Вы находитесь на странице: 1из 129

MPC 07FP06 - FCC - Gas Con - CORE SPECS

File Name doc_no doc_title


1_15.PDF 1 CONCRETE SELECTION, DESIGN AND QUALITY ASSURANCE
16_29.PDF 16 PIPING MATERIAL
18_26.XLS 18 HYDROCARBONS W/ HYDROGEN BELOW 50 PSIA PP; CAUSTIC LESS
22_17.XLS 22 HYDROCARBONS AND TRACE HF ACID (UOP HF ALKY UNIT DESIGN,
23_19.XLS 23 HYDROCARBONS W/ HYDROGEN ABOVE 50 PSIA PP; HYDROGEN (
24_15.XLS 24 LIQUID SULFUR [CARBON STEEL JACKETED]
25_18.XLS 25 HYDROCARBONS W/ HYDROGEN BELOW 50 PSIA PP
27_17.XLS 27 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN; H
28_15.XLS 28 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN (P
31_21.XLS 31 AMINE (W/ OR W/O HYDROGEN) (PWHT REQUIRED)
33_13.XLS 33 CATALYST LIFT PIPING W/ HYDROGEN BELOW 50 PSIA PP
34_17.XLS 34 HYDROCARBONS (LOW TEMPERATURE)
39_20.XLS 39 SODIUM HYPOCHLORITE (BLEACH), CHLORINATED WATER, CHEMIC
41_17.XLS 41 HYDROCARBONS W/ OR W/O HYDROGEN
43_19.XLS 43 HYDROCARBONS W/ OR W/O HYDROGEN; VACUUM TRANSFER LINES;
45_20.XLS 45 SULFURIC ACID (LESS THAN 93% SOLUTION OR 66° BAUME)
46_17.XLS 46 HIGH TEMPERATURE - CCR VENT GAS (W/ CHLORIDES)
49_17.XLS 49 HYDROCARBONS W/ HYDROGEN BELOW 50 PSIA PP; AIR/CATALYST;
53_19.XLS 53 HYDROCARBONS AND TRACE HF ACID (UOP HF ALKY UNIT DESIGN,
54_18.XLS 54 HYDROCARBONS W/ HYDROGEN ABOVE 50 PSIA PP; HYDROGEN (
55_15.XLS 55 LPG (OUTSIDE BATTERY LIMITS)
57_15.XLS 57 HYDROCARBONS W/ HYDROGEN BELOW 50 PSIA PP
58_16.XLS 58 SIMPLE WET H2S - HYDROCARBONS W/ HYDROGEN BELOW 50 PSIA
61_17.XLS 61 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN; ST
63_16.XLS 63 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN; H
66_14.XLS 66 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN (P
69_15.XLS 69 AMINE (W/ OR W/O HYDROGEN) (PWHT REQUIRED)
70_20.XLS 70 HYDROFLUORIC ACID (COP HF ALKY UNIT DESIGN) (PWHT REQUIR
71_19.XLS 71 HYDROFLUORIC ACID (UOP HF ALKY UNIT DESIGN, HF-2) (PWHT R
72_12.XLS 72 CATALYST LIFT PIPING W/ HYDROGEN BELOW 50 PSIA PP
73_14.XLS 73 HYDROCARBONS (LOW TEMP)
75_15.XLS 75 HOT / WET HYDROFLUORIC ACID (UOP HF ALKY UNIT DESIGN, HF-
76_17.XLS 76 HYDROCARBONS W/ OR W/O HYDROGEN
78_15.XLS 78 HYDROCARBONS W/ HYDROGEN BELOW 50 PSIA PP; HIGH PRESSU
81_19.XLS 81 HYDROCARBONS W/ HYDROGEN ABOVE 50 PSIA PP; HYDROGEN (
83_21.XLS 83 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN (P
85_18.XLS 85 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN; H
86_18.XLS 86 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN (P
87_15.XLS 87 AMINE (W/ OR W/O HYDROGEN) (PHWT REQUIRED)
88_18.XLS 88 HYDROCARBONS W/ OR W/O HYDROGEN
89_20.XLS 89 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN;
92_18.XLS 92 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN (P
94_18.XLS 94 HYDROCARBONS W/ HYDROGEN ABOVE 50 PSIA PP; HYDROGEN (
96_13.XLS 96 SANITARY SEWER, OILY WATER DRAINS, CAUSTIC DRAINS, AMINE
97_11.XLS 97 STORM WATER (UNDERGROUND) [CARBON STEEL & CONCRETE]
98_14.XLS 98 CORROSIVE DRAINS / WATER CHLORINATING (UNDERGROUND) [CP
99_10.XLS 99 HF ACID DRAINS (UNDERGOUND)
100_16.XLS 100 COOLING WATER, PLANT WATER, SOFTENED WATER (ABOVEGROU
102_23.XLS 102 FIREWATER PER NFPA 24 (UL/FM), CLARIFIED WATER (ABOVEGROU
104_32.XLS 104 POTABLE WATER NSF-61 CERTIFIED MATERIALS (ABOVEGROUND O
106_23.XLS 106 STEAM, CONDENSATE, BOILER FEEDWATER
107_16.XLS 107 STEAM, CONDENSATE, BOILER FEEDWATER (ASME B31.1)
108_24.XLS 108 STEAM, CONDENSATE, BOILER FEEDWATER
109_21.XLS 109 STEAM, CONDENSATE, BOILER FEEDWATER (ASME B31.1)
111_19.XLS 111 STEAM, CONDENSATE, BOILER FEEDWATER (ASME B31.1 CODE)
114_19.XLS 114 HIGH TEMPERATURE - STEAM, CONDENSATE, BOILER FEEDWATER (P
115_13.XLS 115 STEAM TRACING [304 & 316 SS TUBING]
116_22.PDF 116 EQUIPMENT LAYOUT
120_17.PDF 120 GENERAL PIPING FABRICATION
121_18.PDF 121 UNDERGROUND GRAVITY SEWERS
123_19.PDF 123 PROCESS AND UTILITY PIPING PRESSURE TESTING
124_14.PDF 124 MATERIAL PURCHASE SPECIFICATION - PIPE
125_11.PDF 125 MATERIAL PURCHASE SPECIFICATION - FITTINGS
126_15.PDF 126 MATERIAL PURCHASE SPECIFICATION - FLANGES
127_19.PDF 127 IN-SERVICE WELDING OR HOT TAPPING ON PIPING AND/OR EQUI
128_17.PDF 128 PIPING SELECTION CRITERIA
129_18.PDF 129 VALVE SELECTION CRITERIA
130_23.PDF 130 FLANGES, FITTINGS, GASKETS, AND BOLTING
131_12.PDF 131 PIPING FLEXIBILITY ANALYSIS
132_18.PDF 132 DESIGN LOADS FOR STRUCTURES
133_13.PDF 133 SURGE VIBRATION DESIGN LOADS
134_10.PDF 134 EARTHQUAKE DESIGN LOADS
135_12.PDF 135 AUXILIARY STRUCTURES FOR OPERATION & MAINTENANCE
136_13.PDF 136 PIPE SUPPORT STRUCTURES
137_11.PDF 137 REINFORCED CONCRETE FOUNDATIONS
138_12.PDF 138 SUPPORTING STRUCTURES & FOUNDATIONS FOR HEAVY MACHINE
140_9.PDF 140 EQUIPMENT NOISE LEVEL REQUIREMENTS
141_7.PDF 141 GUIDELINES FOR SELECTION OF SPARE PARTS
142_48.PDF 142 PRESSURE VESSELS
143_19.PDF 143 INTERNALS FOR TOWERS & DRUMS
145_10.PDF 145 INTERNALS FOR FIXED BED REACTORS
146_14.PDF 146 REFRACTORY LINING
147_12.PDF 147 ATMOSPHERIC STORAGE TANKS
148_11.PDF 148 SHOP ASSEMBLED WELDED STEEL STORAGE TANKS
149_12.PDF 149 ACCESSORIES FOR ATMOSPHERIC STORAGE TANKS
150_10.PDF 150 VENTS FOR FIXED ROOF ATMOSPHERIC STORAGE TANKS
151_8.PDF 151 INTERNAL FLOATING COVERS FOR ATMOSPHERIC STORAGE TANKS
152_17.PDF 152 MAINTENANCE OF ATMOSPHERIC STORAGE TANKS
155_14.PDF 155 SPECIAL PURPOSE LUBE SYSTEMS
156_24.PDF 156 RECIPROCATING COMPRESSORS & AUXILIARY SYSTEMS
157_20.PDF 157 CENTRIFUGAL COMPRESSORS - GENERAL
159_12.PDF 159 SPECIAL PURPOSE CENTRIFUGAL FANS
162_26.PDF 162 AIR COOLED HEAT EXCHANGERS
163_21.PDF 163 SHELL & TUBE HEAT EXCHANGERS
164_24.PDF 164 FIRED HEATER DESIGN
165_41.PDF 165 HEAVY DUTY CENTRIFUGAL PUMPS IN HYDROCARBON SERVICE
166_11.PDF 166 ASME B73.1 TYPE HORIZONTAL CENTRIFUGAL PUMPS
167_7.PDF 167 GENERAL PURPOSE STEAM TURBINES FOR REFINERY SERVICE
168_7.PDF 168 SIZING OF DRIVERS & TRANSMISSIONS
171_14.PDF 171 POWER SYSTEM DESIGN REQUIREMENTS & GUIDES
177_14.PDF 177 ELECTRICAL HAZARDOUS AREA CLASSIFICATION AND RELATED ELEC
182_8.PDF 182 MEDIUM AND LOW VOLTAGE BUS DUCT AND CABLE BUS DUCT
183_8.PDF 183 ARC-RESISTANT LOW VOLTAGE MOTOR CONTROL CENTERS
185_21.PDF 185 INSTRUMENTATION DESIGN & ENGINEERING REQUIREMENTS
187_11.PDF 187 SELECTION, DESIGN, MANUFACTURING AND INSTALLATION SPECIF
189_18.PDF 189 MATERIAL REQUIREMENTS FOR HIGH TEMPERATURE HYDROGEN S
194_21.PDF 194 MATERIAL REQUIREMENTS FOR WET H2S SERVICE
234_1.DOC 234 FENWAL HALON 1301 FIRE PROTECTION SYSTEM
238_10.PDF 238 AIR FOAM SYSTEM FOR ATMOSPHERIC STORAGE TANKS
260_21.PDF 260 STEAM TRACING AND TRAPS
264_11.PDF 264 VALVE PURCHASE SPECIFICATION
282_16.PDF 282 MATERIAL PURCHASE SPECIFICATION - FACTORY-MADE INDUCTION
342_19.PDF 342 SPACING & LAYOUT OF EQUIPMENT GUIDELINES FOR NEW UNITS
343_17.PDF 343 LIQUEFIED PETROLEUM GAS (LPG) STORAGE INSTALLATIONS
345_16.PDF 345 CAUSTIC AND UTILITY CONNECTIONS TO PROCESS LINES AND VESS
348_21.PDF 348 BLINDING & ENERGY ISOLATION
349_13.PDF 349 REFINERY SAMPLING SYSTEMS
351_13.PDF 351 EMERGENCY RESPONSE EQUIPMENT AND PREPAREDNESS
352_20.PDF 352 HF ACID ALKYLATION UNIT PERSONAL PROTECTIVE EQUIPMENT (PP
354_17.PDF 354 HF ALKY UNIT PROTECTION & MITIGATION SYSTEMS
355_11.PDF 355 HF ALKY UNIT FIRST AID
356_22.XLS 356 STANDARD PRACTICE WAIVER FORM
358_25.PDF 358 SAFETY INSTRUMENTED SYSTEMS (SIS) GENERAL
359_14.PDF 359 FLUID CATALYTIC CRACKING UNIT APPLICATION STANDARD
361_20.PDF 361 HEATER APPLICATION STANDARD
362_20.PDF 362 FIRED BOILER APPLICATION STANDARD
364_12.PDF 364 SRU APPLICATION STANDARD
1157_20.PDF 1157 EMERGENCY ISOLATION VALVES (EIV)
1159_13.PDF 1159 LIFE CYCLE COST ANAYLSIS
1162_7.PDF 1162 HYDROGEN REMOVAL (BAKE-OUT) GUIDELINES
1205_1.DOC 1205 SPECIFICATION FOR HALON 1301 FIRE PROTECTION SYSTEM
1310_15.PDF 1310 TURNAROUNDS (TAR)
1313_12.PDF 1313 DISTRIBUTION & POWER TRANSFORMERS
1314_9.PDF 1314 OUTDOOR HIGH VOLTAGE POWER CIRCUIT BREAKERS
1315_9.PDF 1315 ARC RESISTANT MEDIUM VOLTAGE METAL CLAD/METAL ENCLOSED
1316_9.PDF 1316 NEUTRAL GROUNDING RESISTOR SYSTEMS
1317_9.PDF 1317 LIGHTNING / SURGE ARRESTERS
1318_9.PDF 1318 LOW VOLTAGE ARC-RESISTANT SWITCHGEAR
1319_8.PDF 1319 ARC RESISTANT MEDIUM VOLTAGE MOTOR CONTROLLERS
1320_9.PDF 1320 MEDIUM VOLTAGE ADJUSTABLE SPEED DRIVE CONTROLLERS
1321_10.PDF 1321 LOW VOLTAGE ADJUSTABLE SPEED AC DRIVE CONTROLLERS
1322_12.PDF 1322 MEDIUM VOLTAGE POWER CABLES
1323_7.PDF 1323 LOW VOLTAGE POWER & CONTROL CABLES
1325_8.PDF 1325 ELECTRICAL DISTRIBUTION BUILDINGS
1326_7.PDF 1326 UNINTERRUPTIBLE POWER SUPPLY (UPS)
1327_7.PDF 1327 STATIONARY BATTERY & BATTERY CHARGERS
1328_9.PDF 1328 MOTOR OPERATED VALVE (MOV) ACTUATORS
1330_10.PDF 1330 SERIES-CONNECTED REACTORS
1331_12.PDF 1331 GENERAL DESIGN AND INSTALLATION OF ELECTRICAL EQUIPMENT
1332_15.PDF 1332 ELECTRICAL EQUIPMENT PREVENTATIVE AND PREDICTIVE MAINTE
1333_14.PDF 1333 INDUCTION MOTORS
1335_12.PDF 1335 CENTRIFUGAL COMPRESSOR GEAR UNIT
1337_10.PDF 1337 CENTRIFUGAL COMPRESSOR DRY GAS SEALS
1338_16.PDF 1338 CENTRIFUGAL COMPRESSOR INSTRUMENTATION
1339_11.PDF 1339 CENTRIFUGAL COMPRESSOR - CONTROL SYSTEM
1341_12.PDF 1341 FIBER OPTICS CABLES & ACCESSORIES
1342_17.PDF 1342 SAFE EQUIPMENT PREPARATION GUIDELINES
1343_14.PDF 1343 OXYGEN PIPING DESIGN
1344_11.PDF 1344 OXYGEN PIPING SYSTEMS CLEANLINESS
1346_13.PDF 1346 POSITIVE MATERIAL IDENTIFICATION (PMI) OF NEW AND EXISTING
1347_16.PDF 1347 RELIEF VALVE TESTING & INSPECTION INTERVALS
1348_8.PDF 1348 REACTOR PROCESS DESIGN GUIDELINES
1349_12.PDF 1349 CATALYST LOADING
1356_15.PDF 1356 REFINERY PRODUCT RELEASE PRACTICE
1358_20.PDF 1358 PRESSURE AND DIFFERENTIAL PRESSURE INSTRUMENTS
1360_6.PDF 1360 CORRATER ELECTRODE MAINTENANCE
1361_13.XLS 1361 WARM DRY OXYGEN
1362_12.XLS 1362 WARM DRY OXYGEN
1363_11.XLS 1363 WARM DRY OXYGEN; OXYGEN PRESSURE EQUALIZATION
1364_12.XLS 1364 WARM DRY OXYGEN
1381_14.PDF 1381 MACHINERY INSTALLATION & INSTALLATION DESIGN
1384_3.PDF 1384 DUMMY SUPPORTS, SUPPORT TRUNNIONS & RISER CLAMP SHEAR
1387_3.PDF 1387 VENTS, DRAINS, & UTILITY STATIONS
1394_4.PDF 1394 FIREWATER AND SEWER SYSTEM PIPING DETAILS
1396_11.PDF 1396 TYPICAL INJECTION SYSTEM INSTALLATION
1402_3.XLS 1402 INTERNALS FOR TOWERS & DRUMS DATA SHEET
1403_27.PDF 1403 GENERAL SPECIFICATION FOR CONTROL VALVES, POSITIONERS AN
1407_23.PDF 1407 GENERAL SPECIFICATION FOR FLOW INSTRUMENTS
1418_12.PDF 1418 CONFINED SPACE ENTRY
1419_11.PDF 1419 SYNCHRONOUS MOTORS
1425_9.PDF 1425 RELIABILITY PERFORMANCE MONITORING
1427_12.PDF 1427 SAFE WORK PERMIT
1428_30.PDF 1428 PIPING INSPECTION PROGRAM
1430_18.PDF 1430 BLACK OIL RELEASE PRACTICE
1433_14.PDF 1433 ADDITIVE OVERSIGHT PROGRAM
1434_13.PDF 1434 ADDITIVE TESTING
1437_13.PDF 1437 SAFE ENTRY INTO INERT ATMOSPHERE
1438_12.PDF 1438 HIGH TEMPERATURE SULFIDIC & NAPHTHENIC ACID CORROSION
1441_27.PDF 1441 REFINING DOCUMENT CONTROL POLICY
1445_10.PDF 1445 TANK GAUGING FOR INVENTORY RECONCILIATION
1446_13.PDF 1446 BUDGET SYSTEM USER MANUAL
1447_10.PDF 1447 AFE SYSTEM USERS MANUAL
1449_12.PDF 1449 MULTISTAGE CENTRIFUGAL BLOWERS
1450_9.PDF 1450 INBOUND AND OUTBOUND EXTERIOR INSPECTION OF RAILCARS
1451_11.PDF 1451 LOADING & UNLOADING HAZMAT RAILCARS
1452_4.PDF 1452 FORM - PRESSURE TANK CAR INSPECTION FORM
1453_6.PDF 1453 FORM - GENERAL SERVICE TANK CAR INSPECTION FORM
1454_12.PDF 1454 RECIPROCATING GAS COMPRESSOR REPAIR
1455_5.XLS 1455 COMPRESSOR CRANKCASE WORKSHEET
1456_14.PDF 1456 INSPECTION MANAGEMENT
1457_14.PDF 1457 SUCTION & DISCHARGE PIPING FOR PUMPS
1458_7.PDF 1458 STRAINERS FOR MECHANICAL EQUIPMENT
1459_15.PDF 1459 MATERIAL REQUIREMENTS FOR CAUSTIC SERVICE
1460_3.XLS 1460 TAR FORM - TECH SERVICE TAR RESPONSIBILITIES
1461_3.XLS 1461 TAR FORM - ENVIRONMENTAL DEPARTMENT TAR CHECKLIST
1462_2.XLS 1462 TAR FORM - SAFETY PPE SAMPLE CHECKLIST
1463_5.DOC 1463 TAR FORM - TURNAROUND WORK SCOPE APPROVAL FORM
1465_4.XLSX 1465 TAR FORM - CONTRACT STATUS
1466_6.DOC 1466 TAR FORM - TURNAROUND WORK SCOPE DEVELOPMENT CHECKLIS
1467_5.XLS 1467 TAR FORM - REFINERY DAILY TURNAROUND REPORT
1468_1.XLS 1468 TAR FORM - SAFETY DEPARTMENT TAR CHECKLIST
1470_3.XLS 1470 TAR FORM - TAR PERFORMANCE SUMMARY
1475_3.PDF 1475 TAR FORM - POP TEMPLATES
1476_2.XLS 1476 TAR FORM - TAR PIPING ESTIMATOR 1
1477_2.XLS 1477 TAR FORM - ESTIMATING NORMS
1478_2.XLS 1478 TAR FORM - TAR PIPING ESTIMATOR 2
1517_6.DOCX 1517 (WITHDRAWN) CLARIFIERS
1554_11.PDF 1554 ATMOSPHERIC STORAGE TANK INSTRUMENTATION
1555_15.PDF 1555 DCS ALARM MANAGEMENT
1556_3.XLS 1556 EMERGENCY EYEWASH & SHOWER EQUIPMENT RISK-BASED EVAL
1557_17.PDF 1557 AFE PREPARATION & APPROVAL
1561_14.PDF 1561 PROCESS HEATER NOT-TO-EXCEED (NTE) LIMITS & ALARMS
1562_8.PDF 1562 PETROCHEMICALS RELEASE PROCEDURES
1563_11.PDF 1563 HF ALKYLATION UNIT PROPANE MONITORING
1564_16.XLS 1564 STANDARDS CHANGE REQUEST FORM
1565_1.XLS 1565 INVENTORY CONTROL OF FRESH PRECIOUS METALS CATALYST FOR
1566_1.XLS 1566 SPENT CATALYST CONTROL FORM
1571_0.DWG 1571 CONCRETE COLUMN GROUNDING CONNECTION
1572_0.DWG 1572 RISER ASSEMBLY GROUNDING CONNECTION
1573_0.DWG 1573 CABLE TRAY GROUNDING CONNECTION
1574_0.DWG 1574 STEEL COLUMN OR EQUIPMENT GROUND ASSEMBLY
1575_0.DWG 1575 GROUND WELL ASSEMBLY
1576_0.DWG 1576 GROUND ROD ASSEMBLY
1577_0.DWG 1577 CADWELD CONNECTION
1578_0.DWG 1578 (WITHDRAWN) GROUND BUS CONCRETE COLUMN MOUNT ASSEM
1579_0.DWG 1579 LIGHTING AND RECEPTACLE TRANSFORMER GROUNDING ASSEMBL
1580_0.DWG 1580 EQUIPMENT GROUND ASSEMBLY
1581_0.DWG 1581 MOTOR GROUND ASSEMBLY
1582_0.DWG 1582 GROUND GRID CADWELD TAP DETAIL
1583_0.DWG 1583 TANK OR VESSEL GROUND ASSEMBLY
1584_0.DWG 1584 (WITHDRAWN) GROUND BUS STEEL COLUMN MOUNT ASSEMBLY
1585_0.DWG 1585 TRANSFORMER GROUNDING ASSEMBLY
1586_0.DWG 1586 GROUND REEL MOUNTING DETAIL
1587_0.DWG 1587 AREA CLASSIFICATION STORAGE TANK (OUTDOORS)
1588_0.DWG 1588 AREA CLASSIFICATION API/DNF SEPARATOR TANKS
1589_0.DWG 1589 CABLE TRAY EXPANSION GUIDE ASSEMBLY
1590_0.DWG 1590 CABLE TRAY HOLD DOWN ASSEMBLY
1591_0.DWG 1591 VERTICAL HINGED SPLICE PLATE ASSEMBLY
1592_0.DWG 1592 CABLE TRAY GROUNDING ASSEMBLY
1593_0.DWG 1593 HORIZONTAL ADJUSTABLE CONNECTOR ASSEMBLY
1594_0.DWG 1594 CABLE TRAY TO CONDUIT TRANSITION
1595_0.DWG 1595 CONTROL STAND
1596_0.DWG 1596 CONTROL STATION HANDRAIL MOUNT
1597_0.DWG 1597 CONTROL STATION OR DISC. SW. COLUMN MOUNT
1598_0.DWG 1598 MOTOR CONNECTION ONE OVERHEAD CONDUIT HAZARDOUS ARE
1599_0.DWG 1599 MOTOR CONNECTION TWO OVERHEAD CONDUITS HAZARDOUS AR
1600_0.DWG 1600 MOTOR CONNECTION 120V METERING PUMP HAZARDOUS AREA
1601_0.DWG 1601 480V MOTOR TERMINAL BOX CONNECTION
1602_0.DWG 1602 LIGHTING FLOODLIGHTING WOOD POLE
1603_0.DWG 1603 HANDRAIL MAST., STEEL PLATFORM, CLASS 1, DIV. 1 OR 2, GROUP B
1604_0.DWG 1604 PENDANT MOUNTED FIXTURE CLASS 1, DIV. 2, GROUP B, C, AND D
1605_0.DWG 1605 BRACKET MOUNTED FIXTURE CLASS 1, DIV. 1 OR 2, GROUP B, C, A
1606_0.DWG 1606 HANDRAIL MOUNTED REC. OR SWITCH CLASS 1, DIV. 1 OR 2, GROU
1607_0.DWG 1607 STEEL COLUMN MOUNTED RECPTACLE OR SWITCH ABOVE GROUND
1608_0.DWG 1608 ELECTRICAL DETAIL CONDUIT SUPPORT (VERTICAL)
1609_0.DWG 1609 ELECTRICAL DETAIL 3/4" GROUND ROD INSTALLATION
1610_0.DWG 1610 ELECTRICAL DETAIL EQUIPMENT GROUND MECH. CONNECTION
1611_0.DWG 1611 ELECTRICAL DETAIL EQUIPMENT GROUND CONDUIT
1612_0.DWG 1612 ELECTRICAL DETAIL FENCE POST GROUND
1613_0.DWG 1613 ELECTRICAL DETAIL DEAD-END POWER TRANSITION
1614_0.DWG 1614 SEPARATE POWER AND CONTROL STEEL CONDUIT CLASS 1, DIVISIO
1615_0.DWG 1615 TRUCK GROUNDING STATION
1616_0.DWG 1616 JUNCTION BOX 40 OR 60 TERMINAL
1617_0.DWG 1617 JUNCTION BOX 80 OR 120 TERMINAL
1618_0.DWG 1618 JUNCTION BOX 120 OR 180 TERMINAL
1619_0.DWG 1619 (WITHDRAWN) COLUMN MOUNTED PANEL AND TRANSFORMER ABOVE
1620_0.DWG 1620 TYPICAL VERTICAL AND HORIZONTAL CONDUIT SUPPORT AND SPA
1621_0.DWG 1621 TYPICAL JUNCTION BOX INSTALLATION
1622_0.DWG 1622 TYPICAL CABLE TRAY ARRANGEMENT
1623_0.DWG 1623 TYPICAL CONDUIT SUPPORT ON LADDER
1624_0.DWG 1624 JUNCTION BOX AND EQUIPMENT SUPPORT TO COLUMN
1625_0.DWG 1625 TRAPEZE SUPPORT ASSEMBLY STRUT
1626_0.DWG 1626 CABLE TRAY CLAMP ASSEMBLY
1627_0.DWG 1627 TYPICAL CONDUIT STUB-UP
1628_0.DWG 1628 ELECTRICAL DETAIL U.G. STUB-UP (GALV. CONDUIT)
1629_0.DWG 1629 ELECTRICAL POWER POLE DETAIL (CONCRETE)
1630_1.DWG 1630 ELECTRICAL STANDARD DETAIL CABLE TRAY SUPPORT PIPE RACK
1631_1.DWG 1631 ELECTRICAL STANDARD DETAIL CABLE TRAY SUPPORT VERTICAL C
1632_0.DWG 1632 ELECTRICAL STANDARD DETAIL CONDUIT TO C-L-X TRANSITION TE
1633_0.DWG 1633 ELECTRICAL STANDARD DETAIL CABLE CHANNEL TO CABLE TRAY TR
1634_0.DWG 1634 ELECTRICAL STANDARD DETAIL CABLE TRAY SUPPORT VERTICAL C
1635_0.DWG 1635 ELECTRICAL STANDARD DETAIL CABLE TRAY SUPPORT HORIZONTAL
1636_0.DWG 1636 ELECTRICAL STANDARD DETAIL PROTECTIVE SLEEVE ASSEMBLY FO
1637_0.DWG 1637 ELECTRICAL STANDARD DETAIL EQUIPMENT GROUND MECHANICA
1638_0.DWG 1638 ELECTRICAL STANDARD DETAIL MOTOR AND CTRL STAND GROUN
1639_0.DWG 1639 ELECTRICAL STANDARD DETAIL TRANSFORMER GROUND SECOND
1640_0.DWG 1640 ELECTRICAL STANDARD DETAIL TRANSFORMER GROUND PRIMAR
1641_0.DWG 1641 ELECTRICAL STANDARD DETAIL EQUIPMENT GROUND MECHANICA
1642_0.DWG 1642 ELECTRICAL STANDARD DETAIL EQUIPMENT GROUND MECHANICA
1643_0.DWG 1643 POWER AND CONTROL STEEL CONDUIT CLASS 1, DIVISION 2
1644_0.DWG 1644 (WITHDRAWN) BRACKET MOUNTED FLOODLIGHT, STEEL OR CONCRE
1645_0.DWG 1645 (WITHDRAWN) VERTICAL MOTOR INSTALLATION TOP AND ABOVE
1646_0.DWG 1646 AIR CONNECTIONS AIR SUPPLY W/O REGULATOR
1647_0.DWG 1647 ELECTRICAL CONNECTIONS SINGLE INST. NO SEAL REQUIIRED
1648_0.DWG 1648 ELECTRICAL CONNECTIONS SINGLE INST. SEAL REQUIIRED
1649_0.DWG 1649 ELECTRICAL CONNECTIONS SINGLE INST. W/ PRIMARY ELEMENT
1650_0.DWG 1650 ELECTRICAL CONNECTIONS TE PRIMARY ELEMENT
1651_0.DWG 1651 ELECTRICAL CONNECTIONS SOLENOID, NO SEAL REQUIRED
1652_0.DWG 1652 ELECTRICAL CONNECTIONS LEVEL INST. W/ REMOTE INDICATOR
1653_0.DWG 1653 ELECTRICAL CONNECTIONS ENCLOSURE SEAL REQUIRED
1654_0.DWG 1654 ELECTRICAL CONNECTIONS PRIMARY ELEMENT NO SEAL REQUIRED
1655_0.DWG 1655 ELECTRICAL CONNECTIONS INST. W/ PRIMARY ELEMENT W/ DISC.
1656_0.DWG 1656 ELECTRICAL CONNECTIONS INTERPOSING RELAY
1657_0.DWG 1657 INSTRUMENT SUPPORTS SINGLE INST. STAND 4 FEET - 6 INCHES
1658_1.DWG 1658 INSTRUMENT MOUNTING ASSEMBLY - DUAL PEDESTAL
1659_0.DWG 1659 INSTRUMENT SUPPORTS SINGLE INST. COLUMN MOUNT
1660_0.DWG 1660 INSTRUMENT SUPPORTS STAND MOUNTING GRATING
1661_0.DWG 1661 INSTRUMENT SUPPORTS STAND MOUNTING ON CONCRETE
1662_0.DWG 1662 INSTRUMENT CONNECTIONS FLOW D/P BELOW TAP
1663_0.DWG 1663 INSTRUMENT CONNECTIONS LEVEL D/P BELOW TAP
1664_0.DWG 1664 INSTRUMENT CONNECTIONS PRESSURE BELOW TAP
1665_0.DWG 1665 INSTRUMENT CONNECTIONS PRESSURE ABOVE TAP
1666_0.DWG 1666 INSTRUMENT CONNECTIONS PRESSURE DIRECT MOUNT
1667_0.DWG 1667 INSTRUMENT CONNECTIONS LEVEL BUBBLER ON SUMP
1668_0.DWG 1668 INSTRUMENT CONNECTIONS PRESSURE GAUGES
1669_0.DWG 1669 INSTRUMENT CONNECTIONS PRESSURE SWITCHES, 2"
1670_0.DWG 1670 AIR CONNECTIONS PNEUMATIC SIGNAL CONNECTION
1671_0.DWG 1671 INSTALLATION DETAIL PRESSURE TRANSMITTER LIQUID SERVICE
1672_0.DWG 1672 INSTALLATION DETAIL DIFF. PRESSURE TRANSMITTER LIQUID SERVI
1673_0.DWG 1673 INSTALLATION DETAIL TEMPERATURE ELEMENT
1674_0.DWG 1674 INSTALLATION DETAIL LEVEL TRANSMITTER DISPLACER TYPE
1675_0.DWG 1675 INSTALLATION DETAIL CONTROL VALVE WITH POSITIONER
1676_0.DWG 1676 INSTALLATION DETAIL LO LEVEL SWITCH DISPLACER TYPE
1677_0.DWG 1677 INSTALLATION DETAIL ON/OFF VALVE SOLENOID ACTUATED
1678_0.DWG 1678 INSTALLATION DETAIL MOUNTING STAND SINGLE PEDESTAL SUPPO
1679_0.DWG 1679 INSTALLATION DETAIL DIFF PRESSURE INDICATOR LIQUID SERVICE,
1680_4.DWG 1680 INSTALLATION DETAIL MOUNTING STAND SINGLE PEDESTAL SUPPO
1681_0.DWG 1681 INSTALLATION DETAIL MOUNTING STAND SINGLE PEDESTAL SUPPO
1682_0.DWG 1682 INSTALLATION DETAIL SULFUR ANALYZER SAMPLE TUBE BUNDLE C
1683_0.DWG 1683 INSTALLATION DETAIL DOPAK SAMPLE SYSTEM MOUNTING AND HO
1684_0.DWG 1684 INSTALLATION DETAIL TYPICAL RCS ACTUATOR AND ENCLOSURE DE
1685_0.DWG 1685 TYPICAL INSTALLATION DETAIL FLOW TRANSMITTER LIQUID SERVIC
1686_0.DWG 1686 TYPICAL INSTALLATION DETAIL TEMPERATURE TRANSMITTER ELEM
1687_0.DWG 1687 INSTALLATION DETAIL TYPICAL REXA ACTUATOR AND ENCLOSURE D
1688_0.DWG 1688 INSTALLATION DETAIL MOUNTING STAND SINGLE PEDESTAL SUPPO
1689_0.DWG 1689 INSTALLATION DETAIL PRESSURE TRANSMITTER DIRECT MOUNT
1690_0.DWG 1690 INSTRUMENT INSTALLATION DETAIL ON/OFF VALVES MECHANICAL/
1691_0.DWG 1691 INSTALLATION DETAIL GAS DETECTOR MOUNTED ON COLUMN
1692_0.DWG 1692 PROCESS DETAIL LEVEL ASSEMBLY LIQUID SERVICE
1693_0.DWG 1693 PNEUMATIC DETAIL AIR SUPPLY ASSEMBLY ON-OFF CONTROL VALV
1694_0.DWG 1694 PNEUMATIC DETAIL AIR SUPPLY ASSEMBLY CONTROL VALVE WITH
1695_0.DWG 1695 PROCESS DETAIL FLOW TRANSMITTER ASSEMBLY MULTIPLE TRANS
1696_0.DWG 1696 PROCESS DETAIL PRESSURE TRANSMITTER ASSEMBLY VAPOR SERVI
1697_0.DWG 1697 MOUNTING DETAIL SUPPORT FABRICATION DETAIL TRIPLE PEDEST
1698_0.DWG 1698 PNEUMATIC DETAIL PRESSURE INDICATOR ASSEMBLY REMOTE MO
1699_0.DWG 1699 PROCESS DETAIL FLOW INDICATOR ASSEMBLY REMOTE MOUNTED F
1700_0.DWG 1700 PROCESS DETAIL PILOT AIR/GAS SUPPLY ASSEMBLY CLAUS COMBU
1701_0.DWG 1701 FABRICATION DETAIL PURGE PANEL ASSEMBLY INSTRUMENT AIR/
1702_0.DWG 1702 FABRICATION DETAIL PURGE PANEL ASSEMBLY INSTRUMENT AIR/
1703_0.DWG 1703 PNEUMATIC DETAIL FLAME SCANNER ASSEMBLY CLAUS COMBUSTO
1704_0.DWG 1704 PNUEMATIC DETAIL FLAME SCANNER ASSEMBLY INCINERATOR BU
1705_0.DWG 1705 PNUEMATIC DETAIL PURGE CONNECTION ASSEMBLY TEMP. TRANS
1706_0.DWG 1706 PROCESS DETAIL PILOT AIR/GAS SUPPLY ASSEMBLY INCINERATOR
1707_0.DWG 1707 PROCESS DETAIL ROTAMETER ASSEMBLY MULTIPLE ROTAMETER C
1708_0.DWG 1708 FABRICATION DETAIL PURGE PANEL ASSEMBLY INSTRUMENT AIR/
1709_0.DWG 1709 FABRICATION DETAIL PURGE PANEL ASSEMBLY INSTRUMENT AIR/
1710_0.DWG 1710 PROCESS DETAIL LEVEL ASSEMBLY (BUBBLER) LIQUID SERVICE
1711_0.DWG 1711 PNEUMATIC DETAIL PRESSURE ASSEMBLY REMOTE MOUNTED PRES
1712_0.DWG 1712 PNEUMATIC DETAIL PRESSURE ASSEMBLY SCREWED WITH DIAPHR
1713_0.DWG 1713 PNEUMATIC DETAIL PRESSURE ASSEMBLY SCREWED WITH DIAPHR
1714_0.DWG 1714 PNEUMATIC DETAIL AIR SUPPLY ASSEMBLY ON-OFF CONTROL VALV
1715_0.DWG 1715 GENERAL NOTES FOR INSTRUMENTATION
1716_0.DWG 1716 SUPPORT DETAIL INSTRUMENT TUBING SUPPORT TRAY
1717_0.DWG 1717 WINTERIZAION DETAIL INSTRUMENT ENCLOSURE DETAILS
1718_0.DWG 1718 PROCESS DETAIL LEVEL ASSEMBLY DIAPHRAGM SEAL WITH STEAM
1719_0.DWG 1719 PROCESS DETAIL PRESSURE ASSEMBLY PILOT OPERATED PRESSURE
1720_0.DWG 1720 PROCESS DETAIL PRESSURE INDICATOR ASSEMBLY SCREWED WITH
1721_0.DWG 1721 MOUNTING DETAIL STANCHION ASSEMBLY CAPILLARY TUBING SPO
1722_0.DWG 1722 MOUNTING DETAIL STANCHION ASSEMBLY CAPILLARY TUBING SPO
1723_0.DWG 1723 PROCESS DETAIL FLOW INDICATOR ASSEMBLY REMOTE MOUNTED F
1724_0.DWG 1724 PNEUMATIC DETAIL AIR SUPPLY ASSEMBLY CONTROL VALVE WITH
1725_0.DWG 1725 MOUNTING DETAIL STANCHION ASSEMBLY H2S DETECTOR
1726_0.DWG 1726 PROCESS DETAIL PRESSURE ASSEMBLY GLYCOL FILL
1727_0.DWG 1727 PROCESS DETAIL PRESSURE ASSEMBLY ELEC. TRACE WITH DIAPHRA
1728_0.DWG 1728 PROCESS DETAIL PRESSURE ASSEMBLY ELEC. TRACE WITH IND.
1729_0.DWG 1729 PROCESS DETAIL PRESSURE ASSEMBLY STEAM TRACE WITH DIAPHR
1730_0.DWG 1730 PROCESS DETAIL PRESSURE ASSEMBLY STEAM TRACE WITH INDICA
1731_0.DWG 1731 PROCESS DETAIL O2 ANALYZER ASSEMBLY WITH CALIBRATION PAN
1732_0.DWG 1732 PROCESS DETAIL PRESSURE ASSEMBLY BELOW TAP
1733_0.DWG 1733 LEVEL ASSEMBLY LIQUID SERVICE
1734_0.DWG 1734 LEVEL ASSEMBLY LIQUID SERVICE
1735_5.PDF 1735 PRECIOUS METALS CATALYST MANAGEMENT
1736_4.XLS 1736 EIV SCREENING ANALYSIS WORKSHEET
1737_0.DWG 1737 PRESSURE GAUGE FOR MEASUREMENT IN HYDROCARBON SERVIC
1741_1.XLS 1741 ANALOG SIGNAL RATIONALIZATION WORKSHEET
1742_1.XLS 1742 DISCRETE SIGNAL RATIONALIZATION WORKSHEET
1743_15.XLS 1743 HOT / WET HYDROFLUORIC ACID (COP HF ALKY UNIT DESIGN) (PW
1776_25.PDF 1776 PSM/RMP OPERATIONS / PRODUCTS CONTROL TRAINING
1777_12.XLS 1777 CORE SPECIFICATION WAIVER FORM
1778_13.PDF 1778 PSM/RMP EMPLOYEE PARTICIPATION
1779_8.PDF 1779 RETRACTABLE, FIXED AND WATER WASH INJECTION QUILL
1787_37.PDF 1787 PSM/RMP MANAGEMENT OF CHANGE (MOC) & PRE-STARTUP SAFET
1788_16.XLS 1788 HAZARD EVALUATION & RISK RANKING CHECKLIST
1789_41.PDF 1789 PSM/RMP REFINING OPERATING PROCEDURES
1790_8.XLS 1790 EMERGENCY MOC FORM
1791_2.XLS 1791 NEW CRUDE COMPARISON WORKSHEET
1792_12.PDF 1792 NEW CRUDE OIL APPROVAL PROCESS
1793_10.PDF 1793 PSM/RMP TRADE SECRETS
1794_0.DWG 1794 INSTALLATION DETAIL PRESSURE INDICATOR ASSEMBLY DIRECT M
1795_0.DWG 1795 INSTALLATION DETAIL PRESSURE INDICATOR ASSEMBLY DIRECT M
1796_0.DWG 1796 INSTRUMENT CONNECTIONS PRESSURE ABOVE VERTICAL TAP
1797_0.DWG 1797 CONTROL STAND
1798_0.DWG 1798 MUSTER READER STAND-MOB-3 INSTALLATION DETAIL
1799_0.DWG 1799 MUSTER READER OUTSIDE STAND MOUNT INSTALLATION DETAIL
1800_0.DWG 1800 MUSTER READER OUTSIDE STAND MOUNT WITH 1300 ENCLOSURE I
1801_0.DWG 1801 MUSTER READER FLUSH WALL MOUNT INSTALLATION DETAIL
1802_0.DWG 1802 SLURRY PUMP FLUSH FOR PUMPS 93J-481 AND 93J-482
1803_15.PDF 1803 REFINERY SAMPLING PROCEDURES
1804_20.PDF 1804 PSM/RMP PROCESS HAZARD ANALYSIS (PHA)
1805_23.PDF 1805 PSM/RMP PROCESS SAFETY INFORMATION (PSI)
1806_26.PDF 1806 PSM/RMP MECHANICAL INTEGRITY
1809_3.DOC 1809 (WITHDRAWN) PHA - TYPICAL PHA REPORT CHECKLIST
1810_3.DOC 1810 (WITHDRAWN) PHA - RECOMMENDATION LIST
1811_2.XLS 1811 PHA - OFF-SITE ENVIRONMENTAL PROTECTION CHECKLIST
1812_2.XLS 1812 PHA - REVALIDATION CHECKLIST
1813_2.XLS 1813 PHA - HUMAN FACTORS ISSUES CHECKLIST
1814_2.XLS 1814 PHA - FACILITY & STATIONARY SOURCE SITING ISSUES CHECKLIST
1817_14.PDF 1817 FIREPROOFING
1818_4.XLS 1818 HF ALKY INTERNAL API 751 AUDIT CHECKLIST
1819_12.PDF 1819 PSM/RMP CONTRACTORS
1820_14.PDF 1820 PSM/RMP EMERGENCY RESPONSE AND PLANNING
1821_12.PDF 1821 PSM/RMP SAFE WORK PRACTICES
1822_21.PDF 1822 PSM/RMP COMPLIANCE AUDITS
1823_22.PDF 1823 PSM/RMP INCIDENT INVESTIGATION
1824_14.XLS 1824 MPMS MANDATORY DELIVERABLE LIST
1826_2.XLS 1826 FUME HOOD AUDIT DETAILS
1827_3.XLS 1827 FUME HOOD INSPECTION CHECKLIST
1830_5.XLS 1830 EQUIPMENT NOISE DATA SHEET
1832_15.PDF 1832 H2S EXPOSURE CONTROL PROGRAM
1833_9.PDF 1833 HF ALKY INTERNAL API 751 AUDIT PLAN
1834_20.PDF 1834 LARGE PROJECT EXECUTION REQUIREMENTS
1836_7.PDF 1836 REFINING SAFETY POLICY
1866_10.PDF 1866 LIFE CRITICAL SAFETY RULES & ACCOUNTABILITY
1884_11.PDF 1884 FUME HOOD SYSTEM REQUIREMENTS FOR REFINERY AND RAD LA
1954_22.PDF 1954 APPROVED MANUFACTURERS LIST (AML) FOR PIPING SYSTEMS
1968_12.PDF 1968 MOTOR VEHICLE SAFETY & DRIVING STANDARD
1970_4.XLS 1970 MATERIAL PURCHASE SPECIFICATION - FACTORY-MADE INDUCTION
1996_77.XLS 1996 PIPING LINE CLASS MASTER INDEX
2058_0.DWG 2058 PROCESS FLOW ASSEMBLY D/P FLOW TRANSMITTER LIQUID SERVIC
2059_0.DWG 2059 SUPPORT FOR CLOSED LOOP SAMPLING SYSTEMS - DETAIL SHEET
2126_10.PDF 2126 PRODUCT QUALITY MANAGEMENT
2207_5.XLS 2207 MERIDIUM ENHANCEMENT REQUEST FORM
2208_2.XLS 2208 NEW EMPLOYEE FIELD REVIEW DOCUMENTATION FORM
2211_4.PDF 2211 FUEL GAS & PILOT GAS PIPING ARRANGEMENT DRAWING
2212_2.PDF 2212 HYDROGEN & FEED HYDROGEN & FEED TRIP DRAWING
2213_2.PDF 2213 FEED HEATER FEED TRIP DRAWING
2214_2.PDF 2214 STEAM ECONOMIZER DRAWING
2215_3.PDF 2215 BALANCED DRAFT HEATER W/ AUTOMATED DOORS DRAWING
2216_3.PDF 2216 FORCED DRAFT HEATER W/O AUTOMATED DOORS DRAWING
2217_3.PDF 2217 NATURAL DRAFT HEATER DRAWING
2218_4.PDF 2218 TYPICAL BURNER DETAIL
2219_0.DWG 2219 INSTALLATION DETAIL LEVEL TRANSMITTER & LOCAL INDICATOR
2220_0.DWG 2220 INSTALLATION DETAIL EMERGENCY ISOLATION VALVE WITH SOLEN
2221_0.DWG 2221 INSTALLATION DETAIL PRESSURE TRANSMITTER STORAGE TANKS
2222_0.DWG 2222 INSTALLATION DETAIL LEVEL TRANSMITTER / TEMP. ELEMENT & LO
2229_1.XLS 2229 HAZARDOUS AREA CLASSIFICATION DATA SHEET
2230_4.DOCX 2230 PMI REPORT FORM
2231_11.PDF 2231 POSITIVE MATERIAL IDENTIFICATION (PMI) OF NEW AND EXISTING
2232_3.XLS 2232 REFINING NUMBERING CROSS REFERENCE
2233_3.XLS 2233 PRESSURE VESSEL MATERIAL RECORD
2234_4.XLS 2234 PRESSURE VESSEL DATA SHEET
2235_2.PDF 2235 COLUMN DAVITS (2 SHEETS)
2236_2.PDF 2236 VESSEL PIPE SUPPORTS
2237_3.PDF 2237 VESSEL PIPE GUIDES
2238_2.PDF 2238 MIST ELIMINATOR DETAILS
2239_3.PDF 2239 VORTEX BREAKER DETAILS
2240_2.PDF 2240 VERTICAL VESSEL SUPPORT SKIRT DETAILS
2241_2.PDF 2241 VERTICAL VESSEL SKIRT AND BASE DETAILS (3 SHEETS)
2242_4.PDF 2242 SUPPORTS FOR HOT INSULATION AND FABRICATION (4 SHEETS)
2243_2.PDF 2243 SUPPORT LEG AND BASE PLATE DETAILS
2244_2.PDF 2244 HINGE AND DAVIT DETAILS FOR MANWAY (4 SHEETS)
2245_2.PDF 2245 SADDLE DETAILS FOR HORIZONTAL VESSELS (4 SHEETS)
2246_4.PDF 2246 LADDER AND BRACKET DETAILS (5 SHEETS)
2247_4.PDF 2247 TYPICAL VESSEL LADDERS AND PLATFORMS (5 SHEETS)
2250_3.PDF 2250 GAGE WELL AND GUIDE POLE
2274_2.XLS 2274 MOTOR STARTING REACTORS DATA SHEET
2275_2.XLS 2275 REFRACTORY INSTALLATION LOG
2276_3.XLS 2276 FACTORY ACCEPTANCE TEST - INSTRUMENT SHELTER CHECKOUT
2277_3.XLS 2277 FACTORY ACCEPTANCE TEST - SYSTEM CHECKOUT
2278_4.XLS 2278 FACTORY ACCEPTANCE TEST - OPERATOR STATION CHECKOUT
2279_3.XLS 2279 FACTORY ACCEPTANCE TEST - MARSHALLING PANEL CHECKOUT
2280_4.XLS 2280 FACTORY ACCEPTANCE TEST - SYSTEM ACCEPTANCE CHECKOUT
2281_8.PDF 2281 HEAT EXCHANGER TUBE BUNDLE ENHANCED INSPECTION
2282_8.DOC 2282 OPERATING PROCEDURES - TEMPLATE 01 - EMERGENCY SHUTDO
2283_6.DOC 2283 OPERATING PROCEDURES - TEMPLATE 02 - STEP-BY-STEP PROCEDU
2284_7.DOC 2284 OPERATING PROCEDURES - TEMPLATE 06 - GUIDELINE
2285_9.DOC 2285 OPERATING PROCEDURES - TEMPLATE 07 - CRITICAL PROCESS VARI
2286_10.DOC 2286 OPERATING PROCEDURES - TEMPLATE 08 - TROUBLESHOOTING GU
2288_1.XLS 2288 NDE MANUAL - MAGNETIC PARTICLE/LIQUID PENETRANT EXAMIN
2289_1.XLSX 2289 NDE MANUAL - REPORT OF RADIOGRAPHIC INSPECTION OF WELDS
2290_9.PDF 2290 NDE MANUAL - MANUAL DISTRIBUTION & REVISION CONTROL PR
2291_9.PDF 2291 NDE MANUAL - QUALIFICATION & CERTIFICATION OF NDE PERSON
2292_9.PDF 2292 NDE MANUAL - MAGNETIC PARTICLE TESTING (MT)
2293_9.PDF 2293 NDE MANUAL - LIQUID PENETRANT TESTING (PT)
2294_9.PDF 2294 NDE MANUAL - RADIOGRAPHIC TESTING FILM INTERPRETATION (RT
2295_10.PDF 2295 NDE MANUAL - RADIOGRAPHIC FILM PROFILE (THICKNESS) EXAMI
2296_8.PDF 2296 NDE MANUAL - DIGITAL ULTRASONICS THICKNESS EXAMINATION (
2297_9.PDF 2297 NDE MANUAL - VISUAL EXAMINATION PROCEDURE (VE)
2304_1.XLS 2304 OUTDOOR HIGH VOLTAGE POWER CIRCUIT BREAKERS DATA SHEET
2305_2.XLS 2305 HAZARD RADII FOR PUMPS FORM PER API RP 500 APPENDIX D
2311_3.XLS 2311 IN-SERVICE WELDING CHECKLIST
2312_1.XLS 2312 LOW VOLTAGE SWITCHGEAR DATA SHEET
2313_0.DWG 2313 WELDED DUMMY SUPPORT ON ELBOW TURNING UP WITH SHOE NP
2314_1.DWG 2314 WELDED DUMMY SUPPORT ON ELBOW TURNING UP WITH NO INSUL
2315_0.DWG 2315 WELDED DUMMY SUPPORT ON ELBOW TURNING DOWN WITH SHOE
2316_1.DWG 2316 WELDED DUMMY SUPPORT ON ELBOW TURNING DOWN WITH NO IN
2317_0.DWG 2317 WELDED DOUBLE TRUNNION SUPPORT NPS 2" THRU 24"
2318_0.DWG 2318 WELDED DUMMY SUPPORT ON VERTICAL PIPE NPS 2" THRU 24"
2319_0.DWG 2319 WELDED DUMMY SUPPORT ON ELBOW FLAT TURNING WITH SHOE N
2320_1.DWG 2320 WELDED DUMMY SUPPORT ON ELBOW FLAT TURNING WITH NO INS
2321_1.DWG 2321 WELDED BASE SUPPORT VERTICAL ON ELBOW NO INSULATION NPS
2322_1.XLS 2322 RELIEF VALVE TEST / INSPECTION INTERVAL EVALUATION FORM
2323_26.PDF 2323 PRESSURE PROTECTION AND DISPOSAL
2324_2.DOCX 2324 ELECTRICAL DATA SHEET FOR DISTRIBUTION AND POWER TRANSF
2332_14.PDF 2332 SCHEDULING GUIDELINES FOR OPERATING EMPLOYEES DURING
2342_8.PDF 2342 RELIEF SYSTEM STUDY RISK MANAGEMENT AND MITIGATION PLAN
2343_0.XLS 2343 EQUIPMENT RECEIVING / STORAGE CHECKLIST
2344_0.XLS 2344 EQUIPMENT INSTALLATION CHECKLIST
2345_0.XLS 2345 EQUIPMENT COMMISSIONING CHECKLIST
2346_6.PDF 2346 INSTALLATION & USE OF EMERGENCY EYEWASH AND SHOWER EQ
2347_2.XLS 2347 ELECTRICAL DATA SHEET FOR MEDIUM VOLTAGE SWITCHGEAR
2348_5.XLS 2348 INSPECTION TEST PLAN FOR HORIZONTAL PUMPS
2349_3.XLS 2349 INSPECTION TEST PLAN FOR VERTICAL PUMPS
2350_7.DOCX 2350 SEAL FLUSH DRAWINGS
2351_1.XLS 2351 ELECTRICAL DATA SHEET FOR NEUTRAL GROUNDING RESISTOR SY
2352_0.XLS 2352 ELECTRICAL DATA SHEET FOR LIGHTNING/SURGE ARRESTERS
2353_1.XLS 2353 ELECTRICAL DATA SHEET FOR BUS DUCT
2354_2.XLS 2354 ELECTRICAL DATA SHEET FOR MEDIUM VOLTAGE MOTOR CONTROL
2357_1.XLS 2357 ELECTRICAL DATA SHEET FOR LOW VOLTAGE MOTOR CONTROL CEN
2358_3.XLS 2358 ELECTRICAL DATA SHEET FOR MEDIUM VOLTAGE ADJUSTABLE SPEE
2359_2.XLS 2359 ELECTRICAL DATA SHEET FOR LOW VOLTAGE ADJUSTABLE SPEED AC
2360_3.XLS 2360 ELECTRICAL DATA SHEET FOR MEDIUM VOLTAGE POWER CABLES
2361_0.XLS 2361 ELECTRICAL DATA SHEET FOR LOW VOLTAGE POWER AND CONTROL
2362_1.XLS 2362 ELECTRICAL DATA SHEET FOR UNINTERRUPTIBLE POWER SUPPLY
2363_1.XLS 2363 ELECTRICAL DATA SHEET FOR BATTERIES & CHARGERS
2364_2.XLS 2364 ELECTRICAL DATA SHEET FOR MOTOR OPERATED VALVE ACTUATOR
2365_2.XLS 2365 ELECTRICAL DATA SHEET FOR PACKAGED SUBSTATIONS
2375_0.DWG 2375 GUARD POST DETAIL
2376_5.XLS 2376 ORIFICE PLATE INSPECTION FORM
2377_1.XLS 2377 AIR COOLED HEAT EXCHANGER DATA SHEET
2378_1.XLS 2378 HF VALVE REPAIR SHOP ASSESSMENT
2379_2.XLS 2379 INJECTION DEVICE DATA SHEET
2380_6.PDF 2380 ASSESSMENT & QUALIFICATION OF HF ALKY SERVICE VALVE REPAI
2381_15.PDF 2381 PSM/RMP BUILDING AND TENT SITING
2385_7.PDF 2385 MINIMUM REQUIREMENTS FOR BYPASSING AN EMERGENCY SHUT
2390_6.PDF 2390 TECHNICAL SERVICES EXCELLENCE (TSE)
2391_3.PDF 2391 TECHNOLOGISTS ROLES ON MAJOR CAPITAL PROJECTS
2394_1.PDF 2394 TAR FORM - EARNED VALUE COST CURVE EXAMPLE
2395_3.XLS 2395 TAR FORM - HIRING PLAN TEMPLATE
2397_1.XLSX 2397 TAR FORM - MONTHLY TAR STATUS REPORT
2398_0.XLS 2398 TAR FORM - RENTAL EQUIPMENT TEMPLATE
2399_8.PDF 2399 HTHA MANAGEMENT PROGRAM GUIDANCE
2401_6.PDF 2401 INDUSTRIAL WIRELESS INSTRUMENTATION
2402_0.PDF 2402 THREADED PIPE BUSHINGS
2403_0.PDF 2403 SMALL-BORE, THREADED PIPING POLICY UPDATE
2404_0.PDF 2404 SCHEDULE 80 THREADED PIPING
2414_0.DWG 2414 BARBED TEE FOR PIGGED LINES
2417_6.PDF 2417 CONTROL SYSTEMS FOR PROCESS RECIPROCATING COMPRESSORS
2420_2.XLS 2420 SHIFT TURNOVER CHECKLIST FOR CONSOLE OPERATOR
2423_0.DWG 2423 STANDARD DETAIL FOR SW & THRD PIPE HORIZONTAL OR VERTICAL
2424_7.PDF 2424 DEEP WELL PUMP CASING INSPECTION
2425_0.DWG 2425 SECURITY DETAIL FOR BOLLARDS DOC. NO. 501B E.2 SECURITY DET
2426_1.XLS 2426 CYLINDER PACKING CASE WORKSHEET
2427_1.XLS 2427 CYLINDER WIPER PACKING CASE WORKSHEET
2428_3.XLS 2428 COMPRESSOR MAINTENANCE FREQUENCY TABLE
2429_8.PDF 2429 LOST OPPORTUNITY EVENTS FAILURE CODING PRACTICES
2430_4.PDF 2430 PROCEDURE FOR CREATING, CLAIMING AND MERGING PROJECTS FO
2431_5.PDF 2431 SMARTPLANT INSTRUMENTATION UTILITIES GUIDE
2432_4.PDF 2432 SMARTPLANT INSTRUMENTATION ADMINISTRATION GUIDE
2433_4.PDF 2433 LPG WATER DRAIN POT DESIGN
2435_1.XLS 2435 CENTRIFUGAL - POST-FACTORY ACCEPTANCE TEST
2436_1.DOC 2436 CENTRIFUGAL - COMPRESSOR NAME DCS TO COMPRESSOR CONTRO
2437_1.DOC 2437 CENTRIFUGAL - COMPRESSOR NAME CONTROL VALVE TESTING
2438_1.DOC 2438 CENTRIFUGAL - COMPRESSOR NAME LUBE/WORKING OIL SYSTEM
2439_1.DOC 2439 CENTRIFUGAL - COMPRESSOR NAME SHUTDOWNS
2440_1.DOC 2440 CENTRIFUGAL - INSTALLATION & COMMISSIONING CHECK-OUT
2441_1.DOC 2441 CENTRIFUGAL - EIV DIAGNOSTIC ALARMS
2442_2.PDF 2442 CENTRIFUGAL - CAUSE AND EFFECT CHART
2443_0.XLS 2443 CONTRACTOR FIELD VERIFICAITON AUDIT CHECKLIST
2451_1.DOC 2451 PROCESS SAFETY ADVSIORY BLANK TEMPLATE
2452_24.PDF 2452 INCIDENT INVESTIGATION
2472_4.PDF 2472 EIV APPLICATION STANDARDS FOR AROMATIC EXTRACTION UNITS
2473_7.PDF 2473 EIV APPLICATION STANDARDS FOR DELAYED COKER UNITS (DCU)
2474_5.PDF 2474 EIV APPLICATION STANDARDS FOR CRUDE-VACUUM UNITS
2475_7.PDF 2475 EIV APPLICATION STANDARDS FOR DIESEL HYDROPROCESSING UNI
2476_6.PDF 2476 EIV APPLICATION STANDARDS FOR FLUID CATALYTIC CRACKING (FCC
2477_6.PDF 2477 EIV APPLICATION STANDARDS FOR GAS OIL HYDROPROCESSING UN
2478_5.PDF 2478 EIV APPLICATION STANDARDS FOR HF ALKYLATION UNITS
2479_4.PDF 2479 EIV APPLICATION STANDARDS FOR ISOMERIZATION UNITS
2480_5.PDF 2480 EIV APPLICATION STANDARDS FOR NAPHTHA HYDROPROCESSING U
2481_6.PDF 2481 EIV APPLICATION STANDARDS FOR REFORMING UNITS
2482_6.PDF 2482 EIV APPLICATION STANDARDS FOR ROSE UNITS
2483_4.PDF 2483 EIV APPLICATION STANDARDS FOR SOLVENT DEASPHALTING (SDA)
2484_6.PDF 2484 EIV APPLICATION STANDARDS FOR AMINE SRU
2485_3.PDF 2485 HOT TAP NOZZLE 2 INCH AND SMALLER
2486_1.PDF 2486 HOT TAP NOZZLE 2-1/2 INCH AND LARGER
2487_26.PDF 2487 PROCESS DESIGN GUIDELINES
2488_0.DWG 2488 TEMPLATE FOR VESSEL/EQUIPMENT NAMEPLATE, REPAIR, ALTERAT
2502_0.XLS 2502 TRAINING PACKAGES REVIEW FORM
2503_8.PDF 2503 REFINING HESS TRAINING STANDARD
2504_0.DWG 2504 WELDED BASE SUPPORT VERTICAL ON PIPE NO INSTALLATION NPS
2505_8.PDF 2505 HF ALKY UNIT API RP 751 REQUIREMENTS
2506_10.PDF 2506 HAND INJURY PREVENTION AND GENERAL DUTY GLOVE STANDARD
2507_1.XLS 2507 ENHANCED INSPECTION SPREADSHEET
2508_1.DOC 2508 INSPECTION REPORT FORM
2512_7.XLSX 2512 CAPITAL BUDGET EXHIBITS
2513_13.PDF 2513 REFINING BUDGET DEVELOPMENT AND PRESENTATION GUIDELINE
2514_2.XLS 2514 PROCEDURE GENERAL PRINCIPLES
2515_2.XLS 2515 SHUTDOWN PROCEDURE CHECKLIST
2516_4.XLS 2516 STARTUP PROCEDURE CHECKLIST
2517_2.XLS 2517 EMERGENCY PROCEDURE CHECKLIST
2518_5.DOC 2518 OPERATING PROCEDURES - TEMPLATE 03 - OPTIONAL STEP-BY-ST
2519_8.PDF 2519 HYDROPROCESSING REACTOR EFFLUENT AND STRIPPER OVERHEAD
2520_5.PDF 2520 PRESSURE VESSEL MAWT EXCEEDANCE OF MAXIMUM TEMPERATUR
2521_10.PDF 2521 FATIGUE RISK MANAGEMENT
2522_5.PDF 2522 EIV APPLICATION STANDARD FOR SATURATE (SAT) GAS UNIT
2523_0.DWG 2523 SUPPORT FOR INSTRUMENT ATTACHMENT - DETAIL SHEET
2524_0.DWG 2524 SPOOL FOR INSTRUMENT ATTACHMENT - DETAIL SHEET
2525_2.PDF 2525 NDE MANUAL - LEVEL III EMPLOYER ORGANIZATION LETTER
2526_2.PDF 2526 DESIGN OF DIKES FOR STORAGE TANKS AND STORAGE VESSELS
2527_7.PDF 2527 INSTRUCTIONS FOR MANAGING THE REFINING WORST ACTORS LIS
2528_7.PDF 2528 SUPPORT OF ON-LINE ANALYZERS
2530_0.DOC 2530 QUARTERLY REPORT TEMPLATE
2531_8.PDF 2531 REMOVABLE INSULATION COVERS
2532_0.XLS 2532 REFINING FUEL MEASUREMENT AND REPORTING CERTIFICATION
2533_1.PDF 2533 REFINING FUEL MEASUREMENT AND REPORTING GUIDELINES
2537_1.DOC 2537 (WITHDRAWN) OPERATOR FIELD/CONSOLE TRAINING EXCEPTION
2540_2.PDF 2540 CIRCUIT BREAKER - MEDIUM VOLTAGE OFFLINE TESTING
2541_2.PDF 2541 CIRCUIT BREAKER - LOW VOLTAGE OFFLINE TESTING
2542_2.PDF 2542 CIRCUIT BREAKER - MOLDED CASE OFFLINE TESTING
2543_2.PDF 2543 PROTECTIVE RELAYS (ELECTRONIC) OFFLINE TESTING
2544_6.PDF 2544 CIRCUIT BREAKERS - MEDIUM VOLTAGE (AIR/VACUUM)
2545_5.PDF 2545 POWER CIRCUIT BREAKERS - LOW VOLTAGE
2546_6.PDF 2546 CIRCUIT BREAKERS - MOLDED CASE
2547_5.PDF 2547 PROTECTIVE RELAYS (ELECTRONIC)
2548_2.PDF 2548 10MVA AND LARGER TRANSFORMER OFFLINE TESTING
2549_2.PDF 2549 GREATER THAN 200 KVA (LESS THAN 10 MVA) TRANSFORMER OFFL
2550_2.PDF 2550 SWITCHGEAR (MAIN SUBSTATION) OFFLINE TESTING
2551_2.PDF 2551 SWITCHGEAR (UNIT SUBSTATION) OFFLINE TESTING
2552_6.PDF 2552 MAIN SUBSTATION TRANSFORMERS (OIL-FILLED) GREATER THAN 1
2553_6.PDF 2553 UNIT SUBSTATION TRANSFORMERS (OIL-FILLED) MEDIUM VOLTAGE
2554_6.PDF 2554 SWITCHGEAR (MAIN SUBSTATION)
2555_7.PDF 2555 SWITCHGEAR (UNIT SUBSTATION) AND MEDIUM VOLTAGE MCC
2556_14.PDF 2556 OPERATING LIMITS
2557_0.XLS 2557 CAUSE AND EFFECT TEMPLATE
2558_0.DOC 2558 COMPRESSOR UNLOADER TESTING
2559_0.DOC 2559 INSTALLATION & COMMISSIONING CHECK-OUT
2560_0.DOC 2560 COMPRESSOR JACKET WATER SYSTEM
2561_0.DOC 2561 COMPRESSOR SHUTDOWNS
2562_0.DOC 2562 COMPRESSOR LUBE OIL SYSTEM
2563_0.DOC 2563 EIV DIAGNOSTIC ALARMS
2564_0.DOC 2564 COMPRESSOR DCS TO COMPRESSOR CONTROL SYSTEM INTERFACE
2565_0.DWG 2565 TEMPLATE FOR HEAT EXCHANGER NAMEPLATE, REPAIR, ALTERATIO
2739_5.PDF 2739 ACCEPTANCE TESTING FOR ELECTRICAL EQUIPMENT
2886_0.PDF 2886 CATALYST LINE ADDENDUM
2890_0.XLS 2890 INSPECTION TEST PLAN - EXTERNAL COATING
2892_9.XLS 2892 PIPE WELD DATA SHEET - CARBON STEEL - GENERAL REFINERY SER
2893_6.XLS 2893 PIPE WELD DATA SHEET - CARBON STEEL - GENERAL REFINERY SERV
2894_6.XLS 2894 PIPE WELD DATA SHEET - CARBON STEEL - HYDROCARBON W/ HYD
2895_7.XLS 2895 PIPE WELD DATA SHEET - CARBON STEEL - HYDROCARBON W/ HYDR
2896_7.XLS 2896 PIPE WELD DATA SHEET - CARBON STEEL - HYDROCARBONS W/ HYD
2897_7.XLS 2897 PIPE WELD DATA SHEET - CARBON STEEL - HYDROCARBON W/ OR
2898_6.XLS 2898 PIPE WELD DATA SHEET - CARBON STEEL - AMINE, CAUSTIC
2899_6.XLS 2899 PIPE WELD DATA SHEET - CARBON STEEL - COKER CLOSED BLOW
2900_13.XLS 2900 PIPE WELD DATA SHEET - CARBON STEEL AND STAINLESS STEEL - C
2901_3.XLS 2901 PIPE WELD DATA SHEET - 1-¼ CHROME
2902_3.XLS 2902 PIPE WELD DATA SHEET - 2-¼ CHROME
2903_3.XLS 2903 PIPE WELD DATA SHEET - 5 CHROME
2904_3.XLS 2904 PIPE WELD DATA SHEET - 9 CHROME
2905_2.XLS 2905 PIPE WELD DATA SHEET - 304/304L SS
2906_2.XLS 2906 PIPE WELD DATA SHEET - 304H SS
2907_3.XLS 2907 PIPE WELD DATA SHEET - 316/316L SS
2908_2.XLS 2908 PIPE WELD DATA SHEET - 316H SS
2909_2.XLS 2909 PIPE WELD DATA SHEET - 317/317L SS
2910_4.XLS 2910 PIPE WELD DATA SHEET - 321 SS
2911_3.XLS 2911 PIPE WELD DATA SHEET - 347 SS (CLASS 150 THROUGH 1500)
2912_2.XLS 2912 PIPE WELD DATA SHEET - 347/347H SS (CLASS 2500)
2913_3.XLS 2913 PIPE WELD DATA SHEET - DUPLEX 2205 SS
2914_4.XLS 2914 PIPE WELD DATA SHEET - ALLOY 400 (MONEL) - NOT IN HF SERVICE
2915_2.XLS 2915 PIPE WELD DATA SHEET - ALLOY 600 (INCONEL)
2916_3.XLS 2916 PIPE WELD DATA SHEET - ALLOY 800/800H/800HT/825 (INCOLOY)
2917_2.XLS 2917 PIPE WELD DATA SHEET - ALLOY 20
2918_2.XLS 2918 PIPE WELD DATA SHEET - ALLOY 400 (MONEL) - HF ACID (UOP AND
2919_5.XLS 2919 PIPE WELD DATA SHEET - CARBON STEEL - HF ACID, CAUSTIC IN HF
2920_4.XLS 2920 PIPE WELD DATA SHEET - CARBON STEEL - HF ACID (COP DESIGN)
2923_9.PDF 2923 PUMP SEAL SELECTION AND PUMP SEAL AUXILIARIES
2925_4.PDF 2925 EQUIPMENT FAILURE AND MAINTENANCE CODING
2926_1.PDF 2926 EXTERNAL FLOATING ROOF SUMP FOR 4-INCH DRAIN
2927_1.PDF 2927 EXTERNAL FLOATING ROOF SUMP FOR 6-INCH DRAIN
2928_2.PDF 2928 ANTI-ROTATION POLE
2929_1.PDF 2929 PIPE SUPPORT "DETAIL J"
2930_1.PDF 2930 CIRCULATION VENT/OVERFLOW SLOT
2931_1.PDF 2931 TANK 4-INCH SUMP DETAIL
2932_1.PDF 2932 TANK 6-INCH SUMP DETAIL
2933_1.PDF 2933 GUIDEPOLE FOR FLOATING ROOF
2934_1.PDF 2934 GUIDEPOLE SEAL DETAIL
2935_1.PDF 2935 FILL DISTRIBUTOR
2936_1.PDF 2936 SUCTION
2937_1.PDF 2937 TANK AUTO-GAUGE WELL COVER OPENING DETAIL
2938_1.PDF 2938 AUTOMATIC BLEEDER VENT
2939_1.PDF 2939 GAUGE & SAMPLE HATCH STANDARD
2940_1.PDF 2940 SAMPLE VALVE LOCATION
2941_1.PDF 2941 SWINGLINE CABLE FITTING
2942_1.PDF 2942 FLOATING ROOF SEAL (MECH. SPRING STYLE)
2944_7.PDF 2944 CRANE OPERATOR TRAINING
2945_1.XLS 2945 INSPECTION TEST PLAN - FIREPROOFING
2946_0.DWG 2946 STANDARD FLOOR PLATE AND GRATING DETAIL
2948_4.PDF 2948 PROCESS UNIT SIGN-IN AND SIGN-OUT
2949_2.XLS 2949 PIPE WELD DATA SHEET - ALLOY C-276
2950_5.PDF 2950 CAR SEAL MANAGEMENT SYSTEM
2952_8.PDF 2952 RATE LIMIT INCREASE GUIDELINES
2953_5.PDF 2953 DEAD LEG MANAGEMENT SYSTEM
2954_5.PDF 2954 REFINING PUBLIC PRESENTATIONS OR PUBLICATIONS POLICY
2955_1.DOC 2955 (WITHDRAWN) MPC CORE SPECIFICATIONS IMPLEMENTATION AT G
2956_2.PDF 2956 RECIPROCATING COMPRESSOR
2957_2.PDF 2957 COMPRESSOR WATER JACKET
2958_3.PDF 2958 COMPRESSOR MOTOR LOCAL PANEL AND UTILITIES
2959_3.PDF 2959 COMPRESSOR LUBE OIL
2960_3.PDF 2960 COMPRESSOR CYLINDER OIL
2962_4.PDF 2962 MEDIUM VOLTAGE SWITCH (ENCLOSED)
2963_4.PDF 2963 MOTOR STARTERS - MEDIUM VOLTAGE (AIR / VACUUM)
2964_5.PDF 2964 LOW VOLTAGE MOTOR CONTROL CENTERS
2965_4.PDF 2965 LOW VOLTAGE COMBINATION STARTERS
2966_5.PDF 2966 LOW VOLTAGE SWITCHRACKS (BUS BOX AND STRUCTURE)
2967_17.PDF 2967 GENERAL PIPING DESIGN
2968_5.PDF 2968 PIPE SUPPORT ELEMENTS
2969_0.DWG 2969 VESSEL NOZZLE INSPECTION TEMPLATE
2970_2.PDF 2970 PROJECT ESTIMATE REVIEW AND VALIDATION GUIDELINES
2971_17.XLS 2971 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN;
2972_4.DOC 2972 MANAGING MINOR HAZARDOUS LEAKS RISK ASSESSMENT
2973_5.XLS 2973 PROCEDURALIZED MOC FOR DESIGN, INSTALLATION AND LIFE M
2974_0.PDF 2974 EXAMPLE DESIGN PACKAGE
2975_10.PDF 2975 OPERATIONS TURNAROUND PLANNING
2976_1.XLS 2976 HEATER/BURNER CHARACTERISTICS AND PRELIMINARY OPERABILI
2977_1.XLS 2977 FIELD TEST RESULTS LOG
2978_3.PDF 2978 GUIDELINES FOR ESTABLISHING FLUE GAS O2 TARGETS AND FOR
2979_7.PDF 2979 MANAGEMENT OF MINOR LEAKS AND CLAMP/WRAP LIFE CYCLE
2980_15.XLS 2980 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN;
2981_1.DOC 2981 EMPLOYEE PARTICIPATION AUDIT FORM
2982_2.DOC 2982 PROCESS SAFETY INFORMATION AUDIT FORM
2983_1.DOC 2983 PROCESS HAZARD ANALYSIS AUDIT FORM
2984_4.DOC 2984 OPERATING PROCEDURES AUDIT FORM
2985_3.DOC 2985 TRAINING AUDIT FORM
2986_1.DOC 2986 CONTRACTORS AUDIT FORM
2987_2.DOC 2987 MANAGEMENT OF CHANGE AND PRE-STARTUP SAFETY REVIEW AU
2988_1.DOC 2988 MECHANICAL INTEGRITY AUDIT FORM
2989_1.DOC 2989 SAFE WORK PRACTICES AUDIT FORM
2990_1.DOC 2990 INCIDENT INVESTIGATION AUDIT FORM
2991_2.DOC 2991 EMERGENCY RESPONSE AND PLANNING AUDIT FORM
2992_1.DOC 2992 COMPLIANCE AUDITS AUDIT FORM
2993_1.DOC 2993 TRADE SECRETS AUDIT FORM
2994_2.DOC 2994 BUILDING AND TENT SITING AUDIT FORM
2995_1.DOC 2995 EPA RISK MANAGEMENT PROGRAM AUDIT FORM
2996_3.XLS 2996 MANAGEMENT OF CHANGE (MOC) METRIC SCORE SHEET
2998_10.PDF 2998 LIQUID OVERFILL APPLICATION STANDARD
2999_9.PDF 2999 GAS/VAPOR FLOW TO TANK APPLICATION STANDARD
3000_10.PDF 3000 REVERSE FLOW TO VESSEL APPLICATION STANDARD
3001_9.PDF 3001 GAS/VAPOR BLOW THROUGH TO VESSEL APPLICATION STANDARD
3002_12.PDF 3002 PUMP SEALS APPLICATION STANDARD
3003_10.PDF 3003 MINIMUM PROTECTIVE SYSTEMS FOR COMPRESSORS APPLICATIO
3004_4.PDF 3004 DELAYED COKER UNIT APPLICATION STANDARD
3005_2.DOCX 3005 (WITHDRAWN - DRAFT) HYDROCRACKING UNIT APPLICATION STA
3006_9.XLS 3006 HIGH TEMPERATURE - SEVERE WET H2S - HYDROCARBONS W/ OR
3007_7.XLS 3007 LPG (OUTSIDE BATTERY LIMITS)
3008_8.XLS 3008 LPG (OUTSIDE BATTERY LIMITS)
3009_6.XLS 3009 COKER CLOSED BLOWDOWN WITH THERMAL CYCLING (PWHT REQU
3010_9.XLS 3010 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN; C
3011_16.XLS 3011 HIGH TEMPERATURE - SUPERHEATED STEAM; HYDROCARBONS W/
3012_18.XLS 3012 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN;
3013_15.XLS 3013 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN
3014_15.XLS 3014 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN;
3015_17.XLS 3015 SEVERE WET H2S - HYDROCARBONS W/ OR W/O HYDROGEN; SOUR
3016_10.XLS 3016 SEVERE WET H2S - HYDROCARBONS W/ OR W/O HYDROGEN; SOUR
3017_10.XLS 3017 SEVERE WET H2S - HYDROCARBONS W/ OR W/O HYDROGEN; SOUR
3018_11.XLS 3018 SEVERE WET H2S - HYDROCARBONS W/ OR W/O HYDROGEN; SOU
3019_9.XLS 3019 SEVERE WET H2S - HYDROCARBONS W/ OR W/O HYDROGEN; SOUR
3020_10.XLS 3020 SEVERE WET H2S - HYDROCARBONS W/ OR W/O HYDROGEN (PWH
3021_8.XLS 3021 SEVERE WET H2S - HYDROCARBONS W/ OR W/O HYDROGEN; SOUR
3022_10.XLS 3022 SEVERE WET H2S - HYDROCARBONS W/ OR W/O HYDROGEN; SOUR
3023_8.XLS 3023 SIMPLE WET H2S - HYDROCARBONS W/ OR W/OUT HYDROGEN; S
3024_8.XLS 3024 SEVERE WET H2S - HYDROCARBONS W/ OR W/O HYDROGEN; SOUR
3025_10.XLS 3025 SEVERE WET H2S - HYDROCARBONS W/ OR W/O HYDROGEN; SOUR
3026_10.XLS 3026 SEVERE WET H2S - HYDROCARBONS W/ OR W/O HYDROGEN; SOUR
3027_7.XLS 3027 S32205 DUPLEX STAINLESS STEEL
3028_12.XLS 3028 S32205 DUPLEX 2205 STAINLESS STEEL
3029_9.XLS 3029 S32205 DUPLEX STAINLESS STEEL
3030_11.XLS 3030 HYDROCARBONS W/ OR W/O HYDROGEN
3031_14.XLS 3031 SIMPLE WET H2S - HYDROCARBONS W/ HYDROGEN ABOVE 50 PSIA
3032_7.XLS 3032 SIMPLE WET H2S - HYDROCARBONS W/ HYDROGEN ABOVE 50 PSIA
3033_9.XLS 3033 SIMPLE WET H2S - HYDROCARBONS W/ HYDROGEN ABOVE 50 PSIA
3034_9.XLS 3034 SIMPLE WET H2S - HYDROCARBONS W/ HYDROGEN ABOVE 50 PSIA
3035_12.XLS 3035 SIMPLE WET H2S - HYDROCARBONS W/ HYDROGEN BELOW 50 PSIA
3037_10.XLS 3037 HYDROCARBONS W/ HYDROGEN ABOVE 50 PSIA PP; HYDROGEN (
3038_10.XLS 3038 HYDROCARBONS W/ HYDROGEN ABOVE 50 PSIA PP; HYDROGEN (
3039_11.XLS 3039 HYDROCARBONS W/ OR W/O HYDROGEN; VACUUM TRANSFER LIN
3040_10.XLS 3040 HYDROCARBONS W/ OR W/O HYDROGEN
3042_6.XLS 3042 SIMPLE WET H2S - HYDROCARBONS W/ HYDROGEN BELOW 50 PSIA
3043_6.XLS 3043 SIMPLE WET H2S - HYDROCARBONS W/ HYDROGEN BELOW 50 PSIA
3044_6.XLS 3044 SIMPLE WET H2S - HYDROCARBONS W/ HYDROGEN BELOW 50 PSIA
3045_8.XLS 3045 SIMPLE WET H2S - HYDROCARBONS W/ HYDROGEN BELOW 50 PSIA
3046_8.XLS 3046 SIMPLE WET H2S - HYDROCARBONS W/ HYDROGEN BELOW 50 PSIA
3047_15.XLS 3047 SIMPLE WET H2S - HYDROCARBONS W/ HYDROGEN BELOW 50 PSIA
3048_9.XLS 3048 CAUSTIC (FOR OPERATION IN AREA "A" OF THE NACE CAUSTIC SO
3049_10.XLS 3049 CAUSTIC (FOR OPERATION IN AREA "A" OF THE NACE CAUSTIC SER
3050_9.XLS 3050 AMINE (W/ OR W/O HYDROGEN) (PWHT REQUIRED)
3051_12.XLS 3051 AMINE (W/ OR W/O HYDROGEN)
3052_9.XLS 3052 AMINE (W/ OR W/O HYDROGEN)
3053_7.XLS 3053 AMINE (W/ OR W/O HYDROGEN)
3054_9.XLS 3054 AMINE (W/ OR W/O HYDROGEN) (PWHT REQUIRED)
3055_8.XLS 3055 AMINE (W/ OR W/O HYDROGEN) (PHWT REQUIRED)
3056_10.XLS 3056 AMINE (W/ OR W/O HYDROGEN) (PWHT REQUIRED)
3057_7.XLS 3057 AMINE (W/ OR W/O HYDROGEN) (PWHT REQUIRED)
3058_10.XLS 3058 AMINE (W/ OR W/O HYDROGEN) (PWHT REQUIRED)
3059_10.XLS 3059 HIGH TEMPERATURE - PROCESS HOT AIR W/ HYDROGEN ABOVE 50 P
3060_12.XLS 3060 SULFURIC ACID (93 - 98% SOLUTION) LESS THAN 125°F OPERATING
3062_5.XLS 3062 LUBE OIL / SEAL OIL
3063_11.XLS 3063 HYDROCARBONS W/ OR W/O HYDROGEN; STEAM/CONDENSATE D
3064_10.XLS 3064 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN; PR
3065_9.XLS 3065 HYDROCARBONS W/ OR W/O HYDROGEN; DEMINERALIZED WATER;
3067_12.XLS 3067 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN; H
3068_10.XLS 3068 SIMPLE WET H2S - HYDROCARBONS W/ HYDROGEN BELOW 50 PSIA
3069_7.XLS 3069 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN; H
3070_11.XLS 3070 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN; H
3071_10.XLS 3071 SEVERE WET H2S - HYDROCARBONS W/ OR W/O HYDROGEN; SOUR
3072_11.XLS 3072 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN; H
3073_7.XLS 3073 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN (P
3074_6.XLS 3074 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN (P
3075_11.XLS 3075 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN; H
3077_9.XLS 3077 SULFURIC ACID (LESS THAN 93% SOLUTION OR 66° BAUME)
3078_16.XLS 3078 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN
3079_1.XLS 3079 VAPOR PHASE CHLORIDE GUARD ABSORBENT PROPOSAL REQUEST
3080_0.XLS 3080 MPC CHLORIDE GUARD BED SURVEY
3081_3.PDF 3081 CHLORIDE GUARD BEDS
3082_8.XLS 3082 S32205 DUPLEX 2205 STAINLESS STEEL
3083_9.XLS 3083 S32205 DUPLEX 2205 STAINLESS STEEL
3084_14.XLS 3084 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN
3085_10.XLS 3085 HYDROCARBONS W/ HYDROGEN BELOW 50 PSIA PP; STEAM, CONDE
3086_11.XLS 3086 HYDROCARBONS AND/OR HYDROGEN; CHEMICAL INJECTION
3087_10.XLS 3087 HYDROCARBONS AND/OR HYDROGEN
3088_8.XLS 3088 QUENCH WATER
3089_11.XLS 3089 SULFURIC ACID (93 - 98% SOLUTION) LESS THAN 125°F OPERATING
3090_0.DWG 3090 120V INJECTION PUMP MOTOR CONNECTION
3091_3.XLS 3091 SANITARY SEWER SYSTEM (UNDERGROUND)
3092_5.XLS 3092 COOLING WATER, PLANT WATER, SOFTENED WATER (ABOVEGROU
3093_10.XLS 3093 STEAM, CONDENSATE, BOILER FEEDWATER
3095_4.XLS 3095 POTABLE WATER (UNDERGROUND) [CPVC]
3096_9.XLS 3096 HIGH TEMPERATURE - STEAM, CONDENSATE, BOILER FEEDWATER
3098_3.XLS 3098 ACID TRENCH PIPING (UNDERGROUND) [DUCTILE IRON PVDF LINED
3100_7.XLS 3100 FIREWATER (UNDERGROUND) [DUCTILE IRON]
3101_3.XLS 3101 SEWER WATER (UNDERGROUND) [PVC]
3102_7.XLS 3102 FIREWATER (UNDERGROUND) [FM APPROVED HDPE]
3103_4.XLS 3103 CATALYST LIFT LINE W/ HYDROGEN ABOVE 50 PSIA PP (PWHT REQUI
3104_5.XLS 3104 HIGH TEMPERATURE - CATALYST LIFT & HYDROCARBONS W/ HYDROG
3105_11.XLS 3105 HIGH TEMPERATURE - SUPERHEATED STEAM
3106_6.XLS 3106 WATER; 2 PPM SODIUM HYPOCHLORITE (SALT OR CHLORIDE CONTAM
3107_4.XLS 3107 CATALYST LIFT LINE W/ HYDROGEN ABOVE 50 PSIA PP (PWHT REQUI
3108_3.XLS 3108 CATALYST WITHDRAWAL AND HYDROCARBONS W/ HYDROGEN BELOW 5
3109_4.XLS 3109 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN, CAT
3110_5.XLS 3110 CATALYST AND HYDROCARBONS W/ HYDROGEN BELOW 50 PSIA PP (
3111_3.XLS 3111 CATALYST LIFT LINE W/ HYDROGEN ABOVE 50 PSIA PP (PWHT REQUI
3112_9.XLS 3112 BLEACH (SODIUM HYPOCHLORITE ALL STRENGTHS), PHOSPHORIC & S
3113_3.XLS 3113 CATALYST ADDITION AND HYDROCARBONS W/ HYDROGEN BELOW 50
3114_0.DWG 3114 WELDED BASE SUPPORT VERTICAL ON PIPE NPS 2" THRU 24"
3115_2.DOC 3115 OPERATING PROCEDURES - TEMPLATE 09 - PROCEDURE CERTIFICA
3116_7.XLS 3116 RAW / COOLING WATER (UNDERGROUND) [HDPE]
3117_11.PDF 3117 TEMPERATURE INSTRUMENTS
3118_9.PDF 3118 LEVEL INSTRUMENTS
3119_4.PDF 3119 BUSWAY AND BUS DUCT
3120_4.PDF 3120 MOTORS - 13.8 KV
3121_4.PDF 3121 MOTORS 480VAC / 2300VAC / 4160VAC / 4800VAC
3122_4.PDF 3122 INSULATED POWER CABLES (5KV AND ABOVE)
3123_4.PDF 3123 INSULATED POWER CABLES LESS THAN 5KV
3124_4.PDF 3124 BATTERY SYSTEMS (FLOODED CELL, VRLA, AND NI-CD)
3125_3.PDF 3125 PROCESS UNIT ELECTRICAL EQUIPMENT INSPECTIONS
3127_21.PDF 3127 INSTRUMENT PIPING DESIGN AND MATERIAL
3128_4.PDF 3128 INSTRUMENT WIRE AND CABLE
3129_4.PDF 3129 OIL CIRCUIT BREAKERS
3130_4.PDF 3130 GAS CIRCUIT BREAKERS
3131_4.PDF 3131 HIGH VOLTAGE SWITCHES (GOABS AND MOABS)
3132_4.PDF 3132 SURGE ARRESTERS (STATION AND INTERMEDIATE CLASS)
3133_4.PDF 3133 POWER POLES AND HARDWARE
3134_5.PDF 3134 TRANSFER SWITCHES - AUTOMATIC AND MANUAL
3135_3.PDF 3135 UN-INSULATED OVERHEAD POWER LINES
3136_4.PDF 3136 CATHODIC PROTECTION (RECTIFIERS)
3137_1.XLS 3137 PIPE FLANGE TORQUE VALUES
3138_2.PDF 3138 EQUIPMENT TROUBLESHOOTING GUIDES
3139_12.XLS 3139 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN, C
3141_3.XLS 3141 STEAM TRACING [COPPER TUBING]
3142_7.XLS 3142 UTILITY WATER, FIRE/SPRINKLER WATER [GALV CARBON STEEL]
3143_3.PDF 3143 GUIDELINES FOR CONDUCTING A FITNESS-FOR-SERVICE ASSESSME
3144_4.PDF 3144 GAGE GLASSES AND MAGNETIC LIQUID LEVEL INDICATORS
3145_8.PDF 3145 LOCAL CONTROL PANELS
3146_6.PDF 3146 BOLTED JOINTS IN PIPING AND FIXED EQUIPMENT
3147_0.DOC 3147 LIVE FLARE HEADER INVASIVE WORK APPROVAL & HAZARD MITIG
3148_0.PDF 3148 LIVE FLARE HEADER INVASIVE WORK
3149_0.XLS 3149 ELEVATED LEL HOT WORK APPROVAL FORM
3150_2.PDF 3150 HOT WORK
3151_9.PDF 3151 OPERATIONS EXCELLENCE
3152_4.XLSX 3152 PIPING CROSS REFERENCE
3153_8.XLS 3153 CUMENE W/ PHOSPHORIC ACID
3154_1.XLSX 3154 CRITICAL THERMOWELL LIST
3155_7.PDF 3155 CRITICAL THERMOWELL INSPECTION
3156_0.DOC 3156 PSM ELEMENT REVIEW DOCUMENTATION FORM
3157_10.PDF 3157 LIQUID RING COMPRESSORS AND VACUUM PUMPS
3158_0.PDF 3158 BUSWAY AND BUS DUCT OFFLINE TESTING FORM [SEG/NON-SEG]
3159_0.PDF 3159 BUSWAY AND BUS DUCT OFFLINE TESTING FORM [ISO]
3160_0.PDF 3160 BUSWAY AND BUS DUCT OFFLINE TESTING FORM [SANDWICH]
3161_0.PDF 3161 OIL CIRCUIT BREAKER OFFLINE TESTING FORM
3162_0.PDF 3162 GAS CIRCUIT BREAKER OFFLINE TESTING FORM
3163_0.PDF 3163 HIGH VOLTAGE SWITCH (GOAB / MOAB) OFFLINE TESTING FORM
3164_0.PDF 3164 MEDIUM VOLTAGE SWITCH (ENCLOSED) OFFLINE TESTING FORM
3165_0.PDF 3165 MOTOR STARTER (MEDIUM VOLTAGE) OFFLINE TESTING FORM
3166_0.PDF 3166 LOW VOLTAGE MOTOR CONTROL CENTER OFFLINE TESTING FORM
3167_0.PDF 3167 LOW VOLTAGE SWITCHRACK OFFLINE TESTING FORM
3168_0.PDF 3168 MOTORS - 13.8KV OFFLINE TESTING FORM
3169_0.PDF 3169 MOTORS - 480V / 2300V / 4160V / 4800V OFFLINE TESTING FORM
3170_0.PDF 3170 INSULATED SHIELDED POWER CABLES (5KV AND ABOVE) OFFLINE
3171_0.PDF 3171 INSULATED POWER CABLE (LESS THAN 5KV) OFFLINE TESTING FOR
3172_0.PDF 3172 LOW VOLTAGE COMBINATION STARTER OFFLINE TESTING FORM 1
3173_0.PDF 3173 LOW VOLTAGE COMBINATION STARTER OFFLINE TESTING FORM 2
3174_3.PDF 3174 VARIABLE FREQUENCY DRIVES (MEDIUM AND LOW VOLTAGE)
3175_4.PDF 3175 LOCKOUT RELAYS (ANSI DEVICE #86)
3176_3.PDF 3176 UPS SYSTEMS (CRITICAL)
3177_3.PDF 3177 SUBSTATION AND CONTROL ROOM GROUNDING SYSTEMS
3178_3.PDF 3178 GENERAL PURPOSE ROTARY PUMPS
3179_8.XLS 3179 HYDROCARBONS W/ OR W/O HYDROGEN AND CONTAINS CHLORIDES;
3180_5.XLS 3180 CAUSTIC; OXYGEN; HF ACID BY EXCEPTION ONLY
3181_7.XLS 3181 HYDROCARBONS W/ OR W/O HYDROGEN; LOW TEMPERATURE HYDROC
3182_3.XLSX 3182 PIPING LINE CLASS MATRIX
3185_3.PDF 3185 SMARTPLANT INSTRUMENTATION (SPI)
3186_11.PDF 3186 WELDING REQUIREMENTS OF FIXED EQUIPMENT
3187_2.PDF 3187 SUCTION, DISCHARGE, AND INTERSTAGE PIPING FOR RECIPROCAT
3188_5.PDF 3188 TANK MIXERS
3189_3.PDF 3189 METERING PUMPS
3190_2.PDF 3190 LIQUID INJECTION AND DRAIN PIPING FOR CENTRIFUGAL GAS CO
3191_2.PDF 3191 STEAM TURBINE PIPING
3192_5.PDF 3192 GENERAL SPECIFICATION FOR INSTRUMENT PIPING FIELD PRESSUR
3193_3.PDF 3193 SOLENOID VALVES
3194_4.PDF 3194 SELF-OPERATED PRESSURE REGULATING VALVES
3195_4.PDF 3195 CONTROL SYSTEM FACTORY ACCEPTANCE TESTING
3196_3.PDF 3196 INSTRUMENTATION FIELD CHECKOUT AND CALIBRATION
3197_0.DOC 3197 DAILY REPORT FORM 1 - SINGLE SHAFT RECORD REPORT
3198_0.DOC 3198 DAILY REPORT FORM 2
3199_3.PDF 3199 PILING INSTALLATION AND TESTING
3200_2.XLS 3200 ELECTRICAL SWITCHING PROCEDURE FORM
3201_3.XLS 3201 TEMPORARY POWER APPROVAL CHECKLIST
3202_3.XLS 3202 ENERGIZED ELECTRICAL WORK PERMIT
3203_7.PDF 3203 ELECTRICAL SAFE WORK PRACTICES
3204_5.PDF 3204 BYPASSING CONTROL VALVES AND EQUIPMENT
3205_3.PDF 3205 FUEL GAS AND UTILITY PIPING FOR FURNACES AND BOILERS
3207_2.PDF 3207 WASHING SYSTEMS FOR STEAM TURBINES
3208_2.PDF 3208 RULES AND PRINCIPLES OF RISK-BASED INSPECTION
3209_1.XLSX 3209 ESTIMATED FINANCIAL IMPACT DUE TO TANK SETTLEMENT TABLE
3210_2.PDF 3210 TANK FOUNDATION DECISION TREE AND TUTORIAL
3211_4.PDF 3211 ANNUNCIATORS, ALARM SWITCHES AND ELECTRICAL DEVICES
3212_1.PDF 3212 THERMOCOUPLE EXTENSION CABLE
3213_3.DOCX 3213 MPC PUMP REPAIR FORM
3214_1.DOCX 3214 MPC VERTICAL TURBINE PUMP REPAIR FORM
3215_2.DOCX 3215 MPC BETWEEN BEARING PUMP REPAIR FORM
3216_1.PDF 3216 CENTRIFUGAL PUMP REPAIR
3217_0.XLS 3217 RELIEF DEVICE ISOLATION APPROVAL FORM
3218_2.PDF 3218 RELIEF DEVICE ISOLATION
3219_2.PDF 3219 WELDED ANGLE GUSSET SUPPORTS (TYPE 1)
3220_2.PDF 3220 TWO GUSSET SUPPORTS, TWO DIRECTIONS ON 90 DEGREE PLANES
3221_3.PDF 3221 WELDED ANGLE GUSSET SUPPORTS (TYPE 2)
3222_3.PDF 3222 BOLTED STRAIGHT GUSSET SUPPORTS (TYPE 3)
3223_3.PDF 3223 BOLTED ANGLE GUSSET SUPPORTS (TYPE 4)
3224_3.PDF 3224 BOLTED ANGLE GUSSET SUPPORTS (TYPE 5)
3225_3.PDF 3225 BOLTED STRAIGHT GUSSET SUPPORTS (TYPE 6)
3226_5.PDF 3226 PIPE BRANCH GUSSET SUPPORTS
3227_8.PDF 3227 STRUCTURAL STEEL FABRICATION AND ERECTION
3228_1.PDF 3228 CONCRETE CONSTRUCTION
3229_0.DOC 3229 (NUMBER CHANGED TO SP-50-01.5) SPACING & LAYOUT OF EQUIP
3230_1.PDF 3230 DIGITAL CONTROL SYSTEM (DCS) DESIGN
3231_5.PDF 3231 INSTRUCTIONS FOR USING THE PHA PRO HAZOP TEMPLATE
3232_3.PDF 3232 SHEET METAL DUCTWORK
3233_4.PDF 3233 FILL, DISCHARGE, AND AUXILIARY PIPING FOR ATMOSPHERIC STO
3234_1.PDF 3234 CLEANING, PROTECTION, PICKLING AND PASSIVATING PROCEDURE
3235_2.PDF 3235 MATERIALS REVIEW FOR PHA HYDROPROCESSING UNITS
3236_4.PDF 3236 MATERIALS REVIEW FOR PHA AMINE TREATING UNIT
3237_3.PDF 3237 MATERIALS REVIEW FOR PHA CATALYTIC REFORMER
3238_2.PDF 3238 MATERIALS REVIEW FOR PHA CDU & VDU
3239_2.PDF 3239 MATERIALS REVIEW FOR PHA DELAYED COKER UNIT
3240_3.PDF 3240 MATERIALS REVIEW FOR PHA FLUID CATALYTIC CRACKING AND LI
3241_3.PDF 3241 MATERIALS REVIEW FOR PHA HYDROFLUORIC ACID ALKYLATION
3242_2.PDF 3242 MATERIALS REVIEW FOR PHA SRU AND TGU
3243_2.PDF 3243 MATERIALS REVIEW FOR PHA SULFURIC ACID ALKYLATION
3245_3.PDF 3245 SOIL INVESTIGATION
3246_7.PDF 3246 METALLIC EXPANSION JOINTS
3247_14.XLS 3247 HIGH TEMPERATURE - PROCESS W/ OR W/O HYDROGEN OR HOT A
3248_3.PDF 3248 FOUNDATION FIELDBUS DESIGN
3249_9.XLS 3249 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN; H
3250_9.XLS 3250 AMINE (W/ OR W/O HYDROGEN)
3251_1.PDF 3251 HDPE HEAT FUSION BONDING FOR BUTT FUSION JOINTS
3252_2.PDF 3252 SITE PREPARATION, EARTHWORK, CHAIN LINK FENCING, AND ASPH
3253_4.PDF 3253 UNIT DECONTAMINATION
3254_8.PDF 3254 LOSS OF COOLING APPLICATION STANDARD
3255_4.PDF 3255 EMPLOYEE LOGS, NIGHT LETTERS AND SHIFT TURNOVER
3256_2.PDF 3256 MANAGING CCR CATALYST UNLOADING/RELOADING
3257_0.PDF 3257 SURGE ARRESTER (STATION AND INTERMEDIATED CLASS) OFFLINE
3258_0.PDF 3258 TRANSFER SWITCH - AUTOMATIC AND MANUAL OFFLINE TESTING
3259_0.PDF 3259 TRANSFER SWITCH - AUTOMATIC AND MANUAL OFFLINE TESTING
3260_0.PDF 3260 LOCKOUT RELAYS (ANSI DEVICE #86) OFFLINE TESTING FORM
3261_1.PDF 3261 RAILROAD EXTENSION
3262_2.PDF 3262 METAL BUILDING SYSTEMS
3263_0.XLS 3263 DOUBLE PIPE / HAIRPIN HEAT EXCHANGER DATA SHEET
3264_5.PDF 3264 STEEL STACKS
3265_2.PDF 3265 ULTRASONIC EXAMINATION OF FORGED AND ROLLED MATERIALS
3266_1.PDF 3266 PLATE AND SPIRAL PLATE HEAT EXCHANGERS
3267_3.PDF 3267 DOUBLE PIPE / HAIRPIN HEAT EXCHANGERS
3268_3.PDF 3268 DESIGN, MATERIAL SELECTION & MANUFACTURING PROCEDURES F
3269_0.DGN 3269 STANDARD STARTER RACK WITH NEMA 3R BUS DUCT 600V)
3270_2.PDF 3270 HEAT EXCHANGER TUBE INSPECTION AND REPAIR
3271_2.PDF 3271 REFORMER STARTUP
3272_1.PDF 3272 PROTECTION OF AUSTENITIC STAINLESS STEELS AND OTHER AUST
3273_1.PDF 3273 REFORMER SHUTDOWN AND DECONTAMINATION
3274_2.PDF 3274 DRAIN CONTROLLED USING WATER SEAL
3275_2.PDF 3275 DRAIN CONTROLLED USING INSERT SEAL
3276_2.PDF 3276 DRAIN CONTROLLED USING HARD PIPED CONNECTION/HOSE CON
3277_3.PDF 3277 DRAIN CONTROLLED USING SEALED CAP, PLUG, OR BLIND FLANGE
3278_2.PDF 3278 CATCH BASIN CONTROLLED USING BOX TRAP INSERT TO CREATE W
3279_2.PDF 3279 OILY WATER SEWER MANHOLE - TYPICAL INLET WATER SEAL (OPTIO
3280_2.PDF 3280 OILY WATER SEWER MANHOLE - TYPICAL INLET WATER SEAL (OPTIO
3281_2.PDF 3281 OILY WATER SEWER MANHOLE - TYPICAL BAFFLE INLET WATER SEA
3282_2.PDF 3282 PUMP SUMP WITH NITROGEN BLANKET VENTED TO CONTROL DEV
3283_3.PDF 3283 TYPICAL TWO CANISTER CARBON ADSORPTION SYSTEM FOR CONT
3284_2.PDF 3284 CLEAN OUT
3285_3.PDF 3285 SEWER SYSTEMS REQUIRING NESHAP CONTROL
3286_2.DOC 3286 LOPA STUDY APPROVAL FORM
3287_5.PDF 3287 LAYER OF PROTECTION ANALYSIS (LOPA)
3288_2.DOCX 3288 GENERAL MOOC PROCEDURE FORM
3289_2.DOC 3289 REFINERY DIVISION MANAGER REPLACEMENT GUIDELINES
3290_2.DOC 3290 REFINERY MAINTENANCE MANAGER REPLACEMENT GUIDELINES
3291_2.DOC 3291 REFINERY OPERATIONS MANAGER REPLACEMENT GUIDELINES
3292_2.DOC 3292 REFINERY TECHNICAL SERVICE MANAGER REPLACEMENT GUIDELIN
3293_2.DOC 3293 REFINERY PRODUCTS CONTROL MANAGER REPLACEMENT GUIDELI
3294_2.DOC 3294 REFINERY ENGINEERING MANAGER REPLACEMENT GUIDELINES
3295_2.DOC 3295 REFINERY ENVIRONMENTAL, SAFETY, AND SECURITY MANAGER RE
3296_2.DOC 3296 REFINERY HUMAN RESOURCES MANAGER REPLACEMENT GUIDELI
3297_2.DOC 3297 REFINERY PURCHASING/WAREHOUSING MANAGER REPLACEMENT
3298_2.DOC 3298 REFINERY CONTROLLER REPLACEMENT GUIDELINES (OPTIONAL)
3299_2.DOC 3299 REFINERY SUPERVISOR REPLACEMENT GUIDELINES (OPTIONAL)
3300_2.DOCX 3300 REFINERY ACQUISITION MOOC PROCEDURE FORM
3301_3.DOCX 3301 GENERAL PROCEDURALIZED MANAGEMENT OF CHANGE FOR MOO
3302_3.DOCX 3302 PROCEDURALIZED MANAGEMENT OF CHANGE FOR PERSONNEL R
3303_3.DOCX 3303 PROCEDURALIZED MANAGEMENT OF ORGANIZATIONAL CHANGE TE
3304_2.PDF 3304 HVAC AIR FLOW DIAGRAM SYSTEM A1
3305_1.PDF 3305 HVAC AIR FLOW DIAGRAM SYSTEM A2
3306_1.PDF 3306 HVAC AIR FLOW DIAGRAM SYSTEM B1
3307_1.PDF 3307 HVAC AIR FLOW DIAGRAM SYSTEM B2
3308_1.PDF 3308 HVAC AIR FLOW DIAGRAM SYSTEM C1
3309_1.PDF 3309 HVAC AIR FLOW DIAGRAM SYSTEM C2
3310_1.PDF 3310 HVAC AIR FLOW DIAGRAM SYSTEM D1
3311_2.PDF 3311 HVAC AIR FLOW DIAGRAM SYSTEM D2
3312_1.PDF 3312 HVAC AIR FLOW DIAGRAM SYSTEM E2
3313_1.PDF 3313 HVAC BLACK START DETAIL
3314_1.DOC 3314 HVAC SYSTEM DATASHEET
3315_7.PDF 3315 HEATING, VENTILATION AND AIR CONDITIONING (HVAC) UNITS DE
3340_2.PDF 3340 PROTECTIVE RELAYS (ELECTROMECHANICAL)
3341_2.PDF 3341 STANDBY GENERATORS
3342_2.PDF 3342 ELECTRIC HEAT TRACING SYSTEM
3343_3.PDF 3343 MOTOR OPERATED VALVE ACTUATORS
3344_10.XLS 3344 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN
3345_4.XLS 3345 ALLOY 825 (INCOLOY® 825) - UNS N08825
3346_1.PDF 3346 GUIDED WAVE RADAR
3347_2.PDF 3347 COKER STARTUP
3348_1.PDF 3348 COKER UNIT SHUTDOWN AND DECONTAMINATION
3349_1.PDF 3349 FCCU STARTUP FOLLOWING TURNAROUND
3350_0.PDF 3350 FCCU SHUTDOWN AND DECONTAMINATION
3351_2.PDF 3351 FCC FLARELESS START-UP
3352_0.DOC 3352 DISCREPANCY & DEVIATION REQUEST FORM
3353_0.PDF 3353 CONTROL VALVE REPAIR
3354_0.XLSX 3354 PRD ON-STREAM VISUAL INSPECTION CHECKLIST
3355_1.PDF 3355 CATHODIC PROTECTION SYSTEM RECTIFIERS
3356_3.PDF 3356 UNDERGROUND PIPING SOIL SIDE GALVANIC CATHODIC PROTECTIO
3357_2.PDF 3357 ABOVEGROUND STORAGE TANK SOIL SIDE CATHODIC PROTECTION
3358_2.PDF 3358 EIV APPLICATION STANDARDS FOR FLARE SYSTEMS
3359_2.PDF 3359 REFORMER UNIT MONITORING
3360_0.XLS 3360 DAMPER DATA SHEET
3361_4.PDF 3361 CONTROL AND GUILLOTINE DAMPERS FOR FIRED HEATER AND BOIL
3363_2.DOC 3363 PMOC - FULL DEFERRAL ANALYSIS
3364_1.DOC 3364 PMOC - SIMPLE ANALYSIS
3365_1.PDF 3365 COOLING TOWERS
3366_4.PDF 3366 SELECTION OF PROTECTIVE COATING SYSTEMS FOR ATMOSPHERIC
3367_1.PDF 3367 SURFACE PREPARATION AND APPLICATION OF PROTECTIVE COATIN
3368_4.PDF 3368 PRESSURE RELIEVING DEVICES APPLICATION AND MATERIAL SELEC
3369_0.XLS 3369 SPRING LOADED PRV PROCESS DEISGN SPECIFICATION SHEET
3370_0.XLSX 3370 PILOT OPERATED PRV PROCESS DEISGN SPECIFICATION SHEET
3371_0.XLS 3371 PRESSURE VACUUM RELIEF VALVES PROCESS DEISGN SPECIFICATIO
3372_0.XLS 3372 RUPTURE DISK DEVICE PROCESS DEISGN SPECIFICATION SHEET
3373_6.PDF 3373 SMALL BORE THREADED PIPING AND BUSHING PROGRAM
3374_0.XLS 3374 RTJ CALCULATIONS
3375_0.DOC 3375 RUBBER HOSE SPECIFICATION SHEET
3376_0.XLS 3376 CORRUGATED METAL HOSE SPECIFICATION SHEET
3377_5.PDF 3377 RUBBER AND CORRUGATED METAL HOSES
3378_0.XLS 3378 HYDROBLASTING AUDIT FORM
3379_0.DOC 3379 HYDROBLASTING CHECKLIST
3380_0.PDF 3380 HYDROBLASTING
3381_1.PDF 3381 HAZARDOUS GAS DETECTORS
3382_0.DOC 3382 PHA - PROCESS HAZARD ANALYSIS (PHA) STUDY APPROVAL FORM
3383_2.PDF 3383 PRODUCTION IMPACT REPORTING
3384_1.PDF 3384 INTERMEDIATE INVENTORY MANAGEMENT
3385_1.PDF 3385 PRODUCTION PLANNING FORECAST
3386_4.XLS 3386 HYDROFLUORIC ACID (UOP HF ALKY UNIT DESIGN, HF-20) (PWHT
3387_0.DOCX 3387 EQUIPMENT CUI CONDITION ASSESSMENT
3388_0.DOCX 3388 PIPING CUI CONDITION ASSESSMENT
3389_0.DOCX 3389 PIPE STRESS CORROSION CRACKING CONDITION ASSESSMENT
3390_3.PDF 3390 CORROSION UNDER INSULATION (CUI) - INSPECTION AND ASSESS
3391_6.PDF 3391 WINTERIZING AND HEAT CONSERVATION
3392_0.XLSX 3392 SPREADSHEET METHOD
3393_2.PDF 3393 METHOD FOR DETERMINING NSPS SUBPART JA HEATER APPLICABIL
3394_0.PDF 3394 FIRED EQUIPMENT FLAME DETECTION
3395_1.PDF 3395 FIRE DETECTION INSTRUMENTS
3396_4.PDF 3396 PACKAGED FIRED BOILERS
3397_0.XLS 3397 PUMP PARALLEL OPERATION EVALUATION DATA ENTRY SHEET
3398_0.PDF 3398 PARALLEL PUMP OPERATION EVALUATION CRITERIA
3399_15.DOC 3399 PRODUCT SHIPMENTS WITHOUT PRODUCT CERTIFICATION (LIVE S
3400_13.XLS 3400 REFINERY FINISHED PRODUCT ADDITIVES
3401_1.PDF 3401 PLANNED MAJOR MAINTENANCE PLANNING REQUIREMENTS
3402_0.XLS 3402 CLEANER HEAT TRANS HVBP EXAMPLE
3403_3.PDF 3403 TOTAL CONDENSING OVERHEAD PRESSURE CONTROL DESIGN
3405_0.XLS 3405 SHIFT TURNOVER CHECKLIST FOR FIELD OPERATOR
3406_0.XLS 3406 SHIFT TURNOVER CHECKLIST FOR SHIFT FOREMAN/CHIEF OPERAT
3407_0.XLS 3407 SHIFT TURNOVER CHECKLIST FOR CONTROL LAB ANALYST
3408_0.XLS 3408 LIQUID PHASE CHLORIDE GUARD ABSORBENT PROPOSAL REQUEST
3409_10.PDF 3409 BLOCKED OUTLET APPLICATION STANDARD
3410_4.DOCX 3410 PMOC FOR NEW CRUDE APPROVAL
3411_1.PDF 3411 HOT TANK CORNER WELD DETAIL
3412_1.PDF 3412 IFR CLEARANCE
3413_1.PDF 3413 TYPICAL 8" GAUGE & GUIDE POLE - BOTTOM SUPPORTS
3414_1.PDF 3414 TYPICAL PONTOON MANWAY COVER
3415_1.PDF 3415 WATER DRAW SUMP DISH - TYPE
3416_1.PDF 3416 SLOTTED GUIDE POLE WITH RADAR UNIT AND VAPOR SLEEVE AND
3417_1.PDF 3417 STEAM TRACING FOR PIPING
3418_1.PDF 3418 STEAM TRACING - VALVES, FLANGES, CONTROL VALVE MANIFOLDS
3419_2.PDF 3419 STEAM TRACING LIQUID LEVEL INSTRUMENTS
3420_1.PDF 3420 STEAM TRACING TAGGING PROCEDURE
3421_1.PDF 3421 STEAM TRACING RUNS, LOOPS, AND ANCHORS
3422_3.XLSX 3422 AGREED TEST PROCEDURES
3423_1.PDF 3423 RELIABILITY & OPERATIONAL EXCELLENCE ADVISORY (ROEA) WORK
3424_0.DOCX 3424 RELIABILITY & OPERATIONAL EXCELLENCE ADVISORY (ROEA) TEMP
3425_5.XLS 3425 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN; S
3426_5.XLS 3426 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN (P
3427_4.XLS 3427 HYDROCARBONS W/ HYDROGEN BELOW 50 PSIA PP; STEAM, CONDE
3428_5.XLS 3428 HYDROCARBONS W/ OR W/OUT HYDROGEN
3429_7.XLS 3429 HIGH TEMPERATURE - STEAM, CONDENSATE, BOILER FEEDWATER (P
3430_5.XLS 3430 SEVERE WET H2S - HYDROCARBONS W/ OR W/O HYDROGEN (PWH
3431_5.XLS 3431 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN; H
3432_4.XLS 3432 HYDRAULIC OIL SERVICE
3433_6.XLS 3433 SEVERE WET H2S - HYDROCARBONS W/ OR W/O HYDROGEN; SOU
3434_5.XLS 3434 HYDROCARBONS W/ HYDROGEN BELOW 50 PSIA PP
3435_4.XLS 3435 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN; H
3436_7.XLS 3436 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN
3437_2.PDF 3437 CLARIFIERS AND COLD LIME SOFTENERS
3438_3.PDF 3438 MULTI-MEDIA FILTERS FOR WATER TREATMENT SYSTEMS
3439_2.PDF 3439 WATER DEAERATORS AND DEGASIFIERS (DECARBONATORS)
3440_2.DOC 3440 PMOC FORM FOR TEMPORARY PORTABLE PUMPS
3441_0.PDF 3441 BASELINE ULTRASONIC THICKNESS MEASUREMENTS ON FIXED EQU
3443_1.XLS 3443 INSTRUCTIONS FOR ENERGY ISOLATION LIST FORM
3444_0.XLS 3444 INSTRUCTIONS FOR STATUS CHANGE / TEMPORARY RELEASE FOR
3445_1.XLS 3445 ENERGY ISOLATION LIST FORM (EXCEL VERSION)
3446_1.XLS 3446 SUPPLEMENTAL ENERGY ISOLATION LIST FORM (EXCEL VERSION)
3447_1.XLS 3447 ISOLATION BLIND LIST FORM (EXCEL VERSION)
3448_1.XLS 3448 STATUS CHANGE / TEMPORARY RELEASE FORM
3449_1.DOCX 3449 HOT WORK ISOLATION BY ENGINEERED PLUG APPROVAL FORM
3450_0.DOCX 3450 BLINDING AND ENERGY ISOLATION INSPECTION FORM
3451_2.XLSX 3451 PRODUCT QUALITY AUDIT CHECKLIST
3452_3.PDF 3452 PRODUCT QUALITY AUDIT PROTOCOL
3453_4.XLS 3453 CAUSTIC (FOR OPERATION IN AREA "B" OF THE NACE CAUSTIC SO
3454_3.XLS 3454 ALLOY 400 (PROCESS SERVICE AND HOT CAUSTIC IN AREA "C" OF
3455_3.XLS 3455 HYDROCARBONS W/ OR W/O HYDROGEN; CRYOGENIC PROCESS
3456_5.XLS 3456 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN
3457_4.XLS 3457 FIREWATER, FIREWATER MAKEUP, FIREWATER MAKEUP USING SE
3458_9.XLS 3458 INSTRUMENT AIR [GALV CARBON STEEL]
3459_6.XLS 3459 PLANT AIR
3460_4.XLS 3460 CAUSTIC (FOR OPERATION IN AREA "B" OF THE NACE CAUSTIC SE
3461_2.XLS 3461 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN; H
3462_2.XLS 3462 HIGH TEMPERATURE - SEVERE WET H2S - HYDROCARBONS W/ OR
3463_6.XLS 3463 HYDROFLUORIC ACID (COP HF ALKY UNIT DESIGN) (PWHT REQUIR
3464_0.PDF 3464 SRU SULFUR PITS
3465_4.XLSX 3465 GBR PIPING CROSS REFERENCE
3466_6.PDF 3466 PROJECT TEMPLATE ECONOMICS MODEL USAGE GUIDELINES
3467_0.XLSX 3467 ELECTRICAL INFRASTRUCTURE RISK SCORECARD
3468_0.PDF 3468 ASSESSMENT OF ELECTRICAL INFRASTRUCTURE
3469_1.XLS 3469 LABORATORY RETURN-TO-WORK CHECKLIST
3470_3.PDF 3470 LABORATORY TRAINING STANDARD PRACTICE
3471_2.XLS 3471 SEVERE WET H2S - HYDROCARBONS (LOW TEMPERATURE) W/ OR
3472_3.XLS 3472 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN;
3473_1.PDF 3473 FLS LEAD YOUR TEAM GUIDE
3474_2.XLS 3474 ALLOY 400 (PROCESS SERVICE AND HOT CAUSTIC IN AREA "C" OF T
3475_0.XLSX 3475 FUME HOOD FACE VELOCITY MONITORING
3476_0.XLSX 3476 TANK CLEANING BID TEMPLATE
3477_0.XLSX 3477 TANK WASTE BID TEMPLATE
3478_0.PDF 3478 HIGH SOLIDS TANK CLEANING
3479_2.PDF 3479 SCHEDULE QUALITY GUIDELINE
3480_1.PDF 3480 OIL MIST SYSTEMS
3481_1.PDF 3481 EGRESS STAIRS (W/ ANGLE POSTS) PLAN AND SECTIONS
3482_1.PDF 3482 EGRESS STAIRS (W/ ANGLE POSTS) DETAILS
3483_2.PDF 3483 GUARDRAIL SYSTEM
3484_0.PDF 3484 NITROGEN IN BUILDINGS AND ENCLOSED AREAS
3485_1.PDF 3485 REFINING PRODUCT QUALITY INCIDENT SUPPLEMENT
3486_5.DOCX 3486 BULK CHEMICAL UNLOADING CHECKLIST
3487_1.DOCX 3487 BULK CHEMICAL LOADING CHECKLIST
3488_7.PDF 3488 LOADING AND UNLOADING BULK CHEMICAL SHIPMENTS
3489_0.XLS 3489 OXYGEN ENRICHED AIR (LESS THAN OR EQUAL TO 35% OXYGEN)
3490_1.PDF 3490 EXAMPLE BASIC GUIDELINES CMD
3491_2.PDF 3491 EXAMPLE SYSTEM LEVEL CMD
3492_2.PDF 3492 EXAMPLE CORROSION LOOP CMD
3493_1.PDF 3493 EXAMPLE BLANK CMD
3494_4.PDF 3494 CORROSION AND MATERIALS DIAGRAM (CMD) GUIDELINES
3495_1.XLS 3495 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN; H
3496_1.XLS 3496 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN; H
3497_3.XLS 3497 HYDRAULIC OIL SERVICE
3498_1.PDF 3498 COLD SET CLEARANCE REPORT EXAMPLE
3499_1.PDF 3499 STUFFING BOX ARRANGEMENT EXAMPLE
3500_1.PDF 3500 STEM INSPECTION FORM EXAMPLE
3501_1.PDF 3501 VALVE STEM INSPECTION EXAMPLE
3502_1.PDF 3502 STEM/DISC INSPECTION EXAMPLE
3503_1.PDF 3503 EXAMPLE INSPECTION TEST PLAN
3504_1.PDF 3504 FLUE GAS DOUBLE DISC SLIDE A/B VALVE SAT PROCEDURE
3505_1.PDF 3505 FLUE GAS DOUBLE DISC SLIDE C/D VALVE SAT PROCEDURE
3506_1.PDF 3506 REGEN CATALYST SLIDE VALVE SAT PROCEDURE
3507_1.PDF 3507 SPENT CATALYST SLIDE VALVE SAT PROCEDURE
3508_1.PDF 3508 SLIDE VALVE TAR MAINTENANCE AND INSPECTION STRATEGIES
3509_2.PDF 3509 PROCESS DESIGN ENGINEER ROLES AND RESPONSIBILITIES
3510_1.PDF 3510 RBI RESIDUAL RISK - INSPECTION PLANNING GUIDANCE
3511_0.DOCX 3511 RBI - ACTION DEFERRAL FORM
3512_1.PDF 3512 LEVELS OF INSPECTION EFFECTIVENESS FOR RBI AND INSPECTION
3513_0.DOC 3513 ENERGY OPTIMIZATION ACTION ITEMS LOG
3514_0.DOC 3514 ENERGY OPTIMIZATION VIP PARTICIPATION LOG
3515_0.DOC 3515 HEATER AIR INFILTRATION CHECKLIST
3516_1.PDF 3516 ENERGY OPTIMIZATION FOR PROJECTS AND PROCESS DESIGN
3517_0.DOC 3517 PSA CREATION REVIEW CHECKLIST
3518_0.DOCX 3518 EXAMPLE VIDEO PRODUCTION WORKSHEET
3519_0.DOCX 3519 MACT DDDDD TUNE-UP FORM
3520_1.PDF 3520 REFINERY FIRE PROTECTION
3521_3.PDF 3521 PSM-RELATED RECOMMENDATION MANAGEMENT
3522_0.PPTX 3522 INTERNAL AUDITING POWERPOINT PRESENTATION
3523_0.DOCX 3523 CANTON TOOLBOX TOPIC ON TANK GAUGING
3524_1.XLS 3524 TRADITIONAL CONTINGENCY PLUS MANAGEMENT RESERVE RATIN
3525_1.XLSX 3525 CONTINGENCY AS A % OF TIC RELATIVE TO PROBABILITY FACTOR
3526_0.XLS 3526 MANAGEMENT RESERVE REQUISITION FORM
3527_0.XLS 3527 PRODUCTIVITY TOOL GUIDELINE
3528_2.XLS 3528 COST SUMMARY SHEET GUIDELINE
3529_0.XLS 3529 INDIRECT COST TOOLS GUIDELINE
3530_0.XLS 3530 DETAILED OWNERS COST GUIDELINE
3531_0.XLS 3531 DESIGN ALLOWANCE MODEL GUIDE
3532_0.XLSX 3532 CONTINGENCY DRAW-DOWN PLAN GUIDE
3533_0.PDF 3533 CONTINGENCY AND MANAGEMENT RESERVE GUIDE FOR LARGE PR
3534_0.PDF 3534 ESTIMATE STRUCTURE GUIDE APPLICABLE TO LARGE PROJECTS
3535_0.PDF 3535 DESIGN ALLOWANCE GUIDE FOR LARGE PROJECTS AT OR EXCEEDI
3536_0.PDF 3536 CONTINGENCY DRAW-DOWN GUIDE FOR LARGE PROJECTS GREAT
3537_3.PDF 3537 DESIGN AND INSTALLATION OF FIRE WATER SYSTEMS AND COMPO
3538_0.DOCX 3538 ENERGY ISOLATION LIST FORM (WORD VERSION)
3539_0.DOCX 3539 SUPPLEMENTAL ENERGY ISOLATION LIST FORM (WORD VERSION)
3540_0.DOCX 3540 ISOLATION BLIND LIST FORM (WORD VERSION)
3541_0.XLSX 3541 SUPPLEMENTAL ISOLATION BLIND LIST FORM (EXCEL VERSION)
3542_0.DOCX 3542 SUPPLEMENTAL ISOLATION BLIND LIST FORM (WORD VERSION)
3543_3.PDF 3543 GENERATION OF INSPECTION TASKS
3544_3.XLS 3544 HYDROCARBONS W/ OR W/O HYDROGEN; SIMPLE OR SEVERE WET
3545_0.DOC 3545 LARGE, COMPLEX AND HIGH DENSITY WORK CONFINED SPACE HA
3546_0.DOC 3546 RECLASSIFIED NON-CONFINED SPACE NOTICE
3547_0.DOCX 3547 CONFINED SPACE ENTRY REFERENCE SHEET TEMPLATE
3548_1.PPTX 3548 PROCESS SAFETY FLASH TEMPLATE
3549_1.DOCX 3549 (WITHDRAWN - TEMPORARY FILE TO EXPIRE 10/1/2017) REV 5 OF
3550_0.XLS 3550 SHIFT TURNOVER CHECKLIST FOR PRODUCT LOADER
3551_0.PDF 3551 INFERENTIAL AND QUALITY CALCULATIONS RECOMMENDED PRACT
3552_2.PDF 3552 SELECTION AND ACQUISITION OF MONITORING AND TRENDING SY
3553_0.DOC 3553 SAFE ENTRY INTO INERT ATMOSPHERE PRE-ENTRY CHECKLIST
3555_5.PDF 3555 SAFE USE OF ELECTRONIC DEVICES
3556_2.PDF 3556 REFINERY LABORATORY STATISTICAL TESTING
3557_0.PDF 3557 REFINERY PROFIT PROJECTION REFERENCE GUIDE
3558_3.PDF 3558 DESIGN TEMPERATURE AND PRESSURE REQUIREMENTS
3559_1.PDF 3559 PCG FOR FUELS COMPLIANCE REPORTING
3560_2.PDF 3560 ASSET CRITICALITY ANALYSIS GUIDELINES
3561_0.PDF 3561 10 MVA (OR LARGER) TRANSFORMER ACCEPTANCE TESTING FORM
3562_4.PDF 3562 TRANSFORMERS (OIL-FILLED) GREATER THAN OR EQUAL TO 10 MV
3563_0.PDF 3563 GREATER THAN 200KVA AND LESS THAN 10MVA TRANSFORMER AC
3564_0.PDF 3564 SWITCHGEAR (MAIN SUBSTATION) ACCEPTANCE TESTING FORM
3565_0.PDF 3565 SWITCHGEAR (UNIT SUBSTATION) AND MEDIUM VOLTAGE MCC AC
3566_1.PDF 3566 TRANSFORMERS (OIL-FILLED) GREATER THAN 200 KVA AND LESS T
3567_1.PDF 3567 SWITCHGEAR (MAIN SUBSTATION)
3568_1.PDF 3568 SWITCHGEAR (UNIT SUBSTATION) AND MEDIUM VOLTAGE MCC
3569_2.PDF 3569 LUBE OIL SYSTEM
3570_2.PDF 3570 PLAN 54 SYSTEM
3571_1.PDF 3571 BUSINESS ENGINEERING ALIGNMENT MEETING (BEAM) TEMPLATE
3572_3.XLS 3572 LIFE CYCLE COST EVALUATION SPREADSHEET
3573_0.DOCX 3573 LIFE CYCLE COST ANALYSIS EXAMPLE CASE STUDY
3574_0.XLS 3574 LIFE CYCLE COST ANALYSIS TOOL FOR EXAMPLE CASE STUDY
3575_0.XLS 3575 REM MODEL FOR EXAMPLE CASE STUDY
3576_0.PDF 3576 STRATEGIC PROJECT PLANNING WORKSHOP (SPPW) TEMPLATE AND
3577_2.PDF 3577 PACKAGED AIR COMPRESSORS
3578_0.PDF 3578 COKER UNIT MONITORING
3579_1.PDF 3579 CONTROL SYSTEMS EXCELLENCE
3580_0.PDF 3580 REFINERY LP MODEL POST AUDIT REFERENCE GUIDE
3581_0.PDF 3581 BUS DUCT ACCEPTANCE TESTING FORM [SEG/NON-SEG]
3582_0.PDF 3582 BUS DUCT ACCEPTANCE TESTING FORM [ISO]
3583_0.PDF 3583 GAS CIRCUIT BREAKER ACCEPTANCE TESTING FORM
3584_0.PDF 3584 VACUUM CIRCUIT BREAKER (MEDIUM VOLTAGE) ACCEPTANCE TES
3585_0.PDF 3585 GAS CIRCUIT BREAKERS
3586_0.PDF 3586 VACUUM CIRCUIT BREAKERS - MEDIUM VOLTAGE
3587_0.PDF 3587 CIRCUIT BREAKER (LOW VOLTAGE) ACCEPTANCE TESTING FORM
3588_0.PDF 3588 CIRCUIT BREAKER (MOLDED CASE) ACCEPTANCE TESTING FORM
3589_0.PDF 3589 MOTOR STARTER (MEDIUM VOLTAGE) ACCEPTANCE TESTING FORM
3590_0.PDF 3590 LOW VOLTAGE MOTOR CONTROL CENTER ACCEPTANCE TESTING F
3591_0.PDF 3591 LOW VOLTAGE COMBINATION STARTER ACCEPTANCE TESTING FOR
3592_0.PDF 3592 MISCELLANEOUS SWITCHRACK/MCC BREAKER ACCEPTANCE TESTI
3593_0.PDF 3593 LOW VOLTAGE SWITCHRACK ACCEPTANCE TESTING FORM
3594_0.PDF 3594 BUS DUCT
3595_0.PDF 3595 CIRCUIT BREAKERS - LOW VOLTAGE
3596_0.PDF 3596 CIRCUIT BREAKERS - MOLDED CASE
3597_0.PDF 3597 MOTOR STARTERS - MEDIUM VOLTAGE (AIR/VACUUM)
3598_0.PDF 3598 LOW VOLTAGE MOTOR CONTROL CENTERS
3599_0.PDF 3599 LOW VOLTAGE COMBINATION STARTERS
3600_0.PDF 3600 LOW VOLTAGE SWITCHRACKS (BUS BOX AND STRUCTURE)
3601_0.XLS 3601 PIPE WELD DATA SHEET - CARBON STEEL - LOW TEMPERATURE GEN
3602_0.XLS 3602 PIPE WELD DATA SHEET - CARBON STEEL - LOW TEMPERATURE HY
3603_1.XLS 3603 HYDROCARBONS W/ OR W/O HYDROGEN
3605_0.DOCX 3605 OPERATING PROCEDURES - TEMPLATE 04 - CHECKLIST
3606_0.DOCX 3606 OPERATING PROCEDURES - TEMPLATE 05 - ALTERNATE CHECKLIST
3607_2.DOCX 3607 OPERATING PROCEDURES - TEMPLATE 10 - PROCEDURE CHANGE L
3608_0.XLS 3608 COMPLETED PROCEDURE ASSESSMENT CHECKLIST
3609_0.XLSX 3609 PROCEDURE RISK MATRIX
3610_0.XLSX 3610 STANDARD IOW SPREADSHEET
3611_0.XLSX 3611 CORROSION LOOP TABLE FORMAT
3612_2.PDF 3612 INTEGRITY OPERATING WINDOW (IOW) AND CORROSION CONTROL
3613_0.PDF 3613 QA/QC PERSONNEL REQUIREMENTS
3614_1.PDF 3614 REFINING HES&S POLICY
3615_1.XLSX 3615 CORPORATE REFINING HES&S COMPLIANCE OBLIGATIONS
3616_2.PDF 3616 RC MULTI-SITE AUDIT FINDING PROCESS DECISION TREE
3619_3.PDF 3619 DECISION SUPPORT PACKAGE (DSP) REQUIREMENTS
3620_0.PDF 3620 REFINERY FUELS COMPLIANCE REPORTING (PACE)
3621_0.DOC 3621 SODIUM HYPOCHLORITE (BLEACH) ADDITIVE SYSTEMS DATASHEET
3622_3.PDF 3622 SODIUM HYPOCHLORITE (BLEACH) ADDITIVE SYSTEMS
3623_1.PDF 3623 PRESSURE-RATED BLINDS, NON-RATED BLINDS, VENT (BLEEDER) BL
3624_6.PDF 3624 REFINING HES&S MANAGEMENT SYSTEM MANUAL
3625_4.PDF 3625 CREATING INTELEX RECOMMENDATIONS FOR APPLICATION STAND
3626_1.PDF 3626 GUIDANCE ON CLOSURE OF APPLICATION STANDARD GAPS ALSO ID
3627_0.PDF 3627 MOBILE INSPECTION, TEST, PREVENTATIVE AND PREDICTIVE MAIN
3628_0.PDF 3628 IDENTIFYING AND ADDRESSING BAD ACTORS GUIDELINE
3629_0.PDF 3629 FCC UNIT MONITORING
3630_0.PDF 3630 MPLXRL BUSINESS PLANNING GUIDELINES FOR REFINING STAFF
3631_2.PDF 3631 MPLXRL MASTER PROJECT AND SERVICES RECOVERY AGREEMENT G
3632_2.PDF 3632 TYPICAL INJECTION SYSTEM INSTALLATION FOR BASINS
3633_0.XLS 3633 PIPE WELD DATA SHEET - CARBON STEEL - ASME B31.1 BOILER EXT
3634_0.XLS 3634 PIPE WELD DATA SHEET - CARBON STEEL - ASME B31.1 BOILER EXTE
3635_0.XLS 3635 PIPE WELD DATA SHEET - 1-¼ CHROME - ASME B31.1 BOILER EXTER
3636_0.XLS 3636 PIPE WELD DATA SHEET - 9 CHROME - ASME B31.1 BOILER EXTERNAL
3637_0.PDF 3637 LIFT STATION
3638_1.PDF 3638 LIFT STATION SPECIFICATION
3639_1.PDF 3639 GUIDANCE FOR EXISTING LIFT STATIONS
3640_0.PDF 3640 UNIT SUBSTATION TRANSFORMERS (OIL-FILLED) LOW VOLTAGE
3641_0.PDF 3641 STRUCTURAL INTEGRITY ASSESSMENT
3642_0.DOCX 3642 PRE-FABRICATED ELECTRICAL BUILDING INSTALLATION CHECKLIST
3643_0.DOCX 3643 CABLE TRAY INSTALLATION CHECKLIST
3644_0.DOCX 3644 CONDUIT INSTALLATION CHECKLIST
3645_0.DOCX 3645 POWER PANEL INSTALLATION CHECKLIST
3646_0.DOCX 3646 AUTO-TRANSFER SWITCH CHECKLIST
3647_0.DOCX 3647 BATTERY CHARGER INSTALLATION CHECKLIST
3648_0.DOCX 3648 ANNUNCIATOR/NETWORK CABINET INSTALLATION CHECKLIST
3649_0.DOCX 3649 HIGH RESISTANCE GROUND INSTALLATION CHECKLIST
3650_0.DOCX 3650 CABLE TERMINATION AND INSTALLATION CHECKLIST
3651_0.DOCX 3651 MEDIUM VOLTAGE SWITCHGEAR CHECKLIST
3652_0.DOCX 3652 MEDIUM VOLTAGE DRAWOUT BREAKER/CUBICLE INSTALLATION CH
3653_0.DOCX 3653 MEDIUM VOLTAGE MCC INSTALLATION CHECKLIST
3654_0.DOCX 3654 MEDIUM VOLTAGE MCC SECTION INSTALLATION CHECKLIST
3655_0.DOCX 3655 LOW VOLTAGE SWITCHGEAR INSTALLATION CHECKLIST
3656_0.DOCX 3656 LOW VOLTAGE DRAWOUT BREAKER/CUBICLE INSTALLATION CHECKL
3657_0.DOCX 3657 LOW VOLTAGE MCC CHECKLIST
3658_0.DOCX 3658 LOW VOLTAGE MCC BUCKET INSTALLATION CHECKLIST
3659_0.DOCX 3659 LOW VOLTAGE VARIABLE FREQUENCY DRIVE INSTALLATION CHECKL
3660_0.DOCX 3660 DRY-TYPE TRANSFORMER INSTALLATION CHECKLIST
3661_0.DOCX 3661 OIL FILLED TRANSFORMER INSTALLATION CHECKLIST
3662_0.XLSX 3662 SUBSTATION FAT PUNCHLIST
3663_0.PDF 3663 PRE-FABRICATED ELECTRICAL BUILDING FACTORY ACCEPTANCE TE
3664_0.DOCX 3664 PRE-HYDROTEST CHECKLIST
3665_0.DOCX 3665 POST-HYDROTEST CHECKLIST
3666_1.PDF 3666 SIMPLEX AND TMR PROGRAMMABLE LOGIC CONTROLLER SYSTEM
3667_1.PDF 3667 FIRED BOILER TIME DELAY REQUIREMENTS FOR FLAME SCANNERS
3668_0.PDF 3668 LAB EXCELLENCE
3669_2.XLSX 3669 MOC TASKS
3670_1.XLSX 3670 RELIEF CHECKLIST
3671_1.XLSX 3671 GENERAL EVALUATION CHECKLIST
3673_2.XLS 3673 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN; ST
3674_1.XLS 3674 HIGH TEMPERATURE - HYDROCARBONS W/ OR W/O HYDROGEN; ST
3675_1.XLS 3675 LUBE OIL / SEAL OIL; DEAERATOR FEED
3676_2.XLS 3676 HIGH TEMPERATURE - STEAM (ASME B31.1 CODE) (FOR GALVESTON
3677_1.XLS 3677 HIGH TEMPERATURE - STEAM (FOR GALVESTON BAY SHGP ONLY)
3678_0.XLS 3678 HIGH TEMPERATURE - STEAM (FOR GALVESTON BAY SHGP ONLY)
3679_0.PDF 3679 AIRGAS SYSTEM ENTIRE OPERATING PROCEDURE
3680_0.PDF 3680 AIRGAS SOP TASK OVERVIEW - PUMPOUT OF AMMONIA STORAGE
3681_2.PDF 3681 SAFE HANDLING OF ANHYDROUS AMMONIA - CYLINDERS AND TAN
3682_1.PDF 3682 REFINERY JET FUEL MANAGEMENT
3683_0.DOCX 3683 PMOC FOR UTILITY TO PROCESS CONNECTION INSTALLATION
3684_0.PDF 3684 CAUSTIC AND UTILITY CONNECTIONS TO PROCESS LINES AND VESS
3685_0.XLS 3685 EQUIPMENT/PUMP REPAIR SHOP ASSESSMENT AND QUALIFICATI
3686_0.PDF 3686 MECHANICAL SHOP AUDIT PROCEDURE
3687_2.PDF 3687 ABOVEGROUND STORAGE TANK INSPECTION PROGRAM
3688_0.PPTX 3688 VALUE CHAIN
3689_0.PDF 3689 DESIGN AND SELECTION OF INSULATION SYSTEMS
3690_0.PDF 3690 INSTALLATION OF THERMAL INSULATION MATERIALS
3691_3.XLSX 3691 APPROVED MANUFACTURERS LIST (AML) [NON-PVF]
3692_0.XLS 3692 FABRICATOR PRELIMINARY QUESTIONNAIRE
3693_0.DOCX 3693 MANUFACTURER AND FABRICATOR ON-SITE ASSESSMENT
3694_0.DOCX 3694 REFINING POST FABRICATION EVALUATION FORM
3695_1.DOCX 3695 AML ADDITION, DELETION AND TEMPORARY DEVIATION FORM
3696_2.PDF 3696 APPROVED MANUFACTURER AND FABRICATOR LIST
3697_0.PDF 3697 MAINTENANCE TRAINING STANDARD PRACTICE
3698_0.DOCX 3698 REPAIRS/ALTERATIONS/RE-RATINGS AUTHORIZATION/APPROVAL F
3699_1.PDF 3699 PRESSURE VESSEL INSPECTION PROGRAM
3700_0.PDF 3700 REPAIRS/ALTERATIONS/RE-RATINGS PROGRAM FOR PRESSURE EQU
3701_0.XLSX 3701 CONTRACTOR ELECTRONIC DEVICE FORM
3702_0.PDF 3702 CORPORATE REFINING SPARES INVENTORY MANAGEMENT
3703_1.XLSX 3703 MANAGEMENT SYSTEMS FACTOR ASSESSMENT
3704_0.PDF 3704 RBI - ASSESSMENT FOR MANAGEMENT SYSTEMS FACTOR
3705_0.PDF 3705 RISK-BASED INSPECTION - KEY PERFORMANCE INDICATORS
3706_0.XLSX 3706 TAR FORM - TAR BUDGET DEVELOPMENT STRATEGY FORM
3707_0.XLSX 3707 TAR FORM - TAR BUDGET DEVELOPMENT SCHEDULE
3708_0.DOCX 3708 TAR FORM - TAR BUDGET DEVELOPMENT CHECKLIST
3709_0.PDF 3709 TAR ATTACHMENT - TAR BUDGET DEVELOPMENT FLOWCHART
3710_0.DOCX 3710 TAR ATTACHMENT - MARATHON (MPC) SMART GUIDELINES
3711_0.DOCX 3711 TAR ATTACHMENT - COST CONSISTENCY DOCUMENT
3712_1.PDF 3712 TURNAROUND (TAR) BUDGET DEVELOPMENT GUIDELINES
3713_2.PDF 3713 TURNAROUND (TAR) CHECK ESTIMATE PROCEDURE
3714_1.PDF 3714 TURNAROUND (TAR) CONTROL ESTIMATE
3715_0.PDF 3715 TAR ATTACHMENT - EXAMPLE P6 SCHEDULE FORECAST CURVE
3716_0.XLSX 3716 TAR ATTACHMENT - EXAMPLE EXPENSE CLASS FORECAST CURVE
3717_1.PDF 3717 TURNAROUND (TAR) COST FORECASTING PROCEDURE
3718_1.PDF 3718 TURNAROUND (TAR) PLANNING ORGANIZATION AND RESPONSIBILI
3719_1.XLSX 3719 TAR ATTACHMENT - TAR WORK SCOPE DEVELOPMENT DOCUMENT
3720_1.PDF 3720 TURNAROUND (TAR) SCOPE DEVELOPMENT GUIDELINES
3721_0.XLSX 3721 TAR FORM - DAILY FORCE REPORT
3722_0.XLSX 3722 TAR FORM - COST ESTIMATE WORKSHEET
3723_0.DOCX 3723 OPERATOR READINESS CHECK LIST
3724_0.PDF 3724 TAR FORM - RENTAL EQUIPMENT RECORD (RER)
3725_0.DOCX 3725 RELIEF SYSTEM IMPACT CHECKLIST
3726_0.PDF 3726 RELIEF SYSTEM EVERGREENING
3727_0.XLSX 3727 PHA MATERIALS ASSESSMENT QUESTIONS FOR HYDROPROCESSING
3728_0.XLSX 3728 PHA MATERIALS ASSESSMENT QUESTIONS FOR AMINE TREATING U
3729_0.XLSX 3729 PHA MATERIALS ASSESSMENT QUESTIONS FOR CATALYTIC REFORM
3730_0.XLSX 3730 PHA MATERIALS ASSESSMENT QUESTIONS FOR CRUDE DISTILLATIO
3731_1.XLSX 3731 PHA MATERIALS ASSESSMENT QUESTIONS FOR VACUUM DISTILLAT
3732_0.XLSX 3732 PHA MATERIALS ASSESSMENT QUESTIONS FOR DELAYED COKER UN
3733_0.XLSX 3733 PHA MATERIALS ASSESSMENT QUESTIONS FOR FLUID CATALYTIC C
3734_0.XLSX 3734 PHA MATERIALS ASSESSMENT QUESTIONS FOR LIGHT ENDS RECOV
3735_1.XLSX 3735 PHA MATERIALS ASSESSMENT QUESTIONS FOR HYDROFLUORIC ACI
3736_0.XLSX 3736 PHA MATERIALS ASSESSMENT QUESTIONS FOR SULFUR RECOVERY
3737_0.XLSX 3737 PHA MATERIALS ASSESSMENT QUESTIONS FOR TAIL GAS UNITS
3738_0.XLSX 3738 PHA MATERIALS ASSESSMENT QUESTIONS FOR SULFURIC ACID ALK
3739_2.PDF 3739 GASOLINE OVERSIGHT PROGRAM
3740_1.PDF 3740 PERSONAL PROTECTIVE EQUIPMENT
3741_0.PDF 3741 FLARE AND FLARE STACK INSPECTION PROGRAM
3742_0.DOC 3742 FIRED HEATER BURNER INSPECTION CHECKLIST
3743_2.PDF 3743 BOILER AND FIRED HEATER INSPECTION PROGRAM
3744_0.PDF 3744 NUMERIC INDEX FOR TESORO ENGINEERING STANDARDS
3745_0.PDF 3745 ENGINEERING, PROCUREMENT, AND CONSTRUCTION QUALITY RE
3746_0.XLSX 3746 SUPPLIER QUALITY RATING CRITERIA
3747_0.PDF 3747 SAFETY AND LOSS PREVENTION
3748_0.PDF 3748 FIRE PROTECTION GENERAL
3749_0.XLS 3749 GENERAL PLANT SITE DATA SHEET
3750_0.XLS 3750 CIVIL DESIGN CRITERIA FOR ANACORTES REFINERY
3751_0.XLS 3751 CIVIL DESIGN CRITERIA FOR GOLDEN EAGLE REFINERY
3752_0.XLS 3752 CIVIL DESIGN CRITERIA FOR LOS ANGELES REFINERY
3753_0.XLS 3753 CIVIL DESIGN CRITERIA FOR MANDAN REFINERY
3754_0.XLS 3754 CIVIL DESIGN CRITERIA FOR SALT LAKE CITY REFINERY
3755_0.PDF 3755 CIVIL DETAILS DESIGN DRAWINGS
3756_0.XLS 3756 PROJECT DATA SHEET
3757_0.PDF 3757 TOPOGRAPHIC AND PLANT SURVEY
3758_0.XLSX 3758 EARTHWORK INSPECTION CHECKLIST
3759_0.PDF 3759 SEWER DETAILS
3760_0.PDF 3760 VERTICAL VESSEL FOUNDATION DESIGN
3761_0.PDF 3761 HEAT EXCHANGER AND HORIZONTAL VESSEL FOUNDATION DESIGN
3762_0.PDF 3762 DEADMAN AND GUY ANCHORS
3763_0.PDF 3763 TYPICAL STANCHION FOUNDATION DRAWINGS
3764_0.DOC 3764 ATMOSPHERIC STORAGE TANK FOUNDATION MONITORING, REPAIR
3765_0.PDF 3765 PILE INSTALLATION INSPECTION CHECKLIST
3766_0.PDF 3766 PILE PLAN DRAWING CHECKLIST
3767_0.PDF 3767 ACCESSIBILITY REQUIREMENTS FOR BUILDINGS AFFECTED BY AMERI
3768_0.PDF 3768 BLAST RESISTANT BUILDINGS DESIGN CRITERIA
3769_0.PDF 3769 ARCHITECTURAL DESIGN
3770_0.PDF 3770 ARCHITECTURAL WORK
3771_0.PDF 3771 ARCHITECTURAL AND BUILDING UTILITIES DESIGN CRITERIA
3772_0.PDF 3772 BUILDING DATA SHEETS
3773_0.PDF 3773 GENERAL REQUIREMENTS FOR BUILDINGS INSPECTION CHECKLIST
3774_0.PDF 3774 STANDARD STEEL DOORS AND FRAMES
3775_0.PDF 3775 SECTIONAL OVERHEAD DOORS
3776_0.PDF 3776 HOLLOW METAL DOORS AND PRESSED STEEL FRAMES
3777_0.PDF 3777 DOOR HARDWARE
3778_0.PDF 3778 STRUCTURAL STEEL CONSTRUCTION INSPECTION CHECKLIST
3779_0.PDF 3779 CS VESSELS / EXCHANGERS IN SEVERE SERVICE
3780_0.PDF 3780 LOW ALLOY VESSELS / EXCHANGERS
3781_0.PDF 3781 ALLOY CLAD VESSELS / EXCHANGERS
3782_0.PDF 3782 FLANGES, GASKETS, AND STUD DESIGN
3783_0.PDF 3783 FLANGE CLOSURE STUD MATERIAL GENERAL APPLICATION TABLE
3784_0.PDF 3784 GRAPHITE COVERED GROOVED METAL (KAMMPROFILE) GASKETS
3785_0.PDF 3785 GRAPHITE COVERED CORRUGATED METAL (CGG) STYLE GASKETS
3786_0.PDF 3786 VERTICAL FLARE
3787_0.XLS 3787 DATA SHEET FOR VERTICAL FLARES
3788_0.PDF 3788 ELECTRICAL DESIGN CRITERIA
3789_0.XLS 3789 DATA SHEET FOR ELECTRICAL DESIGN CRITERIA
3790_0.PDF 3790 ARC FLASH
3791_0.PDF 3791 ARC FLASH ASSESSMENT
3792_0.PDF 3792 LOW-VOLTAGE SWITCH RACKS
3793_0.XLSX 3793 DATA SHEET FOR LOW-VOLTAGE SWITCH RACKS
3794_0.PDF 3794 LOW-VOLTAGE AC AUTOMATIC TRANSFER SWITCH
3795_0.XLSX 3795 DATA SHEET FOR LOW-VOLTAGE AC AUTOMATIC TRANSFER SWITCH
3796_0.XLS 3796 DATA SHEET FOR ELECTRICAL REQUIREMENTS FOR PACKAGED EQ
3797_0.DOCX 3797 ELECTRICAL REQUIREMENTS FOR PACKAGED EQUIPMENT - PREFE
3798_0.PDF 3798 ELECTRIC HEAT TRACING SYSTEMS
3799_0.DOCX 3799 ELECTRIC HEAT TRACE MASTER DOCUMENT
3800_0.XLSX 3800 DATA SHEET FOR 600-VOLT POWER AND CONTROL CABLES
3801_0.PDF 3801 DISTRIBUTED CONTROL SYSTEMS
3802_0.PDF 3802 CEMS ANALYZER SHELTERS
3803_0.PDF 3803 MATERIAL SELECTION GUIDE
3804_0.PDF 3804 MATERIALS SELECTION AND SPECIAL FABRICATION REQUIREMENTS
3805_0.PDF 3805 SUPPLEMENTAL MATERIAL SELECTION REQUIREMENTS FOR METAL
3806_0.PDF 3806 MATERIALS SELECTION FOR PIPING IN AGGRESSIVE SERVICE
3807_0.PDF 3807 WELDING OF PRESSURE EQUIPMENT
3808_0.PDF 3808 WELDING OF PIPING
3809_0.PDF 3809 WELDING OF API-650 TANKS
3810_0.PDF 3810 HARDNESS TESTING REQUIREMENTS
3811_0.PDF 3811 FLANGES, GASKETS, AND BOLTING
3812_0.PDF 3812 EXCHANGER FLANGE WARPAGE FORM
3813_0.PDF 3813 EXCHANGER GASKET TORQUING TAG FORM
3814_0.PDF 3814 EXCHANGER CLEANING TAG FORM
3815_0.PDF 3815 PIPING / PRESSURE VESSEL FLANGE TORQUE FORM
3816_0.PDF 3816 EXCHANGER FLANGE AND GASKET SURFACE WARPAGE INSPECTIO
3817_0.PDF 3817 EXCHANGER FLANGE INSPECTION AND ASSEMBLY PROCEDURE
3818_0.PDF 3818 EXCHANGER FLANGE TORQUE PROCEDURE (MODIFIED STAR PATTE
3819_0.PDF 3819 PIPING FLANGE INSPECTION AND ASSEMBLY PROCEDURE
3820_0.PDF 3820 PIPING STAR PATTERN TORQUE PROCEDURE
3821_0.PDF 3821 HOT AND HALF BOLTING PROCEDURE
3822_0.PDF 3822 PIPING MATERIAL SPECIFICATION GUIDE / SERVICE INDEX
3823_0.PDF 3823 PIPING LINE CLASS DESIGNATOR SYSTEM/LINE SERVICE CODES
3824_0.PDF 3824 DESIGN OF ASME B31.3 METALLIC PIPING SYSTEMS
3825_0.PDF 3825 PIPE SUPPORT CRITERIA FOR ASME B31.3 METALLIC PIPING
3826_0.PDF 3826 SDA UNIT MONITORING
3827_0.PDF 3827 ISOMERIZATION UNIT MONITORING
3828_0.PDF 3828 ULTRAFORMER (CYCLIC REFORMER) CATALYST REGENERATION
3829_0.PDF 3829 VENTS, DRAINS, AND INSTRUMENT CONNECTION DETAILS
3830_0.PDF 3830 PIPE SUPPORTS DETAILS
3831_0.PDF 3831 WAFER VALVE STUD/BOLT FIRE SHIELDS
3832_0.PDF 3832 PIPING FLEXIBILITY ANALYSIS CRITERIA FOR ASME B31.3 METALLIC
3833_0.PDF 3833 KILLED CS, CLASS 150, 0.063" C.A.
3834_0.PDF 3834 KILLED CS, CLASS 150, 0.125" C.A.
3835_0.PDF 3835 KILLED CS, CLASS 150, 0.125" C.A. (ALLOY 20 TRIM, TEFLON PACKI
3836_0.PDF 3836 KILLED CS, CLASS 150, 0.125" C.A. (316 SS NACE TRIM)
3837_0.PDF 3837 KILLED CS, CLASS 300, 0.063" C.A.
3838_0.PDF 3838 KILLED CS, CLASS 300, 0.125" C.A.
3839_0.PDF 3839 KILLED CS, CLASS 300, 0.125" C.A. (ALLOY 20 TRIM, TEFLON PACKI
3840_0.PDF 3840 KILLED CS, CLASS 300, 0.125" C.A. (316 SS NACE TRIM)
3841_0.PDF 3841 KILLED CS, CLASS 600, 0.063" C.A.
3842_0.PDF 3842 KILLED CS, CLASS 600, 0.125" C.A.
3843_0.PDF 3843 KILLED CS, CLASS 900, 0.063" C.A.
3844_0.PDF 3844 KILLED CS, CLASS 900, 0.125" C.A.
3845_0.PDF 3845 KILLED CS, CLASS 1500, 0.063" C.A.
3846_0.PDF 3846 KILLED CS, CLASS 1500, 0.125" C.A.
3847_0.PDF 3847 KILLED AND PWHT CS, CLASS 150, 0.125" C.A. (ALLOY 400 TRIM &
3848_0.PDF 3848 KILLED AND PWHT CS, CLASS 150, 0.125" C.A. (316 SS NACE TRIM)
3849_0.PDF 3849 KILLED AND PWHT CS, CLASS 300, 0.125" C.A. (ALLOY 400 TRIM &
3850_0.PDF 3850 KILLED AND PWHT CS, CLASS 300, 0.125" C.A. (316 SS NACE TRIM)
3851_0.PDF 3851 KILLED AND PWHT CS, CLASS 600, 0.125" C.A. (316 SS NACE TRIM)
3852_0.PDF 3852 KILLED AND PWHT CS, CLASS 900, 0.125" C.A. (316 SS NACE TRIM)
3853_0.PDF 3853 KILLED AND PWHT CS, CLASS 1500, 0.125" C.A. (316 SS NACE TRIM
3854_0.PDF 3854 1¼ CR - ½ MO, CLASS 150, 0.063" C.A.
3855_0.PDF 3855 2¼ CR - 1 MO, CLASS 150, 0.063" C.A.
3856_0.PDF 3856 5 CR - ½ MO, CLASS 150, 0.063" C.A.
3857_0.PDF 3857 9 CR - 1 MO, CLASS 150, 0.063" C.A.
3858_0.PDF 3858 1¼ CR - ½ MO, CLASS 300, 0.063" C.A.
3859_0.PDF 3859 2¼ CR - 1 MO, CLASS 300, 0.063" C.A.
3860_0.PDF 3860 5 CR - ½ MO, CLASS 300, 0.063" C.A.
3861_0.PDF 3861 9 CR - 1 MO, CLASS 300, 0.063" C.A.
3862_0.PDF 3862 1¼ CR - ½ MO, CLASS 600, 0.063" C.A.
3863_0.PDF 3863 2¼ CR - 1 MO, CLASS 600, 0.063" C.A.
3864_0.PDF 3864 5 CR - ½ MO, CLASS 600, 0.063" C.A.
3865_0.PDF 3865 9 CR - 1 MO, CLASS 600, 0.063" C.A.
3866_0.PDF 3866 1¼ CR - ½ MO, CLASS 900, 0.063" C.A.
3867_0.PDF 3867 2¼ CR - 1 MO, CLASS 900, 0.063" C.A.
3868_0.PDF 3868 5 CR - ½ MO, CLASS 900, 0.063" C.A.
3869_0.PDF 3869 9 CR - 1 MO, CLASS 900, 0.063" C.A.
3870_0.PDF 3870 1¼ CR - ½ MO, CLASS 1500, 0.063" C.A.
3871_0.PDF 3871 2¼ CR - 1 MO, CLASS 1500, 0.063" C.A.
3872_0.PDF 3872 5 CR - ½ MO, CLASS 1500, 0.063" C.A.
3873_0.PDF 3873 9 CR - 1 MO, CLASS 1500, 0.063" C.A.
3874_0.PDF 3874 304/304L SS, CLASS 150, 0.000" CA (LUBE AND SEAL OIL SERVICE)
3875_0.PDF 3875 304/304L SS, CLASS 150, 0.000" C.A.
3876_0.PDF 3876 304/304L SS, CLASS 150, 0.063" C.A.
3877_0.PDF 3877 304/304L SS, CLASS 300, 0.000" C.A. (LUBE AND SEAL OIL SERVICE)
3878_0.PDF 3878 304/304L SS, CLASS 300, 0.000" C.A.
3879_0.PDF 3879 304/304L SS, CLASS 300, 0.063" C.A.
3880_0.PDF 3880 304/304L SS, CLASS 600, 0.000" C.A.
3881_0.PDF 3881 304/304L SS, CLASS 900, 0.000" C.A.
3882_0.PDF 3882 304/304L SS, CLASS 1500, 0.000" C.A.
3883_0.PDF 3883 316/316L SS, CLASS 150, 0.000" C.A.
3884_0.PDF 3884 316/316L SS, CLASS 150, 0.000" C.A. (OXYGEN SERVICE)
3885_0.PDF 3885 316/316L SS, CLASS 150, 0.063" C.A.
3886_0.PDF 3886 316/316L SS, CLASS 150, 0.125" C.A.
3887_0.PDF 3887 316/316L SS, CLASS 300, 0.000" C.A.
3888_0.PDF 3888 316/316L SS, CLASS 300, 0.063" C.A.
3889_0.PDF 3889 316/316L SS, CLASS 600, 0.000" C.A.
3890_0.PDF 3890 316/316L SS, CLASS 900, 0.000" C.A.
3891_0.PDF 3891 316/316L SS, CLASS 1500, 0.000" C.A.
3892_0.PDF 3892 317/317L SS, LINE CLASS 150, 0.100" C.A.
3893_0.PDF 3893 317/317L SS, LINE CLASS 300, 0.063" C.A.
3894_0.PDF 3894 321 SS, CLASS 600, 0.000" C.A.
3895_0.PDF 3895 321 SS, CLASS 600, 0.063" C.A.
3896_0.PDF 3896 321 SS, CLASS 900, 0.000" C.A.
3897_0.PDF 3897 321 SS, CLASS 900, 0.063" C.A.
3898_0.PDF 3898 321 SS, CLASS 1500, 0.000" C.A.
3899_0.PDF 3899 321 SS, CLASS 1500, 0.063" C.A.
3900_0.PDF 3900 2205 DUPLEX SS, CLASS 150, 0.063" C.A.
3901_0.PDF 3901 2205 DUPLEX SS, CLASS 300, 0.063" C.A.
3902_0.PDF 3902 2205 DUPLEX SS, CLASS 600, 0.063" C.A.
3903_0.PDF 3903 ALLOY 400, CLASS 150, 0.000" C.A.
3904_0.PDF 3904 ALLOY 400, CLASS 150, 0.000" C.A.
3905_0.PDF 3905 ALLOY 400, CLASS 300, 0.000" C.A.
3906_0.PDF 3906 ALLOY 400, CLASS 300, 0.000" C.A.
3907_0.PDF 3907 ALLOY 20, CLASS 150, 0.000" C.A.
3908_0.PDF 3908 ALLOY 20, CLASS 150, 0.000" C.A.
3909_0.PDF 3909 ALLOY 20, CLASS 300, 0.000" C.A.
3910_0.PDF 3910 ALLOY 20, CLASS 300, 0.000" C.A.
3911_0.PDF 3911 CARBON STEEL, CLASS 150, 0.063" C.A.
3912_0.PDF 3912 CARBON STEEL, CLASS 300, 0.063" C.A.
3913_0.PDF 3913 CARBON STEEL, CLASS 600, 0.063" C.A.
3914_0.PDF 3914 CARBON STEEL, CLASS 900, 0.063" C.A.
3915_0.PDF 3915 CARBON STEEL, CLASS 1500, 0.063" C.A.
3916_0.PDF 3916 CARBON STEEL, GALVANIZED SMALL, CLASS 125, 0.063" C.A.
3917_0.PDF 3917 CARBON STEEL, GALVANIZED SMALL, CLASS 125, 0.125" C.A.
3918_0.PDF 3918 HIGH DENSITY POLYETHYLENE (HDPE) SDR-11/160PSI, 0.000" C.A.
3919_0.PDF 3919 GALVANIZED CARBON STEEL, 250 PSI, 0.000" C.A. - AG UL/FM
3920_0.PDF 3920 HIGH DENSITY POLYETHYLENE (HDPE), FM CL150, 0.000" C.A. (U
3921_0.PDF 3921 HIGH DENSITY POLYETHYLENE (HDPE), FM CL200, 0.000" C.A. (U
3922_0.PDF 3922 HDPE, SDR-11/160 PSI, 0.000" C.A.
3923_0.PDF 3923 VALVE COMMODITY CODES
3924_0.PDF 3924 CARBON STEEL VALVE DESCRIPTIONS
3925_0.PDF 3925 CARBON STEEL GATE VALVE DESCRIPTIONS
3926_0.PDF 3926 CARBON STEEL GLOBE VALVE DESCRIPTIONS
3927_0.PDF 3927 CARBON STEEL CHECK VALVE DESCRIPTIONS
3928_0.PDF 3928 CARBON STEEL BALL VALVE DESCRIPTIONS
3929_0.PDF 3929 CARBON STEEL BUTTERFLY VALVE DESCRIPTIONS
3930_0.PDF 3930 CARBON STEEL PLUG VALVE DESCRIPTIONS
3931_0.PDF 3931 ALLOY STEEL VALVE DESCRIPTIONS
3932_0.PDF 3932 LOW AND INTERMEDIATE ALLOY STEEL GATE VALVE DESCRIPTIONS
3933_0.PDF 3933 LOW AND INTERMEDIATE ALLOY STEEL GLOBE VALVE DESCRIPTION
3934_0.PDF 3934 LOW AND INTERMEDIATE ALLOY STEEL CHECK VALVE DESCRIPTION
3935_0.PDF 3935 STAINLESS STEEL VALVE DESCRIPTIONS
3936_0.PDF 3936 STAINLESS STEEL GATE VALVE DESCRIPTIONS
3937_0.PDF 3937 STAINLESS STEEL GLOBE VALVE DESCRIPTIONS
3938_0.PDF 3938 STAINLESS STEEL CHECK VALVE DESCRIPTIONS
3939_0.PDF 3939 STAINLESS STEEL BALL VALVE DESCRIPTIONS
3940_0.PDF 3940 STAINLESS STEEL BUTTERFLY VALVE DESCRIPTIONS
3941_0.PDF 3941 STAINLESS STEEL PLUG VALVE DESCRIPTIONS
3942_0.PDF 3942 STAINLESS STEEL OTHER VALVE DESCRIPTIONS
3943_0.PDF 3943 NICKEL ALLOY VALVE DESCRIPTIONS
3944_0.PDF 3944 NICKEL AND NICKEL ALLOY GATE VALVE DESCRIPTIONS
3945_0.PDF 3945 NICKEL AND NICKEL ALLOY GLOBE VALVE DESCRIPTIONS
3946_0.PDF 3946 NICKEL AND NICKEL ALLOY CHECK VALVE DESCRIPTIONS
3947_0.PDF 3947 NICKEL AND NICKEL ALLOY BALL VALVE DESCRIPTIONS
3948_0.PDF 3948 NICKEL AND NICKEL ALLOY PLUG VALVE DESCRIPTIONS
3949_0.PDF 3949 NICKEL AND NICKEL ALLOY OTHER VALVE DESCRIPTIONS
3950_0.PDF 3950 BRONZE AND IRON VALVE DESCRIPTIONS
3951_0.PDF 3951 BRONZE AND IRON GATE VALVE DESCRIPTIONS
3952_0.PDF 3952 BRONZE AND IRON GLOBE VALVE DESCRIPTIONS
3953_0.PDF 3953 BRONZE AND IRON CHECK VALVE DESCRIPTIONS
3954_0.PDF 3954 BRONZE AND IRON BALL VALVE DESCRIPTIONS
3955_0.PDF 3955 BRONZE AND IRON BUTTERFLY VALVE DESCRIPTIONS
3956_0.PDF 3956 PLASTIC AND PLASTIC-LINED VALVE DESCRIPTIONS
3957_0.PDF 3957 PLASTIC AND PLASTIC-LINED CHECK VALVE DESCRIPTIONS
3958_0.PDF 3958 PLASTIC AND PLASTIC-LINED BALL VALVE DESCRIPTIONS
3959_0.PDF 3959 PLASTIC AND PLASTIC-LINED BUTTERFLY VALVE DESCRIPTIONS
3960_0.PDF 3960 PLASTIC AND PLASTIC-LINED PLUG VALVE DESCRIPTIONS
3961_0.PDF 3961 PLASTIC AND PLASTIC-LINED OTHER VALVE DESCRIPTIONS
3962_0.PDF 3962 SLIDE VALVES FOR FLUID CATALYTIC CRACKING UNITS
3963_0.PDF 3963 DATA SHEET FOR SLIDE VALVES FOR FLUID CATALYTIC CRACKING UN
3964_0.PDF 3964 PROCUREMENT OF PIPING MATERIALS
3965_0.PDF 3965 PROCUREMENT OF COMMODITY VALVES
3966_0.PDF 3966 CONTROL SYSTEMS SECURITY STANDARDS
3967_0.PDF 3967 MPC CORE SPECIFICATIONS IMPLEMENTATION AT ANDEAVOR HERIT
3968_0.PDF 3968 LIGHTNING SAFETY
3969_0.PDF 3969 GROUNDING LUG DETAIL
3970_0.PDF 3970 LIFTING TRUNNION DETAILS
3971_0.PDF 3971 VESSEL STUDDED JOINTS
3972_0.PDF 3972 COOLING WATER SYSTEM
3973_0.PDF 3973 HF ALKY UNIT MONITORING
3974_0.XLS 3974 EXAMPLE INSPECTION PLAN
3975_0.PDF 3975 INSPECTION PLANNING PROGRAM
3976_1.PDF 3976 OVERSIGHT OF VENDORS/CONTRACTORS PROVIDING NDE SERVICE
3977_1.XLS 3977 SEVERE WET H2S - HYDROCARBONS (LOW TEMPERATURE) W/ OR
3978_0.XLSX 3978 NELSON CURVES FOR SP-95-01
3981_0.PDF 3981 IMPLEMENTATION OF EVALUATION, INSPECTION AND REPAIR REQ
3982_0.XLSX 3982 BALLOT COMMENTS RESOLUTION FORM
3983_0.PDF 3983 BUY/MAKE ANALYSIS
3984_1.PDF 3984 SINGLE STAND
3985_1.PDF 3985 DUAL PEDESTAL
3986_1.PDF 3986 TRIPLE PEDESTAL
3987_0.PDF 3987 LINE MOUNTED - SIDE MOUNT
3988_0.PDF 3988 LINE MOUNTED - TOP MOUNT / VERTICAL PIPE MOUNT
3989_0.PDF 3989 LINE MOUNTED - BOTTOM MOUNT
3990_0.PDF 3990 HANDRAIL MOUNT - SINGLE INSTRUMENT
3991_0.PDF 3991 HANDRAIL MOUNT - DUAL INSTRUMENT
3992_0.PDF 3992 HANDRAIL MOUNT - TRIPLE INSTRUMENT
3993_0.PDF 3993 COLUMN MOUNT - SINGLE INSTRUMENT
3994_0.PDF 3994 COLUMN MOUNT - DUAL INSTRUMENT
3995_0.PDF 3995 STAND - ENCLOSURE
3996_0.PDF 3996 RACK - JUNCTION BOX
3997_0.PDF 3997 PLATFORM BASE MOUNTING
3998_0.PDF 3998 GRADE BASE MOUNTING
3999_0.DOCX 3999 CHECKLIST FOR AUDITING CHEMICAL INJECTION SYSTEMS
4000_0.DOC 4000 INJECTION POINT DATA SHEET
4001_0.DOC 4001 MIXING POINT DATA SHEET
4002_1.PDF 4002 CHEMICAL INJECTION AND PROCESS MIX POINTS
4003_1.PDF 4003 LOPA GAP CLOSURE USING THE ANDEAVOR RISK STANDARD AND
4004_0.PDF 4004 HYDROPROCESSING UNIT MONITORING
4005_0.PDF 4005 ROTATING EQUIPMENT LUBRICATION BEST PRACTICES
4006_1.PDF 4006 TANK BLANKETING
4007_0.PDF 4007 GROUND WELL ASSEMBLY
4008_0.PDF 4008 FENCE POST AND GATE
4009_0.PDF 4009 FIREPROOFED/INSULATED STEEL COLUMN GROUND ASSEMBLY
4010_0.PDF 4010 STEEL COLUMN OR EQUIPMENT GROUND ASSEMBLY
4011_0.PDF 4011 CONCRETE COLUMN RISER GROUND ASSEMBLY
4012_0.PDF 4012 GROUND CONDUCTOR RISER ASSEMBLY
4013_0.PDF 4013 GROUND BUS CONCRETE MOUNT ASSEMBLY
4014_0.PDF 4014 GROUND BUS STEEL COLUMN MOUNT ASSEMBLY
4015_0.PDF 4015 FOUNDATION REBAR/PILING GROUND ASSEMBLY
4016_0.PDF 4016 CARBON CANISTER/TOTE
4017_0.PDF 4017 MOTOR AND CONTROL STATION SUPPORT GROUND ASSEMBLY
4018_0.PDF 4018 VERTICAL VESSEL
4019_0.PDF 4019 ELEVATED HORIZONTAL VESSEL OR EXCHANGER
4020_0.PDF 4020 AIR COOLER/COOLING TOWER MOTOR GROUND ASSEMBLY
4021_0.PDF 4021 EXOTHERMIC GROUND ROD AND CONNECTIONS
4022_0.PDF 4022 MISCELLANEOUS EQUIPMENT, PANEL OR ENCLOSURE
4023_0.PDF 4023 POWER TRANSFORMER, SWITCHGEAR AND MCC
4024_0.PDF 4024 ISOLATED GROUND BUS FLOOR OR WALL MOUNT ASSEMBLY
4025_0.PDF 4025 CONDUIT STUB-UP/TERMINATION BONDING JUMPER
4026_0.PDF 4026 COMPRESSION GROUND ROD AND CONNECTIONS
4027_0.PDF 4027 GROUND TRIAD
4028_0.PDF 4028 STATIC DISCHARGE REEL FIREPROOFED STEEL COLUMN GROUND A
4029_0.PDF 4029 STATIC TRUCK GROUNDING STATION
4030_0.PDF 4030 TRAPEZE SUPPORT
4031_0.PDF 4031 HOLD DOWN/EXPANSION GUIDE CLAMP
4032_0.PDF 4032 BONDING AND GROUNDING
4033_0.PDF 4033 CONDUIT ATTACHMENT AND DROPOUT ASSEMBLY
4034_0.PDF 4034 HORIZONTAL SUPPORT
4035_0.PDF 4035 VERTICAL SUPPORT
4036_0.PDF 4036 EXPANSION, MID-SPAN SPLICE PLATES
4037_0.PDF 4037 TYPICAL PLAN WITH SYMBOLS
4038_0.PDF 4038 CONDUIT ON LADDER
4039_0.PDF 4039 ELECTRICAL EQUIPMENT TYPICAL ENTRY
4040_0.PDF 4040 CONCRETE STUB-UP
4041_0.PDF 4041 CLASS I, DIVISION 1, ARCING/SPARKING/HIGH TEMP INSTRUMENT
4042_0.PDF 4042 CLASS I, DIVISION 1, SEALED ARCING/SPARKING/HIGH TEMP INST
4043_0.PDF 4043 CLASS I, DIVISION 2, ARCING/SPARKING/HIGH TEMP INSTRUMENT
4044_0.PDF 4044 CLASS I, DIVISION 2, SEALED ARCING/SPARKING/HIGH TEMP INST
4045_0.PDF 4045 CONTROL STATION SUPPORT LOCATION
4046_0.PDF 4046 COMBINED POWER & CONTROL ABOVE GROUND STEEL CONDUIT, CLA
4047_0.PDF 4047 COMBINED POWER & CONTROL UNDER GROUND STEEL CONDUIT, CL
4048_0.PDF 4048 SEPARATE POWER & CONTROL ABOVE GROUND STEEL CONDUIT, CLA
4049_0.PDF 4049 SEPARATE POWER & CONTROL UNDER GROUND STEEL CONDUIT, CLA
4050_0.PDF 4050 5KV TYPE MC-HL IN CABLE TRAY & CONTROL IN STEEL CONDUIT, CLA
4051_0.PDF 4051 5KV TYPE MC-HL IN CABLE TRAY & CONTROL IN ALUMINUM CONDUIT
4052_0.PDF 4052 COMBINED POWER & CONTROL ABOVE GROUND ALUMINUM CONDUIT
4053_0.PDF 4053 COMBINED POWER & CONTROL UNDER GROUND ALUMINUM CONDUIT
4054_0.PDF 4054 SEPARATE POWER & CONTROL ABOVE GROUND ALUMINUM CONDUIT,
4055_0.PDF 4055 SEPARATE POWER & CONTROL UNDER GROUND ALUMINUM CONDUIT,
4056_0.PDF 4056 5KV TYPE MC-HL IN CABLE TRAY & CONTROL, RTD, HEATER IN STEEL
4057_0.PDF 4057 5KV TYPE MC-HL IN CABLE TRAY & CONTROL, RTD, HEATER IN ALU
4058_0.PDF 4058 CONTROL STATION/CONDUIT SUPPORT
4059_0.PDF 4059 OPERATED VALVE INSTALLATION, STEEL CONDUIT CLASS 1, DIV 2,
4060_0.PDF 4060 480V TERMINATION
4061_0.PDF 4061 5KV TERMINATION
4062_0.PDF 4062 (2500 AND ABOVE HP) 5KV/15KV TERMINATION
4063_0.PDF 4063 5KV/15KV TERMINATION
4064_0.PDF 4064 SUPPORT ELECTRICAL EQUIPMENT COLUMN SUPPORT
4065_0.PDF 4065 SUPPORT ELECTRICAL EQUIPMENT FREE STANDING
4066_0.PDF 4066 OPERATED VALVE INSTALLATION, ALUMINUM CONDUIT CLASS 1, DI
4067_0.PDF 4067 SEPARATE POWER & CONTROL ABOVE GROUND MC-HL, CLASS 1, DI
4068_0.PDF 4068 COMBINED POWER & CONTROL ABOVE GROUND STEEL CONDUIT, CL
4069_0.PDF 4069 COMBINED POWER & CONTROL UNDER GROUND STEEL CONDUIT, CL
4070_0.PDF 4070 SEPARATE POWER & CONTROL ABOVE GROUND STEEL CONDUIT, CLA
4071_0.PDF 4071 SEPARATE POWER & CONTROL UNDER GROUND STEEL CONDUIT, CLA
4072_0.PDF 4072 5KV TYPE MC-HL IN CABLE TRAY & CONTROL IN STEEL CONDUIT, CLA
4073_0.PDF 4073 5KV TYPE MC-HL IN CABLE TRAY & CONTROL IN ALUMINUM CONDUIT
4074_0.PDF 4074 COMBINED POWER & CONTROL ABOVE GROUND ALUMINUM CONDUIT
4075_0.PDF 4075 COMBINED POWER & CONTROL UNDER GROUND ALUMINUM CONDUI
4076_0.PDF 4076 SEPARATE POWER & CONTROL ABOVE GROUND ALUMINUM CONDUIT
4077_0.PDF 4077 SEPARATE POWER & CONTROL UNDER GROUND ALUMINUM CONDUIT
4078_0.PDF 4078 5KV TYPE MC-HL IN CABLE TRAY & CONTROL, RTD, HEATER IN STEEL
4079_0.PDF 4079 5KV TYPE MC-HL IN CABLE TRAY & CONTROL, RTD, HEATER IN ALU
4080_0.PDF 4080 FIXTURE PENDANT MOUNT, CLASS 1, DIV 1 OR 2 AND UNCLASSIFIE
4081_0.PDF 4081 FIXTURE BRACKET OR CEILING MOUNT ON CONCRETE, CLASS 1, DIV
4082_0.PDF 4082 FIXTURE BRACKET OR CEILING MOUNT ON STEEL, CLASS 1, DIV 1 O
4083_0.PDF 4083 BRACKET OR CEILING MOUNT ON FIREPROOFED STEEL, CLASS 1, DI
4084_0.PDF 4084 BRACKET MOUNTED FLOODLIGHT, STEEL, CONCRETE OR FIREPROOF
4085_0.PDF 4085 POLE MOUNTED FLOODLIGHT, CLASS 1, DIV 2 OR UNCLASSIFIED
4086_0.PDF 4086 FIXTURE HANDRAIL STANCHION MOUNT, RIGID CONDUIT, CLASS 1,
4087_0.PDF 4087 FIXTURE HANDRAIL STANCHION MOUNT, V-SPRING, CLASS 1, DIV 2
4088_0.PDF 4088 FIXTURE HANDRAIL STANCHION MOUNT, SWIVELPOLE, CLASS 1, DI
4089_0.PDF 4089 MOUNT ON COLUMN, CLASS 1, DIV 1 OR 2 AND UNCLASSIFIED
4090_0.PDF 4090 MOUNT ON HANDRAIL, CLASS 1, DIV 2 AND UNCLASSIFIED
4091_0.PDF 4091 MOUNT ON PLATFORM, CLASS 1, DIV 1 OR 2 AND UNCLASSIFIED
4092_0.PDF 4092 TRANSFORMER/PANELBOARD TYPICAL WIRING DIAGRAM
4093_0.PDF 4093 COLUMN MOUNT TRANSFORMER/PANELBOARD, CLASS 1, DIVISION
4094_0.PDF 4094 COLUMN MOUNT TRANSFORMER/PANELBOARD, CLASS 1, DIVISIO
4095_0.PDF 4095 SUPPORTS COLUMN MOUNT TRANSFORMER
4096_0.PDF 4096 DUCT BANKS, FLUSH STUB UP
4097_0.PDF 4097 DUCT BANKS, REINFORCED
4098_0.PDF 4098 DUCT BANKS, NON-REINFORCED
4099_3.PDF 4099 TANK MICROBIAL MANAGEMENT PROGRAM
4100_0.PDF 4100 ELECTRICAL ASSEMBLY THERMOCOUPLE
4101_1.PDF 4101 ELECTRICAL ASSEMBLY 2 T/C WITH TRANSMITTER
4102_0.PDF 4102 D/P LEVEL W/ ROD OUT
4103_1.PDF 4103 D/P W/ STEAM TRACE & ROD OUT
4104_1.PDF 4104 CAPILLARY/SEAL
4105_1.PDF 4105 D/P LIQUID - ELEC. TRACE
4106_1.PDF 4106 GUIDED WAVE RADAR IN CHAMBER
4107_1.PDF 4107 MAGNETIC LEVEL GAUGE WITH OR WITHOUT TRANSMITTER
4108_1.PDF 4108 ASCO PANEL - AIR ASSEMBLY
4109_0.PDF 4109 AIR ASSEMBLY
4110_0.PDF 4110 ENHANCED INSPECTION OF MAIN AND TRACE HYDROFLUORIC (HF)
4111_0.PDF 4111 TRICONEX PROGRAMMING ACCESS SECURITY REQUIREMENTS
4112_0.PDF 4112 SULFURIC ACID ADDITIVE SYSTEMS
4113_0.DOC 4113 SULFURIC ACID ADDITIVE SYSTEM DATASHEET
4114_0.PDF 4114 PRESSURE GAUGE LINE MOUNTED LIQUID OR VAPOR
4115_1.PDF 4115 PRESSURE GAUGE LINE MOUNTED WITH SIPHON
4116_1.PDF 4116 PRESSURE GAUGE LINE MOUNTED WITH PULSATION DAMPENER
4117_1.PDF 4117 PRESSURE GAUGE LINE MOUNTED WITH SIPHON AND PULSATION
4118_1.PDF 4118 PRESSURE GAUGE LINE MOUNTED WITH DIAPHRAGM SEAL
4119_1.PDF 4119 PRESSURE - VAPOR
4120_1.PDF 4120 PRESSURE - LIQUID - LINE MOUNT
4121_1.PDF 4121 PRESSURE - LIQUID - REMOTE MOUNT
4122_1.PDF 4122 PRESSURE - SEAL WITH CAPILLARY
4123_0.PDF 4123 PRESSURE - LIQUID OR STEAM - STEAM TRACED - LINE MOUNT -
4124_0.PDF 4124 PRESSURE - LIQUID OR STEAM - STEAM TRACED - REMOTE MOUNT
4125_0.PDF 4125 PRESSURE - LIQUID OR STEAM - STEAM TRACED - LINE MOUNT
4126_0.PDF 4126 D/P VAPOR - REMOTE MOUNT - ROD-OUT
4127_0.PDF 4127 D/P STEAM OR LIQUID
4128_0.PDF 4128 D/P STEAM OR LIQUID - STEAM TRACED
4129_1.PDF 4129 D/P WITH SEAL AND CAPILLARY
4130_0.PDF 4130 D/P VAPOR INDICATOR
4131_0.PDF 4131 D/P LIQUID INDICATOR
4132_1.PDF 4132 PRESSURE GAUGE DRAFT REMOTE MOUNTED
4133_1.PDF 4133 PRESSURE GAUGE ACROSS FILTERS - GAS
4134_1.PDF 4134 PRESSURE GAUGE ACROSS FILTERS - LIQUID
4135_0.PDF 4135 PRESSURE GAUGE ON LEVEL BRIDLE
4136_0.PDF 4136 PRESSURE GAUGE WITH SEAL & CAPILLARY
4137_0.PDF 4137 PRESSURE GAUGE GAS REMOTE MOUNTED
4138_1.PDF 4138 PRESSURE TRANSMITTER VAPOR WITH GAUGE
4139_1.PDF 4139 PRESSURE TRANSMITTER VAPOR W/ STEAM TRACE
4140_0.PDF 4140 PRESSURE TRANSMITTER LIQUID ELEC TRACE W/ GAUGE
4141_1.PDF 4141 PRESSURE TRANSMITTER VAPOR ELECTRIC TRACE
4142_1.PDF 4142 PRESSURE TRANSMITTER LIQUID ELEC TRACE
4143_0.PDF 4143 D/P LIQUID ELEC TRACE
4144_1.PDF 4144 D/P GAS ELEC TRACE
4145_0.PDF 4145 D/P GAS STEAM TRACE
4146_0.PDF 4146 FLOW GAS OR VAPOR D/P LINE OR REMOTE MOUNT
4147_0.PDF 4147 FLOW LIQUID D/P LINE OR REMOTE MOUNT WITH ROD-OUT
4148_1.PDF 4148 FLOW GAS OR VAPOR D/P LINE OR REMOTE MOUNT WITH STEAM
4149_1.PDF 4149 FLOW LIQUID D/P LINE OR REMOTE MOUNT WITH STEAM TRACE
4150_0.PDF 4150 FLOW D/P DUAL TRANSMITTERS LIQUID WITH ROD-OUT
4151_0.PDF 4151 FLOW D/P DUAL TRANSMITTERS LIQUID WITH STEAM TRACE & RO
4152_0.PDF 4152 FLOW PITOT TUBE GAS
4153_0.PDF 4153 FLOW PITOT TUBE LIQUID
4154_1.PDF 4154 FLOW VENTURI VAPOR SERVICE
4155_1.PDF 4155 FLOW WEDGE WITH DIAPHRAGM SEAL AND CAPILLARY
4156_0.PDF 4156 FLOW LIQUID DP ELECTRIC TRACED
4157_1.PDF 4157 FLOW GAS DP ELECTRIC TRACE
4158_0.PDF 4158 FLOW GAS DP DUAL TRANSMITTERS
4159_1.PDF 4159 FLOW GAS DP DUAL TRANSMITTERS - ELECTRIC TRACE
4160_1.PDF 4160 FLOW LIQUID DP DUAL TRANSMITTERS - ELECTRIC TRACE
4161_1.PDF 4161 FLOW LIQUID DP CAPILLARY
4162_0.PDF 4162 STEAM TRACING AND TRAPS PROGRAM
4163_0.PPTX 4163 EXAMPLE SAMPLING PRESENTATION
4164_0.PPTX 4164 LPG PROGRAM STANDARDIZATION PRESENTATION
4165_0.DOC 4165 EXAMPLE WORK INSTRUCTION CONCERNING LDAR
4166_0.PDF 4166 EXAMPLE SAMPLE STATION AUDIT REPORT #1
4167_0.PDF 4167 EXAMPLE SAMPLE STATION AUDIT REPORT #2
4168_2.XLSX 4168 SAMPLE STATION AUDIT FORM
4169_0.PDF 4169 REFINING PPM CAPITAL AFE GUIDELINES
4170_0.XLSX 4170 SPP PIPING CROSS REFERENCE
4171_1.PDF 4171 PROJECT QUALITY ASSURANCE (PQA) PROCESS
4172_0.PDF 4172 PROJECT REQUEST FORM AND CHARTER REVIEW
4173_0.PDF 4173 PROJECT BUSINESS CASE/BEAM AND SCOPE REVIEW
4174_0.PDF 4174 ALIGNMENT THERMOMETER CHECK
4175_0.PDF 4175 PHASE DELIVERABLE REVIEW
4176_0.PDF 4176 PROJECT DEFINITION RATING INDEX
4177_0.PDF 4177 INDEPENDENT PROJECT ANALYSIS (IPA) REVIEW
4178_0.XLS 4178 ANDEAVOR PIPING CROSS REFERENCE
4179_0.DOCX 4179 PERMIT STRATEGY DOCUMENT TEMPLATE
4180_0.PDF 4180 PERMIT STRATEGY GUIDELINES FOR SIGNIFICANT REFINERY PROJEC
4181_0.XLS 4181 FIELD TEST RECORD INSTRUMENT TUBING PRESSURE TEST
4182_0.DOC 4182 INSTRUMENT AIR PIPE TEST
4183_0.XLS 4183 FACTORY ACCEPTANCE TEST - ELECTRICAL CHECKOUT
4184_0.XLS 4184 FACTORY ACCEPTANCE TEST - HARDWARE INSPECTION CHECKOUT
4185_0.PDF 4185 PROCESS DESIGN BASIS DOCUMENT GUIDELINES
4186_0.PDF 4186 PROCESS DESIGN REPORT GUIDELINES
4187_0.PDF 4187 VESSEL DESIGN AND RATING
4188_0.PDF 4188 STEAM CONDENSATE RECOVERY PROCESS DESIGN GUIDELINES
4189_0.PDF 4189 BENTLY NEVADA 1900/65A RECIP VIBRATION PROTECTION
spec_no sub_class field_description
SP-00-12 CIVIL/STRUCTURAL Civil and Structural
SP-50-03 PIPING Piping & Plant Layout
SP-50-03-A2 COMMON Piping & Plant Layout
SP-50-03-A2FU ALKY Piping & Plant Layout
SP-50-03-A2H HC W/ H2 Piping & Plant Layout
SP-50-03-A2J MISC Piping & Plant Layout
SP-50-03-A4 COMMON Piping & Plant Layout
SP-50-03-AD2 HI TEMP Piping & Plant Layout
SP-50-03-AE2 HI TEMP Piping & Plant Layout
SP-50-03-A3G AMINE Piping & Plant Layout
SP-50-03-A2PU CATALYST Piping & Plant Layout
SP-50-03-AK2 LOW TEMP Piping & Plant Layout
SP-50-03-APC MISC Piping & Plant Layout
SP-50-03-AR1 HC W/ H2 Piping & Plant Layout
SP-50-03-AT1 HC W/ H2 Piping & Plant Layout
SP-50-03-AX1 SULFURIC ACID Piping & Plant Layout
SP-50-03-AY1 HI TEMP Piping & Plant Layout
SP-50-03-C2 COMMON Piping & Plant Layout
SP-50-03-C2FU ALKY Piping & Plant Layout
SP-50-03-C2H HC W/ H2 Piping & Plant Layout
SP-50-03-C2LPG LPG Piping & Plant Layout
SP-50-03-C4 COMMON Piping & Plant Layout
SP-50-03-C4AS SIMPLE WET H2S Piping & Plant Layout
SP-50-03-CB2 HI TEMP Piping & Plant Layout
SP-50-03-CD2 HI TEMP Piping & Plant Layout
SP-50-03-CE2 HI TEMP Piping & Plant Layout
SP-50-03-C3G AMINE Piping & Plant Layout
SP-50-03-CH2F ALKY Piping & Plant Layout
SP-50-03-CH2FU ALKY Piping & Plant Layout
SP-50-03-C2PU CATALYST Piping & Plant Layout
SP-50-03-CK2 LOW TEMP Piping & Plant Layout
SP-50-03-CM2U ALKY Piping & Plant Layout
SP-50-03-CR1 HC W/ H2 Piping & Plant Layout
SP-50-03-F2 COMMON Piping & Plant Layout
SP-50-03-F2H HC W/ H2 Piping & Plant Layout
SP-50-03-FB2 HI TEMP Piping & Plant Layout
SP-50-03-FD3 HI TEMP Piping & Plant Layout
SP-50-03-FE2 HI TEMP Piping & Plant Layout
SP-50-03-F3G AMINE Piping & Plant Layout
SP-50-03-FR1 HC W/ H2 Piping & Plant Layout
SP-50-03-FW1 HI TEMP Piping & Plant Layout
SP-50-03-GD2 HI TEMP Piping & Plant Layout
SP-50-03-H2H HC W/ H2 Piping & Plant Layout
SP-50-03-K2U SEWERS AND DRAINS Piping & Plant Layout
SP-50-03-K3U SEWERS AND DRAINS Piping & Plant Layout
SP-50-03-KPDU SEWERS AND DRAINS Piping & Plant Layout
SP-50-03-KPCU2 ALKY Piping & Plant Layout
SP-50-03-L2 UTILITIES Piping & Plant Layout
SP-50-03-LB2 UTILITIES Piping & Plant Layout
SP-50-03-LGR1 UTILITIES Piping & Plant Layout
SP-50-03-N2 STEAM Piping & Plant Layout
SP-50-03-N2AA STEAM Piping & Plant Layout
SP-50-03-R2 STEAM Piping & Plant Layout
SP-50-03-R2AA STEAM Piping & Plant Layout
SP-50-03-S2AA STEAM Piping & Plant Layout
SP-50-03-SB2AA STEAM Piping & Plant Layout
SP-50-03-Y1 STEAM TRACING Piping & Plant Layout
SP-50-01 EQUIP LAYOUT Piping & Plant Layout
SP-50-02 PIPING Piping & Plant Layout
SP-50-07 PIPING Piping & Plant Layout
SP-50-09 INSPECTION Inspection and Quality Control
SP-50-11 PIPING Piping & Plant Layout
SP-50-12 PIPING Piping & Plant Layout
SP-50-13 PIPING Piping & Plant Layout
SP-50-24 WELDING Materials and Welding
SP-50-32 PIPING Piping & Plant Layout
SP-50-33 VALVES Piping & Plant Layout
SP-50-34 PIPING Piping & Plant Layout
SP-50-51 PIPING Piping & Plant Layout
SP-00-13 CIVIL/STRUCTURAL Civil and Structural
SP-00-14 CIVIL/STRUCTURAL Civil and Structural
SP-00-15 CIVIL/STRUCTURAL Civil and Structural
SP-00-16 CIVIL/STRUCTURAL Civil and Structural
SP-00-17 CIVIL/STRUCTURAL Civil and Structural
SP-00-18 CIVIL/STRUCTURAL Civil and Structural
SP-00-19 CIVIL/STRUCTURAL Civil and Structural
SP-40-01 SAFETY Safety
SP-40-02 SPARE PARTS Miscellaneous
SP-42-01 PRESSURE VESSELS Fixed Equipment
SP-42-05 PRESSURE VESSELS Fixed Equipment
SP-42-06 PRESSURE VESSELS Fixed Equipment
SP-42-16 REFRACTORY Fixed Equipment
SP-42-18 TANK Fixed Equipment
SP-42-18.1 TANK Fixed Equipment
SP-42-18.2 TANK Fixed Equipment
SP-42-18.3 TANK Fixed Equipment
SP-42-18.4 TANK Fixed Equipment
SP-42-18.5 TANK Fixed Equipment
SP-43-03 ROTATING EQUIPMENT Rotating Equipment
SP-43-04 COMPRESSOR Rotating Equipment
SP-43-05 COMPRESSOR Rotating Equipment
SP-43-08 FANS Rotating Equipment
SP-44-01 FIXED EQUIPMENT Fixed Equipment
SP-44-02 FIXED EQUIPMENT Fixed Equipment
SP-45-01 FIRED HEATERS Fixed Equipment
SP-46-01 PUMPS Rotating Equipment
SP-46-02 PUMPS Rotating Equipment
SP-46-03 ROTATING EQUIPMENT Rotating Equipment
SP-46-07 ROTATING EQUIPMENT Rotating Equipment
SP-60-02 ELECTRICAL Electrical Systems
RSP-1161-010 ELECTRICAL Electrical Systems
SP-60-17 ELECTRICAL Electrical Systems
SP-60-19 ELECTRICAL Electrical Systems
SP-70-01 INSTRUMENTATION Instrumentation
SP-70-16 INSTRUMENTATION Instrumentation
SP-95-01 MATERIAL SELECTION Materials and Welding
SP-99-06 MATERIAL SELECTION Materials and Welding
SP-30-29-GV NULL Civil and Structural
SP-42-18.6 TANK Fixed Equipment
SP-50-04.1 PIPING Piping & Plant Layout
SP-50-10 VALVES Piping & Plant Layout
SP-50-38 PIPING Piping & Plant Layout
SP-50-01.5 LAYOUT OF EQUIP Piping & Plant Layout
RSP-1135-LPG PROCESS DESIGN Fixed Equipment
SP-50-05 PROCESS DESIGN Piping & Plant Layout
RSP-1121-010 SAFETY Safety
RSP-1122-000 QUALITY Safety
RSP-1124-000 FIRE PROTECTION Safety
RSP-1129-010 HF ALKY Safety
RSP-1129-030 HF ALKY Safety
RSP-1129-040 HF ALKY Safety
REF-1051-WRSP DOCUMENT CONTROL Standard Practice
RSP-1172-020 SIS Instrumentation
RSP-1172-022 SIS Instrumentation
RSP-1172-024 SIS Instrumentation
RSP-1172-025 SIS Instrumentation
RSP-1172-021 SIS Instrumentation
RSP-1171-010 PROCESS DESIGN Instrumentation
RRD-1901-000 PROJECTS Miscellaneous
RRD-1190-031 HEAT TREATMENT Materials and Welding
SP-30-29-RB NULL Safety
RSP-1100-001 TAR Miscellaneous
SP-60-07 ELECTRICAL Electrical Systems
SP-60-09 ELECTRICAL Electrical Systems
SP-60-10 ELECTRICAL Electrical Systems
SP-60-11 ELECTRICAL Electrical Systems
SP-60-12 ELECTRICAL Electrical Systems
SP-60-16 ELECTRICAL Electrical Systems
SP-60-18 ELECTRICAL Electrical Systems
SP-60-20 ELECTRICAL Electrical Systems
SP-60-21 ELECTRICAL Electrical Systems
SP-60-22 ELECTRICAL Electrical Systems
SP-60-23 ELECTRICAL Electrical Systems
SP-60-34 ELECTRICAL Electrical Systems
SP-60-30 ELECTRICAL Electrical Systems
SP-60-31 ELECTRICAL Electrical Systems
SP-60-32 ELECTRICAL Electrical Systems
SP-60-35 ELECTRICAL Electrical Systems
SP-60-38 ELECTRICAL Electrical Systems
SP-M-60-39 ELECTRICAL Electrical Systems
SP-60-27 ELECTRICAL Electrical Systems
SP-43-05.2 COMPRESSOR Rotating Equipment
SP-43-05.4 COMPRESSOR Rotating Equipment
SP-43-05.5 COMPRESSOR Rotating Equipment
SP-43-05.6 COMPRESSOR Rotating Equipment
SP-70-26 INSTRUMENTATION Instrumentation
RRD-1323-000 OPERATIONS Safety
SP-50-18 PIPING Piping & Plant Layout
SP-50-19 PIPING Piping & Plant Layout
SP-90-20 INSPECTION Inspection and Quality Control
SP-90-30 INSPECTION Inspection and Quality Control
RRD-1230-042 PROCESS DESIGN Fixed Equipment
RRD-1108-010 CATALYST Miscellaneous
RSP-1503-010 QUALITY Product Quality
SP-70-03 INSTRUMENTATION Instrumentation
RRD-1177-010 UTILITIES Fixed Equipment
SP-50-03-AT1X OXYGEN Piping & Plant Layout
SP-50-03-C2X OXYGEN Piping & Plant Layout
SP-50-03-CM1X OXYGEN Piping & Plant Layout
SP-50-03-CT1X OXYGEN Piping & Plant Layout
SP-43-15 ROTATING EQUIPMENT Rotating Equipment
RSD-50-00-04 DUMMY SUPPORT Piping & Plant Layout
RSD-50-00-05 GENERAL PIPING Piping & Plant Layout
RSD-50-00-06 GENERAL PIPING Piping & Plant Layout
RSD-50-00-02 GENERAL PIPING Piping & Plant Layout
SP-42-05-DS PRESSURE VESSELS Fixed Equipment
SP-70-09 INSTRUMENTATION Instrumentation
SP-70-05 INSTRUMENTATION Instrumentation
RSP-1127-000 SAFETY Safety
SP-60-29 ELECTRICAL Electrical Systems
RSP-1600-000 PLANNING Miscellaneous
RSP-1128-000 SAFETY Safety
SP-90-10 INSPECTION Inspection and Quality Control
RSP-1501-000 QUALITY Product Quality
RSP-1501-020 QUALITY Product Quality
RSP-1501-010 QUALITY Product Quality
RSP-1121-020 SAFETY Safety
SP-99-13 DAMAGE MECHANISM Materials and Welding
REF-1051 DOCUMENT CONTROL Standard Practice
RSP-1610-001 PLANNING Product Quality
RRD-1920-000 PROJECTS Miscellaneous
RRD-1921-000 PROJECTS Miscellaneous
SP-43-06 BLOWERS Rotating Equipment
RSP-1710-001 RAIL Safety
RSP-1710-002 RAIL Safety
RSP-1710-001-PRTC RAIL Safety
RSP-1710-001-GSTC RAIL Safety
SP-M-43-10 COMPRESSOR Rotating Equipment
SP-43-10-FORM COMPRESSOR Rotating Equipment
SP-90-00 INSPECTION Inspection and Quality Control
SP-50-26 PIPING Piping & Plant Layout
SP-50-29 ROTATING EQUIPMENT Rotating Equipment
SP-99-08 MATERIAL SELECTION Materials and Welding
RSP-1100-001-FORM02 TAR Miscellaneous
RSP-1100-001-FORM04 TAR Miscellaneous
RSP-1100-001-FORM03 TAR Miscellaneous
RSP-1100-001-FORM01 TAR Miscellaneous
RSP-1100-001-FORM07 TAR Miscellaneous
RSP-1100-001-FORM06 TAR Miscellaneous
RSP-1100-001-FORM15 TAR Miscellaneous
RSP-1100-001-FORM05 TAR Miscellaneous
RSP-1100-001-FORM17 TAR Miscellaneous
RSP-1100-001-FORM13 TAR Miscellaneous
RSP-1100-001-FORM11 TAR Miscellaneous
RSP-1100-001-FORM10 TAR Miscellaneous
RSP-1100-001-FORM12 TAR Miscellaneous
SP-30-02-3-TC NULL Environmental and Utility Equipment
RSP-1172-010 INSTRUMENTATION Instrumentation
RSP-1173-010 CONTROLS Instrumentation
RSP-1130-000-EEWSE SAFETY Safety
RSP-1901-AFE PROJECTS Miscellaneous
RSP-1139-010 FIRED HEATERS Instrumentation
RSP-1502-001 QUALITY Product Quality
RSP-1201-005 HF ALKY Safety
REF-1051-SCR DOCUMENT CONTROL Standard Practice
RSP-1200-000-FORM1 CATALYST Inspection and Quality Control
RSP-1200-000-FORM2 CATALYST Inspection and Quality Control
TDS-6-101 NULL Electrical Systems
TDS-6-102 NULL Electrical Systems
TDS-6-103 NULL Electrical Systems
TDS-6-104 NULL Electrical Systems
TDS-6-105 NULL Electrical Systems
TDS-6-106 NULL Electrical Systems
TDS-6-107 NULL Electrical Systems
TDS-6-108 NULL Electrical Systems
TDS-6-109 NULL Electrical Systems
TDS-6-110 NULL Electrical Systems
TDS-6-111 NULL Electrical Systems
TDS-6-112 NULL Electrical Systems
TDS-6-113 NULL Electrical Systems
TDS-6-114 NULL Electrical Systems
TDS-6-115 NULL Electrical Systems
TDS-6-116 NULL Electrical Systems
TDS-6-117 NULL Electrical Systems
TDS-6-118 NULL Electrical Systems
TDS-6-119 NULL Electrical Systems
TDS-6-120 NULL Electrical Systems
TDS-6-121 NULL Electrical Systems
TDS-6-122 NULL Electrical Systems
TDS-6-123 NULL Electrical Systems
TDS-6-124 NULL Electrical Systems
TDS-6-125 NULL Electrical Systems
TDS-6-126 NULL Electrical Systems
TDS-6-127 NULL Electrical Systems
TDS-6-128 NULL Electrical Systems
TDS-6-129 NULL Electrical Systems
TDS-6-130 NULL Electrical Systems
TDS-6-131 NULL Electrical Systems
TDS-6-132 NULL Electrical Systems
TDS-6-133 NULL Electrical Systems
TDS-6-134 NULL Electrical Systems
TDS-6-135 NULL Electrical Systems
TDS-6-136 NULL Electrical Systems
TDS-6-137 NULL Electrical Systems
TDS-6-139 NULL Electrical Systems
TDS-6-140 NULL Electrical Systems
TDS-6-141 NULL Electrical Systems
TDS-6-142 NULL Electrical Systems
TDS-6-143 NULL Electrical Systems
TDS-6-145 NULL Electrical Systems
TDS-6-148 NULL Electrical Systems
TDS-6-149 NULL Electrical Systems
TDS-6-150 NULL Electrical Systems
TDS-6-151 NULL Electrical Systems
TDS-6-152 NULL Electrical Systems
TDS-6-153 NULL Electrical Systems
TDS-6-154 NULL Electrical Systems
TDS-6-155 NULL Electrical Systems
TDS-6-156 NULL Electrical Systems
TDS-6-157 NULL Electrical Systems
TDS-6-158 NULL Electrical Systems
TDS-6-159 NULL Electrical Systems
TDS-6-160 NULL Electrical Systems
TDS-6-161 NULL Electrical Systems
TDS-6-162 NULL Electrical Systems
TDS-6-163 NULL Electrical Systems
TDS-6-164 NULL Electrical Systems
TDS-6-165 NULL Electrical Systems
TDS-6-167 NULL Electrical Systems
TDS-6-168 NULL Electrical Systems
TDS-6-169 NULL Electrical Systems
TDS-6-170 NULL Electrical Systems
TDS-6-172 NULL Electrical Systems
TDS-6-173 NULL Electrical Systems
TDS-6-174 NULL Electrical Systems
TDS-6-175 NULL Electrical Systems
TDS-6-176 NULL Electrical Systems
TDS-6-177 NULL Electrical Systems
TDS-6-178 NULL Electrical Systems
TDS-6-182 NULL Electrical Systems
TDS-6-200 NULL Electrical Systems
TDS-6-209 NULL Electrical Systems
TDS-7-001 NULL Instrumentation
TDS-7-002 NULL Instrumentation
TDS-7-003 NULL Instrumentation
TDS-7-004 NULL Instrumentation
TDS-7-005 NULL Instrumentation
TDS-7-006 NULL Instrumentation
TDS-7-007 NULL Instrumentation
TDS-7-008 NULL Instrumentation
TDS-7-009 NULL Instrumentation
TDS-7-010 NULL Instrumentation
TDS-7-011 NULL Instrumentation
TDS-7-012 NULL Instrumentation
TDS-7-013 NULL Instrumentation
TDS-7-014 NULL Instrumentation
TDS-7-015 NULL Instrumentation
TDS-7-016 NULL Instrumentation
TDS-7-017 NULL Instrumentation
TDS-7-018 NULL Instrumentation
TDS-7-019 NULL Instrumentation
TDS-7-020 NULL Instrumentation
TDS-7-021 NULL Instrumentation
TDS-7-022 NULL Instrumentation
TDS-7-023 NULL Instrumentation
TDS-7-024 NULL Instrumentation
TDS-7-025 NULL Instrumentation
TDS-7-026 NULL Instrumentation
TDS-7-027 NULL Instrumentation
TDS-7-028 NULL Instrumentation
TDS-7-029 NULL Instrumentation
TDS-7-030 NULL Instrumentation
TDS-7-031 NULL Instrumentation
TDS-7-032 NULL Instrumentation
TDS-7-033 NULL Instrumentation
TDS-7-034 NULL Instrumentation
TDS-7-041 NULL Instrumentation
TDS-7-044 NULL Instrumentation
TDS-7-271 NULL Instrumentation
TDS-7-272 NULL Instrumentation
TDS-7-273 NULL Instrumentation
TDS-7-274 NULL Instrumentation
TDS-7-275 NULL Instrumentation
TDS-7-276 NULL Instrumentation
TDS-7-277 NULL Instrumentation
TDS-7-278 NULL Instrumentation
TDS-7-279 NULL Instrumentation
TDS-7-280 NULL Instrumentation
TDS-7-281 NULL Instrumentation
TDS-7-282 NULL Instrumentation
TDS-7-283 NULL Instrumentation
TDS-7-284 NULL Instrumentation
TDS-7-285 NULL Instrumentation
TDS-7-286 NULL Instrumentation
TDS-7-287 NULL Instrumentation
TDS-7-288 NULL Instrumentation
TDS-7-289 NULL Instrumentation
TDS-7-290 NULL Instrumentation
TDS-7-290A NULL Instrumentation
TDS-7-291 NULL Instrumentation
TDS-7-292 NULL Instrumentation
TDS-7-293 NULL Instrumentation
TDS-7-294 NULL Instrumentation
TDS-7-295 NULL Instrumentation
TDS-7-296 NULL Instrumentation
TDS-7-296A NULL Instrumentation
TDS-7-297 NULL Instrumentation
TDS-7-298 NULL Instrumentation
TDS-7-299 NULL Instrumentation
TDS-7-300 NULL Instrumentation
TDS-7-301 NULL Instrumentation
TDS-7-302 NULL Instrumentation
TDS-7-303 NULL Instrumentation
TDS-7-304 NULL Instrumentation
TDS-7-305 NULL Instrumentation
TDS-7-306 NULL Instrumentation
TDS-7-307 NULL Instrumentation
TDS-7-308 NULL Instrumentation
TDS-7-309 NULL Instrumentation
TDS-7-310 NULL Instrumentation
TDS-7-311 NULL Instrumentation
TDS-7-312 NULL Instrumentation
TDS-7-313 NULL Instrumentation
TDS-7-314 NULL Instrumentation
TDS-7-315 NULL Instrumentation
TDS-7-316 NULL Instrumentation
TDS-7-317 NULL Instrumentation
TDS-7-318 NULL Instrumentation
TDS-7-319 NULL Instrumentation
TDS-7-320 NULL Instrumentation
TDS-7-321 NULL Instrumentation
RSP-1200-000 CATALYST Inspection and Quality Control
RSP-1171-010-EIVWS PROCESS DESIGN Instrumentation
TDS-7-322 NULL Instrumentation
RSP-1173-ANASIG CONTROLS Instrumentation
RSP-1173-DISSIG CONTROLS Instrumentation
SP-50-03-CM2S ALKY Piping & Plant Layout
RSP-1305 PSM/RMP Safety
REF-1051-WRCS DOCUMENT CONTROL Standard Practice
RSP-1301 PSM/RMP Safety
RSD-50-00-01 GENERAL PIPING Piping & Plant Layout
RSP-1307 PSM/RMP Safety
RSP-1307-CHECKLIST PSM/RMP Safety
RSP-1304 PSM/RMP Safety
RSP-1307-EMOC-FORM PSM/RMP Safety
RSP-1220-NCCW PLANNING Product Quality
RSP-1220-000 PLANNING Product Quality
RSP-1313 PSM/RMP Safety
TDS-7-323 NULL Instrumentation
TDS-7-324 NULL Instrumentation
TDS-7-325 NULL Instrumentation
TDS-7-326 NULL Instrumentation
TDS-6-203 NULL Electrical Systems
TDS-6-205 NULL Electrical Systems
TDS-6-206 NULL Electrical Systems
TDS-6-207 NULL Electrical Systems
TDS-9-001 NULL Piping & Plant Layout
RSP-1503-020 QUALITY Product Quality
RSP-1303 PSM/RMP Safety
RSP-1302 PSM/RMP Safety
RSP-1308 PSM/RMP Safety
RSP-1303-PHARPTCKLST PSM/RMP Safety
RSP-1303-RECOMLST PSM/RMP Safety
RSP-1303-ENVPROCKLSTPSM/RMP Safety
RSP-1303-REVALCKLST PSM/RMP Safety
RSP-1303-HUMFACCKLSTPSM/RMP Safety
RSP-1303-FACSTACKLST PSM/RMP Safety
SP-10-06 FIREPROOFING Protective Coatings
RSP-1129-005-CHKLST HF ALKY Safety
RSP-1306 PSM/RMP Safety
RSP-1311 PSM/RMP Safety
RSP-1309 PSM/RMP Safety
RSP-1312 PSM/RMP Safety
RSP-1310 PSM/RMP Safety
RSP-1903-000-ATT1 PROJECTS Miscellaneous
RSP-1801-001-AUDIT LAB Miscellaneous
RSP-1801-001-CHKLST LAB Miscellaneous
SP-40-01-DATASHT SAFETY Safety
RSP-1701-000 SAFETY Safety
RSP-1129-005 HF ALKY Safety
RSP-1903-000 PROJECTS Miscellaneous
REF-1054 SAFETY Safety
RSP-1700-000 SAFETY Safety
RSP-1801-001 LAB Miscellaneous
RSP-1565-000-PVFAML AML Product Quality
RSP-1713-000 SAFETY Safety
SP-50-38-FORM PIPING Piping & Plant Layout
_SP-50-03-INDEX INDEX Piping & Plant Layout
TDS-7-327 NULL Instrumentation
TDS-7-328 NULL Piping & Plant Layout
RSP-1503-000 QUALITY Product Quality
SP-90-00-REQ INSPECTION Inspection and Quality Control
RSP-1710-002-NEWEM RAIL Safety
RSD-1172-024-01 MISC Instrumentation
RSD-1172-024-02 MISC Instrumentation
RSD-1172-024-03 MISC Instrumentation
RSD-1172-024-04 MISC Instrumentation
RSD-1172-024-05 MISC Instrumentation
RSD-1172-024-06 MISC Instrumentation
RSD-1172-024-07 MISC Instrumentation
RSD-1172-024-08 MISC Instrumentation
TDS-7-037 NULL Instrumentation
TDS-7-040 NULL Instrumentation
TDS-7-035 NULL Instrumentation
TDS-7-036 NULL Instrumentation
RSP-1161-010-DS ELECTRICAL Electrical Systems
SP-90-PMIFORM INSPECTION Inspection and Quality Control
SP-90-21 INSPECTION Inspection and Quality Control
000-001 NULL Standard Practice
SP-42-01-PVMR PRESSURE VESSELS Fixed Equipment
SP-42-01-PVDATA PRESSURE VESSELS Fixed Equipment
RSD-42-01-01 VESSEL Fixed Equipment
RSD-42-01-02 VESSEL Fixed Equipment
RSD-42-01-03 VESSEL Fixed Equipment
RSD-42-01-04 VESSEL Fixed Equipment
RSD-42-01-05 VESSEL Fixed Equipment
RSD-42-01-06 VESSEL Fixed Equipment
RSD-42-01-07 VESSEL Fixed Equipment
RSD-42-01-08 VESSEL Fixed Equipment
RSD-42-01-09 VESSEL Fixed Equipment
RSD-42-01-10 VESSEL Fixed Equipment
RSD-42-01-11 VESSEL Fixed Equipment
RSD-42-01-12 VESSEL Fixed Equipment
RSD-42-01-13 VESSEL Fixed Equipment
RSD-42-18.2-02 TANK Fixed Equipment
SP-60-35-DS ELECTRICAL Electrical Systems
SP-42-16-LOG REFRACTORY Protective Coatings
SP-75-05-ISC INSTRUMENTATION Instrumentation
SP-75-05-SC INSTRUMENTATION Instrumentation
SP-75-05-OSC INSTRUMENTATION Instrumentation
SP-75-05-MPC INSTRUMENTATION Instrumentation
SP-75-05-SAC INSTRUMENTATION Instrumentation
SP-90-40 INSPECTION Inspection and Quality Control
RSP-1304-TMP01-EMSD PSM/RMP Safety
RSP-1304-TMP02-STEP PSM/RMP Safety
RSP-1304-TMP06-GUIDEPSM/RMP Safety
RSP-1304-TMP07-CPV PSM/RMP Safety
RSP-1304-TMP08-TROUBPSM/RMP Safety
SP-90-50-MTPTFORM INSPECTION Inspection and Quality Control
SP-90-50-04-REPORT INSPECTION Inspection and Quality Control
SP-90-50 INSPECTION Inspection and Quality Control
SP-90-50-01 INSPECTION Inspection and Quality Control
SP-90-50-02 INSPECTION Inspection and Quality Control
SP-90-50-03 INSPECTION Inspection and Quality Control
SP-90-50-04 INSPECTION Inspection and Quality Control
SP-90-50-05 INSPECTION Inspection and Quality Control
SP-90-50-06 INSPECTION Inspection and Quality Control
SP-90-50-07 INSPECTION Inspection and Quality Control
SP-60-09-DS ELECTRICAL Electrical Systems
RSP-1161-010-PUMPDS ELECTRICAL Electrical Systems
SP-50-24-CHKLIST WELDING Materials and Welding
SP-60-16-DS ELECTRICAL Electrical Systems
TDS-9-002 NULL Piping & Plant Layout
TDS-9-003 NULL Piping & Plant Layout
TDS-9-004 NULL Piping & Plant Layout
TDS-9-005 NULL Piping & Plant Layout
TDS-9-006 NULL Piping & Plant Layout
TDS-9-007 NULL Piping & Plant Layout
TDS-9-008 NULL Piping & Plant Layout
TDS-9-009 NULL Piping & Plant Layout
TDS-9-010 NULL Piping & Plant Layout
SP-90-30-EVAL INSPECTION Inspection and Quality Control
RSP-1131-000 PROCESS DESIGN Fixed Equipment
SP-60-07-DS ELECTRICAL Electrical Systems
IG-22 OPERATIONS Standard Practice
RSP-1240-000 PROCESS DESIGN Standard Practice
SP-43-15-R/S_CHKLST ROTATING EQUIPMENT Rotating Equipment
SP-43-15-INST_CHKLST ROTATING EQUIPMENT Rotating Equipment
SP-43-15-COMM_CHKLS ROTATING EQUIPMENT Rotating Equipment
RSP-1130-000 SAFETY Safety
SP-60-10-DS ELECTRICAL Electrical Systems
SP-46-01-ITP-HP PUMPS Rotating Equipment
SP-46-01-ITP-VP PUMPS Rotating Equipment
SP-46-06-SFDWG PUMPS Rotating Equipment
SP-60-11-DS ELECTRICAL Electrical Systems
SP-60-12-DS ELECTRICAL Electrical Systems
SP-60-17-DS ELECTRICAL Electrical Systems
SP-60-18-DS ELECTRICAL Electrical Systems
SP-60-19-DS ELECTRICAL Electrical Systems
SP-60-20-DS ELECTRICAL Electrical Systems
SP-60-21-DS ELECTRICAL Electrical Systems
SP-60-22-DS ELECTRICAL Electrical Systems
SP-60-23-DS ELECTRICAL Electrical Systems
SP-60-30-DS ELECTRICAL Electrical Systems
SP-60-31-DS ELECTRICAL Electrical Systems
SP-60-32-DS ELECTRICAL Electrical Systems
SP-60-34-DS ELECTRICAL Electrical Systems
TDS-9-011 NULL Piping & Plant Layout
SP-70-05-OPI-FORM INSTRUMENTATION Instrumentation
SP-44-01-DS FIXED EQUIPMENT Fixed Equipment
SP-90-60-AUDIT FIXED EQUIPMENT Fixed Equipment
SP-50-INJDS INSPECTION Inspection and Quality Control
SP-90-60 FIXED EQUIPMENT Inspection and Quality Control
RSP-1314 PSM/RMP Safety
RSP-1324-000 OPERATIONS Miscellaneous
RRD-1210-010 TECHNICAL GUIDANCE Miscellaneous
RRD-1210-000 TECHNOLOGIES Miscellaneous
RSP-1100-001-FORM09 TAR Miscellaneous
RSP-1100-001-FORM14 TAR Miscellaneous
RSP-1100-001-FORM16 TAR Miscellaneous
RSP-1100-001-FORM18 TAR Miscellaneous
RRD-1230-050 PROCESS DESIGN Fixed Equipment
RSP-1173-020 CONTROLS Instrumentation
LEG-1 DIRECTIVES Fixed Equipment
LEG-2 DIRECTIVES Fixed Equipment
LEG-3 DIRECTIVES Fixed Equipment
TDS-9-012 NULL Piping & Plant Layout
SP-43-04.1 COMPRESSOR Controls
RRD-1340-000-FORM04 OPERATIONS Miscellaneous
TDS-9-013 NULL Piping & Plant Layout
SP-90-04 INSPECTION Inspection and Quality Control
TDS-9-014 NULL Environmental and Utility Equipment
SP-43-10-CYLWS1 COMPRESSOR Rotating Equipment
SP-43-10-CYLWS2 COMPRESSOR Rotating Equipment
SP-43-10-MFTAB COMPRESSOR Rotating Equipment
RRD-1400-020 RELIABILITY Miscellaneous
RRD-1400-005 RELIABILITY Miscellaneous
RRD-1400-007 RELIABILITY Miscellaneous
RRD-1400-006 RELIABILITY Miscellaneous
SP-30-30 DESIGN Fixed Equipment
SP-43-05.6-PFAT COMPRESSOR Controls
SP-43-05.6-CNDCS COMPRESSOR Controls
SP-43-05.6-CNCVT COMPRESSOR Controls
SP-43-05.6-CNLWOS COMPRESSOR Controls
SP-43-05.6-CNS COMPRESSOR Controls
SP-43-05.6-ICC COMPRESSOR Controls
SP-43-05.6-EIVDA COMPRESSOR Controls
SP-43-05.6-CHART COMPRESSOR Controls
RSP-1306-CKLST PSM/RMP Rotating Equipment
RSP-1310-TEMP01 PSM/RMP Safety
RSP-1704-000 SAFETY Safety
RSP-1171-010-ARU PROCESS DESIGN Instrumentation
RSP-1171-010-COKER PROCESS DESIGN Instrumentation
RSP-1171-010-CRVC PROCESS DESIGN Instrumentation
RSP-1171-010-DHT PROCESS DESIGN Instrumentation
RSP-1171-010-FCC PROCESS DESIGN Instrumentation
RSP-1171-010-GOHT PROCESS DESIGN Instrumentation
RSP-1171-010-HFALKY PROCESS DESIGN Instrumentation
RSP-1171-010-ISOM PROCESS DESIGN Instrumentation
RSP-1171-010-NPT PROCESS DESIGN Instrumentation
RSP-1171-010-REFORM PROCESS DESIGN Instrumentation
RSP-1171-010-ROSE PROCESS DESIGN Instrumentation
RSP-1171-010-SDA PROCESS DESIGN Instrumentation
RSP-1171-010-SRU PROCESS DESIGN Instrumentation
RSD-50-24-01 GENERAL PIPING Piping & Plant Layout
RSD-50-24-02 GENERAL PIPING Piping & Plant Layout
RRD-1250-000 PROCESS DESIGN Fixed Equipment
TDS-3-001 NULL Miscellaneous
RSP-1305-001-FORM1 PSM/RMP Safety
RSP-1305-001 PSM/RMP Safety
TDS-9-015 NULL Piping & Plant Layout
RSP-1129-000 HF ALKY Safety
RSP-1703-000 SAFETY Safety
SP-90-40-EISHEET INSPECTION Inspection and Quality Control
SP-90-40-IRFORM INSPECTION Inspection and Quality Control
RRD-1923-000-EXHIB PROJECTS Miscellaneous
RRD-1923-000 PROJECTS Miscellaneous
RSP-1304-PGP PSM/RMP Safety
RSP-1304-SHPC PSM/RMP Safety
RSP-1304-STPC PSM/RMP Safety
RSP-1304-EPC PSM/RMP Safety
RSP-1304-TMP03-STEP PSM/RMP Safety
RRD-1230-060 PROCESS DESIGN Safety
SP-90-05 INSPECTION Inspection and Quality Control
RSP-1328-000 OPERATIONS Safety
RSP-1171-010-SAT PROCESS DESIGN Instrumentation
TDS-7-342 NULL Instrumentation
TDS-7-343 NULL Instrumentation
SP-90-50-ATT1 INSPECTION Inspection and Quality Control
SP-00-30 CIVIL/STRUCTURAL Civil and Structural
RRD-1100-000 GENERAL Miscellaneous
RRD-1810-000 INSTRUMENTATION Civil and Structural
RSP-1129-030-TEMP HF ALKY Safety
SP-80-08 INSULATION Protective Coatings
RRD-1210-020-FORM TECHNICAL GUIDANCE Miscellaneous
RRD-1210-020 TECHNICAL GUIDANCE Miscellaneous
RRD-1331-000-FORM2 OPERATIONS Miscellaneous
SP-60-39.12-FORM1 ELECTRICAL Electrical Systems
SP-60-39.13-FORM1 ELECTRICAL Electrical Systems
SP-60-39.14-FORM1 ELECTRICAL Electrical Systems
SP-60-39.41-FORM1 ELECTRICAL Electrical Systems
SP-M-60-39.12 ELECTRICAL Electrical Systems
SP-M-60-39.13 ELECTRICAL Electrical Systems
SP-M-60-39.14 ELECTRICAL Electrical Systems
SP-M-60-39.41 ELECTRICAL Electrical Systems
SP-60-39.01-FORM1 ELECTRICAL Electrical Systems
SP-60-39.02-FORM1 ELECTRICAL Electrical Systems
SP-60-39.05-FORM1 ELECTRICAL Electrical Systems
SP-60-39.06-FORM1 ELECTRICAL Electrical Systems
SP-M-60-39.01 ELECTRICAL Electrical Systems
SP-M-60-39.02 ELECTRICAL Electrical Systems
SP-M-60-39.05 ELECTRICAL Electrical Systems
SP-M-60-39.06 ELECTRICAL Electrical Systems
RSP-1330-000 OPERATIONS Safety
SP-43-04.1-CETMP COMPRESSOR Standard Practice
SP-43-04.1-CUT COMPRESSOR Standard Practice
SP-43-04.1-ICC COMPRESSOR Standard Practice
SP-43-04.1-CJWS COMPRESSOR Standard Practice
SP-43-04.1-CS COMPRESSOR Standard Practice
SP-43-04.1-CLOS COMPRESSOR Standard Practice
SP-43-04.1-EIVDA COMPRESSOR Standard Practice
SP-43-04.1-CDCCSIT COMPRESSOR Standard Practice
TDS-3-002 NULL Miscellaneous
SP-M-60-40 ELECTRICAL Electrical Systems
SP-50-03-CATADDM-DT NULL Standard Practice
SP-50-06-ITP COATINGS Protective Coatings
SP-50-03-DS1A PIPING Piping & Plant Layout
SP-50-03-DS1B PIPING Piping & Plant Layout
SP-50-03-DS1C PIPING Piping & Plant Layout
SP-50-03-DS1D PIPING Piping & Plant Layout
SP-50-03-DS1E PIPING Piping & Plant Layout
SP-50-03-DS1F PIPING Piping & Plant Layout
SP-50-03-DS1G PIPING Piping & Plant Layout
SP-50-03-DS1H PIPING Piping & Plant Layout
SP-50-03-DS1I PIPING Piping & Plant Layout
SP-50-03-DS2A PIPING Piping & Plant Layout
SP-50-03-DS2B PIPING Piping & Plant Layout
SP-50-03-DS2C PIPING Piping & Plant Layout
SP-50-03-DS2D PIPING Piping & Plant Layout
SP-50-03-DS3A PIPING Piping & Plant Layout
SP-50-03-DS3B PIPING Piping & Plant Layout
SP-50-03-DS3C PIPING Piping & Plant Layout
SP-50-03-DS3D PIPING Piping & Plant Layout
SP-50-03-DS3E PIPING Piping & Plant Layout
SP-50-03-DS3F PIPING Piping & Plant Layout
SP-50-03-DS3G PIPING Piping & Plant Layout
SP-50-03-DS3H PIPING Piping & Plant Layout
SP-50-03-DS4A PIPING Piping & Plant Layout
SP-50-03-DS6A PIPING Piping & Plant Layout
SP-50-03-DS6C PIPING Piping & Plant Layout
SP-50-03-DS6E PIPING Piping & Plant Layout
SP-50-03-DS6G PIPING Piping & Plant Layout
SP-50-03-DS7A PIPING Piping & Plant Layout
SP-50-03-DS7B PIPING Piping & Plant Layout
SP-50-03-DS7C PIPING Piping & Plant Layout
SP-46-06 PUMPS Rotating Equipment
RRD-1400-010 RELIABILITY Miscellaneous
RSD-42-18.5-01 TANK Fixed Equipment
RSD-42-18.5-02 TANK Fixed Equipment
RSD-42-18.5-03 TANK Fixed Equipment
RSD-42-18.5-04 TANK Fixed Equipment
RSD-42-18.5-05 TANK Fixed Equipment
RSD-42-18.5-06 TANK Fixed Equipment
RSD-42-18.5-07 TANK Fixed Equipment
RSD-42-18.5-08 TANK Fixed Equipment
RSD-42-18.5-09 TANK Fixed Equipment
RSD-42-18.5-10 TANK Fixed Equipment
RSD-42-18.5-11 TANK Fixed Equipment
RSD-42-18.5-12 TANK Fixed Equipment
RSD-42-18.5-13 TANK Fixed Equipment
RSD-42-18.5-14 TANK Fixed Equipment
RSD-42-18.5-15 TANK Fixed Equipment
RSD-42-18.5-16 TANK Fixed Equipment
RSD-42-18.5-17 TANK Fixed Equipment
IG-33 MAINTENANCE Standard Practice
SP-10-06-ITP FIREPROOFING Protective Coatings
TDS-4-004 NULL Piping & Plant Layout
RSP-1709-000 SAFETY Safety
SP-50-03-DS6H PIPING Piping & Plant Layout
RRD-1333-000 OPERATIONS Miscellaneous
RRD-1251-000 PROCESS DESIGN Fixed Equipment
RRD-1334-000 OPERATIONS Miscellaneous
REF-1055 DOCUMENT CONTROL Miscellaneous
IG-36 DOCUMENT CONTROL Miscellaneous
RSD-43-04-01 COMPRESSOR Rotating Equipment
RSD-43-04-05 COMPRESSOR Rotating Equipment
RSD-43-04-02 COMPRESSOR Rotating Equipment
RSD-43-04-04 COMPRESSOR Rotating Equipment
RSD-43-04-03 COMPRESSOR Rotating Equipment
SP-M-60-39.21 ELECTRICAL Electrical Systems
SP-M-60-39.30 ELECTRICAL Electrical Systems
SP-M-60-39.31 ELECTRICAL Electrical Systems
SP-M-60-39.32 ELECTRICAL Electrical Systems
SP-M-60-39.33 ELECTRICAL Electrical Systems
SP-50-00 PIPING Piping & Plant Layout
SP-50-52 PIPING Piping & Plant Layout
TDS-3-003 NULL Miscellaneous
RRD-1924-000 PROJECTS Miscellaneous
SP-50-03-JWH0 HI TEMP Piping & Plant Layout
RSP-1150-040-FORM1 PIPING Piping & Plant Layout
RSP-1150-040-FORM2 PIPING Piping & Plant Layout
RSP-1150-040-ATT1 PIPING Piping & Plant Layout
RRD-1335-000 OPERATIONS Miscellaneous
RRD-1401-000-FORM1 RELIABILITY Miscellaneous
RRD-1401-000-FORM2 RELIABILITY Miscellaneous
RRD-1401-000 RELIABILITY Miscellaneous
RSP-1150-040 PIPING Piping & Plant Layout
SP-50-03-JW0 HI TEMP Piping & Plant Layout
RSP-1312-FORM01 PSM/RMP Safety
RSP-1312-FORM02 PSM/RMP Safety
RSP-1312-FORM03 PSM/RMP Safety
RSP-1312-FORM04 PSM/RMP Safety
RSP-1312-FORM05 PSM/RMP Safety
RSP-1312-FORM06 PSM/RMP Safety
RSP-1312-FORM07 PSM/RMP Safety
RSP-1312-FORM08 PSM/RMP Safety
RSP-1312-FORM09 PSM/RMP Safety
RSP-1312-FORM10 PSM/RMP Safety
RSP-1312-FORM11 PSM/RMP Safety
RSP-1312-FORM12 PSM/RMP Safety
RSP-1312-FORM13 PSM/RMP Safety
RSP-1312-FORM14 PSM/RMP Safety
RSP-1312-FORM15 PSM/RMP Safety
RSP-1312-MOCMSS PSM/RMP Safety
RSP-1172-026 PROCESS DESIGN Fixed Equipment
RSP-1172-027 PROCESS DESIGN Instrumentation
RSP-1172-028 PROCESS DESIGN Instrumentation
RSP-1172-029 PROCESS DESIGN Instrumentation
RSP-1172-030 PROCESS DESIGN Instrumentation
RSP-1172-031 PROCESS DESIGN Rotating Equipment
RSP-1172-032 PROCESS DESIGN Standard Practice
RSP-1172-034-DRAFT PROCESS DESIGN Instrumentation
SP-50-03-AL1AV HI TEMP Piping & Plant Layout
SP-50-03-F2LPG LPG Piping & Plant Layout
SP-50-03-G2LPG LPG Piping & Plant Layout
SP-50-03-A2T MISC Piping & Plant Layout
SP-50-03-FF0R HI TEMP Piping & Plant Layout
SP-50-03-GWH1 HI TEMP Piping & Plant Layout
SP-50-03-GW1 HI TEMP Piping & Plant Layout
SP-50-03-FV1 HI TEMP Piping & Plant Layout
SP-50-03-GV1 HI TEMP Piping & Plant Layout
SP-50-03-A2AV SEVERE WET H2S Piping & Plant Layout
SP-50-03-A3AV SEVERE WET H2S Piping & Plant Layout
SP-50-03-F3AV SEVERE WET H2S Piping & Plant Layout
SP-50-03-G3AV SEVERE WET H2S Piping & Plant Layout
SP-50-03-G2AV SEVERE WET H2S Piping & Plant Layout
SP-50-03-H2AV SEVERE WET H2S Piping & Plant Layout
SP-50-03-A4AV SEVERE WET H2S Piping & Plant Layout
SP-50-03-C2AV SEVERE WET H2S Piping & Plant Layout
SP-50-03-C3AV SEVERE WET H2S Piping & Plant Layout
SP-50-03-C4AV SEVERE WET H2S Piping & Plant Layout
SP-50-03-F2AV SEVERE WET H2S Piping & Plant Layout
SP-50-03-F4AV SEVERE WET H2S Piping & Plant Layout
SP-50-03-AQD1 DUPLEX SS Piping & Plant Layout
SP-50-03-FQD1 DUPLEX SS Piping & Plant Layout
SP-50-03-CQD1 DUPLEX SS Piping & Plant Layout
SP-50-03-FQ1 HC W/ H2 Piping & Plant Layout
SP-50-03-A2ASH SIMPLE WET H2S W/ H2 Piping & Plant Layout
SP-50-03-C2ASH SIMPLE WET H2S W/ H2 Piping & Plant Layout
SP-50-03-F2ASH SIMPLE WET H2S W/ H2 Piping & Plant Layout
SP-50-03-G2ASH SIMPLE WET H2S W/ H2 Piping & Plant Layout
SP-50-03-H2AS SIMPLE WET H2S Piping & Plant Layout
SP-50-03-G2H HC W/ H2 Piping & Plant Layout
SP-50-03-J2H HC W/ H2 Piping & Plant Layout
SP-50-03-AQ1 HC W/ H2 Piping & Plant Layout
SP-50-03-CQ1 HC W/ H2 Piping & Plant Layout
SP-50-03-A3AS SIMPLE WET H2S Piping & Plant Layout
SP-50-03-A4AS SIMPLE WET H2S Piping & Plant Layout
SP-50-03-C3AS SIMPLE WET H2S Piping & Plant Layout
SP-50-03-F2AS SIMPLE WET H2S Piping & Plant Layout
SP-50-03-F4AS SIMPLE WET H2S Piping & Plant Layout
SP-50-03-A2AS SIMPLE WET H2S Piping & Plant Layout
SP-50-03-A2N CAUSTIC Piping & Plant Layout
SP-50-03-C2N CAUSTIC Piping & Plant Layout
SP-50-03-A2G AMINE Piping & Plant Layout
SP-50-03-GT1G AMINE Piping & Plant Layout
SP-50-03-AT1G AMINE Piping & Plant Layout
SP-50-03-CT1G AMINE Piping & Plant Layout
SP-50-03-G2G AMINE Piping & Plant Layout
SP-50-03-F2G AMINE Piping & Plant Layout
SP-50-03-G3G AMINE Piping & Plant Layout
SP-50-03-C2G AMINE Piping & Plant Layout
SP-50-03-H2G AMINE Piping & Plant Layout
SP-50-03-CRH1 HI TEMP Piping & Plant Layout
SP-50-03-A2Q SULFURIC ACID ALKY Piping & Plant Layout
SP-50-03-AR1L MISC Piping & Plant Layout
SP-50-03-FT1 HC W/ H2 Piping & Plant Layout
SP-50-03-CTH1PU HI TEMP Piping & Plant Layout
SP-50-03-CT1 HC W/ H2 Piping & Plant Layout
SP-50-03-HB2 HI TEMP Piping & Plant Layout
SP-50-03-C2AS SIMPLE WET H2S Piping & Plant Layout
SP-50-03-AB2 HI TEMP Piping & Plant Layout
SP-50-03-GB2 HI TEMP Piping & Plant Layout
SP-50-03-HB2AV SEVERE WET H2S Piping & Plant Layout
SP-50-03-FD2 HI TEMP Piping & Plant Layout
SP-50-03-AE4 HI TEMP Piping & Plant Layout
SP-50-03-CE4 HI TEMP Piping & Plant Layout
SP-50-03-GE2 HI TEMP Piping & Plant Layout
SP-50-03-CX1 SULFURIC ACID Piping & Plant Layout
SP-50-03-HW1 HI TEMP Piping & Plant Layout
RRD-1230-070-FORM01 PROCESS DESIGN Piping & Plant Layout
RRD-1230-070-ATT1 PROCESS DESIGN Piping & Plant Layout
RRD-1230-070 PROCESS DESIGN Piping & Plant Layout
SP-50-03-HQD1 DUPLEX SS Piping & Plant Layout
SP-50-03-GQD1 DUPLEX SS Piping & Plant Layout
SP-50-03-HV1 HI TEMP Piping & Plant Layout
SP-50-03-H2 COMMON Piping & Plant Layout
SP-50-03-HT1 HC W/ H2 Piping & Plant Layout
SP-50-03-HR1 HC W/ H2 Piping & Plant Layout
SP-50-03-J2R UTILITIES Piping & Plant Layout
SP-50-03-C2Q SULFURIC ACID ALKY Piping & Plant Layout
TDS-6-221 NULL Electrical Systems
SP-50-03-KPCU SEWERS AND DRAINS Piping & Plant Layout
SP-50-03-L4 UTILITIES Piping & Plant Layout
SP-50-03-S2 STEAM Piping & Plant Layout
SP-50-03-LGPDU UTILITIES Piping & Plant Layout
SP-50-03-SB2 STEAM Piping & Plant Layout
SP-50-03-KLPU1 SEWERS AND DRAINS Piping & Plant Layout
SP-50-03-LBLPU UTILITIES Piping & Plant Layout
SP-50-03-KPCU3 UTILITIES Piping & Plant Layout
SP-50-03-LBPHU UTILITIES Piping & Plant Layout
SP-50-03-F9PUH CATALYST Piping & Plant Layout
SP-50-03-FB9PUH CATALYST Piping & Plant Layout
SP-50-03-TRH1 STEAM Piping & Plant Layout
SP-50-03-LFG UTILITIES Piping & Plant Layout
SP-50-03-C9PUH CATALYST Piping & Plant Layout
SP-50-03-C9PU CATALYST Piping & Plant Layout
SP-50-03-CB9PU CATALYST Piping & Plant Layout
SP-50-03-A9PU CATALYST Piping & Plant Layout
SP-50-03-A9PUH CATALYST Piping & Plant Layout
SP-50-03-APT MISC Piping & Plant Layout
SP-50-03-AR9PU CATALYST Piping & Plant Layout
TDS-9-016 NULL Piping & Plant Layout
RSP-1304-TMP09-CERT PSM/RMP Safety
SP-50-03-LPHU UTILITIES Piping & Plant Layout
SP-70-02 INSTRUMENTATION Instrumentation
SP-70-07 INSTRUMENTATION Instrumentation
SP-M-60-39.07 ELECTRICAL Electrical Systems
SP-M-60-39.45 ELECTRICAL Electrical Systems
SP-M-60-39.46 ELECTRICAL Electrical Systems
SP-M-60-39.51 ELECTRICAL Electrical Systems
SP-M-60-39.52 ELECTRICAL Electrical Systems
SP-M-60-39.61 ELECTRICAL Electrical Systems
SP-M-60-39.70 ELECTRICAL Electrical Systems
SP-75-01 INSTRUMENTATION Instrumentation
SP-70-13 INSTRUMENTATION Instrumentation
SP-M-60-39.10 ELECTRICAL Electrical Systems
SP-M-60-39.11 ELECTRICAL Electrical Systems
SP-M-60-39.20 ELECTRICAL Electrical Systems
SP-M-60-39.22 ELECTRICAL Electrical Systems
SP-M-60-39.23 ELECTRICAL Electrical Systems
SP-M-60-39.24 ELECTRICAL Electrical Systems
SP-M-60-39.50 ELECTRICAL Electrical Systems
SP-M-60-39.80 ELECTRICAL Electrical Systems
SP-50-16-ATT1 PIPING Piping & Plant Layout
RRD-1337-000 OPERATIONS Miscellaneous
SP-50-03-GB4 HI TEMP Piping & Plant Layout
SP-50-03-Y2 STEAM TRACING Piping & Plant Layout
SP-50-03-L2V UTILITIES Piping & Plant Layout
SP-90-61 INSPECTION Inspection and Quality Control
SP-70-08 INSTRUMENTATION Instrumentation
SP-70-15 INSTRUMENTATION Instrumentation
SP-50-16 PIPING Piping & Plant Layout
RSP-1121-030-FORM01 SAFETY Safety
RSP-1121-030 SAFETY Safety
RSP-1715-000-FORM01 SAFETY Safety
RSP-1715-000 SAFETY Safety
RRD-1316-000 OPERATIONS Miscellaneous
_CROSS PIPING Piping & Plant Layout
SP-50-03-CT1P MISC Piping & Plant Layout
SP-90-07-FORM1 INSPECTION Inspection and Quality Control
SP-90-07 INSPECTION Inspection and Quality Control
RSP-1301-FORM1 PSM/RMP Safety
SP-43-16 ROTATING EQUIPMENT Rotating Equipment
SP-60-39.07-FORM1 ELECTRICAL Electrical Systems
SP-60-39.07-FORM1 ELECTRICAL Electrical Systems
SP-60-39.07-FORM1 ELECTRICAL Electrical Systems
SP-60-39.10-FORM1 ELECTRICAL Electrical Systems
SP-60-39.11-FORM1 ELECTRICAL Electrical Systems
SP-60-39.20-FORM1 ELECTRICAL Electrical Systems
SP-60-39.21-FORM1 ELECTRICAL Electrical Systems
SP-60-39.30-FORM1 ELECTRICAL Electrical Systems
SP-60-39.31-FORM1 ELECTRICAL Electrical Systems
SP-60-39.33-FORM1 ELECTRICAL Electrical Systems
SP-60-39.45-FORM1 ELECTRICAL Electrical Systems
SP-60-39.46-FORM1 ELECTRICAL Electrical Systems
SP-60-39.51-FORM1 ELECTRICAL Electrical Systems
SP-60-39.52-FORM1 ELECTRICAL Electrical Systems
SP-60-39.32-FORM1 ELECTRICAL Electrical Systems
SP-60-39.32-FORM2 ELECTRICAL Electrical Systems
SP-M-60-39.34 ELECTRICAL Electrical Systems
SP-M-60-39.42 ELECTRICAL Electrical Systems
SP-M-60-39.60 ELECTRICAL Electrical Systems
SP-M-60-39.73 ELECTRICAL Electrical Systems
SP-46-04 ROTATING EQUIPMENT Rotating Equipment
SP-50-03-ZL INST TUBING Piping & Plant Layout
SP-50-03-ZM INST TUBING Piping & Plant Layout
SP-50-03-ZT INST TUBING Piping & Plant Layout
_SP-50-03-MATRIX MATRIX Piping & Plant Layout
SP-70-25 INSTRUMENTATION Instrumentation
SP-99-03 WELDING Materials and Welding
SP-50-27.1 ROTATING EQUIPMENT Piping & Plant Layout
SP-47-05 ROTATING EQUIPMENT Tanks
SP-46-09 ROTATING EQUIPMENT Rotating Equipment
SP-50-27.3 ROTATING EQUIPMENT Piping & Plant Layout
SP-50-28.1 ROTATING EQUIPMENT Piping & Plant Layout
SP-75-04 INSTRUMENTATION Instrumentation
SP-70-21 INSTRUMENTATION Instrumentation
SP-70-22 INSTRUMENTATION Instrumentation
SP-75-05 INSTRUMENTATION Instrumentation
SP-75-03 INSTRUMENTATION Instrumentation
SP-00-25-FORM1 CIVIL/STRUCTURAL Civil and Structural
SP-00-25-FORM2 CIVIL/STRUCTURAL Civil and Structural
SP-00-25 CIVIL/STRUCTURAL Civil and Structural
RSP-1162-000-FORM1 ELECTRICAL Electrical Systems
RSP-1162-000-FORM2 ELECTRICAL Electrical Systems
RSP-1162-000-FORM3 ELECTRICAL Electrical Systems
RSP-1162-000 ELECTRICAL Electrical Systems
RSP-1324-010 OPERATIONS Miscellaneous
SP-50-30 PIPING Piping & Plant Layout
SP-50-28.2 PIPING Piping & Plant Layout
SP-96-00 INSPECTION Inspection and Quality Control
RRD-1132-000-TABLE1 TANK Fixed Equipment
RRD-1132-000 TANK Fixed Equipment
SP-70-12 INSTRUMENTATION Instrumentation
SP-70-14 INSTRUMENTATION Instrumentation
SP-46-10-FORM1 PUMPS Rotating Equipment
SP-46-10-FORM2 PUMPS Rotating Equipment
SP-46-10-FORM3 PUMPS Rotating Equipment
SP-M-46-10 PUMPS Rotating Equipment
RSP-1338-000-FORM1 OPERATIONS Safety
RSP-1338-000 OPERATIONS Safety
RSD-50-40-01 MISC STEEL SUPPORT Piping & Plant Layout
RSD-50-40-02 MISC STEEL SUPPORT Piping & Plant Layout
RSD-50-40-03 MISC STEEL SUPPORT Piping & Plant Layout
RSD-50-40-04 MISC STEEL SUPPORT Piping & Plant Layout
RSD-50-40-05 MISC STEEL SUPPORT Piping & Plant Layout
RSD-50-40-06 MISC STEEL SUPPORT Piping & Plant Layout
RSD-50-40-07 MISC STEEL SUPPORT Piping & Plant Layout
SP-50-40 PIPING Piping & Plant Layout
SP-00-09 CIVIL/STRUCTURAL Civil and Structural
SP-00-04 CIVIL/STRUCTURAL Civil and Structural
RSP-1102-010 GENERAL Civil and Structural
RRD-1173-030 CONTROLS Instrumentation
RRD-1303-001 PSM/RMP Safety
SP-30-18 HVAC Miscellaneous
SP-50-31 PIPING Piping & Plant Layout
SP-50-15 PIPING Piping & Plant Layout
RRD-1190-070 PSM/RMP Inspection and Quality Control
RRD-1190-071 PSM/RMP Inspection and Quality Control
RRD-1190-072 PSM/RMP Inspection and Quality Control
RRD-1190-073 PSM/RMP Inspection and Quality Control
RRD-1190-074 PSM/RMP Inspection and Quality Control
RRD-1190-075 PSM/RMP Inspection and Quality Control
RRD-1190-076 PSM/RMP Inspection and Quality Control
RRD-1190-077 PSM/RMP Inspection and Quality Control
RRD-1190-078 PSM/RMP Inspection and Quality Control
SP-00-01 CIVIL/STRUCTURAL Civil and Structural
SP-50-53 PIPING Piping & Plant Layout
SP-50-03-FRH1 HI TEMP Piping & Plant Layout
SP-70-24 INSTRUMENTATION Instrumentation
SP-50-03-HE2 HI TEMP Piping & Plant Layout
SP-50-03-FT1G AMINE Piping & Plant Layout
SP-50-17 PIPING Piping & Plant Layout
SP-00-06 CIVIL/STRUCTURAL Civil and Structural
RRD-1339-000 OPERATIONS Miscellaneous
RSP-1172-033 PROCESS DESIGN Instrumentation
RRD-1340-000 OPERATIONS Miscellaneous
RRD-1341-000 OPERATIONS Miscellaneous
SP-60-39.22-FORM1 ELECTRICAL Electrical Systems
SP-60-39.24-FORM1 ELECTRICAL Electrical Systems
SP-60-39.24-FORM1 ELECTRICAL Electrical Systems
SP-60-39.42-FORM1 ELECTRICAL Electrical Systems
SP-00-11 CIVIL/STRUCTURAL Civil and Structural
SP-30-28 CIVIL/STRUCTURAL Civil and Structural
SP-44-02.1-DS FIXED EQUIPMENT Fixed Equipment
SP-45-01.1 FIXED EQUIPMENT Fixed Equipment
SP-42-12 FIXED EQUIPMENT Inspection and Quality Control
SP-44-05 FIXED EQUIPMENT Fixed Equipment
SP-44-02.1 FIXED EQUIPMENT Fixed Equipment
SP-46-11 ROTATING EQUIPMENT Rotating Equipment
TDS-6-225 NULL Electrical Systems
SP-90-41 INSPECTION Inspection and Quality Control
RRD-1350-001 OPERATIONS Miscellaneous
SP-99-14 MATERIAL SELECTION Materials and Welding
RRD-1351-001 OPERATIONS Miscellaneous
RSD-50-07-01 GENERAL PIPING Piping & Plant Layout
RSD-50-07-02 GENERAL PIPING Piping & Plant Layout
RSD-50-07-03 GENERAL PIPING Piping & Plant Layout
RSD-50-07-04 GENERAL PIPING Piping & Plant Layout
RSD-50-07-05 GENERAL PIPING Piping & Plant Layout
RSD-50-07-06 GENERAL PIPING Piping & Plant Layout
RSD-50-07-07 GENERAL PIPING Piping & Plant Layout
RSD-50-07-08 GENERAL PIPING Piping & Plant Layout
RSD-50-07-09 GENERAL PIPING Piping & Plant Layout
RSD-50-07-10 GENERAL PIPING Piping & Plant Layout
RSD-50-07-11 GENERAL PIPING Piping & Plant Layout
SP-50-07.1 PIPING Piping & Plant Layout
RSP-1315-000-FORM1 PSM/RMP Safety
RSP-1315-000 PSM/RMP Safety
RSP-1307-PMOC1-01 PSM/RMP Safety
RSP-1307-PMOC2-01 PSM/RMP Safety
RSP-1307-PMOC2-02 PSM/RMP Safety
RSP-1307-PMOC2-03 PSM/RMP Safety
RSP-1307-PMOC2-04 PSM/RMP Safety
RSP-1307-PMOC2-05 PSM/RMP Safety
RSP-1307-PMOC2-06 PSM/RMP Safety
RSP-1307-PMOC2-07 PSM/RMP Safety
RSP-1307-PMOC2-08 PSM/RMP Safety
RSP-1307-PMOC2-09 PSM/RMP Safety
RSP-1307-PMOC2-10 PSM/RMP Safety
RSP-1307-PMOC2-11 PSM/RMP Safety
RSP-1307-PMOC3-01 PSM/RMP Safety
RSP-1307-PMOC1 PSM/RMP Safety
RSP-1307-PMOC2 PSM/RMP Safety
RSP-1307-PMOC3 PSM/RMP Safety
RSD-30-25-01 HVAC Miscellaneous
RSD-30-25-02 HVAC Miscellaneous
RSD-30-25-03 HVAC Miscellaneous
RSD-30-25-04 HVAC Miscellaneous
RSD-30-25-05 HVAC Miscellaneous
RSD-30-25-06 HVAC Miscellaneous
RSD-30-25-07 HVAC Miscellaneous
RSD-30-25-08 HVAC Miscellaneous
RSD-30-25-09 HVAC Miscellaneous
RSD-30-25-10 HVAC Miscellaneous
SP-30-25-DS1 HVAC Miscellaneous
SP-30-25 HVAC Miscellaneous
SP-M-60-39.40 ELECTRICAL Electrical Systems
SP-M-60-39.71 ELECTRICAL Electrical Systems
SP-M-60-39.82 ELECTRICAL Electrical Systems
SP-M-60-39.83 ELECTRICAL Electrical Systems
SP-50-03-CV1 HI TEMP Piping & Plant Layout
SP-50-03-AFC1 MISC Piping & Plant Layout
RRD-1174-000 CONTROLS Instrumentation
RRD-1350-002 OPERATIONS Miscellaneous
RRD-1351-002 OPERATIONS Miscellaneous
RRD-1350-003 OPERATIONS Miscellaneous
RRD-1351-003 OPERATIONS Miscellaneous
RRD-1350-103 OPERATIONS Miscellaneous
SP-70-29-FORM01 INSTRUMENTATION Instrumentation
SP-70-29 INSTRUMENTATION Instrumentation
SP-90-30-VISCL INSPECTION Inspection and Quality Control
SP-60-28 ELECTRICAL Electrical Systems
SP-99-15 MATERIAL SELECTION Materials and Welding
SP-99-17 MATERIAL SELECTION Materials and Welding
RSP-1171-010-FS PROCESS DESIGN Instrumentation
RRD-1352-001 OPERATIONS Miscellaneous
SP-45-03-FORM1 FIRED HEATERS Fired Equipment
SP-45-03 FIRED HEATERS Fixed Equipment
RSP-1308-PMOC01 PSM/RMP Safety
RSP-1308-PMOC02 PSM/RMP Safety
SP-44-03 COOLING TOWERS Fixed Equipment
SP-80-20 COATINGS Protective Coatings
SP-80-21 COATINGS Protective Coatings
SP-50-21 PIPING Piping & Plant Layout
SP-50-21-DS01 PIPING Piping & Plant Layout
SP-50-21-DS02 PIPING Piping & Plant Layout
SP-50-21-DS03 PIPING Piping & Plant Layout
SP-50-21-DS04 PIPING Piping & Plant Layout
IG-34 PIPING Piping & Plant Layout
SP-50-16-ATT2 PIPING Piping & Plant Layout
SP-50-14-FORM01 PIPING Piping & Plant Layout
SP-50-14-FORM02 PIPING Piping & Plant Layout
SP-50-14 PIPING Piping & Plant Layout
RSP-1708-000-FORM1 SAFETY Safety
RSP-1708-000-FORM2 SAFETY Safety
RSP-1708-000 SAFETY Safety
SP-70-23 INSTRUMENTATION Instrumentation
RSP-1303-ATT1 PSM/RMP Safety
RRD-1620-000 PLANNING Miscellaneous
RRD-1620-001 PLANNING Miscellaneous
RRD-1620-002 PLANNING Miscellaneous
SP-50-03-CH4FU ALKY Piping & Plant Layout
SP-90-01-FORM01 INSPECTION Inspection and Quality Control
SP-90-01-FORM02 INSPECTION Inspection and Quality Control
SP-90-01-FORM03 INSPECTION Inspection and Quality Control
SP-90-01 INSPECTION Inspection and Quality Control
RRD-1250-700 PROCESS DESIGN Fixed Equipment
RRD-1720-000-ATT1 ENVIRONMENTAL Environmental and Utility Equipment
RRD-1720-000 ENVIRONMENTAL Environmental and Utility Equipment
SP-70-27 INSTRUMENTATION Instrumentation
SP-70-28 INSTRUMENTATION Instrumentation
SP-45-02 FIRED HEATERS Fixed Equipment
RSP-1144-000-FORM01 ROTATING EQUIPMENT Rotating Equipment
RSP-1144-000 ROTATING EQUIPMENT Rotating Equipment
RSP-1501-ATT1 QUALITY Product Quality
RSP-1501-ATT2 QUALITY Product Quality
RRD-1620-003 PLANNING Miscellaneous
RRD-1250-100-ATT1 PROCESS DESIGN Fixed Equipment
RRD-1250-100 PROCESS DESIGN Fixed Equipment
RRD-1340-000-FORM01 OPERATIONS Miscellaneous
RRD-1340-000-FORM02 OPERATIONS Miscellaneous
RRD-1340-000-FORM03 OPERATIONS Miscellaneous
RRD-1230-070-FORM02 PROCESS DESIGN Piping & Plant Layout
RSP-1172-035 PROCESS DESIGN Instrumentation
RSP-1220-000-PMOC1 PLANNING Product Quality
RSD-42-18.5-18 TANK Fixed Equipment
RSD-42-18.5-19 TANK Fixed Equipment
RSD-42-18.5-20 TANK Fixed Equipment
RSD-42-18.5-21 TANK Fixed Equipment
RSD-42-18.5-22 TANK Fixed Equipment
RSD-42-18.2-01 TANK Fixed Equipment
RSD-50-04.1-01 GENERAL PIPING Piping & Plant Layout
RSD-50-04.1-02 GENERAL PIPING Piping & Plant Layout
RSD-50-04.1-03 GENERAL PIPING Piping & Plant Layout
RSD-50-04.1-04 GENERAL PIPING Piping & Plant Layout
RSD-50-04.1-05 GENERAL PIPING Piping & Plant Layout
SP-46-01-ATT1 PUMPS Rotating Equipment
RRD-1030-000 RELIABILITY Miscellaneous
RRD-1030-000-TEMP RELIABILITY Miscellaneous
SP-50-03-FC2 HI TEMP Piping & Plant Layout
SP-50-03-FC3 HI TEMP Piping & Plant Layout
SP-50-03-G2 COMMON Piping & Plant Layout
SP-50-03-GR1 HC W/ H2 Piping & Plant Layout
SP-50-03-TB2AA STEAM Piping & Plant Layout
SP-50-03-H3AV SEVERE WET H2S Piping & Plant Layout
SP-50-03-HC2 HI TEMP Piping & Plant Layout
SP-50-03-HR1L MISC Piping & Plant Layout
SP-50-03-HT1AV SEVERE WET H2S Piping & Plant Layout
SP-50-03-J2 COMMON Piping & Plant Layout
SP-50-03-JE2 HI TEMP Piping & Plant Layout
SP-50-03-JV1 HI TEMP Piping & Plant Layout
RRD-1250-800 UTILITIES Environmental and Utility Equipment
RRD-1250-801 UTILITIES Environmental and Utility Equipment
RRD-1250-802 UTILITIES Environmental and Utility Equipment
RSP-1715-000-FORM02 SAFETY Safety
SP-90-12 INSPECTION Inspection and Quality Control
RSP-1121-010-ATT1 SAFETY Safety
RSP-1121-010-ATT2 SAFETY Safety
RSP-1121-010-FORM01 SAFETY Safety
RSP-1121-010-FORM02 SAFETY Safety
RSP-1121-010-FORM03 SAFETY Safety
RSP-1121-010-FORM04 SAFETY Safety
RSP-1121-010-FORM05 SAFETY Safety
RSP-1121-010-FORM06 SAFETY Safety
RRD-1503-001-FORM01 QUALITY Product Quality
RRD-1503-001 QUALITY Product Quality
SP-50-03-A2M CAUSTIC Piping & Plant Layout
SP-50-03-AM1 CAUSTIC Piping & Plant Layout
SP-50-03-AR1K LOW TEMP Piping & Plant Layout
SP-50-03-AV1 HI TEMP Piping & Plant Layout
SP-50-03-LBN2 UTILITIES Piping & Plant Layout
SP-50-03-XG0 UTILITIES Piping & Plant Layout
SP-50-03-XP2 UTILITIES Piping & Plant Layout
SP-50-03-C2M CAUSTIC Piping & Plant Layout
SP-50-03-CD3 HI TEMP Piping & Plant Layout
SP-50-03-CE2AV HI TEMP Piping & Plant Layout
SP-50-03-CH4F ALKY Piping & Plant Layout
SP-10-01 SULFUR PITS Civil and Structural
_GBR CROSS PIPING Piping & Plant Layout
RRD-1923-001 PROJECTS Miscellaneous
RSP-1163-000-ATT1 ELECTRICAL Electrical Systems
RSP-1163-000 ELECTRICAL Electrical Systems
RSP-1305-002-FORM01 TRAINING Electrical Systems
RSP-1305-002 TRAINING Electrical Systems
SP-50-03-AK2AV LOW TEMP Piping & Plant Layout
SP-50-03-CW1 HI TEMP Piping & Plant Layout
RRD-1316-000-ATT1 OPERATIONS Miscellaneous
SP-50-03-CM1 CAUSTIC Piping & Plant Layout
RSP-1801-001-ATT1 LAB Miscellaneous
RRD-1132-001-ATT1 TANK Fixed Equipment
RRD-1132-001-ATT2 TANK Fixed Equipment
RRD-1132-001 TANK Fixed Equipment
RRD-1905-000 PROJECTS Miscellaneous
SP-46-05 ROTATING EQUIPMENT Rotating Equipment
RSD-00-16-01 STRUCTURAL Civil and Structural
RSD-00-16-02 STRUCTURAL Civil and Structural
RSD-00-16-03 STRUCTURAL Civil and Structural
RSP-1121-025 SAFETY Safety
RSP-1503-050 QUALITY Product Quality
RSP-1710-050-FORM01 SAFETY Safety
RSP-1710-050-FORM02 SAFETY Safety
RSP-1710-050 SAFETY Safety
SP-50-03-A2XLP OXYGEN Piping & Plant Layout
RRD-1190-200-FIG1 MATERIALS Materials and Welding
RRD-1190-200-FIG2 MATERIALS Materials and Welding
RRD-1190-200-FIG3 MATERIALS Materials and Welding
RRD-1190-200-FIG4 MATERIALS Materials and Welding
RRD-1190-200 MATERIALS Materials and Welding
SP-50-03-JC2 HI TEMP Piping & Plant Layout
SP-50-03-JD2 HI TEMP Piping & Plant Layout
SP-50-03-JR1L MISC Piping & Plant Layout
SP-90-06-ATT1 INSPECTION Inspection and Quality Control
SP-90-06-ATT2 INSPECTION Inspection and Quality Control
SP-90-06-ATT3A INSPECTION Inspection and Quality Control
SP-90-06-ATT3B INSPECTION Inspection and Quality Control
SP-90-06-ATT4 INSPECTION Inspection and Quality Control
SP-90-06-ATT5 INSPECTION Inspection and Quality Control
SP-90-06-SAT1 INSPECTION Inspection and Quality Control
SP-90-06-SAT2 INSPECTION Inspection and Quality Control
SP-90-06-SAT3 INSPECTION Inspection and Quality Control
SP-90-06-SAT4 INSPECTION Inspection and Quality Control
SP-90-06 INSPECTION Inspection and Quality Control
RRD-1250-001 PROCESS DESIGN Fixed Equipment
SP-96-10 INSPECTION Inspection and Quality Control
SP-96-10-FORM01 INSPECTION Inspection and Quality Control
SP-96-30 INSPECTION Inspection and Quality Control
RRD-1250-002-FORM01 PROCESS DESIGN Fixed Equipment
RRD-1250-002-FORM02 PROCESS DESIGN Fixed Equipment
RRD-1250-002-FORM03 PROCESS DESIGN Fixed Equipment
RRD-1250-002 PROCESS DESIGN Fixed Equipment
RSP-1310-FORM01 PSM/RMP Safety
RSP-1310-ATT1 PSM/RMP Safety
RRD-1401-000-FORM3 RELIABILITY Miscellaneous
RSP-1705-000 SAFETY Safety
RSP-1300-015 PSM/RMP Safety
RSP-1610-001-ATT1 PLANNING Product Quality
RSP-1610-001-ATT2 PLANNING Product Quality
RRD-1925-000-ATT1 PROJECTS Miscellaneous
RRD-1925-000-ATT2 PROJECTS Miscellaneous
RRD-1925-000-FORM01 PROJECTS Miscellaneous
RRD-1926-000-ATT1 PROJECTS Miscellaneous
RRD-1926-000-ATT2 PROJECTS Miscellaneous
RRD-1926-000-FORM01 PROJECTS Miscellaneous
RRD-1926-000-FORM02 PROJECTS Miscellaneous
RRD-1927-000-ATT1 PROJECTS Miscellaneous
RRD-1928-000-ATT1 PROJECTS Miscellaneous
RRD-1925-000 PROJECTS Miscellaneous
RRD-1926-000 PROJECTS Miscellaneous
RRD-1927-000 PROJECTS Miscellaneous
RRD-1928-000 PROJECTS Miscellaneous
SP-20-00 SAFETY Safety
RSP-1121-010-FORM01 SAFETY Safety
RSP-1121-010-FORM02 SAFETY Safety
RSP-1121-010-FORM03 SAFETY Safety
RSP-1121-010-FORM07 SAFETY Safety
RSP-1121-010-FORM07 SAFETY Safety
SP-90-18 INSPECTION Inspection and Quality Control
SP-50-03-ZFCT INST TUBING Piping & Plant Layout
RSP-1127-000-FORM01 SAFETY Safety
RSP-1127-000-FORM02 SAFETY Safety
RSP-1127-000-TEMP SAFETY Safety
RSP-1310-TEMP02 PSM/RMP Safety
RSP-1307-CHECKLIST NULL Safety
RRD-1340-000-FORM05 OPERATIONS Miscellaneous
RRD-1260-004 CONTROLS Instrumentation
SP-43-01 COMPRESSOR Rotating Equipment
RSP-1121-020-FORM01 SAFETY Safety
REF-1056 SAFETY Safety
RSP-1501-030 LABORATORY Product Quality
RRD-1620-004 PLANNING Miscellaneous
SP-00-05 GENERAL Miscellaneous
RRD-1620-005 PLANNING Miscellaneous
RRD-1101-000 RELIABILITY Miscellaneous
SP-60-40.01-FORM1 ELECTRICAL Electrical Systems
SP-M-60-40.01 ELECTRICAL Electrical Systems
SP-60-40.02-FORM1 ELECTRICAL Electrical Systems
SP-60-40.05-FORM1 ELECTRICAL Electrical Systems
SP-60-40.06-FORM1 ELECTRICAL Electrical Systems
SP-M-60-40.02 ELECTRICAL Electrical Systems
SP-M-60-40.05 ELECTRICAL Electrical Systems
SP-M-60-40.06 ELECTRICAL Electrical Systems
RSD-43-03-01 COMPRESSOR Rotating Equipment
RSD-43-03-02 COMPRESSOR Rotating Equipment
RRD-1929-000 PROJECTS Miscellaneous
RRD-1901-000-ATT1 PROJECTS Miscellaneous
RRD-1901-000-ATT2 PROJECTS Miscellaneous
RRD-1901-000-ATT3 PROJECTS Miscellaneous
RRD-1901-000-ATT4 PROJECTS Miscellaneous
RRD-1930-000 PROJECTS Miscellaneous
SP-43-09 ROTATING EQUIPMENT Rotating Equipment
RRD-1352-002 OPERATIONS Miscellaneous
RRD-1210-015 TECHNOLOGIES Miscellaneous
RRD-1620-007 PLANNING Miscellaneous
SP-60-40.07-FORM1 ELECTRICAL Electrical Systems
SP-60-40.07-FORM1 ELECTRICAL Electrical Systems
SP-60-40.11-FORM1 ELECTRICAL Electrical Systems
SP-60-40.12-FORM1 ELECTRICAL Electrical Systems
SP-M-60-40.11 ELECTRICAL Electrical Systems
SP-M-60-40.12 ELECTRICAL Electrical Systems
SP-60-40.13-FORM1 ELECTRICAL Electrical Systems
SP-60-40.14-FORM1 ELECTRICAL Electrical Systems
SP-60-40.30-FORM1 ELECTRICAL Electrical Systems
SP-60-40.31-FORM1 ELECTRICAL Electrical Systems
SP-60-40.32-FORM1 ELECTRICAL Electrical Systems
SP-60-40.32-FORM2 ELECTRICAL Electrical Systems
SP-60-40.33-FORM1 ELECTRICAL Electrical Systems
SP-M-60-40.07 ELECTRICAL Electrical Systems
SP-M-60-40.13 ELECTRICAL Electrical Systems
SP-M-60-40.14 ELECTRICAL Electrical Systems
SP-M-60-40.30 ELECTRICAL Electrical Systems
SP-M-60-40.31 ELECTRICAL Electrical Systems
SP-M-60-40.32 ELECTRICAL Electrical Systems
SP-M-60-40.33 ELECTRICAL Electrical Systems
SP-50-03-DS1J PIPING Piping & Plant Layout
SP-50-03-DS1K PIPING Piping & Plant Layout
SP-50-03-CQ2 HC W/ H2 Piping & Plant Layout
RSP-1304-TMP04-CKLST PSM/RMP Safety
RSP-1304-TMP05-CKLST PSM/RMP Safety
RSP-1304-TMP10-PCLOGPSM/RMP Safety
RSP-1304-CPAC PSM/RMP Safety
RSP-1304-PRM PSM/RMP Safety
RRD-1190-201-FORM01 MATERIALS Materials and Welding
RRD-1190-201-FORM02 MATERIALS Materials and Welding
RRD-1190-201 MATERIALS Materials and Welding
SP-90-24 INSPECTION Inspection and Quality Control
REF-1057-ATT1 SAFETY Safety
REF-1057-ATT2 SAFETY Safety
REF-1057-ATT3 SAFETY Safety
RSP-1906-000 PROJECTS Miscellaneous
RSP-1605-000 PLANNING Miscellaneous
SP-50-41-DS01 PIPING Piping & Plant Layout
SP-50-41 PIPING Piping & Plant Layout
SP-50-39 PIPING Piping & Plant Layout
REF-1057 SAFETY Safety
IG-42 PSM/RMP Safety
IG-43 PSM/RMP Safety
RRD-1190-001 INSPECTION Inspection and Quality Control
RRD-1102-000 RELIABILITY Miscellaneous
RRD-1352-004 OPERATIONS Miscellaneous
RRD-1950-001 PROJECTS Miscellaneous
RRD-1950-002 PROJECTS Miscellaneous
RSD-50-00-03 GENERAL PIPING Piping & Plant Layout
SP-50-03-DS1U PIPING Piping & Plant Layout
SP-50-03-DS1V PIPING Piping & Plant Layout
SP-50-03-DS2V PIPING Piping & Plant Layout
SP-50-03-DS2Z PIPING Piping & Plant Layout
RSD-00-02-01 GENERAL PIPING Piping & Plant Layout
SP-00-02 GENERAL Miscellaneous
IG-44 GENERAL Miscellaneous
SP-M-60-39.03 ELECTRICAL Electrical Systems
SP-90-08 INSPECTION Inspection and Quality Control
SP-60-41-FORM01 ELECTRICAL Electrical Systems
SP-60-41-FORM02 ELECTRICAL Electrical Systems
SP-60-41-FORM03 ELECTRICAL Electrical Systems
SP-60-41-FORM04 ELECTRICAL Electrical Systems
SP-60-41-FORM05 ELECTRICAL Electrical Systems
SP-60-41-FORM06 ELECTRICAL Electrical Systems
SP-60-41-FORM07 ELECTRICAL Electrical Systems
SP-60-41-FORM08 ELECTRICAL Electrical Systems
SP-60-41-FORM09 ELECTRICAL Electrical Systems
SP-60-41-FORM10 ELECTRICAL Electrical Systems
SP-60-41-FORM11 ELECTRICAL Electrical Systems
SP-60-41-FORM12 ELECTRICAL Electrical Systems
SP-60-41-FORM13 ELECTRICAL Electrical Systems
SP-60-41-FORM14 ELECTRICAL Electrical Systems
SP-60-41-FORM15 ELECTRICAL Electrical Systems
SP-60-41-FORM16 ELECTRICAL Electrical Systems
SP-60-41-FORM17 ELECTRICAL Electrical Systems
SP-60-41-FORM18 ELECTRICAL Electrical Systems
SP-60-41-FORM19 ELECTRICAL Electrical Systems
SP-60-41-FORM20 ELECTRICAL Electrical Systems
SP-60-41-FORM21 ELECTRICAL Electrical Systems
SP-60-41 ELECTRICAL Electrical Systems
SP-42-18.5-FORM01 TANK Fixed Equipment
SP-42-18.5-FORM02 TANK Fixed Equipment
SP-70-17 INSTRUMENTATION Instrumentation
IG-47 INSTRUMENTATION Instrumentation
RRD-1620-006 PLANNING Miscellaneous
RSP-1307-TASKS PSM/RMP Safety
RSP-1307-RCL PSM/RMP Safety
RSP-1307-GENCL PSM/RMP Safety
SP-50-03-AC2 HI TEMP Piping & Plant Layout
SP-50-03-CC2 HI TEMP Piping & Plant Layout
SP-50-03-CR1L MISC Piping & Plant Layout
SP-50-03-HEV2AA HI TEMP Piping & Plant Layout
SP-50-03-JTH1 HI TEMP Piping & Plant Layout
SP-50-03-MC2 HI TEMP Piping & Plant Layout
IG-48-ATT1 SAFETY Safety
IG-48-ATT2 SAFETY Safety
IG-48 SAFETY Safety
RSP-1505-000 QUALITY Product Quality
RSP-1150-010-PMOC01 OPERATIONS Piping & Plant Layout
RSP-1150-010 OPERATIONS Piping & Plant Layout
RSP-1566-000-FORM01 PURCHASING Rotating Equipment
RSP-1566-000 PURCHASING Rotating Equipment
SP-90-13 INSPECTION Fixed Equipment
REF-1057-ATT4 SAFETY Safety
SP-80-40 INSULATION Protective Coatings
SP-80-41 INSULATION Protective Coatings
RSP-1565-000-AML AML Product Quality
RSP-1565-000-FPQFORMAML Product Quality
RSP-1565-000-OSAFORMAML Product Quality
RSP-1565-000-PFAFORMAML Product Quality
RSP-1565-000-DRFORM AML Product Quality
RSP-1565-000 AML Product Quality
RSP-1305-003 TRAINING Miscellaneous
SP-90-17-FORM01 INSPECTION Inspection and Quality Control
SP-90-11 INSPECTION Inspection and Quality Control
SP-90-17 INSPECTION Inspection and Quality Control
REF-1056-FORM01 SAFETY Safety
RRD-1570-000 PURCHASING Product Quality
SP-96-15-FORM01 INSPECTION Inspection and Quality Control
SP-96-15 INSPECTION Inspection and Quality Control
SP-96-25 INSPECTION Inspection and Quality Control
RRD-1100-002-FORM01 TAR Miscellaneous
RRD-1100-002-FORM02 TAR Miscellaneous
RRD-1100-002-FORM03 TAR Miscellaneous
RRD-1100-002-ATT1 TAR Miscellaneous
RRD-1100-002-ATT2 TAR Miscellaneous
RRD-1100-002-ATT3 TAR Miscellaneous
RRD-1100-002 TAR Miscellaneous
RRD-1100-003 TAR Miscellaneous
RRD-1100-004 TAR Miscellaneous
RRD-1100-005-ATT1 TAR Miscellaneous
RRD-1100-005-ATT2 TAR Miscellaneous
RRD-1100-005 TAR Miscellaneous
RRD-1100-006 TAR Miscellaneous
RRD-1100-007-ATT1 TAR Miscellaneous
RRD-1100-007 TAR Miscellaneous
RSP-1100-001-FORM19 TAR Miscellaneous
RSP-1100-001-FORM20 TAR Miscellaneous
RSP-1305-FORM01 PSM/RMP Safety
RSP-1100-001-FORM08 TAR Miscellaneous
RRD-1241-000-FORM01 PROCESS DESIGN Miscellaneous
RRD-1241-000 PROCESS DESIGN Miscellaneous
RRD-1190-070-FORM01 PSM/RMP Inspection and Quality Control
RRD-1190-071-FORM01 PSM/RMP Inspection and Quality Control
RRD-1190-072-FORM01 PSM/RMP Inspection and Quality Control
RRD-1190-073-FORM01 PSM/RMP Inspection and Quality Control
RRD-1190-073-FORM02 PSM/RMP Inspection and Quality Control
RRD-1190-074-FORM01 PSM/RMP Inspection and Quality Control
RRD-1190-075-FORM01 PSM/RMP Inspection and Quality Control
RRD-1190-075-FORM02 PSM/RMP Inspection and Quality Control
RRD-1190-076-FORM01 PSM/RMP Inspection and Quality Control
RRD-1190-077-FORM01 PSM/RMP Inspection and Quality Control
RRD-1190-077-FORM02 PSM/RMP Inspection and Quality Control
RRD-1190-078-FORM01 PSM/RMP Inspection and Quality Control
RSP-1503-030 QUALITY Product Quality
RSP-1716-000 SAFETY Safety
SP-90-19 INSPECTION Inspection and Quality Control
SP-90-14-FORM01 INSPECTION Inspection and Quality Control
SP-90-14 INSPECTION Inspection and Quality Control
TES-002 NULL Standard Practice
TES-010 NULL Standard Practice
TES-010F1 NULL Standard Practice
TES-050 NULL Standard Practice
TES-060 NULL Standard Practice
TES-105DS1 NULL Standard Practice
TES-105LAN NULL Standard Practice
TES-105LGE NULL Standard Practice
TES-105LLA NULL Standard Practice
TES-105LND NULL Standard Practice
TES-105LSL NULL Standard Practice
TES-110D1 NULL Standard Practice
TES-110DS1 NULL Standard Practice
TES-111 NULL Standard Practice
TES-120F1 NULL Standard Practice
TES-130D1 NULL Standard Practice
TES-163 NULL Standard Practice
TES-164 NULL Standard Practice
TES-166D1 NULL Standard Practice
TES-166D2 NULL Standard Practice
TES-167F1 NULL Standard Practice
TES-175F1 NULL Standard Practice
TES-175F2 NULL Standard Practice
TES-204 NULL Standard Practice
TES-205 NULL Standard Practice
TES-210 NULL Standard Practice
TES-211 NULL Standard Practice
TES-220 NULL Standard Practice
TES-220DS1 NULL Standard Practice
TES-220F1 NULL Standard Practice
TES-240 NULL Standard Practice
TES-241 NULL Standard Practice
TES-242 NULL Standard Practice
TES-244 NULL Standard Practice
TES-260F1 NULL Standard Practice
TES-311C1 NULL Standard Practice
TES-311C2 NULL Standard Practice
TES-311C3 NULL Standard Practice
TES-320 NULL Standard Practice
TES-320C1 NULL Standard Practice
TES-320C2 NULL Standard Practice
TES-320C3 NULL Standard Practice
TES-360 NULL Standard Practice
TES-360DS1 NULL Standard Practice
TES-601 NULL Standard Practice
TES-601DS1 NULL Standard Practice
TES-605 NULL Standard Practice
TES-606 NULL Standard Practice
TES-632 NULL Standard Practice
TES-632DS1 NULL Standard Practice
TES-635 NULL Standard Practice
TES-635DS1 NULL Standard Practice
TES-662DS1 NULL Standard Practice
TES-662DS2 NULL Standard Practice
TES-663 NULL Standard Practice
TES-663F1 NULL Standard Practice
TES-671DS1 NULL Standard Practice
TES-752 NULL Standard Practice
TES-773 NULL Standard Practice
TES-910 NULL Standard Practice
TES-912 NULL Standard Practice
TES-912C1 NULL Standard Practice
TES-913 NULL Standard Practice
TES-930 NULL Standard Practice
TES-931 NULL Standard Practice
TES-932 NULL Standard Practice
TES-972 NULL Standard Practice
TRS-510 NULL Standard Practice
TRS-510F1 NULL Standard Practice
TRS-510F2 NULL Standard Practice
TRS-510F3 NULL Standard Practice
TRS-510F4 NULL Standard Practice
TRS-510P1 NULL Standard Practice
TRS-510P2 NULL Standard Practice
TRS-510P3 NULL Standard Practice
TRS-510P4 NULL Standard Practice
TRS-510P5 NULL Standard Practice
TRS-510P6 NULL Standard Practice
TES-501 NULL Standard Practice
TES-504 NULL Standard Practice
TES-510 NULL Standard Practice
TES-510C1 NULL Standard Practice
RRD-1352-008 OPERATIONS Miscellaneous
RRD-1352-009 OPERATIONS Miscellaneous
RRD-1353-001 OPERATIONS Miscellaneous
TES-510D1 NULL Standard Practice
TES-510D2 NULL Standard Practice
TES-510D3 NULL Standard Practice
TES-517 NULL Standard Practice
TES-521 T1CB1S01 NULL Standard Practice
TES-521 T1CB2S01 NULL Standard Practice
TES-521 T1CB2S98 NULL Standard Practice
TES-521 T1CB2S99 NULL Standard Practice
TES-521 T3CB1S01 NULL Standard Practice
TES-521 T3CB2S01 NULL Standard Practice
TES-521 T3CB2S98 NULL Standard Practice
TES-521 T3CB2S99 NULL Standard Practice
TES-521 T6CB1S01 NULL Standard Practice
TES-521 T6CB2S01 NULL Standard Practice
TES-521 T9CB1S01 NULL Standard Practice
TES-521 T9CB2S01 NULL Standard Practice
TES-521 T15CB1S01 NULL Standard Practice
TES-521 T15CB2S01 NULL Standard Practice
TES-522 T1CH2S97 NULL Standard Practice
TES-522 T1CH2S99 NULL Standard Practice
TES-522 T3CH2S97 NULL Standard Practice
TES-522 T3CH2S99 NULL Standard Practice
TES-522 T6CH2S99 NULL Standard Practice
TES-522 T9CH2S99 NULL Standard Practice
TES-522 T15CH2S99 NULL Standard Practice
TES-523 T1CJ1S01 NULL Standard Practice
TES-523 T1CK1S01 NULL Standard Practice
TES-523 T1CL1S01 NULL Standard Practice
TES-523 T1CM1S01 NULL Standard Practice
TES-523 T3CJ1S01 NULL Standard Practice
TES-523 T3CK1S01 NULL Standard Practice
TES-523 T3CL1S01 NULL Standard Practice
TES-523 T3CM1S01 NULL Standard Practice
TES-523 T6CJ1S01 NULL Standard Practice
TES-523 T6CK1S01 NULL Standard Practice
TES-523 T6CL1S01 NULL Standard Practice
TES-523 T6CM1S01 NULL Standard Practice
TES-523 T9CJ1S01 NULL Standard Practice
TES-523 T9CK1S01 NULL Standard Practice
TES-523 T9CL1S01 NULL Standard Practice
TES-523 T9CM1S01 NULL Standard Practice
TES-523 T15CJ1S01 NULL Standard Practice
TES-523 T15CK1S01 NULL Standard Practice
TES-523 T15CL1S01 NULL Standard Practice
TES-523 T15CM1S01 NULL Standard Practice
TES-524 T1SA0B01 NULL Standard Practice
TES-524 T1SA0S01 NULL Standard Practice
TES-524 T1SA1S99 NULL Standard Practice
TES-524 T3SA0B01 NULL Standard Practice
TES-524 T3SA0S01 NULL Standard Practice
TES-524 T3SA1S99 NULL Standard Practice
TES-524 T6SA0S01 NULL Standard Practice
TES-524 T9SA0S01 NULL Standard Practice
TES-524 T15SA0S01 NULL Standard Practice
TES-524 T1SD0S01 NULL Standard Practice
TES-524 T1SD0S96 NULL Standard Practice
TES-524 T1SD1S99 NULL Standard Practice
TES-524 T1SD2S94 NULL Standard Practice
TES-524 T3SD0S01 NULL Standard Practice
TES-524 T3SD1S99 NULL Standard Practice
TES-524 T6SD0S01 NULL Standard Practice
TES-524 T9SD0S01 NULL Standard Practice
TES-524 T15SD0S01 NULL Standard Practice
TES-524 T1SH1S94 NULL Standard Practice
TES-524 T3SH1S94 NULL Standard Practice
TES-524 T6SJ0S01 NULL Standard Practice
TES-524 T6SJ1S01 NULL Standard Practice
TES-524 T9SJ0S01 NULL Standard Practice
TES-524 T9SJ1S01 NULL Standard Practice
TES-524 T15SJ0S01 NULL Standard Practice
TES-524 T15SJ1S01 NULL Standard Practice
TES-524 T1SP1S01 NULL Standard Practice
TES-524 T3SP1S01 NULL Standard Practice
TES-524 T6SP1S01 NULL Standard Practice
TES-525 T1NM0B01 NULL Standard Practice
TES-525 T1NM0S01 NULL Standard Practice
TES-525 T3NM0B01 NULL Standard Practice
TES-525 T3NM0S01 NULL Standard Practice
TES-525 T1NU0B01 NULL Standard Practice
TES-525 T1NU0S01 NULL Standard Practice
TES-525 T3NU0B01 NULL Standard Practice
TES-525 T3NU0S01 NULL Standard Practice
TES-531 T1CS1S02 NULL Standard Practice
TES-531 T3CS1S02 NULL Standard Practice
TES-531 T6CS1S01 NULL Standard Practice
TES-531 T9CS1S01 NULL Standard Practice
TES-531 T15CS1S01 NULL Standard Practice
TES-532 T12CS1T01 NULL Standard Practice
TES-532 T12CS2T01 NULL Standard Practice
TES-532 T12PD0H95U NULL Standard Practice
TES-533 T12CG0T95 NULL Standard Practice
TES-533 T12PD0H95R1 NULL Standard Practice
TES-533 T12PD0H95R2 NULL Standard Practice
TES-534 T12PD0H95B NULL Standard Practice
TES-550 NULL Standard Practice
TES-552 NULL Standard Practice
TES-552C1 NULL Standard Practice
TES-552C2 NULL Standard Practice
TES-552C3 NULL Standard Practice
TES-552C4 NULL Standard Practice
TES-552C5 NULL Standard Practice
TES-552C6 NULL Standard Practice
TES-553 NULL Standard Practice
TES-553C1 NULL Standard Practice
TES-553C2 NULL Standard Practice
TES-553C3 NULL Standard Practice
TES-554 NULL Standard Practice
TES-554C1 NULL Standard Practice
TES-554C2 NULL Standard Practice
TES-554C3 NULL Standard Practice
TES-554C4 NULL Standard Practice
TES-554C5 NULL Standard Practice
TES-554C6 NULL Standard Practice
TES-554C7 NULL Standard Practice
TES-555 NULL Standard Practice
TES-555C1 NULL Standard Practice
TES-555C2 NULL Standard Practice
TES-555C3 NULL Standard Practice
TES-555C4 NULL Standard Practice
TES-555C5 NULL Standard Practice
TES-555C6 NULL Standard Practice
TES-556 NULL Standard Practice
TES-556C1 NULL Standard Practice
TES-556C2 NULL Standard Practice
TES-556C3 NULL Standard Practice
TES-556C4 NULL Standard Practice
TES-556C5 NULL Standard Practice
TES-557 NULL Standard Practice
TES-557C1 NULL Standard Practice
TES-557C2 NULL Standard Practice
TES-557C3 NULL Standard Practice
TES-557C4 NULL Standard Practice
TES-557C5 NULL Standard Practice
TES-559C1 NULL Standard Practice
TES-559DS NULL Standard Practice
TES-560 NULL Standard Practice
TES-561 NULL Standard Practice
TES-762 NULL Standard Practice
IG-50 DOCUMENT CONTROL Miscellaneous
RSP-1706-000 SAFETY Safety
RSD-42-01-14 VESSEL Fixed Equipment
RSD-42-01-15 VESSEL Fixed Equipment
RSD-42-01-17 VESSEL Fixed Equipment
RRD-1250-803 UTILITIES Environmental and Utility Equipment
RRD-1352-006 OPERATIONS Miscellaneous
SP-90-16-ATT1 INSPECTION Inspection and Quality Control
SP-90-16 INSPECTION Inspection and Quality Control
SP-90-23 INSPECTION Inspection and Quality Control
SP-50-03-CK2AV LOW TEMP Piping & Plant Layout
SP-95-01-FORM01 MATERIAL SELECTION Materials and Welding
IG-51 MATERIAL SELECTION Materials and Welding
REF-1051-BCR DOCUMENT CONTROL Standard Practice
RRD-1620-008 PLANNING Miscellaneous
RSD-75-01-01 MOUNTING Instrumentation
RSD-75-01-02 MOUNTING Instrumentation
RSD-75-01-03 MOUNTING Instrumentation
RSD-75-01-04 MOUNTING Instrumentation
RSD-75-01-05 MOUNTING Instrumentation
RSD-75-01-06 MOUNTING Instrumentation
RSD-75-01-07 MOUNTING Instrumentation
RSD-75-01-08 MOUNTING Instrumentation
RSD-75-01-09 MOUNTING Instrumentation
RSD-75-01-10 MOUNTING Instrumentation
RSD-75-01-11 MOUNTING Instrumentation
RSD-75-01-12 MOUNTING Instrumentation
RSD-75-01-13 MOUNTING Instrumentation
RSD-75-01-14 MOUNTING Instrumentation
RSD-75-01-15 MOUNTING Instrumentation
RRD-1250-701-DS01 PROCESS DESIGN Fixed Equipment
RRD-1250-701-DS-INJ PROCESS DESIGN Fixed Equipment
RRD-1250-701-DS-MP PROCESS DESIGN Fixed Equipment
RRD-1250-701 PROCESS DESIGN Fixed Equipment
IG-53 PSM/RMP Safety
RRD-1352-007 OPERATIONS Miscellaneous
RRD-1143-000 ROTATING EQUIPMENT Rotating Equipment
SP-42-20 TANK Fixed Equipment
RSD-60-38-002 GROUNDING Electrical Systems
RSD-60-38-004 GROUNDING Electrical Systems
RSD-60-38-005 GROUNDING Electrical Systems
RSD-60-38-006 GROUNDING Electrical Systems
RSD-60-38-007 GROUNDING Electrical Systems
RSD-60-38-008 GROUNDING Electrical Systems
RSD-60-38-009 GROUNDING Electrical Systems
RSD-60-38-010 GROUNDING Electrical Systems
RSD-60-38-011 GROUNDING Electrical Systems
RSD-60-38-012 GROUNDING Electrical Systems
RSD-60-38-013 GROUNDING Electrical Systems
RSD-60-38-014 GROUNDING Electrical Systems
RSD-60-38-015 GROUNDING Electrical Systems
RSD-60-38-020 GROUNDING Electrical Systems
RSD-60-38-023 GROUNDING Electrical Systems
RSD-60-38-024 GROUNDING Electrical Systems
RSD-60-38-025 GROUNDING Electrical Systems
RSD-60-38-029 GROUNDING Electrical Systems
RSD-60-38-030 GROUNDING Electrical Systems
RSD-60-38-038 GROUNDING Electrical Systems
RSD-60-38-039 GROUNDING Electrical Systems
RSD-60-38-040 GROUNDING Electrical Systems
RSD-60-38-041 GROUNDING Electrical Systems
RSD-60-38-042 CABLE TRAY Electrical Systems
RSD-60-38-043 CABLE TRAY Electrical Systems
RSD-60-38-044 CABLE TRAY Electrical Systems
RSD-60-38-045 CABLE TRAY Electrical Systems
RSD-60-38-046 CABLE TRAY Electrical Systems
RSD-60-38-047 CABLE TRAY Electrical Systems
RSD-60-38-048 CABLE TRAY Electrical Systems
RSD-60-38-049 CABLE TRAY Electrical Systems
RSD-60-38-050 CONDUIT Electrical Systems
RSD-60-38-051 CONDUIT Electrical Systems
RSD-60-38-052 CONDUIT Electrical Systems
RSD-60-38-054 CONDUIT Electrical Systems
RSD-60-38-055 CONDUIT Electrical Systems
RSD-60-38-057 CONDUIT Electrical Systems
RSD-60-38-058 CONDUIT Electrical Systems
RSD-60-38-059 MOTORS Electrical Systems
RSD-60-38-060 MOTORS Electrical Systems
RSD-60-38-061 MOTORS Electrical Systems
RSD-60-38-062 MOTORS Electrical Systems
RSD-60-38-063 MOTORS Electrical Systems
RSD-60-38-064 MOTORS Electrical Systems
RSD-60-38-065 MOTORS Electrical Systems
RSD-60-38-066 MOTORS Electrical Systems
RSD-60-38-067 MOTORS Electrical Systems
RSD-60-38-068 MOTORS Electrical Systems
RSD-60-38-069 MOTORS Electrical Systems
RSD-60-38-070 MOTORS Electrical Systems
RSD-60-38-071 MOTORS Electrical Systems
RSD-60-38-072 MOTORS Electrical Systems
RSD-60-38-073 MOTORS Electrical Systems
RSD-60-38-074 MOTORS Electrical Systems
RSD-60-38-075 MOTORS Electrical Systems
RSD-60-38-076 MOTORS Electrical Systems
RSD-60-38-077 SWITCHGEAR Electrical Systems
RSD-60-38-079 MISC Electrical Systems
RSD-60-38-080 MISC Electrical Systems
RSD-60-38-081 MOTORS Electrical Systems
RSD-60-38-083 MOTORS Electrical Systems
RSD-60-38-086 MOTORS Electrical Systems
RSD-60-38-087 MOTORS Electrical Systems
RSD-60-38-088 MOTORS Electrical Systems
RSD-60-38-089 MOTORS Electrical Systems
RSD-60-38-090 MOTORS Electrical Systems
RSD-60-38-091 MOTORS Electrical Systems
RSD-60-38-092 MOTORS Electrical Systems
RSD-60-38-093 MOTORS Electrical Systems
RSD-60-38-094 MOTORS Electrical Systems
RSD-60-38-095 MOTORS Electrical Systems
RSD-60-38-096 MOTORS Electrical Systems
RSD-60-38-097 MOTORS Electrical Systems
RSD-60-38-098 LIGHTING Electrical Systems
RSD-60-38-099 LIGHTING Electrical Systems
RSD-60-38-100 LIGHTING Electrical Systems
RSD-60-38-101 LIGHTING Electrical Systems
RSD-60-38-102 LIGHTING Electrical Systems
RSD-60-38-103 LIGHTING Electrical Systems
RSD-60-38-104 LIGHTING Electrical Systems
RSD-60-38-105 LIGHTING Electrical Systems
RSD-60-38-106 LIGHTING Electrical Systems
RSD-60-38-107 SWITCHES Electrical Systems
RSD-60-38-108 SWITCHES Electrical Systems
RSD-60-38-109 SWITCHES Electrical Systems
RSD-60-38-110 PANEL BOARDS Electrical Systems
RSD-60-38-111 PANEL BOARDS Electrical Systems
RSD-60-38-112 PANEL BOARDS Electrical Systems
RSD-60-38-113 MISC Electrical Systems
RSD-60-38-114 UG CONDUIT Electrical Systems
RSD-60-38-115 UG CONDUIT Electrical Systems
RSD-60-38-116 UG CONDUIT Electrical Systems
RSP-1506-000 QUALITY Product Quality
RSD-70-02-01 TEMPERATURE Instrumentation
RSD-70-02-02 TEMPERATURE Instrumentation
RSD-70-07-01 LEVEL Instrumentation
RSD-70-07-02 LEVEL Instrumentation
RSD-70-07-03 LEVEL Instrumentation
RSD-70-07-04 LEVEL Instrumentation
RSD-70-07-05 LEVEL Instrumentation
RSD-70-07-06 LEVEL Instrumentation
RSD-70-09-01 CONTROL VALVES Instrumentation
RSD-70-09-02 CONTROL VALVES Instrumentation
IG-56 INSPECTION Inspection and Quality Control
IG-55 CONTROLS Controls
SP-50-42 PIPING Piping & Plant Layout
SP-50-42-DS01 PIPING Piping & Plant Layout
RSD-70-03-01 PRESSURE GAGE Instrumentation
RSD-70-03-02 PRESSURE GAGE Instrumentation
RSD-70-03-03 PRESSURE GAGE Instrumentation
RSD-70-03-04 PRESSURE GAGE Instrumentation
RSD-70-03-05 PRESSURE GAGE Instrumentation
RSD-70-03-06 PRESSURE Instrumentation
RSD-70-03-07 PRESSURE Instrumentation
RSD-70-03-08 PRESSURE Instrumentation
RSD-70-03-09 PRESSURE Instrumentation
RSD-70-03-10 PRESSURE Instrumentation
RSD-70-03-11 PRESSURE Instrumentation
RSD-70-03-12 PRESSURE Instrumentation
RSD-70-03-13 DIFF PRESSURE Instrumentation
RSD-70-03-14 DIFF PRESSURE Instrumentation
RSD-70-03-15 DIFF PRESSURE Instrumentation
RSD-70-03-16 DIFF PRESSURE Instrumentation
RSD-70-03-17 DIFF PRESSURE Instrumentation
RSD-70-03-18 DIFF PRESSURE Instrumentation
RSD-70-03-19 PRESSURE GAGE Instrumentation
RSD-70-03-20 PRESSURE GAGE Instrumentation
RSD-70-03-21 PRESSURE GAGE Instrumentation
RSD-70-03-22 PRESSURE GAGE Instrumentation
RSD-70-03-23 PRESSURE GAGE Instrumentation
RSD-70-03-24 PRESSURE GAGE Instrumentation
RSD-70-03-25 PRESSURE Instrumentation
RSD-70-03-26 PRESSURE Instrumentation
RSD-70-03-27 PRESSURE Instrumentation
RSD-70-03-28 PRESSURE Instrumentation
RSD-70-03-29 PRESSURE Instrumentation
RSD-70-03-30 DIFF PRESSURE Instrumentation
RSD-70-03-31 DIFF PRESSURE Instrumentation
RSD-70-03-32 DIFF PRESSURE Instrumentation
RSD-70-05-01 FLOW Instrumentation
RSD-70-05-02 FLOW Instrumentation
RSD-70-05-03 FLOW Instrumentation
RSD-70-05-04 FLOW Instrumentation
RSD-70-05-05 FLOW Instrumentation
RSD-70-05-06 FLOW Instrumentation
RSD-70-05-07 FLOW Instrumentation
RSD-70-05-08 FLOW Instrumentation
RSD-70-05-09 FLOW Instrumentation
RSD-70-05-10 FLOW Instrumentation
RSD-70-05-11 FLOW Instrumentation
RSD-70-05-12 FLOW Instrumentation
RSD-70-05-13 FLOW Instrumentation
RSD-70-05-14 FLOW Instrumentation
RSD-70-05-15 FLOW Instrumentation
RSD-70-05-16 FLOW Instrumentation
RRD-1250-702 PROCESS DESIGN Fixed Equipment
RSP-1503-020-ATT1 QUALITY Product Quality
RSP-1503-020-ATT2 QUALITY Product Quality
RSP-1503-020-ATT3 QUALITY Product Quality
RSP-1503-020-ATT4 QUALITY Product Quality
RSP-1503-020-ATT5 QUALITY Product Quality
RSP-1503-020-FORM01 QUALITY Product Quality
RRD-1901-001 PROJECTS Miscellaneous
_SPP CROSS PIPING Piping & Plant Layout
RRD-1908-000 PROJECTS Miscellaneous
RRD-1908-020 PROJECTS Miscellaneous
RRD-1908-030 PROJECTS Miscellaneous
RRD-1908-040 PROJECTS Miscellaneous
RRD-1908-050 PROJECTS Miscellaneous
RRD-1908-060 PROJECTS Miscellaneous
RRD-1908-070 PROJECTS Miscellaneous
_AND CROSS PIPING Piping & Plant Layout
RRD-1722-000-TEMP1 ENVIRONMENTAL Environmental and Utility Equipment
RRD-1722-000 ENVIRONMENTAL Environmental and Utility Equipment
SP-75-04-FORM01 INSTRUMENTATION Instrumentation
SP-75-04-FORM02 INSTRUMENTATION Instrumentation
SP-75-05-EC INSTRUMENTATION Instrumentation
SP-75-05-HIC INSTRUMENTATION Instrumentation
RRD-1250-003 PROCESS DESIGN Fixed Equipment
RRD-1250-004 PROCESS DESIGN Fixed Equipment
RRD-1250-200 PROCESS DESIGN Fixed Equipment
RRD-1250-804 PROCESS DESIGN Fixed Equipment
RSD-43-01-01 COMPRESSOR Rotating Equipment
spec_class revision_no plant_name revision_date
CORE SPECIFICATION 15 ALL REFINERIES 8/5/2016
CORE SPECIFICATION 15 ALL REFINERIES 2/27/2019
CORE LINE CLASS 17 ALL REFINERIES 12/21/2018
CORE LINE CLASS 13 ALL REFINERIES 3/10/2017
CORE LINE CLASS 14 ALL REFINERIES 12/21/2018
CORE LINE CLASS 12 ALL REFINERIES 12/21/2018
CORE LINE CLASS 14 ALL REFINERIES 12/21/2018
CORE LINE CLASS 15 ALL REFINERIES 12/21/2018
CORE LINE CLASS 14 ALL REFINERIES 12/21/2018
CORE LINE CLASS 17 ALL REFINERIES 12/21/2018
CORE LINE CLASS 10 ALL REFINERIES 2/22/2017
CORE LINE CLASS 15 ALL REFINERIES 12/21/2018
CORE LINE CLASS 10 ALL REFINERIES 12/21/2018
CORE LINE CLASS 13 ALL REFINERIES 12/21/2018
CORE LINE CLASS 14 ALL REFINERIES 12/21/2018
CORE LINE CLASS 15 ALL REFINERIES 2/1/2019
CORE LINE CLASS 14 ALL REFINERIES 12/21/2018
CORE LINE CLASS 12 ALL REFINERIES 12/21/2018
CORE LINE CLASS 12 ALL REFINERIES 3/10/2017
CORE LINE CLASS 16 ALL REFINERIES 12/21/2018
CORE LINE CLASS 12 ALL REFINERIES 12/21/2018
CORE LINE CLASS 11 ALL REFINERIES 12/21/2018
CORE LINE CLASS 16 ALL REFINERIES 12/21/2018
CORE LINE CLASS 14 ALL REFINERIES 12/21/2018
CORE LINE CLASS 14 ALL REFINERIES 12/21/2018
CORE LINE CLASS 14 ALL REFINERIES 12/21/2018
CORE LINE CLASS 14 ALL REFINERIES 12/21/2018
CORE LINE CLASS 19 ALL REFINERIES 3/10/2017
CORE LINE CLASS 12 ALL REFINERIES 3/10/2017
CORE LINE CLASS 8 ALL REFINERIES 2/22/2017
CORE LINE CLASS 12 ALL REFINERIES 12/21/2018
CORE LINE CLASS 9 ALL REFINERIES 3/10/2017
CORE LINE CLASS 10 ALL REFINERIES 12/21/2018
CORE LINE CLASS 11 ALL REFINERIES 12/21/2018
CORE LINE CLASS 15 ALL REFINERIES 12/21/2018
CORE LINE CLASS 13 ALL REFINERIES 12/21/2018
CORE LINE CLASS 13 ALL REFINERIES 12/21/2018
CORE LINE CLASS 12 ALL REFINERIES 12/21/2018
CORE LINE CLASS 13 ALL REFINERIES 12/21/2018
CORE LINE CLASS 12 ALL REFINERIES 12/21/2018
CORE LINE CLASS 11 ALL REFINERIES 12/21/2018
CORE LINE CLASS 11 ALL REFINERIES 5/31/2019
CORE LINE CLASS 12 ALL REFINERIES 6/4/2019
CORE LINE CLASS 8 ALL REFINERIES 10/17/2017
CORE LINE CLASS 8 ALL REFINERIES 1/10/2017
CORE LINE CLASS 7 ALL REFINERIES 8/14/2018
CORE LINE CLASS 5 ALL REFINERIES 1/10/2017
CORE LINE CLASS 12 ALL REFINERIES 2/22/2017
CORE LINE CLASS 18 ALL REFINERIES 12/21/2018
CORE LINE CLASS 21 ALL REFINERIES 12/21/2018
CORE LINE CLASS 15 ALL REFINERIES 12/21/2018
CORE LINE CLASS 13 ALL REFINERIES 12/21/2018
CORE LINE CLASS 12 ALL REFINERIES 12/21/2018
CORE LINE CLASS 14 ALL REFINERIES 12/21/2018
CORE LINE CLASS 12 ALL REFINERIES 12/21/2018
CORE LINE CLASS 12 ALL REFINERIES 12/21/2018
CORE LINE CLASS 9 ALL REFINERIES 1/6/2017
CORE SPECIFICATION 39 ALL REFINERIES 11/19/2018
CORE SPECIFICATION 23 ALL REFINERIES 3/23/2018
CORE SPECIFICATION 19 ALL REFINERIES 9/4/2018
CORE SPECIFICATION 26 ALL REFINERIES 1/3/2019
CORE SPECIFICATION 15 ALL REFINERIES 6/2/2016
CORE SPECIFICATION 14 ALL REFINERIES 6/2/2016
CORE SPECIFICATION 16 ALL REFINERIES 6/2/2016
CORE SPECIFICATION 17 ALL REFINERIES 6/2/2016
CORE SPECIFICATION 17 ALL REFINERIES 3/23/2018
CORE SPECIFICATION 15 ALL REFINERIES 10/14/2019
CORE SPECIFICATION 12 ALL REFINERIES 5/2/2019
CORE SPECIFICATION 13 ALL REFINERIES 6/2/2016
CORE SPECIFICATION 19 ALL REFINERIES 11/7/2016
CORE SPECIFICATION 10 ALL REFINERIES 1/23/2017
CORE SPECIFICATION 19 ALL REFINERIES 5/2/2017
CORE SPECIFICATION 12 ALL REFINERIES 3/13/2017
CORE SPECIFICATION 11 ALL REFINERIES 11/19/2018
CORE SPECIFICATION 9 ALL REFINERIES 2/27/2019
CORE SPECIFICATION 11 ALL REFINERIES 1/2/2018
CORE SPECIFICATION 11 ALL REFINERIES 3/29/2019
CORE SPECIFICATION 10 ALL REFINERIES 3/26/2018
CORE SPECIFICATION 30 ALL REFINERIES 12/4/2018
CORE SPECIFICATION 18 ALL REFINERIES 10/23/2017
CORE SPECIFICATION 12 ALL REFINERIES 8/15/2016
CORE SPECIFICATION 10 ALL REFINERIES 12/2/2016
CORE SPECIFICATION 15 ALL REFINERIES 9/20/2017
CORE SPECIFICATION 13 ALL REFINERIES 6/28/2016
CORE SPECIFICATION 17 ALL REFINERIES 3/22/2017
CORE SPECIFICATION 13 ALL REFINERIES 6/28/2016
CORE SPECIFICATION 12 ALL REFINERIES 12/22/2015
CORE SPECIFICATION 12 ALL REFINERIES 4/18/2018
CORE SPECIFICATION 18 ALL REFINERIES 5/11/2018
CORE SPECIFICATION 7 ALL REFINERIES 4/11/2019
CORE SPECIFICATION 21 ALL REFINERIES 4/9/2018
CORE SPECIFICATION 12 ALL REFINERIES 3/21/2018
CORE SPECIFICATION 24 ALL REFINERIES 3/26/2018
CORE SPECIFICATION 22 ALL REFINERIES 3/26/2018
CORE SPECIFICATION 19 ALL REFINERIES 12/5/2016
CORE SPECIFICATION 33 ALL REFINERIES 8/7/2019
CORE SPECIFICATION 17 ALL REFINERIES 9/14/2018
CORE SPECIFICATION 12 ALL REFINERIES 3/9/2017
CORE SPECIFICATION 11 ALL REFINERIES 6/16/2016
CORE SPECIFICATION 8 ALL REFINERIES 9/4/2018
REFINING STANDARD PRACTICE 6 ALL REFINERIES 1/30/2018
CORE SPECIFICATION 2 ALL REFINERIES 10/26/2016
CORE SPECIFICATION 3 ALL REFINERIES 9/13/2018
CORE SPECIFICATION 29 ALL REFINERIES 1/3/2019
CORE SPECIFICATION 10 ALL REFINERIES 8/20/2018
CORE SPECIFICATION 16 ALL REFINERIES 1/4/2019
CORE SPECIFICATION 16 ALL REFINERIES 2/22/2018
LOCAL SPECIFICATIONS 3 GARYVILLE NULL
CORE SPECIFICATION 10 ALL REFINERIES 8/15/2016
CORE SPECIFICATION 11 ALL REFINERIES 11/7/2016
CORE SPECIFICATION 19 ALL REFINERIES 10/14/2019
CORE SPECIFICATION 8 ALL REFINERIES 7/23/2018
CORE SPECIFICATION 12 ALL REFINERIES 10/18/2017
REFINING STANDARD PRACTICE 11 ALL REFINERIES 10/17/2017
CORE SPECIFICATION 10 ALL REFINERIES 6/7/2018
REFINING STANDARD PRACTICE 11 ALL REFINERIES 3/23/2018
REFINING STANDARD PRACTICE 7 ALL REFINERIES 5/4/2015
REFINING STANDARD PRACTICE 6 ALL REFINERIES 12/14/2016
REFINING STANDARD PRACTICE 14 ALL REFINERIES 8/10/2018
REFINING STANDARD PRACTICE 10 ALL REFINERIES 7/29/2019
REFINING STANDARD PRACTICE 4 ALL REFINERIES 9/29/2014
REFINING POLICY 9 ALL REFINERIES 10/7/2013
REFINING STANDARD PRACTICE 11 ALL REFINERIES 4/17/2018
REFINING STANDARD PRACTICE 7 ALL REFINERIES 2/14/2018
REFINING STANDARD PRACTICE 11 ALL REFINERIES 3/6/2017
REFINING STANDARD PRACTICE 11 ALL REFINERIES 12/11/2018
REFINING STANDARD PRACTICE 5 ALL REFINERIES 1/31/2019
REFINING STANDARD PRACTICE 10 ALL REFINERIES 5/16/2017
REFINING REFERENCE DOCUME 5 ALL REFINERIES 12/4/2017
REFINING REFERENCE DOCUME 4 ALL REFINERIES 1/25/2018
LOCAL SPECIFICATIONS 0 ROBINSON NULL
REFINING STANDARD PRACTICE 9 ALL REFINERIES 1/22/2019
CORE SPECIFICATION 3 ALL REFINERIES 9/12/2018
CORE SPECIFICATION 3 ALL REFINERIES 5/31/2017
CORE SPECIFICATION 5 ALL REFINERIES 9/14/2018
CORE SPECIFICATION 4 ALL REFINERIES 9/14/2018
CORE SPECIFICATION 4 ALL REFINERIES 9/14/2018
CORE SPECIFICATION 6 ALL REFINERIES 2/27/2019
CORE SPECIFICATION 4 ALL REFINERIES 2/27/2019
CORE SPECIFICATION 5 ALL REFINERIES 8/17/2017
CORE SPECIFICATION 5 ALL REFINERIES 8/17/2017
CORE SPECIFICATION 7 ALL REFINERIES 9/12/2018
CORE SPECIFICATION 5 ALL REFINERIES 9/12/2018
CORE SPECIFICATION 7 ALL REFINERIES 2/27/2019
CORE SPECIFICATION 4 ALL REFINERIES 1/17/2017
CORE SPECIFICATION 3 ALL REFINERIES 10/27/2016
CORE SPECIFICATION 5 ALL REFINERIES 8/5/2016
CORE SPECIFICATION 4 ALL REFINERIES 10/18/2017
CORE SPECIFICATION 7 ALL REFINERIES 4/1/2019
CORE SPECIFICATION 6 ALL REFINERIES 4/10/2018
CORE SPECIFICATION 14 ALL REFINERIES 1/16/2017
CORE SPECIFICATION 20 ALL REFINERIES 4/13/2017
CORE SPECIFICATION 19 ALL REFINERIES 6/16/2016
CORE SPECIFICATION 21 ALL REFINERIES 2/25/2019
CORE SPECIFICATION 22 ALL REFINERIES 10/1/2019
CORE SPECIFICATION 7 ALL REFINERIES 8/16/2016
REFINING REFERENCE DOCUME 9 ALL REFINERIES 2/20/2018
CORE SPECIFICATION 7 ALL REFINERIES 6/2/2016
CORE SPECIFICATION 8 ALL REFINERIES 6/2/2016
CORE SPECIFICATION 11 ALL REFINERIES 8/5/2016
CORE SPECIFICATION 10 ALL REFINERIES 1/10/2018
REFINING REFERENCE DOCUME 3 ALL REFINERIES 2/7/2018
REFINING REFERENCE DOCUME 7 ALL REFINERIES 3/30/2017
REFINING STANDARD PRACTICE 7 ALL REFINERIES 10/15/2018
CORE SPECIFICATION 14 ALL REFINERIES 7/10/2019
REFINING REFERENCE DOCUME 4 ALL REFINERIES 2/2/2018
CORE LINE CLASS 9 ALL REFINERIES 12/21/2018
CORE LINE CLASS 9 ALL REFINERIES 12/21/2018
CORE LINE CLASS 7 ALL REFINERIES 12/21/2018
CORE LINE CLASS 9 ALL REFINERIES 12/21/2018
CORE SPECIFICATION 10 ALL REFINERIES 1/25/2018
STANDARD DRAWINGS 3 ALL REFINERIES 9/22/1989
STANDARD DRAWINGS 4 ALL REFINERIES 5/2/1988
STANDARD DRAWINGS 6 ALL REFINERIES 4/29/2016
STANDARD DRAWINGS 5 ALL REFINERIES 4/25/2018
SP FORM 13 ALL REFINERIES 7/29/2011
CORE SPECIFICATION 17 ALL REFINERIES 4/15/2019
CORE SPECIFICATION 26 ALL REFINERIES 7/10/2019
REFINING STANDARD PRACTICE 6 ALL REFINERIES 12/3/2018
CORE SPECIFICATION 5 ALL REFINERIES 1/25/2018
REFINING STANDARD PRACTICE 8 ALL REFINERIES 1/25/2018
REFINING STANDARD PRACTICE 7 ALL REFINERIES 1/22/2018
CORE SPECIFICATION 21 ALL REFINERIES 6/18/2018
REFINING STANDARD PRACTICE 15 ALL REFINERIES 6/10/2019
REFINING STANDARD PRACTICE 7 ALL REFINERIES 6/20/2019
REFINING STANDARD PRACTICE 8 ALL REFINERIES 6/20/2019
REFINING STANDARD PRACTICE 8 ALL REFINERIES 8/1/2017
CORE SPECIFICATION 7 ALL REFINERIES 9/12/2016
REFINING POLICY 15 ALL REFINERIES 1/4/2019
REFINING STANDARD PRACTICE 5 ALL REFINERIES 6/12/2017
REFINING REFERENCE DOCUME 8 ALL REFINERIES 6/21/2019
REFINING REFERENCE DOCUME 6 ALL REFINERIES 9/27/2018
CORE SPECIFICATION 5 ALL REFINERIES 6/16/2016
REFINING STANDARD PRACTICE 4 ALL REFINERIES 7/9/2014
REFINING STANDARD PRACTICE 4 ALL REFINERIES 7/11/2017
RSP FORM 6 ALL REFINERIES 3/25/2013
RSP FORM 6 ALL REFINERIES 3/25/2013
CORE SPECIFICATION 8 ALL REFINERIES 11/5/2018
SP FORM 3 ALL REFINERIES 11/5/2018
CORE SPECIFICATION 10 ALL REFINERIES 8/5/2016
CORE SPECIFICATION 5 ALL REFINERIES 11/6/2017
CORE SPECIFICATION 7 ALL REFINERIES 4/9/2018
CORE SPECIFICATION 6 ALL REFINERIES 11/9/2018
RSP FORM 5 ALL REFINERIES 1/22/2019
RSP FORM 5 ALL REFINERIES 5/3/2011
RSP FORM 4 ALL REFINERIES 5/3/2011
RSP FORM 6 ALL REFINERIES 9/14/2018
RSP FORM 5 ALL REFINERIES 9/14/2018
RSP FORM 5 ALL REFINERIES 2/27/2015
RSP FORM 6 ALL REFINERIES 1/25/2018
RSP FORM 4 ALL REFINERIES 5/3/2011
RSP FORM 6 ALL REFINERIES 3/27/2013
RSP FORM 6 ALL REFINERIES 9/14/2018
RSP FORM 4 ALL REFINERIES 5/3/2011
RSP FORM 4 ALL REFINERIES 5/3/2011
RSP FORM 4 ALL REFINERIES 5/3/2011
WITHDRAWN NA TEXAS CITY 12/2/2016
REFINING STANDARD PRACTICE 4 ALL REFINERIES 3/16/2016
REFINING STANDARD PRACTICE 7 ALL REFINERIES 9/7/2018
RSP FORM 0 ALL REFINERIES 11/1/2010
REFINING STANDARD PRACTICE 10 ALL REFINERIES 8/12/2019
REFINING STANDARD PRACTICE 9 ALL REFINERIES 4/5/2016
REFINING STANDARD PRACTICE 3 ALL REFINERIES 6/8/2018
REFINING STANDARD PRACTICE 4 ALL REFINERIES 4/8/2016
REFINING POLICY 10 ALL REFINERIES 6/4/2018
RSP FORM 0 ALL REFINERIES 2/25/2008
RSP FORM 0 ALL REFINERIES 2/25/2008
WITHDRAWN 0 TEXAS CITY 8/12/2003
WITHDRAWN 0 TEXAS CITY 8/12/2003
WITHDRAWN 2 TEXAS CITY 6/6/2006
WITHDRAWN 0 TEXAS CITY 8/12/2003
WITHDRAWN 0 TEXAS CITY 8/12/2003
WITHDRAWN 0 TEXAS CITY 8/12/2003
WITHDRAWN 0 TEXAS CITY 8/12/2003
WITHDRAWN NA TEXAS CITY 8/12/2003
WITHDRAWN 0 TEXAS CITY 8/12/2003
WITHDRAWN 0 TEXAS CITY 6/6/2006
WITHDRAWN 0 TEXAS CITY 8/12/2003
WITHDRAWN 0 TEXAS CITY 6/6/2006
WITHDRAWN 0 TEXAS CITY 6/6/2006
WITHDRAWN NA TEXAS CITY 8/12/2003
WITHDRAWN 0 TEXAS CITY 8/12/2003
WITHDRAWN 0 TEXAS CITY 5/23/2005
WITHDRAWN 0 TEXAS CITY 10/22/2003
WITHDRAWN 0 TEXAS CITY 10/22/2003
WITHDRAWN 1 TEXAS CITY 10/22/2003
WITHDRAWN 1 TEXAS CITY 10/22/2003
WITHDRAWN 1 TEXAS CITY 10/22/2003
WITHDRAWN 1 TEXAS CITY 10/22/2003
WITHDRAWN 1 TEXAS CITY 10/22/2003
WITHDRAWN 0 TEXAS CITY 11/3/2003
WITHDRAWN 0 TEXAS CITY 11/3/2003
WITHDRAWN 1 TEXAS CITY 9/28/2006
WITHDRAWN 0 TEXAS CITY 11/3/2003
WITHDRAWN 0 TEXAS CITY 9/28/2006
WITHDRAWN 0 TEXAS CITY 11/4/2003
WITHDRAWN 0 TEXAS CITY 9/28/2006
WITHDRAWN 0 TEXAS CITY 11/4/2003
WITHDRAWN 0 TEXAS CITY 10/22/2003
WITHDRAWN 1 TEXAS CITY 5/5/2006
WITHDRAWN 1 TEXAS CITY 5/5/2006
WITHDRAWN 1 TEXAS CITY 5/5/2006
WITHDRAWN 1 TEXAS CITY 5/5/2006
WITHDRAWN 1 TEXAS CITY 5/5/2006
WITHDRAWN 0 TEXAS CITY 12/3/2003
WITHDRAWN 0 TEXAS CITY 12/3/2003
WITHDRAWN 0 TEXAS CITY 12/3/2003
WITHDRAWN 0 TEXAS CITY 12/3/2003
WITHDRAWN 0 TEXAS CITY 12/3/2003
WITHDRAWN 0 TEXAS CITY 6/23/2004
WITHDRAWN 0 TEXAS CITY 5/1/2005
WITHDRAWN 0 TEXAS CITY 5/1/2005
WITHDRAWN 0 TEXAS CITY 5/1/2005
WITHDRAWN 0 TEXAS CITY 5/1/2005
WITHDRAWN 0 TEXAS CITY 5/1/2005
WITHDRAWN NA TEXAS CITY 5/1/2005
WITHDRAWN 0 TEXAS CITY 5/1/2005
WITHDRAWN 0 TEXAS CITY 5/1/2005
WITHDRAWN 0 TEXAS CITY 5/1/2005
WITHDRAWN 0 TEXAS CITY 5/1/2005
WITHDRAWN 0 TEXAS CITY 5/1/2005
WITHDRAWN 0 TEXAS CITY 5/1/2005
WITHDRAWN 0 TEXAS CITY 5/1/2005
WITHDRAWN 0 TEXAS CITY 5/1/2005
WITHDRAWN 0 TEXAS CITY 7/8/2004
WITHDRAWN 0 TEXAS CITY 6/27/2005
WITHDRAWN 1 TEXAS CITY 4/28/2006
WITHDRAWN 1 TEXAS CITY 2/16/2006
WITHDRAWN 0 TEXAS CITY 2/16/2006
WITHDRAWN 0 TEXAS CITY 2/16/2006
WITHDRAWN 0 TEXAS CITY 2/16/2006
WITHDRAWN 0 TEXAS CITY 2/16/2006
WITHDRAWN 0 TEXAS CITY 2/16/2006
WITHDRAWN 0 TEXAS CITY 2/16/2006
WITHDRAWN 0 TEXAS CITY 2/16/2006
WITHDRAWN 0 TEXAS CITY 2/16/2006
WITHDRAWN 0 TEXAS CITY 2/16/2006
WITHDRAWN 0 TEXAS CITY 2/16/2006
WITHDRAWN 0 TEXAS CITY 2/16/2006
WITHDRAWN 0 TEXAS CITY 9/1/2006
WITHDRAWN NA TEXAS CITY 7/12/2007
WITHDRAWN NA TEXAS CITY 9/28/2007
WITHDRAWN 0 TEXAS CITY 11/20/2003
WITHDRAWN 0 TEXAS CITY 11/20/2003
WITHDRAWN 0 TEXAS CITY 11/20/2003
WITHDRAWN 0 TEXAS CITY 11/20/2003
WITHDRAWN 0 TEXAS CITY 11/20/2003
WITHDRAWN 0 TEXAS CITY 11/20/2003
WITHDRAWN 0 TEXAS CITY 11/20/2003
WITHDRAWN 0 TEXAS CITY 11/20/2003
WITHDRAWN 0 TEXAS CITY 11/20/2003
WITHDRAWN 0 TEXAS CITY 11/20/2003
WITHDRAWN 0 TEXAS CITY 11/20/2003
WITHDRAWN 0 TEXAS CITY 11/20/2003
WITHDRAWN 1 TEXAS CITY 12/13/2010
WITHDRAWN 0 TEXAS CITY 11/20/2003
WITHDRAWN 0 TEXAS CITY 11/20/2003
WITHDRAWN 0 TEXAS CITY 11/20/2003
WITHDRAWN 0 TEXAS CITY 11/20/2003
WITHDRAWN 0 TEXAS CITY 11/20/2003
WITHDRAWN 0 TEXAS CITY 11/20/2003
WITHDRAWN 0 TEXAS CITY 11/20/2003
WITHDRAWN 0 TEXAS CITY 11/20/2003
WITHDRAWN 0 TEXAS CITY 11/20/2003
WITHDRAWN 0 TEXAS CITY 11/20/2003
WITHDRAWN 0 TEXAS CITY 11/20/2003
WITHDRAWN 0 TEXAS CITY 11/20/2003
WITHDRAWN 0 TEXAS CITY 3/17/2005
WITHDRAWN 0 TEXAS CITY 3/17/2005
WITHDRAWN 0 TEXAS CITY 3/18/2005
WITHDRAWN 0 TEXAS CITY 3/18/2005
WITHDRAWN 0 TEXAS CITY 3/18/2005
WITHDRAWN 0 TEXAS CITY 3/18/2005
WITHDRAWN 0 TEXAS CITY 3/18/2005
WITHDRAWN 0 TEXAS CITY 2/24/2005
WITHDRAWN 0 TEXAS CITY 3/28/2005
WITHDRAWN 2 TEXAS CITY 5/14/2012
WITHDRAWN 0 TEXAS CITY 2/21/2005
WITHDRAWN 0 TEXAS CITY 5/31/2005
WITHDRAWN 0 TEXAS CITY 6/6/2005
WITHDRAWN 0 TEXAS CITY 7/1/2005
WITHDRAWN 0 TEXAS CITY 6/24/2005
WITHDRAWN 0 TEXAS CITY 7/1/2005
WITHDRAWN 0 TEXAS CITY 7/1/2005
WITHDRAWN 0 TEXAS CITY 7/1/2005
WITHDRAWN 0 TEXAS CITY 7/1/2005
WITHDRAWN 0 TEXAS CITY 5/1/2006
WITHDRAWN 0 TEXAS CITY 2/22/2006
WITHDRAWN 1 TEXAS CITY 6/30/2006
WITHDRAWN 4 TEXAS CITY 6/30/2006
WITHDRAWN 4 TEXAS CITY 6/30/2006
WITHDRAWN 0 TEXAS CITY 6/30/2006
WITHDRAWN 0 TEXAS CITY 6/30/2006
WITHDRAWN 0 TEXAS CITY 6/30/2006
WITHDRAWN 0 TEXAS CITY 6/30/2006
WITHDRAWN 1 TEXAS CITY 7/18/2006
WITHDRAWN 1 TEXAS CITY 7/6/2006
WITHDRAWN 2 TEXAS CITY 7/5/2006
WITHDRAWN 2 TEXAS CITY 7/5/2006
WITHDRAWN 1 TEXAS CITY 7/5/2006
WITHDRAWN 1 TEXAS CITY 7/5/2006
WITHDRAWN 1 TEXAS CITY 7/5/2006
WITHDRAWN 0 TEXAS CITY 7/6/2006
WITHDRAWN 0 TEXAS CITY 7/6/2006
WITHDRAWN 2 TEXAS CITY 7/5/2006
WITHDRAWN 2 TEXAS CITY 7/5/2006
WITHDRAWN 1 TEXAS CITY 7/26/2006
WITHDRAWN 0 TEXAS CITY 7/26/2008
WITHDRAWN 0 TEXAS CITY 7/26/2008
WITHDRAWN 0 TEXAS CITY 7/26/2008
WITHDRAWN 4 TEXAS CITY 6/30/2006
WITHDRAWN 0 TEXAS CITY 9/13/2006
WITHDRAWN 0 TEXAS CITY 10/16/2006
WITHDRAWN 0 TEXAS CITY 9/13/2006
WITHDRAWN 0 TEXAS CITY 6/30/2006
WITHDRAWN 0 TEXAS CITY 9/18/2006
WITHDRAWN 1 TEXAS CITY 9/18/2006
WITHDRAWN 0 TEXAS CITY 9/18/2006
WITHDRAWN 1 TEXAS CITY 9/18/2006
WITHDRAWN 0 TEXAS CITY 7/18/2006
WITHDRAWN 1 TEXAS CITY 6/30/2006
WITHDRAWN 2 TEXAS CITY 9/18/2006
WITHDRAWN 0 TEXAS CITY 10/3/2006
WITHDRAWN 1 TEXAS CITY 10/3/2006
WITHDRAWN 0 TEXAS CITY 10/3/2006
WITHDRAWN 1 TEXAS CITY 10/3/2006
WITHDRAWN 2 TEXAS CITY 10/3/2006
WITHDRAWN 0 TEXAS CITY 10/4/2006
WITHDRAWN 0 TEXAS CITY 11/7/2006
WITHDRAWN 0 TEXAS CITY 2/8/2007
WITHDRAWN 0 TEXAS CITY 2/8/2007
REFINING STANDARD PRACTICE 2 ALL REFINERIES 6/19/2018
RSP FORM 1 ALL REFINERIES 1/15/2010
WITHDRAWN 0 TEXAS CITY 5/1/2007
RSP FORM 1 ALL REFINERIES 12/20/2010
RSP FORM 1 ALL REFINERIES 12/20/2010
CORE LINE CLASS 7 ALL REFINERIES 3/10/2017
REFINING STANDARD PRACTICE 10 ALL REFINERIES 9/17/2018
REFINING POLICY 8 ALL REFINERIES 10/7/2013
REFINING STANDARD PRACTICE 5 ALL REFINERIES 7/3/2019
STANDARD DRAWINGS 5 ALL REFINERIES 10/28/2014
REFINING STANDARD PRACTICE 14 ALL REFINERIES 9/12/2019
RSP FORM 6 ALL REFINERIES 8/1/2017
REFINING STANDARD PRACTICE 23 ALL REFINERIES 3/26/2018
RSP FORM 6 ALL REFINERIES 8/29/2017
RSP FORM 0 ALL REFINERIES 10/1/2008
REFINING STANDARD PRACTICE 5 ALL REFINERIES 8/21/2018
REFINING STANDARD PRACTICE 3 ALL REFINERIES 3/20/2015
WITHDRAWN 1 TEXAS CITY 5/27/2008
WITHDRAWN 1 TEXAS CITY 5/27/2008
WITHDRAWN 0 TEXAS CITY 6/27/2008
WITHDRAWN 0 TEXAS CITY 7/3/2008
WITHDRAWN 0 TEXAS CITY 5/29/2007
WITHDRAWN 0 TEXAS CITY 8/3/2007
WITHDRAWN 0 TEXAS CITY 8/3/2007
WITHDRAWN 0 TEXAS CITY 8/3/2007
WITHDRAWN 0 TEXAS CITY 7/3/2007
REFINING STANDARD PRACTICE 10 ALL REFINERIES 8/12/2019
REFINING STANDARD PRACTICE 7 ALL REFINERIES 2/15/2017
REFINING STANDARD PRACTICE 9 ALL REFINERIES 2/14/2017
REFINING STANDARD PRACTICE 9 ALL REFINERIES 1/16/2019
WITHDRAWN NA ALL REFINERIES 11/6/2015
WITHDRAWN NA ALL REFINERIES 11/6/2015
RSP FORM 1 ALL REFINERIES 12/2/2011
RSP FORM 1 ALL REFINERIES 12/2/2011
RSP FORM 2 ALL REFINERIES 11/6/2015
RSP FORM 2 ALL REFINERIES 11/6/2015
CORE SPECIFICATION 17 ALL REFINERIES 5/9/2019
RSP FORM 2 ALL REFINERIES 10/24/2012
REFINING STANDARD PRACTICE 4 ALL REFINERIES 10/21/2016
REFINING STANDARD PRACTICE 4 ALL REFINERIES 9/29/2017
REFINING STANDARD PRACTICE 2 ALL REFINERIES 7/17/2018
REFINING STANDARD PRACTICE 9 ALL REFINERIES 7/18/2018
REFINING STANDARD PRACTICE 8 ALL REFINERIES 12/12/2018
RSP FORM 9 ALL REFINERIES 10/24/2018
RSP FORM 1 ALL REFINERIES 1/27/2012
RSP FORM 1 ALL REFINERIES 1/27/2012
SP FORM 1 ALL REFINERIES 11/1/2010
REFINING STANDARD PRACTICE 7 ALL REFINERIES 6/7/2018
REFINING STANDARD PRACTICE 6 ALL REFINERIES 3/9/2018
REFINING STANDARD PRACTICE 10 ALL REFINERIES 8/21/2019
REFINING POLICY 3 ALL REFINERIES 12/21/2017
REFINING STANDARD PRACTICE 3 ALL REFINERIES 4/25/2018
REFINING STANDARD PRACTICE 7 ALL REFINERIES 6/7/2018
REFINING STANDARD PRACTICE 31 ALL REFINERIES 6/20/2019
REFINING STANDARD PRACTICE 5 ALL REFINERIES 5/1/2018
SP FORM 3 ALL REFINERIES 10/16/2012
CORE LINE CLASS 9 ALL REFINERIES 1/29/2019
WITHDRAWN 0 TEXAS CITY 7/1/2009
WITHDRAWN 0 TEXAS CITY 11/1/2009
REFINING STANDARD PRACTICE 7 ALL REFINERIES 8/15/2017
SP FORM 2 ALL REFINERIES 4/21/2015
RSP FORM 2 ALL REFINERIES 1/29/2010
STANDARD DRAWINGS 5 ALL REFINERIES 5/26/2016
STANDARD DRAWINGS 3 ALL REFINERIES 6/2/2011
STANDARD DRAWINGS 3 ALL REFINERIES 6/2/2011
STANDARD DRAWINGS 3 ALL REFINERIES 6/2/2011
STANDARD DRAWINGS 4 ALL REFINERIES 10/3/2013
STANDARD DRAWINGS 4 ALL REFINERIES 10/3/2013
STANDARD DRAWINGS 4 ALL REFINERIES 10/3/2013
STANDARD DRAWINGS 5 ALL REFINERIES 4/5/2016
WITHDRAWN 0 TEXAS CITY 3/28/2005
WITHDRAWN 0 TEXAS CITY 3/28/2005
WITHDRAWN 0 TEXAS CITY 3/28/2005
WITHDRAWN 0 TEXAS CITY 3/28/2005
RSP FORM 1 ALL REFINERIES 9/22/2010
SP FORM 3 ALL REFINERIES 9/28/2015
CORE SPECIFICATION 8 ALL REFINERIES 8/5/2016
MISC 0 ALL REFINERIES 8/17/2010
SP FORM 2 ALL REFINERIES 9/2/2011
SP FORM 2 ALL REFINERIES 9/2/2011
STANDARD DRAWINGS 4 ALL REFINERIES 8/17/2000
STANDARD DRAWINGS 1 ALL REFINERIES 1/21/1991
STANDARD DRAWINGS 1 ALL REFINERIES 1/21/1991
STANDARD DRAWINGS 3 ALL REFINERIES 12/4/2018
STANDARD DRAWINGS 4 ALL REFINERIES 12/4/2018
STANDARD DRAWINGS 3 ALL REFINERIES 12/4/2018
STANDARD DRAWINGS 3 ALL REFINERIES 4/4/2000
STANDARD DRAWINGS 4 ALL REFINERIES 2/27/2014
STANDARD DRAWINGS 1 ALL REFINERIES 1/30/1991
STANDARD DRAWINGS 4 ALL REFINERIES 12/4/2018
STANDARD DRAWINGS 3 ALL REFINERIES 4/4/2000
STANDARD DRAWINGS 8 ALL REFINERIES 6/17/2019
STANDARD DRAWINGS 5 ALL REFINERIES 8/20/2018
STANDARD DRAWINGS 2 ALL REFINERIES 9/13/2011
SP FORM 3 ALL REFINERIES 10/18/2017
SP FORM 2 ALL REFINERIES 4/18/2011
SP FORM 1 ALL REFINERIES 11/11/2011
SP FORM 1 ALL REFINERIES 11/11/2011
SP FORM 2 ALL REFINERIES 10/1/2019
SP FORM 1 ALL REFINERIES 11/11/2011
SP FORM 1 ALL REFINERIES 11/11/2011
CORE SPECIFICATION 5 ALL REFINERIES 3/14/2017
RSP FORM 6 ALL REFINERIES 1/19/2018
RSP FORM 4 ALL REFINERIES 1/19/2018
RSP FORM 5 ALL REFINERIES 1/19/2018
RSP FORM 7 ALL REFINERIES 1/19/2018
RSP FORM 7 ALL REFINERIES 1/19/2018
SP FORM 1 ALL REFINERIES 4/21/2015
SP FORM 1 ALL REFINERIES 4/21/2015
CORE SPECIFICATION 7 ALL REFINERIES 8/5/2016
CORE SPECIFICATION 6 ALL REFINERIES 8/5/2016
CORE SPECIFICATION 6 ALL REFINERIES 10/10/2017
CORE SPECIFICATION 6 ALL REFINERIES 10/10/2017
CORE SPECIFICATION 5 ALL REFINERIES 8/5/2016
CORE SPECIFICATION 5 ALL REFINERIES 8/5/2016
CORE SPECIFICATION 5 ALL REFINERIES 8/5/2016
CORE SPECIFICATION 5 ALL REFINERIES 8/5/2016
SP FORM 2 ALL REFINERIES 5/31/2017
RSP FORM 0 ALL REFINERIES 9/22/2010
SP FORM 1 ALL REFINERIES 10/24/2011
SP FORM 1 ALL REFINERIES 7/19/2010
WITHDRAWN 0 TEXAS CITY 9/16/2010
WITHDRAWN 1 TEXAS CITY 5/9/2011
WITHDRAWN 0 TEXAS CITY 9/16/2010
WITHDRAWN 1 TEXAS CITY 5/9/2011
WITHDRAWN 0 TEXAS CITY 9/16/2010
WITHDRAWN 0 TEXAS CITY 9/16/2010
WITHDRAWN 0 TEXAS CITY 9/16/2010
WITHDRAWN 1 TEXAS CITY 5/9/2011
WITHDRAWN 2 TEXAS CITY 5/9/2011
SP FORM 1 ALL REFINERIES 4/21/2015
REFINING STANDARD PRACTICE 9 ALL REFINERIES 12/13/2018
SP FORM 2 ALL REFINERIES 9/12/2018
INTERIM GUIDANCE 7 ALL REFINERIES 8/9/2016
REFINING STANDARD PRACTICE 3 ALL REFINERIES 12/15/2017
SP FORM 0 ALL REFINERIES 10/21/2010
SP FORM 0 ALL REFINERIES 10/21/2010
SP FORM 0 ALL REFINERIES 10/21/2010
REFINING STANDARD PRACTICE 3 ALL REFINERIES 3/29/2019
SP FORM 2 ALL REFINERIES 8/5/2016
SP FORM 5 ALL REFINERIES 11/9/2017
SP FORM 3 ALL REFINERIES 10/1/2014
SP FORM 4 ALL REFINERIES 8/1/2017
SP FORM 2 ALL REFINERIES 10/26/2016
SP FORM 1 ALL REFINERIES 11/3/2010
SP FORM 2 ALL REFINERIES 10/26/2016
SP FORM 3 ALL REFINERIES 2/27/2019
SP FORM 2 ALL REFINERIES 10/27/2016
SP FORM 3 ALL REFINERIES 8/17/2017
SP FORM 2 ALL REFINERIES 8/17/2017
SP FORM 3 ALL REFINERIES 4/3/2017
SP FORM 1 ALL REFINERIES 11/9/2010
SP FORM 2 ALL REFINERIES 1/17/2017
SP FORM 2 ALL REFINERIES 10/27/2016
SP FORM 3 ALL REFINERIES 9/2/2015
SP FORM 3 ALL REFINERIES 2/27/2019
WITHDRAWN 0 TEXAS CITY NULL
SP FORM 3 ALL REFINERIES 7/11/2017
SP FORM 2 ALL REFINERIES 9/26/2011
SP FORM 1 ALL REFINERIES 4/21/2015
SP FORM 1 ALL REFINERIES 4/8/2014
CORE SPECIFICATION 3 ALL REFINERIES 8/5/2016
REFINING STANDARD PRACTICE 4 ALL REFINERIES 1/2/2018
REFINING STANDARD PRACTICE 3 ALL REFINERIES 5/16/2017
REFINING REFERENCE DOCUME 2 ALL REFINERIES 3/30/2017
REFINING REFERENCE DOCUME 2 ALL REFINERIES 9/21/2016
RSP FORM 1 ALL REFINERIES 9/14/2018
RSP FORM 0 ALL REFINERIES 5/3/2011
RSP FORM 1 ALL REFINERIES 9/14/2018
RSP FORM 0 ALL REFINERIES 5/3/2011
REFINING REFERENCE DOCUME 5 ALL REFINERIES 8/12/2019
REFINING STANDARD PRACTICE 2 ALL REFINERIES 9/7/2018
ASHLAND LEGACY 0 ASHLAND LEGACY 6/16/2011
ASHLAND LEGACY 0 ASHLAND LEGACY 6/16/2011
ASHLAND LEGACY 0 ASHLAND LEGACY 6/16/2011
WITHDRAWN 0 TEXAS CITY 6/30/2011
CORE SPECIFICATION 7 ALL REFINERIES 10/1/2019
RRD FORM 2 ALL REFINERIES 7/21/2017
WITHDRAWN 0 TEXAS CITY 8/9/2011
CORE SPECIFICATION 4 ALL REFINERIES 9/14/2016
WITHDRAWN 0 TEXAS CITY 8/24/2011
SP FORM 1 ALL REFINERIES 11/5/2018
SP FORM 1 ALL REFINERIES 11/5/2018
SP FORM 3 ALL REFINERIES 11/5/2018
REFINING REFERENCE DOCUME 3 ALL REFINERIES 8/31/2018
REFINING REFERENCE DOCUME 1 ALL REFINERIES 11/3/2017
REFINING REFERENCE DOCUME 2 ALL REFINERIES 11/3/2017
REFINING REFERENCE DOCUME 2 ALL REFINERIES 10/24/2018
CORE SPECIFICATION 3 ALL REFINERIES 1/20/2017
SP FORM 0 ALL REFINERIES 11/11/2011
SP FORM 0 ALL REFINERIES 11/11/2011
SP FORM 0 ALL REFINERIES 11/11/2011
SP FORM 0 ALL REFINERIES 11/11/2011
SP FORM 0 ALL REFINERIES 11/11/2011
SP FORM 0 ALL REFINERIES 11/11/2011
SP FORM 0 ALL REFINERIES 11/11/2011
SP FORM 1 ALL REFINERIES 4/5/2019
RSP FORM 0 ALL REFINERIES 11/17/2011
RSP FORM 1 ALL REFINERIES 1/30/2014
REFINING STANDARD PRACTICE 7 ALL REFINERIES 12/12/2018
REFINING STANDARD PRACTICE 1 ALL REFINERIES 2/17/2017
REFINING STANDARD PRACTICE 3 ALL REFINERIES 2/21/2017
REFINING STANDARD PRACTICE 2 ALL REFINERIES 3/1/2017
REFINING STANDARD PRACTICE 3 ALL REFINERIES 3/6/2019
REFINING STANDARD PRACTICE 2 ALL REFINERIES 1/17/2017
REFINING STANDARD PRACTICE 3 ALL REFINERIES 8/25/2017
REFINING STANDARD PRACTICE 2 ALL REFINERIES 5/17/2017
REFINING STANDARD PRACTICE 1 ALL REFINERIES 1/13/2017
REFINING STANDARD PRACTICE 2 ALL REFINERIES 4/3/2017
REFINING STANDARD PRACTICE 2 ALL REFINERIES 2/17/2017
REFINING STANDARD PRACTICE 2 ALL REFINERIES 2/21/2017
REFINING STANDARD PRACTICE 1 ALL REFINERIES 2/17/2017
REFINING STANDARD PRACTICE 2 ALL REFINERIES 12/19/2017
STANDARD DRAWINGS 13 ALL REFINERIES 2/28/2012
STANDARD DRAWINGS 6 ALL REFINERIES 2/28/2012
REFINING REFERENCE DOCUME 11 ALL REFINERIES 11/30/2018
WITHDRAWN 0 TEXAS CITY 2/1/2012
RSP FORM 0 ALL REFINERIES 4/4/2012
REFINING STANDARD PRACTICE 2 ALL REFINERIES 5/1/2015
WITHDRAWN 0 TEXAS CITY 4/4/2012
REFINING STANDARD PRACTICE 3 ALL REFINERIES 6/8/2017
REFINING STANDARD PRACTICE 8 ALL REFINERIES 3/1/2018
SP FORM 1 ALL REFINERIES 3/14/2017
SP FORM 1 ALL REFINERIES 3/14/2017
RRD FORM 5 ALL REFINERIES 2/14/2019
REFINING REFERENCE DOCUME 5 ALL REFINERIES 2/14/2019
RSP FORM 2 ALL REFINERIES 1/19/2018
RSP FORM 2 ALL REFINERIES 1/19/2018
RSP FORM 4 ALL REFINERIES 1/19/2018
RSP FORM 2 ALL REFINERIES 1/19/2018
RSP FORM 5 ALL REFINERIES 1/19/2018
REFINING REFERENCE DOCUME 4 ALL REFINERIES 5/31/2017
CORE SPECIFICATION 4 ALL REFINERIES 3/14/2017
REFINING STANDARD PRACTICE 7 ALL REFINERIES 6/26/2017
REFINING STANDARD PRACTICE 2 ALL REFINERIES 3/1/2017
WITHDRAWN 0 TEXAS CITY 6/20/2012
WITHDRAWN 0 TEXAS CITY 6/27/2012
SP FORM 1 ALL REFINERIES 9/3/2015
CORE SPECIFICATION 2 ALL REFINERIES 8/16/2017
REFINING REFERENCE DOCUME 4 ALL REFINERIES 11/19/2018
REFINING REFERENCE DOCUME 4 ALL REFINERIES 8/14/2018
RSP FORM 0 ALL REFINERIES 9/26/2012
CORE SPECIFICATION 4 ALL REFINERIES 7/20/2018
RRD FORM 0 ALL REFINERIES 10/12/2012
REFINING REFERENCE DOCUME 1 ALL REFINERIES 10/12/2012
WITHDRAWN NA ALL REFINERIES 7/18/2018
SP FORM 2 ALL REFINERIES 9/3/2014
SP FORM 2 ALL REFINERIES 9/3/2014
SP FORM 2 ALL REFINERIES 9/3/2014
SP FORM 2 ALL REFINERIES 9/3/2014
CORE SPECIFICATION 3 ALL REFINERIES 8/20/2018
CORE SPECIFICATION 3 ALL REFINERIES 8/20/2018
CORE SPECIFICATION 3 ALL REFINERIES 8/20/2018
CORE SPECIFICATION 3 ALL REFINERIES 8/20/2018
SP FORM 2 ALL REFINERIES 6/30/2014
SP FORM 2 ALL REFINERIES 9/3/2014
SP FORM 2 ALL REFINERIES 9/3/2014
SP FORM 2 ALL REFINERIES 9/3/2014
CORE SPECIFICATION 3 ALL REFINERIES 4/10/2018
CORE SPECIFICATION 3 ALL REFINERIES 4/10/2018
CORE SPECIFICATION 3 ALL REFINERIES 4/10/2018
CORE SPECIFICATION 3 ALL REFINERIES 8/20/2018
REFINING STANDARD PRACTICE 8 ALL REFINERIES 2/12/2018
SP FORM 0 ALL REFINERIES 11/19/2012
SP FORM 0 ALL REFINERIES 11/19/2012
SP FORM 0 ALL REFINERIES 11/19/2012
SP FORM 0 ALL REFINERIES 11/19/2012
SP FORM 0 ALL REFINERIES 11/19/2012
SP FORM 0 ALL REFINERIES 11/19/2012
SP FORM 0 ALL REFINERIES 11/19/2012
SP FORM 0 ALL REFINERIES 11/19/2012
WITHDRAWN 0 TEXAS CITY 12/4/2012
CORE SPECIFICATION 2 ALL REFINERIES 1/30/2018
LOCAL LINE CLASS 0 DETROIT 11/22/2004
SP FORM 0 ALL REFINERIES 1/30/2013
SP FORM 5 ALL REFINERIES 3/6/2019
SP FORM 2 ALL REFINERIES 1/2/2018
SP FORM 3 ALL REFINERIES 1/2/2018
SP FORM 4 ALL REFINERIES 1/2/2018
SP FORM 4 ALL REFINERIES 1/2/2018
SP FORM 4 ALL REFINERIES 1/2/2018
SP FORM 3 ALL REFINERIES 1/2/2018
SP FORM 3 ALL REFINERIES 1/2/2018
SP FORM 6 ALL REFINERIES 1/2/2018
SP FORM 2 ALL REFINERIES 2/25/2016
SP FORM 2 ALL REFINERIES 2/25/2016
SP FORM 2 ALL REFINERIES 2/25/2016
SP FORM 2 ALL REFINERIES 2/25/2016
SP FORM 1 ALL REFINERIES 2/8/2013
SP FORM 1 ALL REFINERIES 2/8/2013
SP FORM 2 ALL REFINERIES 3/6/2019
SP FORM 1 ALL REFINERIES 2/8/2013
SP FORM 1 ALL REFINERIES 2/8/2013
SP FORM 2 ALL REFINERIES 4/26/2017
SP FORM 1 ALL REFINERIES 2/8/2013
SP FORM 1 ALL REFINERIES 2/8/2013
SP FORM 2 ALL REFINERIES 6/15/2015
SP FORM 3 ALL REFINERIES 3/6/2019
SP FORM 1 ALL REFINERIES 2/8/2013
SP FORM 2 ALL REFINERIES 8/28/2015
SP FORM 1 ALL REFINERIES 2/8/2013
SP FORM 1 ALL REFINERIES 2/8/2013
SP FORM 4 ALL REFINERIES 12/1/2014
SP FORM 2 ALL REFINERIES 1/15/2014
CORE SPECIFICATION 6 ALL REFINERIES 9/19/2019
REFINING REFERENCE DOCUME 2 ALL REFINERIES 8/31/2018
STANDARD DRAWINGS 0 ALL REFINERIES 4/19/2013
STANDARD DRAWINGS 0 ALL REFINERIES 4/19/2013
STANDARD DRAWINGS 1 ALL REFINERIES 10/27/2016
STANDARD DRAWINGS 0 ALL REFINERIES 4/19/2013
STANDARD DRAWINGS 0 ALL REFINERIES 4/19/2013
STANDARD DRAWINGS 0 ALL REFINERIES 4/19/2013
STANDARD DRAWINGS 0 ALL REFINERIES 4/19/2013
STANDARD DRAWINGS 0 ALL REFINERIES 4/19/2013
STANDARD DRAWINGS 0 ALL REFINERIES 4/19/2013
STANDARD DRAWINGS 0 ALL REFINERIES 4/19/2013
STANDARD DRAWINGS 0 ALL REFINERIES 4/19/2013
STANDARD DRAWINGS 0 ALL REFINERIES 4/19/2013
STANDARD DRAWINGS 0 ALL REFINERIES 4/19/2013
STANDARD DRAWINGS 0 ALL REFINERIES 4/19/2013
STANDARD DRAWINGS 0 ALL REFINERIES 4/19/2013
STANDARD DRAWINGS 0 ALL REFINERIES 4/19/2013
STANDARD DRAWINGS 0 ALL REFINERIES 4/19/2013
INTERIM GUIDANCE 1 ALL REFINERIES 9/21/2015
SP FORM 0 ALL REFINERIES 6/7/2013
WITHDRAWN 0 TEXAS CITY 2/1/2011
REFINING STANDARD PRACTICE 2 ALL REFINERIES 7/31/2018
SP FORM 2 ALL REFINERIES 2/10/2014
REFINING REFERENCE DOCUME 4 ALL REFINERIES 8/31/2018
REFINING REFERENCE DOCUME 4 ALL REFINERIES 9/7/2018
REFINING REFERENCE DOCUME 4 ALL REFINERIES 8/21/2018
REFINING POLICY 3 ALL REFINERIES 4/24/2019
WITHDRAWN NA ALL REFINERIES 10/20/2014
STANDARD DRAWINGS 1 ALL REFINERIES 3/1/2012
STANDARD DRAWINGS 1 ALL REFINERIES 3/1/2012
STANDARD DRAWINGS 2 ALL REFINERIES 7/31/2014
STANDARD DRAWINGS 2 ALL REFINERIES 7/31/2014
STANDARD DRAWINGS 1 ALL REFINERIES 3/1/2012
CORE SPECIFICATION 2 ALL REFINERIES 10/22/2018
CORE SPECIFICATION 2 ALL REFINERIES 10/22/2018
CORE SPECIFICATION 3 ALL REFINERIES 10/22/2018
CORE SPECIFICATION 2 ALL REFINERIES 10/22/2018
CORE SPECIFICATION 2 ALL REFINERIES 10/22/2018
CORE SPECIFICATION 9 ALL REFINERIES 6/8/2018
CORE SPECIFICATION 2 ALL REFINERIES 12/14/2017
WITHDRAWN 0 TEXAS CITY 11/19/2013
REFINING REFERENCE DOCUME 2 ALL REFINERIES 9/7/2018
CORE LINE CLASS 4 ALL REFINERIES 12/21/2018
RSP FORM 2 ALL REFINERIES 12/13/2018
RSP FORM 2 ALL REFINERIES 12/13/2018
RSP FORM 0 ALL REFINERIES 1/2/2014
REFINING REFERENCE DOCUME 6 ALL REFINERIES 4/26/2019
RRD FORM 1 ALL REFINERIES 5/31/2017
RRD FORM 1 ALL REFINERIES 5/31/2017
REFINING REFERENCE DOCUME 2 ALL REFINERIES 4/10/2019
REFINING STANDARD PRACTICE 3 ALL REFINERIES 12/13/2018
CORE LINE CLASS 4 ALL REFINERIES 12/21/2018
RSP FORM 1 ALL REFINERIES 4/28/2017
RSP FORM 2 ALL REFINERIES 4/28/2017
RSP FORM 1 ALL REFINERIES 4/28/2017
RSP FORM 3 ALL REFINERIES 7/18/2018
RSP FORM 1 ALL REFINERIES 4/28/2017
RSP FORM 1 ALL REFINERIES 4/28/2017
RSP FORM 2 ALL REFINERIES 7/18/2018
RSP FORM 1 ALL REFINERIES 4/28/2017
RSP FORM 1 ALL REFINERIES 4/28/2017
RSP FORM 1 ALL REFINERIES 4/28/2017
RSP FORM 1 ALL REFINERIES 4/28/2017
RSP FORM 1 ALL REFINERIES 4/28/2017
RSP FORM 1 ALL REFINERIES 4/28/2017
RSP FORM 2 ALL REFINERIES 4/28/2017
RSP FORM 1 ALL REFINERIES 4/28/2017
RSP FORM 2 ALL REFINERIES 1/22/2018
REFINING STANDARD PRACTICE 1 ALL REFINERIES 9/21/2018
REFINING STANDARD PRACTICE 1 ALL REFINERIES 9/21/2018
REFINING STANDARD PRACTICE 1 ALL REFINERIES 9/21/2018
REFINING STANDARD PRACTICE 1 ALL REFINERIES 9/21/2018
REFINING STANDARD PRACTICE 2 ALL REFINERIES 4/26/2019
REFINING STANDARD PRACTICE 2 ALL REFINERIES 10/14/2019
REFINING STANDARD PRACTICE 0 ALL REFINERIES 12/18/2018
REFINING STANDARD PRACTICE NA ALL REFINERIES 8/7/2019
CORE LINE CLASS 6 ALL REFINERIES 12/21/2018
CORE LINE CLASS 3 ALL REFINERIES 12/21/2018
CORE LINE CLASS 3 ALL REFINERIES 5/31/2019
CORE LINE CLASS 3 ALL REFINERIES 12/21/2018
CORE LINE CLASS 4 ALL REFINERIES 12/21/2018
CORE LINE CLASS 5 ALL REFINERIES 12/21/2018
CORE LINE CLASS 4 ALL REFINERIES 5/31/2019
CORE LINE CLASS 3 ALL REFINERIES 12/21/2018
CORE LINE CLASS 4 ALL REFINERIES 5/31/2019
CORE LINE CLASS 8 ALL REFINERIES 12/21/2018
CORE LINE CLASS 5 ALL REFINERIES 12/21/2018
CORE LINE CLASS 5 ALL REFINERIES 12/21/2018
CORE LINE CLASS 6 ALL REFINERIES 5/31/2019
CORE LINE CLASS 5 ALL REFINERIES 5/31/2019
CORE LINE CLASS 5 ALL REFINERIES 6/4/2019
CORE LINE CLASS 5 ALL REFINERIES 12/21/2018
CORE LINE CLASS 7 ALL REFINERIES 12/21/2018
CORE LINE CLASS 5 ALL REFINERIES 12/21/2018
CORE LINE CLASS 5 ALL REFINERIES 12/21/2018
CORE LINE CLASS 5 ALL REFINERIES 12/21/2018
CORE LINE CLASS 5 ALL REFINERIES 12/21/2018
CORE LINE CLASS 4 ALL REFINERIES 12/21/2018
CORE LINE CLASS 4 ALL REFINERIES 12/21/2018
CORE LINE CLASS 5 ALL REFINERIES 12/21/2018
CORE LINE CLASS 3 ALL REFINERIES 12/21/2018
CORE LINE CLASS 7 ALL REFINERIES 12/21/2018
CORE LINE CLASS 5 ALL REFINERIES 12/21/2018
CORE LINE CLASS 4 ALL REFINERIES 12/21/2018
CORE LINE CLASS 4 ALL REFINERIES 5/31/2019
CORE LINE CLASS 5 ALL REFINERIES 6/4/2019
CORE LINE CLASS 4 ALL REFINERIES 5/31/2019
CORE LINE CLASS 2 ALL REFINERIES 12/21/2018
CORE LINE CLASS 5 ALL REFINERIES 12/21/2018
CORE LINE CLASS 4 ALL REFINERIES 12/21/2018
CORE LINE CLASS 4 ALL REFINERIES 12/21/2018
CORE LINE CLASS 4 ALL REFINERIES 12/21/2018
CORE LINE CLASS 4 ALL REFINERIES 12/21/2018
CORE LINE CLASS 4 ALL REFINERIES 12/21/2018
CORE LINE CLASS 4 ALL REFINERIES 12/21/2018
CORE LINE CLASS 7 ALL REFINERIES 6/11/2019
CORE LINE CLASS 6 ALL REFINERIES 12/21/2018
CORE LINE CLASS 6 ALL REFINERIES 12/21/2018
CORE LINE CLASS 6 ALL REFINERIES 12/21/2018
CORE LINE CLASS 5 ALL REFINERIES 5/31/2019
CORE LINE CLASS 4 ALL REFINERIES 12/21/2018
CORE LINE CLASS 4 ALL REFINERIES 12/21/2018
CORE LINE CLASS 5 ALL REFINERIES 5/31/2019
CORE LINE CLASS 4 ALL REFINERIES 12/21/2018
CORE LINE CLASS 5 ALL REFINERIES 5/31/2019
CORE LINE CLASS 5 ALL REFINERIES 12/21/2018
CORE LINE CLASS 5 ALL REFINERIES 6/4/2019
CORE LINE CLASS 4 ALL REFINERIES 12/21/2018
CORE LINE CLASS 8 ALL REFINERIES 2/1/2019
CORE LINE CLASS 3 ALL REFINERIES 12/21/2018
CORE LINE CLASS 3 ALL REFINERIES 12/21/2018
CORE LINE CLASS 4 ALL REFINERIES 12/21/2018
CORE LINE CLASS 3 ALL REFINERIES 12/21/2018
CORE LINE CLASS 3 ALL REFINERIES 6/4/2019
CORE LINE CLASS 6 ALL REFINERIES 12/21/2018
CORE LINE CLASS 4 ALL REFINERIES 12/21/2018
CORE LINE CLASS 4 ALL REFINERIES 5/31/2019
CORE LINE CLASS 4 ALL REFINERIES 6/4/2019
CORE LINE CLASS 3 ALL REFINERIES 12/21/2018
CORE LINE CLASS 3 ALL REFINERIES 12/21/2018
CORE LINE CLASS 3 ALL REFINERIES 12/21/2018
CORE LINE CLASS 5 ALL REFINERIES 5/31/2019
CORE LINE CLASS 6 ALL REFINERIES 2/1/2019
CORE LINE CLASS 4 ALL REFINERIES 6/4/2019
RRD FORM 1 ALL REFINERIES 9/13/2016
RRD FORM 0 ALL REFINERIES 2/13/2014
REFINING REFERENCE DOCUME 3 ALL REFINERIES 9/7/2018
CORE LINE CLASS 4 ALL REFINERIES 6/4/2019
CORE LINE CLASS 5 ALL REFINERIES 5/31/2019
CORE LINE CLASS 4 ALL REFINERIES 6/4/2019
CORE LINE CLASS 4 ALL REFINERIES 6/4/2019
CORE LINE CLASS 4 ALL REFINERIES 6/4/2019
CORE LINE CLASS 4 ALL REFINERIES 6/4/2019
CORE LINE CLASS 3 ALL REFINERIES 12/21/2018
CORE LINE CLASS 6 ALL REFINERIES 2/1/2019
WITHDRAWN 0 TEXAS CITY 8/1/2012
CORE LINE CLASS 1 ALL REFINERIES 1/10/2017
CORE LINE CLASS 3 ALL REFINERIES 12/21/2018
CORE LINE CLASS 4 ALL REFINERIES 12/21/2018
CORE LINE CLASS 1 ALL REFINERIES 1/6/2017
CORE LINE CLASS 3 ALL REFINERIES 12/21/2018
CORE LINE CLASS 1 ALL REFINERIES 1/10/2017
CORE LINE CLASS 5 ALL REFINERIES 9/19/2018
CORE LINE CLASS 1 ALL REFINERIES 1/10/2017
CORE LINE CLASS 3 ALL REFINERIES 12/22/2016
CORE LINE CLASS 1 ALL REFINERIES 12/1/2016
CORE LINE CLASS 2 ALL REFINERIES 12/1/2016
CORE LINE CLASS 3 ALL REFINERIES 12/21/2018
CORE LINE CLASS 2 ALL REFINERIES 12/22/2016
CORE LINE CLASS 2 ALL REFINERIES 2/22/2017
CORE LINE CLASS 1 ALL REFINERIES 12/22/2016
CORE LINE CLASS 2 ALL REFINERIES 12/22/2016
CORE LINE CLASS 3 ALL REFINERIES 12/22/2016
CORE LINE CLASS 1 ALL REFINERIES 12/22/2016
CORE LINE CLASS 6 ALL REFINERIES 12/21/2018
CORE LINE CLASS 1 ALL REFINERIES 12/22/2016
WITHDRAWN 0 TEXAS CITY 3/10/2014
RSP FORM 2 ALL REFINERIES 1/19/2018
CORE LINE CLASS 2 ALL REFINERIES 12/22/2016
CORE SPECIFICATION 9 ALL REFINERIES 4/15/2019
CORE SPECIFICATION 6 ALL REFINERIES 4/15/2019
CORE SPECIFICATION 2 ALL REFINERIES 4/22/2019
CORE SPECIFICATION 2 ALL REFINERIES 4/22/2019
CORE SPECIFICATION 2 ALL REFINERIES 4/22/2019
CORE SPECIFICATION 2 ALL REFINERIES 4/22/2019
CORE SPECIFICATION 2 ALL REFINERIES 4/22/2019
CORE SPECIFICATION 3 ALL REFINERIES 4/22/2019
CORE SPECIFICATION 2 ALL REFINERIES 4/22/2019
CORE SPECIFICATION 8 ALL REFINERIES 4/15/2019
CORE SPECIFICATION 4 ALL REFINERIES 8/20/2018
CORE SPECIFICATION 2 ALL REFINERIES 5/30/2019
CORE SPECIFICATION 2 ALL REFINERIES 5/30/2019
CORE SPECIFICATION 2 ALL REFINERIES 5/30/2019
CORE SPECIFICATION 2 ALL REFINERIES 5/30/2019
CORE SPECIFICATION 2 ALL REFINERIES 5/30/2019
CORE SPECIFICATION 3 ALL REFINERIES 5/30/2019
CORE SPECIFICATION 2 ALL REFINERIES 5/30/2019
CORE SPECIFICATION 2 ALL REFINERIES 5/30/2019
SP FORM 1 ALL REFINERIES 1/27/2016
REFINING REFERENCE DOCUME 2 ALL REFINERIES 5/29/2019
CORE LINE CLASS 4 ALL REFINERIES 12/21/2018
CORE LINE CLASS 1 ALL REFINERIES 1/6/2017
CORE LINE CLASS 3 ALL REFINERIES 12/21/2018
CORE SPECIFICATION 2 ALL REFINERIES 7/13/2016
CORE SPECIFICATION 4 ALL REFINERIES 1/10/2018
CORE SPECIFICATION 4 ALL REFINERIES 1/3/2019
CORE SPECIFICATION 5 ALL REFINERIES 5/2/2019
RSP FORM 0 ALL REFINERIES 7/1/2014
REFINING STANDARD PRACTICE 0 ALL REFINERIES 7/1/2014
RSP FORM 0 ALL REFINERIES 7/1/2014
REFINING STANDARD PRACTICE 1 ALL REFINERIES 12/6/2016
REFINING REFERENCE DOCUME 3 ALL REFINERIES 7/18/2018
CORE LINE CLASS 0 ALL REFINERIES 8/20/2019
CORE LINE CLASS 3 ALL REFINERIES 12/21/2018
SP FORM 1 ALL REFINERIES 5/27/2015
CORE SPECIFICATION 3 ALL REFINERIES 8/5/2016
RSP FORM 0 ALL REFINERIES 7/28/2014
CORE SPECIFICATION 4 ALL REFINERIES 4/22/2019
SP FORM 0 ALL REFINERIES 8/26/2014
SP FORM 0 ALL REFINERIES 8/26/2014
SP FORM 0 ALL REFINERIES 8/26/2014
SP FORM 0 ALL REFINERIES 8/26/2014
SP FORM 0 ALL REFINERIES 8/26/2014
SP FORM 0 ALL REFINERIES 8/26/2014
SP FORM 0 ALL REFINERIES 8/26/2014
SP FORM 0 ALL REFINERIES 8/26/2014
SP FORM 0 ALL REFINERIES 8/26/2014
SP FORM 0 ALL REFINERIES 8/26/2014
SP FORM 0 ALL REFINERIES 8/26/2014
SP FORM 0 ALL REFINERIES 8/26/2014
SP FORM 0 ALL REFINERIES 8/26/2014
SP FORM 0 ALL REFINERIES 8/26/2014
SP FORM 0 ALL REFINERIES 8/26/2014
SP FORM 0 ALL REFINERIES 8/26/2014
CORE SPECIFICATION 2 ALL REFINERIES 10/1/2019
CORE SPECIFICATION 2 ALL REFINERIES 10/1/2019
CORE SPECIFICATION 2 ALL REFINERIES 10/1/2019
CORE SPECIFICATION 2 ALL REFINERIES 10/1/2019
CORE SPECIFICATION 2 ALL REFINERIES 6/3/2019
CORE LINE CLASS 5 ALL REFINERIES 7/11/2017
CORE LINE CLASS 2 ALL REFINERIES 1/6/2017
CORE LINE CLASS 4 ALL REFINERIES 7/11/2017
CORE LINE CLASS 8 ALL REFINERIES 4/27/2017
CORE SPECIFICATION 2 ALL REFINERIES 10/1/2019
CORE SPECIFICATION 4 ALL REFINERIES 5/31/2017
CORE SPECIFICATION 2 ALL REFINERIES 9/9/2019
CORE SPECIFICATION 3 ALL REFINERIES 6/3/2019
CORE SPECIFICATION 3 ALL REFINERIES 6/3/2019
CORE SPECIFICATION 2 ALL REFINERIES 10/2/2019
CORE SPECIFICATION 2 ALL REFINERIES 10/2/2019
CORE SPECIFICATION 3 ALL REFINERIES 10/1/2019
CORE SPECIFICATION 3 ALL REFINERIES 9/18/2018
CORE SPECIFICATION 3 ALL REFINERIES 9/18/2018
CORE SPECIFICATION 2 ALL REFINERIES 10/1/2019
CORE SPECIFICATION 3 ALL REFINERIES 1/22/2019
SP FORM 0 ALL REFINERIES 9/26/2014
SP FORM 0 ALL REFINERIES 9/26/2014
CORE SPECIFICATION 2 ALL REFINERIES 10/4/2019
RSP FORM 1 ALL REFINERIES 9/18/2019
RSP FORM 2 ALL REFINERIES 9/18/2019
RSP FORM 3 ALL REFINERIES 9/18/2019
REFINING STANDARD PRACTICE 6 ALL REFINERIES 9/18/2019
REFINING STANDARD PRACTICE 1 ALL REFINERIES 5/4/2015
CORE SPECIFICATION 3 ALL REFINERIES 8/9/2016
CORE SPECIFICATION 2 ALL REFINERIES 8/7/2019
CORE SPECIFICATION 1 ALL REFINERIES 5/23/2017
RRD FORM 1 ALL REFINERIES 9/18/2019
REFINING REFERENCE DOCUME 2 ALL REFINERIES 9/18/2019
CORE SPECIFICATION 2 ALL REFINERIES 3/23/2017
CORE SPECIFICATION 1 ALL REFINERIES 3/15/2016
SP FORM 2 ALL REFINERIES 4/26/2019
SP FORM 1 ALL REFINERIES 10/31/2018
SP FORM 2 ALL REFINERIES 4/26/2019
CORE SPECIFICATION 1 ALL REFINERIES 10/31/2018
RSP FORM 0 ALL REFINERIES 10/23/2014
REFINING STANDARD PRACTICE 0 ALL REFINERIES 10/23/2014
STANDARD DRAWINGS 0 ALL REFINERIES 10/28/2014
STANDARD DRAWINGS 0 ALL REFINERIES 10/28/2014
STANDARD DRAWINGS 0 ALL REFINERIES 10/28/2014
STANDARD DRAWINGS 0 ALL REFINERIES 10/28/2014
STANDARD DRAWINGS 0 ALL REFINERIES 10/28/2014
STANDARD DRAWINGS 0 ALL REFINERIES 10/28/2014
STANDARD DRAWINGS 0 ALL REFINERIES 10/28/2014
CORE SPECIFICATION 3 ALL REFINERIES 11/19/2018
CORE SPECIFICATION 4 ALL REFINERIES 6/17/2019
CORE SPECIFICATION 1 ALL REFINERIES 8/5/2016
WITHDRAWN NA WITHDRAWN 11/13/2014
REFINING REFERENCE DOCUME 1 ALL REFINERIES 9/7/2018
REFINING REFERENCE DOCUME 2 ALL REFINERIES 11/26/2018
CORE SPECIFICATION 2 ALL REFINERIES 9/30/2019
CORE SPECIFICATION 2 ALL REFINERIES 8/12/2019
CORE SPECIFICATION 1 ALL REFINERIES 6/29/2016
REFINING REFERENCE DOCUME 1 ALL REFINERIES 10/1/2018
REFINING REFERENCE DOCUME 1 ALL REFINERIES 10/1/2018
REFINING REFERENCE DOCUME 1 ALL REFINERIES 10/1/2018
REFINING REFERENCE DOCUME 1 ALL REFINERIES 10/1/2018
REFINING REFERENCE DOCUME 1 ALL REFINERIES 10/1/2018
REFINING REFERENCE DOCUME 1 ALL REFINERIES 10/1/2018
REFINING REFERENCE DOCUME 1 ALL REFINERIES 10/1/2018
REFINING REFERENCE DOCUME 1 ALL REFINERIES 10/1/2018
REFINING REFERENCE DOCUME 1 ALL REFINERIES 10/1/2018
CORE SPECIFICATION 2 ALL REFINERIES 10/4/2019
CORE SPECIFICATION 1 ALL REFINERIES 8/15/2016
CORE LINE CLASS 3 ALL REFINERIES 12/21/2018
CORE SPECIFICATION 2 ALL REFINERIES 4/6/2016
CORE LINE CLASS 4 ALL REFINERIES 6/4/2019
CORE LINE CLASS 3 ALL REFINERIES 12/21/2018
CORE SPECIFICATION 1 ALL REFINERIES 6/2/2016
CORE SPECIFICATION 2 ALL REFINERIES 2/22/2018
REFINING REFERENCE DOCUME 2 ALL REFINERIES 9/11/2018
REFINING STANDARD PRACTICE 1 ALL REFINERIES 9/21/2018
REFINING REFERENCE DOCUME 2 ALL REFINERIES 7/21/2017
REFINING REFERENCE DOCUME 1 ALL REFINERIES 9/12/2018
SP FORM 0 ALL REFINERIES 1/9/2015
SP FORM 0 ALL REFINERIES 1/9/2015
SP FORM 0 ALL REFINERIES 1/9/2015
SP FORM 0 ALL REFINERIES 1/9/2015
CORE SPECIFICATION 1 ALL REFINERIES 8/5/2016
CORE SPECIFICATION 1 ALL REFINERIES 8/5/2016
SP FORM 0 ALL REFINERIES 1/30/2015
CORE SPECIFICATION 1 ALL REFINERIES 8/15/2016
CORE SPECIFICATION 1 ALL REFINERIES 8/5/2016
CORE SPECIFICATION 1 ALL REFINERIES 8/15/2016
CORE SPECIFICATION 1 ALL REFINERIES 8/15/2016
CORE SPECIFICATION 2 ALL REFINERIES 11/6/2017
WITHDRAWN 0 TEXAS CITY 2/2/2015
CORE SPECIFICATION 2 ALL REFINERIES 8/5/2016
REFINING REFERENCE DOCUME 1 ALL REFINERIES 9/12/2018
CORE SPECIFICATION 1 ALL REFINERIES 6/2/2016
REFINING REFERENCE DOCUME 1 ALL REFINERIES 9/12/2018
STANDARD DRAWINGS 0 ALL REFINERIES 3/16/2015
STANDARD DRAWINGS 0 ALL REFINERIES 3/16/2015
STANDARD DRAWINGS 0 ALL REFINERIES 3/16/2015
STANDARD DRAWINGS 0 ALL REFINERIES 3/16/2015
STANDARD DRAWINGS 0 ALL REFINERIES 3/16/2015
STANDARD DRAWINGS 0 ALL REFINERIES 3/16/2015
STANDARD DRAWINGS 0 ALL REFINERIES 3/16/2015
STANDARD DRAWINGS 0 ALL REFINERIES 3/16/2015
STANDARD DRAWINGS 0 ALL REFINERIES 3/16/2015
STANDARD DRAWINGS 0 ALL REFINERIES 3/16/2015
STANDARD DRAWINGS 0 ALL REFINERIES 3/16/2015
CORE SPECIFICATION 1 ALL REFINERIES 8/5/2016
RSP FORM 1 ALL REFINERIES 5/3/2019
REFINING STANDARD PRACTICE 2 ALL REFINERIES 10/1/2019
RSP FORM 0 ALL REFINERIES 3/27/2015
RSP FORM 0 ALL REFINERIES 3/27/2015
RSP FORM 0 ALL REFINERIES 3/27/2015
RSP FORM 0 ALL REFINERIES 3/27/2015
RSP FORM 0 ALL REFINERIES 3/27/2015
RSP FORM 0 ALL REFINERIES 3/27/2015
RSP FORM 0 ALL REFINERIES 3/27/2015
RSP FORM 0 ALL REFINERIES 3/27/2015
RSP FORM 0 ALL REFINERIES 3/27/2015
RSP FORM 0 ALL REFINERIES 3/27/2015
RSP FORM 0 ALL REFINERIES 3/27/2015
RSP FORM 0 ALL REFINERIES 3/27/2015
RSP FORM 0 ALL REFINERIES 3/27/2015
RSP FORM 0 ALL REFINERIES 3/27/2015
RSP FORM 0 ALL REFINERIES 3/27/2015
RSP FORM 1 ALL REFINERIES 10/27/2016
STANDARD DRAWINGS 0 ALL REFINERIES 3/27/2015
STANDARD DRAWINGS 0 ALL REFINERIES 3/27/2015
STANDARD DRAWINGS 0 ALL REFINERIES 3/27/2015
STANDARD DRAWINGS 0 ALL REFINERIES 3/27/2015
STANDARD DRAWINGS 0 ALL REFINERIES 3/27/2015
STANDARD DRAWINGS 0 ALL REFINERIES 3/27/2015
STANDARD DRAWINGS 0 ALL REFINERIES 3/27/2015
STANDARD DRAWINGS 0 ALL REFINERIES 3/27/2015
STANDARD DRAWINGS 0 ALL REFINERIES 3/27/2015
STANDARD DRAWINGS 0 ALL REFINERIES 3/27/2015
SP FORM 0 ALL REFINERIES 3/27/2015
CORE SPECIFICATION 3 ALL REFINERIES 3/26/2018
CORE SPECIFICATION 1 ALL REFINERIES 8/5/2016
CORE SPECIFICATION 1 ALL REFINERIES 8/5/2016
CORE SPECIFICATION 1 ALL REFINERIES 8/5/2016
CORE SPECIFICATION 2 ALL REFINERIES 6/17/2019
CORE LINE CLASS 3 ALL REFINERIES 12/21/2018
CORE LINE CLASS 2 ALL REFINERIES 12/21/2018
REFINING REFERENCE DOCUME 1 ALL REFINERIES 9/19/2018
REFINING REFERENCE DOCUME 1 ALL REFINERIES 3/30/2017
REFINING REFERENCE DOCUME 0 ALL REFINERIES 9/8/2015
REFINING REFERENCE DOCUME 1 ALL REFINERIES 2/2/2018
REFINING REFERENCE DOCUME 0 ALL REFINERIES 9/8/2015
REFINING REFERENCE DOCUME 1 ALL REFINERIES 2/2/2018
SP FORM 0 ALL REFINERIES 9/21/2015
CORE SPECIFICATION 0 ALL REFINERIES 9/21/2015
SP FORM 0 ALL REFINERIES 9/22/2015
CORE SPECIFICATION 1 ALL REFINERIES 8/5/2016
CORE SPECIFICATION 1 ALL REFINERIES 6/28/2016
CORE SPECIFICATION 1 ALL REFINERIES 6/28/2016
REFINING STANDARD PRACTICE 1 ALL REFINERIES 12/5/2017
REFINING REFERENCE DOCUME 2 ALL REFINERIES 9/12/2018
SP FORM 0 ALL REFINERIES 10/28/2015
CORE SPECIFICATION 1 ALL REFINERIES 5/19/2016
RSP FORM 0 ALL REFINERIES 11/9/2015
RSP FORM 0 ALL REFINERIES 11/9/2015
CORE SPECIFICATION 0 ALL REFINERIES 11/13/2015
CORE SPECIFICATION 2 ALL REFINERIES 2/14/2018
CORE SPECIFICATION 1 ALL REFINERIES 5/19/2016
CORE SPECIFICATION 2 ALL REFINERIES 11/6/2018
SP FORM 0 ALL REFINERIES 12/1/2015
SP FORM 0 ALL REFINERIES 12/1/2015
SP FORM 0 ALL REFINERIES 12/1/2015
SP FORM 0 ALL REFINERIES 12/1/2015
INTERIM GUIDANCE 5 ALL REFINERIES 10/4/2019
SP FORM 0 ALL REFINERIES 1/27/2016
SP FORM 0 ALL REFINERIES 2/19/2016
SP FORM 0 ALL REFINERIES 2/19/2016
CORE SPECIFICATION 2 ALL REFINERIES 4/26/2019
RSP FORM 0 ALL REFINERIES 2/23/2016
RSP FORM 0 ALL REFINERIES 2/23/2016
REFINING STANDARD PRACTICE 0 ALL REFINERIES 2/23/2016
CORE SPECIFICATION 1 ALL REFINERIES 10/18/2017
RSP FORM 0 ALL REFINERIES 3/18/2016
REFINING REFERENCE DOCUME 2 ALL REFINERIES 6/25/2019
REFINING REFERENCE DOCUME 1 ALL REFINERIES 9/14/2018
REFINING REFERENCE DOCUME 1 ALL REFINERIES 9/14/2018
CORE LINE CLASS 3 ALL REFINERIES 3/10/2017
SP FORM 0 ALL REFINERIES 5/23/2016
SP FORM 0 ALL REFINERIES 5/23/2016
SP FORM 0 ALL REFINERIES 5/23/2016
CORE SPECIFICATION 3 ALL REFINERIES 9/23/2019
REFINING REFERENCE DOCUME 3 ALL REFINERIES 10/2/2019
RRD FORM 0 ALL REFINERIES 6/2/2016
REFINING REFERENCE DOCUME 1 ALL REFINERIES 9/11/2018
CORE SPECIFICATION 0 ALL REFINERIES 6/7/2016
CORE SPECIFICATION 0 ALL REFINERIES 6/7/2016
CORE SPECIFICATION 1 ALL REFINERIES 8/9/2016
RSP FORM 0 ALL REFINERIES 6/28/2016
REFINING STANDARD PRACTICE 0 ALL REFINERIES 6/28/2016
RSP FORM 12 ALL REFINERIES 6/20/2019
RSP FORM 42 ALL REFINERIES 8/16/2019
REFINING REFERENCE DOCUME 1 ALL REFINERIES 9/14/2018
RRD FORM 0 ALL REFINERIES 7/12/2016
REFINING REFERENCE DOCUME 2 ALL REFINERIES 6/13/2019
RRD FORM 0 ALL REFINERIES 8/29/2016
RRD FORM 0 ALL REFINERIES 8/29/2016
RRD FORM 0 ALL REFINERIES 8/29/2016
RRD FORM 0 ALL REFINERIES 9/13/2016
REFINING STANDARD PRACTICE 1 ALL REFINERIES 9/21/2018
RSP FORM 2 ALL REFINERIES 8/21/2018
STANDARD DRAWINGS 0 ALL REFINERIES 10/27/2016
STANDARD DRAWINGS 0 ALL REFINERIES 10/27/2016
STANDARD DRAWINGS 0 ALL REFINERIES 10/27/2016
STANDARD DRAWINGS 0 ALL REFINERIES 10/27/2016
STANDARD DRAWINGS 0 ALL REFINERIES 10/27/2016
STANDARD DRAWINGS 0 ALL REFINERIES 10/27/2016
STANDARD DRAWINGS 0 ALL REFINERIES 11/7/2016
STANDARD DRAWINGS 0 ALL REFINERIES 11/7/2016
STANDARD DRAWINGS 0 ALL REFINERIES 11/7/2016
STANDARD DRAWINGS 0 ALL REFINERIES 11/7/2016
STANDARD DRAWINGS 0 ALL REFINERIES 11/7/2016
SP FORM 2 ALL REFINERIES 1/24/2018
REFINING REFERENCE DOCUME 0 ALL REFINERIES 11/22/2016
RRD FORM 0 ALL REFINERIES 11/22/2016
CORE LINE CLASS 1 ALL REFINERIES 12/21/2018
CORE LINE CLASS 1 ALL REFINERIES 12/21/2018
CORE LINE CLASS 2 ALL REFINERIES 5/31/2019
CORE LINE CLASS 2 ALL REFINERIES 5/31/2019
CORE LINE CLASS 3 ALL REFINERIES 12/21/2018
CORE LINE CLASS 3 ALL REFINERIES 6/4/2019
CORE LINE CLASS 2 ALL REFINERIES 6/4/2019
CORE LINE CLASS 2 ALL REFINERIES 6/4/2019
CORE LINE CLASS 2 ALL REFINERIES 6/4/2019
CORE LINE CLASS 1 ALL REFINERIES 12/21/2018
CORE LINE CLASS 1 ALL REFINERIES 12/21/2018
CORE LINE CLASS 1 ALL REFINERIES 12/21/2018
REFINING REFERENCE DOCUME 1 ALL REFINERIES 5/4/2018
REFINING REFERENCE DOCUME 1 ALL REFINERIES 5/4/2018
REFINING REFERENCE DOCUME 1 ALL REFINERIES 5/4/2018
RSP FORM 1 ALL REFINERIES 10/4/2017
CORE SPECIFICATION 0 ALL REFINERIES 12/12/2016
RSP FORM 1 ALL REFINERIES 6/22/2017
RSP FORM 0 ALL REFINERIES 12/15/2016
RSP FORM 1 ALL REFINERIES 6/22/2017
RSP FORM 1 ALL REFINERIES 6/22/2017
RSP FORM 1 ALL REFINERIES 6/22/2017
RSP FORM 0 ALL REFINERIES 12/15/2016
RSP FORM 1 ALL REFINERIES 6/22/2017
RSP FORM 0 ALL REFINERIES 12/15/2016
RRD FORM 0 ALL REFINERIES 12/19/2016
REFINING REFERENCE DOCUME 1 ALL REFINERIES 3/16/2018
CORE LINE CLASS 2 ALL REFINERIES 12/21/2018
CORE LINE CLASS 1 ALL REFINERIES 12/21/2018
CORE LINE CLASS 2 ALL REFINERIES 12/21/2018
CORE LINE CLASS 1 ALL REFINERIES 12/21/2018
CORE LINE CLASS 3 ALL REFINERIES 12/21/2018
CORE LINE CLASS 5 ALL REFINERIES 9/12/2019
CORE LINE CLASS 3 ALL REFINERIES 12/21/2018
CORE LINE CLASS 2 ALL REFINERIES 12/21/2018
CORE LINE CLASS 1 ALL REFINERIES 12/21/2018
CORE LINE CLASS 2 ALL REFINERIES 12/21/2018
CORE LINE CLASS 3 ALL REFINERIES 3/27/2017
CORE SPECIFICATION 0 ALL REFINERIES 12/30/2016
CORE LINE CLASS 2 ALL REFINERIES 5/16/2018
REFINING REFERENCE DOCUME 3 ALL REFINERIES 4/11/2019
RSP FORM 0 ALL REFINERIES 2/10/2017
REFINING STANDARD PRACTICE 0 ALL REFINERIES 2/10/2017
RSP FORM 1 ALL REFINERIES 12/4/2018
REFINING STANDARD PRACTICE 1 ALL REFINERIES 12/4/2018
CORE LINE CLASS 1 ALL REFINERIES 12/21/2018
CORE LINE CLASS 1 ALL REFINERIES 12/21/2018
RRD FORM 0 ALL REFINERIES 2/15/2017
CORE LINE CLASS 1 ALL REFINERIES 12/21/2018
RSP FORM 0 ALL REFINERIES 2/16/2017
RRD FORM 0 ALL REFINERIES 2/21/2017
RRD FORM 0 ALL REFINERIES 2/21/2017
REFINING REFERENCE DOCUME 0 ALL REFINERIES 2/21/2017
REFINING REFERENCE DOCUME 0 ALL REFINERIES 2/22/2017
CORE SPECIFICATION 0 ALL REFINERIES 3/10/2017
STANDARD DRAWINGS 0 ALL REFINERIES 3/13/2017
STANDARD DRAWINGS 0 ALL REFINERIES 3/13/2017
STANDARD DRAWINGS 1 ALL REFINERIES 8/15/2018
REFINING STANDARD PRACTICE 0 ALL REFINERIES 3/14/2017
REFINING STANDARD PRACTICE 1 ALL REFINERIES 5/10/2018
RSP FORM 3 ALL REFINERIES 1/23/2018
RSP FORM 0 ALL REFINERIES 3/17/2017
REFINING STANDARD PRACTICE 2 ALL REFINERIES 11/20/2017
CORE LINE CLASS 0 ALL REFINERIES 3/20/2017
RRD FORM 0 ALL REFINERIES 4/12/2017
RRD FORM 0 ALL REFINERIES 4/12/2017
RRD FORM 0 ALL REFINERIES 4/12/2017
RRD FORM 0 ALL REFINERIES 4/12/2017
REFINING REFERENCE DOCUME 1 ALL REFINERIES 12/19/2017
CORE LINE CLASS 1 ALL REFINERIES 12/21/2018
CORE LINE CLASS 1 ALL REFINERIES 12/21/2018
CORE LINE CLASS 1 ALL REFINERIES 12/21/2018
SP FORM 0 ALL REFINERIES 4/26/2017
SP FORM 0 ALL REFINERIES 4/26/2017
SP FORM 0 ALL REFINERIES 4/26/2017
SP FORM 0 ALL REFINERIES 4/26/2017
SP FORM 0 ALL REFINERIES 4/26/2017
SP FORM 0 ALL REFINERIES 4/26/2017
SP FORM 0 ALL REFINERIES 4/26/2017
SP FORM 0 ALL REFINERIES 4/26/2017
SP FORM 0 ALL REFINERIES 4/26/2017
SP FORM 0 ALL REFINERIES 4/26/2017
CORE SPECIFICATION 1 ALL REFINERIES 10/10/2017
REFINING REFERENCE DOCUME 0 ALL REFINERIES 5/5/2017
CORE SPECIFICATION 0 ALL REFINERIES 5/23/2017
SP FORM 0 ALL REFINERIES 5/23/2017
CORE SPECIFICATION 1 ALL REFINERIES 10/26/2017
RRD FORM 0 ALL REFINERIES 5/26/2017
RRD FORM 0 ALL REFINERIES 5/26/2017
RRD FORM 0 ALL REFINERIES 5/26/2017
REFINING REFERENCE DOCUME 0 ALL REFINERIES 5/26/2017
RSP FORM 0 ALL REFINERIES 5/31/2017
RSP FORM 0 ALL REFINERIES 5/31/2017
RRD FORM 0 ALL REFINERIES 5/31/2017
REFINING STANDARD PRACTICE 0 ALL REFINERIES 6/8/2017
REFINING STANDARD PRACTICE 1 ALL REFINERIES 12/11/2018
RSP FORM 0 ALL REFINERIES 6/12/2017
RSP FORM 0 ALL REFINERIES 6/12/2017
RRD FORM 0 ALL REFINERIES 6/14/2017
RRD FORM 0 ALL REFINERIES 6/14/2017
RRD FORM 0 ALL REFINERIES 6/14/2017
RRD FORM 0 ALL REFINERIES 6/14/2017
RRD FORM 1 ALL REFINERIES 5/1/2018
RRD FORM 0 ALL REFINERIES 6/14/2017
RRD FORM 0 ALL REFINERIES 6/14/2017
RRD FORM 0 ALL REFINERIES 6/14/2017
RRD FORM 0 ALL REFINERIES 6/14/2017
REFINING REFERENCE DOCUME 0 ALL REFINERIES 6/14/2017
REFINING REFERENCE DOCUME 0 ALL REFINERIES 6/14/2017
REFINING REFERENCE DOCUME 0 ALL REFINERIES 6/14/2017
REFINING REFERENCE DOCUME 0 ALL REFINERIES 6/14/2017
CORE SPECIFICATION 0 ALL REFINERIES 6/19/2017
RSP FORM 1 ALL REFINERIES 6/22/2017
RSP FORM 1 ALL REFINERIES 6/22/2017
RSP FORM 1 ALL REFINERIES 6/22/2017
RSP FORM 0 ALL REFINERIES 6/22/2017
RSP FORM 0 ALL REFINERIES 6/22/2017
CORE SPECIFICATION 2 ALL REFINERIES 1/3/2019
CORE LINE CLASS 1 ALL REFINERIES 10/24/2017
RSP FORM 0 ALL REFINERIES 7/14/2017
RSP FORM 0 ALL REFINERIES 7/14/2017
RSP FORM 0 ALL REFINERIES 7/14/2017
RSP FORM 0 ALL REFINERIES 5/31/2017
WITHDRAWN 5 WITHDRAWN 11/7/2016
RRD FORM 0 ALL REFINERIES 7/21/2017
WITHDRAWN 0 ALL REFINERIES 7/28/2017
CORE SPECIFICATION 2 ALL REFINERIES 10/14/2019
RSP FORM 0 ALL REFINERIES 8/1/2017
REFINING POLICY 4 ALL REFINERIES 6/11/2019
REFINING STANDARD PRACTICE 1 ALL REFINERIES 10/15/2018
REFINING REFERENCE DOCUME 0 ALL REFINERIES 9/29/2017
CORE SPECIFICATION 2 ALL REFINERIES 11/30/2018
REFINING REFERENCE DOCUME 0 ALL REFINERIES 10/18/2017
REFINING REFERENCE DOCUME 0 ALL REFINERIES 9/24/2018
SP FORM 0 ALL REFINERIES 11/6/2017
CORE SPECIFICATION 0 ALL REFINERIES 11/6/2017
SP FORM 0 ALL REFINERIES 11/7/2017
SP FORM 0 ALL REFINERIES 11/7/2017
SP FORM 0 ALL REFINERIES 11/7/2017
CORE SPECIFICATION 0 ALL REFINERIES 11/7/2017
CORE SPECIFICATION 0 ALL REFINERIES 11/7/2017
CORE SPECIFICATION 0 ALL REFINERIES 11/7/2017
STANDARD DRAWINGS 2 ALL REFINERIES 9/11/2018
STANDARD DRAWINGS 2 ALL REFINERIES 9/11/2018
REFINING REFERENCE DOCUME 0 ALL REFINERIES 11/28/2017
RRD FORM 0 ALL REFINERIES 12/4/2017
RRD FORM 0 ALL REFINERIES 12/4/2017
RRD FORM 0 ALL REFINERIES 12/4/2017
RRD FORM 0 ALL REFINERIES 12/4/2017
REFINING REFERENCE DOCUME 0 ALL REFINERIES 12/5/2017
CORE SPECIFICATION 1 ALL REFINERIES 6/21/2019
REFINING REFERENCE DOCUME 0 ALL REFINERIES 12/19/2017
REFINING REFERENCE DOCUME 0 ALL REFINERIES 12/19/2017
REFINING REFERENCE DOCUME 0 ALL REFINERIES 12/20/2017
SP FORM 0 ALL REFINERIES 1/10/2018
SP FORM 0 ALL REFINERIES 1/10/2018
SP FORM 0 ALL REFINERIES 1/10/2018
SP FORM 0 ALL REFINERIES 1/10/2018
CORE SPECIFICATION 0 ALL REFINERIES 1/10/2018
CORE SPECIFICATION 0 ALL REFINERIES 1/10/2018
SP FORM 0 ALL REFINERIES 1/10/2018
SP FORM 0 ALL REFINERIES 1/10/2018
SP FORM 0 ALL REFINERIES 1/10/2018
SP FORM 0 ALL REFINERIES 1/10/2018
SP FORM 0 ALL REFINERIES 1/10/2018
SP FORM 0 ALL REFINERIES 1/10/2018
SP FORM 0 ALL REFINERIES 1/10/2018
CORE SPECIFICATION 0 ALL REFINERIES 1/10/2018
CORE SPECIFICATION 0 ALL REFINERIES 1/10/2018
CORE SPECIFICATION 0 ALL REFINERIES 1/10/2018
CORE SPECIFICATION 0 ALL REFINERIES 1/10/2018
CORE SPECIFICATION 0 ALL REFINERIES 1/10/2018
CORE SPECIFICATION 0 ALL REFINERIES 1/10/2018
CORE SPECIFICATION 0 ALL REFINERIES 1/10/2018
SP FORM 0 ALL REFINERIES 1/12/2018
SP FORM 0 ALL REFINERIES 1/12/2018
CORE LINE CLASS 0 ALL REFINERIES 1/12/2018
RSP FORM 0 ALL REFINERIES 1/19/2018
RSP FORM 0 ALL REFINERIES 1/19/2018
RSP FORM 1 ALL REFINERIES 3/26/2018
RSP FORM 0 ALL REFINERIES 1/19/2018
RSP FORM 0 ALL REFINERIES 1/19/2018
RRD FORM 0 ALL REFINERIES 1/23/2018
RRD FORM 0 ALL REFINERIES 1/23/2018
REFINING REFERENCE DOCUME 0 ALL REFINERIES 1/23/2018
CORE SPECIFICATION 0 ALL REFINERIES 2/20/2018
REFINING POLICY 1 ALL REFINERIES 5/3/2019
REFINING POLICY 0 ALL REFINERIES 2/28/2018
REFINING POLICY 1 ALL REFINERIES 6/12/2019
REFINING STANDARD PRACTICE 2 ALL REFINERIES 2/27/2019
REFINING STANDARD PRACTICE 0 ALL REFINERIES 2/22/2018
SP FORM 0 ALL REFINERIES 2/27/2018
CORE SPECIFICATION 0 ALL REFINERIES 2/27/2018
CORE SPECIFICATION 0 ALL REFINERIES 2/27/2018
REFINING POLICY 3 ALL REFINERIES 11/1/2018
INTERIM GUIDANCE 3 ALL REFINERIES 10/16/2019
INTERIM GUIDANCE 0 ALL REFINERIES 2/28/2018
REFINING REFERENCE DOCUME 0 ALL REFINERIES 3/6/2018
REFINING REFERENCE DOCUME 0 ALL REFINERIES 3/6/2018
REFINING REFERENCE DOCUME 0 ALL REFINERIES 3/7/2018
REFINING REFERENCE DOCUME 0 ALL REFINERIES 3/16/2018
REFINING REFERENCE DOCUME 2 ALL REFINERIES 2/13/2019
STANDARD DRAWINGS 1 ALL REFINERIES 12/14/2018
SP FORM 0 ALL REFINERIES 3/23/2018
SP FORM 0 ALL REFINERIES 3/23/2018
SP FORM 0 ALL REFINERIES 3/23/2018
SP FORM 0 ALL REFINERIES 3/23/2018
STANDARD DRAWINGS 0 ALL REFINERIES 4/9/2018
CORE SPECIFICATION 0 ALL REFINERIES 4/9/2018
INTERIM GUIDANCE 0 ALL REFINERIES 4/9/2018
CORE SPECIFICATION 0 ALL REFINERIES 4/10/2018
CORE SPECIFICATION 0 ALL REFINERIES 4/10/2018
SP FORM 0 ALL REFINERIES 4/13/2018
SP FORM 0 ALL REFINERIES 4/13/2018
SP FORM 0 ALL REFINERIES 4/13/2018
SP FORM 0 ALL REFINERIES 4/13/2018
SP FORM 0 ALL REFINERIES 4/13/2018
SP FORM 0 ALL REFINERIES 4/13/2018
SP FORM 0 ALL REFINERIES 4/13/2018
SP FORM 0 ALL REFINERIES 4/13/2018
SP FORM 0 ALL REFINERIES 4/13/2018
SP FORM 0 ALL REFINERIES 4/13/2018
SP FORM 0 ALL REFINERIES 4/13/2018
SP FORM 0 ALL REFINERIES 4/13/2018
SP FORM 0 ALL REFINERIES 4/13/2018
SP FORM 0 ALL REFINERIES 4/13/2018
SP FORM 0 ALL REFINERIES 4/13/2018
SP FORM 0 ALL REFINERIES 4/13/2018
SP FORM 0 ALL REFINERIES 4/13/2018
SP FORM 0 ALL REFINERIES 4/13/2018
SP FORM 0 ALL REFINERIES 4/13/2018
SP FORM 0 ALL REFINERIES 4/13/2018
SP FORM 0 ALL REFINERIES 4/13/2018
CORE SPECIFICATION 0 ALL REFINERIES 4/13/2018
SP FORM 0 ALL REFINERIES 4/18/2018
SP FORM 0 ALL REFINERIES 4/18/2018
CORE SPECIFICATION 0 ALL REFINERIES 4/23/2018
INTERIM GUIDANCE 0 ALL REFINERIES 5/1/2018
REFINING REFERENCE DOCUME 0 ALL REFINERIES 5/1/2018
RSP FORM 2 ALL REFINERIES 9/12/2019
RSP FORM 1 ALL REFINERIES 4/22/2019
RSP FORM 1 ALL REFINERIES 4/22/2019
CORE LINE CLASS 1 ALL REFINERIES 12/21/2018
CORE LINE CLASS 1 ALL REFINERIES 12/21/2018
CORE LINE CLASS 1 ALL REFINERIES 12/21/2018
CORE LINE CLASS 2 ALL REFINERIES 6/4/2019
CORE LINE CLASS 0 ALL REFINERIES 5/16/2018
CORE LINE CLASS 0 ALL REFINERIES 5/16/2018
INTERIM GUIDANCE 0 ALL REFINERIES 5/30/2018
INTERIM GUIDANCE 0 ALL REFINERIES 5/30/2018
INTERIM GUIDANCE 0 ALL REFINERIES 5/30/2018
REFINING STANDARD PRACTICE 0 ALL REFINERIES 6/7/2018
RSP FORM 0 ALL REFINERIES 6/7/2018
REFINING STANDARD PRACTICE 0 ALL REFINERIES 6/7/2018
RSP FORM 0 ALL REFINERIES 6/25/2018
REFINING STANDARD PRACTICE 0 ALL REFINERIES 6/25/2018
CORE SPECIFICATION 0 ALL REFINERIES 7/13/2018
REFINING POLICY 0 ALL REFINERIES 7/13/2018
CORE SPECIFICATION 0 ALL REFINERIES 7/20/2018
CORE SPECIFICATION 0 ALL REFINERIES 7/20/2018
REFINING STANDARD PRACTICE 1 ALL REFINERIES 5/23/2019
RSP FORM 0 ALL REFINERIES 8/7/2018
RSP FORM 0 ALL REFINERIES 8/7/2018
RSP FORM 0 ALL REFINERIES 8/7/2018
RSP FORM 0 ALL REFINERIES 8/7/2018
REFINING STANDARD PRACTICE 1 ALL REFINERIES 5/23/2019
REFINING STANDARD PRACTICE 0 ALL REFINERIES 8/7/2018
SP FORM 0 ALL REFINERIES 8/10/2018
CORE SPECIFICATION 0 ALL REFINERIES 8/10/2018
CORE SPECIFICATION 0 ALL REFINERIES 8/10/2018
REFINING POLICY 0 ALL REFINERIES 8/16/2018
REFINING REFERENCE DOCUME 0 ALL REFINERIES 9/6/2018
SP FORM 0 ALL REFINERIES 9/11/2018
CORE SPECIFICATION 0 ALL REFINERIES 9/11/2018
CORE SPECIFICATION 0 ALL REFINERIES 9/11/2018
RRD FORM 0 ALL REFINERIES 9/13/2018
RRD FORM 0 ALL REFINERIES 9/13/2018
RRD FORM 0 ALL REFINERIES 9/13/2018
RRD FORM 0 ALL REFINERIES 9/13/2018
RRD FORM 0 ALL REFINERIES 9/13/2018
RRD FORM 0 ALL REFINERIES 9/13/2018
REFINING REFERENCE DOCUME 1 ALL REFINERIES 1/22/2019
REFINING REFERENCE DOCUME 1 ALL REFINERIES 1/22/2019
REFINING REFERENCE DOCUME 0 ALL REFINERIES 9/13/2018
RRD FORM 0 ALL REFINERIES 9/13/2018
RRD FORM 0 ALL REFINERIES 9/13/2018
REFINING REFERENCE DOCUME 0 ALL REFINERIES 9/13/2018
REFINING REFERENCE DOCUME 1 ALL REFINERIES 1/22/2019
RRD FORM 1 ALL REFINERIES 1/22/2019
REFINING REFERENCE DOCUME 1 ALL REFINERIES 1/22/2019
RSP FORM 0 ALL REFINERIES 9/14/2018
RSP FORM 0 ALL REFINERIES 9/14/2018
RSP FORM 0 ALL REFINERIES 9/17/2018
RSP FORM 0 ALL REFINERIES 9/17/2018
RRD FORM 0 ALL REFINERIES 9/25/2018
REFINING REFERENCE DOCUME 0 ALL REFINERIES 9/25/2018
RRD FORM 0 ALL REFINERIES 10/1/2018
RRD FORM 0 ALL REFINERIES 10/1/2018
RRD FORM 0 ALL REFINERIES 10/1/2018
RRD FORM 0 ALL REFINERIES 10/1/2018
RRD FORM 0 ALL REFINERIES 10/1/2018
RRD FORM 0 ALL REFINERIES 10/1/2018
RRD FORM 0 ALL REFINERIES 10/1/2018
RRD FORM 0 ALL REFINERIES 10/1/2018
RRD FORM 0 ALL REFINERIES 10/1/2018
RRD FORM 0 ALL REFINERIES 10/1/2018
RRD FORM 0 ALL REFINERIES 10/1/2018
RRD FORM 0 ALL REFINERIES 10/1/2018
REFINING STANDARD PRACTICE 1 ALL REFINERIES 3/8/2019
REFINING STANDARD PRACTICE 1 ALL REFINERIES 12/13/2018
CORE SPECIFICATION 0 ALL REFINERIES 11/9/2018
SP FORM 0 ALL REFINERIES 11/12/2018
CORE SPECIFICATION 0 ALL REFINERIES 11/12/2018
ANDEAVOR 5 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 2 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 2 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 2 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 2 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 2 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 2 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 3 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 3 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 2 ANDEAVOR HERITAG 11/26/2018
ANDEAVOR 2 ANDEAVOR HERITAG 11/26/2018
REFINING REFERENCE DOCUME 0 ALL REFINERIES 11/27/2018
REFINING REFERENCE DOCUME 0 ALL REFINERIES 11/27/2018
REFINING REFERENCE DOCUME 0 ALL REFINERIES 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 2 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 2 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 2 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 2 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 2 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 2 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 2 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 2 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 2 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 2 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 2 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 2 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 2 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 2 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 2 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 2 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 2 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 2 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 0 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 1 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 5 ANDEAVOR HERITAG 11/27/2018
ANDEAVOR 3 ANDEAVOR HERITAG 11/27/2018
INTERIM GUIDANCE 3 ALL REFINERIES 11/28/2018
REFINING STANDARD PRACTICE 0 ALL REFINERIES 12/3/2018
STANDARD DRAWINGS 0 ALL REFINERIES 12/4/2018
STANDARD DRAWINGS 0 ALL REFINERIES 12/4/2018
STANDARD DRAWINGS 0 ALL REFINERIES 12/4/2018
REFINING REFERENCE DOCUME 0 ALL REFINERIES 12/10/2018
REFINING REFERENCE DOCUME 0 ALL REFINERIES 12/10/2018
SP FORM 0 ALL REFINERIES 12/14/2018
CORE SPECIFICATION 0 ALL REFINERIES 12/14/2018
CORE SPECIFICATION 0 ALL REFINERIES 12/14/2018
CORE LINE CLASS 0 ALL REFINERIES 12/21/2018
SP FORM 0 ALL REFINERIES 1/4/2019
INTERIM GUIDANCE 0 ALL REFINERIES 1/4/2019
REFINING POLICY 0 ALL REFINERIES 1/4/2019
REFINING REFERENCE DOCUME 0 ALL REFINERIES 1/4/2019
STANDARD DRAWINGS 0 ALL REFINERIES 1/7/2019
STANDARD DRAWINGS 0 ALL REFINERIES 1/7/2019
STANDARD DRAWINGS 0 ALL REFINERIES 1/7/2019
STANDARD DRAWINGS 0 ALL REFINERIES 1/7/2019
STANDARD DRAWINGS 0 ALL REFINERIES 1/7/2019
STANDARD DRAWINGS 0 ALL REFINERIES 1/7/2019
STANDARD DRAWINGS 0 ALL REFINERIES 1/7/2019
STANDARD DRAWINGS 0 ALL REFINERIES 1/7/2019
STANDARD DRAWINGS 0 ALL REFINERIES 1/7/2019
STANDARD DRAWINGS 0 ALL REFINERIES 1/7/2019
STANDARD DRAWINGS 0 ALL REFINERIES 1/7/2019
STANDARD DRAWINGS 0 ALL REFINERIES 1/7/2019
STANDARD DRAWINGS 0 ALL REFINERIES 1/7/2019
STANDARD DRAWINGS 0 ALL REFINERIES 1/7/2019
STANDARD DRAWINGS 0 ALL REFINERIES 1/7/2019
RRD FORM 0 ALL REFINERIES 2/20/2019
RRD FORM 0 ALL REFINERIES 2/20/2019
RRD FORM 0 ALL REFINERIES 2/20/2019
REFINING REFERENCE DOCUME 0 ALL REFINERIES 2/20/2019
INTERIM GUIDANCE 1 ALL REFINERIES 7/30/2019
REFINING REFERENCE DOCUME 0 ALL REFINERIES 3/25/2019
REFINING REFERENCE DOCUME 0 ALL REFINERIES 3/27/2019
CORE SPECIFICATION 0 ALL REFINERIES 3/28/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/1/2019
REFINING STANDARD PRACTICE 2 ALL REFINERIES 10/14/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/15/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/15/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/15/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/15/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/15/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/15/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/15/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/15/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/15/2019
STANDARD DRAWINGS 0 ALL REFINERIES 4/15/2019
INTERIM GUIDANCE 0 ALL REFINERIES 4/16/2019
INTERIM GUIDANCE 0 ALL REFINERIES 4/24/2019
CORE SPECIFICATION 0 ALL REFINERIES 7/9/2019
SP FORM 0 ALL REFINERIES 7/9/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 1 ALL REFINERIES 8/30/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 1 ALL REFINERIES 8/30/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 0 ALL REFINERIES 7/10/2019
STANDARD DRAWINGS 1 ALL REFINERIES 8/30/2019
REFINING REFERENCE DOCUME 0 ALL REFINERIES 7/29/2019
RSP FORM 0 ALL REFINERIES 8/12/2019
RSP FORM 0 ALL REFINERIES 8/12/2019
RSP FORM 0 ALL REFINERIES 8/12/2019
RSP FORM 0 ALL REFINERIES 8/12/2019
RSP FORM 0 ALL REFINERIES 8/12/2019
RSP FORM 0 ALL REFINERIES 8/12/2019
REFINING REFERENCE DOCUME 1 ALL REFINERIES 10/21/2019
CORE LINE CLASS 0 ALL REFINERIES 8/27/2019
REFINING REFERENCE DOCUME 0 ALL REFINERIES 9/10/2019
REFINING REFERENCE DOCUME 0 ALL REFINERIES 9/10/2019
REFINING REFERENCE DOCUME 0 ALL REFINERIES 9/10/2019
REFINING REFERENCE DOCUME 0 ALL REFINERIES 9/10/2019
REFINING REFERENCE DOCUME 0 ALL REFINERIES 9/10/2019
REFINING REFERENCE DOCUME 0 ALL REFINERIES 9/10/2019
REFINING REFERENCE DOCUME 0 ALL REFINERIES 9/10/2019
CORE LINE CLASS 0 ALL REFINERIES 9/10/2019
RRD FORM 0 ALL REFINERIES 9/24/2019
REFINING REFERENCE DOCUME 0 ALL REFINERIES 9/24/2019
SP FORM 0 ALL REFINERIES 10/1/2019
SP FORM 0 ALL REFINERIES 10/1/2019
SP FORM 0 ALL REFINERIES 10/1/2019
SP FORM 0 ALL REFINERIES 10/1/2019
REFINING REFERENCE DOCUME 0 ALL REFINERIES 10/2/2019
REFINING REFERENCE DOCUME 0 ALL REFINERIES 10/2/2019
REFINING REFERENCE DOCUME 0 ALL REFINERIES 10/2/2019
REFINING REFERENCE DOCUME 0 ALL REFINERIES 10/2/2019
STANDARD DRAWINGS 0 ALL REFINERIES 10/14/2019