Вы находитесь на странице: 1из 5

TECHNICAL ARTICLE

AS PUBLISHED IN

The Journal January 2019 Volume 137 Part 1

If you would like to reproduce this article,


please contact:

Alison Stansfield
MARKETING DIRECTOR
Permanent Way Institution
alison.stansfield@thepwi.org

PLEASE NOTE THE OPINIONS EXPRESSED IN THIS JOURNAL


ARE NOT NECESSARILY THOSE OF THE EDITOR OR OF THE
INSTITUTION AS A BODY.
TECHNICAL

Implementation of AUTHOR:

a phased array rail Joseph Buckley


Level X NDT

weld inspection Daniel Harrison, Peter Willats


Ops-LU Engineering

programme for
London Underground

London Underground
INTRODUCTION 2. Some of the broken welds had been in use 2. Existing Welding Inspectors are qualified
for years before failing. Often these breakages and experienced welders but are not ultrasonic
The London Underground system has been are associated with nearby track work, which NDT personnel. It is desirable that procedures
steadily expanding since the Metropolitan changed the stresses on welds. are reasonably simple and robust, allowing
Railway, consisting of eight stations and 6km them to carry out the work with limited
of track each way, opened in 1863. Currently Currently all new welds carried out on the additional training.
it contains around 270 stations and 400 km underground network are independently
of operational track. It is estimated that this inspected within 28 days of cast. The 3. It is desirable that the weight and bulk
track contains around 50,000 welds, many existing procedures include both visual and of equipment is minimised so that the NDT
produced using the aluminothermic process. dimensional checks. While cracking or porosity equipment, along with the other equipment
This process uses a mixture of metal oxides are cause for rejection where visible on the required for weld inspection, can be carried
and additives in a crucible above a mould surface, this approach cannot find ‘hidden’ out by one member of staff. Access to the
formed around the region to be welded. The defects. inspection location may involve walking some
mixture is ignited, and an exothermic reaction distance and use of long flights of stairs is
occurs, causing superheated metal to run into A programme was initiated in 2016 to improve frequent.
the mould. Whilst this process is extremely performance in these areas; initially by
reliable, manufacturing defects can sometimes investigating the possibility to incorporate 4. It was necessary to comply with many LUL
occur, see image 1. additional requirements into the weld and railway standards such as track standards
inspection procedure. and equipment approval etc. Trade Unions
With so many joints it is inevitable that there also needed to approve changes in working
will be a few fractures. However recent LUL owned, and were familiar with, Sonatest practice; this presented some disagreements
changes to 24 hours running on Fridays and Prisma phased array instruments. The author as their representatives, whilst very supportive,
Saturdays on some lines, which reduces had provided training to LUL while working needed to be kept involved and satisfied.
the time available for repair and inspection at Sonatest and was asked to assist with
work, and the introduction of digital signalling, additional training and assistance in developing INITIAL INVESTIGATIONS
have increased the reliability requirement procedures.
significantly. Heavier and more frequent trains (See image 2) Three different approaches
have increased substantially the load on the CONSTRAINTS were evaluated:
track. Analysis of weld related track breakages
has shown that: 1. Like all railways track access has very SHEAR-WAVE ANGLE BEAM SCAN OF THE
limited hours and safety is paramount. It FOOT OF THE RAIL
1. Defect origination mechanisms are typically is necessary that any potentially unsafe
either weld porosity, or cracking resulting from situation can be identified immediately, so that This was really the only method considered for
weld induced stresses. A particular cracking appropriate precautions (e.g. clamping track this region – It is a reasonably straightforward
issue was ‘hot tears’ i.e. movement of the joint and/or imposing speed restrictions) can be test, similar in many ways to a conventional
before the weld had fully cooled. implemented before trains must run. butt-weld inspection. The rail foot is
approximately 20mm thick and tapers slightly.

Image 1: Expansion of London Underground network Image 2: Proposed scan locations

21
TECHNICAL

This taper does mean that multi-skip testing


will give inconsistent positioning across the
width of the rail foot but did not appear to affect
defect detection significantly. The geometry
of a ‘good weld’ gives minimal spurious
indications. See image 2.

Reflections from the underside of the rail


outside the weld region were sufficiently
reliable to find defects at the top of the weld
using a ‘skip’ technique. A number of probe
types were evaluated for this. While there
Image 3: Foot of rail scan would have been a preference for using a
probe with a replaceable wedge, the ones tried
were a bit too large to be easily manipulated in
the critical region. A 4MHz 16 element array
probe was used (8x9mm, with an integral
wedge in a standard size housing).
See image 3.

Results were generally unambiguous; once


operators had seen a ‘real crack’ they were
unlikely to be confused by surface geometry
and similar indications.

SHEAR WAVE ANGLE BEAM SCAN FOR


WELD POROSITY
Image 4: Shear wave angle beam scan for weld porosity (good weld shown)
While this was initially expected to be a
promising technique it was found that:

1. Work–hardening and similar effects on


the top of the rail made it very inconsistent on
installed rails.

2. The normal level of ‘weld noise’ varied


significantly See image 4 and thus it was
difficult to create criteria to reliably distinguish
scattered porosity defects from normal welds,
especially without very consistent calibration.

3. A ‘skip’ technique resulted in a long path


length; small variations in material attenuation
Image 5: Longitudinal wave scan for weld porosity
could greatly affect sensitivity. Without
skipping it was difficult to test the upper region
of the weld.

4. In a few cases there were bolt holes


obstructing regions of the weld, making it
difficult or impossible to inspect them. These
were always present where suspect welds
had been clamped. This effectively meant that
no weld that had failed or was suspect (and
had been subsequently clamped) could be
inspected, making technique validation almost
impossible. Although this technique has some
advantages it was felt that without complicating
Image 6: Results on weld with severe porosity the procedure to ensure very consistent
calibration, results were likely to be difficult to
interpret.

LONGITUDINAL WAVE ‘ZERO-DEGREE’


SCAN FOR WELD POROSITY

This is the approach that was eventually


selected. A 16 element probe was used with
a scan over +/- 20 degrees. Because the
probe was used without a wedge or delay line,
protective tape was specified. This gave a
‘clean’ response on a good weld, see image
5. It was thus much easier to evaluate, and
the identification of defects did not require a
Image 8: Equipment verification on CB87M block
precise calibration.

22
TECHNICAL

previously was integrated into updates in


the relevant LUL procedures and welding
specifications. The internal work instruction
for aluminothermic weld inspections was also
updated. These documents are mandatory
for all aluminothermic welds carried out on
the underground network. Reporting forms
‘Aluminothermic weld inspection report’
(completed for all welds) and ‘Report of
noncompliant weld’, were also updated
to include new sections for the ultrasonic
reporting. Once this had been done (see
image 9) the procedure was ready to be rolled
out as part of the routine weld inspection.
Welds are inspected visually and dimensionally
at the time of manufacture, and must have an
independent final inspection within 28 days of
being placed into service; this now included
Image 7: Response from isolated porosity defect phased array inspection.

During the first phase, internal LUL personnel


were used. However much of the welding and
inspection work is carried out by external sub-
contractors, so it was necessary to develop
a standardised training and certification
procedure to ensure that weld inspectors
carrying out the Phased array inspection are
approved to do so.

OPERATOR TRAINING

Level X currently provides “equipment


familiarisation” training for users of phased
array equipment. The existing course was
adapted and additional content added for the
rail inspection requirement. As noted, most
Image 9: Related TFL documents of the weld inspection personal have minimal
ultrasonic knowledge or experience, so it was
Tests were carried out on a number of samples A key point was to simplify the procedure so necessary to develop an appropriate course
containing defects due to porosity. The rail that it could be used by relatively unskilled (in assuming minimal prior knowledge, and giving
in image 6 had been in use for some years NDT) operators. what was necessary to follow the procedures.
before it broke.
Accordingly: The course that was developed contained the
Because the weld is ‘full’ of porosity the • ‘Standard’ probes were used. Using several following components:
energy is all reflected at the top of the weld different probes of the same type it was
and the lower section is ‘quiet’. Operators are confirmed that the probes were sufficiently • Classroom training covering theory, use of
taught to recognise this as a sign of gross consistent and that a standard configuration the equipment and the detailed procedures. A
porosity. Isolated indications present in a file was acceptable for the required test. brief exam was included.
more familiar manner. Attempts were made to
induce deliberate porosity in this weld. After • After selection of probe and configuration • On track practical / mentoring comprising
investigation it was milled down to investigate file, correct operation is verified using the one night with instruction as necessary and
the indications. See image 7. CB87M block. Other than checking correct one night with minimal assistance to confirm
operation no attempt was made to ‘fine competence.
PROCEDURE DEVELOPMENT calibrate’ the test.
Subject to adequate examination and practical
Once the approach had been agreed, outline • Reporting is intended to be simple process performance trainees are approved to carry
procedures were developed. As noted in the – pass, fail or ‘monitor’ actions are applied; out the inspection work and were issued with
constraints, weight is a critical aspect for (typically the monitor category applies to minor a credit-card size approval ‘ticket’. This, in
the practical implementation, so calibration/ porosity or indications where the operator conjunction with their LU access pass and
verification procedures were developed using felt uncertain about ‘minor’ indications). The other relevant approvals, demonstrates
the lightweight CB87M calibration block procedure specifies that all ‘fail’ or ‘monitor’ competence to inspect welds in accordance
already in wide use in the railways. N.B. this indications are to be recorded, screen images with LUL procedures.London Underground
block weighs approximately 1.2 kg with its taken and emailed to LUL NDT experts, now have greater confidence in all new welded
protective case, see image 8. There would be and, in the case of a ‘fail’ appropriate track joints and expect to see positive performance
some scope for reducing this weight further by protection and minimum actions are to be improvements as the new procedures are
using a custom test block, but it was felt that taken immediately. introduced throughout the network.
this was not justified.
IMPLEMENTATION For more information please contact the
A standard kit was developed containing all primary author or refer to the ‘papers’ section
phased array inspection related items. This After testing and investigation of new, on www.levelxndt.com
was issued to operators along with the phased suspect and in-service welds by LUL
array instrument. NDT specialists, the approach detailed

23
thepwi.org

Journey with us

FaceBook: PermanentWayInstitution

Twitter: @PermWayInstit

LinkedIn: Permanent Way Institution

You Tube: The PWI

Instagram: @the_pwi

Вам также может понравиться