Академический Документы
Профессиональный Документы
Культура Документы
AS PUBLISHED IN
Alison Stansfield
MARKETING DIRECTOR
Permanent Way Institution
alison.stansfield@thepwi.org
Implementation of AUTHOR:
programme for
London Underground
London Underground
INTRODUCTION 2. Some of the broken welds had been in use 2. Existing Welding Inspectors are qualified
for years before failing. Often these breakages and experienced welders but are not ultrasonic
The London Underground system has been are associated with nearby track work, which NDT personnel. It is desirable that procedures
steadily expanding since the Metropolitan changed the stresses on welds. are reasonably simple and robust, allowing
Railway, consisting of eight stations and 6km them to carry out the work with limited
of track each way, opened in 1863. Currently Currently all new welds carried out on the additional training.
it contains around 270 stations and 400 km underground network are independently
of operational track. It is estimated that this inspected within 28 days of cast. The 3. It is desirable that the weight and bulk
track contains around 50,000 welds, many existing procedures include both visual and of equipment is minimised so that the NDT
produced using the aluminothermic process. dimensional checks. While cracking or porosity equipment, along with the other equipment
This process uses a mixture of metal oxides are cause for rejection where visible on the required for weld inspection, can be carried
and additives in a crucible above a mould surface, this approach cannot find ‘hidden’ out by one member of staff. Access to the
formed around the region to be welded. The defects. inspection location may involve walking some
mixture is ignited, and an exothermic reaction distance and use of long flights of stairs is
occurs, causing superheated metal to run into A programme was initiated in 2016 to improve frequent.
the mould. Whilst this process is extremely performance in these areas; initially by
reliable, manufacturing defects can sometimes investigating the possibility to incorporate 4. It was necessary to comply with many LUL
occur, see image 1. additional requirements into the weld and railway standards such as track standards
inspection procedure. and equipment approval etc. Trade Unions
With so many joints it is inevitable that there also needed to approve changes in working
will be a few fractures. However recent LUL owned, and were familiar with, Sonatest practice; this presented some disagreements
changes to 24 hours running on Fridays and Prisma phased array instruments. The author as their representatives, whilst very supportive,
Saturdays on some lines, which reduces had provided training to LUL while working needed to be kept involved and satisfied.
the time available for repair and inspection at Sonatest and was asked to assist with
work, and the introduction of digital signalling, additional training and assistance in developing INITIAL INVESTIGATIONS
have increased the reliability requirement procedures.
significantly. Heavier and more frequent trains (See image 2) Three different approaches
have increased substantially the load on the CONSTRAINTS were evaluated:
track. Analysis of weld related track breakages
has shown that: 1. Like all railways track access has very SHEAR-WAVE ANGLE BEAM SCAN OF THE
limited hours and safety is paramount. It FOOT OF THE RAIL
1. Defect origination mechanisms are typically is necessary that any potentially unsafe
either weld porosity, or cracking resulting from situation can be identified immediately, so that This was really the only method considered for
weld induced stresses. A particular cracking appropriate precautions (e.g. clamping track this region – It is a reasonably straightforward
issue was ‘hot tears’ i.e. movement of the joint and/or imposing speed restrictions) can be test, similar in many ways to a conventional
before the weld had fully cooled. implemented before trains must run. butt-weld inspection. The rail foot is
approximately 20mm thick and tapers slightly.
21
TECHNICAL
22
TECHNICAL
OPERATOR TRAINING
23
thepwi.org
Journey with us
FaceBook: PermanentWayInstitution
Twitter: @PermWayInstit
Instagram: @the_pwi