Академический Документы
Профессиональный Документы
Культура Документы
Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019
Project name AMC Connectivity Corridors & Concourse Bridge Project Project No M1467
Main Contractor McLaren Construction Ltd. Document No MCL-ME-A-MST-MSS-003
Title/Task Structured Cabling Revision No 01
Document
Date of issue 19/02/2019 Prepared By
Frasat Ahmed
Duration of
Proposed start date 12/04/2019 task 1 Month
Contents
Section A Register of Revisions
Section B Scope of Works to be undertaken:
Section C Location of the Project
Section D Location of the Works to be Undertaken with the Project
Section E Site Access/Egress and Access to the Work Zone
Section F Emergency Contacts Details and Procedures:
Section G McLaren Site Specific HSE Safety Induction:
Section H Welfare facilities:
Section I Personal Protective Equipment
Section J Plant/Equipment and tools to be Used
Section K Materials To be used.
Section L Communication/Toolbox Talks/Training Requirements:
Section M Works Permits
Section N Environmental and Waste Management:
Section O Programme for the Works:
Section P Housekeeping and Storage:
Section Q Hygiene and cleanliness
Section R Working At Height
Section S Occupational Health
Section T Sequence of Works/Activities
Appendices
Appendix A Site Logistic Plans and Other Design Information Relative to the Works
Appendix B Crisis/Emergency Plan
Appendix C COSHH Assessments and Material Data Sheets (to be provided by Subcontractor)
Appendix D Risk Assessments (to be provided by Subcontractor)
Appendix E Technical Information (to be provided by the Subcontractor)
Appendix F Risk Assessment
Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019
Revision Date Reason for Amendment Amended By Signature Has this amendment been briefed
No (Name) to the operatives involved and have
the operatives signed the register.
00 11/02/ Mixed with ESCF Project Requirements Frasat
2019
00 11/02/ How the work to be carried at or working Frasat
2019 platform used not being Identified
00 11/02/ Risk Assessment to match the sequence of work Frasat
2019 and the activity being carried out.
This method statement has been prepared in conjunction with the following documents;
1. OSHAD regulation and requirements
2. OHSAD- Code of Practices, HSE Regulations, Technical Guidelines, Mechanisms
3. GR HSE Guidelines and Requirements
4. Federal Environmental Authority Law No 24/1999 and its supplements.
5. Federal Labour Law No 8
6. Articles (3,4,5,7) Local Law No 21/2005 (Waste Management)
7. McLaren SHE Procedures
8. McLaren’s site specific SHEQ Plan (including TMMS, SWMP, EPP).
9. McLaren’s Integrated Management System Policy Statement (IMS) .
Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019
Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019
Add full sketch of the project and mark up your areas of work (logistics plan to be updated)
Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019
Please refer to the attached Crisis/Emergency Plan, (Appendix B) which is to be implemented where the need
arises.
The Qualified First Aiders for the Project are listed below, and the first Aid Boxes will be available either in the
Induction/First Aid Room or in the Main Office.
McLaren: (details of First Aiders ) Subcontractors(Details of First Aiders )
Joby John- 050-6372060 Syed Faisal Ahmed 056-5465814
Jijo Mathew 055-2152903 Prabir Kumar 056-5465847
Prior to any works taking place, all Operatives arriving at AMC project will be required to undergo a
Multiplex/Gulf Related safety induction followed by McLaren Site Safety induction, which will be held in the
induction room, by McLaren’s HSE Representative or other designated person. Once the operatives have received
the site specific safety induction, they then will be briefed on the contents of this RAMS, by their respective Site
Supervisor, from which they will then be required a sign a RAMS Briefing Register (SAF019 UAE) confirming that
they have been briefed and that they fully understand the RAMS and what is expected from them during the
execution of the site works. The Operatives will also be briefed on the Emergency and Security Procedures for the
project, which is also a part of site safety induction programme.
Any operative who will be operating any plant and equipment will be required to produce a copy of their
competency certificate/card carried out by an OSHAD approved third party training provider, to enable McLaren
to issue them with the Plant Operators Authorisation (SAF023 UAE).
Section H- Welfare facilities:
Drinking Water-
Clean drinking water will be provided on site (as per approved Logistics plan) and all operatives are to ensure they
take on enough fluids throughout the day .
It is anticipated that the following Plant and Equipment will be used during the execution of the works; other
items will also be identified on the schedule below;
Generator
Distribution Boards
110V Transformers
Fork lif
Ladder (Only for Congested Area)
Scaffolding
*Note: All relevant competency certificates (as per OHSAD /GR requirements) to be submitted to HSE
Manager/Eng./Advisor prior to start of any activity.
Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019
The following Materials will be utilised during the execution of the works, the Material Data sheets being
provided, which will allow the relevant COSHH assessments to be carried out; (See Appendix C)
During the Preparation of this RAMS the following training for the staff and operatives has been identified;
Item Description Of Training Has the Training been If not, when will be
completed? (Yes/No) completed(Date)
1 3rd party training for operative of plant and N/A
equipment
2 3rd party competency card for operators No 1/3/2019
*Note: All relevant certificates will be submitted prior to works commencing or during induction. Where the
training has not been carried out, it must do so prior to the works/activities commencing.
Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019
The following works permits will be required during the execution of the Works;
Item Description of the Work Permit Permit Issued By Tick only applicable
Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019
The works will commence on 4/03/2019 For a duration of 4 Month, as the works are scheduled to take place
during day light hours, there will be no requirement for any additional lighting
However if Night shif starts, adequate task lighting to be provided by the Genfocus
Section P- Housekeeping and Storage:
Housekeeping will be carried out as and when required and storage of materials will be in an agreed location ( as
per approved site logistics plan) within the segregated area and as agreed in subcontractor prestart meeting. The
subcontractor will remove from site.
Section Q- Hygiene and cleanliness:
Hygiene and cleanliness are the upmost requirements for the project. All works carried out within the catering
facility should comply with Etihad’s catering Hygiene Procedures and requirements. Compliance of PPE pertaining
to Hygiene and cleanliness to be strictly complied.
Section R- Working at Height
During the preparation of the RAMS, the following activities for working at height have been identified and have
been addressed within the risk assessments within Appendix D. ( to be filled if applicable to your works)
materials at site to final fix including safety precautions taken during the sequence of works )
cost time and money, but they also cause loss in both signal quality and strength. In fact, most designers
specify point-to-point or device-to-device runs to avoid needless signal loss from splices.
Pull the pull tape into the conduit, or along the cable path, for an initial measurement, and add to that
extra length for terminations, and future access coils, if specified.
23 Procedure for Termination of CAT-6 Cable in Outlet & Patch Panel: The CAT-6 Cable will be prepared and
dressed up to the Panel and the cable will be taken inside the Panel and outlet.
Splicing of all CAT-6 cable shall be carried out by means of a punch down tool.
All data/voice jacks shall be terminated using the “T568B" wiring scheme.
24 Fluke Testing for CAT-6 Cable: Upon completion of the installation, testing to all outlets will take place
using a Fluke copper cable Tester. Testing will comprise of the following elements - Headroom, Wire Map,
NEXT and ELFEXT, Length, Propagation Delay, Delay Skew, Impedance, Attenuation, Resistance, ACR, Return
Loss, Power Sum NEXT, Power Sum ELFEXT and Power Sum ACR.
25 Installation of Fiber Optic Cable: Identify exact terminating locations in advance, keeping in mind that the
cable must be pulled all the way to where it will be terminated, not just into the room. This obvious though
ofen overlooked step can lead to costly mistakes if forgotten.
26 Carefully measure the cable's path before the conduit pull to avoid the need for splices. Not only do splices
cost time and money, but they also cause loss in both signal quality and strength. In fact, most designers
specify point-to-point or device-to-device runs to avoid needless signal loss from splices.
27 Pull the pull tape into the conduit, or along the cable path, for an initial measurement, and add to that
extra length for splices, terminations, and future access coils, if specified. The amount of additional cable
needed for splicing depends on site conditions, splicing method used, and long-range plans for cable usage.
28 Choose crews based on the length of the pull, total degrees of bend, tail loading (force required to pull
cable off feed reel). In most cases, two- or three-person crews are ideal. That way, one person pays the
cable off the reel and into the duct, while one or two others pull at the other end.
29 Procedure for Termination of FOC in Patch Panel: The FOC will be prepared and dressed up to the Panel
and the cable will be taken inside the Panel.
Splicing of all FOC shall be carried out by means of a fusion-splicing machine & optical fibre cleaver.
30 The SC Pigtail (1.5m long) based will be spliced on the individual fibers & will be terminated on the splice
tray in the patch panel.
The theoretical splice loss readings, which are displayed on the fusion splice machine, shall be kept to a
maximum of 0.10 dB to reduce the number of re-splicing. The minimum splice loss shall be 0.5dB.
31 The actual splice loss of each individual splice shall be equal to or less than the stated splice loss in the
contractual specification.
If the average splice loss is greater than 0.5 dB on any two fiber spliced, then the splice shall be remade.
Maximum attempts to re-splice a particular high fiber shall be made to bring the actual splice loss within
the 0.5 dB.
32 Procedure for Fiber Optic Cable Testing:
Testing using OTDR:
An OTDR measurement shall be made on every fiber from fiber
Optic Patch Panel (origin end) to fiber optic Patch Panel (remote
End) to measure the attenuation per kilometre, afer testing all
fibers record the results. These results will give the optical length
of the link. The test will be carried out in both wavelengths 1310nm
Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019
Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019
APPENDIX A
APPENDIX B
CRISIS PLAN
Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019
CRISIS PLAN
1. Upon an incident, being discovered the first member of McLaren’s staff or the site operative
discovering the incident shall inform the Project Manager and Site HSE team through AMC Project
emergency Contact No-056-7459621.
2. Both the HSE Engineer/advisor and the First Aider are to attend the scene with their mobile. The
project Manager or authorised person waits in office ready to contact relevant emergency
services.
3. Both the HSE Engineer/advisor and the first Aider are to assess the situation and put in place the
relevant systems to end/deal with the emergency.
4. Both the HSE Engineer/advisor and the first Aider are to ensure all trades are gathered at the
assembly point and liaise with supervisor to account for all operatives - no person should leave
site.
5. Either the HSE Engineer/advisor or the first Aider phones the project Manager or site receptionist
and informs him/her of which emergency services are required.
7. Both the HSE Engineer/advisor and the first Aider waits for the emergency services at scene.
8. Once emergency services arrive, The Project Manager will telephone the relevant authorities, i.e.
the HSE/Client’s Safety Advisor/QHSE Manager/McLaren’s operations Director.
9. Both the HSE Engineer/advisor and the first Aider keep trades informed of the situation and
releases trades to return to work or leave site only when emergency services or The Project
Manager instruct that it is safe to do so, and all names of witnesses are recorded.
10. Project Manager or Construction Manager are to arrange for photographs of the scene to be
taken, and if necessary the area to be cordoned.
A full investigation of the Incident is to be carried out, with a written report being submitted the
SHEQ Director, as soon as practicably possible afer the incident, including all witness statements,
11. photos of the scene, induction and method statement records, recommendation to prevent a re-
occurrence and what action has been taken since the incident taking place.
Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019
APPENDIX C
(Not Applicable)
Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019
APPENDIX- D
RISK ASSESSMENTS
Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019
APPENDIX-E
TECHNICAL INFORMATION
Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019
Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019