I. Plumbing Installations
1 Instalasi Air Bersih m2 8,165 16,668 136,097,098
2 Instalasi Air Kotor m2 8,165 16,668 136,097,098
3 Instalasi Air Flushing m2 8,165 16,668 136,097,098
4 Instalasi Air Bekas m2 8,165 16,668 136,097,098
5 Instalasi Air Kitchen m2 8,165 16,668 136,097,098
6 Instalasi Vent m2 8,165 16,668 136,097,098
7 Instalasi Drainase m2 8,165 16,668 136,097,098
8 Instalasi Air Hujan m2 8,165 16,668 136,097,098
TOTAL I. 1,088,776,785
V. Electronic Installations
1 Instalasi Fire Alarm m2 8,165 27,049 220,858,351
2 Instalasi Telephone & Data m2 8,165 27,049 220,858,351
3 Instalasi Tata Suara m2 8,165 27,049 220,858,351
4 Instalasi Security & CCTV m2 8,165 27,049 220,858,351
5 Instalasi Kabel Tray m2 8,165 27,049 220,858,351
TOTAL V. 1,104,291,755
Project Office Mr Dadan
Package M&E Services Installations
Location Jakarta / Bandung
Year 2019 to 2021
TOTAL X. 339,657,876