Вы находитесь на странице: 1из 128

The Improvement and Study: Bergamo’s Node

Faculty of Civil and Industrial Engineering


Department of Civil, Constructional and Environmental Engineering (DICEA)
Master Degree in Transport Systems Engineering

Juan David Correa Panesso


Matricola 1818433

Relatore Correlatore
Paola Di Mascio Giuseppe Loprencipe

A.A. 2018-2019
TABLE OF CONTENTS
1. ABSTRACT................................................................................................................................... 10

2. INTRODUCTION........................................................................................................................ 11

3. CONCEPTS AT IMPROVING INFRASTRUCTURES ......................................................... 14

3.1. Context of the CBA For Infrastructures ............................................................................... 14

3.2. Delays as a Main Factor ......................................................................................................... 15

3.3. The Level of Service ................................................................................................................ 16

4. CONTEXT OF THE PROJECT................................................................................................... 19

4.1. Premise ..................................................................................................................................... 19

4.2. Territorial Framing ................................................................................................................. 20

4.3. Functional analysis of the junction ....................................................................................... 21

4.4. Analysis of the Current Transport Offer ............................................................................. 23

4.4.1. State Strada SS671.................................................................................................................. 24

4.4.2. Strada Provinciale SP EX SS 470.......................................................................................... 24

4.4.3. The Highway.......................................................................................................................... 25

4.4.4. Bergamo A4 Toll ................................................................................................................... 26

4.5. Analysis of Current Transport Demand .............................................................................. 27

4.5.1. Bergamo A4 Casello Data .................................................................................................... 28

4.5.2. Demand 2016 ......................................................................................................................... 29

4.5.3. Demand 2019 ......................................................................................................................... 35

4.5.4. Traffic Summary .................................................................................................................... 36

5. SOLUTIONS AND IMPROVMENTS OF THE CONFLICT AREAS ................................... 38

5.1. Analysis of the Current State................................................................................................. 38

5.2. Analysis of Project Alternatives ............................................................................................ 41

5.2.1. Project Alternative No. 1 ...................................................................................................... 41

5.2.2. Project Alternative No. 2 ...................................................................................................... 44

5.2.3. Project Alternative 3 .............................................................................................................. 46


2
5.2.4. Project Alternative 4 .............................................................................................................. 49

5.3. LEVEL OF SERVICES ANALYSYS OF THE CONFLICT ZONES .................................. 52

5.3.1. Matrix OD Update ................................................................................................................ 52

5.3.2. Current State .......................................................................................................................... 54

5.3.2.1. Interchange Ramps ............................................................................................................ 54

5.3.2.1.1. Interchange Ramp 1 ........................................................................................................ 55

5.3.2.1.2 Interchange Ramp 2 ......................................................................................................... 66

5.3.2.1.3 Interchange Ramp 3 ......................................................................................................... 68

5.3.2.2. Entry Ramps........................................................................................................................ 70

5.3.2.2.1 Entry Ramp 1 ................................................................................................................... 71

5.3.2.2.2 Entry Ramp 2 .................................................................................................................... 73

5.3.2.3. Exit Ramps........................................................................................................................... 74

5.3.2.3.1 Exit Ramp 1 ....................................................................................................................... 75

5.3.3. Solution 1 ................................................................................................................................ 78

5.3.3.1. Interchange Ramp .............................................................................................................. 78

5.3.3.2. Entrie Ramp ........................................................................................................................ 78

5.3.3.3. Exit Ramp. ........................................................................................................................... 79

5.3.3.3.1 Exit Ramp 1 ....................................................................................................................... 79

5.3.3.3.2 Exit Ramp 2 ....................................................................................................................... 79

5.3.3.3.3 Exit Ramp 3 ....................................................................................................................... 80

5.3.4. Solution 2 ................................................................................................................................ 80

5.3.4.1. Interchange Ramp .............................................................................................................. 80

5.3.4.2. Entrie Ramp ........................................................................................................................ 80

5.3.4.3. Exit Ramp. ........................................................................................................................... 81

5.3.5. Solution 3 ................................................................................................................................ 81

5.3.5.1. Interchange Ramp .............................................................................................................. 81

5.3.5.2. Entrie Ramps ....................................................................................................................... 81

5.3.5.3. Exit Ramps........................................................................................................................... 81

3
5.3.6. Solution 4 ................................................................................................................................ 81

5.3.6.1. Interchange Ramps ............................................................................................................ 81

5.3.6.2. Entrie Ramps ....................................................................................................................... 82

5.3.6.3. Exit Ramps........................................................................................................................... 82

6. TRAFFIC SIMULATION ............................................................................................................ 83

6.1.1. Network Construction .......................................................................................................... 84

6.2. Input Data.................................................................................................................................. 85

6.3. Calibration of the Model ......................................................................................................... 88

7. RESULTS ...................................................................................................................................... 92

7.1. 2016 Results .............................................................................................................................. 96

7.2. 2024 Results ............................................................................................................................ 100

7.3. 2048 Results ............................................................................................................................ 102

8. COST BENEFIT ANALISYS .................................................................................................... 106

8.1. Cost of Expenses.................................................................................................................... 106

8.1.1. Total Cost of Infrastructure................................................................................................ 106

8.1.2. Cost of Maintenance ........................................................................................................... 107

8.2. Cost of Benefits ..................................................................................................................... 107

8.2.1. Calculation of Total Delay ................................................................................................. 108

8.3. CBA ......................................................................................................................................... 118

9. CONCLUSIONS ........................................................................................................................ 124

10. BIBLIOGRAPHY ..................................................................................................................... 128

LIST OF FIGURES

Figure 1 Level of Service Criteria for unsignalized intersections ........................................... 18

Figure 2: Study are location ........................................................................................................... 19


4
Figure 3: Study area before the first intervention....................................................................... 21

Figure 4: Southwest Junction Overview View ........................................................................... 22

Figure 5: Territorial Framing ......................................................................................................... 23

Figure 6: State Road 671- between junction A4 and SS42 ......................................................... 24

Figure 7: SP ex SS470 – north bound way with the A4 –northbound ..................................... 25

Figure 8: Section via Highways – northbound direction .......................................................... 26

Figure 9: Bergamo's A4 Toll........................................................................................................... 27

Figure 10: Annual data – Bergamo's A4 tollbooth...................................................................... 28

Figure 11: Average Annual Daily Data – Bergamo's A4 Tollbooth ......................................... 29

Figure 12: Sections monitored year 2016 ..................................................................................... 33

Figure 13: OD Sections ................................................................................................................... 34

Figure 14: Localizing Automatic Survey Stations ...................................................................... 35

Figure 15: Traffic Surveys 2019 - HPM ........................................................................................ 36

Figure 16: Comparison with Survey Campaign 2016 - HPM ................................................... 37

Figure 17: Conflict analysis of the current state.......................................................................... 38

Figure 18:Interference Matrix – Analysis of individual traffic conflicts ................................. 39

Figure 19: Functional Diagram Solution 1 .................................................................................. 42

Figure 20: Interference Matrix – Analysis of individual traffic conflicts ................................ 43

Figure 21: Functional diagram solution 2 .................................................................................... 44

Figure 22: Interference Matrix – Analysis of individual traffic conflicts ................................ 45

Figure 23: Functional Diagrama Solution 3 ................................................................................. 47

Figure 24: Interference Matrix – Analysis of individual traffic conflicts ................................ 48

Figure 25: Functional Diagram Solution 4 ................................................................................... 50

Figure 26: Interference Matrix – Analysis of individual traffic conflicts ................................ 51

Figure 27: 2016 OD Matrix ............................................................................................................. 53

Figure 28: Update 2019 OD matrix ............................................................................................... 54

Figure 29: interchange Graphic locations .................................................................................... 55

Figure 30: Passenger car equivalent flow rate veh/h 8 - 9 2019 ............................................... 58

5
Figure 31: Ns configuration .......................................................................................................... 61

Figure 32: Flows Quality depending on the interchange length and flow ............................. 66

Figure 33: Entry ramps location .................................................................................................... 71

Figure 34: Exit ramps location ....................................................................................................... 75

Figure 35: Vissim network solution 4 ........................................................................................... 84

Figure 36: 2016 OD matrix for the current scenario ................................................................... 86

Figure 37: 2016 OD matrix for the first solution ......................................................................... 86

Figure 38: 2016 OD matrix for the second solution .................................................................... 86

Figure 39: 2016 OD matrix for the third solution ....................................................................... 86

Figure 40: 2016 OD matrix for the fourth solution ..................................................................... 87

Figure 41: Driving behavior parameters ...................................................................................... 90

Figure 42: Google traffic map at peak hour................................................................................. 91

Figure 43:Evaluation configuration .............................................................................................. 93

Figure 44: Simulation Parameters ................................................................................................. 95

Figure 45: Delay OD matrix for the current scenario in 2016 .................................................. 97

Figure 46: LOS OD matrix for the current scenario 2016 .......................................................... 97

Figure 47: delay OD matrix for solution 1 in 2016 scenario ...................................................... 97

Figure 48: LOS OD matrix for solution 1 (2016) ........................................................................ 97

Figure 49: Delay OD matrix for solution 2 in 2016 scenario ..................................................... 98

Figure 50: LOS OD matrix for solution 2 (2016) ........................................................................ 98

Figure 51: delay OD matrix for solution 3 in 2016 scenario ...................................................... 98

Figure 52: LOS OD matrix for solution 3 (2016) ........................................................................ 99

Figure 53: Delay OD matrix for solution 4 in 2016 scenario .................................................... 99

Figure 54: LOS OD matrix for solution 4 (2016) ........................................................................ 99

Figure 55: Delay OD matrix for solution 1 in 2024 scenario .................................................. 100

Figure 56: LOS OD matrix for solution 1 (2024) ...................................................................... 100

Figure 57: delay OD matrix for solution 2 in 2024 scenario .................................................... 100

Figure 58: LOS OD matrix for solution 2 (2024) ...................................................................... 101

6
Figure 59: delay OD matrix for solution 3 in 2024 scenario ................................................... 101

Figure 60: LOS OD matrix for solution 3 (2024) ...................................................................... 101

Figure 61: delay OD matrix for solution 4 in 2024 scenario ................................................... 102

Figure 62: LOS OD matrix for solution 4 (2024) ...................................................................... 102

Figure 63: Delay OD matrix for solution 1 in scenario 2048 .................................................. 102

Figure 64: LOS OD matrix for solution 1 (2048) ....................................................................... 103

Figure 65: delay OD matrix for solution 2 in scenario 2048 ................................................... 103

Figure 66: LOS OD matrix for solution 2 (2048) ....................................................................... 103

Figure 67: delay OD matrix for solution 3 in scenario 2048 ................................................... 104

Figure 68: LOS OD matrix for solution 3 (2048) ....................................................................... 104

Figure 69: Delay OD matrix for solution 4 in 2048 scenario .................................................. 104

Figure 70: LOS OD matrix for solution 4 (2048) ....................................................................... 105

Figure 71: Personal delay vs node demand solution 1 ............................................................ 109

Figure 72: Personal delay vs node demand solution 3 ............................................................ 109

Figure 73: Personal delay vs node demand solution 3 ............................................................ 110

Figure 74: Personal delay vs node demand solution 4 ............................................................ 110

Figure 75: Distribution demand over the day. ......................................................................... 112

LIST OF TABLES

Table 1: 2016 OD matrices for each means at morning peak hour .......................................... 31

Table 2: 2016 OD matrices for each means at night peak hour ................................................ 32

Table 3: Passenger- Car equivalents on extended Freeway ...................................................... 57

Table 4: PROPORTION OF TRUCKS/BUSES IN THE TRAFFIC ............................................ 57

Table 5: Heavy - vehicle adjustment factor ................................................................................. 58


7
Table 6: Symbols and definitions for interchange zones ........................................................... 59

Table 7: Constants for Ws and Wns Factors ................................................................................ 63

Table 8: Level of service by density .............................................................................................. 65

Table 9: Quality of the interchange flow...................................................................................... 65

Table 10: Symbols and definitions for entries zones calculations ............................................ 71

Table 11: The value of Pac for the entries calculations .............................................................. 72

Table 12: Level of service by density ............................................................................................ 73

Table 13: Symbols and definitions for exit zones calculations ................................................. 75

Table 14: The value of Pac for the exit ramps ............................................................................. 76

Table 15: Level of service according to the Vissim manual ...................................................... 96

Table 16: Total cost of infrastructure by categories .................................................................. 107

Table 17: Cost of maintenance ..................................................................................................... 107

Table 18: Hour delay in seconds per year for the current state .............................................. 112

Table 19: Hour delay in seconds per year for the solution 1 .................................................. 113

Table 20: Hour delay in seconds per year for the solution 2 .................................................. 113

Table 21: Hour delay in seconds per year for the solution 3 .................................................. 114

Table 22: Hour delay in seconds per year for the solution 4 .................................................. 114

Table 23: Value of time per person and average occupancy factor according the handbook

on external cost of transport. ....................................................................................................... 115

Table 24: Total cost process of benefits per each year for solution 1 ..................................... 116

Table 25: Total cost process of benefits per each year for solution 2 ..................................... 117

Table 26: Total cost process of benefits per each year for solution 3 ..................................... 117

Table 27: Total cost process of benefits per each year for solution 4 ..................................... 118

Table 28: CBA Solution 1 .............................................................................................................. 120

Table 29: CBA indicators solution 1 ........................................................................................... 120

Table 30: CBA Solution 2 .............................................................................................................. 121

Table 31: CBA indicators solution 2 ........................................................................................... 121

Table 32: CBA Solution 3 ............................................................................................................. 122

8
Table 33: CBA indicators solution 3 .......................................................................................... 122

Table 34: CBA Solution 4 .............................................................................................................. 123

Table 35: CBA indicators solution 4 ........................................................................................... 123

9
1. ABSTRACT

The following is a study of a road node intersection in a real case in the city of Bergamo,

which, due to its high vehicular demand, represents a constant problem, in terms of

delays, service level, and safety.

It has been identified for different reasons such as construction facilities, particular

interests and underestimation of transport analysis that when it comes to addressing this

kind of projects in reality there is an absence of analysis in the different benefits that

directly had an impact for the users that make use of these infrastructures. In this way, it

has been decided to start a transport analysis considering the users as the most benefited

with these decisions.

Having identified the main points of conflict of the node, it has been decided to propose 4

possible road infrastructure solutions, and make a study of traffic in a general, detailed

and total way (by means of a micro simulation) as well as a financial study of all the road

node in its current state, and for all possible solutions taking into account the current

demand, as well as future demand projections.

Thus, with all the results, an analysis has been carried out to explained in detail which

solution is more convenient and provides greater benefits during its useful life.

10
2. INTRODUCTION

The roads infrastructure works make a crucial contribution to economic development and

growth and bring important social benefits. They are of vital importance in order to make

a nation grow and develop. In addition, providing access to employment, social, health

and education services makes a road network crucial in fighting against poverty.

And it is so much like this so that even the most developed countries never stop building,

maintaining and repowering their infrastructures, even if that means, spending most of

the country's budget or entering a considerable debt, but knowing that the multiple

benefits will eventually return positively for all the parties, both for the state and for

society. Society that as individuals enjoy the benefits from the new infrastructure works so

they found themselves with the possibility to improve their quality of life, by providing

accessibility, reducing delays, reducing noise and environmental pollution, saving fuel,

and so forth.

And it is precisely there where all the efforts should be focused, in society. And build

road infrastructure projects, implies a long process that involves the development of

activities in sequence, limited budget, which seeks to solve a problem most of the times for

the good of society. And it is in this process when the parties involved, private and the

public, tend to lose the priorities on the final objectives of maximizing the benefits to the

individuals when it comes to evaluating the possible solutions to an infrastructure

problem.

11
And normally this is due the fact that in the planning, bidding and construction process,

problems related to construction processes, budget limitation, purchase of land, among

others, often makes the chosen option the best immediate option that adapt to a present

context, but not the one that will maximize the benefit for the users. and this does not

mean that no benefits for society will not be evidenced, in fact they are evidenced, and this

makes this problem overlooked by the fact that these problems are always reflected in

future costs.

The main objective of the thesis is to analyze, the current state, and the alternatives

(proposed by INGESCA company in charge of the pre-feasibility study and viability of

the design) of a road infrastructure project "REDEVELOPMENT OF THE A4

MOTORWAY EXIT AND CONNECTION WITH THE BERGAMO INTERURBAN AXIS”

(which I served as junior designer), so they can be evaluated in order to reach the best of

them in terms of benefits for the users.

In Chapter 3 the CBA for infrastructures, the importance of the delays as a main factor,

and the level of services concepts will be studied. For that, the general concept of CBA,

delays and level of service will be explained.

In chapter 4 the context of the project will be explained, the characteristics of demand,

territorial framing, traffic state, functional analysis, the scope of the project, the challenges

and the expected results will be described in this chapter.

12
In chapter 5 the different alternatives project will be explained; the project will be

analyzed from the geometric technical point of view. in which all areas of conflict will be

analyzed, in a way that a technical review of the current scenario and future scenarios will

be done by carry out a confrontation between them.

In chapter 6 the description of the entire creation of the 3D network will be made in order

to run the simulation and access the results of LOS and delays, the entire process of

creation, calibration of the model will be carried out in the Vissim (For microsimulation)

software, the current state and the alternatives will be evaluated.

In chapter 7 after running the Vissim microsimulation the results of the delays and level of

service, as for the whole will be illustrated, described and analyzed for each branch as for

the whole node.

In chapter 8 once all the results have been obtained for the level of service as for the

delays, for the current state as for each solution, and with the general costs of each one, the

cost-benefit analysis can be performed in order to obtain the main indicators in order to

carry out an appropriate financial analysis.

13
3. CONCEPTS AT IMPROVING

INFRASTRUCTURES

3.1. Context of the CBA For Infrastructures

The growing world population and its inherent need for increased transportation is

straining existing transportation infrastructure and creating the need for megaprojects.

Financial resources are scarce and therefore must be allocated efficiently. Properly valuing

transportation infrastructure in cost-benefit analysis (CBA) will allow for the most efficient

allocation of resources and allow us to do more with less resources (Heather Jones 2014).

CBA is a formal process for evaluating a project that evolved from the economic constructs

of consumer surplus and externality. It then moved into a formal regulated process based

upon work by economists and government agencies and is now required by many entities

for project approval, seeking the efficient allocation of. CBA has been called the “single

most important problem-solving tool in policy work”. It is a decision-making tool that is

one of the most widely accepted and applied methods for project appraisal for large-scale

infrastructure investments in the public sector because it provides many benefits

including, a model of rationality, creating, evaluating and

comparing alternatives including different scales for the alternatives, monetizing the costs

and benefits and guiding decision makers” (Munger, 2000).

CBA weighs the pros and cons of a project or policy in a rational and systematic process.

Inherently requires the creation and evaluation of at least two options, “do it or not” plus

it requires an evaluation at several different scales. Decision makers must assess who are

14
the gainers and losers across both space and time. Therefore, it monetizes both inputs and

outputs. This monetization is founded on a socially accepted valuation system that

transforms the inputs into a monetary value using actual or shadow prices. Essentially, it

seeks to enumerate all direct costs and benefits to society of a particular project, assign

monetary values, discount them to a net present value and add them into a single number

to evaluate the project (Nickel, J 2009).

3.2. Delays as a Main Factor


Travel time is one of the largest categories of transport costs, and time savings are often

claimed to be the greatest benefit of transport projects such as roadway and public transit

improvements. Factors such as traveler comfort and travel reliability can be quantified by

adjusting travel time cost values. On an average people devote 60-90 minutes a day to

travel. Most people seem to enjoy a certain amount of personal travel, about 30 daily

minutes, and dislike devoting more than about 90 minutes a day (Mokhtarian and

Salomon, 2001)

Delay is an important measure of effectiveness in traffic studies, as it presents the direct

cost of fuel consumption and indirect cost of time loss to motorists. Delay, however, is a

parameter that is difficult to estimate because it includes the delay associated with

decelerating the vehicle to stop, the stopped delay, and the delay associated with

accelerating from a stop. This is particularly true in oversaturated traffic demand

conditions, where vehicles continuously decelerate and accelerate. The problems

associated with vehicular traffic moving through an urban street network are numerous.

In particular, as a result of the continuous increase of traffic in central urban areas, traffic

queues and delays are often experienced. For any policy making process to deal with the

worsening situation, it is the initial priority to estimate the impacts of traffic delay on the

overall national economy in monetary terms. Besides, estimates of delay costs give the

15
value that can be imposed on the road users which is a very effective and widely used

method of traffic demand management.

With increasing delays and congestion on streets and highways, finding effective ways to

maintain acceptable levels of service is critical to satisfying users as well as protecting the

environment. As a result, traffic and transportation problems are aggravating day by day.

These problems are manifesting themselves in the form of increased traffic congestion,

delays and subsequently causing wastage of fuels and creation of pollution and make it a

hoard of residential, commercial and business activities. Lack of proper planning and

designing of intersection signals, bus bays, parking areas etc. are the main reasons for the

cause of delays and congestions faced by road transportation. Here comes the importance

of developing methods for estimating and quantifying the amount of delay in the form of

value of time, fuel cost and pollution costing

3.3. The Level of Service

Quality of service requires quantitative measures to characterize operational conditions

within a traffic stream. Level of service (LOS) is a quality measure describing operational

conditions within a traffic stream, generally in terms of such service measures as speed

and travel time, freedom to maneuver, traffic interruptions, and comfort and convenience

(HCM 2000).

Six levels of service are defined for each type of facility that has analysis procedures

available. Letters designate each level, from A to F, with LOS A representing the best

operating conditions and LOS F the worst. Each level of service represents a range of

16
operating conditions and the driver’s perception of those conditions. Safety is not included

in the measures that establish service levels (HCM 2000).

For unsignalized intersections LOS criteria can be further reduced into two intersection

types: all-way stop-controlled and two-way stop-controlled. All-way, stop-controlled

intersection LOS is expressed in terms of the average vehicle delay of all of the

movements, much like that of a signalized intersection. Two-way, stop-controlled

intersection LOS is defined in terms of the average vehicle delay of an individual

movement(s). This is because the performance of a two-way, stop-controlled intersection

is more closely reflected in terms of its individual movements, rather than its performance

overall. For this reason, LOS for a two-way, stop-controlled intersection is defined in terms

of its individual movements. With this in mind, total average vehicle delay (i.e., average

delay of all movements) for a two-way, stop-controlled intersection should be viewed

with discretion. Table 2 shows LOS criteria for unsignalized intersections (both all-way

and two-way, stop controlled) (HCM 2000).

Figure 1 Level of Service Criteria for unsignalized intersections

17
The Los criteria for unsignalized intersections are somewhat different from the criteria

used for signalized intersections primarily because different transportation facilities create

different driver perceptions. The expectation is that a signalized intersection is designed to

carry higher traffic volumes and experience greater delay than an

unsignalized intersection.

18
4. CONTEXT OF THE PROJECT

4.1. Premise
This study aims to assess the possible road-related consequences of the project to

redevelop the tiered roundabout junction located on the intercity axis of Bergamo at the

A4 motorway junction, which is the main access node to the city.

The roundabout located on the Interurban Axis of Bergamo, at the A4 motorway junction

of the city of Bergamo, is submerged by a substantial vehicle volumes on the , mainly that

coming and heading towards the highway and connecting with the airport of Orio al

Serio, the east-west flows passing along the "Interurban Axis", those in the north-south

direction in and out of the city and heading towards the valleys along the Sp ex SS470. In

particular, recent traffic estimates (March 2019) show a significant commitment of the

motorway node, with about 13,750 vehicles/h affecting it during peak hours.

The junction is therefore simultaneously affected by large traffic flows, some of which

overlap and mutually interfering, which make the junction particularly difficult,

particularly during peak hours. Morning and evenings.

Figure 2: Study are location

19
The work therefore arises from the need to improve the connections affecting the node and

at the same time raise the service levels of the intersection in relation to the volume of

traffic.

In this sense, the technical and economic feasibility project, to which this study is attached,

has pursued the aim of identifying different design solutions with the intention of

eliminating conflicting maneuvers, improving their capacity and consequently the

expected vehicle outflow on the road node, while trying to contain the costs of building

the infrastructure.

4.2. Territorial Framing

The study area affected by the new infrastructure is located in the southern area of the

City of Bergamo. The area is characterized by a population spread over small or medium-

sized urban centers, the most important of which is the provincial capital, with almost

120,000 inhabitants, followed by Treviglio with 29,000 and Dalmine with 23,000. The other

municipalities do not exceed 20,000 inhabitants.

The motorway junction as we know today, originates with the work related to the World

Cup in Italy in 1990, when the Interurban Axis Cuneo-Seriate was built. Previously, access

to the motorway was made with a two-level junction between the Former SS470 of the

Valleys and Via Highway.

20
Figure 3: Study area before the first intervention

With the works carried out in 1989 by Anas, the junction acquires the existing

conformation. Since then there has been a maximum development of the area with various

urbanization interventions between residential and industrial.

4.3. Functional analysis of the junction


The Bergamo Node is a three-tiered junction that manages, as mentioned above, five

important lines characterized by high levels of traffic. Below the ground level we have the

junction ramp between the SP ex SS 470 and the Interurban Axis, this track manages the

flows coming from the west wanting to climb towards the valleys of Brembo and Serio.

21
Above the ground level, the junction provides continuity to the Interurban Axis through a

viaduct and connects the SP ex SS 470 and the Interurban Axis with a detected ramp that

manages those coming from the valleys and desire to continue east.

All the other directions are managed by a roundabout with a 130m radius crown located

on the ground level. The entries of the different ramps in the roundabout take place in

various ways, through a stop for those coming from the Interurban Axis from any of the

both entrance , with a give priority to those coming from Bergamo, with a direct entry to

the left for those who arrive from the valleys and with the right of way for those who leave

the motorway tollbooth.

One-lane ramps have a width of 6.00 m and two-lane ramps are 10.50m.

Figure 4: Southwest Junction Overview View

22
4.4. Analysis of the Current Transport Offer

The purpose of this document is the improvement of the multi-level roundabout junction

located on the Bergamo intercity axis at the A4 motorway junction, which is the main

access node to the city.

In detail the following road directions converge in the under-analysis node:

From the south, access to the A4 motorway via the Bergamo motorway tollbooth;

In east-west crossing, sPexSS671 "Interurban Axis"; From the north, via Highway, the main

access route to the city center; to the north-west, the Paltriniano ring road, which also

serves as a link with the Seriana Valley (SPexSS671) and the Brembana Valley (SPexSS470).

Figure 5: Territorial Framing

In order to better frame the road reference scenario, the main road ways of the main road

network of the study area will be analyzed.

23
4.4.1. State Strada SS671

The 671 highway of Val Seriana is a separate road infrastructure with two lanes per

direction. Starting from the municipality of Treviolo then at the intersection with the

former highway 470 direction of Val Brembana and up to Seriate, in Cassinone. Within the

study area, the road axis is part of the Bergamo intercity axis. All major roads leading to

the city and the junction for Orio al Serio airport are connected with junctions.

Figure 6: State Road 671- between junction A4 and SS42

4.4.2. Strada Provinciale SP EX SS 470

The SP ex SS470 in the section being analyzed is a separate road infrastructure with two

lanes per direction of travel. the section through the village of Bergamo is characterized by

24
intersections at staggered levels, while near the Bergamo node there is a traffic light

intersection that causes quite consistent queuing’s in the peak time slots.

Figure 7: SP ex SS470 – north bound way with the A4 –northbound

4.4.3. The Highway

It is an urban road connecting the center of Bergamo and the A4 Motorway. In the vicinity

of the study area, there are separate carriageways with two lanes per direction of travel.

25
Figure 8: Section via Highways – northbound direction

4.4.4. Bergamo A4 Toll

The tollbooth A4 of Bergamo is characterized by 7 lanes inbound to the toll (of which 2

dedicated to Tele-pass customers), while on exit there are 11 lanes (of which 3 dedicated to

Tele-pass customers, 2 to pay by card, 5 to pay in cash and 1 for Tele-pass customers and

card payment).

The following image show the details of the lanes and their dislocation along the barrier of

the A4 toll in in Bergamo.

26
Figure 9: Bergamo's A4 Toll

4.5. Analysis of Current Transport Demand

In order to analyze, in detail, and forecast the impact on future decisions, it is necessary to

reconstruct the traffic flows currently circulating on the existing network, it means

estimate the current transport demand. In the case of this study, the data was available

from the automatic surveys carried out by the Province of Milan, the province of Bergamo,

the company ASPI, in addition to the database of traffic detections implemented by

investigations direct in the field.

In particular, the main sources and reference years of such data are:

• The Lombardy Region's OD matrix (2014);

27
• The databases of large-area traffic surveys conducted directly in the field (2014 –

2016);

• traffic surveys from third parties such as, Milan Province, Bergamo Province and

ASPI (2014 – 2018);

• Traffic surveys carried out directly within the study in 2016;

• Traffic surveys carried out directly within the study in March 2019.

4.5.1. Bergamo A4 Casello Data

Autostrade per l’italia has provided aggregated data on the tollbooth of the A4 in

Bergamo for the last decade (divided by entrance and exit and by vehicle class) and the

hourly data in and out of the tollbooth for the month of October 2018.

The following graphs show the trend of flows detected on the tollbooth over the last

decade.

Figure 10: Annual data – Bergamo's A4 tollbooth

28
Figure 11: Average Annual Daily Data – Bergamo's A4 Tollbooth

The peak of the tollbooth's operation is found in the morning peak time slot with about

3,200 outgoing vehicles and 2,300 entering the toll.

4.5.2. Demand 2016

In 2016, the O/D matrix was obtained as result of a traffic investigation campaign carried

out by Tandem in 2013, from 1 to 7 June.

Automatic surveys were performed using radar sensors, pneumatic tubes and inductive

plates (rectangular sections); In addition, data relating to the Bergamo tollbooth (circular

sections) were obtained at Autostrada for Italy.

29
The tables below show the node origin destination matrix 2016, for each means (having

considered car, moto, light, heavy), and for the peak hour both the morning as the night.

which correspond to the zones indicated in the next figure.

30
Table 1: 2016 OD matrices for each means at morning peak hour

31
Table 2: 2016 OD matrices for each means at night peak hour

32
The image below shows the sections monitored on 2016 at the intersection.

Figure 12: Sections monitored year 2016

The image below shows the source and destination zones of the intersection, which

correspond to the zones indicated in the arrays below.

33
Figure 13: OD locations

As it can be seen in both scenarios the network is having a highly demand of vehicles

during the peak hour, with more than 12,000 vehicles. It can also be appreciated it that

behavior of the demand is not changing dramatically between the morning and the night

peak hour.

34
4.5.3. Demand 2019

In order to obtain a precise forecast of the future scenarios, it is important to have

knowledge pf current flows affecting this intersection at 2019. The counts were performed

with cameras of the type Miovision and/or action cameras and Radar systems.

The following image shows the location of the sections being monitored.

Figure 14: Localizing Automatic Survey Stations

35
4.5.4. Traffic Summary

The survey campaign carried out in March 2019 revealed an overall load of traffic flows in

transit on the node approximately of 13,750 vehicles/h in the morning rush hour. In the

evening rush hour, the vehicle load it was also high with approximately of 13,000 vehicles.

Compared to the similar survey campaign carried out in 2016, there was an increase of

13.5%. The following images show the inbound traffic flows to the node at morning rush

hour and the comparison with the survey carried out in 2016.

Figure 15: Traffic Surveys 2019 - HPM

36
Figure 16: Comparison with Survey Campaign 2016 - HPM

37
5. SOLUTIONS AND IMPROVMENTS OF THE

CONFLICT AREAS

5.1. Analysis of the Current State

In the seek to analyze our current state, it has been necessary to enter in detailed level, so

each of the branches was rigorously analyzed in order to determine the total number of

crossings, or points of conflict, so then could be categorized by their level of affectation

and thus be able to have a cleaner perspective of what should be done or proposed in

initial instances for the improvement of the node and its service levels.

Figure 17: Conflict analysis of the current state

38
A.I. SP671 DA LECCO CASELLO A4 A.I. SP671 DA LAGO ISEO SP 470 VIA AUTOSTRADA
RAMO A RAMO B RAMO C RAMO D RAMO E

MANOVRA 1

MANOVRA 2

MANOVRA 3

MANOVRA 4

MANOVRA 1

MANOVRA 2

MANOVRA 3

MANOVRA 4

MANOVRA 1

MANOVRA 2

MANOVRA 3

MANOVRA 4

MANOVRA 1

MANOVRA 2

MANOVRA 3

MANOVRA 4

MANOVRA 1

MANOVRA 2

MANOVRA 3

MANOVRA 4
MANOVRA 1 1 1 1 1 1 1
LECCO RAMO
A.I. SP671 DA

MANOVRA 2 1

1 2 1 2 1 2 3 1 1 2 1 2 2
A

MANOVRA 3

MANOVRA 4 2 2 1 2 1 3 1 2 1 3 2 2

MANOVRA 1 1 1 1 1 1
RAMO B
CASELLO

MANOVRA 2 1 1 1 1 1 1 1 1 1
A4

MANOVRA 3 1 1 2 2 1 1 1 2

MANOVRA 4 2 1 2 1 1 2 2 3
ISEO RAMO C

MANOVRA 1 1 1 1 1
A.I. SP671 DA LAGO

MANOVRA 2 1 1 1 1

MANOVRA 3 1 1 2 2 3

MANOVRA 4 1 2 2 1 2 3

MANOVRA 1 1 1 1

MANOVRA 2 1 1
RAMO
SP
470

1 2 2
D

MANOVRA 3

MANOVRA 4 2 1 2

MANOVRA 1 1 1 1
VIA AUTOSTRADA

1 1
RAMO E

MANOVRA 2

MANOVRA 3 1

MANOVRA 4

LEGENDA
PUNTI DI CONVERGENZA
PUNTI DI DIVERGENZA NUMERO CONFLITTI
PUNTI DI INTERSECAZIONE
PUNTI DI CONVERGENZA + DIVERGENZA
138
PUNTI DI CONVERGENZA + DIVERGENZA + ATTRAVERSAMENTO

Figure 18:Interference Matrix – Analysis of individual traffic conflicts

As it can be seen from the interference matrix, a total of 138 points of conflict were

identified, some tolerable others to be removed, regardless of the assessment of traffic

volumes.

39
In particular, the most serious situations were found on the paths of the following

branches:

- Branch A (Interurban Axis from the west) maneuver 3 (direction Bergamo) and

maneuver 4 (direction Lecco - residential area Canovine) due to the fact that they must

cross the inbound flows to the tollbooth coming from all directions and enter in the flow of

cars coming out of the tollbooth.

- Branch B (Exit from the Toll) maneuver 2 (direction Valli), maneuver 3 (direction

Bergamo) and maneuver 4 (direction Lecco - residential area Canovine) because they are

crossing the flows coming from the west on the roundabout that are coming the

Interurban Axis eastbound access.

- Branch C (Paltrinian Circular – Ex SS470) maneuver 3 (tollbooth direction), maneuver 4

(Orio direction) due that they are crossing the flows that are coming from the Interurban

Axis, Bergamo and those that are leaving the tollbooth.

Further critical elements are the interchange zones that often have completely inadequate

lengths. The most dangerous situation is the entry from Orio of the Interurban Axis, where

the exchange zone has a length of only 30 m. The ramp enters are almost parallel to the

roundabout traffic with a stop, with serious visibility problems. The absence of a priority

for those coming from the tollbooth means that the speed of the vehicles at this point is

already sustained. The inflow is also crossed by those who want to climb towards the

Valleys, causing dangerous situations and severe slowdowns.

40
The situation is also the fact of the queuing’s that are formed on the Interurban Axis

heading Lecco, creating areas at risk even outgoing for those who enter at the last

moment.

Another very dangerous area is the one to the southwest exiting the incoming ramp from

the Ex SS470 to the tollbooth. The interchange zone has a limited length of about 60 m,

there is the presence of an underpass that prevents users from seeing the nearby satin

crossing with stop.

5.2. Analysis of Project Alternatives

Several design solutions were considered during the design process to increase optimally

the functionality of the node in terms of traffic and safety. In the following paragraphs it

will be described all the alternatives analyzed.

5.2.1. Project Alternative No. 1

The first solution analyzed involves a series of works that improve the functionality of the

node, among them are:

• Elimination of roundabout circulation between the southwest quadrant and the

northeast quadrant;

• Creation of direct ramps for the flows out of the tollbooth to the center of Bergamo

with a new underpass and for the Ex SS470 heading to the Valleys;
41
Figure 19: Functional Diagram Solution 1

This proposal allows for a direct connection, taking advantage of the existing roundabout

for those who decides to go to the motorway toll booth from the airport. For the same’s

that are coming from the airport have the free maneuvers on the right both to reach the Ex

SS470 heading to the Valleys, and to go on via Highway heading downtown to Bergamo.

Another important intervention is the enhancement of the entry on the Interurban Axis for

those who come from the tollbooth and head to the Orio junction. The north and south

roadways of the acceleration and deceleration lanes are expected to be connected,

effectively eliminating the need to exchange with the Interurban Axis for directions to and

from the airport.

Finally, it was possible to eliminate the crossing flow of the lanes from the entrance of the

tollbooth by creating a new ramp that allows to connect the Interurban Axis, (Lecco origin)

to the Center of Bergamo, taking advantage in part of the junction ramp with the former

SS470 in the underpass. All this intervention greatly reduces the conflict points between
42
node maneuvers by dropping them from 138 of the fact state to only 53 in the project

solution. Having then eliminated all crossing conflicts the level of safety of all maneuvers

is expected to have a greatly increased.


A.I. SP671 DA LECCO CASELLO A4 A.I. SP671 DA LAGO ISEO SP 470 VIA AUTOSTRADA
RAMO A RAMO B RAMO C RAMO D RAMO E

MANOVRA 1

MANOVRA 2

MANOVRA 3

MANOVRA 4

MANOVRA 1

MANOVRA 2

MANOVRA 3

MANOVRA 4

MANOVRA 1

MANOVRA 2

MANOVRA 3

MANOVRA 4

MANOVRA 1

MANOVRA 2

MANOVRA 3

MANOVRA 4

MANOVRA 1

MANOVRA 2

MANOVRA 3

MANOVRA 4
MANOVRA 1 1 1 S S
LECCO RAMO
A.I. SP671 DA

MANOVRA 2 1 S 1 S

S 1 1 S
A

MANOVRA 3

MANOVRA 4 S S S S S S S S S S S S S S S S

MANOVRA 1 S
RAMO B

1 1 S
CASELLO

MANOVRA 2
A4

MANOVRA 3 1 1 S

MANOVRA 4 2 1 1 2 2 S
ISEO RAMO C

MANOVRA 1 1 1 1 S
A.I. SP671 DA LAGO

MANOVRA 2 1 1 1 S

MANOVRA 3 1 1 2 2 S

MANOVRA 4 1 2 2 1 2 S

MANOVRA 1 1 1 1 S

MANOVRA 2 1 1 S
SP 470
RAMO

S MANOVRA SOPPRESSA
MANOVRA 3 1 1 2 S
D

MANOVRA 4 2 1 S

MANOVRA 1 1 1 S
VIA AUTOSTRADA

MANOVRA 2 1 S
RAMO E

MANOVRA 3 S

MANOVRA 4

LEGENDA
PUNTI DI CONVERGENZA
PUNTI DI DIVERGENZA NUMERO CONFLITTI
PUNTI DI INTERSECAZIONE
PUNTI DI CONVERGENZA + DIVERGENZA
53
PUNTI DI CONVERGENZA + DIVERGENZA + ATTRAVERSAMENTO

Figure 20: Interference Matrix – Analysis of individual traffic conflicts

The weak point of this solution is the impossibility of guaranteeing the maneuver that

allows those from Bergamo to reach the Ex SS470. This route represents about 3% of the

node's overall road load and must be resolved by taking advantage of local traffic, which

at present already appears to have poor levels of service. However, there is an increased

capacity to attract traffic from the node, which brings with it a relief of the urban net

capable of partially mitigating the lack of a maneuver.

43
5.2.2. Project Alternative No. 2

The second solution analyzed involves a series of works that improve the functionality of

the node, among them:

• Elimination of roundabout circulation in the southeast quadrant;

• Creation of direct ramp for the output of the flow coming from the tollbooth for the

Ex SS470 heading towards the valleys;

• Direct ramp creation for the former SS470 direction the Valleys which collects the

other maneuvers

Figure 21: Functional diagram solution 2

The solution involves the construction of a ramp in the south-east quadrant that

undergoes the other ramps with a three-branch intersection, with the branch coming out

of the tollbooth that leads to reach the center of Bergamo on the countryside floor and

with the ramps continuing to the east that continue to the east that are in high detect.

44
The slopes of the ramps in this area are particularly high. The interchange ramps remain

in the northeast, northwest and southwest quadrants. In this solution as well, the intercity

Axis upgrade between the motorway node and the Orio junction is planned, which is

considered essential to ensure an improvement in the levels of exchange between the two

infrastructures.

.
A.I. SP671 DA LECCO CASELLO A4 A.I. SP671 DA LAGO ISEO SP 470 VIA AUTOSTRADA
RAMO A RAMO B RAMO C RAMO D RAMO E
MANOVRA 1

MANOVRA 2

MANOVRA 3

MANOVRA 4

MANOVRA 1

MANOVRA 2

MANOVRA 3

MANOVRA 4

MANOVRA 1

MANOVRA 2

MANOVRA 3

MANOVRA 4

MANOVRA 1

MANOVRA 2

MANOVRA 3

MANOVRA 4

MANOVRA 1

MANOVRA 2

MANOVRA 3

MANOVRA 4
MANOVRA 1 1 1 S
LECCO RAMO
A.I. SP671 DA

MANOVRA 2 1 S 1

S 1 1
A

MANOVRA 3

MANOVRA 4 S S S S S S S S S S S S S S S S

MANOVRA 1 1 1 1
RAMO B

1 1
CASELLO

MANOVRA 2
A4

MANOVRA 3 1 1 2 2 1

MANOVRA 4 2 1 2 1 2 2 2
ISEO RAMO C

MANOVRA 1 1 1 1 1
A.I. SP671 DA LAGO

MANOVRA 2 1 1 1

MANOVRA 3 1 1 2 2 2

MANOVRA 4 1 2 2 1 2 2

MANOVRA 1 1 1 1

1 1
SP 470

MANOVRA 2
RAMO

S MANOVRA SOPPRESSA
1 1 2 2
D

MANOVRA 3

MANOVRA 4 2 1 2

MANOVRA 1 1 1 1
VIA AUTOSTRADA

1 1
RAMO E

MANOVRA 2

MANOVRA 3 1

MANOVRA 4

LEGENDA
PUNTI DI CONVERGENZA
PUNTI DI DIVERGENZA NUMERO CONFLITTI
PUNTI DI INTERSECAZIONE
PUNTI DI CONVERGENZA + DIVERGENZA
77
PUNTI DI CONVERGENZA + DIVERGENZA + ATTRAVERSAMENTO

Figure 22: Interference Matrix – Analysis of individual traffic conflicts

Solution No.2 ensures all maneuvers ensuring full functionality of the node. It is no longer

possible to make the return between the Intercity Axis and the residential area of

Canovine, a maneuver that can be safely solved by exiting earlier and taking advantage of
45
the local roadway. The diverted flow is a few dozen vehicles, which in fact occupy the

entire roundabout being in fact a backwards maneuver.

5.2.3. Project Alternative 3

The third solution analyzed is in fact the most articulate solution of all and was designed

not only to solve the problems of the node but also to improve the local roadway around

the junction. The main interventions that improve the functionality of the node are:

• Elimination of roundabout circulation between the southwest quadrant and the

northeast quadrant;

• Creation of direct ramps for the flows out of the tollbooth to the center of Bergamo

with a new underpass and for the Ex SS470 heading to the Valleys;

• Direct ramp creation for the former SS470 direction the Valleys which collects the

other maneuvers

• Optimal separation, in the north west and southwest quadrants, between direct

tollbooth flows and direct flows to the former SS470 and the Interurban Axis

heading airport

46
Figure 23: Functional Diagram Solution 3

In fact, only the swap zone in the northwest quadrant remains, in the other quadrants the

flows are already optimized for the direction of maneuvers. In this solution too, the

intercity Axis upgrade between the motorway node and the Orio junction is planned,

which is considered essential to ensure an improvement in the levels of exchange between

the two infrastructures.

47
A.I. SP671 DA LECCO CASELLO A4 A.I. SP671 DA LAGO ISEO SP 470 VIA AUTOSTRADA
RAMO A RAMO B RAMO C RAMO D RAMO E

MANOVRA 1

MANOVRA 2

MANOVRA 3

MANOVRA 4

MANOVRA 1

MANOVRA 2

MANOVRA 3

MANOVRA 4

MANOVRA 1

MANOVRA 2

MANOVRA 3

MANOVRA 4

MANOVRA 1

MANOVRA 2

MANOVRA 3

MANOVRA 4

MANOVRA 1

MANOVRA 2

MANOVRA 3

MANOVRA 4
MANOVRA 1 1 1 S

LECCO RAMO
A.I. SP671 DA MANOVRA 2 1 S 1

A MANOVRA 3 S

MANOVRA 4 S S S S S S S S S S S S S S S S

MANOVRA 1 1 1 1
RAMO B

1 1
CASELLO

MANOVRA 2
A4

MANOVRA 3 1 1 1

MANOVRA 4 2 1 2 1 2
ISEO RAMO C

MANOVRA 1 1 1 1 1
A.I. SP671 DA LAGO

MANOVRA 2 1 1 1

MANOVRA 3 1 1 2

MANOVRA 4 1 2 2 1

MANOVRA 1 1 1 1

MANOVRA 2 1 1
SP 470
RAMO

S MANOVRA SOPPRESSA
MANOVRA 3 1 1
D

MANOVRA 4 2

MANOVRA 1 1
VIA AUTOSTRADA
RAMO E

MANOVRA 2

MANOVRA 3 1

MANOVRA 4

LEGENDA
PUNTI DI CONVERGENZA
PUNTI DI DIVERGENZA NUMERO CONFLITTI
PUNTI DI INTERSECAZIONE
PUNTI DI CONVERGENZA + DIVERGENZA
48
PUNTI DI CONVERGENZA + DIVERGENZA + ATTRAVERSAMENTO

Figure 24: Interference Matrix – Analysis of individual traffic conflicts

A further intervention provided by Solution 3 is the direct entry on the Interurban Axis

towards Lecco, effectively separating the local traffic from the passing traffic. In the state

of fact, those who want to access the Interurban Axis must occupy the junction on Via S.

Bernardino and continue straight. The junction has serious safety problems and over the

years have caused often serious safety problems even the deaths of those involved.

48
The weak point of this solution, as we will see later is the cost of it. Solution 3 ensures all

maneuvers ensuring full functionality of the node, except for the back turn between the

Interurban Axis and the residential area of Canovine.

5.2.4. Project Alternative 4

The fourth solution analyzed is in fact an economic optimization of the previous solution,

from which some maneuvers were eliminated that could be done equally and that in the

face of significant costs would not have brought a high benefit. The main interventions

that improve the functionality of the node are:

• Elimination of roundabout circulation in the southeast quadrant;

• Direct ramp creation connecting the center of Bergamo to the Interurban Axis heading

for Orio;

• Creation of direct ramp for the output of the flow coming from the tollbooth for the Ex

SS470 heading towards the valleys;

In this solution, again for economic reasons of overall cost of the work and of the cost-to-

cost relationship, it was decided to limit the upgrade of the Interurban Axis between the

motorway node and the Orio junction, but only in the area of entry of the ramp coming

from the junction towards Orio.

49
Figure 25: Functional Diagram Solution 4

All of the above, it has allowed to significantly reduce the points of conflict between the

maneuvers, making them from 138 of the state of fact to only 51 in the project solution.

Again, all traversal conflicts have been eliminated, increasing the security level of the

node.

The solution fails to guarantee all the maneuvers as it seems impossible for those coming

from Bergamo to reach the Ex SS470. This route represents about 1% of the node's total

road load and must be resolved by taking advantage of local traffic. However, there is an

increased capacity to attract traffic from the node.

50
A.I. SP671 DA LECCO CASELLO A4 A.I. SP671 DA LAGO ISEO SP 470 VIA AUTOSTRADA
RAMO A RAMO B RAMO C RAMO D RAMO E

MANOVRA 1

MANOVRA 2

MANOVRA 3

MANOVRA 4

MANOVRA 1

MANOVRA 2

MANOVRA 3

MANOVRA 4

MANOVRA 1

MANOVRA 2

MANOVRA 3

MANOVRA 4

MANOVRA 1

MANOVRA 2

MANOVRA 3

MANOVRA 4

MANOVRA 1

MANOVRA 2

MANOVRA 3

MANOVRA 4
MANOVRA 1 1 1 S S

LECCO RAMO
A.I. SP671 DA
MANOVRA 2 1 S 1 S

S S
A
MANOVRA 3

MANOVRA 4 S S S S S S S S S S S S S S S S

MANOVRA 1 1 1 1 S
RAMO B

1 1 S
CASELLO

MANOVRA 2
A4

MANOVRA 3 1 1 2 2 S

MANOVRA 4 2 1 2 1 2 S
ISEO RAMO C

MANOVRA 1 1 1 1 S
A.I. SP671 DA LAGO

MANOVRA 2 1 1 S

MANOVRA 3 1 1 2 S

MANOVRA 4 1 2 2 1 S

MANOVRA 1 1 1 1 S

MANOVRA 2 1 1 S
SP 470
RAMO

S MANOVRA SOPPRESSA
1 1 S
D

MANOVRA 3

MANOVRA 4 2 1 S

MANOVRA 1 1 1 S
VIA AUTOSTRADA

MANOVRA 2 1 S
RAMO E

MANOVRA 3 S

MANOVRA 4

LEGENDA
PUNTI DI CONVERGENZA
PUNTI DI DIVERGENZA NUMERO CONFLITTI
PUNTI DI INTERSECAZIONE
PUNTI DI CONVERGENZA + DIVERGENZA
51
PUNTI DI CONVERGENZA + DIVERGENZA + ATTRAVERSAMENTO

Figure 26: Interference Matrix – Analysis of individual traffic conflicts

51
5.3. Level of Services Analysis of The Conflict Zones

In order to improve the level of service and delays in the Bergamo’s node, in this chapter

all relevant conflict areas such as entry ramps, exits, and exchanges will be analyzed. so

that the current state of the work once analyzed will serve as a reference scenario and all

other scenarios will be analyzed with respect to it.

So the process it will start with the study of the current state, by making a geometric check

of the lengths of the different conflict zones and their corresponded flows to which they

are exposed. To do so, it will be followed several processes related to obtaining the level of

service in conflict zones as it is indicated in the high capacity manual 2000.

Thus, once all the service levels of the conflicts of the current state have been calculated,

the calculations will continue for all the conflict zones of the different solutions already

presented previously. considering that many of these conflicts will have disappeared for

reasons of the new geometric layout, and that the traffic flows in some cases due to

changes in the model will change due to the new conditions of the solutions.

5.3.1. Matrix OD Update

With the purpose of initiating the pertinent verifications for each conflict zone, the first

thing that is must be obtained is an update origin destination matrix, due to the fact that

the destination origin matrix is the one that will be used to express the actual flows of the

current demand for each conflict segment. The OD matrix must comply with the following

52
characteristics: it must be reliable based on traffic counts and studies, there must be at

least 2 different OD matrices, one for heavy vehicles and one for light vehicles, fulfilling

the condition of being the OD matrix corresponding peak hour traffic and be updated with

the current demand (2019).

Once the requirements of the OD matrix have been defined, the calculations with the OD

input matrix of the year 2016 will begin. The current matrix is a matrix which is composed

of the sum of 4 matrices (3 of light transport 1 of heavy vehicles), the counts have been

taken in the morning rush hour (8:00 - 9:00) of the year 2016. in which 12109 vehicles / h

were registered.

Although the matrix OD 2019 is not available for the same situation, there is the total

growth of demand, and the counts of the new inflows and flows of the node. which allows

us to start from the assumption that the demand for each route has grown proportionally

with the total demand of the node working with the 2019 matrix.

MATINA A B C D E F TOT
A 0 109 103 50 1630 471 2363
B 131 0 231 83 1078 592 2115
C 134 206 0 88 0 685 1113
D 0 835 0 0 0 0 835
E 1670 835 89 42 0 342 2978
F 688 922 672 429 0 0 2711
TOT 12115

Figure 27: 2016 OD Matrix

53
MATINA A B C D E F TOT
A 0 104 153 48 1892 400 2597
B 155 0 273 97 1293 681 2499
C 171 261 0 137 0 851 1420
D 0 1567 0 0 0 0 1567
E 1840 0 370 57 0 367 2634
F 734 880 908 514 0 0 3036
Total 2900 2812 1704 853 3185 2299 13753

Figure 28: Update 2019 OD matrix

5.3.2. Current State

In the current state of the project as it was described previously, there are 3 sensitive main

conflict areas, which are the interchange areas, these areas in general plays a very

important role in assessing the capacity of the entire node. Due to this fact the main speed

reductions are generated, there is an increase in the density along the length of this area.

but not only the interchange zones will be analyzed, but also an entry ramp and 3 exits,

which also have a component in the overall performance of the node.

Basically, the parameter with which the service level will be defined will be the length of

the different areas analyzed, whether in the interchange, entry, or exits zones. Also,

among the components that are considered in the calculations are: current flows, speeds,

and recorded densities.

5.3.2.1. Interchange Ramps

The 3 exchange ramps that will be analyzed and evaluated with respect to HCM 2000 are

defined below.

54
1

3
2

Figure 29: interchange Graphic locations

5.3.2.1.1. Interchange Ramp 1

In the analysis and verification of the first exchange ramp, a detailed description of the

process will be made, with their respective calculation memories, for the rest will be given

the results explicitly.

The first thing that it must be done is to determine the Vp passenger – car equivalent flow

rate (pc/h/ln) for all values of the update OD matrix 2019.

Equation 1: 15 – min passenger – car equivalent flow rate

55
This process is done by using the PHF (peak – hour factor) which represents the variation

in traffic flow within an hour, bases on the fact that flow rates in the peak 15-min period

within an hour are not sustained throughout the entire hour. Unfortunately, this peak – 15

min flow data is not available. So, the calculations will be made with the actual counted

values, using a factor already studied that normally corresponds in these cases of 0.95.

For the heavy – vehicle adjustment factor the HCM gives the following equations.

Equation 2: heavy vehicle adjustment factor

In this case the proportion of trucks/ buses are gathered in the same category as heavy

vehicles.

The respective values of ET and ER had been taken from the following table that gives an

specific value for each type of terrain.

56
Table 3: Passenger- Car equivalents on extended Freeway

In this case the type of terrain is always going to be level. So the value of 1.5 it was always

used.

For the proportion of heavy vehicles the calculation was done by dividing the number of

trips made by heavy vehcle for each branch by the sum of all trips made by every means

for each branch respectively. The results are showed in the following table.

Table 4: PROPORTION OF TRUCKS/BUSES IN THE TRAFFIC

BRANCH PT
A 0.1112992
B 0.1096927
C 0.1257862
D 0.1293413
E 0.0826058
F 0.0627075

Therefore, everything is given to calculate the heavy – vehicle adjustment factor for each

branch. The results are showed in the following table.

57
Table 5: Heavy - vehicle adjustment factor

BRANCH FHV
A 0.947284025
B 0.948005379
C 0.940828402
D 0.939257593
E 0.960335376
F 0.969599428

In this case the value of N is not going to be considered due to the fact that the value

required is the one that give equivalent flow rate of the complete section, and not per line.

Then in the coming calculations will be done in detail per each line when it is required.

The adjustment factor fp (driver population factor) range from 0.85 to 1.0. In general, de

value of 1.0 is used to reflect commuter traffic. Use of a lower value reflects more

recreational traffic.

Once again having calculated all necessary components to obtain the value of passenger

car equivalent. it will be necessary to calculate it for each of the cells of OD matrix

previously updated. The results are showed in the following figure.

A B C D E F
A 0 116 170 53 2102 444
B 172 0 303 0 1543 756
C 191 292 0 153 0 952
D 0 1121 0 0 0 0
E 2079 621 406 0 0 402
F 797 955 986 558 0 0

Figure 30: Passenger car equivalent flow rate veh/h 8 - 9 2019

58
This is the definitive matrix, with which all the calculations corresponding to the present

and future conflicts will be evaluated, which meets 3 criteria: it is updated to 2019, it

reflects the state of the peak hour, and manages the equivalent flows based on several

criteria of calculation.

then for the calculation of the service levels, all the circulation variables will be defined

with their respective symbol.

Table 6: symbols and definitions for interchange zones


Symbol Definition
L Total length of the interchange segment
N Total number of lanes in the interchange segment
Ns Number of lanes required for the unrestricted regime interchange
Ns max Maximum number of lanes that can be used for interchange according to the configuration
Q Total peak intensity in the interchange section (veh / h)
Q01 Maximum intensity of vehicles that do not interchange (veh / h)
Q02 Minimum intensity of vehicles that do not interchange (veh / h)
QS1 Maximum intensity of the vehicles that interchange (veh / h)
QS2 Minimum intensity of the vehicles that interchange (veh / h)
QS Total interchange intensity QS1 + QS2
QNS Total intensity of non interchange Q01 + Q02
VR Intensity ratio QS / Q
VS Average speed of the vehicles that interchange (km / h)
Vns Average speed of vehicles that do not interchange (km / h)
VFL Average speed of all vehicles that interchange (km / h)
D Density of all vehicles in the section
Ws Interchange intensity facotor
Wns NO interchange intensity factor

The total value of flows are obtained by summing all the flows that during their travel

passed through this section.

• the value of Q is equal to CB + EC + FC + FD + AB + AC + AD +AF

Q = 3980 veh/h

59
• The value of Qs1 is equal to CB + FB

Qs1 = 1247 veh/h

• The value of Qs2 is equal to AC + AD + AF

Qs2 = 668 veh/h

• The value of Q01 is equal to EC + FC + FD

Q01 = 1949 veh/h

• The value of QO2 is equal to AB

Q02 = 116 veh/h

• The value of Qs is equal to Qs1 + Qs2

Qs = 1915 veh/h

• The value of Qns is equal to Q01 + Q02

Qns = 2065 veh/h

• The value of VR is equal to Q/Qs

VR = 0.48119

• The value of VFL its assumed 45 km/h

• The total number of lanes in the interchange segment N is 3.

The maximum number of lanes that can be used for interchange according to the

configuration Ns max is equal to 1.4 according to the different types.

60
Figure 31: Ns configuration

Now Ns will be calculated, to make a verification. If it turns out that Ns < Nsmax. means

it has a "balanced" functioning, in the sense that the speeds of the flows in interchange and

not, are comparable, and the operation is said to be "not constrain". When instead Ns>

Nsmax there is less space than would be necessary for the interchange and the flows

involved experience less quality circulation conditions, with average speed lower than the

flows that do not exchange, and the operation is said to be "constrain".

For the configuration A; NS will be equal to.

61
• Where the total length of the interchange segmente is equal to 65 m

The medium speed of flows that interchange and those who doesn’t must be obtained

The intesity factors of interchange can be calculated with the following formulas.

Equation 3: Intensity factors of interchange

And the constants can be found in the following table

62
Table 7: Constants for Ws and Wns Factors

Having everything to make the respective calculation for the intensity facor the results are

exposed.

• the value of Ws is equal to 0.377

• the value of Wns is equal to 0.10247

Hence everything is set it to calculate the values for Vs and Vns.

• The value of Vs is equal to 53.377

• the value of Vns is equal to 53.102

So finally the value of Ns could be calculated.

• the value of Ns is equal to 1.112

The condition Ns < Ns max is guaranteed, so there is no need to recalculate the constraint

conditions.

63
Once the average speeds of the flows that interchange and those who not are determined,

it is possible to calculate the average speed in the space of all the vehicles as a harmonic

weighted average of the interchange rates.

Equation 4: Average speed

The value of V is equal to 53.23 km/h

The average density is then calculated as

Equation 5: Average density

The value of density is equal to 24,921 Veh/(km*lane).

By comparing the average density with the values on the table, in the category multilane

roads , the service level is obtained.

64
Table 8: Level of service by density

The actual Level of service of the interchange ramp 1 that has total length of 67m is equal

to E wich belong to the category 5 according to the following table.

Table 9: Quality of the interchange flow

and if it is expected to change this current state of service for a more acceptable one such

as D or C, at least in terms of the length of the interchange zone, the length of the same

should be at least 165 m according to the following graph.

65
Figure 32: Flows Quality depending on the interchange length and flow

5.3.2.1.2 Interchange Ramp 2

For the calculation of the interchange ramp number 2 the same exactly same calculation

will be done, and only the results are going to be shown, as the whole proceed was

explained before.

• the value of Q is equal to FA +FB + FC+ FD + EC + ED + CA +CB +BA

Q = 3898 veh/h

• The value of Qs1 is equal to FC + FB +FD

Qs1 = 2499 veh/h

66
• The value of Qs2 is equal to CA + BA

Qs2 = 363 veh/h

• The value of Q01 is equal to FA

Q01 = 797 veh/h

• The value of QO2 is equal to EC + ED + CB

Q02 = 760 veh/h

• The value of Qs is equal to Qs1 + Qs2

Qs = 2863 veh/h

• The value of Qns is equal to Q01 + Q02

Qns = 1557 veh/h

• The value of VR is equal to Q/Qs

VR = 0.734

• The value of VFL its assumed 45 km/h

• The total number of lanes in the interchange segment N is 3

• the value of Ws is equal to 0.67

• the value of Wns is equal to 0.239

Hence everything is set it to calculate the values for Vs and Vns

• The value of Vs is equal to 53.67

67
• the value of Vns is equal to 53.23

So finally the value of Ns could be calculated

• the value of Ns is equal to 1.3

The condition Ns < Ns max is guaranteed, so there is no need to recalculate the constraint

conditions.

• The value of V is equal to 47.212 km/h

• The value of density is equal to 27,921 Veh/(km*lane)

Comparing the average density with the values on the table, in the category multilane

roads , the service level is obtained. The actual Level of service of the interchange ramp 2

that has total length of 46 m is equal to F wich belong to the category 5. and if it is

expected to change this current state of service for a more acceptable one such as D or C, at

least in terms of the length of the interchange zone, this length should be at least 150 m.

5.3.2.1.3 Interchange Ramp 3

For the calculation of the interchange ramp number 3 the same exactly same calculation

will be done, and only the results are going to be shown, as the whole proceed was

explained before.

• the value of Q is equal to AF + BA +BF +CF + CA + CB + EF + EC

Q = 3616 veh/h

68
• The value of Qs1 is equal to AF +BF +CF

Qs1 = 2149 veh/h

• The value of Qs2 is equal to EC

Qs2 = 406 veh/h

• The value of Q01 is equal to CA + CB + BA

Q01 = 655 veh/h

• The value of QO2 is equal to EF

Q02 = 402 veh/h

• The value of Qs is equal to Qs1 + Qs2

Qs = 2558veh/h

• The value of Qns is equal to Q01 + Q02

Qns = 1058 veh/h

• The value of VR is equal to Q/Qs

VR = 0.707

• The value of VFL its assumed 45 km/h

• The total number of lanes in the interchange segment N is 3

• the value of Ws is equal to 0.63079

• the value of Wns is equal to 0.21

69
Hence everything is set it to calculate the values for Vs and Vns

• The value of Vs is equal to 53.63

• the value of Vns is equal to 53.21

So finally the value of Ns could be calculated

• the value of Ns is equal to 1.26

The condition Ns < Ns max is guaranteed, so there is no need to recalculate the constraint

conditions.

• The value of V is equal to 53.5072 km/h

• The value of density is equal to 22,5269 Veh/(km*lane)

Comparing the average density with the values in the table, in the category multilane

roads , the service level is obtained. The actual Level of service of the interchange ramp 3

that has total length of 48 m is equal to D wich belong to the category 4. and if it is

expected to change this current state of service for a more acceptable one such as C, at

least in terms of the length of the interchange zone, this length should be at least 270 m.

5.3.2.2. Entry Ramps

In the analysis and verification of the entry ramps, a detailed description of the process

will be made, with their respective calculation memories, for the rest will be given the

results explicitly. Two entry ramps will be analyzed during all solutions as it is shown in

the next figure.

70
2

Figure 33: Entry ramps location

5.3.2.2.1 Entry Ramp 1

For the calculation of the service levels, all the circulation variables will be defined with

their respective symbol

Table 10: symbols and definitions for entries zones calculations

Symbol Definition
I12 Intensity on lanes 1 and 2 of the highway immediately upstream of the convergence zone
IA Intensity on the highway immediately upstream of the convergence zone
Pac Proportion of the intensity upstream that comes from lanes 1 and 2
IR Total intensity in the area
LA Actual length of acceleration lane

• The value of IA is equal to EA

IA = 1868 veh/h

71
• The value of Pac varies according to the number of lanes, as it is seen in the next

table
Table 11: The value of Pac for the entry’s calculations

Then the value of Pac = 1

• The value I12 is equal to IA * Pac

I12 = 1868 veh/h

The value of IR is equal to BA + CA + FA

IR = 1060 veh/h

• LA = 125m

• The level of service is determined by the density inside the influence area DR

Dr is given by the following expression.

Dr = 3.04 + 0.00456* IR + 0.0048* I12 * LA

Dr = 16.95

72
The corresponding level of service is D according to the following table

Table 12: Level of service by density

5.3.2.2.2 Entry Ramp 2

For the calculation of the entry ramp number 2 the same exactly same calculation will be

done, and only the results are going to be shown, as the whole proceed was explained

before.

• The value of IA is equal to AE

IA = 2102 veh/h

Then the value of Pac = 1

• The value I12 is equal to IA * Pac

I12 = 20102 veh/h

73
The value of IR is equal to BE

IR = 1543 veh/h

• LA = 113m

• The level of service is determined by the density inside the influence area DR

Dr is given by the following expression.

Dr = 3.04 + 0.00456* IR + 0.0048* I12 * LA

Dr = 19.087

The corresponding Level of service is D.

5.3.2.3. Exit Ramps.

In the analysis and verification of the entry ramps, a detailed description of the process

will be made, with their respective calculation memories, for the rest will be given the

results explicitly. Two entry ramps will be analyzed during all solutions as it is shown in

the next figure.

74
3

Figure 34: Exit ramps location

5.3.2.3.1 Exit Ramp 1

For the calculation of the service levels, all the circulation variables will be defined with

their respective symbol

Table 13: symbols and definitions for exit zones calculations

Symbol Definition
I12 Intensity on lanes 1 and 2 of the highway immediately upstream of the convergence zone
IA Intensity on the highway immediately upstream of the convergence zone
Pad Proportion of the intensity on the of the highway coming from lane 1 and 2
IR Total intensity in the area
LA Actual length of acceleration lane

• The value of IA is equal to EA

IA = 3596 veh/h

75
• The value of Pac varies according to the number of lanes, as it is seen in the next

table

Table 14: The value of Pac for the exit ramps

Then the value of Pac = 1

• The value I12 is equal to IA * Pac

I12 = 3596 veh / h

The value of IR is equal to EA

IR = 1008 veh / h

• LA = 35m

• The level of service is determined by the density inside the influence area DR

Dr is given by the following expression.

Dr = 3.402 + 0.00456* IR + 0.0048* I12 - 0.01278*LA

Dr = 21.06
76
The corresponding Level of service is D according to the table 12

5.3.2.3.2 Exit ramp 2

For the rest of the exit ramps calculation the exact same procedure will be done, and only

the results are going to be shown, as the whole proceed was explained before.

• The value of IA is equal to AB + AC + AD + AF + AE

IA = 2887 veh / h

Then the value of Pac = 1

• The value I12 is equal to IA * Pac

I12 = 2887 veh / h

The value of IR is equal to BE

IR = 896 veh / h

• LA = 114m

• Dr = 3.04 + 0.00456* IR + 0.0048* I12 * LA

Dr = 15.85

The corresponding Level of service is C.

5.3.2.3.3 Exit ramp 3

77
• The value of IA is equal to AB + AC + AD + AF + AE

IA = 2887 veh / h

Then the value of Pac = 1

• The value I12 is equal to IA * Pac

I12 = 2887 veh / h

The value of IR is equal to BE

IR = 896 veh / h

• LA = 114m

• Dr = 3.04 + 0.00456* IR + 0.0048* I12 * LA

Dr = 15.85

The corresponding Level of service is C.

5.3.3. Solution 1

5.3.3.1. Interchange Ramp

In the solution 1 all interchange ramps were eliminated

5.3.3.2. Entrie Ramps

The entrance ramps of this solution are exposed to the same level of traffic of the current

scenario and have the same geometry as well.

78
5.3.3.3. Exit Ramp.

5.3.3.3.1 Exit Ramp 1

The value of IA is equal to EA

IA = 2674 veh/h

The value of Pac varies according to the number of lanes, as it is seen in the next table

Then the value of Pac = 1

The value I12 is equal to IA * Pac

I12 = 2674 veh/h

The value of IR is equal to EA

IR = 500 veh/h

LA = 35m

Dr = 16.17

The corresponding Level of service is C.

5.3.3.3.2 Exit Ramp 2

• The value of IA is equal to AB + AC + AD + AF + AE

IA = 2363 veh / h

Then the value of Pac = 1

• The value I12 is equal to IA * Pac

79
I12 = 2363 veh / h

The value of IR is equal to BE

IR = 733 veh / h

• LA = 114m

• Dr = 13.07

The corresponding Level of service is C.

5.3.3.3.3 Exit Ramp 3

The exit ramp 3 of this solution are exposed to the same level of traffic of the current

scenario and have the same geometry as well.

5.3.4. Solution 2

5.3.4.1. Interchange Ramp

In the solution 2, all interchange ramps were eliminated

5.3.4.2. Entrie Ramps

The entrance ramps of this solution are exposed to the same level of traffic of the current

scenario and have the same geometry as well.

80
5.3.4.3. Exit Ramps.

The exit ramps of this solution are exposed to the same level of traffic of the first solution

and have the same geometry as well.

5.3.5. Solution 3

5.3.5.1. Interchange Ramps

In the solution 3, all interchange ramps were eliminated

5.3.5.2. Entrie Ramps

The entrance ramps of this solution are exposed to the same level of traffic of the current

scenario and have the same geometry as well.

5.3.5.3. Exit Ramps.

The exit ramps of this solution are exposed to the same level of traffic of the first solution

and have the same geometry as well.

5.3.6. Solution 4

5.3.6.1. Interchange Ramps

In the solution 4 all interchange ramps were eliminated

81
5.3.6.2. Entrie Ramps

The entrance ramps of this solution are exposed to the same level of traffic of the current

scenario and have the same geometry as well.

5.3.6.3. Exit Ramps

The exit ramps of this solution are exposed to the same level of traffic of the first solution

and have the same geometry as well.

82
6. TRAFFIC SIMULATION

In order to make a realistic and deep detailed analysis of the whole node and not only of

the particular conflict points; in such way that it could be possible to get strong and

consistent results to conclude and make a confrontation between different solutions and

the current state; VISSIM 11 software will be used in order to obtain realistic results by

building all the future and current state scenarios and run multiple simulations, under a

multiple demand requests for each scenario.

The following conditions for the models will be evaluated in order to perform an objective

analysis of the node improvement:

- For the current status and solutions 1,2,3,4 the demand conditions of 2016 will be

evaluated

- for the solution 1, 2, 3, 4 the projected demand of 2024 (corresponding to the year in

which the infrastructure work will be ready for the users) by using a growth rate of

1.5% in the vehicles flow.

- for the solution 1, 2, 3, 4 the projected demand of 2048 (corresponding to 30 years

average of the useful life of an infrastructure of this magnitude) by using a growth rate

of 1.5% in the vehicles flow.

In this subchapter, a detailed description of the entire simulation process will be made,

starting from the construction of the network, the parameter calibration process and the

flow calibration

83
6.1.1. Network Construction

For the construction of the supply network, the first thing that must be done it was to get a

satellite image from google maps with a precise scale, so it could be placed in the Vissim

background with the same realistic scale.

Once the picture is set it can be possible to start tracing the links and connectors in the

network, in which all features such as width of lane, number of lanes, link behavior type

must be compiled.

In this process in order to make a realistic and interactive simulation, it was decided to

create the network with the dimensions of height, (due to the fact that all the designs of

the current and future scenarios from the INGESCA company were available) which made

the process more detailed and extensive because each link had to be united with exact

precision.

Figure 35: Vissim network solution 4

84
6.2. Input Data

Once, the entire supply network is built, all the following input data will be inserted:

vehicle inputs, vehicle route choice, desired speed distribution of the network, proportion

of heavy vehicles per each vehicle input, desired speed segments, and stops segments.

Before describing the process, it should be clarified that the demand flows used to

calibrate the current model, were the flows corresponding to 2016, due to the fact that the

material supplied from the 2019 demand was very poor, instead the demand for 2016 had

all the data to be calibrated correctly

The demands of each of the scenarios are expressed through OD matrices, which fulfill not

only the function of expressing the current and future demand of each solution, but also of

showing the new state of the current maneuvers allowed by the solutions.

As there was no data with the new OD matrices, nor was the macro-modelling model

available; to obtain the results of the new flow distribution many assumptions must be

made for this analysis using google maps as a tool. In this analysis the most attractive

alternatives have been evaluated when the main option is not considered, and thus

distribute the flows in a proportionate way according to google travel times.

The demands of the current state and new solutions for 2016 in the morning peak hour are

shown in the following matrices OD.

85
A B C D E F TOT
A 0 109 103 50 1630 471 2363
B 131 0 231 0 1150 592 2104
C 134 206 0 88 0 685 1113
D 0 1170 0 0 0 0 1170
E 1670 500 89 42 0 342 2643
F 688 922 672 429 0 0 2711
Figure 36: 2016 OD matrix for the current scenario

A B C D E F TOT
A 0 109 103 50 1630 471 2363
B 131 0 231 0 1150 592 2104
C 134 0 0 88 0 685 907
D 0 1170 30 0 0 0 1200
E 1773 500 59 0 0 342 2674
F 688 922 672 429 0 0 2711
Figure 37: 2016 OD matrix for the first solution

A B C D E F TOT
A 0 109 103 50 1630 471 2363
B 131 0 231 0 1150 592 2104
C 134 206 0 88 0 685 1113
D 0 1170 30 0 0 0 1200
E 1670 500 59 0 0 342 2571
F 688 922 672 429 0 0 2711
Figure 38: 2016 OD matrix for the second solution

A B C D E F TOT
A 0 109 103 50 1630 471 2363
B 131 0 231 0 1150 592 2104
C 134 206 0 88 0 685 1113
D 0 1170 30 0 0 0 1200
E 1670 500 59 0 0 342 2571
F 688 922 672 429 0 0 2711
Figure 39: 2016 OD matrix for the third solution

86
A B C D E F TOT
A 0 109 103 50 1630 471 2363
B 131 0 231 0 1150 592 2104
C 134 0 0 88 0 685 907
D 0 1170 30 0 0 0 1200
E 1773 500 59 0 0 342 2674
F 688 922 672 429 0 0 2711
Figure 40: 2016 OD matrix for the fourth solution

The input of the vehicles is inserted by each one of the zones from A to F, in a flow of

vehicles / hour. This number of flows is the one that was counted on site without making

any conversion or using any factor since the program requests for each quantity of

vehicles the proportion of light and heavy vehicles.

Once the flows are inserted the software requests to insert the desired speed distribution

of the vehicles, which would be the speed in which all the flows would behave, the

hypothesis has been taken that all the vehicles within the node will have the same speed

which is the speed most commonly demanded by the current signaling equal to 50 km / h.

all those sections that have different speed limits will be manually adjusted in the software

through the desire speed decision tool.

in the same way and according to the current state signaling, the stops are marked. once

all the signals have been completed, the conflict zones will be identified one by one, and

87
the priority or non-priority of any of the 2 parts of the conflict will be determined in the

knowledge of the operation of the node.

In this way, it just left to assign the vehicle route for each input of the flow by inserting the

proportion of the flow that is distributed on each route. Once the vehicle route is assigned,

everything is ready to run the model and start with the calibration.

6.3. Calibration of the Model

It should be clarified that the entire process of the creation and calibration of the network

was done by using the student version of the Vissim software, which constrict the realism

of the simulation in many aspects

Once all the input data is inserted, the process of calibration of the current state of the

node referring to the year 2016 begins. And without making any modification, the first

simulations are made, in order to have a first perception of the operation of the model.

At first instance and without verifying any kind, several things were evidenced, such as

the large queues of vehicles in branch A, F and in the rest of the branches B,D,E,F not that

large, but in general all branches they showed a queue of an exaggerated and unreal

length and by effect the collapse of the roundabout.

After analyzing several simulations, it could be concluded without making a deep

verification into the traffic counts is that 2 problems had to be corrected.

88
1) The general behavior of all vehicles in the interchange zone was extremely peaceful,

so traffic in this area was highly turbulent. and after 5 minutes the length of the

queues were already considerable

One of the restrictions of the model being used through the student Vissim version is that

the software does not allow you to build a network that exceeds km^2 area. And having

this great length of queues, the vehicles began to enter the network while this was in a

queue state, and this was not realistic because the users normally take route decisions

before they have arrived to the queue.

The first problem it was corrected by doing 2 interventions. First, creating links where the

vehicles had to carry out the interchange zone, which allowed to have very small

connectors (large connectors make it difficult to change lanes). second by changing the

driving behavior parameters of the lane change category only in the links where the

interchange was taking place.

89
Figure 41: Driving behavior parameters

Then the second problem was corrected by creating new invisible links in random and

certainly different directions regarding the direction of the current state of the node. all

this in order that the links in which the formed queue were not large enough to affect the

route choice decision of the users in vehicles.

Once these errors had been corrected, the model will be run a number of times indefinitely

but enough to realize if the model starts to behave in a proper way as it should behave in

reality or in the other hand still somethings had to be corrected. In this case it was still left

to make some modifications on the conflict points priorities but this time without

following the real signaling but the real vehicle behavior.

90
At this point, the flows of the model will be compared, with the state of flows shown by

Google Maps at peak time. To get an idea of how real our model is.

Figure 42: Google traffic map at peak hour

Having done the comparison, satisfactory results were found. This gives place to a more

detailed calibration phase. Having the number of traffic counts in each of the exchange

areas, it will be considered to count from model the number of cars passing through the

section in a certain period of time in order to reach the same number as those counts that

were given as inputs.

To accurately calibrate these traffic counts, it was necessary to iterate again the values of

the lane change behavior of the links that were assigned to the interchange areas.
91
7. RESULTS

Thus, with a model that has already been calibrated, which reflects and gives confidence

in the current state of the node, the simulations for each solution with different demands

can be ran.

Due to the allowance of limited time with the official Vissim software license; for this

study the mainly results that there will be take into account are the general delays of the

node as well as of each route choice, their respective level of service and the lengths of the

queues. Although contamination data can be provided but for the purpose of this study it

will not be taken into account, since the analysis will be done only in terms of traffic and

level service at peak hour.

The first thing that must be done to analyze the models is to create a node over them. and

this node must comply with the characteristics that cover all the entrances and exits of the

node in order to register all movements.

Once the node has been created, interval times must be created in order to write a realistic

simulation. The first interval is to load the network with 40% of the demand for the peak

hour for 30 minutes. the second interval will be the interval of interest and in which all

studies and results will be based on this one-hour interval. The third interval is an interval

of 15 minutes to empty the network.

92
At this point you must configure the evaluation parameters of the node, in which you

must specify what you want to evaluate, the delays, links and the general node. This

evaluation is given for the time range between 1800 and 5400 seconds

Figure 43:Evaluation configuration

93
For the simulation certain parameters must also be regulated. such as the simulation time,

the number of simulations, the resolution of the simulation, the random seed and the

random seed increase.

The simulation time as it was describe already is 6300 second including the time to fill the

network, simulation, and emptying.

In these cases, to obtain a reliable result, and reduce the chances that an out of the

ordinary simulation delivers unreal results, a minimum of 10 simulations is made for each

solution with its respective demand, then for this ten results its easy to obtain the average

values and make the propper evaluation with them.

The random seed value initializes a random number generator. Two simulation runs using

the same network file and random start number look the same. If the random seed varies ,

the stochastic functions in Vissim are assigned a different value sequence and the traffic

flow changes.

The random seed increase is the difference between random seeds when you perform

multiple simulation runs. This number is irrelevant for stochastic distribution.

94
Figure 44: Simulation Parameters

After executing the simulations, the following results were ordered in OD matrices that

show the delay and the corresponding service level, for each solution, for each year.

The following table gives the corresponding value of the service level for both types of

intersections.

95
Table 15: Level of service according to the Vissim manual

7.1. 2016 Results

For the results in different scenarios with the 2016 demand, the following OD matrices are

illustrated, in terms of delay and service level

A B C D E F
A - 416.9 411.6 428.7 6.9 441.2
B 47.5 - 1.2 - 20.7 10.7
C 57.4 89.0 - 13.0 - 21.3
D - 0.9 - - - -
E 2.3 2.4 54.8 60.3 - 6.8
F 36.2 105.0 61.3 65.0 - -

96
Figure 45: Delay OD matrix for the current scenario

A B C D E F
A - F F F A F
B E - A - A B
C E F - B - C
D - A - - - -
E A A F F - A
F E F F F - -
Figure 46: LOS OD matrix for the current scenario 2016

the average delay per vehicle for the whole node configuration for the respective demand
is equal 35,6 s

A B C D E F
A - 2.6 2.8 6.1 2.7 5.8
B 3.0 - 3.1 - 33.9 2.3
C 5.2 - - 4.4 - 4.3
D - 2.2 1.4 - - -
E 2.5 2.9 2.6 - - 2.3
F 1.8 3.6 2.8 5.8 - -

Figure 47: delay OD matrix for solution 1 (2016)

A B C D E F
A - A A A A A
B A - A - D A
C A - - A - A
D - A A - - -
E A A A - - A
F A A A A - -
Figure 48: LOS OD matrix for solution 1 (2016)

the average delay per vehicle for the solution 1 configuration for the respective demand is
equal 5,9 s

97
A B C D E F
A - 6.8 5.2 12.1 2.3 8.9
B 2.9 - 1.2 - 47.9 2.4
C 8.1 9.6 - 8.6 - 7.3
D - 2.0 0.7 - - -
E 1.5 2.0 0.9 - - 1.5
F 1.4 3.3 3.1 7.5 - -

Figure 49: delay OD matrix for solution 2 (2016)

A B C D E F
A - A A B A A
B A - A - E A
C A A - A - A
D - A A - - -
E A A A - - A
F A A A A - -
Figure 50: LOS OD matrix for solution 2 (2016)

the average delay per vehicle for the solution 2 configuration for the respective demand is
equal 7,6
A B C D E F
A - 3.5 2.7 4.5 1.5 4.6
B 2.3 - 4.1 - 2.7 2.1
C 0.5 0.7 - 2.2 - 2.7
D - 2.0 1.2 - - -
E 2.2 2.6 2.1 - - 2.3
F 2.9 5.2 3.5 5.5 - -

Figure 51: delay OD matrix for solution 3 (2016)

A B C D E F
A - A A A A A
B A - A - A A
C A A - A - A
D - A A - - -
E A A A - - A
F A A A A - -

Figure 52: LOS OD matrix for solution 3 (2016)

98
the average delay per vehicle for the solution 3 configuration for the respective demand is
equal 2,7 s

A B C D E F
A - 1.7 4.7 6.7 2.1 6.3
B 2.9 - 1.7 - 58.9 1.8
C 0.8 - - 3.9 - 3.5
D - 2.0 2.4 - - -
E 2.5 2.7 1.7 - - 2.5
F 0.9 3.7 7.0 6.3 - -

Figure 53: delay OD matrix for solution 4 (2016)

A B C D E F
A - A A A A A
B A - A - F A
C A - - A - A
D - A A - - -
E A A A - - A
F A A A A - -
Figure 54: LOS OD matrix for solution 4 (2016)

the average delay per vehicle for the solution 4 configuration for the respective demand is

equal 8,26 s

99
7.2. 2024 Results
For the results in different scenarios with the 2024 demand, the following OD matrices are

illustrated, in terms of delay and service level

A B C D E F
A - 3.5 3.8 9.5 3.5 8.3
B 24.9 - 14.9 - 141.5 25.0
C 9.6 - - 8.2 - 8.5
D - 3.1 1.3 - - -
E 4.1 4.8 3.9 - - 3.7
F 2.8 5.9 4.4 8.8 - -

Figure 55: delay OD matrix for solution 1 (2024)

A B C D E F
A - A A A A A
B D - C - F C
C B - - A - A
D - A A - - -
E A A A - - A
F A A A A - -
Figure 56: LOS OD matrix for solution 1 (2024)

the average delay per vehicle for the solution 1 configuration for the respective demand is

equal 17,93 s

A B C D E F
A - 4.2 5.1 11.1 2.2 12.0
B 28.2 - 15.2 - 154.2 26.0
C 11.4 12.9 - 13.2 - 14.2
D - 2.3 0.5 - - -
E 2.3 2.6 2.2 - - 2.1
F 1.2 4.4 4.8 10.5 - -

Figure 57: delay OD matrix for solution 2 (2024)

100
A B C D E F
A - A A B A B
B D - C - F D
C B B - B - B
D - A A - - -
E A A A - - A
F A A A B - -
Figure 58: LOS OD matrix for solution 2 (2024)

the average delay per vehicle for the solution 2 configuration for the respective demand is

equal 19,8 s

A B C D E F
A - 4.5 3.2 7.1 1.8 5.8
B 3.4 - 4.8 - 4.4 3.1
C 0.7 0.9 - 4.3 - 4.1
D - 2.8 1.0 - - -
E 3.7 4.2 3.8 - - 3.7
F 7.0 9.6 7.1 10.4 - -

Figure 59: delay OD matrix for solution 3 (2024)

A B C D E F
A - A A A A A
B A - A - A A
C A A - A - A
D - A A - - -
E A A A - - A
F A A A B - -
Figure 60: LOS OD matrix for solution 3 (2024)

the average delay per vehicle for the solution 3 configuration for the respective demand is

equal 4,5

101
A B C D E F
A - 2.2 3.6 9.7 2.0 8.1
B 35.6 - 20.7 - 193.4 40.2
C 0.4 - - 4.5 - 4.7
D - 2.3 0.7 - - -
E 2.4 2.7 2.2 - - 2.3
F 0.8 4.3 4.8 6.5 - -

Figure 61: delay OD matrix for solution 4 (2024)

A B C D E F
A - A A A A A
B E - C - F E
C A - - A - A
D - A A - - -
E A A A - - A
F A A A A - -
Figure 62: LOS OD matrix for solution 4 (2024)

the average delay per vehicle for the solution 4 configuration for the respective demand is

equal 20,47 s

7.3. 2048 Results

A B C D E F
A - 10.1 10.1 31.4 10.8 26.3
B 80.3 - 42.9 - 363.4 78.8
C 96.9 - - 95.0 - 96.5
D - 9.6 4.2 - - -
E 6.5 8.8 6.7 - - 6.0
F 8.0 19.1 9.4 27.2 - -

Figure 63: delay OD matrix for solution 1 (2048)

102
A B C D E F
A - B B D B D
B F - E - F F
C F - - F - F
D - A A - - -
E A A A - - A
F A C A D - -
Figure 64: LOS OD matrix for solution 1 (2048)

the average delay per vehicle for the solution 1 configuration for the respective demand is

equal 39,54 s

A B C D E F
A - 15.6 33.1 51.3 8.6 47.5
B 104.8 - 61.1 - 435.9 105.2
C 59.3 58.1 - 55.5 - 57.3
D - 6.6 1.7 - - -
E 4.8 7.0 4.4 - - 4.1
F 6.2 17.7 34.4 48.2 - -

Figure 65: delay OD matrix for solution 2 (2048)

A B C D E F
A - C D F A E
B F - F - F F
C F F - F - F
D - A A - - -
E A A A - - A
F A C D E - -
Figure 66: LOS OD matrix for solution 2 (2048)

the average delay per vehicle for the solution2 configuration for the respective demand is
equal 41,79 s

103
A B C D E F
A - 10.5 9.8 24.4 35.6 21.8
B 39.7 - 25.0 - 201.9 40.7
C 19.6 20.6 - 53.1 - 53.6
D - 5.2 2.3 - - -
E 7.0 7.8 7.0 - - 6.8
F 14.5 19.6 12.7 26.6 - -

Figure 67: delay OD matrix for solution 3 (2048)

A B C D E F
A - B A C D C
B E - D - F E
C C C - F - F
D - A A - - -
E A A A - - A
F B C B D - -
Figure 68: LOS OD matrix for solution 3 (2048)

the average delay per vehicle for the solution 3 configuration for the respective demand is

equal 34,12 S

A B C D E F
A - 30.8 65.2 79.0 8.6 78.4
B 75.6 - 44.7 - 338.2 76.1
C 30.0 - - 59.7 - 60.9
D - 3.0 1.0 - - -
E 4.4 5.4 2.9 - - 4.1
F 7.6 17.2 129.4 142.4 - -

Figure 69: delay OD matrix for solution 4 (2048)

104
A B C D E F
A - D F F A F
B F - E - F F
C D - - F - F
D A A - - -
E A A A - - A
F A C F F - -
Figure 70: LOS OD matrix for solution 4 (2048)

the average delay per vehicle for the solution 4 configuration for the respective demand is

equal 56,73 S

105
8. COST BENEFIT ANALISYS

This study is done with the ultimate goal of assessing which of the options already studied

from the technical point of view is the most convenient in terms of economic benefit.

For this it must be established the variables of benefits and expenses that will be

considered and those that will not. Therefore, it is clear that the benefits considered in this

study are not the total benefits that will have an impact on users, but they will be

proportional when comparing the different options.

The variables considered as expenses are the cost of investment and the maintenance of

the infrastructure.

The variables considered as benefits are the value of time and the fuel consumption, based

on delays saved.

This study does not consider benefits related with noise pollution, air pollution, or safety.

8.1. Cost of Expenses

8.1.1. Total Cost of Infrastructure

The financial costs of the investment for the intervention alternatives are shown in the

following table, in which it can also be appreciate the total cost consisting of 3 categories:

cost of infrastructure, cost of safety, cost of risk and unexpected events.

106
Table 16: Total cost of infrastructure by categories

8.1.2. Cost of Maintenance

The several costs of maintenance per year are shown in the following table, and there is a

certain growing relationship with the construction costs for each solution.

Table 17: Cost of maintenance

Scenarios Cost €
Current state 24300
Solution 1 46400
Solution 2 55950
Solution 3 78610
Solution 4 47340

8.2. Cost of Benefits

As mentioned above the benefits considered are proportional to the delays savings

provided by the different solutions. Taking this into account, the objective is to calculate

107
all delays saved in 25 years and based on an equivalent value per unit of time an

equivalent cost can be given as a benefit.

8.2.1. Calculation of Total Delay

For the calculation of the total delay, it starts from the premise of constructing a demand

vs. delay graph with all the points recorded in the simulations. In this way we can obtain

an equation that adjusts the trend and behavior of the delays that are changing with

respect to the demand year after year.

Once this is done, it should be considered that these delays only make part of the peak

hour segment of all years. Therefore, it is necessary to take as input the graph of

distribution of the demand during normal working days from Monday to Saturday.

It cannot be assumed to make a distribution of the delays proportionally, since you must

study what is the point at which the delays begin, since in a large percentage of the hours

they are not created delays an analysis of the more hours must be made demanded only

equation values where delays values are positive or greater than 0.

In this way a proportional distribution of the delays should not be made, since it is

necessary to study the point at which the delays begin, because in a large percentage of the

hours no delays are created. An analysis is carried out of the most demanded hours where

only equation values where delays are positive or greater than 0 are considered.

108
Figure 71: Personal delay vs node demand solution 1

Figure 72: Personal delay vs node demand solution 3

109
Figure 73: Personal delay vs node demand solution 3

Figure 74: Personal delay vs node demand solution 4

110
Solution 1 presents its positive delays point at the moment when demand is 10300

vehicles/h.

Solution 2 presents its positive delays point at the moment when demand is 10520

vehicles/h.

Solution 3 presents its positive delays point at the moment when demand is 12050

vehicles/h.

Solution 4 presents its positive delays point at the moment when demand is 11000

vehicles/h.

From the following figure the distribution of the demand during the hours of the day can

be appreciated, with this distribution, and with the equation of the general delay

depending on the demand we will start counting all the delays by hours of the day for

each year.

111
Figure 75: Distribution demand over the day.

The following results of the hour delay in seconds per year are given in the following

tables.
Table 18: Hour delay in seconds per year for the current state
Year (1) 7 - 8 (2) 8-9 (3) 16-17 (4) 17-18 (5) 18 - 19 (1) Delay (s) (2) Delay (s) (3 )Delay (s) (4) Delay (s) (5) Delay (s)
2024 13624,3 7992,9 5903,9 8483,4 9082,9 41,4 12,0 19,1
2025 13827,3 8112,0 5991,8 8609,8 9218,2 42,2 12,8 19,9
2026 14033,4 8232,9 6081,1 8738,1 9355,6 43,0 13,6 20,7
2027 14242,4 8355,6 6171,7 8868,3 9495,0 43,9 14,5 21,5
2028 14454,7 8480,1 6263,7 9000,4 9636,4 44,7 15,3 22,3
2029 14670,0 8606,4 6357,0 9134,5 9780,0 45,5 16,1 23,1
2030 14888,6 8734,7 6451,7 9270,6 9925,7 46,3 16,9 23,9
2031 15110,5 8864,8 6547,9 9408,8 10073,6 47,1 17,7 1,0 24,8
2032 15335,6 8996,9 6645,4 9549,0 10223,7 47,9 18,5 1,8 25,6
2033 15564,1 9130,9 6744,4 9691,3 10376,1 48,8 19,3 2,6 26,4
2034 15796,0 9267,0 6844,9 9835,7 10530,7 49,6 20,2 3,5 27,2 1,4
2035 16031,4 9405,1 6946,9 9982,2 10687,6 50,4 21,0 4,3 28,0 2,3
2036 16270,2 9545,2 7050,4 10130,9 10846,8 51,2 21,8 5,1 28,8 3,2
2037 16512,7 9687,4 7155,5 10281,9 11008,4 52,0 22,6 5,9 29,7 4,2
2038 16758,7 9831,8 7262,1 10435,1 11172,5 52,8 23,4 6,7 30,5 5,1
2039 17008,4 9978,3 7370,3 10590,6 11338,9 53,7 24,2 7,5 31,3 6,0
2040 17261,8 10126,9 7480,1 10748,4 11507,9 54,5 25,1 8,3 32,1 7,0
2041 17519,0 10277,8 7591,6 10908,5 11679,4 55,3 25,9 9,2 32,9 7,9
2042 17780,1 10431,0 7704,7 11071,1 11853,4 56,1 26,7 10,0 33,7 8,8
2043 18045,0 10586,4 7819,5 11236,0 12030,0 56,9 27,5 10,8 34,6 9,8
2044 18313,9 10744,1 7936,0 11403,4 12209,2 57,7 28,3 11,6 35,4 10,7
2045 18586,7 10904,2 8054,3 11573,3 12391,2 58,5 29,1 12,4 36,2 11,6
2046 18863,7 11066,7 8174,3 11745,8 12575,8 59,4 29,9 13,2 37,0 12,5
2047 19144,8 11231,6 8296,1 11920,8 12763,2 60,2 30,8 14,1 37,8 13,5
2048 19430,0 11398,9 8419,7 12098,4 12953,3 61,0 31,6 14,9 38,6 14,4

112
Table 19: Hour delay in seconds per year for the solution 1
Year (1) 7:00 - 8:00 (2) 8:00-9:00 (3) 17:00- 18:00 (4) 18:00 - 19:00 (1) Delay (s) (2) Delay (s) (3 )Delay (s) (4) Delay (s)
2024 13461,1 16,8
2025 13661,7 17,7
2026 13865,2 18,7
2027 14071,8 19,6
2028 14281,5 20,5
2029 14494,3 21,5
2030 14710,3 22,4
2031 14929,4 23,3
2032 15151,9 10101,3 24,3
2033 15377,7 10251,8 25,2
2034 15606,8 10404,5 26,1 0,6
2035 15839,3 10559,5 27,0 1,6
2036 16075,3 10009,6 10716,9 28,0 2,5
2037 16314,9 10158,7 10876,6 28,9 3,4
2038 16557,9 10310,1 11038,6 29,8 0,1 4,3
2039 16804,7 10463,7 11203,1 30,8 1,0 5,3
2040 17055,0 10005,6 10619,6 11370,0 31,7 1,9 6,2
2041 17309,2 10154,7 10777,8 11539,4 32,6 2,8 7,1
2042 17567,1 10306,0 10938,4 11711,4 33,6 0,0 3,8 8,1
2043 17828,8 10459,6 11101,4 11885,9 34,5 1,0 4,7 9,0
2044 18094,5 10615,4 11266,8 12063,0 35,4 1,9 5,6 9,9
2045 18364,1 10773,6 11434,7 12242,7 36,3 2,8 6,6 10,9
2046 18637,7 10934,1 11605,1 12425,1 37,3 3,8 7,5 11,8
2047 18915,4 11097,0 11778,0 12610,3 38,2 4,7 8,4 12,7
2048 19197,2 11262,4 11953,5 12798,2 39,1 5,6 9,4 13,6

Table 20: Hour delay in seconds per year for the solution 2
Year (1) 7:00 - 8:00 (2) 8:00-9:00 (3) 17:00- 18:00 (4) 18:00 - 19:00 (1) Delay (s) (2) Delay (s) (3 )Delay (s) (4) Delay (s)
2024 13577,0 7965,2 8454,0 9051,4 17,6
2025 13779,3 8083,9 8579,9 9186,2 18,6
2026 13984,7 8204,3 8707,8 9323,1 19,7
2027 14193,0 8326,6 8837,5 9462,0 20,7
2028 14404,5 8450,6 8969,2 9603,0 21,7
2029 14619,1 8576,6 9102,8 9746,1 22,8
2030 14837,0 8704,3 9238,5 9891,3 23,8
2031 15058,0 8834,0 9376,1 10038,7 24,8
2032 15282,4 8965,7 9515,8 10188,3 25,9
2033 15510,1 9099,3 9657,6 10340,1 26,9
2034 15741,2 9234,8 9801,5 10494,1 27,9
2035 15975,7 9372,4 9947,6 10650,5 29,0 0,7
2036 16213,8 9512,1 10095,8 10809,2 30,0 1,7
2037 16455,4 9653,8 10246,2 10970,2 31,0 2,7
2038 16700,6 9797,7 10398,9 11133,7 32,0 3,8
2039 16949,4 9943,6 10553,8 11299,6 33,1 0,0 4,8
2040 17201,9 10091,8 10711,1 11468,0 34,1 1,1 5,8
2041 17458,2 10242,2 10870,7 11638,8 35,1 2,1 6,9
2042 17718,4 10394,8 11032,6 11812,3 36,2 3,1 7,9
2043 17982,4 10549,7 11197,0 11988,3 37,2 0,0 4,2 8,9
2044 18250,3 10706,9 11363,9 12166,9 38,2 1,0 5,2 10,0
2045 18522,2 10866,4 11533,2 12348,2 39,3 2,1 6,2 11,0
2046 18798,2 11028,3 11705,0 12532,2 40,3 3,1 7,3 12,0
2047 19078,3 11192,6 11879,4 12718,9 41,3 4,1 8,3 13,0
2048 19362,6 11359,4 12056,4 12908,4 42,4 5,2 9,3 14,1

113
Table 21: Hour delay in seconds per year for the solution 3
Year (1) 7:00 - 8:00 (2) 8:00-9:00 (3) 17:00- 18:00 (4) 18:00 - 19:00
(1) Delay (s) (2) Delay (s) (3 )Delay (s) (4) Delay (s)
2024 13577,0 7965,2 8454,0 9051,4 8,3
2025 13779,3 8083,9 8579,9 9186,2 9,3
2026 13984,7 8204,3 8707,8 9323,1 10,3
2027 14193,0 8326,6 8837,5 9462,0 11,4
2028 14404,5 8450,6 8969,2 9603,0 12,4
2029 14619,1 8576,6 9102,8 9746,1 13,5
2030 14837,0 8704,3 9238,5 9891,3 14,5
2031 15058,0 8834,0 9376,1 10038,7 15,5
2032 15282,4 8965,7 9515,8 10188,3 16,6
2033 15510,1 9099,3 9657,6 10340,1 17,6
2034 15741,2 9234,8 9801,5 10494,1 18,7
2035 15975,7 9372,4 9947,6 10650,5 19,7
2036 16213,8 9512,1 10095,8 10809,2 20,7
2037 16455,4 9653,8 10246,2 10970,2 21,8
2038 16700,6 9797,7 10398,9 11133,7 22,8
2039 16949,4 9943,6 10553,8 11299,6 23,8
2040 17201,9 10091,8 10711,1 11468,0 24,9
2041 17458,2 10242,2 10870,7 11638,8 25,9
2042 17718,4 10394,8 11032,6 11812,3 27,0
2043 17982,4 10549,7 11197,0 11988,3 28,0
2044 18250,3 10706,9 11363,9 12166,9 29,0 0,6
2045 18522,2 10866,4 11533,2 12348,2 30,1 1,6
2046 18798,2 11028,3 11705,0 12532,2 31,1 2,6
2047 19078,3 11192,6 11879,4 12718,9 32,2 3,7
2048 19362,6 11359,4 12056,4 12908,4 33,2 4,7

Table 22: Hour delay in seconds per year for the solution 4
Year (1) 7:00 - 8:00 (2) 8:00-9:00 (3) 17:00- 18:00 (4) 18:00 - 19:00 (1) Delay (s) (2) Delay (s) (3 )Delay (s) (4) Delay (s)
2024 13461,1 7897,2 8381,8 8974,1 20,4
2025 13661,7 8014,9 8506,7 9107,8 21,9
2026 13865,2 8134,3 8633,4 9243,5 23,4
2027 14071,8 8255,5 8762,1 9381,2 24,9
2028 14281,5 8378,5 8892,6 9521,0 26,5
2029 14494,3 8503,3 9025,1 9662,9 28,0
2030 14710,3 8630,0 9159,6 9806,8 29,5
2031 14929,4 8758,6 9296,1 9953,0 31,0
2032 15151,9 8889,1 9434,6 10101,3 32,5
2033 15377,7 9021,6 9575,2 10251,8 34,0
2034 15606,8 9156,0 9717,8 10404,5 35,5
2035 15839,3 9292,4 9862,6 10559,5 37,1
2036 16075,3 9430,9 10009,6 10716,9 38,6
2037 16314,9 9571,4 10158,7 10876,6 40,1
2038 16557,9 9714,0 10310,1 11038,6 41,6 0,1
2039 16804,7 9858,7 10463,7 11203,1 43,1 1,6
2040 17055,0 10005,6 10619,6 11370,0 44,6 3,1
2041 17309,2 10154,7 10777,8 11539,4 46,1 4,6
2042 17567,1 10306,0 10938,4 11711,4 47,6 6,2
2043 17828,8 10459,6 11101,4 11885,9 49,2 0,7 7,7
2044 18094,5 10615,4 11266,8 12063,0 50,7 2,2 9,2
2045 18364,1 10773,6 11434,7 12242,7 52,2 3,7 10,7
2046 18637,7 10934,1 11605,1 12425,1 53,7 5,2 12,2
2047 18915,4 11097,0 11778,0 12610,3 55,2 0,6 6,7 13,7
2048 19197,2 11262,4 11953,5 12798,2 56,7 2,2 8,2 15,2

114
Having obtained the results for the delays for all hours, during the different years, it make

way to the calculation of the entire annual delay for each solution, in order to see the

contrast with the current state delay and obtain the difference of delays that It would be

the delay saved. this delay saved will be assigned a value in euros per hour which will be

15 euros / hour, which contains the benefit of saving gasoline and time.

Table 23: Value of time per person and average occupancy factor according the handbook on external cost

of transport.

In the average delay time, 2.4 liters of gasoline / hour are lost. and the value of a liter of

gasoline is 1.6 euros / liters. so that one hour of delay is considered as 3.8 euros / hour.

An average car occupancy factor of 1.7 for the case of Italy it was to high and optimistic to

be assumed, so according with the surveys in north of Italy it was assumed a value of 1.3

persons/ vehicle.

The following tables show the total value of the benefits in euros year after year, after

calculating the time saved after the solution and the current status.

115
Table 24: Total cost process of benefits per each year for solution 1
Total delay (s) Current Delay Time saved (s) Time saved (h) Cost
84222535,6 356677944,7 354192031,9 98386,7 1.475.800,1 €
90201744,8 372807311,3 367387236,5 102052,0 1.530.780,2 €
96340436,2 389338147,0 380897024,0 105804,7 1.587.070,9 €
102642034,9 406278834,6 394727839,6 109646,6 1.644.699,3 €
109110032,7 423637917,8 408886250,5 113579,5 1.703.692,7 €
115747989,3 441424103,6 423378948,6 117605,3 1.764.079,0 €
122559533,5 459646266,0 438212752,2 121725,8 1.825.886,5 €
129548364,5 481168880,3 457106670,5 126974,1 1.904.611,1 €
136718253,2 502685426,2 475757324,9 132154,8 1.982.322,2 €
144073043,5 524736340,9 494862286,5 137461,7 2.061.926,2 €
154057916,8 553677376,6 519505297,8 144307,0 2.164.605,4 €
165482273,2 581237022,5 540481174,0 150133,7 2.252.004,9 €
177212873,1 609495023,9 561966796,0 156101,9 2.341.528,3 €
189256306,1 638466073,3 583972697,4 162214,6 2.433.219,6 €
201840293,9 668165145,9 606222307,7 168395,1 2.525.926,3 €
218151383,3 698607505,1 624592958,4 173498,0 2.602.470,7 €
234903732,5 729808707,3 643376467,2 178715,7 2.680.735,3 €
252106870,0 761784607,4 662581058,6 184050,3 2.760.754,4 €
269896441,0 794551364,5 682051400,5 189458,7 2.841.880,8 €
291649349,6 828125447,2 697418926,9 193727,5 2.905.912,2 €
313990575,1 862523639,2 713092983,3 198081,4 2.971.220,8 €
336932820,1 897763045,2 729079292,6 202522,0 3.037.830,4 €
360489035,0 933861096,6 745383680,2 207051,0 3.105.765,3 €
384672422,5 970835557,6 762012075,6 211670,0 3.175.050,3 €
409496442,9 1008704531,0 778970514,5 216380,7 3.245.710,5 €

116
Table 25: Total cost process of benefits per each year for solution 2
Year Total delay (s) Current Delay Time saved (s) Time saved (h) Cost
2024 88907942,7 356677944,7 348101002,6 96694,7 1.450.420,8 €
2025 95521747,2 372807311,3 360471233,4 100130,9 1.501.963,5 €
2026 127891130,7 389338147,0 339881121,2 94411,4 1.416.171,3 €
2027 136606539,6 406278834,6 350573983,5 97381,7 1.460.724,9 €
2028 145553274,6 423637917,8 361510036,1 100419,5 1.506.291,8 €
2029 154736294,2 441424103,6 372694152,2 103526,2 1.552.892,3 €
2030 164160653,6 459646266,0 384131296,1 106703,1 1.600.547,1 €
2031 173831505,9 481168880,3 399538586,7 110982,9 1.664.744,1 €
2032 183754104,2 502685426,2 414610718,6 115169,6 1.727.544,7 €
2033 193933803,7 524736340,9 430043298,4 119456,5 1.791.847,1 €
2034 204376062,9 553677376,6 454091707,8 126136,6 1.892.048,8 €
2035 218385227,8 581237022,5 471707333,1 131029,8 1.965.447,2 €
2036 234604819,6 609495023,9 487357265,5 135377,0 2.030.655,3 €
2037 251259271,6 638466073,3 503368842,2 139824,7 2.097.370,2 €
2038 268357941,6 668165145,9 519749365,6 144374,8 2.165.622,4 €
2039 286057274,8 698607505,1 536315299,5 148976,5 2.234.647,1 €
2040 309214561,0 729808707,3 546772390,2 151881,2 2.278.218,3 €
2041 332998426,8 761784607,4 557422034,8 154839,5 2.322.591,8 €
2042 357422403,1 794551364,5 568267649,9 157852,1 2.367.781,9 €
2043 382512225,1 828125447,2 579297188,7 160915,9 2.413.738,3 €
2044 413395413,8 862523639,2 583866693,1 162185,2 2.432.777,9 €
2045 445113999,9 897763045,2 588443758,9 163456,6 2.451.849,0 €
2046 477686022,0 933861096,6 593027597,1 164729,9 2.470.948,3 €
2047 511129870,5 970835557,6 597617393,2 166004,8 2.490.072,5 €
2048 545464294,7 1008704531,0 602212307,2 167281,2 2.509.217,9 €

Table 26: Total cost process of benefits per each year for solution 3
Year Total delay (s) Current Delay (s) Time saved (s) Time saved (h) Cost
2024 41755957,8 356677944,7 409398583,0 113721,8 1.705.827,4 €
2025 47701010,2 372807311,3 422638191,5 117399,5 1.760.992,5 €
2026 53813954,9 389338147,0 436181449,7 121161,5 1.817.422,7 €
2027 60098475,3 406278834,6 450034467,2 125009,6 1.875.143,6 €
2028 66558327,1 423637917,8 464203467,9 128945,4 1.934.181,1 €
2029 73197340,1 441424103,6 478694792,6 132970,8 1.994.561,6 €
2030 80019419,0 459646266,0 493514901,1 137087,5 2.056.312,1 €
2031 87028545,3 481168880,3 512382435,4 142328,5 2.134.926,8 €
2032 94228778,5 502685426,2 530993641,9 147498,2 2.212.473,5 €
2033 101624257,5 524736340,9 550045708,4 152790,5 2.291.857,1 €
2034 109219202,0 553677376,6 577795627,0 160498,8 2.407.481,8 €
2035 117017914,2 581237022,5 603484840,8 167634,7 2.514.520,2 €
2036 125024780,3 609495023,9 629811316,6 174947,6 2.624.213,8 €
2037 133244271,8 638466073,3 656788341,8 182441,2 2.736.618,1 €
2038 141680947,5 668165145,9 684429458,0 190119,3 2.851.789,4 €
2039 150339454,5 698607505,1 712748465,8 197985,7 2.969.785,3 €
2040 159224530,5 729808707,3 741759429,9 206044,3 3.090.664,3 €
2041 168341004,8 761784607,4 771476683,4 214299,1 3.214.486,2 €
2042 177693800,7 794551364,5 801914833,1 222754,1 3.341.311,8 €
2043 187287936,4 828125447,2 833088764,0 231413,5 3.471.203,2 €
2044 199698644,3 862523639,2 861672493,4 239353,5 3.590.302,1 €
2045 214599230,8 897763045,2 888112958,8 246698,0 3.700.470,7 €
2046 229899519,6 933861096,6 915150050,1 254208,3 3.813.125,2 €
2047 245608113,8 970835557,6 942795676,9 261887,7 3.928.315,3 €
2048 261733784,2 1008704531,0 971061970,8 269739,4 4.046.091,5 €

117
Table 27: Total cost process of benefits per each year for solution 4
Total delay (s) Current Delay Time saved (s) Time saved (h) Cost
102172203,4 356677944,7 330857463,7 91904,9 1.378.572,77 €
116028117,3 372807311,3 333812952,3 92725,8 1.390.887,30 €
125889270,0 389338147,0 342483540,1 95134,3 1.427.014,75 €
136018525,6 406278834,6 351338401,7 97594,0 1.463.910,01 €
146421684,4 423637917,8 360381103,4 100105,9 1.501.587,93 €
157104659,9 441424103,6 369615276,9 102670,9 1.540.063,65 €
168073480,9 459646266,0 379044620,6 105290,2 1.579.352,59 €
179334294,0 481168880,3 392384962,1 108995,8 1.634.937,34 €
190893365,4 502685426,2 405329679,1 112591,6 1.688.873,66 €
202757083,0 524736340,9 418573035,2 116270,3 1.744.054,31 €
214931959,3 553677376,6 440369042,5 122324,7 1.834.871,01 €
227424632,7 581237022,5 459956106,7 127765,6 1.916.483,78 €
240241870,7 609495023,9 480029099,0 133341,4 2.000.121,25 €
253390571,9 638466073,3 500598151,7 139055,0 2.085.825,63 €
267301425,5 668165145,9 521122836,5 144756,3 2.171.345,15 €
287711518,2 698607505,1 534164783,0 148379,1 2.225.686,60 €
308670488,1 729808707,3 547479685,0 152077,7 2.281.165,35 €
330190160,4 761784607,4 561072781,1 155853,6 2.337.803,25 €
352282591,0 794551364,5 574949405,6 159708,2 2.395.622,52 €
377883030,7 828125447,2 585315141,5 162587,5 2.438.813,09 €
407809935,0 862523639,2 591127815,5 164202,2 2.463.032,56 €
438544767,2 897763045,2 596983761,4 165828,8 2.487.432,34 €
470104959,5 933861096,6 602882978,2 167467,5 2.512.012,41 €
505256620,8 970835557,6 605252617,9 168125,7 2.521.885,91 €
545167836,4 1008704531,0 602597703,0 167388,3 2.510.823,76 €

8.3. CBA

Based on the elements described in the previous paragraphs, the economic analysis was

prepared for the period between 2019 (start-up of the project) and 2048, foreseeing the

entry into operation in 2024.

Therefore, for each year the differential costs and benefits between the project alternative

from time to time have been estimated time considered and that of non-intervention (state

of affairs). The following tables show the values for the various design alternatives

described above.

118
- the Net Present Value (NPV), is the sum of the net discounted benefits. The formula used

is

Equation 6: Net present value

Where

- Bt are the variations determined by the project with reference to the benefits

- Ct are the economic investment costs and the changes in the economic costs of

extraordinary maintenance;

- is the discount social rate: 3 %.

- T is the time period over which the project evaluation extends.

The results are shown in the following tables.

119
Table 28: CBA Solution 1

YEAR COST (1000 €) ANNUAL BENEFIT (1000 €) PV COST PV BENEFITS NPV (1000 €)
1 -1272,3 -1272,3 -1272,3
2 -1272,3 -1235,2 -1235,2
3 -7633,8 -7195,6 -7195,6
4 -10178,4 -9314,6 -9314,6
5 -4300,0 -3820,5 -3820,5
6 -22,1 1475,8 -19,1 1273,0 1254,0
7 -22,1 1530,8 -18,5 1282,0 1263,5
8 -22,1 1587,1 -18,0 1290,4 1272,5
9 -22,1 1644,7 -17,4 1298,3 1280,9
10 -22,1 1703,7 -16,9 1305,7 1288,8
11 -22,1 1764,1 -16,4 1312,6 1296,2
12 -22,1 1825,9 -16,0 1319,1 1303,1
13 -22,1 1904,6 -15,5 1335,9 1320,4
14 -22,1 1982,3 -15,0 1349,9 1334,8
15 -22,1 2061,9 -14,6 1363,2 1348,6
16 -22,1 2164,6 -14,2 1389,4 1375,2
17 -22,1 2252,0 -13,8 1403,4 1389,6
18 -22,1 2341,5 -13,4 1416,7 1403,3
19 -22,1 2433,2 -13,0 1429,3 1416,3
20 -22,1 2525,9 -12,6 1440,5 1427,9
21 -22,1 2602,5 -12,2 1440,9 1428,7
22 -22,1 2680,7 -11,9 1441,0 1429,1
23 -22,1 2760,8 -11,5 1440,8 1429,3
24 -22,1 2841,9 -11,2 1440,0 1428,8
25 -22,1 2905,9 -10,9 1429,5 1418,6
26 -22,1 2971,2 -10,6 1419,1 1408,5
27 -22,1 3037,8 -10,2 1408,6 1398,4
28 -22,1 3105,8 -9,9 1398,2 1388,2
29 -22,1 3175,1 -9,7 1387,7 1378,1
30 -22,1 3245,7 -9,4 1377,3 1367,9

Table 29: CBA indicators solution 1

BCR 1,424
TOTAL NPV € 11212379,8

120
Table 30: CBA Solution 2

YEAR COST (1000 €) ANNUAL BENEFIT (1000 €) PV COST PV BENEFITS NPV (1000 €)
1 -1367,1 -1367,1 -1367,1
2 -1367,1 -1327,3 -1327,3
3 -8202,9 -7732,0 -7732,0
4 -10937,1 -10009,0 -10009,0
5 -4620,6 -4105,3 -4105,3
6 -31,7 1450,4 -27,3 1251,1 1223,8
7 -31,7 1502,0 -26,5 1257,9 1231,4
8 -31,7 1416,2 -25,7 1151,5 1125,7
9 -31,7 1460,7 -25,0 1153,1 1128,1
10 -31,7 1506,3 -24,3 1154,4 1130,2
11 -31,7 1552,9 -23,6 1155,5 1131,9
12 -31,7 1600,5 -22,9 1156,3 1133,4
13 -31,7 1664,7 -22,2 1167,6 1145,4
14 -31,7 1727,5 -21,6 1176,4 1154,8
15 -31,7 1791,8 -20,9 1184,6 1163,7
16 -31,7 1892,0 -20,3 1214,4 1194,1
17 -31,7 1965,4 -19,7 1224,8 1205,1
18 -31,7 2030,7 -19,1 1228,6 1209,4
19 -31,7 2097,4 -18,6 1232,0 1213,4
20 -31,7 2165,6 -18,0 1235,0 1217,0
21 -31,7 2234,6 -17,5 1237,3 1219,7
22 -31,7 2278,2 -17,0 1224,7 1207,6
23 -31,7 2322,6 -16,5 1212,1 1195,6
24 -31,7 2367,8 -16,0 1199,7 1183,7
25 -31,7 2413,7 -15,6 1187,4 1171,8
26 -31,7 2432,8 -15,1 1161,9 1146,8
27 -31,7 2451,8 -14,7 1136,9 1122,2
28 -31,7 2470,9 -14,2 1112,4 1098,1
29 -31,7 2490,1 -13,8 1088,4 1074,5
30 -31,7 2509,2 -13,4 1064,8 1051,3

Table 31: CBA indicators solution 2

BCR 1,139
TOTAL NPV (€) 4538342,9

121
Table 32: CBA Solution 3

YEAR COST (1000 €) ANNUAL BENEFIT (1000 €) PV COST PV BENEFITS NPV (1000 €)
1 -1654,0 -1654,0 -1654,0
2 -1654,0 -1605,8 -1605,8
3 -9923,9 -9354,2 -9354,2
4 -13231,9 -12109,0 -12109,0
5 -5590,0 -4966,6 -4966,6
6 -54,3 1705,8 -46,8 1471,5 1424,6
7 -54,3 1761,0 -45,5 1474,8 1429,3
8 -54,3 1817,4 -44,2 1477,7 1433,6
9 -54,3 1875,1 -42,9 1480,3 1437,4
10 -54,3 1934,2 -41,6 1482,4 1440,8
11 -54,3 1994,6 -40,4 1484,1 1443,7
12 -54,3 2056,3 -39,2 1485,5 1446,3
13 -54,3 2134,9 -38,1 1497,4 1459,3
14 -54,3 2212,5 -37,0 1506,6 1469,6
15 -54,3 2291,9 -35,9 1515,2 1479,3
16 -54,3 2407,5 -34,9 1545,3 1510,4
17 -54,3 2514,5 -33,8 1567,0 1533,1
18 -54,3 2624,2 -32,9 1587,7 1554,8
19 -54,3 2736,6 -31,9 1607,5 1575,6
20 -54,3 2851,8 -31,0 1626,3 1595,4
21 -54,3 2969,8 -30,1 1644,3 1614,2
22 -54,3 3090,7 -29,2 1661,4 1632,2
23 -54,3 3214,5 -28,3 1677,6 1649,3
24 -54,3 3341,3 -27,5 1693,0 1665,5
25 -54,3 3471,2 -26,7 1707,6 1680,9
26 -54,3 3590,3 -25,9 1714,7 1688,8
27 -54,3 3700,5 -25,2 1715,9 1690,7
28 -54,3 3813,1 -24,4 1716,6 1692,2
29 -54,3 3928,3 -23,7 1717,0 1693,2
30 -54,3 4046,1 -23,0 1716,9 1693,9

Table 33: CBA indicators solution 3

BCR 1,247
TOTAL NPV (€) 9244403,8

122
Table 34: CBA Solution 4

YEAR COST (1000 €) ANNUAL BENEFIT (1000 €) PV COST PV BENEFITS NPV (1000 €)
1 -1071,8 -1071,8 -1071,8
2 -1071,8 -1040,6 -1040,6
3 -6430,7 -6061,5 -6061,5
4 -8574,2 -7846,6 -7846,6
5 -3622,3 -3218,4 -3218,4
6 -23,0 1378,6 -19,9 1189,2 1169,3
7 -23,0 1390,9 -19,3 1164,8 1145,6
8 -23,0 1427,0 -18,7 1160,3 1141,6
9 -23,0 1463,9 -18,2 1155,6 1137,4
10 -23,0 1501,6 -17,7 1150,8 1133,2
11 -23,0 1540,1 -17,1 1146,0 1128,8
12 -23,0 1579,4 -16,6 1141,0 1124,3
13 -23,0 1634,9 -16,2 1146,7 1130,6
14 -23,0 1688,9 -15,7 1150,0 1134,4
15 -23,0 1744,1 -15,2 1153,0 1137,8
16 -23,0 1834,9 -14,8 1177,7 1162,9
17 -23,0 1916,5 -14,4 1194,3 1179,9
18 -23,0 2000,1 -13,9 1210,1 1196,2
19 -23,0 2085,8 -13,5 1225,2 1211,7
20 -23,0 2171,3 -13,1 1238,3 1225,1
21 -23,0 2225,7 -12,8 1232,3 1219,6
22 -23,0 2281,2 -12,4 1226,2 1213,9
23 -23,0 2337,8 -12,0 1220,1 1208,1
24 -23,0 2395,6 -11,7 1213,8 1202,2
25 -23,0 2438,8 -11,3 1199,7 1188,4
26 -23,0 2463,0 -11,0 1176,4 1165,4
27 -23,0 2487,4 -10,7 1153,4 1142,7
28 -23,0 2512,0 -10,4 1130,9 1120,5
29 -23,0 2521,9 -10,1 1102,3 1092,2
30 -23,0 2510,8 -9,8 1065,5 1055,7

Table 35: CBA indicators solution 4

BCR 1,442
TOTAL NPV (€) 9728293,7

123
9. CONCLUSIONS

About conflicts solved

In general terms when the solutions were presented, in the maneuver matrices, it is

evident that all were designed with the main criterion of deleting the interchange points,

but also of decreasing points of intersection, convergence, divergence, and in some cases

the combination the mixture of these.

Thus, the solution that most eliminated conflicts was Solution 3 that has gone from 138 to

48 conflicts, followed by Solution 4 that has gone from 138 to 51, followed by Solution 1

that has gone from 138 to 53, and finally Solution 2 that has gone from 138 to 77.

About interchange zones

The interchange lanes have a particularity and happens that some vehicles gain speed in

while others lose in the same lane, so they are especially dangerous, and removing them

not only brings benefits at the level of safety and accident rate, but also according to the

results of this study, the effects of the delay diminish exponentially.

Since users face a decision at some point where it is not really clear who should take the

initiative to do the first maneuver without being certain of what other users think they will

do. This situation leads eventually to a critical situation of non-synchronization and

finishes with long ques when it comes to the critical demand hours.

124
Achieving a reliable simulation that adapts to user behavior is complicated, due to the

parameters of driving behavior vary depending on each society or even each area within a

population.

About simulation results

The results of the simulation will only be analyzed in terms of traffic and service level

The simulation results show how traffic delays and level of service behave over time with

increasing demand. And so, it shows us that all solutions respond well to the current

demand studied on the node.

but when it comes to assess how the infrastructure responds, the results begin to show in

the projected demand to 2024 that only solution number 3 maintains its optimal service

level and time status in delays, the other 3 solutions remain in an acceptable service level

of 17.93, 19.8, and 20.47 seconds / vehicle.

When the results of the projected demand for 2048 are analyzed again all the demands fall

within a certain range of stability, where only solution 4 presents delay of the 56.73 type

the rest has delays of 39.54, 41.79,56.73 (seconds / vehicle).

The only solution that remained below the current delay level (2016) that is 35.6 s / veh

was solution 3. Solution 1 in terms of delay and service level is the second-best option,

then it comes solution 2 and 4.

125
About CBA results

In the analysis of cost benefit analysis, everything about traffic improvement analysis is

put aside, to take everything to monetary terms. And in financial terms, it must be

determined which of all the proposed solutions is the one that returns the most benefits in

terms of net present value, and which is the one that returns the most according to your

investment.

The net present values are theoretically the most striking indicators in terms of return,

since comparing with other solutions we can know directly which provides more

economic benefits, in this case the solution 1 with NPV of 11,212,379 euros is the solution

that returns most benefits, with Regarding the other options. solution 2 with 4,538342

euros. solution 3 with 9,244403 euros. solution 4 with 9.728293 euros

The benefit cost ratio, on the other hand, is an indicator that makes us understand what

proportion the benefits have with respect to investment. and this in real life is very useful

when resources are scarce or limited as usual. in this aspect the options with the highest

ratio were option 1 and 4, which had a ratio of 1.42 and 1.44 respectively, followed by

option 3 with a ratio of 1.24 and finally option 2 with a ratio of 1.13.

Thus, it could be said that option 1 is the most viable option since its investment responds

more efficiently with respect to the other alternatives and returns the benefits more

abundantly both in quantity and in proportion. followed by option 4 which has the same

degree of benefit in proportion but not in amount, and the 3 that has a very large degree of

126
investment, but that does not return enough money despite its good performance that

offers a service level. Finally, option 2 does not meet the expected requirements in any

way.

About how decisions are taken in reality

Unfortunately, in real life, for different reasons, such as constructive facilities, personal

interests, underestimation of the benefits of users, these studies do not have the necessary

weight in decision making, it is something that has to change because they are finally the

users and people who should benefit from these kinds of decisions and not some

individuals.

127
10. BIBLIOGRAPHY

Heather Jones (2014). Transport infrastructure project evaluation using cost-benefit

analysis. Procedia –Social and Behavioral Sciences.

Munger, M. (2000). Analyzing policy: choices, conflicts and practices. New York: W.W.

Norton.

Nickel, J., Ross, A.M., & Rhodes, D.H. (2009). Comparison of project evaluation using cost-

benefit analysis and multi-attribute tadespace exploration in the transportation

domain. Second International Symposium on Engineering Systems, MIT,

Cambridge.

Mokhtarian & Saloman (2001).How derived is the demand for travel? Some conceptual &

measurement of considerations. Transportation

Research Part A 35 (695-719) .

National Research Council (2000) High Capacity Manual.

PTV AG, Karlsruhe, Germany (2018) Vissim 11 Manual.

European Commission (2019) Handbook on the external cost of transport.

128

Вам также может понравиться