combustible 113 1.00 113 Combustible 2,909 1.00 2,909 -2,796
Materiales 230 1.00 230 Materiales 294 1.00 294 -64
Limp cuneta 100 4.59 459 Limp cuneta 459
Cargador Frontal 36 67.00 2,405 Cargador Frontal 0.00 2,405
Scoop 3 116.20 349 349
Retribución extraordinaría 339 1.00 339 339
Mantto y reparación 0 Mantto y reparación 59 1.00 59 -59
Servicios subreparto 178 1.00 178 Servicios subreparto 178
Alimentación 1,181 1.00 1,181 Alimentación 0.00 0 1,181
Contingencia presupuesto 1.00 0 Contingencia presupuesto 10 1.00 10 -10
Dscto CF+GG -11 1.00 -11 -11
Sub total 5,640 Sub total 3,439 2,202
Total General 123,588 Total General 138,920 -15,333
Transporte con locomotora
Ejecutado Programado
Dif ($)
Descripción Cantidad PU Total ($) Descripción Cantidad PU Total ($)
MO(*) 3,845 1 3,845 MO 20,669 1 20,669 -16,824
Sub total 3,845 1 3,845 Sub total 20,669 1 20,669 -16,824
Planchas/adhesivos 84 1 84 Planchas/adhesivos 1,080 1 1,080 -996
Ferreteria 572 1 572 Ferreteria 4,871 1 4,871 -4,299
Material subreparto 636 1 636 Materail subreparto 1 0 636
Combustible 69 1 69 Combustible 703 1 703 -634
Repuestos(*) 9,765 1 9,765 Repuestos 21,132 1 21,132 -11,367
Otros materiales Otros materiales 2,038 1 2,038 -2,038
Sub total 11,127 Sub total 29,824 -18,697
Alimentación mina 214.17 1 214 Alimentación mina 3,509 1 3,509 -3,295
Mantto. Y Reparto 127.85 1 128 Mantto. Y Reparto 6,102 1 6,102 -5,974
scoop 116.2 0 scoop 12 117.16 1,406 -1,406
Alquiler camioneta 0 Alquiler camioneta 3,918 1 3,918 -3,918
Costos Fijos Pers. Motorista 15895.97 1 15,896 Costos Fijos Pers. Motorista 204,000 1 204,000 -188,104
Servicios medicos 0 0 Servicios medicos 315 1 315 -315
Bono Bono 2,163 1 2,163 -2,163
Tareas 162.88 1 163 Tareas 0 163
Flete 756 1 756 Flete 0 756
Contingencia presupuesto 0 Contingencia presupuesto 1,028 1 1,028 -1,028
Obras 179.67 1 180 Obras 0 180
Servicios Subreparto 1401.52 1 1,402 Servicios Subreparto 0 1,402
Sub total 18,738 Sub total 222,442 -203,704
Total 33,710 Total 272,934 -239,225
Tolvas
Ejecutado Programado
Dif ($)
Descripción Cantidad PU Total ($) Descripción Cantidad PU Total ($)
MO 4,030 1 4,030 MO 4,752 1 4,752 -723
Sub total 4,030 Sub total 4,752 -723
Madera 4,965 1 4,965 Madera 2,116 1 2,116 2,849
Planchas/Adhesivos 24,165 1 24,165 Planchas/Adhesivos 13,766 1 13,766 10,399
Ferreteria 13,172 1 13,172 Ferreteria 1,773 1 1,773 11,399
Mater. Elec y Meca. 2492.71 1 2,493 Mater. Elec y Meca. 5 1 5 2,488
Lubri/herra/gases 1849.06 1 1,849 Lubri/herra/gases 1,486 1 1,486 363
Combustible 686 1 686 Combustible 186 1 186 500
Materiales Subreparto 529 1 529 Otros materiales 339 1 339 190
Repuestos 108 1 108 Repuestos 14 1 14 93
Sub total 47,966 Sub total 19,685 28,281
Alimentación mina 25 1 Alimentación mina 855 1 855 -855
Barrera 1,388 1 1,388 Barrera 47.05 0 1,388
Desinstalación de barrera 372 1 372 Desinstalación de barrera 372
Servicios varios 895 1 895 Servicios varios 895
Buzon de madera 2,437 1 2,437 Buzon de madera 2,437
Scoop 4.2 Yd 2,007.24 1 2,007 Scoop 4.2 Yd 18 117 2,109 -102
Volquete Volquete 36 47 1,694 -1,694
Dumper 49.47 1 49 Dumper 49
Tareas operaciones(Etramin) 29,672 1 29,672 Tareas operaciones(Etramin) 29,672
Tareas servicios (Etramin) 43,334 1 43,334 Tareas servicios (Etramin) 43,334
Entablado 11,246 1 11,246 Entablado 11,246
Escalera y descanso 1,549 1 1,549 Escalera y descanso 1,549
Parrilla 1,586 1 1,586 Parrilla 1,586
Bono 572 1 572 Bono 553.51 1 553.51 18
Constru. y montaje de parrillas 0 Constru. y montaje de parrillas 28,205 1 28,205 -28,205
Desmontaje y Repar. Parrilla 0 Desmontaje y Repar. Parrilla 24,000 1 24,000 -24,000
Camioneta 0 Camioneta 859 1 859 -859
Mantto reparación 7,952 1 7,952 Mantto reparación 7,952
Servicios subreparto 1,592 1 1,592 Servicios subreparto 1 0 1,592
Servicios medicos 2.37 1 2 Servicios medicos 63 1 63 -61
Otro servicio 2072.48 1 2,072 Otro servicio 27 1 27 2,045
Contingencia Presupuesto 1 0 Contingencia Presupuesto 236 1 236 -236
Reit varios 542 1 542 Reit varios 1 0 542
Reit x GG+CF 7,076 1 7,076 Reit x GG+CF 7,076
Dscto x Dif TC -870 1 -870 Dscto x Dif TC -870
Dscto x GG+CF -284 1 -284 Dscto x GG+CF -284
Dscto x Dif PU materiales -43 1 -43 Dscto x Dif PU materiales -43
Sub total 113,147 Sub total 58,602 54,545
Total 165,142 Total 83,039 82,103
Anexo Nº 8
Bombeo de agua
Ejecutado Programado
Dif ($)
Cantidad PU Total ($) Cantidad PU Total ($)
MO 19,455 1.00 19,455 MO 16,110 1.00 16,110 3,34
Materiales Materiales 5
Madera 2,283 1.00 2,283 Madera 1,446 1.00 1,446 838
Tela Arpillera 1,900 1.00 1,900 Tela Arpillera 2,628 1.00 2,628 -728
planchas/adhesivos 701 1.00 701 planchas/adhesivos 2,153 1.00 2,153 -1,452
Ferretería 48,840 1.00 48,840 Ferretería 34,137 1.00 34,137 14,704
Material elec./mec. 18,516 1.00 18,516 Material elec./mec. 13,184 1.00 13,184 5,331
Combustible 4,242 1.00 4,242 Combustible 5,450 1.00 5,450 -1,208
Materiales Subreparto 2,790 1.00 2,790 Materiales Subreparto 1.00 0 2,790
Repuestos 26,824 1.00 26,824 Repuestos 51,591 1.00 51,591 -24,767
Lub/Heer/Gras 1,443 1.00 1,443 Lub/Heer/Gras 3,108 1.00 3,108 -1,665
Obras bienes en curso Obras bienes en curso 818 1.00 818 -818
Otros Materiales 442 1.00 442 Otros materiales 2,461 1.00 2,461 -2,019
Total 107,981 Total 116,976 -8,995
Servicios Servicios
Instalación de tub de 4" 42,291 1.00 42,291 Instalación de tub de 4" 6,360 1.00 6,360 35,931
Instalación de tub de 6" 1,128 1.00 1,128 Instalación de tub de 6" 1,128
Recuperación tuberia de 4" 3,493 1.00 3,493 Recuperación tuberia de 4" 2,568 1.00 2,568 925
Instalación tub de 2" 9,017 1.00 9,017 Instalación tub de 2" 5,652 1.00 5,652 3,365
Recuperación tuberia de 2" 1,385 1.00 1,385 Recuperación tuberia de 2" 1.00 0 1,385
Limpieza de cuneta 23,671 1.00 23,671 Limpieza de cuneta 12,420 1.00 12,420 11,251
Instalaciòn barrera 646 1.00 646 Instalaciòn barrera 646
Rec. Linea cauville 345 1.00 345 Rec. Linea cauville 345
Zangrìa 306 1.00 306 Zangrìa 306
Alquiler volquete 4,514 1.00 4,514 Alquiler volquete 14,580 1.00 14,580 -10,066
Alquiler scoop 4.2 Yd. 1,946 1.00 1,946 Alquiler scoop 4.2 Yd. 42,178 1.00 42,178 -40,231
Alquiler scoop 2.5 Yd. 106 1.00 106 Alquiler scoop 2.5 Yd. 7,818 1.00 7,818 -7,712
Cargador Frontal 342 1.00 342 Cargador Frontal 342
Alquiler camioneta 12,628 1.00 12,628 Alquiler camioneta 30,898 1.00 30,898 -18,270
Alquiler dumper 644 1.00 644 Alquiler dumper 5,696 1.00 5,696 -5,052
Tareas ETRAMIN 21,113 1.00 21,113 Tarea ETRAMIN 43,869 1.00 43,869 -22,756
Tareas CONGEMIN 81 1.00 81 Tareas CONGEMIN 81,417 1.00 81,417 -81,336
Valorizaciones varios 1,169 1.00 1,169 Valorizaciones varios 1,169
Serv. Mantto. 17,699 1.00 17,699 Serv. Mantto. 36,000 1.00 36,000 -18,301
Servicios Subreparto 8,133 1.00 8,133 Servicios Subreparto 1.00 0 8,133
Contingencia Presupuesto 1.00 0 Contingencia Presupuesto 824 1.00 824 -824
Serv. Medicos 18 1.00 18 Serv. Medicos 244 1.00 244 -226
Bomberos(*) 77,884 1.00 77,884 Bomberos 1.00 0 77,884
Alimentación mina 3,867 1.00 3,867 Alimentación mina 2,817 1.00 2,817 1,050
Flete 214 1.00 214 Flete 1.00 0 214
Retribuciòn extraordinaria 3,534 1.00 3,534 Retribuciòn extraordinaria 1,669 1.00 1,669 1,865
Reint x alimentaciòn 2,214 1.00 2,214 Reint x alimentaciòn 2,214
Otros reint 369 1.00 369 Otros reint 369
Reint. Reajuste GG+CF Serv. Mina 24,098 1.00 24,098 Reint. Reajuste GG+CF Serv. Mina 1.00 0 24,098
Dscto x GG+CF -136 1.00 -136 Dscto x GG+CF -136
Dscto TC -655 1.00 -655 Dscto TC -655
Servicios 1.00 262,063 Total 1.00 295,010 -32,946
Total 389,499 Total 428,096 -38,597
(*) Bomberos Bateas.
Mantenimiento de vias y accesos
Ejecutado Programado
Dif ($)
Cantidad PU Total ($) Cantidad PU Total ($)
MO 10,401 1.00 10,401 MO 14,878 1.00 14,878 -
Materiales Materiales 4,477
Planchas/adhesivos 1.00 0 Planchas/adhesivos 2,051 1.00 2,051 -2,051
Madera 328 1.00 328 Madera 1 1.00 1 327
Combustible 530 1.00 530 Combustible 31,887 1.00 31,887 -31,357
Mat. Electrico/Mecánico 502 1.00 502 Mat. Electrico/Mecánico 1 1.00 1 502
Ferretería 1,095 1.00 1,095 Ferretería 782 1.00 782 313
Repuestos 8,276 1.00 8,276 Repuestos 23,872 1.00 23,872 -15,596
Otros materiales 193 1.00 193 Otros materiales 67 1.00 67 126
Mat. Subreparto 292 1.00 292 292
Total 11,217 Total 58,661 -47,444
Servicios Servicios
Alquiler motoniveladora y rodillo 28,188 1.00 28,188 Alquiler motoniveladora y rodill 59,333 1.00 59,333 -31,145
Alquiler cisterna(*) 28,674 1.00 28,674 Alquiler cisterna(*) 60,480 1.00 60,480 -31,806
Excavadora 3,905 1.00 3,905 Excavadora 3,905
Alquiler camioneta 1.00 0 Alquiler camioneta 136 1.00 136 -136
Tarea 2,397 1.00 2,397 Tarea 1.00 0 2,397
Alquiler volquete 4,962 1.00 4,962 Alquiler volquete 1.00 0 4,962
Carg. Frontal 2,352 1.00 2,352 Carg. Frontal 2,352
Dumper 237 1.00 237 Dumper 237
Servicios Subreparto 543 1.00 543 Servicios Subreparto 1.00 0 543
Mantto. Línea Cauville 153 1.00 153 Mantto. Línea Cauville 153
Recup. Línea Cauville 230 1.00 230 Recup. Línea Cauville 1.00 0 230
Barrera 792 1.00 792 Barrera 792
Limp. Cuneta(**) 56,843 1.00 56,843 Limp. Cuneta(**) 1.00 0 56,843
Serv. Medicos 60 1.00 60 Serv. Medicos 134 1.00 134 -74
Cont. Presto. 0.00 0 Cont. Presto. 800 1.00 800 -800
Obras 3,266 1.00 3,266 Obras 3,266
Alimentación 1,477 1.00 1,477 Alimentación 138 1.00 138 1,339
Flete 9,766 1.00 9,766 Flete 9,600 1.00 9,600 166
Mantenimiento y Reparación 898 1.00 898 Mantenimiento y Reparación 12,936 1.00 12,936 -12,038
Otro serv(adelanto ) 2,905 1.00 2,905 Otro serv(adelanto ) 2,905
Bono extraordinario 286 1.00 286 Bono extraordinario 286
Otro Reint 126 1.00 126 Otro Reint 1.00 0 126
Reint. Reajuste GG+CF Serv. Mina 12,276 1.00 12,276 Reint. Reajuste GG+CF Serv. Mina 1.00 0 12,276
Dscto TC -96 1.00 -96 Dscto TC -96
Total 160,240 Total 143,557 16,683
Total 181,858 Total 217,096 -35,238
Ventilación
Ejecutado Programado
Dif ($)
Cantidad PU Total ($) Cantidad PU Total ($)
MO 33,933 1.00 33,933 MO 50,388 1.00 50,388 -16,455
Materiales Materiales
Madera 16,344 1.00 16,344 Madera 5,584 1.00 5,584 10,760
Planchas/Aditivos 3,429 1.00 3,429 Planchas/Aditivos 4,703 1.00 4,703 -1,275
Ferreteria 13,214 1.00 13,214 Ferreteria 13,605 1.00 13,605 -391
Mant elec./Mant. mecan. 5,677 1.00 5,677 Mant elec./Mant. mecan. 8,244 1.00 8,244 -2,567
Combustible 2,466 1.00 2,466 Combustible 430 1.00 430 2,036
Lub/Herra/Gases 396 1.00 396 Lub/Herra/Gases 1,674 1.00 1,674 -1,278
Materiales Subreparto 968 1.00 968 Materiales Subreparto 1.00 0 968
Repuestos 32,633 1.00 32,633 Repuestos 25,082 1.00 25,082 7,552
Otros materiales 1,589 1.00 1,589 Otros materiales 6,191 1.00 6,191 -4,602
Total 76,716 Total 65,512 11,203
Servicios Servicios
Desintal manga ventilación 2,996 1.00 2,996 Desintal manga ventilación 13,028 1.00 13,028 -10,032
Ins. Mangas ventilación 12,696 1.00 12,696 Ins. Mangas ventilación 14,121 1.00 14,121 -1,425
Tarea 4,932 1.00 5,002 Tarea 6,267 1.00 6,267 -1,265
Inst. Ventilador 15,129 1.00 15,129 Inst. Ventilador 22,677 1.00 22,677 -7,548
Const. Barrera 49,454 1.00 49,454 Const. Barrera 11,512 1.00 11,512 37,942
Desinstalaciòn . Barrera 2,341 1.00 2,341 Desinstalaciòn . Barrera 8,023 1.00 8,023 -5,682
Desint ventilador 10,010 1.00 10,010 Desint ventilador 9,709 1.00 9,709 301
Mantto linea cauville 184 1.00 184 Mantto linea cauville 1.00 0 184
Plataforma ventilador 9,957 1.00 9,957 Plataforma ventilador 13,472 1.00 13,472 -3,514
Limp. Cuneta 1,588 1.00 1,588 Limp. Cuneta 1.00 0 1,588
Inst. Tub 2,418 1.00 2,418 Inst. Tub 1.00 0 2,418
Rec. Tub 86 1.00 86 Rec. Tub 0 86
Cargador Frontal 469 1.00 469 Cargador Frontal 1.00 0 469
Alquiler scoop 4,473 1.00 4,473 Alquiler scoop 14,059 1.00 14,059 -9,586
Obras civiles 2,201 1.00 2,201 Obras civiles 2,201
Alquiler volquete 286 1.00 286 Alquiler volquete 3,888 1.00 3,888 -3,602
Contingencia presupuesto 0.00 0 Contingencia presupuesto 3,170 1.00 3,170 -3,170
Servicios Subreparto 2,950 1.00 2,950 Servicios Subreparto 1.00 0 2,950
Serv. Mantto 17,851 1.00 17,851 Serv. Mantto 29,000 1.00 29,000 -11,149
Alimentación mina 4,209 1.00 4,209 Alimentación mina 2,119 1.00 2,119 2,090
Servicios Médicos 534 1.00 534 Servicios Médicos 246 1.00 246 288
Alquiler camioneta 492 1.00 492 Alquiler camioneta 2,681 1.00 2,681 -2,189
Flete 72 1.00 72 Flete 0 72
Excavadora 328 1.00 328 Excavadora 0 328
Autorizaciòn ANFO 5,250 1.00 5,250 Autorizaciòn ANFO 0 5,250
Retribuciòn extraordinaria 2,393 1.00 2,393 Retribuciòn extraordinaria 1,040 1.00 1,040 1,353
Otros reintegros 224 1.00 224 Otros reintegros 1.00 0 224
Reint CIS 147 1.00 147 Reint CIS 147
Reint x Dsitribución GG+CF 22,442 1.00 22,442 Reint x Dsitribución GG+CF 1.00 0 22,442
Reint. Alimentaciòn 1,509 1.00 1,509 Reint. Alimentaciòn 1.00 0 1,509
Dscto TC -585 1.00 -585 Dscto TC -585
Dscto x GG+CF -88 1.00 -88 Dscto x GG+CF -88
Total 1.00 177,019 Total 155,012 22,008
Total 287,668 Total 270,912 16,755
Mantenimiento de labores Subterraneas
Ejecutado Programado
Dif ($)
Cantidad PU Total ($) Cantidad PU Total ($)
MO 41,300 1.00 41,300 MO 24,776 1.00 24,776 16,524
Materiales Materiales
Madera 2,510 1.00 2,510 Madera 6,300 1.00 6,300 -3,790
Barretillas 3,131 1.00 3,131 Barretillas 624 1.00 624 2,507
Tela arpillera 1,198 1.00 1,198 Tela arpillera 1,314 1.00 1,314 -116
Planchas/adhesivos 2,464 1.00 2,464 Planchas/adhesivos 10,785 1.00 10,785 -8,321
Ferreteria 5,685 1.00 5,685 Ferreteria 22,946 1.00 22,946 -17,261
Material electrico/mecanico 517 1.00 517 Material electrico/mecanico 2,285 1.00 2,285 -1,768
Lubric/herram/gases 4,866 1.00 4,866 Lubric/herram/gases 5,831 1.00 5,831 -965
Combustible 28,593 1.00 28,593 Combustible 33,482 1.00 33,482 -4,889
Otros materiales 1,438 1.00 1,438 Otros materiales 86 1.00 86 1,351
Repuestos 41,121 1.00 41,121 Repuestos 19,621 1.00 19,621 21,500
Material Subreparto 1,061 1.00 1,061 Material Subreparto 1.00 0 1,061
Total 92,583 Total 103,275 -10,692
Servicios Servicios
Inst. Tub 2,763 1.00 2,763 Inst. Tub 7,950 1.00 7,950 -5,187
Limpieza Cuneta 232,901 1.00 232,901 Limpieza Cuneta 183,816 1.00 183,816 49,085
Cambio durmientes 169 1.00 169 Cambio durmientes 1.00 0 169
Mantto/ Int Linea cauville 13,769 1.00 13,769 Mantto/ Int Linea cauville 52,830 1.00 52,830 -39,061
Recup. Linea cauville 4,426 1.00 4,426 Recup. Linea cauville 13,517 1.00 13,517 -9,091
Carg. Frontal 750 1.00 750 Carg. Frontal 1.00 0 750
Volquete 1,658 1.00 1,658 Volquete 1.00 0 1,658
Tareas 24,767 1.00 24,767 Tareas 18,801 1.00 18,801 5,966
Malla 138 1.00 138 Malla 138
Ins zapa 147 1.00 147 Ins zapa 147
Barrera 259 1.00 259 Barrera 259
Contrucciòn/inst zangrìa 4,604 1.00 4,604 Contrucciòn/inst zangrìa 4,604
Alcayatas 46 1.00 46 Alcayatas 46
Inst. ventilador 175 1.00 175 Inst. ventilador 175
Rec. Tub 486 1.00 486 Rec. Tub 486
Alquiler scoop 10,797 1.00 10,797 Alquiler scoop 43,515 1.00 43,515 -32,718
Alquiler dumper 7,195 1.00 7,195 Alquiler dumper 1.00 0 7,195
Contingecnia presupuesto 1.00 0 Contingecnia presupuesto 1,522 1.00 1,522 -1,522
Alquiler volquete 1.00 0 Alquiler volquete 9,720 1.00 9,720 -9,720
Alquiler camioneta 7,134 1.00 7,134 Alquiler camioneta 7,542 1.00 7,542 -408
Mantto.Reparación 3,798 1.00 3,798 Mantto.Reparación 10,633 1.00 10,633 -6,834
Servicios ( Subreparto) 3,529 1.00 3,529 Servicios ( Subreparto) 1.00 0 3,529
Otros servicios 5,544 1.00 5,544 Otros servicios 5,544
Flete terrestre 41 1.00 41 Flete terrestre 1.00 0 41
Alimentación 5,865 1.00 5,865 Alimentación 113 1.00 113 5,752
Servicios médicos 262 1.00 262 Servicios médicos 115 1.00 115 147
Bono extraordinario 7,813 1.00 7,813 Bono extraordinario 2,936 1.00 2,936 4,877
Reitn. CIS 433 1.00 433 Reitn. CIS 433
Reit. X Dsit GG+CF 51,192 1.00 51,192 Reit. X Dsit GG+CF 1.00 0 51,192
Reint. Varios 2,265 1.00 2,265 Reint. Varios 1.00 0 2,265
Reintegro x alimentaciòn 9,552 1.00 9,552 Reintegro x alimentaciòn 1.00 0 9,552
Dscto TC -1,670 1.00 -1,670 Dscto TC 1.00 0 -1,670
Dscto. Scoop -1,198 1.00 -1,198 Dscto. Scoop 1.00 0 -1,198
Dscto varios -14 1.00 -14 Dscto varios -14
Dscto. GG+CF -340 1.00 -340 Dscto. GG+CF 1.00 0 -340
Total 399,258 Total 353,010 46,248
Total 533,141 Total 481,061 52,080
Alimentación de agua
Ejecutado Programado
Dif ($)
Descripción Cantidad PU Total ($) Descripción Cantidad PU Total ($)
Materiales Materiales
MO 1,439 1.00 1,439 MO 1.00 0 1,439
Ferreteria 23,190 1.00 23,190 Ferretería 27,495 1.00 27,495 -4,306
Otros materiales 500 1.00 500 Otros materiales 615 1.00 615 -115
Tele arpillera 483 1.00 483 Tele arpillera 526 1.00 526 -43
Total 25,611 Total 28,636 -3,025
Servicios Servicios
Recp. Tub. 6,875 1.00 6,875 Recp. Tub. 14,988 1.00 14,988 -8,113
Inst. Tub. 32,846 1.00 32,846 Inst. Tub. 17,225 1.00 17,225 15,621
Barrera 173 1.00 173 Barrera 173
Alcayatas 178 1.00 178 Alcayatas 9,101 1.00 9,101 -8,923
Limpieza de cuneta 1,102 1.00 1,102 Limpieza de cuneta 16,560 1.00 16,560 -15,458
Alquiler scoop 77 1.00 77 Alquiler scoop 1.00 77
Tarea (soldador) 1,496 1.00 1,496 Tarea (soldador) 7,502 1.00 7,502 -6,007
Alquiler cisterna 1.00 0 Alquiler cisterna 1,152 1.00 1,152 -1,152
Alimentación 198 1.00 198 Alimentación 1.00 0 198
Servicios medicos 8 1.00 8 Servicios medicos 0 8
Ser. Subreparto 155 1.00 155 Ser. Subreparto 0 155
Otro servicio 1,286 1.00 1,286 Otro servicio 0 1,286
Obras 13,961 1.00 13,961 Obras 0 13,961
Bomberos 7,625 1.00 7,625 Bomberos 1.00 0 7,625
Reint. CF+GG 9,034 1.00 9,034 Reint. CF+GG 1.00 0 9,034
Otros reint. 593 1.00 593 Otros reint. 1.00 0 593
Bono extraordinario 1,114 1.00 1,114 Bono extraordinario 693 1.00 693 420
Dscto TC -159 1.00 -159 Dscto TC 0 -159
Dscto GG+CF -23 1.00 -23 Dscto GG+CF 0 -23
Total 76,539 Total 67,221 9,317
Total 102,149 Total 95,857 6,292
Aire Comprimido
Ejecutado Programado
Dif ($)
Descripción Cantidad PU Total ($) Descripción Cantidad PU Total ($)
MO 48,986 1.00 48,986 MO 46,299 1.00 46,299 2,68
Materiales Materiales 7
Madera 875 1.00 875 Madera 9 1.00 9 867
Aditivos/adhesivos/lub/planchas 1,466 1.00 1,466 Aditivos/adhesivos/lub 412 1.00 412 1,054
Ferretería 45,752 1.00 45,752 Ferretería 36,131 1.00 36,131 9,621
Material electrico 4,108 1.00 4,108 material electrico/mecanico 904 1.00 904 3,204
Lubricantes/gases 5,338 1.00 5,338 Lub/Herr/Gases 24,034 1.00 24,034 -18,696
Materiales Subreparto 925 1.00 925 Materiales Subreparto 1.00 0 925
Combustible 179,189 1.00 179,189 Combustible 252,446 1.00 252,446 -73,257
Materiales varios 600 1.00 600 Materiales varios 588 1.00 588 12
Repuestos 17,378 1.00 17,378 Repuestos 57,055 1.00 57,055 -39,677
Total 255,631 Total 371,577 -115,947
Servicios Servicios
Insta Tub 43,828 1.00 43,828 Insta Tub 27,282 1.00 27,282 16,546
Rec Tub 13,063 1.00 13,063 Rec Tub 6,360 1.00 6,360 6,703
Inst. de alcayatas 1.00 0 Inst. de alcayatas 22,752 1.00 22,752 -22,752
Desint barrera 596 1.00 596 Desint barrera 596
Const. Barrera 1,526 1.00 1,526 Const. Barrera 1.00 0 1,526
Limpieza de cuneta 3,511 1.00 3,511 Limpieza de cuneta 1.00 0 3,511
Plataforma 469 1.00 469 Plataforma 1.00 0 469
Tarea 6,957 1.00 6,957 Tarea 65,177 1.00 65,177 -58,220
Alquiler volquete 307 1.00 307 Alquiler volquete 1.00 307
Alquiler scoop 845 1.00 845 Alquiler scoop 7,030 1.00 7,030 -6,185
Alquiler dumper 44 1.00 44 Alquiler dumper 1.00 44
Carg. Frontal 1,012 1.00 1,012 Carg. Frontal 1.00 0 1,012
Alquiler compresora 6,000 1.00 6,000 Alquiler compresora 36,000 1.00 36,000 -30,000
Servicios Subreparto 2,996 1.00 2,996 Servicios Subreparto 1.00 0 2,996
Alimentación 7,736 1.00 7,736 Alimentación 1,393 1.00 1,393 6,342
Servicios médicos 937 1.00 937 Servicios médicos 112 1.00 112 825
Contingecia Presp. 1.00 0 Contingecia Presp. 3,437 1.00 3,437 -3,437
Obras 20,840 1.00 20,840 Obras 20,840
Alquiler camioneta 9,512 1.00 9,512 Alquiler camioneta 1,391 1.00 1,391 8,121
Flete 2,836 1.00 2,836 Flete 2,836
Mantto y Reparación compresor 3,561 1.00 3,561 Mantto y Reparación compresor 18,829 1.00 18,829 -15,268
Bono extraordinario 2,273 1.00 2,273 Bono extraordinario 1,289 1.00 1,289 984
Reint x dist GG+CF 14,739 1.00 14,739 Reint x dist GG+CF 1.00 0 14,739
Reint. Varios 1,529 1.00 1,529 Reint. Varios 1.00 0 1,529
Dscto TC -400 1.00 -400 Dscto TC -400
Dscto GG+CF -88 1.00 -88 Dscto GG+CF -88
Total 144,630 Total 191,051 -46,421
Total 449,247 Total 608,927 -159,680
Casa de lamparas
Ejecutado Programado
Dif ($)
Cantidad PU Total ($) Cantidad PU Total ($)
MO 23,485 1.00 23,485 MO 21,558 1.00 21,558 1,927
Materiales varios 33 1.00 33 Materiales varios 101 1.00 101 -69
Repuestos 82 1.00 82 Repuestos 6,872 1.00 6,872 -6,790
Servicios médicos 201 1.00 201 Servicios médicos 1.00 0 201
Contingencia presupuesto 1.00 0 Contingencia presupuesto 1,730 1.00 1,730 -1,730
Servicios varios 120 1.00 120 120
Alimentación 3,517 1.00 3,517 Alimentación 1.00 0 3,517
Total 27,438 Total 30,262 -2,824
Bodegas
Ejecutado Programado
Dif ($)
Cantidad PU Total ($) Cantidad PU Total ($)
MO 63 1.00 63 MO 2,056 1.00 2,056 -1,993
Maderas 1.00 0 Maderas 2,449 1.00 2,449 -2,449
Planchas 1.00 0 Planchas 8,661 1.00 8,661 -8,661
Ferreteria 1.00 0 Ferreteria 11,242 1.00 11,242 -11,242
Otros materiales 8 1.00 8 Otros materiales 2,630 1.00 2,630 -2,622
Tarea ETRAMIN 266 1.00 266 Tarea ETRAMIN 10,445 1.00 10,445 -10,179
Ins tub 239 1.00 239 Ins tub 239
Alquiler camioneta 1.00 0 Alquiler camioneta 424 1.00 424 -424
Alimentación 1.00 0 Alimentación 335 1.00 335 -335
Serv. Mantto. 1.00 0 Serv. Mantto. 1,944 1.00 1,944 -1,944
Contingencia pres 1.00 0 Contingencia pres 91 1.00 91 -91
Obras 916 1.00 916 Obras 0 916
Serv subreparto 23 1.00 23 Serv subreparto 0 23
Dscto -2 1.00 -2 Dscto 0 -2
Reintegros 85 1.00 85 Reintegros 111 1.00 111 -26
Serv. Medicos 1.00 0 Serv. Medicos 51 1.00 51 -51
Total 1,597 Total 40,439 -38,841
Comedores
Ejecutado Programado
Dif ($)
Descripción Cantidad PU Total ($) Descripción Cantidad PU Total ($)
Madera 1.00 0 Madera 1,096 1.00 1,096 -1,096
Aditivos/adhesivos 1.00 Aditivos/adhesivos 188 1.00 188 -188
Ferretería 1.00 0 Ferretería 2,379 1.00 2,379 -2,379
Baño químico/Dispocición de resi 48,851 1.00 48,851 Baño químico/Dispocición de res 37,288 1.00 37,288 11,563
Otro servicio 552 1.00 552 Otro servicio 552
Obras 1,713 1.00 1,713 Obras 1,713
Tarea 1,240 1.00 1,240 Tarea 5,067 1.00 5,067 -3,827
Total 52,356 Total 46,018 6,339
Lineas de transmisión
Ejecutado Programado
Dif ($)
Descripción Cantidad PU Total ($) Descripción Cantidad PU Total ($)
MO 82,767 1.00 82,767 MO 58,828 1.00 58,828 23,939
Materiales Materiales
Materiales Subreparto 11,162 1.00 11,162 Materiales Subreparto 1.00 0 11,162
Planchas/adhesivos 179 1.00 179 Planchas/adhesivos 150 1.00 150 29
Ferretería 4,068 1.00 4,068 Ferretería 4,695 1.00 4,695 -628
Mat. Electrico 31,633 1.00 31,633 Material electri/mecanico 41,711 1.00 41,711 -10,078
Combustible 173 1.00 173 Combustible 1,939 1.00 1,939 -1,766
Lub/Herr/gases 1,601 1.00 1,601 Lub/Herr/gases 52 1.00 52 1,549
Repuestos 2,520 1.00 2,520 Repuestos 2,724 1.00 2,724 -205
Otros materiales 3,537 1.00 3,537 -3,537
Total 51,335 Total 54,808 -3,473
Servicios Servicios
Inst. Tub. 4" 1.00 0 Inst. Tub. 4" 9,540 1.00 9,540 -9,540
Tarea 2,647 1.00 2,647 Tarea ETRAMIN 11,281 1.00 11,281 -8,633
Alquiler scoop 859 1.00 859 Alquiler scoop 4.2 Yd. 1.00 0 859
Mantto. Rep. 1.00 0 Mantto. Rep. 71 1.00 71 -71
Contingencia presupuesto 1.00 0 Contingencia presupuesto 2,603 1.00 2,603 -2,603
Servicios Subreparto 36,012 1.00 36,012 Servicios Subreparto 1.00 0 36,012
Alimentación 1.00 0 Alimentación 9,551 1.00 9,551 -9,551
Alquiler De Central Telefónica 167 1.00 167 Alquiler De Central Telefónica 1.00 0 167
Alquiler camioneta 1.00 0 Alquiler camioneta 12,083 1.00 12,083 -12,083
Alquiler volquete 171 1.00 171 Alquiler volquete 1.00 171
Servicios médicos 1.00 0 Servicios médicos 972 1.00 972 -972
Reint x dist GG+CF 242 1.00 242 Reint x dist GG+CF 1.00 0 242
Otro reintegro 399 1.00 399 Otro reintegro 221 1.00 221 178
Dscto -10 1.00 -10 -10
Total 40,487 Total 46,320 -5,833
Total 174,589 Total 159,957 14,632