Item Description Weight Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13

1 Earthworks 0.94
2 Concreting Works 19.02 1.585 1.585 1.585 1.585 1.585 1.585 1.585
3 Formworks and Scaffoldings 22.39 2.239 2.239 2.239 2.239
4 Masonry Works 14.07 2.01 2.01 2.01
5 Steel Reinforcements 15.19 1.68 1.68 1.68 1.68
6 Roofing 9.57 2.4
7 Doors & Windows 9.02
8 Paintings 1.48
9 Ceilings 1.53
10 Tileworks 4.08
11 Railing Works 0.30
12 Plumbing 2.42
TOTAL DIRECT COST 100.00

Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13


TOTAL WEEKLY (SCHEDULED) 5.504 3.824 3.824 7.514 5.275 5.275 3.985
CUMMULATIVE (SCHEDULED) 22.41 26.24 30.06 37.57 42.85 48.12 52.11
Item Description Weight Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20
1 Earthworks 0.94
2 Concreting Works 19.02
3 Formworks and Scaffoldings 22.39
4 Masonry Works 14.07 2.01 2.01
5 Steel Reinforcements 15.19
6 Roofing 9.57 2.4 2.4 2.4
7 Doors & Windows 9.02
8 Paintings 1.48 0.37
9 Ceilings 1.53 0.765 0.765
10 Tileworks 4.08 1.36 1.36 1.36
11 Railing Works 0.30
12 Plumbing 2.42 0.806 0.807
TOTAL DIRECT COST 100.00

Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20


TOTAL WEEKLY (SCHEDULED) 2.4 4.41 4.41 1.571 2.932 1.36 1.73
CUMMULATIVE (SCHEDULED) 54.51 58.92 63.33 64.90 67.83 69.19 70.92
Item Description Weight Week 21 Week 22 Week 23 Week 24
1 Earthworks 0.94
2 Concreting Works 19.02
3 Formworks and Scaffoldings 22.39 2.239 2.239
4 Masonry Works 14.07
5 Steel Reinforcements 15.19
6 Roofing 9.57
7 Doors & Windows 9.02 4.51 4.51
8 Paintings 1.48 0.37 0.37 0.37
9 Ceilings 1.53
10 Tileworks 4.08
11 Railing Works 0.30 0.3
12 Plumbing 2.42 0.807
TOTAL DIRECT COST 100.00

Week 21 Week 22 Week 23 Week 24


TOTAL WEEKLY (SCHEDULED) 0.37 0.37 7.149 7.856
CUMMULATIVE (SCHEDULED) 71.29 71.66 78.81 86.67