Академический Документы
Профессиональный Документы
Культура Документы
Pipe that is only partly full of sewage or in which air The emphasis in this section is on the piping within
can enter by any means (temperature changes, vortices the pumping station (i.e., exposed) and problems such
in the wet well, or leaks) requires protection against as pipe thickness, flange bolts, and pipe supports. The
corrosion caused by bacterial action. Sometimes, pipe design of external (i.e., buried) piping is limited to
can fail in only a few years. Anaerobic, sulfate-reduc- generalities because there is an extensive body of
ing bacteria (such as Desulfovibrio) living in the slime excellent literature on such problems [9, 1 1-15].
In selecting a pipe size, be aware that it is the out- Table 4-14. Root Areas of Threaded Rods
side—not the inside—diameter that is fixed. The
inside diameter varies with the wall thickness, Nominal rod diameter Root area of coarse thread
whereas the outside diameter does not. This is true for mm in. mm 2 in. 2
all sizes of ductile iron, copper, brass, and plastic 3
pipe. It is also true for most steel pipe used in pump- 10 /8 43.9 0.068
13 V2 81.3 0.126
ing stations. 5
16 /8 130.3 0.202
3
19 /4 194.8 0.302
7
22 /8 270.3 0.419
Exposed Piping 25 1 356.1 0.552
28 IV 8 447.1 0.693
The selection of pipe size governed by hydraulics is 31 IV 4 573.5 0.889
given in Example 3-1. Other practical considerations 35 1% 679.4 1.053
that depend on available pipe diameters and wall and 38 IV 2 834.2 1.293
lining thicknesses are discussed in Sections 4-3 and 41 l5/8 977.4 1.515
4-4 under "Available Sizes and Thicknesses." 44 l3/4 1125 1.744
47 l7/8 1321 1.048
50 2 1479 2.292
Tie Rods 63 2V2 2397 3.716
75 3 3626 5.672
Mechanical couplings, mechanical joints, and push-on
joints (Figures 4-7, 4-8, 4-10, and 4-11) must be
restrained from sliding apart either by soil friction (if
the pipe is buried) or by tie rods (if the pipe is exposed) and bolts for tensile stress at the net cross-sectional
as shown in Figures 4-3 and 4-12. Always design rods area at the root of the threads (see Table 4-14).
Example 4-1
Design of Tie Rods for a Sleeve Pipe Coupling
Problem: Determine the number and size of tie rods required for a sleeve coupling in a 600-mm
(24-in.) DIP under a maximum static and surge pressure of 1070 kPa (155 lb/in.2).
Solution: The outside diameter of the pipe is 655 mm (25.8 in.); because the pressure acts on
the gross face area of the end of the pipe, use the OD (not the ID) to compute thrust.
Many combinations of rod sizes and numbers can be used. Try several and choose a suitable
one. (Note, however, that the resulting bending stresses in the pipe shell should be checked.
Using two large-diameter rods, for example, causes greater bending stresses than using four
smaller ones. Sometimes the pipe wall thickness must be increased to reduce the stress.) From
Table 4-14 the root area of a 22-mm (7/8-in.) bolt is 270 mm2 or 0.000270 m2 (0.419 in.2); thus,
the number of rods required is
Note that the rod material is high-strength steel (ASTM 193 Grade B7). If lower strength
steel (carbon or stainless) were used, the number and/or size of rods would be quite different.
The rods can be supported by lugs welded to the pipe, which is excellent with steel pipe but
can be done with ductile iron pipe only if great care is taken not to overheat the iron. An alternate
detail for ductile iron pipe is to bolt an "ear" (as in Figure 4-3a) to the pipe flange so that the tie
rod clears both the pipe flange and the pipe coupling. From the DIPRA handbook [11] and man-
ufacturers' catalogs, the critical dimensions are (1) flange bolt circle [749 mm (29.5 in.)], (2)
number and size of bolts [20 bolts 32 mm (I1I4 in.) in diameter], (3) flange OD [813 mm
(32.0 in.)], (4) flange thickness [48 mm (1.88 in.)], and (5) coupling OD [782 mm (30.8 in.)]. If
a clearance between the rod and flange of, say, 8 mm (5/16 in.) is chosen, the rod is centered 19
mm ( 3 /4 in.) from the flange OD. The ear can be designed (with an adequate safety factor applied
to the yield stress) to withstand the calculated force in the tie rod, but a more sensible design is to
size the ear so that yield stress is reached simultaneously in the ear and tie rod. The bending
moment in the ear is equal to the lever arm times the force in the tie rod.
M = 0.019 m(2.7 x 10~4 m 2 x 7.25 x 108 N/m2) M = 0.75 in.(0.419 in.2 x 105,000 lb/in.2)
= 3.720 N • m = 33,000 Ib • in.
The formula for bending stress is
s
Mc M (44)
= - = -s
where s is stress in newtons per square meter (pounds per square inch), M is moment in newton-
meters (pound-inches), / is moment of inertia in meters to the fourth power (inches to the fourth
power), and S is the section modulus in cubic meters (cubic inches). For rectangular cross-
setctions, S = bd2/6, where b is width in meters (inches) and d is depth in meters (inches). Rear-
ranging Equation 4-1 and using the yield stress for A 36 steel gives
, ,2 6 x 3720 N - m , ,2 6 x 33,000
! Ib • in.
bd = bd = —
248,000,000 N/m 36,000 lb/in.
= 9.0OxIO" 5 m 3 = 5.5 in.3
Let b = 63 mm = 0.063 m. Let b = 2.5 in.
"^r"""- "Jg-'-"
Use 63 mm x 38 mm plate. Use 21I2 in. x IV 2 in. plate.
Pipe Wall Thickness exceed 75% of the yield strength or the mill test pres-
sure. Depending on the grade of steel used, the yield
The hoop (circumferential) tensile stress in metal strength can lie between 248,000 and 414,000 kPa
pipe due to the working pressure should not exceed (36,000 and 60,000 lb/in.). The yield strength of DIP
50% of the yield strength. The working pressure plus is more uniform — a minimum of 290,000 kPa
surge pressure due to water hammer should not (42,000 lb/in.2).
The hoop tensile stress is given by the equation bolts to prevent longitudinal movement caused by
internal pipeline pressure.
5 = f («) ANSI B31.1 describes hanger and support spac-
ings for steel pipe with a minimum wall thickness of
where s is the allowable circumferential stress in kilo- standard weight. A maximum bending stress of
pascals (pounds per square inch), p is the pressure in 16,000 kPa (2300 lb/in.2) and a maximum deflection
kilopascals (pounds per square inch), D is the outside (sag) of 2.5 mm (0.1 in.) for pipes filled with water is
diameter of the iron or steel cylinder in millimeters assumed in the ANSI spacings. The spacings given in
(inches), and t is the thickness of the iron or steel cyl- Table 4-15 should not be exceeded.
inder in millimeters (inches). (Theoretically, D should Hanger rod sizes should be
be the inside diameter, but the outside diameter is con-
servatively specified in most codes, partly because the • at least 9.5 mm (3/8 in.) for pipe 50 mm (2 in.) and
ID is not known initially.) The longitudinal stress in a smaller;
straight pipe is half of the circumferential stress. • at least 13 mm (1I2 in.) for pipe 63 mm (21I2 in.) and
larger.
Hangers and Supports Design hanger rods for a maximum working stress of
20 to 40% of the yield stress at the root area of the
Supports or hangers must carry the weight of the pipe threaded ends (see Table 4-14). If the hangers are embed-
and fluid in exposed piping systems. The location of ded in or supported by concrete, make sure the embed-
supports and hangers depends on the pipe size, joint ment is as strong as the threaded rod or limit the allowable
systems, piping configurations, location of valves and load to the specifications in UBC Section 2624. Capsule
fittings, weight of pipe and liquid, beam strength of anchors containing a two-part resin (such as Emhart
the pipe, and the structure available to support the Molly Parabond™) are superior to expansion anchors,
weight and all other static and dynamic forces, includ- which use friction to resist being pulled out. Some engi-
ing expansion and contraction. neers do not trust glued anchors, however, because good
Supports or hangers must also carry the lateral and dependable workmanship is critical. Embedded eye
forces due to earthquake. Either design vertical sup- bolts should be welded closed in addition to being welded
ports to resist the horizontal force of pipe and fluid or to the reinforcing bars, as shown in Figure 4-16a and b.
augment vertical supports and hangers with horizontal Hanger rod sizing for plastic pipe should be the same
ones. Note that tension in wall anchors must resist the as for steel pipe, but the spacing of hangers should be as
full horizontal force. Typical pipe supports are shown recommended by the plastic pipe manufacturer. Spacings
in Figure 4-15 and a few of the many hangers manu- are typically half those for steel and ductile iron pipe.
factured are shown in Figure 4-16. In addition to installing supports or hangers for
Some general design precautions for pipe support straight runs of pipe, provide additional hangers or
system design include the following: supports at
• Because pump casing connections to piping systems
• concentrated loads, such as valves;
are rarely designed to support any load transmitted
• fittings;
through the connection, supports should be provided
• both sides of nonrigid joints; and
on both the suction and discharge side of pumps to pre-
• pipe connected to suction and discharge casings of
vent pipe loads being transmitted to the pump casing.
pumps.
• Flexible pipe couplings are recommended at pump
inlets and outlets. They are useful because (1) they A wide variety of standard hangers and supports is
are "forgiving" and allow the contractor to level the available [17]. Combining Equation 4-1 for stress due
pump and make minor horizontal adjustments; (2) to bending (s = McII ) and bending moment for simple
properly selected, they isolate the pump from slight spans (M = wL2/8) and rearranging, the equation for
movements of the pipe; and (3) they reduce vibra- calculating pipe support spacings based on stress (for
tion and, to a limited extent, noise. straight pipe runs) becomes
• If expansion and contraction of the piping could
occur, the pipe supports should allow movement. /O „ J
Table 4-15. Support Spacing for Iron or Steel Pipe per ANSI B31.1
Span
Nominal pipe size Water service Steam, gas, or air service
mm in. m ft m ft
25 1 2.1 7 2.7 9
50 2 3.0 10 4.0 13
75 3 3.7 12 4.6 15
100 4 4.3 14 5.2 17
150 6 5.2 17 6.4 21
200 8 5.8 19 7.3 24
300 12 7.0 23 9.1 30
400 16 8.2 27 10.7 35
500 20 9.1 30 11.9 39
600 24 9.8 32 12.8 42
per square inch), / is the moment of inertia in meters The equation of sag for a uniformly loaded simple
to the fourth power (inches to the fourth power), w is span is
the weight of pipe and water per unit length in new-
tons per meter (pounds per inch), and c is the distance s 5wL ,, cx
8 (4 5)
from the neutral axis to the outer fiber (OD/2) in = 384E/ '
meters (inches). / for pipe is given by
and rearranging to find L gives
4 4
7 _ TC[(OD) -(/D) ]
64 L = (**™*r (4-6)
\ 5w J
where E, the modulus of elasticity, is given in Table
A-IO. Be careful to use compatible units.
Example 4-2
Hanger Rod Sizing and Spacing
Problem: A 600-mm (24-in.) steel pipe of standard weight is filled with water. The allowable
tensile stress (including the factor of safety) in the hanger rods is 62,000 kPa or 62 x 106 N/m2
(9000 lb/in.2). Assume that a factor of safety of 1.5 is to be applied to the ANSI maximum bend-
ing stress in the pipe, so that stress is limited to 1.07 x 107 N/m2 (1500 lb/in.2).
Solution: Calculate / from Equation 4-4 (see Table B-3 or B-4 for dimensions and weight of
the pipe barrel).
w = 141 kg/m + 0.273 m 2 x 1000 kg/m3 w = 94.6 Ib/ft + 2.94 ft2 x 62.4 lb/ft3
= 414 kg/m = 278 lb/ft = 23.2 lb/in.
Transforming mass to force,
From Table 4-14, use rods 31 mm (I1I4 in.) in diameter. However, if the rods are to be anchored
only by embedment in concrete, note that UBC Section 2624 allows a maximum load of only
14,000 N (3200 Ib) per bolt. That requirement would permit a spacing of only
T 14,00ON ,.. , 3200 Ib ., . ,f
L =
4060NM = 3 ' 4 5 m L =
278lWft=1L5ft
Buried Piping bottom to (T) using select bedding material to (3) sup-
porting the pipe on a monolithically poured concrete cra-
External Loads dle. A stable, granular bedding material can be achieved
with a well-graded crushed stone with a maximum parti-
Buried pipes must support external structural loads, cle size of 3/4 in. and containing not less than 95% by
including the weight of the soil above the pipe plus weight of material retained on the No. 8 sieve.
any superimposed wheel loads due to vehicles if the The design of pipe to resist external loads is
pipeline crosses a runway, railway, or roadway. The involved because it depends on the stiffness of the
two broad categories for external structural design are pipe, the width and depth of trench, the kind of bed-
rigid and flexible pipe. Rigid pipe supports external ding, the kind of soil, and the size of pipe. Discussions
loads because of the strength of the pipe itself. Flexi- are given in AWWA Mil [9], AWWA M9 [13], the
ble pipe distributes the external loads to surrounding DIPRA handbook [11], by Spangler [14, 15], and in
soil and/or pipeline bedding material. Consider DIP, many other publications.
steel, and PVC to be flexible, whereas AC and RCPP
are rigid. (FRP is also rigid, but refer to Section 4-5 Thrust Blocks
for a warning about buried service.)
Supporting strengths for flexible conduits are gen- Where changes in flow direction occur, the exposed
erally given as loads required to produce a deflection pipes must be restrained against the resultant thrust.
expressed as a percentage of the diameter. Ductile iron Changes in flow direction occur at all bends, tees,
pipe may be designed for deflections up to 3% of the plugs, caps, and crosses. Joint systems, such as
pipe diameter according to ANSI A21.50. Until flanges, welds, and grooved couplings, are designed to
recently, plastic pipe manufacturers generally agreed provide restraint up to the manufacturer's rating. But
that deflections up to 5% of the diameter were accept- if the joint system is inadequate to contain the calcu-
able. Some manufacturers now suggest that deflec- lated thrust, external restraint is needed. Thrust calcu-
tions up to 7% of the diameter are permissible. Many lations are illustrated in Example 3-5.
engineers, however, believe these values are much too Buried pipes with mechanical or push-on joints
liberal and use 2 to 3% for design. require thrust blocking at deflections, bends, tees,
Pipeline bedding conditions affect the safe supporting plugs, or other changes in flow direction. Thrust
strength of both rigid and flexible conduits. Screenings, blocks are constructed of cast-in-place concrete
silt, or other fine materials are unsuitable for stable pipe- poured in the trench during pipeline installation. They
line bedding and should be avoided particularly where are designed to act as horizontal spread footings that
the groundwater level may rise above the trench bottom. distribute the resultant force to the trench wall. The
Better systems range from (1) merely shaping the trench required area of the thrust block can be determined
Figure 4-17. Typical underground thrust block details. Courtesy of Wilson & Company, Engineers & Architects.
Figure 4-18. Typical thrust blocks for exposed pipes, (a) Combination thrust block pipe support; (b) thrust block/
pipe support for emerging pipe. Courtesy of Wilson & Company, Engineers & Architects.
from the resultant force acting on the bend (see Exam- the soils may be disturbed by future excavations (yard
ple 3-5) and the allowable soil bearing pressure. For piping, treatment plant sites, busy streets, etc.), reli-
the resultant force, use whichever of the following is ance on thrust blocks (particularly for large diameters
greater: (1) the total (working plus water hammer) and high-pressure pipeline systems) is not a very
pressure or (2) the pipeline test pressure. The allow- good idea. Instead, the use of restrained (lugged or
able horizontal bearing pressure can best be found by harnessed) joints and trench friction is a better
calculating the Rankine passive pressure from the approach.
principles of soil mechanics, or it can be found in
tables [9] (see also DIPRA [1 1] or UBC Table 29-B).
The concrete in thrust blocks should have a mini- Cleanouts
mum compressive strength of 13,800 kPa (2000 lb/in.2)
at 28 days. The bearing area should be poured directly Cleanouts should be installed in sludge and slurry
against undisturbed earth. Figures 4-17 and 4-18 show lines that carry grease, grit, or other substances (such
typical thrust block details. as lime) that may form deposits in the pipe (typical
The use of thrust blocks should be considered with designs are shown in Figures 4-19 and 4-20). Lime-
great care. They are only as good as the stability of carrying waters are especially troublesome, so use
the soils used for reaction backing. In locations where troughs instead of pipe where possible.
Figure 4-19. Underground pipe cleanout. Courtesy of Wilson & Company, Engineers & Architects.
Figure 4-20. In-line cleanouts for exposed pipe. Courtesy of Wilson & Company, Engineers & Architects.
Special cleanouts are required for flowmeters, and placed in the pig retrieval pipe prior to the pigging
a suitable system is shown in Figure 20-12. operation. The 2l/2 D barrel length is standard, but if
space is tight, I1I2 D can be used (although not with
deZurik pigs). Pressure gauges are unnecessary. The
Pig Launching and Recovery best way to determine whether the pig has gone is to
isolate the launch barrel and insert a rod through the
Typical pig launching and recovery stations are shown launching valve quick-connect. At the retrieval end,
in Figures 4-21 and 4-22. The pig stop, Figure 4-23, is listen for the sound of the pig arriving.
Figure 4-21. Typical pig launching station. Courtesy of Brown and Caldwell Consultants.
Figure 4-22. Typical pig retrieval station. Courtesy of Brown and Caldwell Consultants.
PVC could be used in Schedule 40 for solvent-
welded joints or Schedule 80 for threaded joints, but it
requires closely spaced supports. Since galvanized
steel pipe within corrosive atmospheres, such as wet
wells, corrodes quickly, a more satisfactory material is
stainless steel or PVC.
Stainless-steel pipe in most pumping station ser-
vices is covered by ASTM A 312 for 3 through 750
mm (V8 through 30 in.) and A 778 for 75 through
1200 mm (3 through 48 in.) for material; for dimen-
sions, it is covered by ANSI B36.19 (not ANSI
B36.10). Note that the minimum wall thickness for
threaded pipe is Schedule 4OS. Fittings 50 or 75 mm
Figure 4-23. Typical pig stop. Courtesy of Brown and
(2 or 3 in.) and smaller should be threaded and
Caldwell Consultants.
should conform with ASTM A 403 and ANSI B 16.3
(see the previous discussion on the applicability of
threaded joints). Fittings larger than 75 mm (3 in.)
should be butt welded, grooved end, or flanged
4-9. Special Piping and Plumbing and should conform to ASTM A 403 or A 774, and
ANSI B 16.9.
The requirements for conveying small flows of wash- The wall thicknesses for the pipe schedules for
down water, fuel, cooling water, and sump drainage stainless-steel pipe are as follows:
are entirely different from the foregoing. Pipes for
• Schedule 4OS for stainless-steel pipe is the same as
fuel, wash water, seal water, and air are small and Schedule 40 for carbon steel pipe in sizes of 10 in.
comparatively inexpensive even when constructed of and smaller.
materials such as copper or stainless steel. Special
• Schedule 4OS for stainless-steel pipe is the same as
piping materials are listed in Table 4-16.
standard weight (3/8-in. wall) for carbon steel pipe
in sizes of 12 in. and larger.
• Schedule 80S for stainless-steel pipe is the same as
Water Schedule 80 for carbon steel pipe in sizes of 8 in.
and smaller.
If water is needed for lavatories or wash-down, galva-
nized steel with threaded connections is practical Note that the letter S always follows the Schedule
because the pipe would rarely exceed 38 mm (11^ in.) number for stainless steel, for example, 4OS.
in diameter. Pipe fittings are usually made of mallea-
ble iron. Thread compound or Teflon™ tape should be
applied to threads. There should be enough strategi-
cally placed unions to allow for dismantling and Threaded Joints
replacement. Threaded pipe must have a wall thick-
ness no less than standard weight per ANSI B36.10. Threaded malleable iron fittings and couplings (ANSI
Copper tubing, with joints soldered with tin- B 16.3) can be used with steel pipe and are usually
antimony (ASTM B 32, Grade SbS), is also practical. cheaper than forged steel fittings conforming to ANSI
Because there is evidence that lead can leach into the B16.ll. Threading conforms to ANSI B 1.20.1 for
water, avoid lead-based solder. Copper, however, is cor- both malleable iron and forged steel fittings.
roded by hydrogen sulfide. So copper or brass piping Forged steel fittings (90° and 45° elbows, tees,
and tubing should be used with caution in areas of crosses, couplings, caps, plugs, and bushings) con-
wastewater pumping stations exposed to a hydrogen forming to ANSI B16.ll are available in sizes of 3
sulfide atmosphere. Copper tubing also should not be through 100 mm (V8 in. through 4 in.) Assembling
allowed to come in contact with prefabricated wood and disassembling threaded fittings and joints larger
trusses that have been treated with ammonium sulfate than 50 to 75 mm (2 to 3 in.) is labor intensive, so
fire-retardant material, because the ammonium sulfate only small pipes are connected by threaded fittings.
is very corrosive to copper. Require that the copper tub- Unions at strategic locations are needed for disas-
ing be attached to wood trusses by pipe hangers, and sembly. Steel unions conform to MSS SP-83; mallea-
not just attached directly to or laid directly on the wood. ble iron unions conform to ANSI B 16.39.
Table 4-16. Piping Materials and Standards
Van Stone Flanges resistant unless the concern is for external corrosion.
The joint is made by roll flaring the end of the pipe.
Van Stone flanges are especially economical for A slip-on flange can then be placed over the pipe to
stainless-steel piping. The flange can be carbon steel make the connection. Such flanges are especially
or ductile iron because it is not in contact with the attractive with stainless-steel pipe, but where flanged
liquid and, hence, does not have to be corrosion joints would be exposed to corrosive conditions (as
in a wastewater pumping station wet well), specify Sewers
stainless-steel flanges.
Cast-iron soil pipe (CISP) 50 through 375 mm (2
through 15 in.) and larger is suitable for use as drain-
Diesel Fuel Service pipe inside buildings if it is installed above the floor
with no-hub ends and with neoprene sealing sleeves
Both the Uniform Fire Code and the Standard Fire and Type 301 or 303 stainless-steel clamps (in accor-
Prevention Code require that steel piping for flamma- dance with CISPI 301). For buried service or service
ble and combustible liquids have a wall thickness under slabs and buildings, use hub-and-spigot ends
determined in accordance with ANSI B 3 1.3 and (see also ASTM A 74 standards). In lieu of CISP, ABS
B31.4 with a minimum wall thickness of standard pipe is frequently used; for drainpipe smaller than 50
weight. ANSI B31.1, B31.3, and B31.4 also contain mm (2 in.) use steel, copper, or PVC.
design guidelines for flammable fluid piping, which
are summarized as follows:
Dry Chlorine Gas
• Prohibited pipe: (1) furnace butt- welded steel, (2)
cast iron, (3) copper, (4) brass, (5) aluminum, and As recommended in ANSI B31 and by the Chlorine
(6) thermoplastic (aboveground). Institute [18], make the piping arrangements as simple
• Prohibited connections: (1) cast, malleable, or as possible. Keep the flanged or screwed joints to a
wrought iron threaded couplings, (2) cast-iron minimum. Slope the pipe to allow drainage, avoid low
flanges, unless integral with cast-iron valves, pres- spots, allow for expansion due to temperature changes,
sure vessels, and other equipment. and be sure that the pipe is well supported.
• Required: (1) double welding for slip-on flanges Details of materials and construction can be
and (2) flat facing connecting steel flanges to cast- obtained from Pamphlet No. 6 of the Chlorine Insti-
iron flanges. tute [18]. Other publications may also be applicable to
• Recommended materials: (1) seamless steel such as pumping stations [19-25]. After assembly and pres-
ASTM A 53 Type S, (2) welded steel with straight sure testing, chlorine gas piping must be thoroughly
seam conforming to ASTM A 53 Type E, ASTM A cleaned and all moisture must be removed.
134, ASTM A 155, or (3) API SL electric resistance
or double- submerged arc welded with allowable
stresses no higher than for ASTM A 53 Type S with Chlorine Solutions
an appropriate longitudinal joint efficiency factor
included. Chlorine solutions can be carried in PVC piping. All
• Recommended: (1) welded joints between steel fittings should be plastic, glass, or Hastelloy™. Most
components where practicable, (2) where bolted metals, including 316 stainless steel, corrode rapidly
flanged joints are necessary, gaskets suitable for the in concentrated chlorine solutions.
service, (3) where threaded joints are necessary, at
least Schedule 80 (extra strong) pipe with extreme
care in assembly to assure leak tightness, (4) steel
or ductile iron for valves, fittings, and other piping Air
components for systems within plants or buildings
that contain equipment with open flame or parts that Use stainless steel or copper. Do not use PVC because
operate at temperatures over 26O0C (50O0F), and (5) heat destroys plastic pipe. Do not use galvanized steel
black steel—never galvanized steel, because the because moisture in the air corrodes it, and although
zinc contaminates the fuel and the galvanizing dryers can be added at the compressor, maintenance
sometimes flakes off and can clog fuel metering ori- cannot always be ensured.
fices.
The UFC Section 79. 305 requires that under- Design of Plumbing Systems
ground piping incorporate swivel joints where the pip-
ing leaves the dispensing location and just before Plumbing work in a pumping station usually includes
connecting to the tank fittings. Swivel joints incorpo- roof drainage, toilet fixtures, floor drains, and sump
rate ball bearings and permit rotation and movement pumps in addition to the necessary water, waste, and
from one to many degrees of freedom. vent piping and a water heater.
Storm Drainage Some codes do not permit the installation of back-
flow preventers, but require potable water to be dis-
The sizing of roof drains, horizontal conductors, and charged through an air break into a tank, from which it
vertical leaders or downspouts (usually covered in the may be pumped to potentially contaminating uses.
applicable plumbing code) is based on roof area and Interior hose bibbs should be conveniently located for
historical rainfall intensity. Storm drainage, including easy wash-down of the station, and exterior hose
roof and area drains, catch basins, and foundation bibbs should be frostproof in cold climates.
drains, should (1) connect to a storm drain, (2) dis-
charge through a trap into a combined sewer, or (3) be
drained to grade if neither (1) nor (2) is available. In Sumps
addition to any sump receiving subgrade sanitary
waste, a separate sump may be required by code for To prevent frequent pump starts, sumps for subgrade
foundation drainage. drainage should be sized to hold at least two to three
Roof drainage piping often conveys water at a tem- times the flowrate capacity of the installed sump
perature below the dew-point temperature of air in the pump below the lowest inlet. Install duplex pumps and
building, so condensation tends to occur on the pipe. a sump high-level alarm if damage to other equipment
The horizontal conductors (at least) should be insu- could follow failure of a single pump. Each pump
lated to prevent dripping from such condensation, should discharge individually through a check valve
especially if the pipes pass over or near electrical and a gate valve before joining in a common discharge
equipment. riser to the gravity flow waste line. If the piping sys-
The materials usually used for storm drainage pip- tem of a sump pump can be subjected to freezing tem-
ing include galvanized steel pipe, galvanized cast-iron peratures, it should either (1) be designed to be self-
drainage fittings, cast-iron soil pipe and fittings, and draining or (2) be protected by heat tracing to prevent
polyvinyl chloride plastic pipe and fittings. Both the formation of ice.
storm and sanitary drain lines buried below floors So that occasional solids can be passed, sump
should be encased in concrete when the floor is pumps should be of the semiopen impeller type with-
poured to protect them from corrosion and settlement. out an inlet screen. Submersible pumps have the
advantage of being inherently floodproof, provided
their control panel is located above the flood level.
Mercury-type float switches are recommended in
Sanitary Drainage
the sump. They are arranged (1) to alternate the opera-
tion of duplex pumps, (2) to start the second pump if
Sanitary soil, waste, and vent piping sizes and
the first does not handle the load for any reason, and
arrangements must conform to the applicable plumb-
(3) to energize local and remote alarms if the design
ing code. Equipment drains receiving pump seal water
HWL is exceeded. The pumps should be capable of
can be enlarged hub drains raised above the floor or
continuous operation. Specify a manual "test" posi-
regular floor-mounted drains fitted with a funnel
tion on pump selector switches to permit periodic
strainer. Cleanouts should be located on both sanitary
manual tests of pump operation, and state the recom-
and storm drainage lines at 15-m (50-ft) intervals to
mended frequency of testing in the O&M manual. The
permit easy cleaning.
pumps and their wiring, controls, and alarms must be
explosionproof if open to a space classified as hazard-
ous by Articles 500 to 502 of the NEC.
Cross Connections