Вы находитесь на странице: 1из 20

Add project/client logo

RISK ASSESSMENT METHOD STATEMENT (RAMS)

Method Statement and Risk Assessment for


Installation and Testing of Structured Cabling, at
AMC Connectivity Corridors & Concourse Bridge
Project, Maryah island,
ABUDHABI
Project No-M- 1467

Document Ref No: MCL-ME-A-MST-MSS-003 (to be obtained from McLaren DC)

Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019

SAF-098 (UAE) 09/16 Rev G 1 of 20 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

Project name AMC Connectivity Corridors & Concourse Bridge Project Project No M1467
Main Contractor McLaren Construction Ltd. Document No MCL-ME-A-MST-MSS-003
Title/Task Structured Cabling Revision No 01
Document
Date of issue 19/02/2019 Prepared By
Frasat Ahmed
Duration of
Proposed start date 12/04/2019 task 1 Month

Contents
Section A Register of Revisions
Section B Scope of Works to be undertaken:
Section C Location of the Project
Section D Location of the Works to be Undertaken with the Project
Section E Site Access/Egress and Access to the Work Zone
Section F Emergency Contacts Details and Procedures:
Section G McLaren Site Specific HSE Safety Induction:
Section H Welfare facilities:
Section I Personal Protective Equipment
Section J Plant/Equipment and tools to be Used
Section K Materials To be used.
Section L Communication/Toolbox Talks/Training Requirements:
Section M Works Permits
Section N Environmental and Waste Management:
Section O Programme for the Works:
Section P Housekeeping and Storage:
Section Q Hygiene and cleanliness
Section R Working At Height
Section S Occupational Health
Section T Sequence of Works/Activities

Appendices

Appendix A Site Logistic Plans and Other Design Information Relative to the Works
Appendix B Crisis/Emergency Plan
Appendix C COSHH Assessments and Material Data Sheets (to be provided by Subcontractor)
Appendix D Risk Assessments (to be provided by Subcontractor)
Appendix E Technical Information (to be provided by the Subcontractor)
Appendix F Risk Assessment

Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019

SAF-098 (UAE) 09/16 Rev G 2 of 20 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

Section A - Register of Revisions

Revision Date Reason for Amendment Amended By Signature Has this amendment been briefed
No (Name) to the operatives involved and have
the operatives signed the register.
00 11/02/ Mixed with ESCF Project Requirements Frasat
2019
00 11/02/ How the work to be carried at or working Frasat
2019 platform used not being Identified
00 11/02/ Risk Assessment to match the sequence of work Frasat
2019 and the activity being carried out.

This method statement has been prepared in conjunction with the following documents;
1. OSHAD regulation and requirements
2. OHSAD- Code of Practices, HSE Regulations, Technical Guidelines, Mechanisms
3. GR HSE Guidelines and Requirements
4. Federal Environmental Authority Law No 24/1999 and its supplements.
5. Federal Labour Law No 8
6. Articles (3,4,5,7) Local Law No 21/2005 (Waste Management)
7. McLaren SHE Procedures
8. McLaren’s site specific SHEQ Plan (including TMMS, SWMP, EPP).
9. McLaren’s Integrated Management System Policy Statement (IMS) .

Section B- Scope of Works to be undertaken:


The work Describes Installation and Testing of Structured Cabling for AMC Connectivity Corridors & Concourse
Bridge Project, Abu Dhabi-UAE.
The following Critical Hazards have been identified during the preparation of the scope of works, please refer to
the Risk Assessments within Appendix D.

1. Manual Handling Injuries


2. Slip Trips and Falls
3. Fall from Height
4. electrical Hazard
5. Struck by Objects
6. Use of ladders
7.Falling objects
8. Sharp Edges
9. Injury to body parts

Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019

SAF-098 (UAE) 09/16 Rev G 3 of 20 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

Section C- Location of the Project


Location of the Project;
Our project is located AMC Connectivity Corridors & Concourse Bridge in between Almaryha and Galleria Mall as
marked below.

Section D- Location of the Works to be Undertaken within the Project

Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019

SAF-098 (UAE) 09/16 Rev G 4 of 20 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

Add full sketch of the project and mark up your areas of work (logistics plan to be updated)

Section E- Site Access/Egress and Access to the Work Zone

Entrance to the Site will be from Gate no 1 as per attached drawing.


(logistics plan to be attached)

Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019

SAF-098 (UAE) 09/16 Rev G 5 of 20 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

Section F- Emergency Contacts Details and Procedures:


The following staff from both McLaren and will be on site during the execution of the works and will be
responsible for managing the works;
Name Position Company Contact Details
Paul Carlin Operations Director McLaren 056-1054691
Luke Watson Project manager McLaren 052-1022402
Prabhu Srinivasulu Construction Manager McLaren 050-9709963
Joby John HSE Manager (First Aider) McLaren 050-6372060
Evangeline Huerto First Aider McLaren 056-1852727
Jijo Mathew Safety Advisor/First Aider McLaren 055-2152903
Ramil Magano QA/QC Engineer(Fire marshal) McLaren 050-2923058
Biju MEP Engineer McLaren 056-8059139
Syed Faisal Ahmed Project Manager Genfocus 056-5465814
Anu Baby Project Engineer Genfocus 0565465807
Prabir Kumar Safety Manager Genfocus 0558179965
Prabir Kumar First Aider Genfocus 0558179965
In case of an Emergency/fire Alarm, all operatives, Staff and Visitors are required to report to the Assembly Point,
which is indicated on the site logistics drawing, as indicated by the symbol below. Where the registers will be
checked to ensure that no one is un-accounted. No one will be allowed to leave the assembly point until the
Emergency response Controller confirms that it is safe to do so.

1 Assembly Point No-01 (TBA)


2 Assembly Point No-02 (TBA)

Please refer to the attached Crisis/Emergency Plan, (Appendix B) which is to be implemented where the need
arises.
The Qualified First Aiders for the Project are listed below, and the first Aid Boxes will be available either in the
Induction/First Aid Room or in the Main Office.
McLaren: (details of First Aiders ) Subcontractors(Details of First Aiders )
Joby John- 050-6372060 Syed Faisal Ahmed 056-5465814
Jijo Mathew 055-2152903 Prabir Kumar 056-5465847

Please see below the Emergency contact details


Authority/Company Contact Telephone No.
McLaren Construction Ltd 04-3417964
Police 999
Ambulance 997
GR Emergency No 058-2864950
AMC Emergency No 056-7459621

Section G- McLaren Site Specific HSE Safety Induction:


Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019

SAF-098 (UAE) 09/16 Rev G 6 of 20 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

Prior to any works taking place, all Operatives arriving at AMC project will be required to undergo a
Multiplex/Gulf Related safety induction followed by McLaren Site Safety induction, which will be held in the
induction room, by McLaren’s HSE Representative or other designated person. Once the operatives have received
the site specific safety induction, they then will be briefed on the contents of this RAMS, by their respective Site
Supervisor, from which they will then be required a sign a RAMS Briefing Register (SAF019 UAE) confirming that
they have been briefed and that they fully understand the RAMS and what is expected from them during the
execution of the site works. The Operatives will also be briefed on the Emergency and Security Procedures for the
project, which is also a part of site safety induction programme.
Any operative who will be operating any plant and equipment will be required to produce a copy of their
competency certificate/card carried out by an OSHAD approved third party training provider, to enable McLaren
to issue them with the Plant Operators Authorisation (SAF023 UAE).
Section H- Welfare facilities:
Drinking Water-
Clean drinking water will be provided on site (as per approved Logistics plan) and all operatives are to ensure they
take on enough fluids throughout the day .

Comply with Summer Working Requirements .

Rest areas and toilet-


Rest area and toilets are being provided at site and located as per AMC logistics layout plan

Section I- Personal Protective Equipment (PPE)


The Following Personal Protective Equipment must be worn/be available during the execution of the works
activities

Type of PPE Required Yes No


Safety Helmet (as per standards) Yes
Safety Footwear (as per standards) Yes
Eye protection (as per standards) Yes
Gloves (as per standards) Yes
Hi- viz Vests Yes
Overalls (for operatives only) Yes
Ear protection Yes
Face Respirator No
Body Harness Yes
Respiratory masks Yes
Others (other specific requirements)
Please ensure that any specific precautions for PPE as identified within MSDS/COSHH assessment or any
specific requirements by supplier/manufacturer are to be complied and adhered to.

Section J- Plant and Equipment to be Used


Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019

SAF-098 (UAE) 09/16 Rev G 7 of 20 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

It is anticipated that the following Plant and Equipment will be used during the execution of the works; other
items will also be identified on the schedule below;
 Generator
 Distribution Boards
 110V Transformers
 Fork lif
 Ladder (Only for Congested Area)
 Scaffolding

*Note: All relevant competency certificates (as per OHSAD /GR requirements) to be submitted to HSE
Manager/Eng./Advisor prior to start of any activity.

(Below schedule to be completed by subcontractor)


Type of Plant/Equipment to be Used Yes No Type of Plant/Equipment to be Used Yes No
Lifing Yes Cradle No
Mechanical hoist No Excavation shoring No
Mobile elevating working platform No Hand tools Yes
Ladder Yes Electrical tools No
Hoist No CAT & Gen Set Yes
Test Equipment No Ventilation/Extraction Equip No
Task Lighting No Pump No
Scaffolding Tubular Yes Lifing slings/chains No
Mobile scaffolds No Mechanical plant No
Podium Scaffold No Others:

Section K- Materials To be used.

Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019

SAF-098 (UAE) 09/16 Rev G 8 of 20 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

The following Materials will be utilised during the execution of the works, the Material Data sheets being
provided, which will allow the relevant COSHH assessments to be carried out; (See Appendix C)

Item Material Description Has MSDS been Has the COSHH


provided and Assessment sheet been
attached? completed and attached?
1 Cat-6 Cable, Fiber Optic Cable, Data Socket, N/A N/A
Patch Panels, Racks

Section L- Communication/Tool Box Talks/Training Requirements:


Once the RAMS has been briefed to the workforce, we will also hold Tool Box Talk relative to the work activities
being carried out, these will be conducted by the HSE team, in conjunction with the relevant site supervisors, this
will ensure that the message gets across to the workforce, in their own language, thus avoiding any
misinterpretation of the RAMS/Toolbox Talk.

During the Preparation of this RAMS the following training for the staff and operatives has been identified;
Item Description Of Training Has the Training been If not, when will be
completed? (Yes/No) completed(Date)
1 3rd party training for operative of plant and N/A
equipment
2 3rd party competency card for operators No 1/3/2019

3 Riggers, Banksman No 1/3/2019

4 First aid training N/A

5 Scaffolding inspection and erection No 1/3/2019

*Note: All relevant certificates will be submitted prior to works commencing or during induction. Where the
training has not been carried out, it must do so prior to the works/activities commencing.

Section M- Works Permits

Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019

SAF-098 (UAE) 09/16 Rev G 9 of 20 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

The following works permits will be required during the execution of the Works;

Item Description of the Work Permit Permit Issued By Tick only applicable

1 Permit to Enter Confined Space McLaren

2 Permit for Lifing Operations. McLaren

3 Permit to Dig McLaren

4 Permit to work Hot cutting or Welding McLaren

5 Permit to Work in Ceiling Void McLaren

6 Permit for Roof Access McLaren

7 Permit to Work with Ladders, steps McLaren 

8 Permit to Work at Height McLaren 

9 Permit To Work – Electrical above 110V McLaren 

10 Permit To Work with COSHH Items McLaren

11 Permit To Work At External Face of The Building McLaren

12 Permit For Removal of Existing Fall Protections McLaren

Any other permits if required to be added

Section N- Environmental and Waste Management:


During the execution of the project, waste will accumulate. Skips will be provided by McLaren and will be
required to put all waste in the skips provided. All waste will be segregated for recycling as per below sequence
1. Metal
2. Plastic
3. General waste
4. Concrete waste
5. Food waste
6. Hazardous waste
7. Wood Waste
Due to the nature of the works and the actual conditions of the present site, airborne dust will be minimal,
however where necessary the area affected by the installation of the temporary works, the dust will be
suppressed by spraying water.
Drip trays to be placed under plant and generator to catch any excess oil. Approved Waste Collection Contractor
will then remove excess oil from site in oil containers and sent back to store for collection.
Section O- Programme for the Works.

Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019

SAF-098 (UAE) 09/16 Rev G 10 of 20 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

The works will commence on 4/03/2019 For a duration of 4 Month, as the works are scheduled to take place
during day light hours, there will be no requirement for any additional lighting
However if Night shif starts, adequate task lighting to be provided by the Genfocus
Section P- Housekeeping and Storage:
Housekeeping will be carried out as and when required and storage of materials will be in an agreed location ( as
per approved site logistics plan) within the segregated area and as agreed in subcontractor prestart meeting. The
subcontractor will remove from site.
Section Q- Hygiene and cleanliness:
Hygiene and cleanliness are the upmost requirements for the project. All works carried out within the catering
facility should comply with Etihad’s catering Hygiene Procedures and requirements. Compliance of PPE pertaining
to Hygiene and cleanliness to be strictly complied.
Section R- Working at Height
During the preparation of the RAMS, the following activities for working at height have been identified and have
been addressed within the risk assessments within Appendix D. ( to be filled if applicable to your works)

Item Activity Risk Assessment Reference


1 Installation and Testing of Structured Refer attached risk assessment
Cabling

Section S- Occupational Health


During the preparation of the RAMS, the following Occupational Health items have been reviewed and addressed
within this Method Statement.
Item Description of OH Item Preventative Measures, (see also within the Risk Assessments)
1 Bad Back/sprain due to improper All Operatives will be briefed on correct lifing techniques and
Manual handling avoid heavy lifing altogether
2 Hand/Arm Vibration N/A
3 Construction dust N/A
4 Noise To be Controlled
5 Sun Operatives will be required to wear long sleeve and pants to
avoid direct sunlight UV rays and drink plenty of water to avoid
dehydration
6 Skin Coveralls and gloves required at all times

Section T- Sequence of Works/Activities


The works will be carried out in the following sequences; (Subcontractor to detail out the sequence of work, from offloading the
Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019

SAF-098 (UAE) 09/16 Rev G 11 of 20 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

materials at site to final fix including safety precautions taken during the sequence of works )

1 RAMS to be briefed to all the operatives involved in the work.


2 STARRT card to be prepared by assessing the area of work prior starting the work.
3 Supervisor to ensure all operatives have received a Multiplex and McLaren site basic induction
4 Supervisor to ensure all operatives have adequate PPE for the job including Full body harness (If required).
5 Supervisor to ensure that all operatives entering the facility have adequate disposable PPE (coverall, hand
gloves).
6 Supervisor to ensure that the site is clean and ready to start the work
7 Supervisor to ensure adequate tools are provided and should be visibly clean and tidy. Advise Site manager
if more tools are needed.
8 Supervisor to ensure that all materials taken into the facility are covered and equipment’s to be used are
clean.
9 Supervisor to ensure proper working platforms such as ladders and scaffoldings are been used and make
sure that all the working platforms are having permit to work.
10 Any damage or irregularity in the supply noted on unpacking will inform to the proper authorities as per
the standard practice.
11 Installation inspection will be carrying out as per specification
12 Site QC Inspector in coordination will conduct inspection with Engineer/Employer Representative prior to
submitting Inspection and/or Test Request to the Engineer/Employer Representative.
13 Inspection for the Engineer/Employer Representative shall be arranged accordingly.
14 Procedure of CAT-6 Installation: CAT-6 cable run will not exceed a maximum installed length of 90 meters,
and when routing shielded cabling or sitting RJ-45 outlets a minimum separation distance will be
maintained, from possible sources of EMI (Electro Magnetic Interference).
15 CAT-6 Cables are to be installed to locations specified using the provided cable trunking in the ceiling voids
in the corridors
16 The CAT-6 cables are to be pulled in manually ensuring that the pulling tension does not exceed the
manufacturers recommended guidelines.
17 Once cables are installed and to point they shall be cut to length and terminated to an RJ45 jack
terminating within the provided trunking.
18 Before pulling the CAT-6 cable the conduits will be checked with the fish tape inside to be assured that
there are no blockages in the route.
19 Connect the strength member of the cable to the pull line. Unless cables are designed for such use, basket
grips and similar methods of attachment should not be used.
20 Use lots of large pull boxes and divide pulls in half or even thirds at corners or pull boxes. A pulling
operation must be stopped if pulling tensions reach the cable's limit. The discontinued pull will have to be
aborted, the cable pulled back out and replaced on the reel, and the pull started again using shorter runs.
The cable may be reused if the pull or extraction has not damaged it.
21 Identify exact terminating locations in advance, keeping in mind that the cable must be pulled all the way
to where it will be terminated, not just into the room. This obvious though ofen overlooked step can lead
to costly mistakes if forgotten.
22 Carefully measure the cable's path before the conduit pull to avoid the need for splices. Not only do splices
Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019

SAF-098 (UAE) 09/16 Rev G 12 of 20 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

cost time and money, but they also cause loss in both signal quality and strength. In fact, most designers
specify point-to-point or device-to-device runs to avoid needless signal loss from splices.
Pull the pull tape into the conduit, or along the cable path, for an initial measurement, and add to that
extra length for terminations, and future access coils, if specified.
23 Procedure for Termination of CAT-6 Cable in Outlet & Patch Panel: The CAT-6 Cable will be prepared and
dressed up to the Panel and the cable will be taken inside the Panel and outlet.
Splicing of all CAT-6 cable shall be carried out by means of a punch down tool.
All data/voice jacks shall be terminated using the “T568B" wiring scheme.
24 Fluke Testing for CAT-6 Cable: Upon completion of the installation, testing to all outlets will take place
using a Fluke copper cable Tester. Testing will comprise of the following elements - Headroom, Wire Map,
NEXT and ELFEXT, Length, Propagation Delay, Delay Skew, Impedance, Attenuation, Resistance, ACR, Return
Loss, Power Sum NEXT, Power Sum ELFEXT and Power Sum ACR.
25 Installation of Fiber Optic Cable: Identify exact terminating locations in advance, keeping in mind that the
cable must be pulled all the way to where it will be terminated, not just into the room. This obvious though
ofen overlooked step can lead to costly mistakes if forgotten.
26 Carefully measure the cable's path before the conduit pull to avoid the need for splices. Not only do splices
cost time and money, but they also cause loss in both signal quality and strength. In fact, most designers
specify point-to-point or device-to-device runs to avoid needless signal loss from splices.
27 Pull the pull tape into the conduit, or along the cable path, for an initial measurement, and add to that
extra length for splices, terminations, and future access coils, if specified. The amount of additional cable
needed for splicing depends on site conditions, splicing method used, and long-range plans for cable usage.
28 Choose crews based on the length of the pull, total degrees of bend, tail loading (force required to pull
cable off feed reel). In most cases, two- or three-person crews are ideal. That way, one person pays the
cable off the reel and into the duct, while one or two others pull at the other end.
29 Procedure for Termination of FOC in Patch Panel: The FOC will be prepared and dressed up to the Panel
and the cable will be taken inside the Panel.
Splicing of all FOC shall be carried out by means of a fusion-splicing machine & optical fibre cleaver.
30 The SC Pigtail (1.5m long) based will be spliced on the individual fibers & will be terminated on the splice
tray in the patch panel.
The theoretical splice loss readings, which are displayed on the fusion splice machine, shall be kept to a
maximum of 0.10 dB to reduce the number of re-splicing. The minimum splice loss shall be 0.5dB.
31 The actual splice loss of each individual splice shall be equal to or less than the stated splice loss in the
contractual specification.
If the average splice loss is greater than 0.5 dB on any two fiber spliced, then the splice shall be remade.
Maximum attempts to re-splice a particular high fiber shall be made to bring the actual splice loss within
the 0.5 dB.
32 Procedure for Fiber Optic Cable Testing:
Testing using OTDR:
An OTDR measurement shall be made on every fiber from fiber
Optic Patch Panel (origin end) to fiber optic Patch Panel (remote
End) to measure the attenuation per kilometre, afer testing all
fibers record the results. These results will give the optical length
of the link. The test will be carried out in both wavelengths 1310nm
Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019

SAF-098 (UAE) 09/16 Rev G 13 of 20 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

& 1550nm for single mode in both directions.


33 The OTDR test result will be provided in the hard copy form in labeled ring binder with signature of witness
to verify execution of all tests.
The documentation package will consist of the following:
a) Calibration Certificate
b) OTDR test in both direction @ 1310nm & 1550nm with OTDR.
Pass criteria for each fiber:
Maximum loss Requirement: Optical Cable Loss < or = 0.4000 dB/km [1310nm]
Maximum loss Requirement: Optical Cable Loss < or = 0.400 dB/km [1550nm]

Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019

SAF-098 (UAE) 09/16 Rev G 14 of 20 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

APPENDIX A

Site Logistics Plan

APPENDIX B

CRISIS PLAN

Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019

SAF-098 (UAE) 09/16 Rev G 15 of 20 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

CRISIS PLAN

1. Upon an incident, being discovered the first member of McLaren’s staff or the site operative
discovering the incident shall inform the Project Manager and Site HSE team through AMC Project
emergency Contact No-056-7459621.

2. Both the HSE Engineer/advisor and the First Aider are to attend the scene with their mobile. The
project Manager or authorised person waits in office ready to contact relevant emergency
services.

3. Both the HSE Engineer/advisor and the first Aider are to assess the situation and put in place the
relevant systems to end/deal with the emergency.

4. Both the HSE Engineer/advisor and the first Aider are to ensure all trades are gathered at the
assembly point and liaise with supervisor to account for all operatives - no person should leave
site.

5. Either the HSE Engineer/advisor or the first Aider phones the project Manager or site receptionist
and informs him/her of which emergency services are required.

6. The Project Manager calls all relevant McLaren staff.

7. Both the HSE Engineer/advisor and the first Aider waits for the emergency services at scene.

8. Once emergency services arrive, The Project Manager will telephone the relevant authorities, i.e.
the HSE/Client’s Safety Advisor/QHSE Manager/McLaren’s operations Director.

9. Both the HSE Engineer/advisor and the first Aider keep trades informed of the situation and
releases trades to return to work or leave site only when emergency services or The Project
Manager instruct that it is safe to do so, and all names of witnesses are recorded.

10. Project Manager or Construction Manager are to arrange for photographs of the scene to be
taken, and if necessary the area to be cordoned.
A full investigation of the Incident is to be carried out, with a written report being submitted the
SHEQ Director, as soon as practicably possible afer the incident, including all witness statements,
11. photos of the scene, induction and method statement records, recommendation to prevent a re-
occurrence and what action has been taken since the incident taking place.

Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019

SAF-098 (UAE) 09/16 Rev G 16 of 20 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

APPENDIX C

COSHH ASSESSMENTS AND MSDS

(Not Applicable)

Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019

SAF-098 (UAE) 09/16 Rev G 17 of 20 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

APPENDIX- D

RISK ASSESSMENTS

Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019

SAF-098 (UAE) 09/16 Rev G 18 of 20 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

APPENDIX-E

TECHNICAL INFORMATION

Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019

SAF-098 (UAE) 09/16 Rev G 19 of 20 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

Method Statement Title Installation and Testing of Structured Doc Ref No: MCL-ME-A-MST-MSS-003
Cabling
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 01
Prepared By Frasat Ahmed Approved By Revision Date: 19-02-2019

SAF-098 (UAE) 09/16 Rev G 20 of 20 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET

Вам также может понравиться