Академический Документы
Профессиональный Документы
Культура Документы
Vehicle used by survey team shall be roadworthy and maintained in good condition.
Vehicle must be fitted with seatbelts and occupants riding in vehicle must wear
Incompetent driver
seatbelts.
Unknown terrain
Driver must hold a valid driving license.
Lost
Daily vehicle inspection shall be conducted by the driver.
Fuel consumption
Experienced drivers shall be assigned with the survey team.
Spillage of fuel/ lube oil
Follow site traffic safety rules and drive within safe speed limits.
Vehicle accident
Driver must not use mobile phone while driving. SIT JV
Rollover of vehicle
Chief surveyor will conduct regular toolbox talks SIT JV Site Construction
1 General survey works Serious injuries 3 4 12 1 3 3
Seat belts shall be worn by all passengers (including rear passengers). Supervisor Manager / HSE
Fatalities
Instruction to all drivers to avoid engine idle and shutdown the engine when not in Manager
Exhaust emission
use to save fuel and avoid emission of carbon dioxide to atmosphere.
Land contamination
Routine preventative maintenance such as changing engine oil, cleaning filters etc.,
Noise generation
to improve fuel efficiency and to prevent the emission of dark smoke into
Natural resource depletion
environment.
Air/ Noise pollution
Exhaust emission monitoring on bi-yearly basis.
Occupational noise monitoring shall be conducted on quarterly basis by the HSE
team.
1
Risk Rating Initial Risk Rating Final Monitoring
Item Activity Hazards Precaution/Control Measures Responsibility
L S R L S R Responsibility
Provide appropriate and safe access for personnel to and from the work area.
Pedestrian walkway shall be segregated from plant movement.
Provide adequate illumination.
Improper access, poor lighting. Install signage and proper barricading with warning signs.
SIT JV
Good housekeeping at site, no materials or other hindrances in the access for SIT JV Site
3 Access & Egress 3 3 9 1 3 3 Construction
Tripping hazard. personnel. Supervisor
Manager
Install signage and proper barricading with warning signs.
Good housekeeping at site, no material or other hindrances in the walkway for
personnel.
Proper cable management. Run either overhead or underground
All machinery will operate inside the fenced site area (where applicable)
Simultaneous work activities and site logistics to be planned in advance.
Movement of plant/vehicles in Only qualified plant operators to be deployed with TPC
proximity to public roads causing Equipment on site to reverse under the control of a trained and designated
accidents and injury to site banksmen/flagman.
personnel and third parties. Ensure the reverse alarm properly working on all plant/vehicle.
Simultaneous activity causing Signal / Eye contact with the operator while passing near the mobile plant. SIT JV
mutual interferences Enforce speed limit (20km/hr.) on site. SIT JV Site Construction
Movement of Injury/fatality to personnel hit by Personnel to wear high visible vest at all times when working on site. Supervisor / Manager / Site
4 3 4 12 1 3 3
Plant/vehicles moving machinery Provide safety path/access. Foreman / Site Manager
Collision between moving Loose clothing to be kept clear of moving parts of power tools. Engineer HSE Officer
equipment Plant and equipment that may cause excessive pressure on unsupported
Loose clothing becoming excavations will not be permitted within a distance from the edge that is equal to
entangled in moving parts. 1.5 times the depth of the excavation.
Fall of Plant into Excavation All the Excavation to be barricaded with safety barriers.
Signage will be in place for operator to identify.
Flashing Warning Light to be placed along with safety barriers for high visibility and
identification
Tools provided will be assessed to ensure they are fit for the purpose and the
environment in which they are to be used. Tools will be used only for the purpose
for which they are intended. The user must ensure that the tools are in good SIT JV
condition and safe to use before commencing work. SIT JV Site Construction
Eye injuries.
The appropriate PPE will be used i.e. eye protection, protective gloves, overall and Supervisor / Manager / Site
6 Use of hand tools Injuries to hands, feet and body. 3 3 9 1 3 3
protective footwear. Foreman / Site Manager
All persons using hand tools will be suitably trained in the correct method of use. Engineer HSE Officer
Sharp instruments such as knives and screwdrivers are to be carried and used so
as not to cause injury to others.
Hand power tools will be inspected prior to use
2
Risk Rating Initial Risk Rating Final Monitoring
Item Activity Hazards Precaution/Control Measures Responsibility
L S R L S R Responsibility
3
Risk Rating Initial Risk Rating Final Monitoring
Item Activity Hazards Precaution/Control Measures Responsibility
L S R L S R Responsibility
Site Supervisor
• Study route and site features before mobilization to access potential hazards.
All drivers
• Use construction access road for entry and exit.
Banksman
• Prepare plan for delivery of plant and equipment on site.
Proximity to public roads causing Site Engineer HSE Officer
Mobilization/Demobilizatio • Access impacts on local traffic.
11 accidents and injury to site 3 3 9 1 3 3 Project Engineer HSE Manager
n of plant and equipment • Induction to machine operator and mobilization team.
personnel and third parties. Construction
• Follow road safe procedure when occupying public roads.
Manager
• Workers to wear appropriate PPE at all times.
Project Manager
4
Risk Rating Initial Risk Rating Final Monitoring
Item Activity Hazards Precaution/Control Measures Responsibility
L S R L S R Responsibility
• Hot works shall only be carried out under a hot works permit system.
• Check certificates of all personnel involved in the welding & cutting works.
• All hot works and electrical equipment shall conform to the project safety plan.
• Ensure that proper earthing is provided prior to work commencement.
• Additional PPE including flame retardant apron, gloves and welding head
shield/goggles shall be worn according to work being carried out.
• Welding masks and welding screens to be provided for the welding activities if
required. Site Supervisor
• Welding, gas cutting, etc.
• Exclusion zones to be barricaded especially if required when welding at height. All drivers
causing fire, explosion, burns.
• Protection to vulnerable equipment (gas bottles etc.) shall be provided as Banksman
• Electrocuted during welding.
required. Fire blankets etc. Site Engineer HSE Officer
• Accident caused by
14 Hot works 3 4 12 • Gas bottles shall be placed in an adequate metallic storage cage. 1 4 4 Project Engineer HSE Manager
unauthorized personnel with
• Employ competent fire watchman during cutting & welding work. Construction
invalid or expired certificates.
• Cutting sets to be provided with flash back arrester and non-return valve. Manager
• Damage hose / cables.
• Gas bottles will be stored/kept (empty and full separately) in a designated area. Project Manager
• Segregation between Oxygen and Fuel bottles will be strictly followed.
• Inspection of gas bottles, hoses, gauges and flashback arrestor to be carried out
before usage.
• Adequate means of extinguishing fire should be at site (fire extinguishers, fire
blankets and buckets etc.).
• Prior inspection of cables and hose.
• Ensure electrical equipment’s are earthed properly.
5
Risk Rating Initial Risk Rating Final Monitoring
Item Activity Hazards Precaution/Control Measures Responsibility
L S R L S R Responsibility
6
Risk Rating Initial Risk Rating Final Monitoring
Item Activity Hazards Precaution/Control Measures Responsibility
L S R L S R Responsibility
Site Supervisor
• Study route and site features before mobilization to access potential hazards.
Site Engineer
• Prepare plan for delivery of plant and equipment on site.
• Proximity to public roads Project Engineer HSS Officer
Mobilization/Demobilizatio • Access impacts on local traffic.
19 causing accidents and injury to 3 3 9 1 3 3 Construction HSS Manager
n of plant and equipment • Induction to machine operator and mobilization team.
site personnel and third parties. Manager
• Follow road safe procedure when occupying public roads.
Project Manager
• Workers to wear appropriate PPE at all times.
• Dust generation.
• Working at height.
• Collision between vehicles and • Restrict personnel entry to workforce and other authorized staff only.
personnel causing injury/death of • Appropriate sand bed shall be prepared to protect the UG services.
workers. • Reinstate all services warning tapes prior to backfill.
Site Supervisor
• Material falling onto workers • Equipment shall be park at safe distance from edge during loading/unloading
All drivers
causing injuries/death of • Nobody allowed to stand at the edge of the excavation.
Banksman
personnel. • Plate compactor shall be in good condition.
Site Engineer HSS Officer
Transportation of Backfill • Presence of UG services • Preventative maintenances shall be performed for the compactor.
20 2 3 6 1 3 3 Project Engineer HSS Manager
Material • Loose sand • Plate compactor shall be operated by competent personnel.
Construction
• Condition of plate compactor • Shutdown the plate compactor when not in use.
Manager
• Personal injuries • Adequate site supervision shall be maintained.
Project Manager
• Toppling or overturn of • Controlled personal movement during compaction activity by roller compactor.
equipment during loading/un • Banksman/flagman to control vehicle movement.
loading • All personnel shall wear site mandatory PPE.
• Dust • Personnel shall use dark goggles and dust masks.
• Vibration
• Damage to UG services