Академический Документы
Профессиональный Документы
Культура Документы
a. certi
fi
ed
b. notarized
c. authorized
d. witnessed
8. Essenti
al vari
able # QW 403.9 has been:
a. correctlyaddressed on the W PS
b. i
ncorrectlyaddressed on the W PS
c. not addressed on the PQR
d. both B & C above
9. The posi
ti
on ofthe groove on the PQR i
s:
a. acceptable as shown
b. unacceptable -essential vari
able not addressed
c. unacceptable -positi
on shown does not correlate to plate
d. both B & C above
97
98
99
100
101
ANSW ER SHEET
W ELDING PROCEDURE REVIEW QUESTIONS
102
ASME SECTION VIII
103
ASME SECTION VIII DIVISION 1
SUBSECTIONS - INFORMATION
x General x General
x Materials x Materials
x Design x Design
x Low Temperature Operation x Fabrication
x Fabrication x Inspection and Tests
x Inspection and Tests x Marking and Reports
x Marking and Reports x Pressure Relief Devices
x Pressure Relief Devices
Mandatory Appendices
Nonmandatory Appendices
104
Subsections of
Division 1
Part UCS Requirements for Pressure Vessels Constructed of Carbon and Low-Alloy
Steels
Part UCL Requirements for Pressure Vessels Constructed of Material with Corrosion
Resistant Integral Cladding,Weld Material Overlay Cladding,or with Applied
Linings
Part UCD Requirements for Pressure Vessels Constructed of Cast Ductile Iron
Part UHT Requirements for Pressure Vessels Constructed of Ferritic Steels with Tensile
Properties Enhanced by Heat Treatment
Part ULT Alternative Rules for Pressure Vessels Constructed of Materials Having Higher
Allowable Stresses at Low Temperature
Part UHX New 2003 Addenda Rules For Shell & Tube Heat Exchangers
105
the Scope of Section VIII,
Division 1 Fired process tubular heaters
Piping systems
Piping components (pipe, flanges, bolting, gaskets, valves, expansion joints,
and fittings) and the pressure containing parts of other components (i.e.,
strainers, mixers, separators, snubbers, distribution devices, metering and flow
controlling devices) which are generally recognized as piping components
Water containing vessels with capacity of 120 gallons or less, and those which
contain air (for cushioning)
Design Pressures Rules based on vessels whose pressure does NOT exceed 3000 psi
For pressures above 3000 psi, there are usually specific additions to, and
deviations from, the rules of the Code. These special rules must be applied to
all such higher pressure vessels, before it may be stamped (new ASME VIII
Div. 3 to be developed).
x First sealing surface for proprietary fittings for which there are no rules in this
division such as gauges/instruments
106
Relief Devices and Scope includes those devices necessary to meet requirements of
Unfired Steam Boilers UG-125 through UG-136 and Appendix II
Fired Vessels and Pressure vessels or parts which are DIRECT FIRED, and which are
Fired Jacketed Steam not within the scope of Sections I, III, or IV, may be built in Kettles
accordance with the rules of this Division
U-1(d) is an important paragraph.. Contrary to what some believe, it does not limit the design of pressure vessel
to 3,000 psi. However, for pressure vessels constructed over 3,000 psi, deviations from and additions to the
rules may be necessary to satisfy the service conditions. If these deviations or additions (such as a complete
stress analysis of each component) still show the vessel meets the Code, then the item may be Code stamped.
U-1(e) is must be clearly understood to ensure a common understanding of where the “pressure vessel” ends
and where the “piping” begins.
107
manway
Denot
esCodeScopeLi
mit
ati
ons
U-1 (e) describes the minimum boundaries to establish a completed pressure vessel, but does not prohibit the
Code application beyond the terminal points, provided all of the rules are satisfied in the extension and the
materials are properly listed on the Manufacturer’s Data Report. For example, a nozzle boundary can be
extended to any length, including all connecting piping many feet or meters away from the vessel. Conversely, a
nozzle can be extended and be in place when the pressure vessel is tested but still be excluded from the Code
construction by a proper entry on the Data Report. In this case, the nozzle does not have to meet Code
requirements.
U-1(f) states that Section VIII - Division 1 includes provisions for pressure relief devices in UG-125 through UG-
136.
U-1(g) allows alternative construction of unfired steam boilers to Section VIII - Division 1, instead of ASME I, as
some jurisdictions (such as Texas) classify these pressure vessels as boilers and require them to be
constructed under Section VIII.
U-1(h) covers direct fired pressure vessels NOT within the scope of ASME I, III, or IV, and U-1(I) covering gas
fired jacketed steam kettles under 50 psi. Both of these classes of vessels may be constructed to Section VIII -
Division 1, provided it is allowed at the point of installation.
108
U-1(j) provides for "UM" stamping of pressure vessels . Pressure vessels may be stamped "UM" provided full
radiography is not a requirement, no quick-opening closures are employed, and provided the following volume
and/or pressure limits are not exceeded:
The primary difference between a pressure vessel stamped "UM" and a pressure vessel stamped "U" is that the
pressure vessel stamped "UM" will not have been inspected during construction by an Authorized Inspector.
Manufacturer’s Data Reports will not be furnished except upon specific request by the owner/user. See UG-120
for details.
U-2, GENERAL
U-2 (a) states that the user and/or his designated agent shall establish design requirements for pressure
vessels, taking into account startups, shutdowns, and upset conditions. Other design factors that the
owner/user must convey to the fabricator are:
U-2(b) covers responsibilities, and clearly states that the manufacturer of the completed pressure vessel has the
total responsibility for Code compliance. The manufacturer of the pressure vessel may subcontract for parts
and/or service to complete the pressure vessel;however, the Manufacturer that will apply the final “U” Code
stamp to the item has the ultimate responsibility to ensure that the proper documentation is received and
available for all work not done by him. ASME stamped parts with Partial Data Reports are usually the document
used to allow manufacturers to accept welded parts from one another. The system of control of subcontracted
services must be defined in each Manufacturers quality control system.
U-2 (e) requires the Authorized Inspector to make all inspections required by the rules, plus any other
inspections he deems necessary to permit him to certify that, to the best of his knowledge, the pressure vessel
meets the Code requirements. The Authorized Inspector is only required to verify that complete design
calculations exist and that are on file at the time the Data Report is signed. Any questions raised by the
Inspector must be resolved by the Manufacturer.
109
U-2(g) states that Section VIII - Division 1 does not contain rules for all types of construction and states that,
subject to the Inspector’s acceptance, other design rules may be used that will provide equivalent factors of
safety.
U-2(h) describes the methods and means to perform field erection and completion of vessels in the field.
Basically, this can occur in three ways:
(2) The manufacturer receives Partial Data Reports for the individual parts, and then Code
stamps and certifies the vessel on a master Data Report, using the partials as supporting
evidence of Code compliance;
(3) The field portion is completed by a sub-contractor and a partial Data Report is
supplied. The Manufacturer, using the sub-contractor’s partial(s) prepares the master
Data Report, and applies the full “U” Code stamp to the vessel.
SUBSECTION A
GENERAL REQUIREMENTS
PART UG -GENERAL REQUIREMENTS FOR ALL METHODS OF CONSTRUCTION AND ALL MATERIALS
UG - 1 SCOPE
Part UG establishes general requirements applicable to all pressure vessels, and shall be used in conjunction
with the specific requirements in Subsections B and C that pertain to the methods of fabrication and material.
MATERIALS
UG-4 GENERAL
(a) -This paragraph requires that materials subject to stress due to pressure must be materials conforming to
Section II - Materials Specifications and further limits these materials to materials listed in the applicable Part of
Subsection C, except where allowed in Part UG.
(b) -Non-pressure part materials attached to pressure parts do not have to conform to Section II, but if welded
must be demonstrated to be of weldable quality.
(e ) -Materials outside the limits of size and/or thickness established in a material specification may be used if
the material is in compliance with the other requirements of the specification, and no size or thickness limitations
are shown in the stress tables in Section II Part D.
(f) - The selection of the right material for the intended service is very important, and is stressed here.
110
UG-5 through UG-9
These paragraphs provide some general details on the different product forms. Particular attention should be
given to UG-8, which discusses rules for integrally-finned tubes, and UG-9, which requires welding
consumables to meet the requirements of Section VIII, Section IX, and the welding procedure to be used.
UG-12 - UG-14
Rules for bolts, studs, nuts, washers, and rods/bars are given, and are sometimes overlooked. These
paragraphs should be watched closely, as some simple requirements are given, and must be followed.
DESIGN
UG-16 GENERAL
(b) The minimum thickness of shells and heads, after forming and regardless of service shall be 1/16", exclusive
of corrosion allowance. This rule does not apply to :
(c ) Plates are allowed an undertolerance of either .01" or 6% of ordered thickness, whichever is less.
(d) Pipe undertolerance shall be per UG-40, which is specified as 12.5% of nominal thickness. This is VERY
important when calculating shells or nozzles made from pipe, as this undertolerance must be considered and
the next heavier schedule must be used to ensure adequate wall thickness for the pressure.
111
UG-20 DESIGN TEMPERATURE
These paragraphs are often overlooked and are very important to know. The maximum and minimum metal
temperatures MUST be established, and the minimum temperature may be based not only on operating
conditions, but also atmospheric conditions at the point of installation.
UG-20(f) This paragraph is very often overlooked when applying impact testing criteria from the other
subsections. This paragraph provides for “blanket” exemptions to the impact testing rules, provided all the
provisions listed (1-5) are complied with.
UG-22 LOADINGS
This paragraph requires that external loads from earthquakes and winds; reactions from piping supports and
lugs; pressure vessel weight; superimposed loads from operating equipment, supports, effects of thermal
reactions and abnormal pressures must be considered when designing a vessel. Specific rules for
“considering” these loadings are not given in the Code, however, many designers use the Pressure Vessel
Handbook or a computer program when confronted with these types of design details.
UG-24 CASTINGS
Steel casting require supplementary inspections in order to use a 90% or 100% quality factor in the design
calculations. The quality factor shall be 80% if only the basic material specification is satisfied. Castings of cast
iron and cast ductile iron are prohibited. See Mandatory Appendix 7 for more requirements on castings.
UG-25 CORROSION
The user or designated agent must tell the vessel manufacturer if corrosion allowance will be needed above and
beyond that required by the Code. This is a contractual matter, and one which the vessel manufacturer will,
undoubtedly, charge more for than for not providing such allowance. The only mandatory requirement for
corrosion allowance exists in Part UCS for pressure vessels used for air, steam, or water and this requirement
may be waived depending on the design used.
(e) Telltale holes are used in pressure vessels as an indicator that a vessel has corroded to a point of losing the
corrosion allowance. They can not be used in pressure vessels containing toxic or flammable substances. UG-
25(e) provides information on size, depth, location, and spacing of telltale holes.
112
UG-33 AND UG-34, CONVEX PRESSURE HEADS AND FLAT HEADS
Rules and formulas are given for calculating required thickness or MAWP are given.
UG-42
The strength of the weld metal, particularly the attachment fillet welds must be calculated when the standard
weld details shown in UW-16 are not applied. Several Figures and formulas are given to allow this computation
to be performed. Reinforcement of multiple openings spaced closely together are covered in UG-42.
113
UG-47 TO UG-50 BRACED AND STAYED SURFACES AND STAYBOLTS
Rules and design formulas are given for these types of vessels. This is a relatively unused section of the Code,
as not many pressure vessels are made, routinely, with stayed surfaces. The most likely usage would be for flat
heads or tubesheets that are high pressure and would require the extra bracing for strength purposes.
UG-53 LIGAMENTS
Ligaments are those spaces between multiple small openings (such as heat exchanger tubesheets) that must
be calculated to ensure that enough material is left to withstand the expected pressure. Again, this paragraph is
used basically for heat exchangers and unfired steam boilers that will be subject to multiple small openings.
FABRICATION
Each manufacturer’s accepted quality control system must establish the details for control of materials and the
transfer of markings during fabrication. The use of coded markings must be described and available for review.
All new materials supplied must include the full marking as required by the applicable material specification.
Except for pressure parts furnished under an acceptable standard such as ANSI, non-welded material formed
by a subcontractor (such as heads must have the full identification as required by the applicable material
specification and must be supported by a Material Test Report.
114
UG-84 CHARPY IMPACT TESTS
This is an extremely long and rather complicated paragraph that provides rules for HOW AND WHERE to
conduct Charpy Impact Tests when required by Subsection C for each class of material. Most importantly, it
also gives the ACCEPTANCE CRITERIA for each material based on the specific minimum yield strength.
UG-90 GENERAL
Examination (QC) requirements are established for the manufacturer and Inspection (QA) requirements are
established for the Authorized Inspector. The specific examinations required for each vessel are spelled out in
(b) (1) through (19), with appropriate references to other paragraphs which contain further information about the
subject. The vessel manufacturer must complete these examinations and provide some kind of objective
evidence (as detailed in the written QC Program) that these examinations have been successfully applied.
The Authorized Inspectors assigned duties are also spelled out in (c)(1) and (c)(2). The (c)(2) duties only apply
in a very special circumstance for multiple, duplicate pressure vessel manufacturers that may produce hundreds
of vessels per day at the same location (such as propane tank manufacturers).
The note under UG-92 explains that an Authorized Inspection Agency or AIA means an accredited inspection
agency in accordance with ASME QAI-1.
(d) - All materials must be examined prior to examination. When a corner joint is made from flat plate, the joint
must be examined prior to welding (and sometimes after welding) by PT or MT to ensure freedom from
laminations.
115
allowable working pressure. The maximum allowable working pressure for a pressure vessel is the maximum
pressure permissible at the top of the pressure vessel in its normal operating position and at the operating
temperature specified for that pressure. This is the ABSOLUTE top end that the vessel can experience, and is
the pressure that the relieving devices should be based on.
The possibility of brittle fracture at the time of the hydrostatic test must be considered. Therefore, the Code
recommends the temperature of the test water be at least 30 degrees above the MDMT. The 120 degree
maximum is intended as a safety measure to ensure personnel do not get burned. The weight of the liquid must
also be considered by the designer, for the acceptability and strength of the supports.
A procedure must be developed for each test and that acceptance of the procedure must be obtained from the
Authorized Inspector before conducting the test. The proof test shall also be witnessed by and the test results
accepted by the Authorized Inspector.
116
MARKING AND REPORTS
(e) - Note the “RT-1" , “RT-2", “RT-3" and “RT-4" stamping requirements to indicate the extent of radiography
performed. This stamping is directly related to the design joint efficiencies used which also correlates to UW-3,
UW-11, and UW-12. These paragraphs will be discussed in more detail in that section.
(f) - Note also the heat treatment designations - “HT” when the entire vessel has been stress relieved; “PHT”
when only part of the vessel has been stress relieved.
These paragraphs are all fairly straightforward, and will not be covered in detail in this course handout.
117
SECTION VIII - DIVISION 1
SUBSECTION B
There are 4 basic joint categories - A, B, C, and D. Category A joints are usually the most critical, as they
usually require the greatest degree of examination for the efficiency allowed. This follows the basic theory of
hoop stress which provides that on any given cylinder, the forces trying to open the vessel longitudinally will be
twice as strong as those trying to separate the vessel circumferentially. Therefore, the next category is B, and
those welds are usually the circumferential joints.
Category C welds connect flanges to nozzles, tubesheets, and flat heads, etc. Category D welds connect
nozzles or chambers to the main shell, and, if the Code is properly followed, will usually see the least amount of
examination (usually only visual).
See the following sketch for a further depiction of weld joint categories and where they are applied.
118
UW-5 MATERIALS
States that materials are to comply with the UG section of the Code. Non pressure parts welded to a pressure
part do not have to be fully identified, provided a satisfactory welding procedure using that material has been
tested and qualified.
(a) - “full” radiography is discussed in this paragraph. As previously shown, full radiography must be employed
if a joint efficiency penalty is to be avoided. This paragraph is saying that all of the following must be
Radiographically examined over their full length:
¾ All butt welds in shell and heads of vessel defined as lethal service. Plus nozzles over 10” NPS or 11/8
inch wall.
¾ All butt-welds over 11/2 inch thick or less as defined in UCS 57 etc. Note@ P5 materials it may be all
thicknesses.
¾ All butt welds in steam boilers exceeding 50 psi. Plus all nozzles over 10” NPS or 11/8” Wall.
¾ Additionally, other situations may require full radiography for service or excessive thickness that are
irrespective of the designers wishes, such as lethal service, unfired steam boilers or butt welds
exceeding 1.5".
Note that RT is not normally required for nozzle butt welds that neither exceed NPS 10 nor 1 1/8" wall
thickness.
(a) (5) (b) - this paragraph gives a lot of people fits. In a nutshell, it really only matters when calculating
seamless vessel sections and heads or when the vessel will be stamped “RT-2”.
¾ The paragraph says that all category A and D welds must be fully radiographed along their full
length.
If you meet these requirements then what UW-12 (a) says later on is that you select the joint efficiency from
Column (a) of Table UW-12 even though you have not done full radiography on all welds.
You only use the efficiency in Column 9 (b) of Table UW012 when the requirements have not been met.
119
(a) (7) - allows UT to be used for the final closure seam on vessels where entry cannot be made.
Absence of RT equipment is not justification for using UT.
CAUTION: There is an ASME Code Case in existence that overrides this rule when applied for thicknesses over
0.5” but does not permit manual ultrasonics.
(d), (e), and (f) - discuss RT rules for electroslag, electrogas, and inertia/friction drive welding processes.
Of course everyone spends so much time trying to understand UW-11 (a) they forget to look at UW-11 (b). For
many people working backwards helps clarify the point. UW-11 (b) discusses and defines ‘ spot’ radiography. It
is clear you may use ‘ spot’ (defined in UW-51 as a six inch area of weld) to check the weld quality and when you
do the penalty is that it drops you into column (b) of Table UW-12 for Joint Efficiency. In this case the vessel will
be stamped RT-3.
UW-11 © tells you when no radiography is required and if it is required and you do not do any then it drops you
in column 9c) of Table UW-12 for joint efficiency. In this case the vessel would be stamdped RT-4.
UW-3 discussed the CATEGORY of joints that may be used in the vessel. Now we will discuss the TYPE of
joint that can be used for each category. Joint types are listed as 1, 2, 3, 4, 5, or 6 in Table UW-12 (shown on a
following page). As you can see from this Table, the joint types are listed in the far left hand side with a narrative
description of the joint in the next column to the right. The next column lists whatever limitations there are on
using that particular type of joint (if any), and the next column states which joint categories that the joint type can
be used with.
The final 3 columns are the ones that give everyone the most problems - degree of radiographic examination.
These are the columns that are used to find the applicable joint efficiency in the formulas in Part UG (remember
UG-27, and the formula for shells, which had a factor “E” that had to be found?). This is how to arrive at that
number, and will also dictate what stamping will be applied to the vessel (remember UG-116 and the RT-1, 2 , 3
& 4 stamping?). “Full” radiography means that the weld joint has been completely radiographed for it’s full length
per UW-51 rules. “Spot” radiography means that only a portion of the weld may be radiographed to assure
quality and acceptability of the welder’s production work. “No” radiography means just that - no radiography of
the joint has been performed.
The tricky part of using this table is that different types of joints and different degrees of radiography may exist
on the same vessel, and therefore, several calculations may have to be done using the correct efficiency for the
same part of one vessel. Also, most confusing is the fact that the Code Committees state that the design
philosophy used is “consider each joint separately”, but “spot” RT requirements are based on cumulative length
of welds on the entire vessel. This has always been a little inconsistent in some people’s minds. (Note: In 1986,
the Code changed from a “whole vessel” design approach to the current philosophy of “consider each welded
joint separately” - some like it, some don’t).
120
The degree of radiographic examination of butt welds, the credit given for radiography, and the stress
reductions for not radiographing and/or using butt welds is an area greatly misunderstood by many designers. If
other than butt welds are used in the pressure vessel or if butt welds are not radiographed the penalty is an
increase in the required wall thickness by decreasing the allowable joint efficiency. However, depending upon
the service, the kind of material, or thickness of the material butt welds, radiography may become a
requirement regardless of the efficiency used in the design calculations.
The Table has been previously discussed, and requires very little further explanation, except to state that the
“limitations” and “joint category” columns are oftentimes overlooked, and must be consulted when finding the
appropriate joint efficiency to be used. Additionally, many people still cannot accept the fact that pressure
vessels can be joined with fillet welds, but as this Table states, the restrictions and efficiencies allow their use
within limitation.
As previously stated, UW-12 (d) is a “tie-in” to UW-11 (a)(5)(b), and pertains to seamless vessel sections and
heads that are not radiographed. This is an area NOT listed on the UW-12 Table, and therefore, gives many
people headaches. Just remember this - only two efficiencies apply for seamless vessels and heads joined by
Category B and C butt welds, either 1.0 for welds that meet the spot RT requirements or 0.85 for those welds
that are NOT Radiographed. Easy way to remember any Radiography E = 1.0 No Radiography E = 0.85
UW-12 (f) - requires an efficiency of .80 for the pressure welding processes, except ERW. Separate production
weld joint test plates must be made for these processes. (See UW-28).
121
UW-13 ATTACHMENT DETAILS
Provides rules and sketches for attachment of heads to shells. Discusses tapered transitions in Para (b)(3), and
requires their use when joining abutting sections differing greatly in thickness. Requirements for “offset heads”
(pressed on heads used primarily in propane tanks) are given, with mandatory PT/MT of the offset prior to
attachment of the head (Sketch UW-13.1 (k)).
122
UW-15 WELDED CONNECTIONS
This paragraph basically states that if you comply with one of the full penetration weld sketches shown in UW-
16, strength calculations are not required. For all other designs, the weld strength must be computed. Telltale
holes are required in reinforcing plates, per this paragraph.
FABRICATION
UW-26 GENERAL
UW-26 through UW-42 cover welding requirements. It is required to use an accepted welding process and to
qualify the welding procedure and welder and/or welding operator to the requirements of Section IX - Welding
Qualifications - prior to production welding.
However, welders not in the employ of the manufacturer can be used, but the manufacturer must add a list of
controls to his QC Manual and he must still qualify them per ASME IX, so it really doesn’t matter who pays
them.
123
UW-33 ALIGNMENT TOLERANCE
The alignment tolerances established in Table UW-33 must be followed. Any mismatch WITHIN the tolerance
must be faired at a 3:1 taper. If weld metal is used to taper, the PT/MT requirements of UW-42 must also be
met.
UW-39 PEENING
Peening is not prohibited, but can’t be used on the root or cap pass of welds unless subsequently PWHT’d.
Peening cannot be done in lieu of PWHT. Shot peening must be done after any required NDE and pressure
test.
124
UW-42 SURFACE WELD METAL BUILDUP
Salvaging material by weld build-up to restore metal thickness and for using deposited weld metal to obtain the
transition between transition in thicknesses is described in this section. MT or PT is required in these areas.
Appendix 6 - Magnetic Particle, Appendix 8 - Liquid Penetrant, both of these appendices reference ASME
Section V for procedural details, and both contain acceptance criteria when conducting the examinations.
125
SECTION VIII DIVISION 1
UCS-1 SCOPE
The rules in PART UCS are applicable to pressure vessels and pressure vessel parts constructed of carbon and
low-alloy steels. It is to be noted that the materials shall be limited to those listed in Table UCS-23 of ASME
Section II Part D. Part UCS should be used in combination with other materials covered in other sections of
Section VIII - Division 1. PART UCS is relatively straightforward (except for impact testing) and does not usually
create many problems for the reader.
MATERIALS
UCS-5 GENERAL
Carbon or low alloy steel having a carbon content greater than .35% shall not be welded or be oxygen cut.
Provides clear rules for the initial temperature, the up/down heating rates, and the allowed cooling after PWHT.
Allows some limited base metal repairs after PWHT, but contractual arrangements usually preclude this from
happening.
126
UCS-57 RADIOGRAPHIC EXAMINATION
Table UCS-57 is an overriding requirement that mandates full radiography of butt welds based on thickness and
material REGARDLESS of service or joint efficiency. Again, this paragraph takes precedence over the other
requirements, and must be consulted when constructing carbon/low alloy vessels.
TABLE UCS-57
THICKNESS ABOVE WHICH FULL RADIOGRAPHIC
EXAMINATION OF BUTT WELDED JOINTS IS MANDATORY
___________________________________________________________________________________
1 GR. 1, 2, 3 1 1/4
3 GR. 1, 2, 3 3/4
4 GR. 1, 2 5/8
5 GR. 1, 2 0
9A GR. 1 5/8
9B GR. 1 5/8
10A GR. 1 3/4
10B GR. 2 5/8
10C GR. 1 5/8
10F GR. 6 3/4
___________________________________________________________________________________
UCS-66 MATERIALS
This paragraph deals and the accompanying Tables are probably the most misunderstood and hardest to apply.
Basically, the idea here is not about when you MUST impact test your materials, but how to GET OUT OF
impact testing your materials. This is reasonable, because if your base metal must be impact tested, then:
x the weld metal must be impact tested (or be bought with results listed)
x the welding procedures must be impact tested upon qualification
x the production welds must be impact tested
As one can imagine, this is quite a lengthy and involved process, and can be quite expensive if not performed
correctly. Therefore, it is in the fabricator’s best interest NOT to run impact tests if it can be avoided.
Fig UCS-66 lists exemptions for various grades and types of materials. The key to using this chart is to find the
Curve assigned to the specific material in question. If the material thickness and corresponding temperature are
ON or ABOVE the assigned curve, the material is exempted from impact testing. If the point of intersection falls
below the curve, the material must be impact tested.
127
If the material must be impact tested per Fig. UCS-66 then another “out” is provided in Fig. UCS-66.1. This
graph allows the designer to “over design” the vessel by making it more thick, and thereby increasing the safety
factor. This then allows for a reduction in the minimum design metal temperature without having to perform
impact testing. The flow chart provided in Fig. UCS-66.2 explains all this in a more clear-cut fashion.
UCS-67
As previously stated, if the base metal requires impact tests, then so too does the welding procedure.
Additionally, rules are given for welds made without the use of filler metal.
MANDATORY APPENDICES
The Mandatory Appendices are VERY important and should not be overlooked. In particular, the appendices
that will usually be consulted most often are:
Remember, all of these appendices are MANDATORY, and must be applied when referenced by the main body
of the Code. Many times users forget about these requirements stuck “way in the back”, but they must still be
followed, obscure as they are.
128
Open Book Practice Questions
ASME SECTION VIII, DIV. 1 PRACTICE QUESTIONS
1. An item, which can not be found on a mill test report for material, is:
A. SA Specification number
B. Heat number
C. Allowable stress value
D. Chemical composition
2. What is the minimum thickness of plate that can be used in the shell or head of a pressure vessel?
A. 1/4”
B. 3/16”
C. 1/16”
D. There is no minimum thickness
4. Design and fabrication of power boilers is in accordance with which of the following:
A. ASME Section I
B. ASME Section VIII
C. Engineering Guides and General Specifications
D. API – Pressure Vessels
5. Which of the following types of heads will normally require the greatest wall thickness?
6. Design and fabrication of pressure vessels shall be in accordance with which of the following:
A. ASME Section I
B. ASME Section VIII
C. Engineering Guides and General Specifications
D. API – Pressure Vessels Section IV
129
7. A nozzle was originally PWHT when the vessel was constructed because of lethal service application.
The material was SA-516 Gr 70 with a thickness of 1/8 in. A full thickness repair is made. The
minimum holding time is _____ hours.
A. 1/2 hour
B. 1/4 hour
C. 1 hour
D. 4 hours
8. The maximum deviation from the true circular form of a vessel shall not exceed:
A. 2%
B. 1%
C. 10 % of the nominal inside diameter
D. 5%
9. DELETED
10. For non-ferrous and ductile cast iron, a casting quality factor of _________ maximum should be applied.
A. 80%
B. 90%
C. 100%
D. 70%
12. According to the ASME Code, Section VIII, the metal temperature during pneumatic test shall be at
least _____ above the minimum design metal temperature to minimize the risk of brittle fracture.
A. 20qF
B. 30qF
C. 40qF
D. 50qF
13. The maximum postweld heat treatment cooling rate required for a 1 1/2inch, SA-516 Gr. 70 material,
flush patch installed as part of a repair to a pressure vessel is:
A. 333qF/hr
B. 500qF/hr
C. 267qF/hr
D. 400qF/hr
130
14. Ultrasonic examination may be substituted for radiography when:
15. If a vessel is so large that it must be PWHT in more than one heat, what is the minimum overlap in the
furnace?
A. 5’
B. 10’
C. 15’
D. 50’
16. What documentation is required for a plate of SA-516 Gr. 70 material to be used in a repair procedure?
A. A certified material test report
B. A certificate of conformity
C. A material test report
D. A certified certificate of compliance
A. Only part of the complete vessel has satisfied the radiographic requirements of UW-11(a)
B. The complete vessel satisfies the requirements of UW-11(a)(5) and the spot radiography
requirements of UW-11(a)(5)(b) have been applied
C. All butt welds have been 100% radiographed
D. All butt welds have been spot radiographed per UW-52
20. If an additional ASME Code nameplate (in addition to the original nameplate) is installed on the skirt,
jacket or other permanent attachment to the vessel, how should the nameplate be marked?
A. SAMPLE
B. DUPLICATE
C. ADDITIONAL
D. EXTRA
131
21. A welded carbon steel joint has an MDMT that is colder than 120qF, at what governing thickness must
impact tested materials always be used?
A. > 4 in.
B. < 2 in.
C. 6 in.
D. 3 in.
22 The Manufacturer’s Data report for a shop fabricated single chamber pressure vessel is:
A. U-1
B. U-3
C. U-1A
D. U-2
23. An isolated rounded indication is found in a 3/4 inch thick weld. The maximum acceptable size is:
A. 0.250 in.
B. 0.156 in.
C. 0.031 in.
D. 0.568 in.
24. What is the minimum size for a liquid pressure relief valve?
A. NPS 3/4
B. NPS 1/4
C. NPS 1/2
D. NPS 1 1/2
25. If a user signs a contract to build a pressure vessel on May 1, 1997, what edition and addenda of the
Code would be mandatory?
26. Which of the following is not considered a piping component and therefore not exempt from the scope
of the Code?
A. Pipe
B. Fittings
C. Valves
D. Product storage vessel
27. Which of the following pressure vessel categories are exempt from inspection by an Authorized
Inspector during construction?
132
28. Deleted
29. Who establishes the design requirements for a new pressure vessel?
A. Manufacturer
B. Design firm
C. The user or his designated agent
D. ASME
30. Which of the following are classified as service restrictions under Section VIII, Division 1?
A. Lethal
B. Vessels operating below certain temperatures
C. Unfired steam boilers exceeding 50 PSI
D. All of the above
31. Vessels containing lethal substances are required to be postweld heat treated in what thicknesses?
A. All
B. Above 5/8 in.
C. Above 1 1/4 in.
D. Above 1 in.
32. Butt welds in vessels that contain lethal substances are required to be _____ radiographed.
A. Spot
B. Fully
C. Partially
D. None of the above
33. Pressure vessels subject to direct firing do not permit what type weld joints for Category A and B joints?
A. 3
B. 4
C. 1
D. None of the above
34. Longitudinal welded joints within the main shell or nozzles are Category _____.
A. C
B. D
C. A
D. B
35. The temperature used when calculating the required thickness of a shell or head is known as the _____
design temperature.
A. Marginal
B. Minimum
C. Maximum
D. Optimal
133
36. The acronym MDMT stands for _____.
37. Which carbon low-alloy material listed below can be exempted from impact testing per UG-84?
38. P-No. 1, Group 1 or 2 material listed on Curve A is exempted from impact testing if it does not exceed
_____.
A. 1 in.
B. 2 in.
C. 1/2 in.
D. 9/16 in.
40. If a steel casting has a weld seam with a joint efficiency of 0.70 and is examined in accordance with the
minimum requirements of the material specification, what would be the appropriate “E” value to use
when calculating the required thickness of the casting?
A. 0.70
B. 1.00
C. 0.80
D. 1.00
41. You are calculating the required thickness of a cylindrical shell under internal pressure. The inside
radius including corrosion allowance is 24 in. The corrosion allowance is 0.125 in. What inside radius
would you use?
A. 24 in.
B. 24.125 in.
C. 48.50 in.
D. 26 in.
42. A full size Charpy impact test specimen has a dimension of _____.
A. 10 mm x 11 mm
B. 0.394 in. x 0.394 in.
C. 0.394 in. x 0.393 in.
D. 0.262 in. x 0.394
134
43. What is done when full size impact test specimens cannot be obtained?
44. You are to impact test a material, which is 1 in. thick, and has a minimum specified yield strength of 55
ksi. What is the required average for the 3 specimens?
A. 20 ft-lbf
B. 15 ft-lbf
C. 30 ft-lbf
D. 50 ft-lbf
45. When full radiography is required of the Category A and D butt welds, the Category B and C butt welds
shall as a minimum meet the requirements for _____.
46. Ultrasonic examination in accordance with UW-53 may be substituted for radiography for what
condition?
A. It is never permitted
B. When radiographic equipment is not available
C. For the final closure seam if the construction does not permit interpretable radiographs
D. For longitudinal welded seams when they are in excess of 1 1/4 in.
47. Joint efficiencies for welded joints shall be in accordance with _____.
A. Subsection C
B. UW-11(a)(5)(b)
C. Paragraph UW-12(d)
D. Table UW-12
48. When a value of E is taken from column (a) of Table UW-12 what are the values for Type 1 and Type 2
welded joints?
A. 1.00 & 0.90
B. 1.00 & 0.85
C. 0.85 & 0.70
D. 0.85 & 0.65
49. What would be the value of E for a butt-welded longitudinal joint welded from both sides on pipe?
A. 1.00
B. 0.85
C. 0.45
D. 0.60
135
50. Material for pressure parts shall comply with the requirements for materials given in ___.
51. Material for non-pressure parts, which are welded to the vessel _____ prior to being used in the vessel.
A. Must be tested using PT or MT
B. Must be proven of weldable quality
C. Must be ultrasonic thickness tested
D. Must be pressure tested
52. For material which is not identifiable in accordance with UG-10, UG-11, UG-15, or UG-93, proof of
weldable quality can be demonstrated by:
53. When adjacent abutting sections differ in thickness by more than the lesser of one-fourth the thickness
of the thinner section of 1/8 in. what must be done?
54. Longitudinal welded joints of adjacent courses shall be separated by at least _____ to avoid additional
radiographic requirements.
55. Full radiography is required for which of the following butt welds:
56. Category B and C butt welds in nozzles and communicating chambers never require radiographic
examination provided they neither exceed:
A. NPS 10
B. 1 1/8 in.
C. NPS 6
D. NPS 10 nor 1 1/8 in.
136
57. What formula would be used to determine the internal design pressure for a circular unstayed flat
cover?
A. UG-34, (1)
B. UG-34, (3)
C. UG-32 (e)
D. UG-34, (7)
58. The maximum inside diameter of a welded opening in a vessel head of 1/2 in. thickness, which does not
require a reinforcement calculation, is _____.
A. 3 1/2 in.
B. 6 in.
C. 3tr
D. 2 3/8 in.
59. No two isolated unreinforced openings shall have their centers closer to each other than:
60. When calculating the required thickness of a seamless nozzle for a reinforcement problem and the
nozzle is made from ERW pipe what efficiency would be used?
A. 0.65
B. 0.90
C. 1.00
D. 0.85
61. The allowable stresses of the nozzle and shell are 17500 and 13800 respectively, what would be the
maximum strength reduction factor?
A. 1.00
B. 1.268
C. 0.788
D. 0.60
62. What happens to the formula for A in Figure UG-37.1 when fr1 = 1.0?
A. Nothing
B. Everything after the plus (+) sign is equal to 0
C. (1 – fr1) = 1
D. F becomes 0.5
63. When calculating the limits of reinforcement normal to the surface and there is no reinforcing element
installed the value of _____ is used for te.
A. 1.0
B. 0.5
C. 0
D. 32
137
64. The governing limit of reinforcement parallel to the vessel surface is the larger of:
A. R or Dn + t
B. D or Rn + tn + t
C. d or Rn + tn + t
D. 1 or 3 above
65. What is the set pressure tolerance for a pressure relief device set at 350 PSI?
A. +/- 2 PSI
B. +/- 30 PSI
C. +/- 10.5 PSI
D. +/- 15%
66. A pressure vessel, which is 50 in. inside diameter, has a flat spot. What is the maximum permitted out
of roundness at this location?
A. 2.00 in.
B. 1.00 in.
C. 0.750 in.
D. 0.500 in.
67. The formula that is to be used calculating thickness and pressure for cylindrical shells subject to
circumferential stress is found in Appendix _____.
A. 1-1, formula 2
B. 1-1, formula 1
C. 1-4, formula 3
D. 1-8, formula 1
68. When calculating the required thickness for external pressure of a shell factor B must be determined.
Considering the Do / t ratio what are the three parameters required to determine the factor?
A. Material, stress, temperature
B. Factor A, modulus of elasticity, material
C. Factor A, material, and the design temperature
D. Thickness, factor A, design temperature
69. A nozzle similar to Figure UW-16.1, sketch (e) has a shell thickness of 9/16 in. and a nozzle thickness
of 3/4 in., what is the value of tmin?
A. 9/16 in.
B. 1/2 in.
C. 1 1/2 in.
D. 1 in.
70 Two shells are to be butt welded together to form a circumferential joint. Each shell is 1” thick. What is
the maximum permitted offset?
A. 3/16 in.
B. 1/4 t
C. 1/8 in.
D. 3/4 in.
138
71. Pressure vessels with a volume of 1 1/2 cu ft and 600 PSI design pressure can be exempted from
Authorized Inspection provided they are not to be _____.
72. If a head is formed with a flattened spot what is the C factor that must be used?
A. 0.33m
B. 0.25
C. 1.2
D. 0.17
73. When performing thickness calculations for shells and tubes under external pressure what value must
first be determined?
A. L / Do ratio
B. D / D ratio
C. Do / t ratio
D. t / Do ratio
74. Reinforcing plates and saddles of nozzles attached to the outside of a vessel shall be provided with at
least one telltale hole _____ in size.
75. A pressure vessel is to be hydrostatically tested in accordance with the ASME Code. The MAWP is 654
PSI. Sd = 8600 PSI and St = 17500 PSI. What is the minimum required test pressure?
A. 981
B. 818
C. 1730
D. 1308
76. The temperature of the furnace shall not exceed _____ oF at the time the vessel or part is placed in it.
A. 600
B. 500
C. 800
D. 300
77. Ultrasonic examination of welds shall be performed using methods described in _____ of ASME Code
Section V.
A. Article 1
B. Article 4
C. Article 5
D. Article 23
139
78. Ellipsoidal heads of what ratio are calculated using the formula in UG-32?
A. 3:1
B. 2:1.2
C. 4:1
D. 2:1
79. It is recommended that no welding be performed when the metal temperature is lower than _____oF.
A. 32
B. 60
C. 0
D. 5
81. Which of the following is not considered a piping component and therefore not exempt from the scope
of the Code?
A. Pipe
B. Fittings
C. Valves
D. Product storage vessel
82. Which of the following pressure vessel categories are exempt from inspection by an Authorized
Inspector during construction?
83. Pressure vessels with a volume of 1 1/2 cu ft and 600 PSI design pressure can be exempted from
Authorized Inspection provided they are not required by the rules to be _______.
84. Who establishes the design requirements for a new pressure vessel?
A. Manufacturer
B. Design firm
C. The user or his designated agent
D. ASME
140
85. What is the date of the acceptable edition of SNT-TC-1A to be used for new construction?
A. 1992
B. 1984
C. 1996
D. 1975
87. Which of the following parts are not considered to be subject to stress due to pressure?
A. Reinforcing pads
B. Legs of the vessel
C. Shells
D. Stiffening rings
89. Welding materials only have to comply with the requirements for _____ to be used in the manufacture
of a pressure vessel.
A. Carbon content
B. Proper chemistry
C. Correct length
D. Marking or tagging
90. The Code paragraph that allows using of a material that is not fully identified with a specification
permitted by the Code is _____.
A. UG-77
B. UG-10
C. Appendix 3
D. UG-11
91. When no specific exceptions apply, the minimum thickness of the heat transfer plates of plate type heat
exchangers is _____.
A. 1/4 in.
B. No minimum
C. 1/16 in.
D. 3/8 in.
141
92. Plate material may be used at full design pressure when the mill undertolerance does not exceed
_____.
A. 12 1/2%
B. 18%
C. The value established by the owner
D. The smaller of 0.01 in. or 6% of the ordered thickness
93. Pipe is ordered by its nominal thickness, where would this manufacturing undertolerance limits be
found?
94. The dimensional symbols used in the design formulas throughout the Code represent dimensions in the
_____ condition.
A. Corroded
B. As built
C. As designed
D. Normally desirable
95. The temperature used when calculating the required thickness of a shell or head is known as the _____
design temperature.
A. Marginal
B. Minimum
C. Maximum
D. Optimal
97. Which carbon low-alloy material listed below can be exempted from impact testing per UG-84?
98. P-No. 1, Group 1 or 2 material listed on Curve A is exempted from impact testing if it does not exceed
_____.
A. 1 in.
B. 2 in.
C. 1/2 in.
D. 9/16 in.
142
99. Loadings to be considered in designing a pressure vessel are:
100. If a steel casting has a weld seam with a joint efficiency of 0.70 and is examined in accordance with the
minimum requirements of the material specification what would be the appropriate “E” value to use
when calculating the required thickness of the casting?
A. 0.70
B. 1.00
C. 0.80
D. 1.00
101. You are calculating the required thickness of a cylindrical shell under internal pressure. The inside
radius including corrosion allowance is 24 in. The corrosion allowance is 0.125 in. What inside radius
would you use?
A. 24 in.
B. 24.125 in.
C. 48.50 in.
D. 26 in.
102. What is the weld joint efficiency to be used on an NPS 12 nozzle of P-No. 1 material butt welded to a
3/4 in. shell, which has a backing strip, left in place and is spot radiographed?
A. 0.85
B. 0.60
C. 1.00
D. 0.80
103. When performing thickness calculations for shells and tubes under external pressure what value must
first be determined?
A. L / Do ratio
B. D / D ratio
C. Do / t ratio
D. t / Do ratio
104. You are calculating the required thickness for external pressure of a shell having a Do / t ratio of 66.
The actual L / Do ratio is 75. At what value would you enter Figure G on the L / Do ordinate?
A. 50
B. 75
C. 0.50
D. 0.20
143
105. When calculating the required thickness for external pressure of a shell factor B must be determined.
Considering the Do / t ratio what are the three parameters required to determine the factor?
106. The minimum required thickness of a formed head with pressure on the concave side is the thinnest
point after _____.
107. Ellipsoidal heads of what ratio are calculated using the formula in UG-32?
A. 3:1
B. 2:1.2
C. 4:1
D. 2:1
109. The UG-32 formula for determining minimum thickness of a torispherical head considers what specific
knuckle radius?
110. If a head is formed with a flattened spot what is the C factor that must be used?
A. 0.33m
B. 0.25
C. 1.2
D. 0.17
111. An unstayed flat head similar to Figure UG-34(f) is made up of two pieces welded together using a Type
2 butt joint, which is only visually examined. What joint efficiency would be applicable?
A. 0.65
B. 0.80
C. 0.90
D. 1.00
144
112. A seamless unstayed flat head similar to Figure UG-34 (b)(1) is welded to a shell using a butt weld.
What efficiency would be used to calculate required thickness if there was no radiography performed on
the circumferential weld?
A. 1.00
B. 0.55
C. 0.85
D. 0.90
113. What formula would be used to determine the internal design pressure for a circular unstayed flat
cover?
A. UG-34, (1)
B. UG-34, (3)
C. UG-32,(e)
D. UG-34, (7)
114. The maximum inside diameter of a welded opening in a vessel head of 1/2 in. thickness, which does not
require a reinforcement calculation, is _____.
A. 3 1/2 in.
B. 6 in.
C. 3tr
D. 2 3/8 in.
115. No two isolated unreinforced openings shall have their centers closer to each other than:
116. When calculating the required thickness of a seamless nozzle for a reinforcement problem and the
nozzle is made from ERW pipe what efficiency would be used?
A. 0.65
B. 0.90
C. 1.00
D. 0.85
117. The allowable stresses of the nozzle and shell are 17500 and 13800 respectively, what would be the
maximum strength reduction factor?
A. 1.00
B. 1.268
C. 0.788
D. 0.60
145
118. What happens to the formula for A in Figure UG-37.1 when fr1 = 1.0?
A. Nothing
B. Everything after the plus (+) sign is equal to 0
C. (1 – fr1) = 1
D. F becomes 0.5
119. When calculating the limits of reinforcement normal to the surface and there is no reinforcing element
installed the value of _____ is used for te.
A. 1.0
B. 0.5
C. 0
D. 32
120. The governing limit of reinforcement parallel to the vessel surface is the larger of:
A. R or Dn + t
B. D or Rn + tn + t
C. d or Rn + tn + t
D. 1 or 3 above
121. With the exception of studding outlet flanges _____ within the limits of reinforcement shall not be
considered to have reinforcing value.
A. Machined, chamfered
B. Chamfered, rounded
C. Avoided, rounded
D. Tapered, rounded
123. Material traceability can be maintained by several methods. One of those is:
124. Where service conditions prohibit the use of die-stamping for material identification, which of the
following is a substitute?
A. Magic marker
B. vibro etching
C. color coding
D. All of the above
146
125. When plates are rolled to form a longitudinal joint for a cylindrical shell they are first _____ to avoid flat
spots along the finished joint.
A. Crimped
B. Beveled
C. Radiographed
D. Visually inspected
126. When a shell section is welded into a vessel operating under internal pressure the difference between
the maximum and minimum inside diameters at any cross section shall not exceed _____ of the
nominal diameter at the cross section being considered.
A. 2%
B. Square root of Rt
C. 5/8%
D. 1%
127. When pressure parts extend over pressure retaining welds the welds shall be _____ for the portion of
the weld to be covered.
A. Left as is
B. Ground flush
C. Notched
D. Radiographed
128. Non pressure parts extending over pressure retaining welds shall be _____ or _____ to clear those
welds
A. Ground flush, notched or coped
B. Machined, beveled
C. Radiographed, MT
D. MT, PT
129. Each set of impact test specimens shall consist of _____ specimens.
A. One
B. Two sets of three
C. Four
D. Three
130. A full size Charpy impact test specimen has a dimension of _____.
A. 10 mm x 11 mm
B. 0.394 in. x 0.394 in.
C. 0.394 in. x 0.393 in.
D. 0.262 in. x 0.394 in.
131. What is done when full size impact test specimens cannot be obtained?
147
132. You are to impact test a material, which is 1 in. thick, and has a minimum specified yield strength of 55
ksi. What is the ft-lbf requirement?
A. 20 ft-lbf
B. 15 ft-lbf
C. 30 ft-lbf
D. 50 ft-lbf
133. The acceptance criteria for materials having a specified minimum tensile strength of 95,000 PSI or
greater is based on the _____.
134. A subsize impact test specimen must be used which is 0.118 in. thick. What temperature reduction
would be taken?
A. 30oF
B. 40oF
C. 80oF
D. 15oF
135. The material being impact tested has a minimum specified yield strength of 35 ksi. A _____
temperature difference is permitted.
A. 25oF
B. 15oF
C. 0oF
D. 10oF
136. When the plate material manufacturer does not performed the heat treatments required by the material
specification a letter _____ is marked next to the material specification designation on the plate.
A. T
B. G
C. NPT
D. N
138. _____ materials are the only product form that must have a material test report provided.
A. Plate
B. Pipe
C. Casting
D. Forging
148
139. A 1 in. shell is to be welded to a tube sheet 3 in. thick using a corner joint per Figure UW-13.2. What
must be done to the weld preparation in the flat plate prior to welding?
141. The maximum allowable working pressure for a complete vessel is:
142. The maximum allowable working pressure for a vessel part is:
A. P = 1.5 x MAWP
B. P = 1.25 x MAWP x St /Sd
C. P = 1.3 x MAWP x St / Sd
D. P = 3 x Design Pressure
144. A special hydrostatic pressure test is permissible which utilizes the _____ thickness including corrosion
allowance and the allowable stress at _____ temperature multiplied by 1 1/2.
A. Nominal, test
B. Minimum, design
C. Postulated, 100oF
D. Assumed, test
145. When a hydrostatic test exceeds the test pressure either accidentally or intentionally what must be
done?
149
146. When hydrostatic testing a pressure vessel which has more than one chamber, each chamber _____.
147. Single wall pressure vessels designed for vacuum service only shall be hydrostatic pressure tested at
not less than _____.
A. 1.3 times the difference between normal atmospheric pressure and the minimum design internal
absolute pressure
B. 30” of water gage
C. Two times the difference between normal atmospheric pressure and the minimum design
internal absolute pressure
D. 15 PSI
148. The required visual inspection after application of the hydrostatic test pressure is conducted at not less
than _____.
150. The recommended test temperature above the MDMT for hydrostatic testing in accordance with the
ASME Code is _____.
A. 10oF
B. 30oF
C. 20oF
D. 50oF
151. The hydrostatic test pressure shall be applied to a filled pressure vessel when _____.
A. The vessel and its contents are at about the same temperature
B. The Inspector believes it should be applied
C. Required by the test procedure
D. All personnel are at a safe distance from the test site
152. What is the maximum metal temperature that need not be exceeded during a hydrostatic pressure test?
A. 70oF
B. 30oF above the MDMT
C. 120oF
D. 10oF above the Design temperature
150
153. A small liquid relief valve installed on the vessel set to _____ times the hydrostatic test pressure is a
recommended precaution to prevent overpressure and damage
A. 3
B. 2
C. 1 1/2
D. 1 1/3
154. Except for lethal service a vessel _____ be painted, coated or internally lined prior to the hydrostatic
pressure test.
A. May
B. May not
C. Should
D. Must
155. The formula for determining the pneumatic test pressure is:
156. The metal temperature during ASME pneumatic test shall be maintained at least _____ above the
MDMT.
A. 10oF
B. 20oF
C. 60oF
D. 30oF
157. The two steps in pressurizing a vessel for the pneumatic test are:
A. Increase to one-half test pressure then in steps of one-tenth test pressure until test pressure is
reached
B. Rapidly raise to one-third test pressure then raise slowly to test pressure
C. Increase to one-third test pressure then in steps of one-twentieth test pressure
D. Raise to one-half test pressure then to full test pressure in equal steps
158. The required visual inspection after application of the pneumatic test pressure is conducted at a
pressure equal to _____ of test pressure.
A. Two-thirds
B. Four-fifths
C. One-half
D. One-tenth
159. Except for lethal service a vessel _____ be painted, coated or internally lined prior to the pneumatic
pressure test.
A. May
B. May not
C. Should
D. Must
151
160. Indicating test gages shall be connected _____.
161. When the operator controlling a pressure test cannot see the pressure gage _____.
A. A telephone system shall be installed between the test gage observer and test controller
B. A second gage shall be installed that can be observed by the test pressure controller
C. They estimate when the test pressure is reached
D. Visual communication between pressure gage observer and pressure test controller must be
established
162. An indicating pressure gage, which has a range _____, should be used for pressure tests.
163. In no case shall indicating pressure gages have a range of neither less than _____ nor more than
_____ times the test pressure.
A. 2, 4
B. 3, 4
C. 1 1/2, 4
D. 3, 5
164. A digital pressure gage having _____ may be used for pressure tests.
A. Any range
B. A range specified by the Inspector
C. A very narrow range
D. A range of only 0.5 to 6 times the test pressure
166. When magnetic particle examinations are prescribed they shall be done in accordance with Appendix
_____,
A. 12
B. 6
C. 8
D. 7
152
167. When liquid penetrant examinations are prescribed they shall be done in accordance with Appendix
_____,
A. 12
B. 6
C. 8
D. 7
168. The units of measurement that are mandatory for Manufacturer’s Data Reports and markings on
pressure vessels is:
A. U.S. Customary and metric
B. U.S. Customary
C. English
D. Metric
169. Which of the following can be found on the required marking for a pressure vessel?
170. A vessel is constructed by arc or gas welding, what symbol would appear under the Code symbol stamp
to denote this type of construction?
A. A
B. L
C. P
D. W
171. A vessel is constructed for special service as an unfired steam boiler, what symbol would appear under
the Code symbol stamp to denote this service condition?
A. UB
B. DF
C. W
D. HT
172. A vessel has been radiographed in accordance with UW-11 where the complete vessel satisfies the
requirements of UW-11(a)(5) and the spot radiography requirements of UW-11 (a)(5)(b) have been
applied, what marking would appear under the Code symbol stamp?
A. None
B. RT 2
C. RT 3
D. SR
173. A vessel has been radiographed in accordance with UW-11 where the complete vessel satisfies the
spot radiography requirements of UW-11(b), what marking would appear under the Code symbol
stamp?
A. None
B. SR 3
C. RT 3
D. RT 4
153
174. A vessel has been radiographed in accordance with UW-11 where only part of the vessel has satisfied
the radiographic requirements of UW-11(a) and none of the markings RT 1, RT 2 or RT 3 apply, what
marking would appear under the Code symbol stamp?
A. None
B. SR 3
C. RT 3
D. RT 4
175. A vessel has been radiographed in accordance with UW-11 where the complete vessel has had all butt
welds radiographically examined for their full length, what marking would appear under the Code
symbol stamp?
A. None
B. SR 2
C. RT 1
D. RT 2
176. A vessel has been designed with only visual examination required of the butt welded joints. What
marking would appear under the Code symbol stamp for this condition?
A. RT 4
B. None
C. RT 3
D. NR
177. The marking HT is used for vessels that have been _____.
178. The marking PHT is used for vessels that have been _____.
179. A pressure vessel is a single chamber and has been completely shop fabricated what Manufacturer'
s
Data Report form would be used?
A. U-1
B. P-4
C. P-1
D. U-1A
180. What Manufacturer’s Data Report form would be used for a pressure vessel part?
A. P-3
B. U-1
C. U-2
D. P-4A
154
181. All pressure vessels other than unfired steam boilers shall be protected by a pressure relieving device
that shall prevent the pressure from rising more than the greater of _____% or _____ PSI above the
MAWP.
A. 10, 3
B. 15, 5
C. 25, 10
D. 40, 3
182. What is the minimum size of liquid relief valve permitted by Section VIII, Division 1?
A. NPS 10
B. NPS 24
C. NPS 1
D. NPS 1/2
183. When a single pressure relief device is used on a pressure vessel it shall be set to operate at a
pressure not exceeding _____.
A. The MAWP
B. The operating pressure
C. The design pressure
D. The mean design pressure
A. Lethal
B. Vessels operating below certain temperatures
C. Unfired steam boilers exceeding 50 PSI
D. All of the above
185. Vessels containing lethal substances are required to be postweld heat treated in what thickness?
A. All
B. Above 5/8 in.
C. Above 1 1/4 in.
D. Above 1 in.
186. Butt welds in vessels that contain lethal substances are required to be _____ radiographed.
A. Spot
B. Fully
C. Partially
D. None of the above
155
187. Pressure vessels subject to direct firing do not permit what type weld joints for Category A and B joints?
A. 3
B. 4
C. 1
D. None of the above
188. Longitudinal welded joints within the main shell or nozzles are Category _____.
A. C
B. D
C. A
D. B
189. Circumferential welded joints within the main shell or transitions in diameter are Category _____.
A. A
B. B
C. C
D. None of the above
190. Circumferential welded joints connecting hemispherical heads to main shells, to nozzles are Category
_____.
A. B
B. A
C. C
D. D
191. Welded joints connecting flanges, tubesheets or flat heads to main shell or formed heads are Category
_____.
A. B
B. A
C. C
D. D
192. Welded joints connecting communicating chambers or nozzles to main shells or heads are Category
_____.
A. A
B. B
C. C
D. D
o
193. When a Circumferential welded joint connecting a transition in diameter exceeds 30 it is not considered
a _____.
A. Butt weld
B. Groove weld
C. Fillet weld
D. Full penetration weld
156
194. Material for pressure parts shall comply with the requirements for materials given in _____.
195. Material for nonpressure parts which are welded to the vessel _____ prior to being used in the vessel.
196. For material which is not identifiable in accordance with UG-10, UG-11, UG-15, or UG-93 proof of
weldable quality can be demonstrated by:
A. Using weld material which meets the requirements of an SFA specification
B. Preparing a butt joint test coupon from each piece of nonidentified material and making guided
bend tests
C. Satisfactory qualification of the welding procedure
D. Both 2 and 3 above
197. When adjacent abutting sections differ in thickness by more than the lesser of one-fourth the thickness
of the thinner section or 1/8 in. what must be done?
A. Provide a tapered transition of at least 3:1
B. Make a six inch radiograph
C. Nothing
D. Provide a tapered transition of at least 4:1
198. Longitudinal welded joints of adjacent courses shall be separated by at least _____ to avoid the
radiographic requirement.
199. Full radiography is required for which of the following butt welds?
200. Category B and C butt welds in nozzles and communicating chambers never require radiographic
examination provided they neither exceed:
A. NPS 10
B. 1 1/8 in.
C. NPS 6
D. NPS 10 nor 1 1/8 in.
157
201. When full radiography is required of the Category A and D butt welds, the Category B and C butt welds
shall as a minimum meet the requirements for _____.
202. Ultrasonic examination in accordance with UW-53 may be substituted for radiography for what
condition?
A. It is never permitted
B. When radiographic equipment is not available
C. For the final closure seam if the construction does not permit interpretable radiographs
D. For longitudinal welded seams when they are in excess of 1 1/4 in.
203. Joint efficiencies for welded joints shall be in accordance with _____.
A. Subsection C
B. UW-11(a)(5)(b)
C. Paragraph UW-12(d)
D. Table UW-12
204. When a value of E is taken from column (a) of Table UW-12 what are the values for Type 1 and Type 2
welded joints?
205. What would be the value of E for a butt welded longitudinal joint welded from one side?
A. 1.00
B. 0.85
C. 0.45
D. 0.60
206. A seamless vessel section is welded into a vessel with the requirements of UW-11(a)(5)(b) spot
radiography requirements met. What value of E would be used in the calculation for the shell?
A. 0.85
B. 0.65
C. 0.90
D. 1.00
207. A seamless head is welded to a vessel shell using a Type 4 joint. What value of E would be used in the
calculation for the head?
A. 0.55
B. 0.45
C. 0.85
D. 1.00
158
208. An ERW pipe is being used as the shell of a vessel, what E value would be used in the calculation of
the shell if the requirements of UW-11(a)(5)(b) were met?
A. 1.00
B. 0.85
C. 0.45
D. 0.60
209. A single unreinforced opening meeting the requirements of UG-36(c)(3) is located in a Category B weld
joint. What radiographic requirements must be met?
A. A radiograph must be taken that is two times the diameter of the hole in length
B. A six inch radiograph must be taken which is centered over where the hole will be placed
C. A twenty inch radiograph must be taken which is centered over the hole area
D. A radiograph must be taken that is three times the diameter of the hole in length
210. Strength calculations are required for which of the following nozzle configurations?
211. Reinforcing plates and saddles of nozzles attached to the outside of a vessel shall be provided with at
least one telltale hole _____ in size.
212. The largest throat size required for a tc fillet weld when only pressure loading is being considered is:
A. 3/4 in.
B. 1/3 the thickness of the nozzle
C. 3/16 in.
D. 1/4 in.
213. A nozzle similar to Figure UW-16.1, sketch (e) has a shell thickness of 9/16 in. and a nozzle thickness
of 3/4 in., what is the value of tmin?
A. 9/16 in.
B. 1/2 in.
C. 1 1/2 in.
D. 1 in.
214. When calculating the allowable load on fillet welds a joint efficiency of _____% is used.
A. 60
B. 55
C. 1.0
D. 85
159
215. Welding procedures used in welding pressure parts and in joining load-carrying nonpressure parts shall
be qualified in accordance with:
A. AWS B1
B. ASME Section IX
C. ASME Section VIII
D. Company engineering specifications
216. When welding nonpressure-bearing attachments, which have no load-carrying function, is made by any
automatic welding process procedure qualification testing is:
217. Each welder and welding operator shall be assigned a/an _____ by the manufacturer/repair firm.
A. Clock number
B. Welding helmet
C. Blue uniform
D. Identifying number, letter or symbol
o
218. It is recommended that no welding be performed when the metal is lower than _____ F.
A. 32
B. 60
C. 0
D. 5
A. Removed completely
B. Ground on the starting and stopping ends
C. Examined with the PT method
D. Either 1 or 2
220. Surfaces to be welded shall be cleaned within what distance from the weld joint?
A. 1”
B. Two times the plate thickness
C. There is no mandatory distance
D. As required by the inspector
221. Two shells are to be butt welded together to form a circumferential joint. Each shell is 1” thick. What is
the maximum permitted offset?
A. 3/16 in.
B. 1/4 t
C. 1/8 in.
D. 3/4 in.
160
222. What is the maximum permitted weld reinforcement for a butt in a pressure vessel shell that is 1 1/2 in.
thick?
A. 1/2 in.
B. 3/32 in.
C. 1/8 in.
D. 1/4 in.
223. When welds are identified by stamping, each welder or welding operator shall stamp their identification
at what intervals for steel fabrications?
A. 6 ft.
B. 2 ft.
C. 10 ft.
D. 3 ft.
224. Peening shall not be used on which of the following welds if the vessel is not subsequently post weld
heat treated?
225. What is the minimum overlap that must be provided when a vessel is heat treated in more than one
heat in a furnace?
A. 10 ft.
B. 5 ft.
C. No minimum specified
D. 15 ft.
227. An example of nominal thickness for the purpose of determining heat treatment time is:
228. Surface weld metal buildup is required to be examined over the full surface of the deposit by which of
the following?
A. Radiographic
B. Ultrasonic
C. Magnetic Particle
D. Acid etching
161
229. The Inspector shall assure that which of the following has been accomplished?
230. When pneumatic testing is used instead of hydrostatic testing which of the following welds must be
examined with MT or PT?
231. When full radiography is required the radiographic personnel shall be qualified to which standard?
A. SNT-TC-1A
B. ACCP
C. CP-189
D. Any of the above
232. A longitudinal butt weld is being fully examined. The weld is 3/4 in. thick which includes a 1/16 in.
reinforcement. What is the longest elongated inclusion permitted?
A. 3/16 in.
B. 1/4 in.
C. 3/4 in.
D. 1/2 t
233. For spot radiography, one spot shall be examined on each vessel for each _____ of length.
A. 50 ft.
B. 25 ft.
C. 60 ft.
D. 10%
A. 24 in.
B. No minimum specified
C. 12 in.
D. 6 in.
235. When a spot radiograph does not meet Code requirements _____.
A. The entire increment will be acceptable if the weld is repaired at the failed spot
B. Two additional spots shall be examined
C. One additional spot shall be examined
D. The entire increment must be rewelded and a new spot examined
162
236. Ultrasonic examination when required is performed in accordance with _____.
A. Section V, Article 5
B. Appendix 8
C. Appendix 12
D. Appendix 7
A. 0.035
B. 0.35
C. 3.5
D. 10
238. SA-36 SA-283 Grades A, B, C, and D and G 40.21 38W steel plates may be used as pressure parts for
which of the following applications?
239. The term nominal thickness for determination of postweld heat treatment holding time is defined as:
240. When pressure parts of two different P-Number groups are joined by welding the postweld heat
treatment shall be that specified in:
A. UCS-66 or UHT-56
B. UCS-56 or UHA-32
C. UHT-56 or UHA-32
D. UNF-56 or UCS-56
o
241. The temperature of the furnace shall not exceed _____ F at the time the vessel or part is placed in it.
A. 600
B. 500
C. 800
D. 300
242. Above 800oF the heating rate shall not be more than _____.
163
243. During the postweld heat treatment holding period there shall be no greater difference than _____oF
between the highest and lowest temperature throughout the portion of the vessel being heat treated.
A. 150
B. 200
C. 300
D. 250
244. During the heating and cooling periods, the furnace atmosphere shall be controlled as to avoid _____.
A. Excessive corrosion
B. Excessive bending
C. Excessive stress
D. Excessive oxidation
o
245. Above 800 F cooling shall be done in _____.
A. A furnace
B. A furnace or cooling chamber
C. A cooling chamber
D. Still air
246. Above 800oF the cooling rate shall not be more than _____.
A. 1100oF
B. 1200oF
C. 900oF
D. 600oF
248. What is the minimum holding time for a P-No. 1 Group 2 welded joint 2 in. thick?
A. 4 hours
B. 2 hours 15 minutes
C. 2 hours
D. 3 hours
249. What is the minimum holding time for a P-No. 1 Group 3 welded joint 1/8 in. thick?
A. 1 hour
B. 12.5 minutes
C. 15 minutes
D. None of the above
164
250. What is the minimum holding time for a P-No. 3 Group 2 welded joint 6 in. thick?
A. 3 hours
B. 3 hours 30 minutes
C. 2 hours
D. 5 hours
251. A welded joint in a P-No. 1 Group 1 material is 1 3/16 in. thick. No special service requirements apply.
What would the minimum holding time be?
252. The special service conditions of UW-2 apply to a P-No. 1 Group 3 material. Which of the following can
o
be exempted from PWHT if a minimum 200 F preheat is applied?
A. Groove welds not over 1/2 in. that attach nozzles with an inside diameter of 2 in.
B. Fillet welds with a throat thickness of 3/4 in. that attach nonpressure parts to pressure parts
C. Any weld less than 1 1/2 in.
D. Any weld not over 1 1/4 in.
253. The maximum depth of a repair weld using the temper bead process that does not require a repostweld
heat treatment for a P-No. 1 Group 2 material is _____.
A. 2 in.
B. 1 1/4 in.
C. 1 1/2 in.
D. 5/8 in.
254. After completing all welding, the repair area shall be maintained at a temperature of _____ for a
minimum period of _____ hours.
o
A. 300-400 F 5 hours
B. 400-500oF 5 hours
C. 450-550oF 4 hours
D. 400-500oF 4 hours
255. The alternative postweld heat treatment temperate of 950oF is to be used for a P-No. 1 Group 2 weld
joint of 4 in. thick. What would the minimum holding time be?
A. 10 hours 45 minutes
B. 10 hours
C. 4 hours
D. 2 hours 30 minutes
165
256. For P-No. 1 Group 1 material full radiography is required when the thicknesses exceeds _____ in.
A. 0
B. 1 1/2
C. 1 1/4
D. 5/8
257. Unless otherwise exempted impact testing is required for a combination of thickness and _____.
258. Components, which are to be evaluated to establish impact test exemptions, are:
A. Shells
B. Heads
C. Attachments, which are essential to the structural integrity of the vessel when, welded to
pressure retaining components
D. All of the above
259. The governing thickness tg for a corner, fillet or lap welded joint is defined as:
260. When the governing thickness for a welded joint exceeds _____ in. and is colder than _____oF impact
tested material shall be used.
A. 4, -50
B. 4, 120
C. 6, 120
D. 2, -50
261. The governing thickness of a flat nonwelded tubesheet of 16 in. thickness is:
A. 4 in.
B. 16 in.
C. Dependent on the attaching shell thickness
D. 6 in.
262. If the governing thickness of a nonwelded part exceeds 6 in., below what MDMT must the material be
impact tested?
A. 100oF
B. 60oF
C. 120oF
D. None of the above
166
263. What is the basic minimum design metal temperature for a SA-216 Grade WCB casting which is
produced to a fine grain practice and water quenched and tempered with the largest nominal thickness
1 1/2 in.?
A. 88oF
B. 14oF
C. 43oF
D. 51oF
264. When the coincident ratio as defined in Figure UCS-66.1 is 0.70 what is the further reduction in the
MDMT of the material?
A. 20oF
B. 30oF
C. 40oF
D. 110oF
265. No impact testing is required for B16.5 steel flanges used at design metal temperatures no colder than
_____oF.
A. 120oF
B. -20oF
C. -50oF
D. 20oF
266. No impact testing is required for UCS materials less than _____ in. thick.
A. 1.000
B. 0.099
C. 0.100
D. 0.250
267. If postweld heat treating is performed on a weld joint joining P-No. 1 materials when not otherwise
required by Section VIII an additional _____oF in impact testing exemption temperature may be given to
the minimum permissible temperature from Figure UCS-66.
A. 30
B. 35
C. 50
D. 70
268. The formula that is to be used calculating thickness and pressure for cylindrical shells subject to
circumferential stress is found in Appendix _____.
A. 1-1, formula 2
B. 1-4, formula 3
C. 1-1, formula 1
D. 1-8, formula 1
167
269. When evaluating rounded indications thickness “t” is the thickness of the weld _____.
270. A butt weld is 1/2 in. thick with the maximum weld reinforcement on each side. The maximum
acceptable size of a random rounded indication is _____ in.
A. 0.168
B. 0.125
C. 0.250
D. 0.063
271. For magnetic particle examinations, only indications that are greater than _____ in. shall be considered
relevant.
A. 1/8
B. 1/32
C. 1/16
D. 1
272. Which of the following are acceptance standards for liquid penetrant examination?
A. Relevant linear indications
B. Relevant rounded indications greater than 3/16 in.
C. Four or more relevant rounded indications in a line separated by 1/16 in., or less
D. All of the above
273. Liquid penetrant examiners are certified by the manufacturer with a _____.
A. NDE examiners certification
B. Certificate of Competency
C. SNT-TC-1A certification
D. None of the above
274. Ultrasonic examination of welds shall be performed using methods described in _____ of ASME Code
Section V.
A. Article 1
B. Article 4
C. Article 5
D. Article 23
275. Personnel performing examinations of welds shall be qualified in accordance with _____.
A. SNT-TC-1A
B. PCS-185
C. PAAC
D. Manufacturer’s standard
168
276. For UT, other than cracks, lack of fusion and incomplete penetration, other imperfections are
unacceptable if the indications exceed the reference level and have lengths, which exceed:
277. The manufacturer shall maintain a record of all UT reflections from uncorrected areas that exceed
_____% of the reference level.
A. 60
B. 50
C. 100
D. 20
278. The Manufacturer’s Data Report form used for a single chamber, completely shop fabricated vessel is:
A. U-3
B. U-1
C. U-1A
D. U-4
279. The Manufacturer’s Data Report form used for a part of a vessel is:
A. U-2
B. U-1A
C. U-3
D. U-4
169
ANSWER SHEET
ASME QUESTIONS
1. C
170