Date: December 2019 Date Duration 5-Dec 6-Dec 7-Dec 8-Dec 9-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec NO Activities Working Area (Hour) Thu Fri Sat Sun Mon Tue Wed Thur Fri Sat Sun 1 Scaffolding Installation level1,2,3 8 2 Mobilize tools box to imery ground floor 2 3 Tools inspection by imery ground floor 2 4 Safety Briefying ground floor 2 Team A 6 Standby new conveyor item and arrange follow sequence ground floor 8 Team B 7 housekeeping & clearing path for working area ground floor level1,2,3 8 Team C 8 Marking and enlarge opening using oxy cutter or grinder. level1,2,3 8 9 Standby 10 Plant shut down 11 Disconnect wire,cable & sensor by imerys level1,2,3 12 Scaffolding installation ground floor 3 Team A 13 Apply lototo ground floor 1 14 Remove bottom casing cover to clear powder. ground floor 2 15 Mobilize old bucket item to workshop area ground floor 2 16 Team B 17 Dismantle screw conveyor ground floor 2.5 18 remove the inlet pipe ground floor 1 19 remove the bottom drum bearing and drum ground floor 1.5 20 Dismantle bucket ground floor 4.5 Team C 21 Remove motor & gearbox level 3 1.5 22 Remove the top cover level 3 1 23 Cutting chute and separate from top section level 3 2 24 Dismount belt after all bucket had been removed ground floor 4 Team A 25 Receive casing segment from level 3 and store at workshop area. ground floor 2 26 Receive casing segment from level 1 and store at workshop area. ground floor 2 27 Receive casing segment from ground floor and store at workshop area. ground floor 2 Team B 28 Installation of bottom drum rubber liner and tensioning device. ground floor 6 29 Remove casing segment level 2 2.5 30 Remove casing segment level 1 2 31 Support team C from level 1 dismantle bottom segment. level 1 2.5 Team C 32 Removed drum, shaft, bearing level 3 3 33 Removed casing level 3 1 34 Lifting casing segment to level 3 from team B level 2 (space constraint) level 3 2 35 Support team B lifting segment level 2 2 Project: Replacement of bucket elevator Customers: Imerys kinta powdertec Date: December 2019 Date Duration 5-Dec 6-Dec 7-Dec 8-Dec 9-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec NO Activities Working Area (Hour) Thu Fri Sat Sun Mon Tue Wed Thur Fri Sat Sun 36 Removed casing segment . ground floor 3 Team A 37 Mobilize Installation Item follow sequence. ground floor 10 Team B 38 Installation of bottom segment ground floor 6 39 Receive & mobilize item to installation area. level 1 2 40 Install level 1 casing segment level 1 2 Team C 41 Installation of bottom segment ground floor 6 42 Support Team B install casing segment level 2 2 43 Receive & mobilize item to installation area. level 3 2 Team A 44 Mobilize Installation Item follow sequence. ground floor 8 Team B 45 Receive & mobilize item to installation area. level 2 2 46 Install level 2 casing segment. level 2 3 47 Support Team C for installation work. level 3 6 Team C 48 Support Team B install casing segment level 3 3 49 Receive & mobilize level 3 item to installation area. level 3 2 50 Level 3 casing segment installation level 3 2 51 Level 3 installation gear box, motor, shaft & accessories. level 3 3 Team A 52 Mobilize Installation Item follow sequence. ground floor 8 Team B 53 Mount and install belt ground floor 4 54 Installation of new bucket on to belt ground floor 9 Team C 55 Mount and install belt level 3 4 56 Fitting of outlet chute & motor support at top section level 3 4 Team A 57 Support team c for chute & screw installation. ground floor 4 58 House keeping ground floor 4 Team B 59 Welding and touch up of top section outlet chute level 3 4 60 Welding and touch up of top section outlet chute ground floor 4 Team C 61 Fitting of inlet chute at bottom section ground floor 4 62 Installation of screw conveyor and inlet pipe ground floor 4 Team A 63 Alignment ground floor level1,2,3 4 64 commisioning ground floor level1,2,3 4 Project: Replacement of bucket elevator Customers: Imerys kinta powdertec Date: December 2019 Date Duration 5-Dec 6-Dec 7-Dec 8-Dec 9-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec NO Activities Working Area (Hour) Thu Fri Sat Sun Mon Tue Wed Thur Fri Sat Sun Team B 65 Alignment ground floor level1,2,3 4 66 commisioning ground floor level1,2,3 4 Team C 67 Alignment ground floor level1,2,3 4 68 commisioning ground floor level1,2,3 4