NEPAL

ELECTRIFICATION
STATISTICS: 2019 i

NEPAL ELECTRICITY AUTHORITY


NEPAL
ELECTRIFICATION
STATISTICS: 2019

NEPAL ELECTRICITY AUTHORITY


Nepal Electrification Statistics: 2019
May 2019

Published by:
Nepal Electricity Authority
Central Office, Durbarmarg Kathmandu Nepal
Tel: 977-1-4153051
Fax: +977-1-4153009
Email: info@nea.org.np
Web: www.nea.org.np

© Nepal Electricity Authority, All rights reserved


Any reproduction in full or in part must mention the title and credit the above-mentioned
publisher as the copyright owner.

Designed and Processed by


Spandan Design Communication, Kupondole, Lalitpur

Printed in Nepal
TABLE OF CONTENTS
MESSAGE FROM MINISTER.. ........................................................... X
MESSAGE FROM SECRETARY......................................................... XI

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
NEA’S PERSPECTIVE...................................................................... 1

1. NEPAL
Grid Connectivity Status.........................................................................................................................2
Local Level Electrification Status (%).................................................................................................. 3
District-wise Household Electrification Status (%) of Nepal...........................................................4
National Status of 33/11 kV Sub Stations................................................................................................. 5
Province-wise Electrification Status......................................................................................................6
Province-wise Household Electrification Status (%) of Nepal..........................................................7

2. Province
Province No. 1
District-wise Electrification Status..................................................................................................... 10
District-wise Household Electrification Status (%) Province no.1..................................................11
Municipality-wise Household Electrification Status (%) Taplejung............................................... 12 v
Municipality-wise Household Electrification Status (%) Panchthar...............................................13
Municipality-wise Household Electrification Status (%) Illam....................................................... 14
Municipality-wise Household Electrification Status (%) Jhapa........................................................15
Municipality-wise Household Electrification Status(%) Morang................................................... 16
Municipality-wise Household Electrification Status (%) Sunsari................................................... 17
Municipality-wise Household Electrification Status (%) Dhankuta............................................... 18

Municipality-wise Household Electrification Status (%) Terathum................................................ 19


Municipality-wise Household Electrification Status(%) Sankhuwasabha.......................................20
Municipality-wise Household Electrification Status (%) Bhojpur.................................................. 21
Municipality-wise Household Electrifications(%) Solukhumbhu.................................................... 22
Municipality-wise Household Electrification Status (%) Okhaldhunga........................................ 23
Municipality-wise Household Electrification Status(%) Khotang..................................................24
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Municipality-wise Household Electrification Status (%) Udayapur................................................ 25

Province No. 2
District-wise Electrification Status..................................................................................................... 28
District-wise Household Electrification Status (%) Province no.2................................................29
Municipality-wise Household Electrification Status (%) Saptari................................................... 30
Municipality-wise Household Electrification Status (%) Siraha......................................................31
Municipality-wise Household Electrification Status (%) dhanusa.................................................. 32
Municipality-wise Household Electrification Status (%) Mahottari.............................................. 33
Municipality-wise Household Electrification Status (%) Sarlahi................................................... 34
Municipality-wise Household Electrification Status (%) Rautahat.................................................35
Municipality-wise Household Electrification Status (%) Bara........................................................ 36
Municipality-wise Household Electrification Status (%) Parsa....................................................... 37

vi Province No. 3
District-wise Electrification Status.....................................................................................................40
District-wise Household Electrification Status (%) Province no.3................................................. 41
Municipality-wise Household Electrification Status (%) Sindhuli.................................................42
Municipality-wise Household Electrification Status (%) Ramechhap............................................. 43
Municipality-wise Household Electrification Status (%) Dolakha.................................................44
Municipality-wise Household Electrification Status (%) Sindhupalchok...................................... 45
Municipality-wise Household Electrification Status (%) Kavrepalanchok....................................46
Municipality-wise Household Electrification Status (%) Lalitpur..................................................47
Municipality-wise Household Electrification Status (%) Bhaktapur.............................................. 48
Municipality-wise Household Electrification Status (%) Kathmandu............................................49
Municipality-wise Household Electrification Status (%) Nuwakot................................................. 50
Municipality-wise Household Electrification Status (%) Rasuwa.....................................................51

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Municipality-wise Household Electrification Status (%) dhading.................................................. 52
Municipality-wise Household Electrification Status (%) Makawanpur............................................53
Municipality-wise Household Electrification Status (%) Chitawan................................................ 54

Gandaki Province
District-wise Electrification Status..................................................................................................... 58
District-wise Household Electrification Status (%) Gandaki Province......................................... 59
Municipality-wise Household Electrification Status (%) Gorkha...................................................60
Municipality-wise Household Electrification Status (%) Lamjung ................................................. 61
Municipality-wise Household Electrification Status (%) Tanahun.................................................62
Municipality-wise Household Electrification Status (%) Syangja................................................... 63
Municipality-wise Household Electrification Status (%) Kaski.......................................................64
Municipality-wise Household Electrification Status (%) Manang.................................................. 65
Municipality-wise Household Electrification Status (%) Mustang.................................................66
Municipality-wise Household Electrification Status (%) Myagdi....................................................67 vii
Municipality-wise Household Electrification Status (%) Parbat.....................................................68
Municipality-wise Household Electrification Status (%) Bagmati...................................................69
Municipality-wise Household Electrification Status (%) Nawalpur................................................70

Province No. 5
District-wise Electrification Status.....................................................................................................74
District-wise Household Electrification Status (%) Province no.5................................................. 75
Municipality-wise Household Electrification Status (%) Parasi......................................................76
Municipality-wise Household Electrification Status (%) Gulmi.....................................................77
Municipality-wise Household Electrification Status (%) Palpa.......................................................78
Municipality-wise Household Electrification Status (%) Rupandehi..............................................79
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Municipality-wise Household Electrification Status (%) Kapilbastu..............................................80


Municipality-wise Household Electrification Status (%) Arghakhanchi....................................... 81
Municipality-wise Household Electrification Status (%) Pyuthan.................................................. 82
Municipality-wise Household Electrification Status (%) Rolpa...................................................... 83
Municipality-wise Household Electrification Status (%) Rukum East............................................84
Municipality-wise Household Electrification Status (%) Dang....................................................... 85
Municipality-wise Household Electrification Status (%) Bardiya...................................................86
Municipality-wise Household Electrification Status (%) Banke......................................................87

Karnali Province
District-wise Electrification Status.....................................................................................................90
District-wise Household Electrification Status (%) Karnali Province.......................................... 91
Municipality-wise Household Electrification Status (%) Rukum West...........................................92
Municipality-wise Household Electrification Status (%) Salyan.................................................... 93
Municipality-wise Household Electrification Status (%) Surkhet.................................................94
viii
Municipality-wise Household Electrification Status (%) Dailekh................................................. 95
Municipality-wise Household Electrification Status (%) Jajarkot.................................................96
Municipality-wise Household Electrification Status (%) Dolpa.....................................................97
Municipality-wise Household Electrification Status (%) Jumla.....................................................98
Municipality-wise Household Electrification Status (%) Kalikot..................................................99
Municipality-wise Household Electrification Status (%) Mugu................................................... 100
Municipality-wise Household Electrification Status (%) Humla...................................................101
Sudurpaschim Province
District-wise Electrification Status................................................................................................... 104
District-wise Household Electrification Status (%) Sudurpaschim Province...............................105
Municipality-wise Household Electrification Status (%) Bajura................................................... 106
Municipality-wise Household Electrification Status (%) Bajhang................................................ 107
Municipality-wise Household Electrification Status (%) Achham................................................ 108

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Municipality-wise Household Electrification Status (%) Doti...................................................... 109
Municipality-wise Household Electrification Status (%) Kailali...................................................110
Municipality-wise Household Electrification Status (%) Kanchanpur...........................................111
Municipality-wise Household Electrification Status (%) Dadeldhura.......................................... 112
Municipality-wise Household Electrification Status (%) Baitadi................................................... 113
Municipality-wise Household Electrification Status (%) Darchula.............................................. 114

3. Transmission Detail
Transmission System Master Plan of Nepal......................................................................................... 115
Existing High Voltage Transmission Lines........................................................................................... 116
Under Construction High Voltage Transmission Lines.................................................................... 117
Under Execution and Planned High Voltage Transmission Lines.................................................... 118
Existing & Under Construction Grid Substation.............................................................................. 119

4. Generation Detail IX
Electricity Generation Power Plants and Projects.......................................................................... 121
IPPs’ Hydro Power Projects (Operation).............................................................................................123
IPPs’ Hydropower Projects (Under Construction) (Financial Closure concluded projects).....126
IPPs’ Hydropower Projects in Different Stages of Development (Without Financial Closure)......131
977-1-4211516
977-1-4211886

Government of Nepal
Ministry of Energy, Water Resources and Irrigation
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Ref.

MESSAGE FROM THE MINISTER


We are fortunate to be born in the country, which is beautiful in many ways I am glad to note that Nepal Electricity Authority (NEA) has taken a com-
and the most remarkable aspect of them is the abundance in vast hydropower mendable initiative to publish for the first time “Nepal Electrification Statistics:
resources. However, the long journey of electricity generation in the country 2019,” which has covered province wise details of electrification along with
has been quite disappointing to us in terms of a low installed capacity and poor the scenario of generation and transmission system of Nepal. I hope that the
per capita electricity consumption. It is highly deplorable to reveal that many report will be extensively welcomed by planners, scholars, people’s represen-
of our villages have not been electrified yet. To the people who live in such tatives and the public as well. In this opportunity, I extend my best wishes to
areas, electricity probably seems a luxury item made for the elites. This plight NEA that it will be successful not only in achieving the target of cent percent
has plunged us into distress and agony tempting us to bring every household electricity access to all people through the expansion of distribution infrastruc-
to light through rapid electrification programs throughout the country and of tures well supported by enough substation capacity throughout the country
course, there is no time to wait. within the given timeframe, but also in improving the quality of life of the
people through safe, secure, stable and also affordable, 24/7 power supply in
In this context, we had issued a Whitepaper as a roadmap of energy, water re- the years to come.
sources and irrigation sector of this country on May 8, 2018, which represented
a long-cherished aspiration of our people with full commitment to accomplish
“Electricity for All” under the present Government’s visionary theme of “Pros-
perous Nepal, Happy Nepali.” We are enthusiastically marching towards it to
make it happen by the year 2022.
Barshaman Pun ‘Ananta’
Minister
Minister for Energy, Water Resources and Irrigation
977-1-4211516
977-1-4211886

Government of Nepal
Ministry of Energy, Water Resources and Irrigation
Fax: 977-1-4211510
Singha Durbar, Kathmandu, Nepal

Ref.

MESSAGE FROM THE SECRETARY


Electricity is the backbone of economy and the Ministry is committed to extend Within next 4 years, government intends to expand electricity access univer-
its every support in implementing the electrification programs through expan- sally with per capita electricity consumption of 700 KWh. This target war-
sion and reinforcement of transmission and distribution facilities throughout rants a massive expansion and reinforcement of the distribution system. It is
the country. in this context, I find this report very timely and relevant which documents
the inventory and information associated with the distribution system of the
While providing electricity for all, massive network expansion not only re- country.
quires a huge budgetary allocation, but also poses a serious challenge to sys-
tem operators and corporate executives in dealing with protection and reliabil- I sincerely appreciate and congratulate NEA for taking initiative to publish
ity issues; technical losses and pilferages; and overall safety aspects. I believe first report of this kind and extend my best wishes to NEA for its continued
that Nepal Electricity Authority will continuously work to increase its capa- contribution in the successful achievement of the electricity target of Govern-
bility in solving and addressing such issues adhering to best utility practices ment of Nepal.
during planning, implementation and operation phase.

Dinesh Kumar Ghimire


Secretary
Ministry of Energy, Water Resources and Irrigation
4
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
NEA’S PERSPECTIVE
Nepal is endowed with huge hydropower resources. The estimated hydro-
power potential is about 83 Giga Watt. There is promising potential of other
renewable energy resources such as solar and wind too, in the country. How- National Electrification by Households 77.82 %
ever, only about 2 percent of these energy sources has been realized. The
90.30 87.39
first Chandrajyoti Hydro-electric power station in Pharping was completed

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
79.77 81.03
75.90
in 1911 and was mainly intended to supply electricity to then Kathmandu
elites for lighting. The domestic consumption, mainly for lighting, is still a 58.90
dominating category in our system. Despite having a huge potential for gen-
erating clean hydropower, more than 22 percent of Nepalese population still
continued to live without grid electricity. Realizing the fact that electricity is 27.03

the most essential driver for socio-economic prosperity of the nation, Minis-
try of Energy, Water Resources and Irrigation (MOEWI), in its Whitepaper
published in 2018, has committed to avail electricity for all and enhance per PROVINCE 1 PROVINCE 2 PROVINCE 3 GANDAKI PROVINCE 5 KARNALI SUDURPASCHIM
capita consumption to 700 Units in the next five years. Nepal Electricity Au- Province Wise Electrification Percentage by Households
thority (NEA), as an executing agency of the Government of Nepal, is com-
mitted to meet this target.

Local Levels* Based on Electrification Percentage NEA has made detailed study of existing electrification scenarios which are
presented in this report. Data has been collected from each ward level so as
Province 0%-5% 5%-35% 35%-65% 65%-90% 90%-100%
to evaluate the existing electrification status of Municipalities, Districts, Prov-
Rural Urban Rural Urban Rural Urban Rural Urban Rural Urban
inces and the country as a whole. The evaluated electrification percentage
Province 1 23 0 11 0 17 6 27 19 10 24
is based on the number of households which have access to electricity from
Province 2 0 0 0 0 8 9 34 48 17 20
NEA system. Ward wise number of households from census 2011 were used
Province 3 6 0 2 0 12 1 28 11 26 33
as basis and the figure for 2019 were derived considering growth rate.
Gandaki 6 0 6 0 8 0 14 7 24 20
Province 5 7 0 4 0 13 3 31 15 18 18
NEA has been relentlessly working to achieve the Government’s target and 1
Karnali 37 6 12 7 3 11 2 1 0 0
has worked out schemes for future expansion of electricity networks, the de-
Sudurpaschim 24 8 12 1 10 5 6 10 2 10
tails of which are numerically presented in this report. We hope the statistics
Total 103 14 47 8 71 35 142 111 97 125
will be useful for executors, planners and also for budgetary allocations to
* Local leves include 6 metropolises, 11 sub-metropolises, 276 municipalities fulfill the Government’s vision of providing “electricity for all” and enhanc-
and 460 gaupalikas. All together, there are 753 Local levels in Nepal. ing “per capita electricity consumption to 700 units” by 2022.
GRID CONNECTIVITY STATUS
Grid Connectivity Status
Grid Connected % 77.49%
Isolated % 0.33%
Total NEA Coverage % 77.82%
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

2 Legend
Isolated
Grid Connected
Local LevelLOCAL LEVEL ELECTRIFICATION STATUS (%)
Electrification Status (%)

117 local levels out of 753 are 0-5% electrified


55 local levels out of 753 are 5-35% electrified

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
106 local levels out of 753 are 35-65% electrified
253 local levels out of 753 are 65-90% electrified
222 local levels out of 753 are 90-100% electrified

Legend
0-5% Electrified-Rural
0-5% Electrified-Urban
5-35% Electrified- Rural
5-35% Electrified- Urban 3
35-65% Electrified- Rural
35-65% Electrified- Urban
65-90% Electrified- Rural
65-90% Electrified- Urban
90-100% Electrified- Rural
90-100% Electrified- Urban
Designated Areas
District-wise Household Electrification Status (%) of Nepal
District Wise Household Electri�ication Status (%) of Nepal
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Legend
4 0% - 5%
5% - 35%
35% - 65%
65% - 90%
90% - 100%
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
5
National Status of 33/11 kV Sub Stations
Province-wise Electrification Status
33/11 kV Substation 33 kV Line 11 kV Line LT Line Dt. Transformer
Under Construc-
Electrifica- Existing Planned
S.N. District Households tion Existing Planned Existing Planned Existing Planned Existing Planned
tion (%)
Capacity Capacity Capacity (km.) (km.) (km.) (km.) (km.) (km.) (Nos.) (Nos.)
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Nos. Nos. Nos.


(MVA) (MVA) (MVA)
1 Province 1 1070519 75.90 32 419.95 15 73.50 18 187.00 815.54 481 6130.96 3457 16955.34 9434 4821 2308
2 Province 2 1056605 79.77 26 349.40 8 64.00 10 240.00 682.42 215 5966.50 1665 13252.59 4210 3819 1338
3 Province 3 1459858 90.30 19 136.70 27 229.20 2 32.00 557.32 40 7788.61 1515 26500.11 3207 7553 1523
4 Gandaki 601920 87.39 18 137.60 12 74.50 9 83.00 623.30 306 3607.53 2126 10524.64 3491 2687 1276
5 Province 5 984341 81.03 28 324.50 17 116.00 19 212.00 1457.43 494 5037.78 3766 22319.67 11215 4788 2178
6 Karnali 339197 27.03 6 23.50 3 9.00 17 106.00 207.00 559 879.02 6171 2197.33 9624 554 1183
7 Sudurpaschim 523808 58.90 21 123.10 11 50.00 10 75.00 562.23 387 4193.31 3152 13397.02 4874 2049 1123
Total 6036248 77.82 150 1514.75 93 616.20 85 935.00 4905.24 2482 33603.71 21852 105146.70 46055 26271 10929

6
Province-wise Household Electrification Status (%) of Nepal
Province Wise Household Electri�ication Status (%) of Nepal

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Legend
0% - 5%
5% - 35% 7
35% - 65%
65% - 90%
90% - 100%
8
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
9
Province No.1
District-wise Electrification Status
Province No. 1
33/11 kV Substation 33 kV Line 11 kV Line LT Line Dt. Transformer
Electrification Existing Under Construction Planned
S.N. District Households Existing Planned Existing Planned Existing Planned Existing Planned
(%) Capacity Capacity Capacity
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Nos. Nos. Nos. (km.) (km.) (km.) (km.) (km.) (km.) (Nos.) (Nos.)
(MVA) (MVA) (MVA)
1 Taplejung 27099 38.74 1 1.50 1 3.00 1 3.00 82.50 23 41.48 267 102.14 852 26 235
2 Pachthar 42198 67.91 3 9.00 1 3.00 1 8.00 58.00 22 145.00 197 193.00 328 62 87
3 Ilam 68775 71.68 3 19.00 1 3.00 1 8.00 73.00 0 367.00 66 1330.00 188 320 145
4 Jhapa 207378 88.10 8 139.00 1 8.00 1 24.00 90.68 18 1396.16 464 4632.80 1271 1329 544
5 Morang 237747 87.87 4 98.40 2 16.00 2 41.00 117.00 40 1023.95 350 3693.72 1595 870 343
6 Sunsari 190662 89.04 4 97.80 0 0.00 2 48.00 100.51 22 887.82 113 2198.65 257 681 171
7 Dhankuta 39213 92.80 2 11.00 1 3.00 1 8.00 34.00 22 281.48 19 1276.03 34 293 24
8 Terathum 21940 74.78 1 3.00 1 8.00 1 8.00 15.00 0 285.00 17 480.00 51 133 9
9 Sankhuwasava 34433 69.54 1 8.00 1 3.00 1 3.00 45.94 57 312.85 368 577.53 654 202 105
10 Bhojpur 34326 44.04 1 3.00 2 11.00 1 3.00 45.00 18 226.00 162 340.00 254 309 99
11 Solukhumbu 23063 14.05 0 0.00 1 1.50 2 11.00 0.00 82 42.00 439 85.00 1267 44 108
12 Okhaldhunga 33176 26.02 1 0.75 0 0.00 2 6.00 33.20 60 314.00 547 473.00 1410 67 114
13 Khotang 36753 54.21 1 1.50 2 6.00 1 8.00 69.00 30 458.53 193 841.02 764 198 152
14 Udayapur 73756 52.89 2 28.00 1 8.00 1 8.00 51.71 87 349.69 255 732.45 510 287 172
Total 1070519 75.90 32 419.95 15 73.50 18 187.00 815.54 481 6130.96 3457 16955.34 9434 4821 2308

10
District-wise Household Electrification Status (%)
District Wise Household Electri�ication Status (%)

PROVINCE No. 1

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 1070519
Electrification Status 75.90%
Existing
132/11kV Substation 0 nos
132/11kV S/S Capacity 0 MVA
66/11kV Substation 0 nos
66/11kV S/S Capacity 0 MVA
33/11kV Substation 32 nos
33/11kV S/S Capacity 419.95 MVA
33kV Line 815.54 km
11kV Line 6130.96 km
LT Line 16955.34 km
Transformers 4821 nos
Under Construction
33/11kV Substation 15 Nos
Substaion Capacity 73.5 MVA
Planned
33/11kV Substation Legend
18 nos 11
Substation Capacity 187 MVA 0% - 5%
33kV Line 481 km 5% - 35%
11kV Line 3457 km
LT Line 35% - 65%
9434 km
Transformers 2308 nos 65% - 90%
90% - 100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

TAPLEJUNG
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 27099


Electrification Status 38.74%
Existing
33/11kV Substation 1 nos
Substation Capacity 1.5 MVA
33kV Line 82.50 km
11kV Line 41.48 km
LT Line 102.14 km
Transformers 26 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 3 MVA
Planned
33/11kV Substation 1 nos
Substation Capacity 3 MVA
33kV Line 23 km
11kV Line 267 km
12 Legend
LT Line 852 km
Transformers 235 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

PANCHTHAR

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 42198
Electrification Status 67.91%
Existing
33/11kV Substation 3 nos
Substation Capacity 9.00 MVA
33kV Line 58.00 km
11kV Line 145.00 km
LT Line 193.00 km
Transformers 62 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 3 MVA
Planned
33/11kV Substation 1 nos
Substation Capacity 8 MVA
33kV Line 22 km
11kV Line 197 km Legend
LT Line 328 km
Transformers 87 nos 0%-5% 13
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

ILLAM
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 68775


Electrification Status 71.68%
Existing
33/11kV Substation 3 nos
Substation Capacity 19.00 MVA
33kV Line 73.00 km
11kV Line 367.00 km
LT Line 1330.00 km
Transformers 320 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 3 MVA
Planned
33/11kV Substation 1 nos
Substation Capacity 8 MVA
33kV Line 0 km
11kV Line 66 km Legend
LT Line 187.50 km
14 Transformers 145 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

JHAPA

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 207378
Electrification Status 88.10%
Existing
33/11kV Substation 8 nos
Substation Capacity 139.00 MVA
33kV Line 90.68 km
11kV Line 1396.16 km
LT Line 4632.80 km
Transformers 1329 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 8 MVA
Planned
33/11kV Substation 1 nos
Substation Capacity 24 MVA
33kV Line 18 km
11kV Line 464 km Legend
LT Line 1270.50 km
Transformers 544 nos 0%-5% 15
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

MORANG
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 237747


Electrification Status 87.87%
Existing
33/11kV Substation 4 nos
Substation Capacity 98.40 MVA
33kV Line 117.00 km
11kV Line 1023.95 km
LT Line 3693.72 km
Transformers 870 nos
Under Construction
33/11kV Substation 2 nos
Substaion Capacity 16 MVA
Planned
33/11kV Substation 2 nos
Substation Capacity 41 MVA
33kV Line 40 km
11kV Line 350 km Legend
LT Line 1595 km
16 Transformers 343 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

SUNSARI

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 190662
Electrification Status 89.04%
Existing
33/11kV Substation 4 nos
Substation Capacity 97.80 MVA
33kV Line 100.51 km
11kV Line 887.82 km
LT Line 2198.65 km
Transformers 681 nos
Under Construction
33/11kV Substation 0 nos
Substaion Capacity 0 MVA
Planned
33/11kV Substation 2 nos
Substation Capacity 48 MVA
33kV Line 22 km
11kV Line 113 km Legend
LT Line 257 km
Transformers 171 nos 0%-5% 17
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

DHANKUTA
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 39213


Electrification Status 92.80%
Existing
33/11kV Substation 2 nos
Substation Capacity 11 MVA
33kV Line 34.00 km
11kV Line 281.48 km
LT Line 1276.03 km
Transformers 293 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 3 MVA
Planned
33/11kV Substation 1 nos
Substation Capacity 8 MVA
33kV Line 22 km
11kV Line 19 km
18 LT Line 34 km
Legend
Transformers 24 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

TERATHUM

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 21940
Electrification Status 74.78%
Existing
33/11kV Substation 1 nos
Substation Capacity 3 MVA
33kV Line 15.00 km
11kV Line 285.00 km
LT Line 470.00 km
Transformers 133 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 8 MVA
Planned
33/11kV Substation 1 nos
Substation Capacity 8 MVA
33kV Line 0 km
11kV Line 17 km
LT Line 51 km
Legend 19
Transformers 9 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

SANKHUWASABHA
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 34433


Electrification Status 69.54%
Existing
33/11kV Substation 1 nos
Substation Capacity 8 MVA
33kV Line 45.94 km
11kV Line 312.85 km
LT Line 577.53 km
Transformers 202 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 3 MVA
Planned
33/11kV Substation 1 nos
Substation Capacity 3 MVA
33kV Line 57 km
11kV Line 368 km
20 LT Line 654 km
Legend
Transformers 105 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

BHOJPUR
BHOJOUR

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 34326
Electrification Status 44.04%
Existing
33/11kV Substation 1 nos
Substation Capacity 3 MVA
33kV Line 45.00 km
11kV Line 226.00 km
LT Line 340.00 km
Transformers 309 nos
Under Construction
33/11kV Substation 2 nos
Substaion Capacity 11 MVA
Planned
33/11kV Substation 1 nos
Substation Capacity 3 MVA
33kV Line 18 km
11kV Line 162 km Legend
LT Line 254 km
Transformers 99 nos 0%-5% 21
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

SOLUKHUMBHU
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 23063


Electrification Status 14.05%
Existing
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0 km
11kV Line 42.00 km
LT Line 85.00 km
Transformers 44 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 1.5 MVA
Planned
33/11kV Substation 2 nos
Substation Capacity 11 MVA
33kV Line 82 km
11kV Line 439 km
22 LT Line 1267 km
Legend
Transformers 108 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

OKHALDHUNGA

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 33176
Electrification Status 26.02%
Existing
33/11kV Substation 1 nos
Substation Capacity 0.75 MVA
33kV Line 33.20 km
11kV Line 314.00 km
LT Line 473.00 km
Transformers 67 nos
Under Construction
33/11kV Substation 0 nos
Substaion Capacity 0 MVA
Planned
33/11kV Substation 2 nos
Substation Capacity 6 MVA
33kV Line 60 km
11kV Line 547 km Legend
LT Line 1410 km
Transformers 114 nos 0%-5% 23
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

KHOTANG
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 36753


Electrification Status 54.21%
Existing
33/11kV Substation 1 nos
Substation Capacity 1.50 MVA
33kV Line 69.00 km
11kV Line 458.53 km
LT Line 841.02 km
Transformers 198 nos
Under Construction
33/11kV Substation 2 nos
Substaion Capacity 6 MVA
Planned
33/11kV Substation 1 nos
Substation Capacity 8 MVA
33kV Line 30 km
11kV Line 193 km Legend
24 LT Line 764 km
Transformers 152 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

UDAYAPUR

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 73756
Electrification Status 52.89%
Existing
33/11kV Substation 2 nos
Substation Capacity 28.00 MVA
33kV Line 51.71 km
11kV Line 349.69 km
LT Line 732.45 km
Transformers 287 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 8 MVA
Planned
33/11kV Substation 1 nos
Substation Capacity 8 MVA
33kV Line 87 km
11kV Line 255 km Legend
LT Line 510 km
Transformers
25
172 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
26
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
27
Province No. 2
District-wise Electrification Status
Province No. 2
33/11 kV Substation 33 kV Line 11 kV Line LT Line Dt. Transformer
Electrification Existing Under Construction Planned
S.N. District Households Existing Planned Existing Planned Existing Planned Existing Planned
(%) Capacity Capacity Capacity
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Nos. Nos. Nos. (km.) (km.) (km.) (km.) (km.) (km.) (Nos.) (Nos.)
(MVA) (MVA) (MVA)
1 Saptari 131491 69.72 4 38.00 1 8.00 1 24.00 151.60 18 564.50 178 1642.00 423 125 246
2 Siraha 128897 77.88 3 57.20 1 8.00 2 48.00 74.50 57 871.36 177 1813.89 354 351 129
3 Dhanusa 151242 83.69 4 88.20 1 8.00 2 48.00 91.76 31 1113.92 132 1992.00 546 414 227
4 Mahotari 124286 90.93 4 41.50 0 0.00 1 24.00 93.42 12 700.30 149 1611.00 426 569 99
5 Sarlahi 152062 90.12 3 47.50 2 16.00 1 24.00 103.97 51 745.02 315 2377.00 552 532 166
6 Rautahat 128368 67.15 3 37.00 1 8.00 1 24.00 60.00 13 629.53 388 1409.00 1294 650 108
7 Bara 128547 80.05 4 32.00 0 0.00 1 24.00 88.00 12 758.78 179 1569.00 305 647 147
8 Parsa 111712 76.20 1 8.00 2 16.00 1 24.00 19.17 21 583.09 147 838.70 310 531 216
Total 1056605 79.77 26 349.40 8 64.00 10 240.00 682.42 215 5966.50 1665 13252.59 4210 3819 1338

28
District-wise Household Electrification Status (%)
District Wise Household Electri�ication Status (%)

PROVINCE No. 2

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 1056605
Electrification Status 79.77%
Existing
132/11kV Substation 2 nos
132/11kV S/S Capacity 90 MVA
66/11kV Substation 2 nos
66/11kV S/S Capacity 97.5 MVA
33/11kV Substation 26 nos
33/11kV S/S Capacity 349.40 MVA
33kV Line 682.42 km
11kV Line 5966.50 km
LT Line 13252.59 km
Transformers 3819 nos
Under Construction
33/11kV Substation 8 Nos
Substaion Capacity 64 MVA
Planned
33/11kV Substation Legend
10 nos 29
Substation Capacity 240 MVA 0% - 5%
33kV Line 215 km 5% - 35%
11kV Line 1665 km
LT Line 35% - 65%
4210 km
Transformers 1338 nos 65% - 90%
90% - 100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

SAPTARI
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 131491


Electrification Status 69.72%
Existing
33/11kV Substation 4 nos
Substation Capacity 38.00 MVA
33kV Line 151.60 km
11kV Line 564.50 km
LT Line 1642.00 km
Transformers 125 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 8 MVA
Planned
33/11kV Substation 1 nos
Substation Capacity 24 MVA
33kV Line 18 km
11kV Line 178 km Legend
LT Line 423 km
30 Transformers 246 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

SIRAHA

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 128897
Electrification Status 77.88%
Existing
33/11kV Substation 3 nos
Substation Capacity 57.20 MVA
33kV Line 74.50 km
11kV Line 871.36 km
LT Line 1813.89 km
Transformers 351 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 8 MVA
Planned
33/11kV Substation 2 nos
Substation Capacity 48 MVA
33kV Line 57 km
11kV Line 177 km Legend
LT Line 354 km
Transformers 129 nos 0%-5% 31
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

DHANUSA
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 151242


Electrification Status 83.69%
Existing
33/11kV Substation 4 nos
Substation Capacity 88.20 MVA
33kV Line 91.76 km
11kV Line 1113.92 km
LT Line 1992.00 km
Transformers 414 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 8 MVA
Planned
33/11kV Substation 2 nos
Substation Capacity 48 MVA
33kV Line 31 km
11kV Line 132 km Legend
LT Line 546 km
32 Transformers 227 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-Wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

MAHOTTARI

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 124286
Electrification Status 90.93%
Existing
33/11kV Substation 4 nos
Substation Capacity 41.50 MVA
33kV Line 93.42 km
11kV Line 700.30 km
LT Line 1611.00 km
Transformers 569 nos
Under Construction
33/11kV Substation 0 nos
Substaion Capacity 0 MVA
Planned
33/11kV Substation 1 nos
Substation Capacity 24 MVA
33kV Line 12 km
11kV Line 149 km Legend
LT Line 426 km 33
Transformers 99 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

SARLAHI
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 152062


Electrification Status 90.12%
Existing
33/11kV Substation 3 nos
Substation Capacity 47.50 MVA
33kV Line 103.97 km
11kV Line 745.02 km
LT Line 2377.00 km
Transformers 532 nos
Under Construction
33/11kV Substation 2 nos
Substaion Capacity 16 MVA
Planned
33/11kV Substation 1 nos
Substation Capacity 24 MVA
33kV Line 51 km
11kV Line 315 km Legend
34 LT Line 552 km
Transformers 166 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

RAUTAHAT

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 128368
Electrification Status 67.15%
Existing
33/11kV Substation 3 nos
Substation Capacity 37.00 MVA
33kV Line 60.00 km
11kV Line 629.53 km
LT Line 1409.00 km
Transformers 650 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 8 MVA
Planned
33/11kV Substation 1 nos
Substation Capacity 24 MVA
33kV Line 13 km
11kV Line 388 km Legend
LT Line 1294 km
Transformers 108 nos 0%-5% 35
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

BARA
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 128547


Electrification Status 80.05%
Existing
33/11kV Substation 4 nos
Substation Capacity 32 MVA
33kV Line 88.00 km
11kV Line 758.78 km
LT Line 1569.00 km
Transformers 647 nos
Under Construction
33/11kV Substation 0 nos
Substaion Capacity 0 MVA
Planned
33/11kV Substation 1 nos
Substation Capacity 24 MVA
33kV Line 12 km
11kV Line 179 km
36 Legend
LT Line 305 km
Transformers 147 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

PARSA

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 111712
Electrification Status 76.20%
Existing
33/11kV Substation 1 nos
Substation Capacity 8 MVA
33kV Line 19.17 km
11kV Line 583.09 km
LT Line 838.70 km
Transformers 531 nos
Under Construction
33/11kV Substation 2 nos
Substaion Capacity 16 MVA
Planned
33/11kV Substation 1 nos
Substation Capacity 24 MVA
33kV Line 21 km
11kV Line 147 km Legend
LT Line 310 km
Transformers 216 nos 0%-5% 37
5%-35%
35%-65%
65%-90%
90%-100%
38
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
39
Province No. 3
District-wise Electrification Status
Province No. 3
33/11 kV Substation 33 kV Line 11 kV Line LT Line Dt. Transformer
Under Construc-
Electrifica- Existing Planned
S.N. District Households tion Existing Planned Existing Planned Existing Planned Existing Planned
tion (%)
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Capacity Capacity Capacity (km.) (km.) (km.) (km.) (km.) (km.) (Nos.) (Nos.)
Nos. Nos. Nos.
(MVA) (MVA) (MVA)
1 Sindhuli 60142 57.31 2 16.00 3 24.00 0 0.00 44.74 0 436.50 87 725.00 146 276 43
2 Ramechhap 45089 81.36 1 3.00 4 27.00 0 0.00 67.00 0 430.00 66 902.00 169 187 23
3 Dolakha 48454 93.35 4 7.50 1 8.00 0 0.00 140.39 0 515.63 78 2163.17 120 386 12
4 Sindhupalchowk 68024 87.85 0 0.00 3 24.00 1 16.00 43.40 25 800.07 155 2331.00 272 642 73
5 Kavlepalanchowk 84169 80.64 0 0.00 3 19.00 0 0.00 18.00 0 634.48 234 1970.06 465 791 182
6 Lalitpur 131387 98.50 0 0.00 2 33.20 0 0.00 0.00 0 482.21 82 1738.58 261 597 129
7 Bhaktpur 78462 97.05 0 0.00 0 0.00 0 0.00 0.00 0 213.69 180 859.16 555 413 195
8 Kathmandu 545648 99.12 0 0.00 0 0.00 0 0.00 0.00 0 1236.87 69 4306.61 150 1799 406
9 Nuwakot 61127 94.38 3 13.60 3 14.00 1 16.00 22.19 15 522.02 57 5115.00 48 508 64
10 Rasuwa 10097 86.89 0 0.00 1 8.00 0 0.00 0.00 0 160.00 37 248.50 91 74 24
11 Dhading 77413 74.71 4 37.00 1 8.00 0 0.00 121.10 0 671.42 205 1980.60 424 392 122
12 Makwanpur 93623 78.59 2 24.60 5 40.00 0 0.00 28.00 0 667.62 125 645.43 226 677 130
13 Chitwan 156223 83.16 3 35.00 1 24.00 0 0.00 72.50 0 1018.10 140 3515.00 280 811 120
Total 1459858 90.30 19 136.70 27 229.20 2 32.00 557.32 40 7788.61 1515 26500.11 3207 7553 1523

40
District-wise Household Electrification Status (%)
District Wise Household Electri�ication Status (%)

PROVINCE No. 3

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 1459858
Electrification Status 90.30%
Existing
132/11kV Substation 5 nos
132/11kV S/S Capacity 210 MVA
66/11kV Substation 12 nos
66/11kV S/S Capacity 456 MVA
33/11kV Substation 19 nos
33/11kV S/S Capacity 136.70 MVA
33kV Line 557.32 km
11kV Line 7788.61 km
LT Line 26500.11 km
Transformers 7553 nos
Under Construction
33/11kV Substation 27 Nos
Substaion Capacity 229.2 MVA
Planned
33/11kV Substation Legend
2 nos 41
Substation Capacity 32 MVA 0% - 5%
33kV Line 40 km 5% - 35%
11kV Line 1515 km
LT Line 35% - 65%
3207 km
Transformers 1523 nos 65% - 90%
90% - 100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

SINDHULI
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 60142


Electrification Status 57.31%
Existing
33/11kV Substation 2 nos
Substation Capacity 16 MVA
33kV Line 44.74 km
11kV Line 436.50 km
LT Line 725.00 km
Transformers 276 nos
Under Construction
33/11kV Substation 3 nos
Substaion Capacity 24 MVA
Planned
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0 km
11kV Line 87 km
42 LT Line 146 km
Legend
Transformers 43 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

RAMECHHAP

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 45089
Electrification Status 81.36%
Existing
33/11kV Substation 1 nos
Substation Capacity 3 MVA
33kV Line 67.00 km
11kV Line 430.00 km
LT Line 902.00 km
Transformers 187 nos
Under Construction
33/11kV Substation 4 nos
Substaion Capacity 27 MVA
Planned
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0 km
11kV Line 66 km Legend
LT Line 169 km
Transformers 23 nos 0%-5% 43
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

DOLAKHA
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 48454


Electrification Status 93.35%
Existing
33/11kV Substation 4 nos
Substation Capacity 7.5 MVA
33kV Line 140.39 km
11kV Line 515.63 km
LT Line 2163.17 km
Transformers 386 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 8 MVA
Planned
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0 km
11kV Line 78 km
44 Legend
LT Line 120 km
Transformers 12 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

SINDHUPALCHOK

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 68024
Electrification Status 87.85%
Existing
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 43.40 km
11kV Line 800.07 km
LT Line 2331.00 km
Transformers 642 nos
Under Construction
33/11kV Substation 3 nos
Substaion Capacity 24 MVA
Planned
33/11kV Substation 1 nos
Substation Capacity 16 MVA
33kV Line 25 km
11kV Line 155 km Legend
LT Line 272 km
Transformers 45
73 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

KAVREPALANCHOK
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 84169


Electrification Status 80.64%
Existing
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 18 km
11kV Line 634.48 km
LT Line 1970.06 km
Transformers 791 nos
Under Construction
33/11kV Substation 3 nos
Substaion Capacity 19 MVA
Planned
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0 km
11kV Line 234 km
46 LT Line 465 km
Legend
Transformers 182 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

LALITPUR

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 131387
Electrification Status 98.50%
Existing
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0 km
11kV Line 482.21 km
LT Line 1738.58 km
Transformers 597 nos
Under Construction
33/11kV Substation 2 nos
Substaion Capacity 33.2 MVA
Planned
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0 km
11kV Line 82 km Legend
LT Line 261 km
Transformers 47
129 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

BHAKTAPUR
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 78462


Electrification Status 97.05%
Existing
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0 km
11kV Line 213.69 km
LT Line 859.16 km
Transformers 413 nos
Under Construction
33/11kV Substation 0 nos
Substaion Capacity 0 MVA
Planned
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0 km
11kV Line 180 km
48 LT Line 555 km
Legend
Transformers 195 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

KATHMANDU

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 545648
Electrification Status 99.12%
Existing
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0 km
11kV Line 1236.87 km
LT Line 4306.61 km
Transformers 1799 nos
Under Construction
33/11kV Substation 0 nos
Substaion Capacity 0 MVA
Planned
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0 km
11kV Line 69 km
LT Line 150 km
Legend 49
Transformers 406 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

NUWAKOT
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 61127


Electrification Status 94.38%
Existing
33/11kV Substation 3 nos
Substation Capacity 13.60 MVA
33kV Line 22.19 km
11kV Line 522.02 km
LT Line 5115.00 km
Transformers 508 nos
Under Construction
33/11kV Substation 3 nos
Substaion Capacity 14 MVA
Planned
33/11kV Substation 1 nos
Substation Capacity 16 MVA
33kV Line 15 km
11kV Line 57 km Legend
50 LT Line 48 km
Transformers 64 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

RASUWA

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 10097
Electrification Status 86.89%
Existing
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0 km
11kV Line 160 km
LT Line 248.50 km
Transformers 74 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 8 MVA
Planned
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0 km
11kV Line 37 km Legend
LT Line 91 km 51
Transformers 24 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

DHADING
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 77413


Electrification Status 74.71%
Existing
33/11kV Substation 4 nos
Substation Capacity 37.00 MVA
33kV Line 121.00 km
11kV Line 671.42 km
LT Line 1980.60 km
Transformers 392 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 8 MVA
Planned
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0 km
11kV Line 205 km
52 LT Line 424 km
Legend
Transformers 122 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

MAKAWANPUR

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 93623
Electrification Status 78.59%
Existing
33/11kV Substation 2 nos
Substation Capacity 24.6 MVA
33kV Line 28.00 km
11kV Line 667.62 km
LT Line 645.43 km
Transformers 677 nos
Under Construction
33/11kV Substation 5 nos
Substaion Capacity 40 MVA
Planned
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0 km
11kV Line 125 km
LT Line 226 km
Legend 53
Transformers 130 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

CHITAWAN
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 156223


Electrification Status 83.16%
Existing
33/11kV Substation 3 nos
Substation Capacity 35 MVA
33kV Line 72.50 km
11kV Line 1018.10 km
LT Line 3515.00 km
Transformers 811 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 24 MVA
Planned
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0 km
11kV Line 140 km
54 LT Line 280 km
Legend
Transformers 120 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
56
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
57
Province
Gandaki
District-wise Electrification Status
Gandaki Province
33/11 kV Substation 33 kV Line 11 kV Line LT Line Dt. Transformer
Electrifica- Existing Under Construction Planned
S.N. District Households Existing Planned Existing Planned Existing Planned Existing Planned
tion (%)
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Capacity Capacity Capacity (km.) (km.) (km.) (km.) (km.) (km.) (Nos.) (Nos.)
Nos. Nos. Nos.
(MVA) (MVA) (MVA)
1 Gorkha 61212 80.63 1 8.00 2 11.00 2 16.00 18.63 47 489.38 400 2093.00 350 184 149
2 Lamjung 43000 94.91 1 8.00 1 8.00 2 16.00 108.00 50 447.00 51 925.20 97 197 69
3 Tanahu 83283 89.33 3 25.60 3 24.00 0 0.00 35.00 0 513.00 119 1300.00 288 415 132
4 Syngha 60726 98.19 3 19.00 0 0.00 0 0.00 95.67 0 372.84 4 805.30 14 351 77
5 Kaski 146788 95.18 1 8.00 1 8.00 0 0.00 14.00 17 870.07 104 2408.00 158 743 152
6 Manang 1405 41.07 0 0.00 1 1.50 1 3.00 0.00 87 8.00 170 23.00 270 2 25
7 Mustang 2884 70.60 1 5.00 0 0.00 1 8.00 20.00 30 131.67 124 197.00 205 44 41
8 Mygdi 27159 67.29 1 0.50 1 8.00 0 0.00 55.00 0 145.00 392 390.00 525 113 86
9 Parbat 36122 99.51 3 17.50 0 0.00 0 0.00 175.00 0 162.09 6 1075.00 29 201 93
10 Baglung 64572 86.51 1 6.00 2 11.00 2 16.00 60.00 57 250.00 281 393.00 590 153 142
11 Nawalpur 74769 66.11 3 40.00 1 3.00 1 24.00 42.00 18 218.48 475 915.14 965 284 310
Total 601920 87.39 18 137.60 12 74.50 9 83.00 623.3 306 3607.53 2126 10524.64 3491 2687 1276

58
District-wise Household Electrification Status (%)
District Wise Household Electri�ication Status (%)

GANDAKI PROVINCE

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 601920
Electrification Status 87.39%
Existing
132/11kV Substation 2 nos
132/11kV S/S Capacity 82.5 MVA
66/11kV Substation 0 nos
66/11kV S/S Capacity 0 MVA
33/11kV Substation 18 nos
33/11kV S/S Capacity 137.60 MVA
33kV Line 623.30 km
11kV Line 3607.53 km
LT Line 10524.64 km
Transformers 2687 nos
Under Construction
33/11kV Substation 12 Nos
Substaion Capacity 74.50 MVA
Planned
33/11kV Substation Legend
9 nos
Substation Capacity 83 MVA 0% - 5%
59
33kV Line 306 km 5% - 35%
11kV Line 2126 km
LT Line 35% - 65%
3491 km
Transformers 1276 nos 65% - 90%
90% - 100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

GORKHA
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 61212


Electrification Status 80.63%
Existing
33/11kV Substation 1 nos
Substation Capacity 8.00 MVA
33kV Line 18.63 km
11kV Line 489.38 km
LT Line 2093.00 km
Transformers 184 nos
Under Construction
33/11kV Substation 2 nos
Substaion Capacity 11 MVA
Planned
33/11kV Substation 2 nos
Substation Capacity 16 MVA
33kV Line 47 km
11kV Line 400 km Legend
60 LT Line 350 km
Transformers 149 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

LAMJUNG

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 43000
Electrification Status 94.91%
Existing
33/11kV Substation 1 nos
Substation Capacity 8.00 MVA
33kV Line 108.00 km
11kV Line 447.00 km
LT Line 925.20 km
Transformers 197 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 8 MVA
Planned
33/11kV Substation 2 nos
Substation Capacity 16 MVA
33kV Line 50 km
11kV Line 51 km Legend
LT Line 97 km
Transformers 69 nos 0%-5% 61
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

TANAHUN
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 83283


Electrification Status 89.33%
Existing
33/11kV Substation 3 nos
Substation Capacity 25.6 MVA
33kV Line 35.00 km
11kV Line 513.00 km
LT Line 1300.00 km
Transformers 415 nos
Under Construction
33/11kV Substation 3 nos
Substaion Capacity 24 MVA
Planned
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0 km
11kV Line 119 km Legend
LT Line 288 km
62 Transformers 132 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

SYANGJA

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 60726
Electrification Status 98.19%
Existing
33/11kV Substation 3 nos
Substation Capacity 19.00 MVA
33kV Line 95.67 km
11kV Line 372.84 km
LT Line 805.30 km
Transformers 351 nos
Under Construction
33/11kV Substation 0 nos
Substaion Capacity 0 MVA
Planned
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0 km
11kV Line 4 km Legend
LT Line 14 km 63
Transformers 77 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

KASKI
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 146788


Electrification Status 95.18%
Existing
33/11kV Substation 1 nos
Substation Capacity 8.00 MVA
33kV Line 14.00 km
11kV Line 870.70 km
LT Line 2408.00 km
Transformers 743 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 8 MVA
Planned
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 17 km
11kV Line 104 km Legend
LT Line 158 km
64 Transformers 152 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

MANANG

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 1405
Electrification Status 41.07%
Existing
33/11kV Substation 0 nos
Substation Capacity 0.00 MVA
33kV Line 0.00 km
11kV Line 8.00 km
LT Line 23.00 km
Transformers 2 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 1.5 MVA
Planned
33/11kV Substation 1 nos
Substation Capacity 3 MVA
33kV Line 87 km
11kV Line 170 km Legend
LT Line 270 km
Transformers 65
25 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

MUSTANG
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 2884


Electrification Status 70.60%
Existing
33/11kV Substation 1 nos
Substation Capacity 5 MVA
33kV Line 20.00 km
11kV Line 131.67 km
LT Line 197.00 km
Transformers 44 nos
Under Construction
33/11kV Substation 0 nos
Substaion Capacity 0 MVA
Planned
33/11kV Substation 1 nos
Substation Capacity 8 MVA
33kV Line 30 km
11kV Line 124 km Legend
LT Line 205 km
66 Transformers 41 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

MYAGDI

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 27159
Electrification Status 67.29%
Existing
33/11kV Substation 1 nos
Substation Capacity 0.50 MVA
33kV Line 55.00 km
11kV Line 145.00 km
LT Line 390.00 km
Transformers 113 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 8 MVA
Planned
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0 km
11kV Line 392 km Legend
LT Line 525 km
Transformers 86 nos 0%-5%
67
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

PARBAT
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 36122


Electrification Status 99.51%
Existing
33/11kV Substation 3 nos
Substation Capacity 17.50 MVA
33kV Line 175.00 km
11kV Line 162.00 km
LT Line 1075.00 km
Transformers 201 nos
Under Construction
33/11kV Substation 0 nos
Substaion Capacity 0 MVA
Planned
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0 km
11kV Line 6 km Legend
LT Line 29 km
68 Transformers 93 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

BAGLUNG

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 64572
Electrification Status 86.51%
Existing
33/11kV Substation 1 nos
Substation Capacity 6.00 MVA
33kV Line 60.00 km
11kV Line 250.00 km
LT Line 393.00 km
Transformers 153 nos
Under Construction
33/11kV Substation 2 nos
Substaion Capacity 11 MVA
Planned
33/11kV Substation 2 nos
Substation Capacity 16 MVA
33kV Line 57 km
11kV Line 281 km Legend
LT Line 590 km 69
Transformers 142 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

NAWALPUR
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 74769


Electrification Status 66.11%
Existing
33/11kV Substation 3 nos
Substation Capacity 40.00 MVA
33kV Line 42.00 km
11kV Line 218.48 km
LT Line 915.14 km
Transformers 284 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 3 MVA
Planned
33/11kV Substation 1 nos
Substation Capacity 24 MVA
33kV Line 18 km
11kV Line 475 km Legend
LT Line 965 km
70 Transformers 310 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
72
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
73
Province No. 5
District-wise Electrification Status
Province No. 5
33/11 kV Substation 33 kV Line 11 kV Line LT Line Dt. Transformer
Electrifica- Existing Under Construction Planned
S.N. District Households Existing Planned Existing Planned Existing Planned Existing Planned
tion (%) Capacity Capacity Capacity (km.) (km.) (km.) (km.) (km.) (km.) (Nos.) (Nos.)
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Nos. Nos. Nos.


(MVA) (MVA) (MVA)
1 Parasi 69109 85.08 2 21.00 1 8.00 1 24.00 69.00 20 440.00 1082 808.00 1934 386 578
2 Gulmi 62020 79.40 2 3.50 2 16.00 2 16.00 111.00 65 185.70 150 788.00 528 356 192
3 Palpa 56700 79.90 1 8.00 2 11.00 1 8.00 118.46 20 226.60 200 2032.00 1400 205 170
4 Rupandehi 195029 87.47 7 105.40 2 16.00 2 48.00 210.81 38 993.00 192 6596.00 598 1094 276
5 Kapilbastu 105125 81.12 4 36.00 2 16.00 0 0.00 84.04 12 800.00 86 2440.19 207 706 178
6 Argakhachi 47869 90.81 1 3.00 3 14.00 0 0.00 252.20 25 202.60 45 595.00 85 190 56
7 Pyuthan 50396 86.32 1 3.00 0 0.00 2 6.00 280.00 40 0.00 36 1850.00 184 161 21
8 Rolpa 45417 39.40 1 3.00 2 11.00 2 16.00 165.00 71 205.00 242 480.00 678 83 88
9 Rukum East 12174 10.51 0 0.00 0 0.00 2 6.00 0.00 45 17.00 225 41.00 76 5 50
10 Dang 134494 79.86 3 46.50 2 16.00 5 40.00 48.00 108 819.00 955 2398.48 3515 596 230
11 Bardiya 91332 94.40 3 28.50 0 0.00 1 24.00 49.67 17 552.00 73 2315.00 150 496 25
12 Banke 114676 77.24 3 66.60 1 8.00 1 24.00 69.25 33 596.88 480 1976.00 1860 510 314
Total 984341 81.03 28 324.50 17 116.00 19 212.00 1457.43 494 5037.78 3766 22319.67 11215 4788 2178

74
District-wise Household Electrification Status (%)
District Wise Household Electri�ication Status (%)

PROVINCE No. 5

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 984341
Electrification Status 81.03%
Existing
132/11kV Substation 2 nos
132/11kV S/S Capacity 42.50 MVA
66/11kV Substation 0 nos
66/11kV S/S Capacity 0 MVA
33/11kV Substation 28 nos
33/11kV S/S Capacity 324.50 MVA
33kV Line 1457.43 km
11kV Line 5037.78 km
LT Line 22319.67 km
Transformers 4788 nos
Under Construction
33/11kV Substation 17 Nos
Substaion Capacity 116.00 MVA
Planned
33/11kV Substation 19 nos
Legend 75
Substation Capacity 212 MVA 0% - 5%
33kV Line 494 km 5% - 35%
11kV Line 3766 km
LT Line 35% - 65%
11215 km
Transformers 2178 nos 65% - 90%
90% - 100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

PARASI
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 69109


Electrification Status 85.08%
Existing
33/11kV Substation 2 nos
Substation Capacity 21.00 MVA
33kV Line 69.00 km
11kV Line 440.00 km
LT Line 808.00 km
Transformers 386 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 8 MVA
Planned
33/11kV Substation 1 nos
Substation Capacity 24 MVA
33kV Line 20 km
11kV Line 1082 km
76 LT Line Legend
1934 km
Transformers 578 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

GULMI

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 62020
Electrification Status 79.40%
Existing
33/11kV Substation 2 nos
Substation Capacity 3.5 MVA
33kV Line 111.00 km
11kV Line 185.70 km
LT Line 788.00 km
Transformers 356 nos
Under Construction
33/11kV Substation 2 nos
Substaion Capacity 16 MVA
Planned
33/11kV Substation 2 nos
Substation Capacity 16 MVA
33kV Line 65 km
11kV Line 150 km
LT Line 528 km
Legend 77
Transformers 192 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

PALPA
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 56700


Electrification Status 79.90%
Existing
33/11kV Substation 1 nos
Substation Capacity 8 MVA
33kV Line 118.46 km
11kV Line 226.60 km
LT Line 2032.00 km
Transformers 205 nos
Under Construction
33/11kV Substation 2 nos
Substaion Capacity 11 MVA
Planned
33/11kV Substation 1 nos
Substation Capacity 8 MVA
33kV Line 20 km
11kV Line 200 km Legend
LT Line 1400 km
78 Transformers 170 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

RUPANDEHI

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 195029
Electrification Status 87.47%
Existing
33/11kV Substation 7 nos
Substation Capacity 105.4 MVA
33kV Line 210.81 km
11kV Line 993.00 km
LT Line 6596.00 km
Transformers 1094 nos
Under Construction
33/11kV Substation 2 nos
Substaion Capacity 16 MVA
Planned
33/11kV Substation 2 nos
Substation Capacity 48 MVA
33kV Line 38 km
11kV Line 192 km Legend
LT Line 598 km
Transformers 79
276 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

KAPILBASTU
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 105125


Electrification Status 81.12%
Existing
33/11kV Substation 4 nos
Substation Capacity 36 MVA
33kV Line 84.04 km
11kV Line 800.00 km
LT Line 2440.19 km
Transformers 706 nos
Under Construction
33/11kV Substation 2 nos
Substaion Capacity 16 MVA
Planned
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 12 km
11kV Line 86 km Legend
LT Line 207 km
80 Transformers 178 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

ARGHAKHANCHI
ARGAKHACHI

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 47869
Electrification Status 90.81%
Existing
33/11kV Substation 1 nos
Substation Capacity 3 MVA
33kV Line 252.20 km
11kV Line 202.60 km
LT Line 595.00 km
Transformers 190 nos
Under Construction
33/11kV Substation 3 nos
Substaion Capacity 14 MVA
Planned
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 25 km
11kV Line 45 km Legend
LT Line 85 km
Transformers 81
56 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

PYUTHAN
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 50396


Electrification Status 86.32%
Existing
33/11kV Substation 1 nos
Substation Capacity 3.00 MVA
33kV Line 280.00 km
11kV Line 0.00 km
LT Line 1850.00 km
Transformers 161 nos
Under Construction
33/11kV Substation 0 nos
Substaion Capacity 0 MVA
Planned
33/11kV Substation 2 nos
Substation Capacity 6 MVA
33kV Line 40 km
11kV Line 36 km Legend
LT Line 184 km
82 Transformers 21 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

ROLPA

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 45417
Electrification Status 39.40%
Existing
33/11kV Substation 1 nos
Substation Capacity 3.00 MVA
33kV Line 165.00 km
11kV Line 205.00 km
LT Line 480.00 km
Transformers 83 nos
Under Construction
33/11kV Substation 2 nos
Substaion Capacity 11 MVA
Planned
33/11kV Substation 2 nos
Substation Capacity 16 MVA
33kV Line 71 km
11kV Line 242 km Legend
LT Line 678 km
Transformers 88 nos 0%-5% 83
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

RUKUM EAST
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 12174


Electrification Status 10.51%
Existing
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0.00 km
11kV Line 17.00 km
LT Line 41.00 km
Transformers 5 nos
Under Construction
33/11kV Substation 0 nos
Substaion Capacity 0 MVA
Planned
33/11kV Substation 2 nos
Substation Capacity 6 MVA
33kV Line 45 km
11kV Line 225 km Legend
LT Line 76 km
Transformers 50 nos 0%-5%
84
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

DANG

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 134494
Electrification Status 79.86%
Existing
33/11kV Substation 3 nos
Substation Capacity 46.50 MVA
33kV Line 48.00 km
11kV Line 819.00 km
LT Line 2398.00 km
Transformers 596 nos
Under Construction
33/11kV Substation 2 nos
Substaion Capacity 16 MVA
Planned
33/11kV Substation 5 nos
Substation Capacity 40 MVA
33kV Line 108 km
11kV Line 955 km Legend
LT Line 3515 km
Transformers 85
230 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

BARDIYA
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 91332


Electrification Status 94.40%
Existing
33/11kV Substation 3 nos
Substation Capacity 28.5 MVA
33kV Line 49.67 km
11kV Line 552.00 km
LT Line 2315.00 km
Transformers 496 nos
Under Construction
33/11kV Substation 0 nos
Substaion Capacity 0 MVA
Planned
33/11kV Substation 1 nos
Substation Capacity 24 MVA
33kV Line 17 km
11kV Line 73 km Legend
LT Line 150 km
86 Transformers 25 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

BANKE

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 114676
Electrification Status 77.24%
Existing
33/11kV Substation 3 nos
Substation Capacity 66.60 MVA
33kV Line 69.25 km
11kV Line 596.88 km
LT Line 1976.00 km
Transformers 510 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 8 MVA
Planned
33/11kV Substation 1 nos
Substation Capacity 24 MVA
33kV Line 33 km
11kV Line 480 km Legend
LT Line 1860 km
Transformers 314 nos 0%-5% 87
5%-35%
35%-65%
65%-90%
90%-100%
88
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
89
Province
Karnali
District-wise Electrification Status
Karnali Province
33/11 kV Substation 33 kV Line 11 kV Line LT Line Dt. Transformer
Electrifica- Existing Under Construction Planned
S.N. District Households Existing Planned Existing Planned Existing Planned Existing Planned
tion (%) Capacity Capacity Capacity (km.) (km.) (km.) (km.) (km.) (km.) (Nos.) (Nos.)
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Nos. Nos. Nos.


(MVA) (MVA) (MVA)
1 Rukum 33284 39.60 0 0.00 0 0.00 2 16.00 0.00 39 156.00 308 376.00 1257 39 109
west
2 Salyan 51687 24.31 1 0.75 0 0.00 2 16.00 46.00 38 250.00 715 416.00 1110 132 171
3 Surkhet 85356 45.64 3 16.75 1 3.00 2 16.00 83.00 90 88.00 575 581.00 1125 160 210
4 Dailekh 54933 21.36 1 3.00 1 3.00 0 0.00 44.00 14 67.00 630 306.00 1035 89 162
5 Jajarkot 34804 8.78 1 3.00 0 0.00 2 11.00 34.00 50 29.66 721 97.13 1341 20 121
6 Dolpa 8497 20.60 0 0.00 0 0.00 2 6.00 0.00 63 46.86 740 33.20 985 21 107
7 Jumla 21876 5.64 0 0.00 0 0.00 2 16.00 0.00 48 67.00 815 105.00 810 0 88
8 Kalikot 27609 15.61 0 0.00 1 3.00 2 16.00 0.00 82 100.50 767 195.00 887 44 92
9 Mugu 10960 18.75 0 0.00 0 0.00 2 6.00 0.00 65 28.00 255 46.00 339 21 38
10 Humla 10191 27.83 0 0.00 0 0.00 1 3.00 0.00 70 46.00 645 42.00 735 28 85
Total 339197 27.03 6 23.5 3 9.00 17 106.00 207 559 879.02 6171 2197.33 9624 554 1183

90
District-wise Household Electrification Status (%)
District Wise Household Electri�ication Status (%)

KARNALI PROVINCE

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 339197
Electrification Status 27.03%
Existing
132/11kV Substation 0 nos
132/11kV S/S Capacity 0 MVA
66/11kV Substation 0 nos
66/11kV S/S Capacity 0 MVA
33/11kV Substation 6 nos
33/11kV S/S Capacity 23.5 MVA
33kV Line 207.00 km
11kV Line 879.02 km
LT Line 2197.33 km
Transformers 554 nos
Under Construction
33/11kV Substation 3 Nos
Substaion Capacity 9 MVA
Planned
33/11kV Substation Legend
17 nos
Substation Capacity 106 MVA 0% - 5% 91
33kV Line 559 km 5% - 35%
11kV Line 6171 km
LT Line 35% - 65%
9624 km
Transformers 1183 nos 65% - 90%
90% - 100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

RUKUM WEST
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 33284


Electrification Status 39.60%
Existing
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0 km
11kV Line 156.00 km
LT Line 376.00 km
Transformers 39 nos
Under Construction
33/11kV Substation 0 nos
Substaion Capacity 0 MVA
Planned
33/11kV Substation 2 nos
Substation Capacity 16 MVA
33kV Line 39 km
11kV Line 308 km Legend
LT Line 1257 km
92 Transformers 109 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

SALYAN

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 51687
Electrification Status 24.31%
Existing
33/11kV Substation 1 nos
Substation Capacity 0.75 MVA
33kV Line 46.00 km
11kV Line 250.00 km
LT Line 416.00 km
Transformers 132 nos
Under Construction
33/11kV Substation 0 nos
Substaion Capacity 0 MVA
Planned
33/11kV Substation 2 nos
Substation Capacity 16 MVA
33kV Line 38 km
11kV Line 715 km Legend
LT Line 1110 km
Transformers 93
171 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

SURKHET
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 85356


Electrification Status 45.64%
Existing
33/11kV Substation 3 nos
Substation Capacity 16.75 MVA
33kV Line 83.00 km
11kV Line 88.00 km
LT Line 581.00 km
Transformers 160 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 3 MVA
Planned
33/11kV Substation 2 nos
Substation Capacity 16 MVA
33kV Line 90 km
11kV Line 575 km Legend
LT Line 1125 km
94 Transformers 210 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

DAILEKH

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 54933
Electrification Status 21.36%
Existing
33/11kV Substation 1 nos
Substation Capacity 3 MVA
33kV Line 44.00 km
11kV Line 67.00 km
LT Line 306.00 km
Transformers 89 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 3 MVA
Planned
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 14 km
11kV Line 630 km Legend
LT Line 1035 km 95
Transformers 162 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

JAJARKOT
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 34804


Electrification Status 8.78%
Existing
33/11kV Substation 1 nos
Substation Capacity 3 MVA
33kV Line 34.00 km
11kV Line 29.66 km
LT Line 97.13 km
Transformers 20 nos
Under Construction
33/11kV Substation 0 nos
Substaion Capacity 0 MVA
Planned
33/11kV Substation 2 nos
Substation Capacity 11 MVA
33kV Line 50 km
11kV Line 721 km Legend
96 LT Line 1341 km
Transformers 121 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

DOLPA

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 8497
Electrification Status 20.60%
Existing
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0.00 km
11kV Line 46.86 km
LT Line 33.20 km
Transformers 21 nos
Under Construction
33/11kV Substation 0 nos
Substaion Capacity 0 MVA
Planned
33/11kV Substation 2 nos
Substation Capacity 6 MVA
33kV Line 63 km
11kV Line 740 km Legend
LT Line 985 km
Transformers 107 nos 0%-5% 97
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

JUMLA
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 21876


Electrification Status 5.64%
Existing
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0.00 km
11kV Line 67.00 km
LT Line 105.00 km
Transformers 0 nos
Under Construction
33/11kV Substation 0 nos
Substaion Capacity 0 MVA
Planned
33/11kV Substation 2 nos
Substation Capacity 16 MVA
33kV Line 48 km
11kV Line 815 km Legend
LT Line 810 km
98 Transformers 88 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

KALIKOT

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 27609
Electrification Status 15.61%
Existing
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0.00 km
11kV Line 100.5 km
LT Line 195.00 km
Transformers 44 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 3 MVA
Planned
33/11kV Substation 2 nos
Substation Capacity 16 MVA
33kV Line 82 km
11kV Line 767 km Legend
LT Line 887 km
Transformers 92 nos 0%-5% 99
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

MUGU
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 10960


Electrification Status 18.75%
Existing
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0.00 km
11kV Line 28.00 km
LT Line 46.00 km
Transformers 21 nos
Under Construction
33/11kV Substation 0 nos
Substaion Capacity 0 MVA
Planned
33/11kV Substation 2 nos
Substation Capacity 6 MVA
33kV Line 65 km
11kV Line 255 km Legend
LT Line 339 km
100 Transformers 38 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

HUMLA

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 10191
Electrification Status 27.83%
Existing
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0.00 km
11kV Line 46.00 km
LT Line 42.00 km
Transformers 28 nos
Under Construction
33/11kV Substation 0 nos
Substaion Capacity 0 MVA
Planned
33/11kV Substation 1 nos
Substation Capacity 3 MVA
33kV Line 70 km
11kV Line 645 km Legend
LT Line 735 km 101
Transformers 85 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
102
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
103

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Sudurpaschim
Province
District-wise Electrification Status
Sudurpaschim Province
33/11 kV Substation 33 kV Line 11 kV Line LT Line Dt. Transformer
Under Con-
Electrification Existing Planned Exist-
S.N. District Households struction Existing Planned Planned Existing Planned Existing Planned
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

(%) ing
Capacity Capacity Capacity (km.) (km.)
(km.)
(km.) (km.) (km.) (Nos.) (Nos.)
Nos. Nos. Nos.
(MVA) (MVA) (MVA)
1 Bajura 28294 11.23 0 0.00 1 3.00 2 11.00 0.00 90 55.00 210 80.00 395 21 130
2 Bajhang 37941 5.99 0 0.00 2 6.00 1 8.00 84.00 93 36.00 660 80.00 930 19 140
3 Achham 53427 24.34 1 3.00 1 8.00 1 8.00 70.00 43 185.00 319 1150.00 423 69 131
4 Doti 41757 66.30 2 4.50 3 6.00 0 0.00 37.00 37 347.10 421 589.00 485 134 108
5 Kailali 170941 87.61 8 65.10 1 8.00 0 0.00 137.73 0 813.17 207 2578.51 289 706 88
6 Kanchanpur 87156 88.50 6 38.50 0 0.00 0 0.00 62.50 0 1428.94 153 5078.71 490 538 195
7 Dadeldhura 29815 49.90 2 6.00 2 16.00 0 0.00 37.00 35 372.00 335 1302.40 550 197 68
8 Baitadi 48016 26.49 1 3.00 0 0.00 4 32.00 97.00 59 584.10 343 1236.00 559 168 163
9 Darchula 26461 29.72 1 3.00 1 3.00 2 16.00 37.00 30 372.00 504 1302.40 753 197 100
Total 523808 58.90 21 123.10 11 50.00 10 75.00 562.23 387 4193.31 3152 13397.02 4874 2049 1123

104
District-wise Household Electrification Status (%)
District Wise Household Electri�ication Status (%)

SUDURPASCHIM PROVINCE

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 523808
Electrification Status 58.90%
Existing
132/11kV Substation 0 nos
132/11kV S/S Capacity 0 MVA
66/11kV Substation 0 nos
66/11kV S/S Capacity 0 MVA
33/11kV Substation 21 nos
33/11kV S/S Capacity 123.1 MVA
33kV Line 562.23 km
11kV Line 4193.31 km
LT Line 13397.02 km
Transformers 2049 nos
Under Construction
33/11kV Substation 11 Nos
Substaion Capacity 50 MVA
Planned
33/11kV Substation Legend
10 nos 105
Substation Capacity 75 MVA 0% - 5%
33kV Line 387 km 5% - 35%
11kV Line 3152 km
LT Line 35% - 65%
4874 km
Transformers 1123 nos 65% - 90%
90% - 100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

BAJURA
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 28294


Electrification Status 11.23%
Existing
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0.00 km
11kV Line 55.00 km
LT Line 80.00 km
Transformers 21 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 3 MVA
Planned
33/11kV Substation 2 nos
Substation Capacity 11 MVA
33kV Line 90 km
11kV Line 210 km Legend
106 LT Line 395 km
Transformers 130 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

BAJHANG

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 37941
Electrification Status 5.99%
Existing
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 84.00 km
11kV Line 36.00 km
LT Line 80.00 km
Transformers 19 nos
Under Construction
33/11kV Substation 2 nos
Substaion Capacity 6 MVA
Planned
33/11kV Substation 1 nos
Substation Capacity 8 MVA
33kV Line 93 km
11kV Line 660 km Legend
LT Line 930 km
Transformers 107
140 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

ACHHAM
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 53427


Electrification Status 24.34%
Existing
33/11kV Substation 1 nos
Substation Capacity 3 MVA
33kV Line 70.00 km
11kV Line 185.00 km
LT Line 1150.00 km
Transformers 69 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 8 MVA
Planned
33/11kV Substation 1 nos
Substation Capacity 8 MVA
33kV Line 43 km
11kV Line 319 km Legend
108 LT Line 423 km
Transformers 131 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

DOTI

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 41757
Electrification Status 66.30%
Existing
33/11kV Substation 2 nos
Substation Capacity 4.5 MVA
33kV Line 37.00 km
11kV Line 347.10 km
LT Line 589.00 km
Transformers 134 nos
Under Construction
33/11kV Substation 3 nos
Substaion Capacity 6 MVA
Planned
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 37 km
11kV Line 421 km Legend
LT Line 485 km
Transformers 109
108 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

KAILALI
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 170941


Electrification Status 87.61%
Existing
33/11kV Substation 8 nos
Substation Capacity 65.10 MVA
33kV Line 137.73 km
11kV Line 813.17 km
LT Line 2578.51 km
Transformers 706 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 8 MVA
Planned
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0 km
11kV Line 207 km Legend
110 LT Line 289 km
Transformers 88 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

KANCHANPUR

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 87156
Electrification Status 88.50%
Existing
33/11kV Substation 6 nos
Substation Capacity 38.50 MVA
33kV Line 62.50 km
11kV Line 1428.94 km
LT Line 5078.71 km
Transformers 538 nos
Under Construction
33/11kV Substation 0 nos
Substaion Capacity 0 MVA
Planned
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 0 km
11kV Line 153 km Legend
LT Line 490 km 111
Transformers 195 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

DADELDHURA
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 29815


Electrification Status 49.90%
Existing
33/11kV Substation 2 nos
Substation Capacity 6.00 MVA
33kV Line 37.00 km
11kV Line 372.00 km
LT Line 1302.40 km
Transformers 197 nos
Under Construction
33/11kV Substation 2 nos
Substaion Capacity 16 MVA
Planned
33/11kV Substation 0 nos
Substation Capacity 0 MVA
33kV Line 35 km
11kV Line 335 km Legend
112 LT Line 550 km
Transformers 68 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

BAITADI

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Total Households 48016
Electrification Status 26.49%
Existing
33/11kV Substation 1 nos
Substation Capacity 3 MVA
33kV Line 97.00 km
11kV Line 584.10 km
LT Line 1236.00 km
Transformers 168 nos
Under Construction
33/11kV Substation 0 nos
Substaion Capacity 0 MVA
Planned
33/11kV Substation 4 nos
Substation Capacity 32 MVA
33kV Line 59 km
11kV Line 343 km Legend
LT Line 559 km 113
Transformers 163 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Municipality-wise Household Electrification Status (%)
Municipalities- Wise Household Electri�ication Status (%)

DARCHULA
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Total Households 26461


Electrification Status 29.72%
Existing
33/11kV Substation 1 nos
Substation Capacity 3 MVA
33kV Line 37.00 km
11kV Line 372.00 km
LT Line 1302.40 km
Transformers 197 nos
Under Construction
33/11kV Substation 1 nos
Substaion Capacity 3 MVA
Planned
33/11kV Substation 2 nos
Substation Capacity 16 MVA
33kV Line 30 km
11kV Line 504 km Legend
LT Line 753 km
114 Transformers 100 nos 0%-5%
5%-35%
35%-65%
65%-90%
90%-100%
Transmission System Master Plan of Nepal
200000.000000 300000.000000 400000.000000 500000.000000 600000.000000 700000.000000 800000.000000 900000.000000

Sutlej
Transmission System Master Plan of Nepal M Trishuli G (65)
Rasuwa Rasuwa Rasuwa
3350000.000000

3350000.000000
Ku

!
(
G
thi

(
d

nkt

Kalapani
i

"
/

r
hi rive
Trishuli (24)
Samundratar
!
(
"
/
G

amc
Tinkar Khola
Trishuli

Mel
Tadi Khola

a
ol Lapsephedi C (22.9)

Pu
ty
a
Kh
Humla Dh
Nuwakot Lik
hu
Kh
(
d
ar ola
ne Sindhupalchok
Kh
ola
Kairang Khola
"
/
Ratmate me
lam
Api Nampa CA ola
chi
rive
Kh Chaln r
an ab
nb an
ya Na
Si la
Darchula
Chameliya (35) HumlaK-Cascade (916)
!
(
G !
(
G

uli
(
d
!
(
chhati Gad (32) Tris
U LotiK (22) Ratmate C-3 (23.7)
Chameliya (85) !
(
G
!
(
G
!
(
G (
d
i
Kal

"
/ Ratmate C-1 (4)

Ind
Humla K II (410)
U Balanch

ra
(
d !
(

wa
G
a

Bajhang U Seti (80)

ti
ol

riv
Kh

Balanch C-1 (43)


!
( !
(
G

er
G
at

U Chameliya (40) Dhading


Gh

Kalphu
(
d Khola
"
/
L Chameliya (20) Balanch C-2 (25) Chapali

Bishnumati
!
(
G !
(
G Balanch
"
/
Bajhang
Humla K-1 (274) Mahes
"
/
!
(
G
h-Kho
la Lapsephedi

ी नदी)
a
Khol

(बागमत
Seti

"
/
"Balaju

ati River
Pithoragarh Chainpur Seti (210) / New Chabel Kathmandu

ा)
"
/

CHINA
MuguK (159.6) "
/

धोबीखोल
/Chabahil
U Kalangad (38.5)
!
( !
(
G
Mugu Karnali !
( "

Bagm
G G
Lainchour

Bishnuma
Namlan (303)
(

hola (
(
d d Mugu
!
(
G
"
/

la
Bajhang C (6)Seti Nadi-3 (80) MuguK C-2 (56)

Kho
Siuchatar Mana "
/

Dhobik
"
/ Rara NP BZ

la
/!( G "
/ Mulpani

ra Kho

ti
U Kalangad " mati

cha
Bajura Rara NP "
/ la
( Bajhang "
/ Kho

Tuku
d an

Aag
Baitadi U Kalangad C (34) Teku Baneshwor (New Airport) Kas

Matatirtha Ha "
/ "
/ Kasan Khola
"
/ nu
ma Bhaktapur
nte Hanuman "
/
Bhaktapur
te
Pancheswor (3240)
Patan
Ri
ve
3260000.000000

3260000.000000
!
(

Kodk
r
"
G
/

Godava
"
/
Pancheswor

u Khola

Pu
ri Khola

ny
Panckkhal

am
ata
"
/ "
/

Riv
Khaptad NP Harsiddhi

er
(
d

sri
Banepa

ng
Na
Syaule C (20)

am
khh
"
/

ati
u
Ruplaigadh (240) Mid K (30) Shey-Phoksundo NP
!
(
G West Seti (750)
(
d !
(
G
Syaule !
(
G BudhiGanga C (45)
"
/ "
/

la
WEST SETI

Kho
(
d Budhi Ganga (20)

irab
Deepayal C (13) !
(
G

a Bha
Khaptad NP BZ Jumla "
/ "
/
Jumla Samjong

Tik
Dadeldhura
Tila Nadi ola
kh
(
d
Jumla C-1 (31) Dolpa
ros
hi

Doti Kalikot
PhukotK (210) Kavrepalanchok

!
(
G
G
Phulkot K (426) Kulekh
ani
Banepa C (7.8)
(
d

"
/Tila-1 (440) Kulekhani-I (60)
Phukot !
(

ki
Achham G Tila-2 (420) /!
" (

nda
!
( (d
G Phukot C (32) Kulekhani-I
G Lalitpur

i Ga
Karnali St-1(184)
Shey Phoksundo NP BZ
!
(

Kal
G
Gh
am
i Kh (
d
Tanakpur
ola Kulekhani-II (32) Kulekhani II- Kulekhani-I C (28.4)

"
/ Makwanpur !
("
G
/ Bagmati Nadi (22)
!
(
G

(
d Jagdulla Kh (307) !
(
G

SR6 (600) !
(
G Thuli Bheri 1 (110)

d
Attariya C-2 (12.3)

li Ga
"
/
!
(
G
UpperK-B (60) !
(
Thuli Bheri (121)

Su
G

River
!
(
G "
/
Hu Jagdulla Bhena

East Rapti
m
la
Ka ThuliBheri (30) Mustang
rn
al
i
(
d
"
/ !
(
G

Sukla Phanta Wildlife Reserve Dunai Kulekhani III (14)


U K (90) Dailekh C-2 (22) L BurbangKh (20) !
( G
Kanchanpur
BetanK (688) !
(
G Dailekh Bheri-1 (617)
(
d (85.39)
Lawan Saharta Bheri !
(
G
"
/ !
(
"
/
G
Jajarkot !
(
G
!
(
Dunai C (25) G Hetauda (
d
NEW ATARIYA BETAN "
/ Jaldigad (21.5) "
/New Hetauda C (13)
Dailekh (
d
!
(
/Attariya
" NalG C-1 (12) G New Hetauda
"
/
Nalgad St. (410)Bheri-2 (256)
Shukla WR BZ L Lohore Kh (20) Saru Kh (100)
!
(
G
!
(
G
"
/ la
Annapurna CA
Kailali !
(
G (
d !
(
G Nalsyau Na
r Kho Kar
ra
Riv
0 1.5 3 6 9 12
ra River

Dailekh C-1 (11) Chera-1 (148.7) Jomsom er


Pahalmanpur KM
Moh

"
/ !
(
G
ana

Ghodaghodi Lake
Ghagha

Kamane

Jha
Dandagau Bheri (128)
"
/ "
/
!
( 1:200,000

rsan
G
Dododhara
Mo
ha

g Kho
na Rukum

ola
3170000.000000

3170000.000000
r Kh
i Sindhuli
"
/

la
yagd Ma
Sani BH-3 (49)
Lumki
Mars Manang
Lete, Titi, Mustang

Na
rsy
! G Sisne
agd
"
/
Sani Bh-4 (40) G "/( !
( !
i Larke Khola

!
(
G
Bafikot Sani Bheri (44.52) (Pelma (90)
G Myagdi Kh A (23)
!
(
U Nar (31)
!
( (
d !
(
Itram Khola

Su
Khola

G G
(
d Pelma -2 (93)

ti
Dhorpatan HR Dana C-1 (24)

Kh
!
( Kali G-Kowan (400)

ola
Suh Bafikot C 3 (29) G
(
d
Khorke

eli
Surkhet
Surkhet C-1 (8)
!
(
G
Nilgiri Kh (38)
Bheri 4 (300)
G !(
Myagdi Kh (57.3)

a)
"
/ !
( !
(
G
!
(
G
!
( G Sup BudhiG (52)

ng (Chin
Surkhet
G Nar Kh (50) Suti Kh (17)
!
(

Tom
Utter Ganga St. (300)
!
( G

ola
!
( Myagdi Thulo Kh (21.3) Nilgiri Kh-II cascade (62) !
(
G
G !
(
G

e Kh

Kho
G
!
( U Dudh Kh (21.16)

ola
Bher
i Rive
U Myagdi (20) G
"
/ !
(
G Marshyangdi-7 (54)
!
( Manasalu CA

Kh
att

la
r G "
/!
!
( Dana !
( (G Dudh Kh (65) Budhi G Prok Kh (420)

Gh

ran

To Keru
Manang (
G G
(
d

Trisu
d !
(

Se
G
"
/ !
( Dana C-2 (48)
!
(
G Manang C (31)

li-Bh
G la

(
d (
d RahuG Mangale (37)
M KaliG (53.5)
Mristi Kh (42) r Kho
!
Shya
( L Manang Marsyangdi (140)

ote
Syar Kh (59.5)

Chhomgrong Khola
Bheri-3 St. ( 480) Rolpa C-1 (10.48)
Tadhekhani C-1 (38)
!
(
G
G
!
(

Kos
!
(
G
!
( Myardi Kh (30) U BudhiG
G

Seti river
G

i
"
/ U Myagdi-I (80) (
d !
(
G
n Kh
ola
!
(
"
/
GG!
(
G
!
(
Mainatara G !
(
Tadhekhani C-2 (24)
!
( G Landruk Modi (86.6)
Madme Kh (24)
Budhi
hilu Gandk Nadi (91)
Ba Bardia NP
"
/ U RahuG (48.5)
!
( Up Seti (20) !
(
G Nyadi-Phidi (24) Ch
(
d
DandakhetDurbang Myagdi Kh (25)
G
Bardiya rdiya Salyan !
(
G !
(
G

Mardi Kohla
Gumda C-2 (8.7)
NP U Marsyangdi -2 (600) Khudi C-1 (24)
!
(

Khola
To Barelly G
BZ Rahughat (40) Karuwa (36) U Madi ( 33) G !
((
dSuper Nyadi (40.27) U BudhiK (203) Bhote
Kosh
Bheri Babai D (48)
!
(
G !
(
G"
/ !
(
G
/!
U Madi(
"(
U Khudi-A (27.8)
!
( !
(
G
i

Modi
G
d

Mid
U KaliG (72.5)Rahughat
G
To Barelly Burtibang !
( Dordi Dudh Kh (20.8)
(
d Kaski G

im
Rolpa
/(d !
(
U Madi C (67)
Baglung
" !
(
G Nyadi i Kh (30) G

Kho
Sharda Babai St. (93) Myagdi Kh (32) !
(
G New Modi C-2 (25)
ali

Ngad
!
(
Burtibang C-2 (47)
ma Seti Nadi (30) Super Madi (44)
!
( Himchuli Dordi (57)

la
G
Karn

G
!
( !
(

Madi River
G Beni KaliG (50)

di Khola
U Modi A (42) G
!
(
G
"
/ rdi
!
(
G Lamjung
!
(
G
Khudi !
(G
U Marsyangdi- (138) !
(G
Gorkha
U Budhi G (254)
"
/d
( G ( !
(
(
d "
/ d U Khudi (26)
(
d !
( G

Darau
Super Dordi Kha (49.6)
(
d
Badigad Kh (21)
"
/ C (20)
New Modi Pokhara G !
( Se
C-3 (25) Khudi C-3 (12.1) Khudi C-2 (16)
U Dordi A (25) !( (
d
!
(
G U Seti-I (21) !
(
G

L Modi Kh (20) Modi Kh


Krishnasar CA ti Riv G Kirtipur C-2 (12) Tatopani Kh (24.3) Sanjen Kh (78)
Jhimruk C-2 (41)
(
d er
(
d d!
( (
G"
/ BudhiG Ka (130) !
( !
(
(
d "
/
!
(G Phedithanti Kirtipur C (16.3)
Kirtipur !
(
G
G G
!
(
G
Mathillo Langtang (24.35)
Tadhekhani C 3 (20)
Kusma Kuiredanda (
d Rasuwagadhi (111)
!
(
Kohalpur "
/ C-1 (30)
Burtibang "
/ /L Modi Kh
" Pokhara !
(
G Marsyangdi Besi (50) Gumda C-1"
/(16) Ilep Tatopani Kh (25)
G
ng Khola ale
Hapure (

g Khola
"
/ d "
Madi Seti (86)
(
d !
(
Rasuwa Langta x

"
/ Kushma C-1 (22)
/
Lekhnath !
(
G
G
Gumda !
(
G
Chilime
!
Udipur C-2 (16)
"
/ Dordi Kh (27) Super Aankhu Kh (25.4) (
G
"
/ d!
((
G

Mailun
Parbat
d"/ (
d

ina)
Banke NP ( Udipur!
(
G !
(
G
Chilime C-1 (34)
!
(
G
Lantang Kh St. (310)

u
Chepe C (51)
!
(

Ch
Lekhnath C-1 (10.5)
LEGEND

se (Ch
U Trishuli-2 (102) G
Begnas Rupa St P(150)

ar
M Marsyangdi (70)
!
(

ol
i Khola
"
/ U Jhimruk St. (100)
! !
( BudhiG Kha (260) G

sh
( "

Kh
Jhimruk Suraud /
G
G
!
( "
/

ng
U Ankhu Kh (35)
!
( !
(

u
G
Tulsipur Madhya Marsyangdi "
/ G

kh
G

Ro
"
/ !
(
G Ankhu Langtang NP

An

Tamba Kosi
Pyuthan
U Daraudi

To Lat
Banke (
d Shyangja
Marsyandi 3(42) (
d Trisuli Khola
SetiKh (27.7) Ankhu Khloa Nyam
(
d

i
!
( Daraudi C-2 (53) Aph U Trishuli-1
Nyam(216)

dak
Jhimruk C-1 (18) Gulmi

chi river
G al Khola
"
/ !
( KhoKh(42.9)
Ankhu !
( Trishuli 3B C-2 (49)

阿龙阿
G

hi Gan
la G
NEPAL HYDROPOWER PLANTS "
/ !
(G
!
(
कालीगकी नदी

Seti Khola

Melam
Tamghash Diyong Khola

Bud
Lu ola
bd
g Kh U Lapche Kh (52)
Banke Kusum (
d i Kh
tan U Trishuli-3A (60) Bramhmayani (40)
!
ola
NP BZ "
/ "
/ KaliG C-2 (10) Akhu Kh-2 (20) Kin
Trishuli 3B!
(
G (
G
!
(
G
CONSTRUCTION LICENSE APPLICATION Phulbari Syangja
!
(
G
"
/ (
d U Nyasim Kh (43)
U Trishuli 3B (37) Trishuli 3B C-1 (25)
G !(
Ghorahi s/s Damauli
(
d !
(
G Lapche Kh (160)
!
( !
( !
(

hi
Ankhu Kh C (7) G G G"
/

te Kos
"
/ "
/ M Trishuli G (65) Super Melamchi (24.7) Up Balephi Lapche
/!
(G Nyasim (35)
Dang "
/ !
(
G " Natang

Bho

Naktok Khola
(
d !
( !
(G Qu

Bho
"
/ (
d New Damauli "
/
G
(
d

te Kos
Tanahu Ma
rsy Dhading Samundratar C (47.8) Jum Kh (62)
!
(
G
SURVEY LICENSE APPLICATION Sandhikharka Kali Gandaki C (15.3)
Andhi Kh St (180) Dumre
ang
New Marsyangdi
di Trishuli (24)
"
/
Balephi Kh (42) Upper Balephi C (7)
Imja Khola
!
( "/ Sindhupalchok

hi
KaliG A (144) Tanahu Seti (140)
Kali Gandaki
G
!
( !
( "
/ !
(
"
/
G Khol
a
Samundratar !
(
"
/
G Rolwaling Kh-2 (88) Sagarmatha NP

Ta
G

r
G Tadi

rive
Trishuli !
( Bhotekoshi C (35.7) Rolwaling Kh (22)

mo
G !
Likhu
Rap
Lamahi
Arghakhanchi
Ramdi-Malung Khola G
!
( (
d !
( (
G Lang

r Riv
ati
ti Tilakpur-murchaur G M BhoteK-1 (40)
muc
Marsyangdi (69)Marsyangdi-
he Kho
Ra

raw
Balephi (23.5) !
(G U Chaku A (22.2)

er
la
"
/
md

!
( (
d "
Balephi (50) G/

Ind
"
/ Nuwakot U TamaK 456
3080000.000000

3080000.000000
G
!
(
i-Kh

Dharne
Super Trishuli Galchhi (100) BudiG (1200)
!
(
G
CONSTRUCTION LICENSE !
(
Lapsephedi C (22.9) G L Balephi
!
( Gaurishankar CA !
(
G
"
/

shi
ola

G "
/
Dang Deukhuri foothill forests and west Rapti wetlands Rampur valley !
(G
Up TamakoshiKhani Kh -1 (40)

Ko
Madhya BhoteK (102)
Seti Khola
Ratmate

Khola
(
d (
d (
d !
( !
(

dh
G G

Du
New Marsyangdi C-1 (10.4) Ratmate C-2 (3.3) Trishuli Galchhi (75) Balephi C (33.6) Sagu Kh (20) Khani Kh (Dolakha) (30)
Palpa L Seti (Tanahu) (92) Dhodeni !
(
G
uli
Tris (
d Nagarjun NP
Shivapuri "
/ Dolakha !
(
G !
(
G

!
(
G Chhapdanda (
d
Ratmate C-3 (23.7)
L Balephi (20) Barhabise
Khare (24.1) DudhK 10 (75) Kimathanka- Arun (434)
!
(
G
IN OPERATION Najmure St. (300) Ratmate C-1 (4)
(
d !
(
Sagarmatha
!
(
NP BZ
d !
( (
G

Bishnumati
G
!
(
G
Khola
Kalphu
"
/ !
(G !
(
G (
d !
(
G
G बण
नदी Kimathanka C (9)

Dudh Kosi
"
/ Bahrabise C (26.25) Singati C-2 (35)
"
/
Chapali "
/
i Ma
(
d Kali Gandak he
sh
-Kh Lapsephedi Lamosangu Singati L Barun Kh (132) Kanchenjungha CA
New Butwal C (7.6) ola
"
/
Kathmandu
"
/
Chabahil (d (
d Solukhumbu
!
(
GU-Dudhkoshi
!
(
G U Tamor A (72)
!
(

Isu
Barandabhar forests and wetlands Lamosangu C (9) Singati C-1 (51) G
"
/ New Chabel
//
" " Nupche Likhu (21.5) "

wa
/ Bhaktapur / Makalu Barun NP
!
( / "
DudhK-6 (83) "
/
G
GOVERNMENT RESERVED PROJECT Chauraha
( !
(Kalika KaliG (50)
G Matatirtha "
/ "
/ Mulpani
!
(

Kh
"
/ d "
/ "
/"
G
G!
!
((
G
U Arun (
d

ola
"
/ Butwal "
/
Motipur New Butwal C-2 (19.2) ni
Baneshwor /
" !
(

R
G
Bharatpur (New Airport)
aya U Tamor C (9.5)
Luja Kh (24.8)

RIVE
Nar
"
/ "
/ "
/ Panckkhal "
/

a
U Arun (335)
Arung Khola

gk
Shivapur Patan Garjyang

an
" yani
"
/ Ikhuwa Kh (30)
/ Banepa "
/

ARI
Nara
(
d

u Dr
Nawalparasi
"
/ Harsiddhi
Super Inkhu Kh (22)
!
(

Sun
Likhu -1 (77)
Khaireni G

Nakhhu
LADH
Arun-4 (300)
Kapilbastu Jagdishpur Reservoir "
/ !
( Super Tamor (155)Ghunsa Kh (98.54)
yani
!
(

nk
Nara Khimti Shivalaya C (30.2) G
!
( ow
G
!
( !
(

Kos

a
Sankhuwasabha
!
( !
(

Hu
G
SURVEY LICENSE

Tamako
Isuwa Kh (97.2) G

ngk
G Taplejung G G
hn
ani Khmiti Shivalaya St. (200)
!
( !
(

i
Naray G
!
(

u Dra
ka Nawa Phulchoki Mountain forests G

La lparas Chitwan NP BZ aya


ni
"
/
G
!
(
DudhK-4 (350)
!
(
G Apsuwa I (23)
!
(
G !
( !
(
G G
Simbuwa Kh (45)

shi
Chapagaon "
/!
Nar Kulekhani
( !
(

Hink
G
G Makalu Barun NP BZ "
/
i

!
(
Narayan

G
ow Khimti II (48.8)
Dun
To
hn
Rupandehi "
/ i fores gre
!
(
Likhu -2 (55) Dudhkoshi-4
(
d
M Hongu Kh B(22.9)
!
(
Palun Kh (21)
!
(
Tamor
G G
ts (
d G Apsuwa Kh (50) !
( !
(G U Simbuwa Kh (46)
((
G
ka
Narayani
Kulekhani-IKulekhani-I (60) !
(
G Likhu Kh- A (51) Tingla C-5 (45.9)
Inkhu Kh (20) G
Tingla C-1 (13)
! d
!
( (
d!
(
G
G
!
(
!
(
G
UNDER CONSTRUCTION La Chitawan Bishhazarilake
!
(
"
/G Lalitpur
Banepa C (7.8)
(
d "
/ !
(
G !
( (
G G Arun-3 (300)
d
M Mewa C ( 49)
"
/
G
Simbuwa Kh (53.7)
To "
/ Kulekhani-II (32)Kulekhani II- Kavrepalanchok
(
d Likhu DudhK-5(48)Inkhu (20)
MEWA
Re d ( Bagmati Nadi (22) Ramechhap New Khimti C (15)
New Khimti !
( !
(
Sankhuwa Kh-1 (35) "
/ Arun-3 C (3.3)
Bardaghat Chitwan NP
u
!
(
"
/
G Kulekhani-I C (28.4)
!
(
SunK-3 (536)
!
(
G"
/ G Khimti -I (60)
Likhu C (31.5)
G G
!
(
G
G
!
(
G
!
( !
(
G "
/ M Mewa (49)
!
(
G
Farmlands in Lumbini area
(
d
TamaK-3 (650) Likhu Kh (30) DudhK-4 (46) (
d Inkhu
!
( !
(
G

G!
(
"
/ Solu (23.5) G G

Lumbini Gandak Nahar


Kulekhani III (14) SunK-3 C ( 27.6)
!
( (
d !
( Inkhu (18.6) Sankhuwa Kh (25)
!
(
G
!
G
(
d HYDROPOWER CLUSTERS BELOW 20 MW (
G Hetauda Likhu-4 (52.4) "
/ Mewa Kh (50) Super Kabeli (20)
Gandak (15)Gandak-
Makwanpur "
/ d ( !
(
G
Tingla "
C-3 (27) L Solu (82)
/ SitalPati !
(
G !
(
G M Tamor (54)

"
/
New Hetauda C (13) / !
" (
G

!
(
"
/
G Tingla 2 L Arun (400) (
d Kabeli 3 (22)
Parsa WR BZ
Kamane
L Likhu (28)
Solu Kh (DudhK) (86) DudhK-2 (240)
(
d !
(
G Sabha Kh C (46.5) Tamur valley and watershed !
(
G

"
/
Kar
ra Riv
er !
(
G
Aayu Malun Kh (23.2) !
(
G!
(
G
Sitalpati C (79)
ola Tamor Mewa (128)
(
d
Parsa Wildlife Reserve !
(
G bh
a Kh
"
/
Hangpang C (23) !
(
G U Kabeli (22)
SunK 2 St. (1100) (
d Sa
!
(
G
Tingla C-4 (9.5) Hangpang (Change)
NEPAL SUBSTATIONS / !
" ( G Okhaldhunga
(
d "
/
"
/ (
d (
d
KhandbariBaneshwor C (27.9) Kabeli
Sunkoshi St2
Tingla C-6 (20)
Okhaldhunga
"
/
!
(
G
Kabeli C (113)
Kabeli B - 1 (25)
"
/ (
d !
(G
Amlekhgunj Baneshwor Basantapur C-2 (24.7) L Tamor (49.5) Kabeli-A 37.6
hpur

"
/ FUTURE_S/S Parsa
"
/ !
(
G
"
/
Pinasegaht LILO
rak

Sindhuli (
d
Go

Basantapur C-1 (30.5)


Sun
Kos
To

"
/ UNDER_CONSTRUCTION_S/S i Rive
r Bhojpur (
d L Hewa (21.6) (
d
Pathlaiya (
d "
/ Terhathum Phidim C-2 (23) !
(
G Phidim C (24.7)

"
/ Pikhuwa C (22.5) New Basantapur
IN_Ramnagar
Na

Khotang
"
/Simra "
/
ra

"
/ EXISTING_S/S
INDIA
ya

Phidim
Panchthar
"
/ DudhK St. (300)
(
ni

d
hpur

Chandranigahapur "
/ !
(
G
DudhK C (9.3)
"
/ DudK
rak

Bara
Parwanipur
To Go

Tamor St. (765)


"
/ !
(
G

अण
2990000.000000

2990000.000000
नदी

ur
Birgunj

m
TRANSMISSION LINES

Ta
"
/ Dhankuta
iya
rs
Si

Rautahat
Sarlahi

132 kV HTLS IN_Raxual New Dhalkebar- Kosi


"
/ "
/ Sun
Ilam
(
d
IllamIllam C (131)
"
/
Udayapur
(
d Mai Valley forests
"
/ Ilam C-2 (18)

Kamala River
220 kV HTLS Dharan "
/
Mahottari
Soyak
!
(G Tapping
Deumail Kh (30)

er
"
/ Mai (22)

Riv
Dhanusa New Mirchaiya !
(
G

hu
PROPOSED 400kV

ard
IN_Bettiah

Sh
PROCTED AREAS "
/ Dharan forests
"
/
"
/ Siraha Itahari
PROPOSED 220kV IN_Bettiah

Khola
"
/ Lahan
HUNTING RESERVE Janakpur "
/

Mawa
Damak

r
R

ve
)
नदी

Ri
ti Rive
uW
Koshi Tappu Wildlife Reserve and Koshi Barrage "
/ Anarmani

मती

ya
Urlabari forest groves

ali
(बाग

Bakra Khola
"
/
PROPOSED 132 kV

pp

Seu

sh
Sunsari

Ke
er

Ta
ti Riv
Rupani

mai
WILDLIFE RESERVE "
/ "
/ Inaruwa

hi
ma
Morang
Jaleswor

kankai
"
/ Kh

Kos
Jaynagar "
/ "
/

er
Bag

i Riv
an Jhapa
do
Duhabi

sh
Saptari Ri
ve

Ko
EXISTING/UNDERCONSTRUCTION 400 kV Coordinate System: MUTM EVEREST 1830 Tx / Gx / SS: - DoED Gx lists (Jan 2018) "
/
r(N
ad
Duhabi (Diesel) (39)
"
/
BUFFER ZONE Projection: Transverse Mercator Rajbiraj r i)
!
(G

ur
Naha
- WSP collected information

Sitagunj Branch
Pump

rp
Koshi
Datum: Everest Bangladesh

fa
Protected Areas: Department of National Parks & Wildlife Conservation (2016)

za
False Easting: 500,000.0000 "
/

uz
Rivers / Lakes: https://data.humdata.org/dataset/nepal-watercourses-rivers Kataiya
EXISTING/UNDERCONSTRUCTION 220 kV
/fli6«o k|;f/0f lu|8 sDkgL lnld6]8 Bhadrapur

M
CONSERVATIONAL AREA

ola
False Northing: 0.0000

To
"
/

li kh
al)
r(Can
Central Meridian: 84.0000

hu
Naha
Pump

ma
Scale Factor: 0.9999 0 4.5 9 18 27 36 Koshi
"
/
NATIONAL PARK Latitude Of Origin: 0.0000 KM Rastriya Prasaran Grid Company Limited Biratnagar
EXISTING 132 kV
Units: Meter
1:550,000 -An Undertaking Company of Government of Nepal_

To
Purn

Khola
Ratua
ea
To
Pur

Si
ng
ne

hy
ah
a

i Ri
ve
r
200000.000000 300000.000000 400000.000000 500000.000000 600000.000000 700000.000000 800000.000000 900000.000000
Existing High Voltage Transmission Lines
S.N 132 kV Transmission Line Type of Ckts Length Circuit km Conductor 27 Mahendranagar-Gaddachauki Single 12 BEAR
Type 28 Marsyangdi -M. Marsyangdi Double 80 CARDINAL
1 Anarmani-Duhabi Single 75.76 BEAR 29 Damak-Godak Double 70 BEAR
2 Kusha-Katiya(India) Single 15 BEAR 30 Kusum-Hapure Single 20.03 BEAR
3 Duhabi-Lahan-Chandraniga- Double 608 BEAR 31 Bhulbhule- Middle Marsyangdi P/S Single 22 BEAR
hapur-Pathalaiya-Parwanipur/
32 Chameliya-Attaria Single 131 BEAR
Pathalaiya- Hetauda
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

33 Raxual-Parwanipur (Cross Bor- Single 16 BEAR


4 Hetauda-KL2 P/S Double 16 BEAR
der-Nepal Portion)
5 Bharatpur-Marsyangdi P/S Single 25 DUCK
34 Kusaha-Kataiya (Cross Border-Nepal Single 13 BEAR
6 Hetauda-Bharatpur Single 70 PANTHER Portion)
7 Marsyangdi P/S-Suichatar Single 84 DUCK 35 Dumre Damauli Double 46 BEAR
8 Suichatar-Matatirtha- KL2 P/S Double 72 BEAR 36 Lamahi Ghorahi Double 25 BEAR
9 Suichatar-Balaju Single 5 BEAR 37 Godak Phidim Double 85.772 BEAR
10 Balaju-Chapali-New Bhaktapur Double 36 BEAR Total 2,996.0
11 New Bhaktapur-Lamosangu Double 96 BEAR
12 Lamosangu-Khimti P/S Single 46 BEAR S.N 400/220 kV Transmission Line Type of Ckts Length Circuit km Conductor
13 Lamosangu-Bhotekoshi P/S Single 31 BEAR Type
14 Bharatpur-Damauli Single 39 WOLF 1 Dhalkebar-Muzzaffarpur Cross Border Double 78 MOOSE
15 Bharatpur-Kawasoti-Bardghat Single 70 PANTHER Line
16 Bardghat-Gandak P/S Double 28 PANTHER 2 Khimti- Dhalkebar 220 kV Transmis- Single 75 BISON
sion Line
17 Bardghat-Butwal Double 86 BEAR
Total 153.0
18 Butwal-KGA P/S Double 116 DUCK
19 KGA P/S-Lekhnath Double 96 DUCK
116 20 Lekhnath-Damauli Single 45 WOLF
21 Lekhnath-Pokhara Single 7 DOG
22 Pokhara-Modikhola P/S Single 37 BEAR
23 Butwal-Shivapur-Lamahi-Kohalpur Double 430 BEAR
24 Lamahi-Jhimruk P/S Single 50 DOG
25 Kohalpur-Bhurigaun-Lumki Single 88.33 BEAR
26 Lamki-Pahalwanpur-Attariya-Ma- Double 203.12 BEAR
hendranagar (Lalpur)
Under Construction High Voltage Transmission Lines
S.N 66 kV Transmission Line Type of Length C Conductor S.N. 132 kV Transmission Line Type of Length Conductor
Ckts ircuit km Type Ckts Circuit km Type
1 Chilime P/S-Trishuli P/S Single 39 WOLF 1 Thankot-Chapagaon Double 57 BEAR
2 Trisuli P/S-Balaju Double 58 DOG 2 Phidim-Amarpur Double 27 BEAR
3 Trisuli P/S-Devighat P/S Single 4.56 WOLF 3 Singati-Lamosangu Double 80 BEAR
4 Devighat P/S-Chapali Double 58.6 DOG 4 Solu Corridor Double 180 CARDINAL

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
5 Chapali-New Chabel Double 10 DOG 5 Butwal-Lumbini Double 44 BEAR
6 New Chabel-Lainchaur Single 7 XLPE Cable 6 Burtibang-Paudi Am- Double 164 BEAR
7 Balaju-Lainchor Single 2 PANTHER arai-Tamghas-Sandhikharka-Motipur
8 Balaju-Siuchatar-KL1 P/S Double 72 WOLF 7 Ramechap-Garjyang-Khimti Double 62 BEAR
9 KL 1 P/S-Hetauda-Birgunj Double 144 WOLF 8 Dordi Corridor Double 20 BEAR
10 Suichatar-Teku Single 4.1 BEAR 9 Modi-Lekhnath Double 84 BEAR
11 Suichatar-New Patan Double 13 WOLF 10 Bardaghat-Sardi Double 40 BEAR
12 Teku-K3 (underground) Singlecore 2.8 XLPE Cable 11 Kushaha- Biratnagar Double 46 BEAR
13 Suichatar-K3 Single 6.9 XLPE Cable 12 Kusma-Lower Modi Single 7 BEAR
14 Bhaktapur- Baneshwor-Patan Single 11 LGJ 120 /WOLF 13 Raxual-Parwanipur 2nd Ckt Single 16 BEAR
Line(Cross Border-Nepal Portion)
15 Bhaktapur-Banepa-Panchkhal-Sun- Single 48 LGJ 120
koshi P/S 14 Kusaha-Kataiya 2nd Ckt Line (Cross Single 13 BEAR
Border-Nepal Portion)
16 Indrawati- Panchkhal Single 28 PANTHER
15 Samundratar Trishuli 3B Double 26 BEAR
Total 508.96
Total 866

117
S.N. 220 kV Transmission Line Type of Length Circuit km Conductor 9 Trishuli 3B - Ratomate 220 kV Double 70 MOOSE
Ckts type
10 Lekhnath-Damauli 220 kV Double 90 MOOSE
1 Khimti-Dhalkebar 2nd Ckt Line Single 75 BISON
11 New Butwal/Lamahi/New Kohalpur/ Double 440 MOOSE
2 Hetauda-Bharatpur Double 146 BISON New Atariya 400 kV
3 Bharatpur-Bardghat Double 150 BISON Total 1878
4 Koshi Corridor Double 286 MOOSE
5 Marsyangdi-Kathmandu Double 170 MOOSE
S.N. 132 kV Transmission Line Type of Length Circuit km Conductor
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

6 Kaligandaki Corridor Double 220 MOOSE Ckts Type


7 Marsyangdi Corridor Double 230 MOOSE 1 Dhalkebar-Loharpatti Double 40 BEAR
8 Chilime-Trishuli Double 54 BISON 2 Dhalkebar- Balganga Double 40 BEAR
Total 1,331
3 Dadakhet- Rahughat Double 50 BEAR

S.N. 400 kV Transmission Line Type of Length Circuit km Conductor Type 4 Ghorahi-Madichaur Double 74 BEAR
Ckts 5 Nawalpur Salimpur Double 40 BEAR
1 Hetauda-Dhalkebar-Duhabi Double 570 MOOSE 6 Pathlaiya Simraungaudh Double 50 BEAR
2 Tamakoshi-Kathmandu 220/400kV Double 170 MOOSE 7 New Butwal Hakwai Double 32 BEAR
Total 740 8 Bajhang-Deepayal-Attariya Double 260 BEAR
9 Madichaur Bafikot Double 150 BEAR
Under Execution and Planned High Voltage 10 Kohalpur-Surkhet-Dailekh Double 178 BEAR
Transmission Lines 11 Kaligandaki- Ridi Double 40 BEAR

S.N. 400 & 220 kV Transmission Line Type of Length Circuit km Conductor 12 Baneshwor-Bhaktapur Double 24 XLPE
Ckts Type 13 Balefi Corridor Double 40 BEAR
1 Kerung-Chilime Hub-Ratmate 400 kV Double 160 MOOSE 14 Kohalpur- Nepalgunjg Double 40 BEAR
2 Bheri Corridor 400 kV Double 40 MOOSE 15 Godak Anarmani Double 70 BEAR
118 3 Arun Inaruwa Anarmani 400 kV Double 460 MOOSE 16 Kabeli Dhungesangu Double 30 BEAR
4 Arun-Dudhkoshi-Tingla 400 kV Double 230 MOOSE 17 Inaruwa Dharan Double 60 BEAR
5 Dudhkoshi-Dhalkebar 400 kV Double 170 MOOSE
18 Godak Soyak Double 16 BEAR
6 New Butwal Gorakhpur 400 kV Double 80 MOOSE
19 Barhabise Lamosaghu (Sunkoshi 132 Double 24 BEAR
7 Borang - Lapan - Ratomate 220 kV Double 98 MOOSE kV SS)
8 Tumlingtal Sitalpati 220 kV Double 40 MOOSE Total 1258
Existing & Under Construction Grid Substation
Existing 220/132 kV Substation (Capacity in MVA)

S.N. Substation Capacity (MVA) 21 Markhichowk 30.0


1 Dhalkebar 320 22 Lahan 63.0
23 Duhabi 189.0
Existing 132 kV Substation (Capacity in MVA)
24 Anarmani 60.0
S.N. Substation Capacity (MVA)

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
25 Pokhara 60.0
1 Mahendranagar 25.0
26 Lekhnath 52.5
2 Attariya 60.0
27 Damauli 60.0
3 Lamki 30.0
28 Lamosagu 30.0
4 Kohalpur 93.0
29 Bhaktapur 94.5
5 Lamahi 93.0
30 Balaju 45.0
6 Shivapur 42.5
31 Suichatar 143.4
7 Butwal 189.0
32 Matatirtha 52.5
8 Bardghat 30.0
33 Hapure 30.0
9 Kawasoti 30.0
34 Chapali 129.0
10 Bharatpur 120.0
35 Mirchaiya 30.0
11 Hetauda 90.0
36 Damak 30.0
12 Parwanipur 193.5
37 Godak 63.0
13 Chandranigahapur 60.0
38 Phidim 16.0
14 Pathlaiya 22.5
39 Amarpur (Kabeli) 30.0
15 Kusum 12.5
40 Pahalmanpur 30.0 119
16 Kamane 93.0
41 Syaule 30.0
17 Syangja 30.0
42 Rupani 63.0
18 Dhalkebar 93.0
19 Bhurigau 30.0 Total 2,698
20 Ghorahi 30.0
Existing 66kV Substation (Capacity in MVA) Under Construction Substation
S.N. Substation Capacity (MVA) S.N. Substation Capacity (MVA)
1 Birgung 120.0 1 132/33 kV Singati 30
2 Amlekhgunj 7.5 2 132/33 kV Purbi Chitwan 60
3 Simra 30.0 3 132/33/11 kV Sunwaul 156
4 K-3 45.0 4 132/33 kV Lahachowk 30
5 Teku 45.0 5 132/33 kV Nawalpur 63
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

6 Patan 72.0 6 132/33 kV Mainhiya 90


7 Balaju 45.0 7 132/33 kV Garjyang 30
8 Hetauda 20.0 8 132/33 kV Biratnagar 126
9 Baneshwor 36.0 9 220/132 kV Trishuli 3B HUB 320
10 Indrawati 10.0 10 220/132 kV New Khimti 300
11 Banepa 45.0 11 220/132 kV Barabishe 160
12 Panchkhal 10.0 12 220/132/11 kV Lapsifedi 160
13 Lainchour 45.0 13 132/11 kV Changunarayan 45
14 New-Chabel 67.5 14 132/33 Sitalpati 200
15 Siuchatar 36.0 15 132/33 kV Tingla 30
Total 634.0 16 400/220 kV Dhalkebar 915
17 Kaligandaki Corridor 350
18 Koshi Corridor 550
19 Marsyangdi Corridor 870
20 132/33 kV Samudratar 60
120 Total 4545
Electricity Generation Power Plants and Projects
Major Hydropower Stations 22 Baglung*** 200
S.N. Power Plants Capacity (kW) 23 Khandbari** 250
1 Kaligandaki A 144,000 24 Phidim** 240
2 Middle Marsyangdi 70,000 25 Surnaiyagad 200

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
3 Marsyangdi 69,000 26 Doti*** 200
4 Trishuli 24,000 27 Ramechhap 150
5 Sunkoshi 10,050 28 Terhathum** 100
6 Gandak 15,000 29 Gamgad 400
7 Kulekhani I 60,000 Subtotal 13,844
8 Devighat 14,100 Total 502,994
9 Kulekhani II 32,000
10 Puwakhola 6,200 Small Hydropower Plants (Isolated)
11 Modikhola 14,800 S.N. Power Plants Capacity (kW)
12 Chameliya 30,000 1 Dhankuta*** 240
Subtotal 489,150 2 Jhurpa (Surkhet)*** 345
3 Gorkhe (Illam)*** 64
Small Hydropower Plants 4 Jumla** 200
S.N. Power Plants Capacity (kW) 5 Dhading*** 32
13 Sundarijal 640 6 Syangja*** 80
14 Panauti 2,400 7 Helambu 50
121
15 Fewa 1,000 8 Darchula** 300
16 Seti (Pokhara) 1,500 9 Chame** 45
17 Tatopani 2,000 10 Taplejung** 125
18 Chatara 3,200 11 Manang** 80
19 Tinau 1,024 12 Chaurjhari (Rukum)** 150
20 Pharping*** 500 13 Syaprudaha (Rukum)** 200
21 Jomsom** 240 14 Bhojpur** 250
15 Bajura** 200 S.No. Under Construction Capacity (KW)
16 Bajhang** 200 1 Upper Tamakoshi HEP 456,000
17 Arughat (Gorkha) 150 2 Tanahu Hydropower Project 140,000
18 Okhaldhunga 125 3 Kulekhani III HEP 14,000
19 Rupalgad 100 4 Upper Trishuli 3A HEP 60,000
20 Achham 400 5 Rahuganga HEP 40,000
21 Dolpa 200 6 Upper Sajen HEP 14,600
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

22 Kalikot 500 7 Sanjen HEP 42,500


23 Heldung (Humla) 500 8 Rasuwagadhi HEP 111,000
Total 4,536 9 Madhya Bhotekoshi 102,000
Thermal Power Plants 10 Upper Trishuli 3B HEP 37,000
S.No. Power Plants Capacity (KW) 11 Gird Solar Porject, Nuwakot 25,000
1 Duhabi Multifuel 39,000 Total 1,042,100
2 Hetauda Diesel 14,410
Total 53,410 S.No. Planned and Proposed Capacity (KW)
Solar Power Plants 1 Upper Arun HEP 1,060,000
S.No. Power Plants Capacity (KW) 2 Upper Modi A HEP 42,000
1 Simikot 50 3 Upper Modi HEP 18,200
2 Gamgadhi 50 4 Dudhkoshi Storage HEP 635,000
Total 100 5 Tamor Storage HEP 762,000
Total Major Hydro (NEA)-Grid Connected 502,994 6 Uttar Ganga Storage HEP 828,000
Total small Hydro (NEA)-Isolated 4,536 7 Tamakoshi V HEP 98,000
Total Hydro (NEA) 507,530 8 Adhikhola Storage HEP 180,000
122
Total Hydro (IPP) 550,705 9 Chainpur Seti HEP 210,000
Total Hydro (Nepal) 1,058,235 10 Begnas Rupa Pump Starage HEP 150,000
Total Thermal (NEA) 53,410 Total 3,833,200
Total Solar (NEA+IPP) 1740.4 Note
** Leased to Private Sector
Total Installed Capacity 1,113,385 *** Not in Normal Operation

Total installed Capacity (NEA and IPP)-Grid 1,108,849


IPPs’ Hydropower Projects (Operation)
S.N. Developer Projects Location Capacity (kW) PPA Date Commercial Operation Date
1 Himal Power Ltd. Khimti Khola Dolakha 60000 2052.10.01 2057.03.27
2 Bhotekoshi Power Company Ltd. Upper Bhotekoshi Sindhupalchowk 45000 2053.04.06 2057.10.11
3 Syange Electricity Company Limited Syange Khola Lamjung 183 2058.10.03 2058.10.10
4 National Hydro Power Company Ltd. Indrawati - III Sindhupalchowk 7500 2054.09.15 2059.06.21

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
5 Chilime Hydro Power Company Ltd. Chilime Rasuwa 22100 2054.03.11 2060.05.08
6 Butwal Power Company Ltd. Jhimruk Khola Pyuthan 12000 2058.03.29 1994
7 Butwal Power Company Ltd. Andhi Khola Syangza 9400 2058.03.29 2071.12.22
8 Arun Valley Hydropower Development Co. (P.) Ltd. Piluwa Khola Small Sankhuwasabha 3000 2056.10.09 2060.06.01
9 Rairang Hydro Power Development Co. (P) Ltd. Rairang Khola Dhading 500 2059.08.27 2061.08.01
10 Sanima Hydropower (Pvt.) Ltd. Sunkoshi Small Sindhupalchowk 2500 2058.07.28 2061.12.11
11 Alliance Power Nepal Pvt.Ltd. Chaku Khola Sindhupalchowk 3000 2056.11.03 2062.03.01
12 Khudi Hydropower Ltd. Khudi Khola Lamjung 4000 2058.03.04 2063.09.15
13 Unique Hydel Co. Pvt.Ltd. Baramchi Khola Sindhupalchowk 4200 2058.12.14 2063.09.27
14 Thoppal Khola Hydro Power Co. Pvt. Ltd. Thoppal Khola Dhading 1650 2059.11.23 2064.07.13
15 Gautam Buddha Hydropower (Pvt.) Ltd. Sisne Khola Small Palpa 750 2061.04.29 2064.06.01
16 Kathmandu Small Hydropower Systems Pvt. Ltd. Sali Nadi Kathmandu 250 2062.04.24 2064.08.01
17 Khoranga Khola Hydropower Dev. Co. Pvt. Ltd. Pheme Khola Panchthar 995 2057.12.31 2064.08.05
18 Unified Hydropower (P.) Ltd. Pati Khola Small Parbat 996 2062.10.28 2065.10.27
19 Task Hydropower Company (P.) Ltd. Seti-II Kaski 979 2063.06.08 2065.11.14
20 Ridi Hydropower Development Co. (P.) Ltd. Ridi Khola Gulmi 2400 2063.05.08 2066.07.10
21 Centre for Power Dev. And Services (P.) Ltd. Upper Hadi Khola Sindhupalchowk 991 2064.04.07 2066.07.22 123
22 Gandaki Hydro Power Co. Pvt. Ltd. Mardi Khola Kaski 4800 2060.07.07 2066.10.08
23 Himal Dolkha Hydropower Company Ltd. Mai Khola Ilam 4500 2063.11.19 2067.10.14
24 Baneswor Hydropower Pvt. Ltd. Lower Piluwa Small Sankhuwasabha 990 2064.07.21 2068.04.01
25 Barun Hydropower Development Co. (P.) Ltd. Hewa Khola Sankhuwasabha 4455 2061.04.02 2068.04.17
26 Bhagawati Hydropower Development Co. (P.) Ltd. Bijayapur-1 Kaski 4410 2066.03.30 2069.05.04
S.N. Developer Projects Location Capacity (kW) PPA Date Commercial Operation Date
27 Kathmandu Upatyaka Khanepani bewasthapan Board Solar Lalitpur 680.4 2069.06.12 2069.07.15
28 Nyadi Group (P.) Ltd. Siuri Khola Lamjung 4950 2064.04.17 2069.07.30
29 United Modi Hydropwer Pvt. Ltd. Lower Modi 1 Parbat 10000 2065.10.20 2069.08.10
30 Synergy Power Development (P.) Ltd. Sipring Khola Dolakha 9658 2065.10.20 2069.10.03
31 Laughing Buddha Power Nepal (P.) Ltd. Middle Chaku Sindhupalchowk 1800 2066.11.03 2069.11.15
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

32 Aadishakti Power Dev. Company (P.) Ltd. Tadi Khola (Thaprek) Nuwakot 5000 2061.12.15 2069.12.14
33 Ankhu Khola Jal Bidhyut Co. (P.) Ltd. Ankhu Khola - 1 Dhading 8400 2066.02.22 2070.05.05
34 Nepal Hydro Developer Pvt. Ltd. Charanawati Khola Dolakha 3520 2067.01.13 2070.02.24
35 Laughing Buddha Power Nepal Pvt. Ltd. Lower Chaku Khola Sindhupalchowk 1800 2063.07.02 2070.04.24
36 Bhairabkunda Hydropower Pvt. Ltd. Bhairab Kunda Sindhupalchowk 3000 2065.08.02 2071.02.22
37 Radhi Bidyut Company Ltd. Radhi Khola Lamjung 4400 2066.10.18 2071.02.31
38 Pashupati Environmental Eng. Power Co. Pvt. Ltd. Chhote Khola Gorkha 993 2067.11.09 2071.03.09
39 Mailung Khola Hydro Power Company (P.) Ltd. Mailung Khola Rasuwa 5000 2058.04.09 2071.03.19
40 Joshi Hydropower Development Company Limited Upper Puwa -1 Illam 3000 2066.01.23 2071.10.01
41 Sanima Mai Hydropower Limited Mai Khola Ilam 22000 2067.01.08 2071.10.14
42 Bojini Company Private Limited Jiri Khola Small Dolakha 2200 2065.10.23 2071.11.01
43 Ruru Hydropower Project (P) Ltd. Upper Hugdi Khola Gulmi 5000 2066.04.04 2071.12.09
44 Prime Hydropower Co. Pvt. Ltd. Belkhu Dhading 518 2064.04.04 2071.12.30
45 Api Power Company Pvt. Ltd. Naugadh gad Khola Darchula 8500 2067.01.19 2072.05.02
46 Kutheli Bukhari Small Hydropower (P).Ltd Suspa Bukhari Dolakha 998 2069.04.32 2072.06.03
47 Sanima Mai Hydropower Ltd. Mai Cascade Ilam 7000 2069.10.12 2072.10.29
48 Chhyangdi Hydropower Limited Chhandi Lamjung 2000 2068.12.23 2072.12.13
124
49 Panchakanya Mai Hydropower Ltd. (Previously Mai Valley Upper Mai Khola Ilam 9980 2061.12.19 2073.03.09
and prior to that East Nepal)
50 Sayapatri Hydropower Private Limited Daram Khola A Baglung 2500 2068.12.19 2073.03.12
51 Electro-com and Research Centre Pvt. Ltd. Jhyadi Khola Sindhupalchowk 2000 2067.01.30 2073.05.31
52 Khani Khola Hydropower Company Pvt. Ltd. Tungun-Thosne Lalitpur 4360 2069.04.05 2073.07.09
53 Daraudi Kalika Hydro Pvt. Ltd. Daraudi Khola A Gorkha 6000 2068.05.19 2073.08.13
54 Khani Khola Hydropower Company Pvt. Ltd. Khani Khola Lalitpur 2000 2069.04.05 2073.08.20
S.N. Developer Projects Location Capacity (kW) PPA Date Commercial Operation Date
55 Sapsu Kalika Hydropower Co. Pvt. Ltd. Miya Khola Khotang 996 2069.08.10 2073.09.03
56 Sinohydro-Sagarmatha Power Company (P) Ltd. Upper Marsyangdi "A" Lamjung 50000 2067.09.14 2073.09.17
57 Madi Power Pvt. Ltd. Upper Madi Kaski 25000 2066.05.21 2073.09.25
58 Panchthar Power Company Pvt. Ltd. Hewa Khola A Panchthar 14900 2068.05.30 2073.10.22
59 Sanvi Energy pvt. Ltd. Jogmai Ilam 7600 2069.08.07 2074.01.18

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
60 Bhugol Energy Dev Compay (P). Ltd Dwari Khola Dailekh 3750 2069.12.30 2074.01.23
61 Mai Valley Hydropower Private Limited Upper Mai C Ilam 5100 2068.12.23 2074.04.09
62 Dronanchal Hydropower Co.Pvt.Ltd Dhunge-Jiri Dolakha 600 2068.09.25 2074.06.01
63 Dibyaswari Hydropower Limited Sabha Khola Sankhuwasabha 4000 2068.11.17 2074.06.02
64 Puwa Khola-1 Hydropower P. Ltd. Puwa Khola -1 Ilam 4000 2070.10.09 2074.06.23
65 Shibani Hydropower Co. Pvt. Ltd. Phawa Khola Taplejung 4950 2063.12.01 2074.07.14
66 Mount Kailash Energy Pvt. Ltd. Thapa Khola Myagdi 13600 2067.10.11 2074.08.22
67 Mandakini Hydropower Limited Sardi Khola Kaski 4000 2068.11.11 2074.08.23
68 Garjang Upatyaka Hydropower (P.) Ltd. Chake Khola Ramechhap 2830 2065.11.06 2074.08.28
69 Union Hydropower Pvt Ltd. Midim Karapu Lamjung 3000 2069.10.28 2074.10.15
70 Syauri Bhumey Microhydro Project Syauri Bhumey Nuwakot 23 2072.11.16 2074.10.18
71 Molung Hydropower Company Pvt. Ltd. Molung Khola Okhaldhunga 7000 2069.11.21 2074.12.12
72 Sikles Hydropower Pvt. Ltd. Madkyu Khola Kaski 13000 2066.08.03 2074.12.19
73 Himal Dolkha Hydropower Company Ltd. Mai sana Cascade Ilam 8000 2069.11.14 2074.12.26
74 Barahi Hydropower Pvt.ltd Theule Khola Baglung 1500 2066.12.16 2075.03.24
75 Leguwa Khola Laghu Jalbidhyut Sahakari Sastha Ltd. Leguwa Khola Dhankuta 40 2072.11.21 2075.03.28
76 Super Mai Hydropower Pvt. Ltd. Super Mai Illam 7800 2073.12.06 2075.07.11 125
77 Chimal Gramin Bidhyut Sahakari Sanstha Ltd. Sobuwa Khola-2 MHP Taplejung 90 2074.11.15 2075.07.14
78 Surya Power Company Pvt. Ltd. Bishnu Priya Solar Farm Nawalparasi 960 2074.04.08 2075.08.13
Project
79 Bindhyabasini Hydropower Development Co. (P.) Ltd. Rudi Khola A Lamjung and Kaski 8800 2069.10.28 2075.12.04
80 Mandu Hydropower Ltd. Bagmati Khola Small Makawanpur/ 22000 2069.10.07 2075.12.19
Lalitpur
TOTAL 552,345.40
IPPs’ Hydropower Projects (Under Construction) (Financial Closure concluded projects)
S.N. Developers Projects Location Installed Capacity (kW) PPA Date RCOD
1 Eastern Hydropower Pvt. Ltd. Pikhuwa Khola Bhojpur 5000 2066.07.24 2076.03.30
2 Upper Tamakoshi Hydropower Ltd. Upper Tamakoshi Dolkha 456000 2067.09.14 2072.9.10 - 4 Units,
2073.3.30 - 2 Units
3 Nama Buddha Hydropower Pvt. Ltd. Tinau Khola Small Palpa 1665 2065.03.31 2066.11.1 (990kw)
2077.09.15 (675kw)
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

4 Himalayan Hydropower Pvt. Ltd. Namarjun Madi Kaski 11800 2066.05.30 2071.4.1
5 Jumdi Hydropower Pvt. Ltd. Jumdi Khola Gulmi 1750 2066.10.21 2069.10.11
6 Hira Ratna Hydropower P.ltd Tadi Khola Nuwakot 5000 2067.01.09 2075.10.01
7 Energy Engineering Pvt. Ltd. Upper Mailung A Rasuwa 6420 2067.03.25 2075.10.01
8 Shiva Shree Hydropower (P.) Ltd. Upper Chaku A Sindhupalchowk 22200 2067.05.22 2073.01.25
9 Greenlife Energy Pvt. Ltd. Khani khola-1 Dolakha 40000 2067.06.24 2074.02.21 2074.12.17 (for 25MW)
2076.09.03 (for 15MW)
10 Himalaya Urja Bikas Co. Pvt. Ltd. Upper Khimti Ramechhap 12000 2067.10.09 2075.3.32
11 Green Ventures Pvt. Ltd. Likhu-IV Ramechhap 52400 2067.10.19 2077.06.30
12 Robust Energy Ltd. Mistri Khola Myagdi 42000 2067.10.20 2076.05.14
13 Manang Trade Link Pvt. Ltd. Lower Modi Parbat 20000 2068.05.20 2074.3.31
14 Mathillo Mailung Khola Jalbidhyut Ltd. (Prv. Molnia Upper Mailun Rasuwa 14300 2068.05.23 2075.10.01
Power Ltd.)
15 Sanjen Hydropower Co.Limited Upper Sanjen Rasuwa 14800 2068.06.23 2075.10.01
16 Middle Bhotekoshi Jalbidhyut Company Ltd. Middle Bhotekoshi Sindhupalchowk 102000 2068.07.28 2076.12.28
17 Chilime Hydro Power Company Ltd. Rasuwagadhi Rasuwa 111000 2068.07.28 2075.10.01
18 Water and Energy Nepal Pvt. Ltd. Badi Gad Baglung 6600 2068.08.13 2072.2.14
126 19 Sanjen Hydropower Company Limited Sanjen Rasuwa 42500 2068.08.19 2075.10.01
20 Gelun Hydropower Co.Pvt.Ltd Gelun Sindhupalchowk 3200 2068.09.25 2074.06.14
21 Dariyal Small Hydropower Pvt.Ltd Upper Belkhu Dhading 750 2068.11.28 2071.7.16
22 Suryakunda Hydroelectric Pvt. Ltd. Upper Tadi Nuwakot 11000 2068.12.03 2075.10.01
23 Himalayan Power Partner Pvt. Ltd. Dordi Khola Lamjung 27000 2069.03.01 2076.05.14
24 Sasha Engingeering Hydropower (P). Ltd Khani Khola(Dolakha) Dolakha 30000 2069.03.25 2074.12.17
25 Arun Kabeli Power Ltd. Kabeli B-1 Taplejung, Panch- 25000 2069.03.29 2075.01.09
thar
S.N. Developers Projects Location Installed Capacity (kW) PPA Date RCOD
26 Rising Hydropower Compnay Ltd. Selang Khola Sindhupalchowk 990 2069.03.31 2071.6.15
27 Liberty Hydropower Pvt. Ltd. Upper Dordi A Lamjung 25000 2069.06.02 2076.05.14
28 Hydro Innovation Pvt. Ltd. Tinekhu Khola Dolakha 990 2069.06.08 2074.12.30
29 Salankhu Khola Hydropower Pvt. Ltd. Salankhu Khola Nuwakot 2500 2069.06.14 2071.11.30
30 Moonlight Hydropower Pvt. Ltd. Balephi A Sindhupalchowk 10600 2069.07.14 2076.12.28
31 Middle Modi Hydropower Ltd. Middle Modi Parbat 15100 2069.08.21 2077.03.31

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
32 Reliable Hydropower Co. Pvt. Ltd. Khorunga Khola Terhathum 4800 2069.08.26 2077.08.16
33 Rara Hydropower Development Co. Pvt. Ltd. Upper Parajuli Khola Dailekh 2150 2069.08.28 2071.12.17
34 Lohore Khola Hydropower Co. Pvt. Ltd. Lohore Khola Dailekh 4200 2069.09.08 2073.06.20
35 Beni Hydropower Project Pvt. Ltd. Upper Solu Solukhumbu 18000 2069.09.16 2073.07.25 2074.10.01
(PPA Revived)
36 Dudhkoshi Power Company Pvt. Ltd. Rawa Khola Khotang 6500 2069.09.26 2073.05.31
37 Universal Power Company Ltd. Lower Khare Dolakha 11000 2069.10.22 2074.9.16 (8.26MW)
2076.04.03 (2.74MW)
38 Madhya Midim Jalbidhyut Company P. Ltd. Middle Midim Lamjung 3100 2069.10.23 2072.5.1
39 Volcano Hydropower Pvt. Ltd. Teliya Khola Dhankuta 996 2069.10.25 2071.7.24
40 Betrawoti Hydropower Company (P).Ltd Phalankhu Khola Rasuwa 13700 2069.12.06 2075.10.01
41 Himalaya Urja Bikas Co. Ltd. Upper Khimti II Ramechhap 7000 2069.12.09 2075.12.01
42 Salmanidevi Hydropower (P). Ltd Kapadi Gad Doti 3330 2069.12.11 2073.08.15
43 Dovan Hydropower Company Pvt. Ltd. Junbesi Khola Solukhumbu 5200 2069.12.29 2076.08.30
44 Ghalemdi Hydro Limited (Previously, Cemat Power Dev Ghalemdi Khola Myagdi 5000 2069.12.30 2074.07.30 (4MW)
Company (P). Ltd.) 2077.05.03(1MW)
45 Tallo Midim Jalbidhut Company Pvt. Ltd. Lower Midim Lamjung 996 2070.01.19 2071.8.1
46 Rairang Hydropower Development Company Ltd. Iwa Khola Taplejung 9900 2070.01.29 2075.4.1 127
47 Tangchhar Hydro Pvt. Ltd Tangchhahara Mustang 2200 2070.02.20 2073.7.1
48 Abiral Hydropower Co. Pvt. Ltd. Upper Khadam Morang 990 2070.02.21 2071.08.01
49 Manakamana Engineering Hydropower Pvt. Ltd. Ghatte Khola Dolakha 5000 2070.04.28 2075.03.16
50 Essel-Clean Solu Hydropower Pvt. Ltd. Lower Solu Solukhumbu 82000 2070.07.15 2076.8.30
51 Consortium Power Developers Pvt. Ltd. Khare Khola Dolakha 24100 2070.07.15 2075.08.15
52 Upper Solu Hydroelectric Company Pvt. Ltd Solu Khola Solukhumbu 23500 2070.07.24 2075.4.1
S.N. Developers Projects Location Installed Capacity (kW) PPA Date RCOD
53 Singati Hydro Energy Pvt. Ltd. Singati Khola Dolakha 25000 2070.07.27 2075.05.31 (16MW)
2077.04.01 (9MW)
54 Maya Khola Hydropower Co. Pvt. Ltd. Maya Khola Sankhuwasabha 14900 2070.08.30 2076.9.1
55 Idi Hydropower Co. P. Ltd. Idi Khola Kaski 975 2070.09.01 2074.09.16
56 Buddha Bhumi Nepal Hydro Power Co. Pvt. Ltd. Lower Tadi Nuwakot 4993 2070.12.10 2075.10.01
57 Mountain Hydro Nepal Pvt. Ltd. Tallo Hewa Khola Panchthar 22100 2071.04.09 2075.01.09
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

58 Bindhyabasini Hydropower Development Co. (P.) Ltd. Rudi Khola B Lamjung and Kaski 6600 2071.4.20 2074.04.01 2076.02.32
59 Dordi Khola Jal Bidyut Company Ltd. Dordi-1 Khola Lamjung 12000 2071.07.19 2076.08.16 (10.3 MW)
2077.04.02 (1.7 MW)
60 River Falls Hydropower Development Pvt. Ltd. Down Piluwa Sankhuwasabha 9500 2071.10.18 2076.09.01
61 Rangoon Khola Hydropower Pvt. Ltd. Jeuligad Small Hydro- Bajhang 996 2071.10.20 2073.10.03 2075.03.32
power Project
62 Peoples' Hydropower Company Pvt. Ltd. Super Dordi 'Kha' Lamjung 54000 2071.11.13 2077.03.29
63 Hydro Venture Private Limited Solu Khola (Dudhkoshi) Solukhumbu 86000 2071.11.13 2077.06.10
64 Global Hydropower Associate Pvt. Ltd. Likhu-2 Solukhumbu/ 33400 2071.11.19 2077.04.01
Ramechap
65 Paan Himalaya Energy Private Limited Likhu-1 Solukhumbu/ 51400 2071.11.19 2077.04.01
Ramechap
66 Numbur Himalaya Hydropower Pvt. Ltd. Likhu Khola A Solukhumbu/ 24200 2071.11.22 2077.04.01
Ramechap
67 Dipsabha Hydropower Pvt. Ltd. Sabha Khola A Sankhuwasabha 9990 2071.12.02 2076.07.15
68 Research and Development Group Pvt. Ltd. Rupse Khola Myagdi 4000 2071.12.17 2076.08.02
69 Hydro Empire Pvt. Ltd. Upper Myagdi Myagdi 20000 2071.12.17 2077.05.30
70 Chandeshwori Mahadev Khola MH. Co. Pvt. Ltd. Chulepu Khola Ramechhap 8520 2071.12.23 2075.04.15
128 71 Nyadi Hydropower Limited Nyadi Lamjung 30000 2072.02.12 2077.01.06
72 Suri Khola Hydropower Pvt. Ltd. Suri Khola Dolakha 6400 2072.02.20 2074.12.30
73 Bungal Hydro Pvt. Ltd. (Previously Sanigad Hydro Pvt. Upper Sanigad Bajhang 10700 2072.03.15 2076.05.29
Ltd.)
74 Kalanga Hydro Pvt. Ltd. Kalangagad Bajhang 15330 2072.03.15 2076.05.29
75 Sanigad Hydro Pvt. Ltd. Upper Kalangagad Bajhang 38460 2072.03.15 2077.04.15
76 Dhaulagiri Kalika Hydro Pvt. Ltd. Darbang-Myagdi Myagdi 25000 2072.04.28 2075.12.25
77 Menchhiyam Hydropower Pvt. Ltd. Upper Piluwa Khola 2 Sankhuwasabha 4720 2072.05.11 2076.04.01
S.N. Developers Projects Location Installed Capacity (kW) PPA Date RCOD
78 Kabeli Energy Limited Kabeli-A Panchthar and 37600 2072.06.07 2076.11.03
Taplejung
79 Upper Syange Hydropower P. Ltd. Upper Syange Khola Lamjung 2400 2072.06.14 2075.10.01
80 Peoples Energy Ltd. (Previously Peoples Hydro Co-opera- Khimti-2 Dolakha and 48800 2072.06.14 2078.04.01
tive Ltd.) Ramechhap
81 Chauri Hydropower (P.) Ltd. Chauri Khola Kavrepalanchowk, 6000 2072.06.14 2075.12.30 (5 MW)

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
Ramechhap, 2078.08.03 (1 MW)
Sindhupalchowk,
Dolakha
82 Pashupati Environmental Power Co. Pvt. Ltd. Lower Chhote Khola Gorkha 997 2072.08.04 2076.05.15
83 Huaning Development Pvt. Ltd. Upper Balephi A Sindhupalchowk 36000 2072.08.29 2075.10.06
84 Upper Hewa Khola Hydropower Co. Pvt. Ltd. Upper Hewa Khola Sankhuwasabha 8500 2072.09.23 2076.03.17
Small
85 Multi Energy Development Pvt. Ltd. Langtang Khola Rasuwa 20000 2072.09.29 2076.12.30 (for 10MW)
2078.04.03 (for 10MW)
86 Ankhu Hydropower (P.) Ltd. Ankhu Khola Dhading 34000 2073.01.30 2076.12.30
87 Myagdi Hydropower Pvt. Ltd. Ghar Khola Myagdi 14000 2073.02.11 2076.08.30 (8.3 MW)
2078.10.17 (5.7 MW)
88 Richet Jalbidhyut Company Pvt. Ltd. Richet Khola Gorkha 4980 2073.02.23 2075.07.30
89 United Idi Mardi and R.B. Hydropower Pvt. Ltd. Upper Mardi Kaski 7000 2073.02.25 2075.04.01
90 Rapti Hydro and General Construction Pvt. Ltd. Rukumgad Rukum 5000 2073.03.07 2076.09.01
91 Rawa Energy Development Pvt. Ltd. Upper Rawa Khotang 3000 2073.04.24 2076.03.30
92 Siddhi Hydropower Company Pvt. Ltd. Siddhi Khola Illam 10000 2074.05.29 2077.03.31
93 Api Power Company Pvt. Ltd. Upper Naugad Gad Darchula 8000 2073.07.12 2077.04.01
94 Terhathum Power Company Pvt. Ltd. Upper Khorunga Terhathum 7500 2073.07.29 2076.09.01 129
95 Nilgiri Khola Hydropower Co. Ltd. Nilgiri Khola Myagdi 38000 2073.11.30 2080.08.30
96 Siuri Nyadi Power Pvt. Ltd. Super Nyadi Lamjung 40270 2074.02.19 2079.04.01
97 Swet-Ganga Hydropower and Construction Ltd. Lower Likhu Ramechhap 28100 2073.09.14 2078.08.15
98 Nilgiri Khola Hydropower Co. Ltd. Nilgiri Khola-2 Myagdi 62000 2074.03.05 2081.08.30
99 Sano Milti Khola Hydropower Ltd. Sano Milti Ramechhap and 3000 2073.01.13 2075.08.01
Dolakha
100 Diamond Hydropower Pvt. Ltd. Upper Daraudi-1 Gorkha 10000 2072.08.14 2075.09.17
S.N. Developers Projects Location Installed Capacity (kW) PPA Date RCOD
101 Chhyangdi Hydropower Limited Upper Chhyangdi Khola Lamjung 4000 2074.03.22 2078.4.05
102 Taksar-Pikhuwa Hydropower Pvt. Ltd. Taksar Pikhuwa Bhojpur 8000 2073.09.01 2076.10.23
103 Rasuwa Hydropower Pvt. Ltd Phalanku Khola Rasuwa 5000 2071.08.24 2076.8.01
104 Civil Hydropower Pvt. Ltd. Bijayapur 2 Khola Small Kaski 4500 2072.09.12 2075.03.32
105 Makari Gad Hydropower Pvt. Ltd. Makarigad Darchula 10000 2072.08.29 2076.02.32
106 Super Madi Hydropower Ltd. (Previously Himal Hydro and Super Madi Kaski 44000 2073.10.27 2078.02.28
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

General Construction Ltd.)


107 Mount Nilgiri Hydropower Company Pvt. Ltd. Rurubanchu-1 Kalikot 13500 2074.05.08 2077.11.03
108 Trishuli Jal Vidhyut Company Ltd. Upper Trishuli 3B Rasuwa 37000 2074.05.06 2078.11.17
109 Century Energy Pvt. Ltd. Hadi Khola Sunkoshi A Sindhupalchowk 997 2074.05.05 2076.11.03
110 Sindhujwala Hydropower Ltd. Upper Nyasem Sindhupalchowk 41400 2073.07.24 2077.03.30
111 Samling Power Company Pvt. Ltd. Mai Beni Illam 9510 2073.07.26 2078.08.02
112 Energy Venture Pvt. Ltd. Upper Lapche Dolakha 52000 2073.04.20 2078.12.30
113 Orbit Energy Pvt. Ltd. (Previously Pokhari Hydropower Sabha Khola B Sankhuwasabha 15100 2074.03.26 2078.2.31
Company Pvt. Ltd.)
114 Eco Power Development Company Pvt. Ltd Mithila Solar PV Electric Dhanusha 10000 2075.09.16 2076.01.17
Project
115 Daram Khola Hydro Energy Ltd. Daram Khola Baglung and Gulmi 9600 2073.10.09 2076.09.08
116 Sagarmatha Jalabidhyut Company Pvt. Ltd. Super Mai 'A' Illam 9600 2074.11.14 2077.09.29
TOTAL 2,581,765

130
IPPs’ Hydropower Projects in Different Stages of Development
(Without Financial Closure)

S.N. Developers Projects Location Installed PPA Date RCOD


Capacity (kW)
1 Balephi Jalbidhyut Co. Ltd. Balephi Sindhupalchowk 23520 2067.09.08 2071.09.16
2077.06.30
2 Ingwa Hydro Power Pvt. Ltd Upper Ingwa khola Taplejung 9700 2068.03.10 2073.04.01

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
3 Deurali Bahuudesiya Sahakari Sanstha Ltd. Midim Khola Lamjung 100 2070.02.20 2070.5.1

4 Yambling Hydropower Pvt. Ltd. Yambling Khola Sindhupalchowk 7270 2072.09.29 2077.03.17
5 United Modi Hydropwer Ltd. Lower Modi 2 Parbat 10500 2072.11.14 2076.03.17
6 Salasungi Power Limited Sanjen Khola Rasuwa 78000 2072.12.02 2077.03.08
7 Siddhakali Power Limited Trishuli Galchi Nuwakot and 75000 2073.02.20 2077.02.01
Dhading
8 Him River Power Pvt. Ltd. Liping Khola Sindhupalchowk 16260 2073.02.28 2077.01.22
9 Chirkhwa Hydropower Pvt. Ltd. Upper Chirkhwa Bhojpur 4700 2073.03.01 2077.04.01
10 Sanima Middle Tamor Hydropower Ltd. (Prv. Tamor Sanima Energy Pvt. Ltd.) Middle Tamor Taplejung 73000 2073.09.26 2078.05.28
11 Pahadi Hydro Power Company (P.) Ltd. Madhya Tara Khola Small Baglung 1700 2073.10.26 2075.08.29
12 Sisa Hydro Electric Company Pvt. Ltd. Sisa Khola A Solukhumbu 2800 2073.10.28 2077.12.12
13 Chirkhwa Hydropower Pvt. Ltd. Lower Chirkhwa Bhojpur 4060 2074.01.20 2078.04.01
14 Him Consult Pvt. Ltd. Rele Khola Myagdi 6000 2074.01.28 2077.02.19
15 Himali Rural Electric Co-operative Ltd. Leguwa Khola Small Dhankuta 640 2074.02.08 2075.12.28
16 Sabha Pokhari Hydro Power (P.) Ltd. Lankhuwa Khola Sankhuwasabha 5000 2074.02.21 2077.09.14
17 United Mewa Khola Hydropower Pvt. Ltd. Mewa Khola Taplejung 50000 2074.02.21 2078.04.01
18 Parbat Paiyun Khola Hydropower Company Pvt. Ltd. Seti Khola Parbat 3500 2074.02.22 2076.12.30 131
19 Sewa Hydro Ltd. Lower Selang Sindhupalchowk 1500 2074.02.22 2075.12.30
20 Gorakshya Hydropower Pvt. Ltd. Super Ankhu Khola Dhading 23500 2074.03.15 2080.09.15
21 Nyam Nyam Hydropower Company Pvt. Ltd. Nyam Nyam Khola Rasuwa 6000 2074.03.27 2077.12.31
22 Saptang Hydro Power Pvt. Ltd. Saptang Khola Nuwakot 2500 2074.04.08 2076.04.12
23 Jhyamolongma Hydropower Development Company Pvt. Ltd. Karuwa Seti Kaski 32000 2074.04.20 2079.01.12
S.N. Developers Projects Location Installed PPA Date RCOD
Capacity (kW)
24 People's Power Limited Puwa - 2 Illam 4960 2074.05.05 2078.06.11
25 Bhujung Hydropower Pvt. Ltd. Upper Midim Lamjung 7500 2074.05.29 2078.04.01
26 Himalayan Water Resources and Energy Development Co. Pvt. Ltd. Upper Chauri Kavrepalanchowk 6000 2074.07.27 2078.04.04
27 Nasa Hydropower Pvt. Ltd. Lapche Khola Dolakha 99400 2074.07.29 2079.04.14
28 Dolti Power Company Pvt. Ltd. Padam Khola Dailekh 4800 2074.08.01 2077.11.08
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

29 IDS Energy Pvt. Ltd. Lower Khorunga Terhathum 5400 2074.08.24 2078.04.01
30 Langtang Bhotekoshi Hydropower Company Pvt. Ltd. Rasuwa Bhotekoshi Rasuwa 120000 2074.09.07 2078.09.07
31 Upper Richet Hydropower Pvt. Ltd. Upper Richet Gorkha 2000 2074.09.20 2077.04.01
32 Him Star Urja Co. Pvt. Ltd. Buku Kapati Okhaldhunga and 5000 2074.10.11 2077.04.15
Solukhumbu
33 Khechereswor Jal Vidhyut Pvt. Ltd. Jadari Gad Small Bajhang 1000 2074.10.12 2077.07.30
34 Khechereswor Jal Vidhyut Pvt. Ltd. Salubyani Gad Small Bajhang 233 2074.10.12 2077.09.29
35 Nepal Water and Energy Development Company Pvt. Ltd. Upper Trishuli - 1 Rasuwa 216000 2074.10.14 2080.12.18
36 Gaughar Ujjyalo Sana Hydropower Co. Pvt. Ltd. Ghatte Khola Small Sindhupalchowk 970 2074.11.11 2077.03.01
37 Unitech Hydropower Co. Pvt. Ltd. Upper Phawa Taplejung 5800 2074.11.11 2078.04.16
38 Seti Khola Hydropower Pvt. Ltd. Seti Khola Kaski 22000 2074.11.11 2079.04.15
39 Vision Energy and Power Pvt. Ltd. Nupche Likhu Ramechhap 57500 2074.11.28 2080.05.02
40 Omega Energy Developer Pvt. Ltd. Sunigad Bajhang 11050 2074.11.30 2080.02.07
41 Mai Khola Hydropower Pvt. Ltd. Super Mai Cascade Illam 3800 2074.12.07 2078.04.01
42 Asian Hydropower Pvt. Ltd. Lower Jogmai Illam 6200 2074.12.07 2078.04.01
43 Gaurishankar Power Development Pvt. Ltd. Middle Hyongu Khola B Solukhumbu 22900 2074.12.08 2079.04.01
44 Upper Lohore Khola Hydropower Co. Pvt. Ltd. Upper Lohore Dailekh 4000 2074.12.08 2077.04.11
132 45 Super Hewa Power Company Pvt. Ltd. Super Hewa Sankhuwasabha 5000 2074.12.27 2078.04.01
46 Khimti Gramin Bidhyut Sahakari Sanstha Ltd. Jhankre Khola Small Dolakha 600 2075.02.04 2076.05.14
47 Baraha Multipower Pvt. Ltd. Irkhuwa Khola B Bhojpur 15524 2075.02.14 2079.04.15
48 Aashutosh Energy Pvt. Ltd. Chepe Khola Small Lamjung 8630 2075.02.15 2078.11.09
49 Lower Irkhuwa Hydropower Co. Pvt. Ltd. Lower Irkhuwa Bhojpur 13040 2075.02.16 2079.04.03
50 Sungava Foundation Pvt. Ltd. Thulo Khola Myagdi 21300 2075.02.17 2079.04.15
51 Jhilimili Hydropower Co. Pvt. Ltd. Gulangdi Khola Gulmi 980 2075.02.24 2078.01.14
52 North Summit Hydro Pvt. Ltd. Nyadi Phidi Lamjung 21400 2075.02.24 2079.12.15
S.N. Developers Projects Location Installed PPA Date RCOD
Capacity (kW)
53 Himali Hydro Fund Pvt. Ltd. Sona Khola Taplejung 9000 2075.03.14 2080.07.30
54 Tanahun Hydropower Ltd. Tanahun Tanahun 140000 2075.03.15 2080.12.30
55 Sailung Power Company Pvt. Ltd. Bhotekoshi-1 Sindhupalchowk 40000 2075.03.15 2079.07.01
56 Jalshakti Hydro Company Pvt. Ltd. Ilep (Tatopani) Dhading 23675 2075.03.25 2081.08.25
57 Three Star Hydropower Company Ltd. Sapsup Khola Khotang 6600 2075.03.25 2078.06.31

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
58 Tundi Power Pvt.Ltd Rahughat Mangale Myagdi 35500 2075.03.29 2079.08.29
59 Tundi Power Pvt.Ltd Upper Rahughat Myagdi 48500 2075.03.29 2080.08.29
60 Arati Power Company Ltd. Upper Irkhuwa Bhojpur 14500 2075.04.01 2079.08.01
61 Mount Everest Power Development Pvt. Ltd. Dudhkunda Khola Solukhumbu 12000 2075.04.01 2079.06.30
62 Shaileshwari Power Nepal Pvt. Ltd. Upper Gaddigad Doti 1550 2075.04.06 2077.12.19
63 Palun Khola Hydropower Pvt. Ltd. Palun Khola Taplejung 21000 2075.04.06 2080.06.21
64 Makar Jitumaya Hydropower Pvt. Ltd. Upper Suri Dolakha 7000 2075.04.10 2079.12.30
65 Him Parbat Hydropower Pvt. Ltd. Sagu Khola-1 Dolakha 5500 2075.04.10 2079.12.30
66 Him Parbat Hydropower Pvt. Ltd. Sagu Khola Dolakha 20000 2075.04.10 2079.12.30
67 Annapurna Bidhyut Bikas Co. Pvt. Ltd. Landruk Modi Kaski 86590 2075.04.13 2081.09.15
68 Madame Khola Hydropower Pvt. Ltd. Madame Khola Kaski 24000 2075.04.15 2080.12.30
69 Mid Solu Hydropower Company Pvt. Ltd. Mid Solu Khola Solukhumbu 9500 2075.04.21 2079.05.14
70 Apolo Hydropower Pvt. Ltd. Buku Khola Solukhumbu 6000 2070.02.02 2074.04.01
2075.04.22
(Revived)
71 Solar Farm Pvt. Ltd. Belchautara Solar Project Tanahun 5000 2075.04.23 2076.04.03
72 Thulo Khola Hydropower Pvt. Ltd. Upper thulo Khola-A Myagdi 15000 2075.04.24 2080.06.30
73 Kalika Energy Ltd. Bhotekoshi-5 Sindhupalchowk 62000 2075.04.25 2080.09.15 133
74 Api Power Company Ltd. Chandranigahpur Solar Project Rautahat 4000 2075.04.27 2076.02.26
75 Api Power Company Ltd. Parwanipur Solar Project Parsa 8000 2075.04.27 2076.02.26
76 Api Power Company Ltd. Dhalkebar Solar Project Dhanusha 1000 2075.05.03 2076.03.02
77 Api Power Company Ltd. Simara Solar Project Bara 1000 2075.05.03 2076.03.02
78 Mewa Developers Pvt. Ltd. Middle Mewa Taplejung 49000 2075.05.04 2080.06.06
79 Super Ghalemdi Hydropower Pvt. Ltd. Super Ghalemdi Myagdi 9140 2075.05.05 2080.12.12
80 Sanvi Energy Pvt. Ltd. Jogmai Cascade Illam 6000 2075.05.07 2078.04.07
S.N. Developers Projects Location Installed PPA Date RCOD
Capacity (kW)
81 Dibyajyoti Hydropower Pvt. Ltd. Marsyangdi Besi Lamjung 50000 2075.05.10 2079.06.06
82 Amar Jyoti Hydro Power Pvt. Ltd. Istul Khola Gorkha 1506 2075.05.13 2079.10.25
83 Apex Makalu Hydro Power Pvt. Ltd. Middle Hongu Khola A Solukhumbu 22000 2075.05.14 2079.04.01
84 Ichowk Hydropower Pvt. Ltd. Gohare Khola Sindhupalchowk 950 2075.05.25 2076.07.29
85 Pike Hydropower Pvt. Ltd. Likhu Khola Ramechhap and 30000 2075.05.26 2082.02.17
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

Okhaldhunga
86 Sita Hydro Power Co. Pvt. Ltd. Nyasim Khola Sindhupalchowk 35000 2075.05.26 2080.03.15
87 Sushmit Energy Pvt. Ltd. Kunaban Khola Myagdi 20000 2075.05.29 2080.11.03
88 Masina Paryatan Sahakari Sanstha Ltd. Masina Kaski and Tanahu 891 2075.06.02 2076.10.29
89 Hydro Village Pvt. Ltd. Myagdi Khola Myagdi 57300 2075.06.04 2080.05.29
90 Ridi Hydropower Development Co. Ltd. Butwal Solar Project Rupandehi 8500 2075.06.09 2076.04.08
91 Shikhar Power Development Pvt. Ltd. Bhim Khola Baglung 4960 2075.06.10 2078.06.05
92 Indushankar Chini Udhyog Ltd. Indushankar Chini Udhyog Ltd. Sarlahi 3000 2075.06.10 2076.12.09
93 Dhading Ankhu Khola Hydro Pvt. Ltd. Upper Ankhu Dhading 38000 2075.06.14 2079.09.15
94 Everest Sugar and Chemical Industries Ltd. Everest Sugar and Chemical Mahottari 3000 2075.06.17 2076.12.30
Industries Ltd.
95 Phedi Khola Hydropower Company Pvt. Ltd. Phedi Khola (Thumlung) Bhojpur 3520 2075.06.21 2079.12.01
96 Sagarmatha Energy and Construction Pvt. Ltd. Dhalkebar Solar Project Dhanusha 3000 2075.06.24 2076.12.23
97 Gorkha Congenial Energy and Investment Pvt. Ltd. Lamahi Solar Project Dang 3000 2075.06.24 2076.12.23
98 Global Energy and Construction Pvt. Ltd. Duhabi Solar Project Sunsari 8000 2075.06.25 2076.12.24
99 Dolakha Nirman Company Pvt. Ltd. Isuwa Khola Sankhuwasabha 97200 2075.06.26 2080.04.01
100 Bikash Hydropower Company Pvt. Ltd. Upper Machha Khola Small Gorkha 4550 2075.07.11 2080.03.30
134 101 Sita Hydropower Co. Pvt. Ltd. Dudh Khola Manang 65000 2075.07.11 2080.03.15
102 Blue Energy Pvt. Ltd. Super Trishuli Gorkha and Chitwan 70000 2075.07.11 2080.11.17
103 Vision Lumbini Ltd. Seti Nadi Kaski 25000 2075.08.06 2079.04.05
104 Kalinchowk Hydropower Pvt. Ltd. Sangu (Sorun) Dolakha 5000 2075.08.09 2079.12.30
105 Arun Valley Hydropower Development Company Ltd. Kabeli B-1 Cascade Panchthar 9940 2075.08.09 2078.06.01
106 Kasuwa Khola Hydropower Ltd. Kasuwa Khola Sankhuwasabha 45000 2075.08.13 2082.04.06
107 Ruru Hydroelectric Company Pvt. Ltd. Rurubanchu Khola-2 Kalikot 12000 2075.08.20 2079.05.25
S.N. Developers Projects Location Installed PPA Date RCOD
Capacity (kW)
108 Gumu Khola Bhyakure Hydropower Pvt. Ltd. Gumu Khola Dolakha 950 2075.08.21 2078.05.30
109 Alliance Energy Solutions Pvt.Ltd. Upper Sit Khola Argakhanchi 905 2075.08.23 2077.05.04
110 Ekikrit Byapar Company Pvt. Ltd. Brahamayani Sindhupalchowk 35470 2075.08.24 2080.04.13
111 Integrated Hydro Fund Nepal Pvt. Ltd. Upper Brahamayani Sindhupalchowk 15150 2075.08.24 2080.04.13
112 Perfect Energy Development Pvt. Ltd Middle Trishuli Ganga Nuwakot 19410 2075.09.03 2080.02.17

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
113 Kabeli Hydropower Company Pvt.Ltd. Kabeli-3 Taplejung 21930 2075.10.03 2079.09.01
114 Union Mewa Hydro Ltd. Mewa Khola Taplejung 23000 2075.10.04 2080.09.15
115 North Summit Hydro Pvt. Ltd. Hidi Khola Lamjung 6820 2075.10.04 2080.05.15
116 Sajha Power Development Pvt. Ltd. Lower Balephi Sindhupalchowk 20000 2075.10.06 2080.07.18
117 Sindhujwala Hydropower Ltd. Upper Nyasem Khola A Sindhupalchowk 21000 2075.10.06 2079.03.30
118 Mount Rasuwa Hydropower Pvt. Ltd. Midim 1 Khola Lamjung 13424 2075.10.07 2080.04.04
119 Habitat Power Company Pvt. Ltd Hewa Khola “A” Panchthar 5000 2075.10.07 2078.04.01
120 Ruby Valley Hydropower Company Ltd Menchet Khola Dhading 7000 2075.10.15 2080.02.13
121 Dudhpokhari Chepe Hydropower Pvt. Ltd. Dudhpokhari Chepe Gorkha 8800 2075.10.15 2080.01.28
122 Maa Shakti Engineering & hydropower Pvt. Ltd. Luja Khola Solukhumbu 23550 2075.10.16 2080.11.14
123 Sankhuwasabha Power Development Pvt. Ltd. Super Sabha Khola Sankhuwasabha 4100 2075.10.23 2080.06.03
124 Hilton Hydro Energy Pvt. Ltd. Super Kabeli Taplejung 12000 2075.11.02 2079.10.04
125 Snow Rivers Pvt. Ltd. Super Kabeli A Taplejung 13500 2075.11.02 2080.01.01
126 Jal Urja Pvt. Ltd. Nuagad Darchula 1000 2075.11.03 2078.10.22
127 Champawati Hydropower Pvt. Ltd Chepe khola A Lamjung 7000 2075.11.07 2079.04.04
128 Api Power Company Ltd. Upper Chameliya Darchula 40000 2075.11.15 2079.11.13
129 Barpak Daruadi Hydropower Pvt. Ltd. Middle Super Daraudi Gorkha 10000 2075.11.23 2080.03.01
130 Helambu Construction Pvt. Ltd Ksumti khola Sindhupalchowk 683 2075.11.29 2078.03.04
135
131 River Side Hydro Energy Pvt. Ltd. Tamor Khola-5 Taplejung 37520 2075.12.04 2080.04.10
132 Hydro Connection Pvt. Ltd. Rauje Khola Solukhumbu 17712 2075.12.04 2080.10.15
133 Milke Jaljale Hydropower Pvt.Ltd. Upper Piluwa Hills Sankhuwasabha 4990 2075.12.4 2081.04.04
134 Ambe Hydropower Pvt. Ltd. Upper Bhurundi Parbat 3750 2075.12.10 2079.04.16
135 Orbit Energy Pvt. Ltd. Sabha Khola C Sankhuwasabha 4196 2075.12.10 2079.04.02
S.N. Developers Projects Location Installed PPA Date RCOD
Capacity (kW)
136 Mabilung Energy (P.) Ltd Upper Piluwa Khola -3 Sankhuwasabha 4950 2075.12.12 2078.11.16
137 Raghuganga Hydropower Ltd. Rahughat Myagdi 40000 2075.12.18 2079.10.17
138 Ridge Line Energy Pvt. Ltd. Super Chepe Gorkha and 9050 2075.12.19 2079.05.20
Lamjung
139 Dhaulagiri Civil Electrical and Mechanical Engineering Pvt. Ltd. Madhya Daram Khola A Baglung 3000 2075.12.26 2077.12.31
N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9

140 Dhaulagiri Civil Electrical and Mechanical Engineering Pvt. Ltd. Madhya Daram Khola B Baglung 4500 2075.12.26 2078.02.31
141 Bhalaudi Khola Hydropower Pvt. Ltd. Bhalaudi Khola Kaski 2645 2076.01.06 2080.04.16
142 Kalika Construction Pvt. Ltd. Upper Daraudi B Gorkha 8300 2076.01.09 2080.09.15
143 Kalika Construction Pvt. Ltd. Upper Daraudi C Gorkha 9820 2076.01.09 2080.09.15
144 Super Khudi Hydropower Pvt. Ltd. Upper Khudi Lamjung 21210 2076.01.11 2080.10.09
Total 2,909,944

136
137

N E PA L E L E C T R I F I C AT I O N S TAT I S T I C S : 2 0 1 9
NEPAL ELECTRICITY AUTHORITY
Central Office, Durbarmarg
Kathmandu Nepal
info@nea.org.np
www.nea.org.np
977-1-4153051
+977-1-4153009