Consumption of supplies at constructionLoss % max

# Item Qty in Unit


1 Ton of Prtland Cemnet 20 Bag
2 Bag of portland cement 50 Kg
3 1 cu.m. Of SAND 24 Bags
4 1 cu.m mortar (masonry works) 1 cu.m sand

5 1 sqm of Concrete Block 40x20xW ,


W=(70,100,120,150,200,250,300 mm)
11.6 No. /m2

6
10 m2 of Block (40x20xw) , 10 mm mortar , Mix Ratio
1:4

Net Block No. Required = Add


Wastage 120
10 *11.6 = 116 No. 3%

7 Block size 100 mm


8 Cement 63 Kg add 5% loss
9 Sand 0.174 m3 add 5% loss
10 Water 18 Liter
11 Block size 150 mm
12 Cement 76 Kg add 5% loss
13 Sand 0.21 m3 add 5% loss
14 Water 21 Liter
15 Block size 200 mm
16 Cement 89 Kg add 5% loss
17 Sand 0.25 m3 add 5% loss
18 Water 25 Liter
19 Block size 250 mm
20 Cement 102 Kg add 5% loss
21 Sand 0.29 m3 add 5% loss
22 Water 29 Liter
23 Rush coat prior to plaster (1m3 sand +
9 Cement bags ) - Tartasha 200 m2
24 Plaster mortar (1m3 sand + 7
B.Cement ) - Rough 30 m2
25 CEMENT SAND WATER
26 30 m2 -Plaster mix 1:4 , 10 mm , 116 Kg 0.32 m3 126 L
27 30 m2 -Plaster mix 1:4 , 15 mm , 173 Kg 0.48 m3 188 L
28 30 m2 -Plaster mix 1:4 , 20 mm , 232 0.64 252

29 (rush coat + plaster


0.35 m3 sand + 0.25 m3 cement 1 m2 oint + plastering)

30 Ceramic/marble tile
1 m3 sand + 6 B cement 30 m2 mortar

31
1 Kg stucco 2 m2 3 coats
32 1 Liter plastic paint 5 m2 3 coats
33 25 Kg Cemntious paint 6 ~ 10 m2
34 1 Liter Bitumin 1 m2 2 coats
35 Membrane Roll 1m X 10 8.50 M2
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
7
0.9215
0.08
11.51875

16.66667

16.66667

64 64

20
4.8
item Activity Crew Productivity / Day
PCC Foundation - pads 1 Carpenter + 1 helper 10 m3
PCC RAFT 1 Carpenter + 1 helper 50
RCC Pads + Gr Beams 1 Carpenter + 1 helper 3
FORM RCC RAFT 1 Carpenter + 1 helper 50
WORKS Columns 1 Carpenter + 1 helper 1.5
solid slab 1 Carpenter + 1 helper 3
flat slab 1 Carpenter + 1 helper 5
Concrete walls 1 Carpenter + 1 helper 3

RCC PADS + Gr Beams 1 steel fixer + helper 3


RAFT 5
STEEL COLUMNS 2.5
REBAR SOLID SLAB 3
FLAT SLAB 3
CONCRETE WALLS 3
Mortar Proprtions used to fix Concrete Blocks
Built up block Area Sqm = A 1 m2
Mortar thickness = t 10 mm

Mortar Mix Ratios Cement : Sand 1 4 W

L 400 mm
Block size without mortar L 400 H 200 W 250 mm
Volume of Sqm block with mortar = B 0.26 m3
One Block Area with Mortar 0.086 m2
(L+t) x (H+t)
H 200 mm
One Block Voume with out mortar 0.02 m3
No. of Blocks with mortar 11.61 No.
Net Blocks Volume = C 0.232 m3
Filling Mortar Quantity =B-C 0.028 m3 Change Blue Values ON

Dry Mix = 1.27 Wet Mix

Quantity of Cement Req. = 0.007 m3

10.14 Kg
1 Bag

Quantity of SAND Req. = 0.028 m3 45.048567 kg


Quantity of water w/c =0.4 0.00282 m3