Академический Документы
Профессиональный Документы
Культура Документы
net/publication/325710777
CITATIONS READS
0 2,023
3 authors:
1 PUBLICATION 0 CITATIONS
Chandigarh University
11 PUBLICATIONS 4 CITATIONS
SEE PROFILE
SEE PROFILE
Uma Malik
3 PUBLICATIONS 3 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
AN EFFICIENT ANALYSIS OF LINEAR AND NONLINEAR MODEL USING VARIOUS REGRESSION LEVEL FOR FLUID DAMPERS View project
Investigation of Expected Seismic Performance on Existing Buildings: A Case Study View project
All content following this page was uploaded by Khushpreet Singh on 12 June 2018.
PROJECT MANAGEMENT IN
IN CONSTRUCTION
USING PRIMAVERA
Hitanshu Saini, Khushpreet Singh, Uma Malik
Department of Civil Engineering, Chandigarh University,
Gharaun, Punjab, India
ABSTRACT
For the successful completion of a project, planning and scheduling are two most
important factors. The demand of construction industry requires a precise planning,
scheduling and management which can allow the overall optimization of the cost, time
and resources. Due to the increase in workloads and shrinking resources
resources public work
department found new technology which helpshelps to manage the project easily. Project
management software is used as a tool for managing and organizing work which helps
industries to grow in a rapid
ra manner. There are so many computer software
softw are
available in market now a days which is such as MSP, Primavera p6,etc…for doing
project management. With the help for these software proper planning and controlling
of project can be done. Primavera can easily compare between the planned progress
off construction work and actual progress of construction project. Project management
software Primavera P6, include collecting, recording, monitoring, controlling and
reporting information concerning project performance. In this study, study the project
controlling and monitoring can be done and the causes of delays can be find out. For
doing this a four storey building of Ayurveda research center has be taken, which is
situated in the Pandoh, Mandi(H.P). A scheduled project on Primavera P6 was
monitored and typess of delays were analyzed which in turn increased the total time of
the project.
Key words: construction; optimization; management; Primavera; controlling.
controlling
Cite this Article: Hitanshu Saini, Khushpreet Singh, Uma Malik,
Malik Project Management
in Construction using Primavera
imavera. International Journal of Civil Engineering and
Technology, 8(8), 2017,, pp. 538–549.
538
http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=8&IType=8
1. INTRODUCTION
Construction industry is the second largest industry in India. The time available for achieving
its goal is shrinking. There are so many problems being faced by the industry that must be
taken care of as Project management is the procedure of the utilization of learning, aptitudes,
devices, and strategies to extend exercises to meet venture prerequisites. There are mainly six
phases of project management which is as follows
http://www.iaeme.com/IJCIET/index.
IJCIET/index.asp 538 editor@iaeme.com
Project Management in Construction using Primavera
• Project Definition: Defining the goals, objectives and critical success factors for the project
• Project Initiation: Everything needed to set up the project before work can start
• Project Planning: Detailed plans of how the work will be carried out, including time, cost
and resource estimates
• Project Execution: Doing the work to deliver the product, service or desired outcome
• Project Monitoring & Control: Ensuring that a project stays on track and taking corrective
action to ensure it does
• Project Closure: Formal acceptance of the deliverables and disbanding of all the elements
required to run the project
There are so many software are available in the market. But now a days, MSP and
Primavera are most popular software which is used. Primavera is amazing software which can
be used for small as well as large project. In this software we can control and monitor as many
projects at one time.
2. PRIMAVERA
Primavera is used for making project management smooth. It is helpful in civil engineering
for creating strategies, controlled the delay of project and determines the optimum use of
resources.. Primavera is used to complete the project within specified time and cost. It is the
application of skills, tools and techniques to project activities in order to fulfill the demand of
the owner. Primavera program is used to scheduling, controlling and estimating all types of
projects.
P6 EPPM is a completely online interface with the goal that venture group can get to the
venture data at anyplace and whenever. P6 EPPM can give arranging, planning, cost and asset
administration programming that empowers association to settle on educated choices and
enhance their capacity to convey projects and tasks on time and on spending plan.
P6 EPPM likewise helps in
• It is a far reaching venture administration arrangement supplier.
• Used and recognized comprehensively
• It can deal with different tasks in a brought together area
• It gives the choice to incorporate ERP or bookkeeping framework.
• It is an electronic venture administration, giving the venture group access to their activities
anyplace and whenever.
• It is a 100% online UI that covers the entire venture administration lifecycle.
2.2. Delays
There are several definitions for delay. In the construction management simplest definition is
given by Mubarak (2005) as “ a condition or an event that result in finishing the project later
than stipulated in the contract.” In another study, to make something happen in later than
expected time.
Types of Delays:
• Critical or noncritical
• Excusable or non excusable.
• Compensable or non compensable
• Concurrent or non concurrent
3. METHODOLOGY
• Personal interviews with working people at site.
• Collection of data and their analysis.
• Project can be made on the Primavera according to collected data from site.
Steps involved in monitoring and control of Ayurveda Research Center project are
1) Make schedule :-To make a schedule for any project, first of all collect data available for
the project. Subsequently the following steps can be followed in Primavera.
2) Enterprise project structure (EPS) :-Make the structure of the company with its branches,
which is executing the project. This is known as Enterprise project structure (EPS).
3) Organizational breakdown structure (OBS) :- After the EPS, OBS is made which is a
hierarchical shape structure, that shows the persons responsible for the projects in the
enterprise.
4) Create a new project :- A project is a collection of activities and associated information that
constitutes a plan for creating a product or service. The project is made under the respective
divisions in Enterprise Project Structure. And allocate the person in charge from Organization
Breakdown Structure to it. Planned start and must finish dates can be given to project. The
project is allocate a calendar which can be global, resource or project calendar.
5) Work breakdown structure (WBS):- WBS is a hierarchical structure of work that must be
able to complete a project. Each project has its own WBS hierarchical structure. Each WBS
element may iclude more detailed WBS levels, activities, or both in it as shown in figure 1.
6) Determining activities:- Activities are the fundamental work elements of a project and , are
the smallest part of a project. An activity has mainly the following characteristics such as
activity ID, name, start and finish dates, activity calendar, activity type, activity codes,
constraints, expenses, predecessor and successor relationships, resources, roles etc, shown in
figure 2.
7) Relations between activities :- To from a network, thee activities should be linked to each
other,
ther, which is done by allocating preceding and succeeding activities with significant
relationship to the activities.
• Finish to start (FS) relationship.
• Finish to finish (FF) relationship.
• Start to start (SS) relationship.
• Start to finish (SF) relationship.
As shown in Figure 3.
http://www.iaeme.com/IJCIET/index.
IJCIET/index.asp 541 editor@ia
editor@iaeme.com
Hitanshu Saini, Khushpreet Singh, Uma Malik
http://www.iaeme.com/IJCIET/index.
IJCIET/index.asp 542 editor@iaeme.com
Project Management in Construction using Primavera
o Critical or noncritical
o Excusable or non excusable.
o Compensable or non compensable
o Concurrent or non concurrent
Critical Vs Non critical Delays :- According to Trauner et al.,(2009) and Callahan et
al.,(1992), in any study of delays the primary focus is that to see the delay affects the progress
of the project or the completion date. The author again says that if the completion date of the
project is extended by delay then it is considered as critical delays. And the delays which do
not affect the project completion date are called as the noncritical delays. The issue of critical
delays is emerged from the Critical Path Method Scheduling. All the projects have its own
critical path. The completion date of the project will extended if the critical activities on the
path are delayed.
Excusable Vs Non excusable:- Basically construction delays are excusable or non
excusable. A delay is excusable or non excusable it depends upon the clauses in the contract.
Standard construction contracts specifies the type of the delays that will allow the contractor
for extension of time. In some contracts unexpected weather conditions are not considered as
excusable . So these contracts do not allow for any type of time extension.. Delays occurs
from the following issues are called as excusable.
• Labor strikes
• Fires
• Floods
• Acts of God
Compensable Vs Non Compensable Delays:- In some of the studies, authors says that
Excusable delay is classified in to two categories:-
• Excusable Compensable
• Excusable Non Compensable
Compensable delays are caused by the designer and the owner. The contractor is typically
entitled to a recovery and time extension of the costs which is related with the delays. Factors
which can effect the project and caused delays are such as :- different site conditions, changes
in the project work, access to site. Non-compensable delays as those which despite being
excusable do not entitle the contractor to any compensation. Excusable non compensable
delays are beyond the control of owner or contractor.
Concurrent Delay:- Mubarak (2005) states that a concurrent delays are the combination of
two or more independent causes of delays that occurs during the same time frame. According
to the author, a concurrent delay may includes non excusable and excusable delay. Another
definition given by Callahan et al. (1992) is that “more than one delay which is contributed in
project delay, not that the delays necessarily arise at the same time.”
The main delays are found in this study are as follows:-
Delays due to critical activities:
• Late start of handing over of construction site :- Shown in figure 4.
• Getting late work permits from the municipality:- Shown in figure 5.
• Delay in mobilization:- Shown in figure 6.
• Problems in excavation of foundation: Shown in figure 7.
• Late start of work:- Shown in figure 8.
http://www.iaeme.com/IJCIET/index.
IJCIET/index.asp 544 editor@iaeme.com
Project Management in Construction using Primavera
Figure
gure 7 Problems in excavation of foundation.
http://www.iaeme.com/IJCIET/index.
IJCIET/index.asp 545 editor@ia
editor@iaeme.com
Hitanshu Saini, Khushpreet Singh, Uma Malik
http://www.iaeme.com/IJCIET/index.
IJCIET/index.asp 546 editor@iaeme.com
Project Management in Construction using Primavera
5. CONCLUSIONS
Construction schedule delays in a project can create problems for contractors and owners,
which results costly disputes, controversial issues and adverse relationships between all the
project participants. In this study, the major cause of delays are listed below.
1. Organizational scarcity of the owner in handing over of construction site,
2. The directorate of the provincial municipality, the absence of detail drawings during the
municipality application,
3. The absence of experience of the contractor in organizing concrete subcontractors,
problems in material procurement,
4. Delay due to initial mobilization of persons and initial mobilization of persons.
5. Very large rocks are available in excavation of foundation. It can affect the schedule of the
project.
6. Due to delay in excavation, water proofing and pile head treatment can start late as the
planned date.
Due to these delays the project can be finished 4 months late. The Primavera software
shows the progress of the project step by step. It can shows the clear image of the project
progress. On the basis of this study, some suggestions are presented here, which could help to
minimize the impact of delays in the project.
• The late handing over of site can be avoided, if the land acquisition act can be followed.
• If the accurate drawings can be submitted in the municipality, the delay caused by the late
approval from municipality can be neglected.
• The design of the project should be finalized with all details before tendering the work so as to
avoid change orders by the owners.
• If the site was timely handover from the pilling contractor then the delay caused by
mobilization can be minimized or avoided.
• Owner should allot sufficient time and sufficient finances for the design stage of the project.
• The schedule should be made by both the contractors and the consulting companies.
• The contractor should hired qualified work teams and provide worker training in order to
improve managerial and technical skills.
• The contractor should also have a project manager in his team for checking the progress of
work and ensure timely delivery of materials.
• The last but most important issue is to create a healthy communication between all parties in
order to solve problems in a timely manner.
REFERENCES
[1] A.Kastor,K.Sirakoulis(2009), “The effectiveness of resource leveling tools for Resource
Constraints Project Scheduling Problem,” International Journal of Project Management,
pp(493-500).
[2] Boskee Sharma, K.N. Labh(2012), “ Application Of A Project Planning Methodology In
Construction Work,” Internationl Journal Of Innovative Research & Development,
vol.1,pp(1-10).
[3] B. S. K. Reddy, SK. Nagaraju, Md. Salman(2015), “A Study On Optimisation of
Resources for Multiple Projects by Using Primavera” Journal of Engineering Science and
Technology,Vol. 10.,pp(235-248).
[4] Callahan, M. T., D. G. Quackenbush, and J. E. Rowings (1992) “Construction Project
Scheduling”, McGraw-Hill, USA.
[5] Harold Kerzner. “Strategic Planning for Project Management using a Project Management
Maturity Model.” John Wiley and sons, Canada.
[6] Hinze, J. (1993) “Construction contracts”, McGraw-Hill, New York.
[7] Mubarak, S. (2005) “Construction Project Scheduling and Control”, Pearson Prentice
Hall, USA.
[8] Pethe Sarang S, Pramila Adavi(2012),” Application Of PRIMAVERA In Construction
Industry,” International Journal of Advanced Technology in Civil Engineering, Volume-1,
pp( 16-17)
[9] Primavera Systems(2013),“Oracle PrimaveraP6 Project Management, Reference manual.”
Oracle corporation.
[10] Raiyan Abdul Rashid Mansoori(2016), “ Application of Primavera & GIS for Effective
Project Management,” International Journal of Engineering Research, Volume
No.5,pp(140-142).
[11] Robert Fabac, Danijel Radoševi, Igor Pihir(2010), “Frequency of Use and Importance of
Software Tools in Project Management Practice in Croatia,” Proceedings of the ITI 2010
32nd Int. Conf. on Information Technology Interfaces,pp(465-470).
[12] Sandip Pawar, P. M. Attarde(2015), “Time and Cost Planning in Construction Project,”
International Journal of Science and Research (IJSR), Volume 4,pp(422-425).
[13] Shaik Mohammad Masood, Devanand.R, Harsha H.N(2014), “An Analysis on Resource
Planning, Cost Estimation and Tracking of Project by Earned Value Management,”
International Journal of Engineering and Innovative Technology (IJEIT), Volume
4,pp(42-48).
[14] Shanmuganathan N, G.Baskar(2016), “Effective Cost And Time Management Technique
In Construction Industry”, International Journal of Advanced Engineering
Technology,vol.7,pp(743-747).
[15] Shweta Rai(2013), “Scheduling of FRP composite bridges using ‘Primavera’ Software,”
International Journal of Scientific & Engineering Research, Volume 4, pp(1547-1552).
[16] Study on Optimisation of Resources for Multiple Projects by Using Primavera” Journal of
Engineering Science and Technology, Vol. 10.
[17] Trauner, T. J., W. A. Manginelli, J. S. Lowe, M. F. Nagata and B. J.Furniss (2009)
“Construction Delays: Understanding Them Clearly, Analyzing Them Correctly”,
Elsevier Inc., USA.
[18] T.Subramani , K.Chinnadurai(2015), “Construction Management And Scheduling Of
Residential Building Using Primavera,” International Journal of Application or
Innovation in Engineering & Management ,Volume 4, pp(188-198).
[19] X. Regina Mary and V. Rathinakumar(2015), “Reducing Construction Constraints using
Primavera,” Indian Journal of Science and Technology, Vol 8,pp(1-7).
[20] Yakubu Adisa Olawale, MCIOB and Ming Sun(2010),“Cost and time control of
construction projects: Inhibiting factors and mitigating measures in practice.”
Construction Management and Economics.
[21] Rajprasad J, Thamila rasu V, Annadurai R and Atish Roy Choudhuri, Application of
Project Management System in Construction Project. International Journal of Civil
Engineering and Technology, 8(4), 2017, pp. 786-791
[22] Sumesh Sudheer Babu and Dr. B. Sudhakar, Construct ion Project Management During
Economic Crisis. International Journal of Management, 7(7), 2016, pp. 371–381.
[23] Amani, M Al Hadidi and Rami Maher. Engineering Project Management Planning and
Scheduling. International Journal of Civil Engineering and Technology, 8(1), 2017, pp.
140–148.