OWNER
CONSULTANT: TCE CONSULTANCE ENGINEERS
LIMITED
Shanghai, China
SUBCONTRACTOR:
HUIBEI FIRST ELECTRIC POWER
CONSTRUCTION ENGINEERING
COMPANY
BTG PACKAGE FOR 4 x 300
MW COAL BASED THERMAL
EPS COMMISSIONING SCHEME POWER STATION AT JAIGAD,
RATNAGIRI DIST.
MAHARASHTRA
REV. NO : 0
ENDORSEMENTS
0 2009/9/2
PREFACE
This commissioning scheme is worked out under the General
Contract of BTG package, manufacturer requirements combined
with the characteristic of 300MW Unit and relevant experience.
This scheme instructs the commissioning scope, flow and method
as well as the required material, resource and safety precaution
required. Since certain part of the document needs to be revised in
accordance with actual condition at site, this scheme is only for the
reference of commissioning activities instead of the guidance for
detailed execution.
CONTENTS
4. Attention ..............................................................................................5
C. Measure earthing resistance and the result shall comply with requirement;
2.5 Check loop logic and it shall be complied with design requirement;
2.7 After the test of above items are complete and ensure there is no error, do entire
ESP start-up test to make it reached design requirement.
After above test is complete and accepted with signature on acceptance sheet, ESP
no-load field charging test can be carried out, the procedure is as following:
3.1 Check entire field to see if there is any foreign matters; if it is confirmed there is
no foreign matter, close all manholes and attach sealing strip and special personnel
to be assigned keep watch to it for ensuring safety;
3.3 Gradually increase voltage, and listen by ear outside ESP to ensure if there is
any discharge sound. Increade the voltage to rated value required by manufacturer,
record voltage and current value by stages during the voltage elevating period.
3.4 Gradually adjust the field voltage to “0”, and then slowly raise voltage in the mean
time start rapping device, record voltage and current value by stages;
3.5 After the ESP no-load field charging test is qualified, sign the acceptance sheet.
4. Attention
4.1 During the construction and commissioning period, closely cooperate with
mechanical specialty, and dispose each defects and fault at any moment;
4.2 While carrying out ESP no-load field charging test, two persons are required to
monitor the charged equipment, mechanical and commissioning personnel must
cooperate closely, power must be broke while dispose the defect so as to avoid
accident.
The qualification inspection items sheet is compiled under the Contract for India
Ratnagiri 4×300MW Thermal Power Station Project, relevant requirement and
requirement of owner carry out inspection one by one.
Due to the particularity of concealed project (such as underground pipes, earthing net,
inner inspection of transformer, secondary grouting, etc.), special control procedure
is carried out during the construction procedure, strictly comply with acceptance
system and contact related department in time for inspection and acceptance.
If any unqualified item is found during inspection, it is forbidden to carry out next
procedure while last procedure is unqualified, repair and rectify the unqualified work
unconditionally until the work is qualified.
As per relevant regulation in the Contract for India Ratnagiri 4×300MW Thermal
Power Station Project, set up start-up commissioning team before start-up, supervise,
check and accept the individual trial operation items and unite trial operation, carry
out construction completion acceptance and document hand-over with referance to
the Contract for India Ratnagiri 4×300MW Thermal Power Station Project.