Академический Документы
Профессиональный Документы
Культура Документы
CONCEPT TO COMMISSIONING
S.S Jamwal
Electricity – Basic Principle
Electricity – Basic Principle
Electricity – Basic Principle
Basic Elements of Electricity Generation
• Motion Prime Mover
• Magnetic Field Electro-magnets on Rotor
coupled to Prime Mover.
Steam Turbine
Gas Turbine
• Prime Mover – Hydro Turbine
Wind Turbine
Diesel Engine
Types of Hydro Turbines
Hydro Turbine
Impulse - Pelton
Three parameters
Voltage
Current
Frequency
Parameters Control
• Voltage and frequency to be maintained within Preset Limits.
Equipment Checklist
Turbine
- Draft Tube Liners/ Pit Dimensions/ Elevations/ Centering-
Liners Alignment/ weld check etc.
Generator
- Rotor - Rotor Building, Spider, rim etc.
(Distribution as per weight)
-Checking Rotor form
-Inter-turn Test of Rotor Poles.
-HV Testing of poles (before and after
mounting)
-Dryout, HV Test of Rotor and current
carrying leads.
Checks during Installation
Generator
- Stator -Stator Frame Assembly Large
-Core Building Machine
-Laying of Winding
-Gap-Joints: Plates and Core at split
-Elevation, radius-bore & magnetic
axis setting etc.
-HV Test of Stator bars before and after
laying
-Ultrasonic testing of brazed stator bar
joints
Checks during Installation
Generator
-Stator -Dryout & AC HV Testing of Stator
-Hydraulic Testing of Air Coolers
-Hydraulic Testing of Brakes
-Alignment -Rotor Shaft Alignment
-Combined Turbine & Rotor Shaft
Alignment
-Final Boxing up -Load Distribution of TB Pads
-Verticality of Turbine & Generator
Shaft
Checks during Installation
Generator
-Final Boxing up -Runner Elevation and Labyrinth
Clearance (Francis)
-Alignment of Runner and Jet Axes
(Pelton)
-TGB, LGB & UGB radial Clearances
Excitation System Standard Checks/ Tests
Pre-Commissioning
Automation Ckts
Control Ckts Start Ckt.
-All interlocks to be checked
-Start Operation from both Control Room &
Unit Control Panel.
Stop Ckt.
-Operation from Control Room and Unit
Control Panel.
-Operation through emergency Control
Circuits.
Pre-Commissioning
Automation Ckts
Control Ckts Generator Air Brakes
-Open/ Close checks and signaling.
Protection Ckts.
-Open/ close checked by initiating the
contacts at fault points.
Annunciation Panels
-Temp. Measurement
Panel:
Check whether temperature indications are
O.K.
Pre-Commissioning
Automation Ckts
Control Ckts Electrical Measurement
Panel:
-Check Whether parameters being measured
are O.K.
Automation AVR Check Following:
-Speed Relay Operation
-Operation of Field Breaker
-Operation of Exciter Field Discharge
-Operation of Field Rheostat
-Operation of de-excitation
Pre-Commissioning
Protection System
and Circuits Secondary and Primary Injection testing of
Protections.
Unit Start-Up & Spinning
After the above discussed checks are satisfactorily completed
with success, the following checks are done to clear the unit
for operation.
Electrical Protection 1
Electrical Protection 2
Electrical Protection Checking
Sensitivity of Generator Differential: 3 Phase Short at “A”.
Stability of Gen. Differential. 3 Phase Short at “B”.
Sensitivity of Split Phase Diff. 3 Phase Short at “B”.
Stability of Stator E/F 3 Phase Short at “B”.
Sensitivity of Neg. Seq. Prot.Relay 1 Phase to Earth at “B”.
Sensitivity of Neg. Seq. Prot.Relay 1 Phase to Earth at “B”.
Residual Voltage across stator E/F on OCC of Gen.
Split phase current
Check on O/V Prot. With delayed tripping
Check on instantaneous O/V Protection SLD
Electrical Protection Checking
-S.C.C
-O.C.C
SLD
Synchronization
After the above tests/ checks are successfully completed, the
following tests are done for clearing the unit for Commercial
Operation.
-Synchronization
-Load throw off -25%
-Test at: -50%
-75%
-100%
Functional & Guarantee Tests
The Unit is tested, so as to meet the Guaranteed Efficiency,
Temperature rise, response time etc.