Академический Документы
Профессиональный Документы
Культура Документы
COURSE
PROJECT SCHEDULE
MANAGEMENT
AMIDEAST KUWAIT 2
PROJECT SCHEDULE MANAGEMENT
Project Schedule
Management includes
the processes
required to ensure the
timely completion of
the project.
AMIDEAST KUWAIT 6
6.1 PLAN SCHEDULE MANAGEMENT
9
AMIDEAST KUWAIT 7
6.1 PLAN SCHEDULE MANAGEMENT
Plan Schedule Man.
The process of
establishing the policies,
procedures and
documentation for
planning, developing,
managing, executing
and controlling the
project schedule.
key benefit
Provides guidance and
direction on how the
Project Schedule will be
managed throughout
the project
AMIDEAST KUWAIT 8
6.1 PLAN SCHEDULE MANAGEMENT
These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management
Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017, Pages 526 & 546.
AMIDEAST KUWAIT 9
6.1 PLAN SCHEDULE MANAGEMENT
(TOOLS & TECHNIQUES)
AMIDEAST KUWAIT 10
6.1 PLAN SCHEDULE MANAGEMENT
(OUTPUTS)
AMIDEAST KUWAIT 11
6.1 PLAN SCHEDULE MANAGEMENT
(OUTPUTS)
Budget
Duration / Method/Rules/ac associated
Outputs
Process/Activity Responsibility Frequency curacy/ forms (if any) -Schedule Management
(What?) (Who?) (When?) (How?) (How Much?)
Plan
define activities Jane 3 weeks Decomposition $2000
(Use OPA)
AMIDEAST KUWAIT 13
6.2 DEFINE ACTIVITIES
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth
Edition, Project Management Institute, Inc., 2017, Figure 6-5, Page 183.
AMIDEAST KUWAIT 14
6.2 DEFINE ACTIVITIES
Define Activities
Project X The process of
identifying and
documenting the
specific actions to be
performed to produce
1. 2. 3.
the project deliverables
Deliverable Deliverable Deliverable
The key benefit of this
Work Package Level
process is that it
decomposes work
1.1 Activity packages into schedule
1.2 Activity activities that provide a
2.1 Activity
basis for estimating,
3.2 Activity
scheduling, executing,
monitoring, and
Activity List / Milestone List
controlling the project
work
This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management
Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017, Page 536.
AMIDEAST KUWAIT 15
6.2 DEFINE ACTIVITIES (INPUTS)
Discussion:
Why not only a Scope Statement?
This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management
Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017,
AMIDEAST KUWAIT 16
6.2 DEFINE ACTIVITIES (TOOLS & TECHNIQUES)
AMIDEAST KUWAIT 17
6.2 DEFINE ACTIVITIES
1. Control Account. A management control point can be placed at selected
management points of the WBS above the work package level where
scope, budget, actual cost, and schedule are integrated and compared to
earned value for performance measurement.. All work and effort
performed within a control account is documented in a control account
plan.
2. Planning Package. A work breakdown structure component below the
control account with known work content but without detailed schedule
activities.
Code of Account : The numbering system for providing unique identifiers for all
components of the WBS
Chart of Account : The financial numbering system of the organization used to
monitor project costs by category
Activities
AMIDEAST KUWAIT 19
6.2 DEFINE ACTIVITIES (OUTPUTS)
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition,
Project Management Institute, Inc., 2017, Page 152.
AMIDEAST KUWAIT 20
6.2 DEFINE ACTIVITIES (OUTPUTS)
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition,
Project Management Institute, Inc., 2017, Page 152.
AMIDEAST KUWAIT 21
6.2 DEFINE ACTIVITIES (OUTPUTS)
AMIDEAST KUWAIT 22
PROJECT TIME MANAGEMENT
AMIDEAST KUWAIT 23
6.3 SEQUENCE ACTIVITIES
AMIDEAST KUWAIT 24
6.3 SEQUENCE ACTIVITIES
Sequence Activities
START A B C D E FINISH
The process of
Not Efficient identifying and
documenting the
A B relationships among
START E FINISH the project activities.
C D
More Efficient
AMIDEAST KUWAIT 25
6.3 SEQUENCE ACTIVITIES (TOOLS & TECHNIQUES)
AMIDEAST KUWAIT 26
6.3 SEQUENCE ACTIVITIES (TOOLS & TECHNIQUES)
AMIDEAST KUWAIT 27
6.3 SEQUENCE ACTIVITIES TOOLS & TECHNIQUES)
• Finish-to-finish (FF).
Tools & Techniques
A logical relationship in which a successor activity .1 Precedence diagramming
cannot finish until a predecessor activity has finished. method
For example, writing a document (predecessor) is .2 Dependency
required to finish before editing the document determination
(successor) can finish. and integration
Activity Activity .3 Leads and lags
1 2 .4 Project management
• Start-to-finish (SF).
information system
A logical relationship in which a successor activity
cannot finish until a predecessor activity has started.
For example, a new accounts payable system
(successor) has to start before the old accounts
payable system can be shut down (predecessor).
Activity Activity
1 2
AMIDEAST KUWAIT 28
6.3 SEQUENCE ACTIVITIES (TOOLS & TECHNIQUES)
• Project or Non-Project:
External Internal
AMIDEAST KUWAIT 29
6.3 SEQUENCE ACTIVITIES (TOOLS & TECHNIQUES)
• Two dependencies can be applicable at the same time in the following ways:
• mandatory external dependencies, mandatory internal dependencies,
discretionary external dependencies, or discretionary internal dependencies.
Mandatory dependencies.
1. dependencies are sometimes referred to as hard logic or hard dependencies
2. Activities that are legally or contractually required or inherent in the nature of
the work.
3. Often involve physical limitations, such as on a construction project, where it is
impossible to erect the superstructure until after the foundation has been built.
Discretionary dependencies.
1. Sometimes referred to as preferred logic, preferential logic, or soft logic.
2. Established based on knowledge of best practices within a particular area.
For example, generally accepted best practices recommend that during
construction, the electrical work should start after finishing the plumbing work.
AMIDEAST KUWAIT 30
6.3 SEQUENCE ACTIVITIES (TOOLS & TECHNIQUES)
AMIDEAST KUWAIT 31
6.3 SEQUENCE ACTIVITIES (TOOLS & TECHNIQUES)
AMIDEAST KUWAIT 32
6.3 SEQUENCE ACTIVITIES (OUTPUTS)
AMIDEAST KUWAIT 33
6.3 SEQUENCE ACTIVITIES (OUTPUTS)
Outputs
Project Documents Updates .1 Project schedule
network diagrams
Project documents that may be updated as a .2 Project documents
result of carrying out this process include but updates
are not limited to: • Activity attributes
• Activity list
Activity attributes. • Assumption log
• Milestone list
Activity list.
Assumption log.
Milestone list.
AMIDEAST KUWAIT 34
PROJECT SCHEDULE MANAGEMENT
AMIDEAST KUWAIT 35
6.4 ESTIMATE ACTIVITY DURATIONS
This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management
Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017, Page 539.
AMIDEAST KUWAIT 37
6.4 ESTIMATE ACTIVITY DURATIONS
Estimating activity durations uses information from the the person or group
who is most familiar with the specific activity. The duration estimate is
progressively elaborated.
In many cases, not only the number of resources that are expected to be
available to accomplish an activity, along with the skill proficiency of those
resources, can determine the activity’s duration but also other factors can
affect activity’s duration.
Other factors for consideration when estimating duration include:
I. Advances in technology.
Advances in technology, may impact duration and resource needs.
II. Motivation of staff.
The project manager also needs to be aware of Student Syndrome—or
procrastination—when people start to apply themselves only at the last
possible moment before the deadline, and Parkinson’s Law where work
expands to fill the time available for its completion.
AMIDEAST KUWAIT 38
6.4 ESTIMATE ACTIVITY DURATIONS
III. Law of diminishing returns.
Additions of one factor start to yield progressively smaller or diminishing
increases in output.
IV. Number of resources.
Increasing the number of resources to twice the original number of the
resources does not always reduce the time by half
AMIDEAST KUWAIT 39
6.4 ESTIMATE ACTIVITY DURATIONS
(TOOLS & TECHNIQUES)
AMIDEAST KUWAIT 40
6.4 ESTIMATE ACTIVITY DURATIONS
(TOOLS & TECHNIQUES)
AMIDEAST KUWAIT 41
6.4 ESTIMATE ACTIVITY DURATIONS
(TOOLS & TECHNIQUES)
AMIDEAST KUWAIT 42
6.4 ESTIMATE ACTIVITY DURATIONS
Normal Distribution
We use this concept to measure our estimating quality
“ how accurate were our estimates
Or how spread out our data is”
-1 σ +1 σ
-2 σ +2 σ
-3 σ +3 σ
Tе, Project
Duration
68.26%
95.46%
99.73%
LCL UCL
AMIDEAST KUWAIT 43
6.4 ESTIMATE ACTIVITY DURATIONS
(TOOLS & TECHNIQUES)
AMIDEAST KUWAIT 44
6.4 ESTIMATE ACTIVITY DURATIONS
(TOOLS & TECHNIQUES)
.8 Meetings
Optimistic Pessimistic
Lower
AMIDEAST KUWAIT 45
6.4 ESTIMATE ACTIVITY DURATIONS
(TOOLS & TECHNIQUES)
AMIDEAST KUWAIT 46
6.4 ESTIMATE ACTIVITY DURATIONS
(TOOLS & TECHNIQUES)
AMIDEAST KUWAIT 48
6.5 DEVELOP SCHEDULE
3 wks 4 wks 2 wks
A B D Develop Schedule
Finish
The process of
Start
8 wks 2 wks 5 wks analyzing activities
C E F sequencing,
durations, resource
requirements and
schedule constraints
to create the project
schedule model.
This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management
Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017, Page 537.
AMIDEAST KUWAIT 49
6.5 Develop Schedule
•These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management
Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017.
AMIDEAST KUWAIT 50
6.5 Develop Schedule
AMIDEAST KUWAIT 52
6.5 DEVELOP SCHEDULE (TOOLS & TECHNIQUES)
AMIDEAST KUWAIT 53
6.5 DEVELOP SCHEDULE (TOOLS & TECHNIQUES)
Start A C E F End
14
AMIDEAST KUWAIT 54
6.5 DEVELOP SCHEDULE (TOOLS & TECHNIQUES)
10
CRITICAL PATH METHOD
STEP 1: FORWARD PASS B
2 8 2 1
Start A C E F End
14
Start A
AMIDEAST KUWAIT 55
6.5 DEVELOP SCHEDULE (TOOLS & TECHNIQUES)
TF = LS – ES = LF – EF FF = EF- ES smallest
AMIDEAST KUWAIT 56
6.5 DEVELOP SCHEDULE (TOOLS & TECHNIQUES)
AMIDEAST KUWAIT 57
6.5 DEVELOP SCHEDULE (TOOLS & TECHNIQUES)
AMIDEAST KUWAIT 58
6.5 DEVELOP SCHEDULE (TOOLS & TECHNIQUES)
AMIDEAST KUWAIT 59
6.5 DEVELOP SCHEDULE (TOOLS & TECHNIQUES)
Start A C E F END
AMIDEAST KUWAIT 60
6.5 DEVELOP SCHEDULE (TOOLS & TECHNIQUES)
Start A C E F END
AMIDEAST KUWAIT 61
6.5 DEVELOP SCHEDULE (TOOLS & TECHNIQUES)
Start A C E F END
AMIDEAST KUWAIT 62
6.5 DEVELOP SCHEDULE (TOOLS & TECHNIQUES)
Start A C E F END
AMIDEAST KUWAIT 63
6.5 DEVELOP SCHEDULE (TOOLS & TECHNIQUES)
Start A C E F END
TF = LS – ES = LF – EF
D
FF = EF- ES smallest
AMIDEAST KUWAIT 64
6.5 DEVELOP SCHEDULE (TOOLS & TECHNIQUES)
0 A 2 2 B 5 5 C 9 9 D 17
0 2 2 2 3 5 5 4 9 9 8 17
0 2 2 F 5 5 G 9 9
H 14
Start E
End
3 2 5 5 3 8 8 4 12 12 5 17
0 I 2 2 J 3
5 2 7 7 1 8
AMIDEAST KUWAIT 65
6.5 DEVELOP SCHEDULE (TOOLS & TECHNIQUES)
0 A 2 2 B 5 5 C 9 9 D 17
0 2 2 2 3 5 5 4 9 9 8 17
0 2 2 5 5 9 9 14
Start E F G H
3 4 5
End
3 2 5 5 8 8 12 12 17
0 I 2 2 J 3
The calculations are really simple.
For Activity F:
5 2 7 7 1 8
Total Float = LF of F – EF of F => 8 – 5 = 3
Free Float = ES of G – EF of F => 5 – 5 = 0
For Activity J:
Total Float = LF of J – EF of J => 8 – 3 = 5
Free Float = ES of G – EF of J => 5 – 3 = 2
Note: Free float can only occur when two or more
activities share a common successor.
AMIDEAST KUWAIT 66
6.5 DEVELOP SCHEDULE (TOOLS & TECHNIQUES)
It is developed from the critical path method Tools & Techniques
approach. .1 Schedule network analysis
Resources are assigned to the activities using the most .2 Critical path method
likely durations .3 Resource optimization
i.e. the time it would take to complete the activity 50% .4 Data analysis
of the time. • What-if scenario analysis
The critical chain method introduces the concept of • Simulation
buffers and buffer management to protect the project .5 Leads and lags
completion date. .6 Schedule compression
.7 PMIS
Critical chain schedule removes buffers from individual
tasks and instead creates: .8 Agile release planning
AMIDEAST KUWAIT 67
6.5 DEVELOP SCHEDULE (TOOLS & TECHNIQUES)
AMIDEAST KUWAIT 68
6.5 DEVELOP SCHEDULE (TOOLS & TECHNIQUES)
AMIDEAST KUWAIT 69
6.5 DEVELOP SCHEDULE (TOOLS & TECHNIQUES)
Resource leveling.
A technique in which start and finish dates
are adjusted based on resource constraints
with the goal of balancing demand for
resources with the available supply.
Used When,
Resources are only available at certain
times, or in limited quantities
Resources are over-allocated, or
supplied at a constant level.
Implication
Can often cause the original critical path
to increase.
Available float is used for leveling
resources. Consequently, the critical path
through the project schedule may change.
AMIDEAST KUWAIT 70
6.5 DEVELOP SCHEDULE (TOOLS & TECHNIQUES)
Resource Smoothing.
• A resource optimization technique in which free and total float are used without
affecting the critical path.
• A technique that adjusts the activities of a schedule model such that the
requirements for resources on the project do not exceed certain predefined
resource limits.
Criteria Resource leveling Resource Smoothing
Project Duration May result in change in project Make use of float, and will not result in change of
And Critical Path duration. project duration.
Resource constraints, like you Desired limits, like although we have 45 hours
do not have more than 45 available for given resource, we wish to allocate
Driven By
hours of the given resource for 38 hours per week so we have some breathing
a week. space.
The allocation limits identified The desired limit identified in resource smoothing
Mandatory or
in resource leveling must be may not be applied in some cases, if we do not
optional
applied. have slack.
The resource leveling is done We apply resource smoothing after applying
Who is done first
first resource leveling.
AMIDEAST KUWAIT 71
6.5 DEVELOP SCHEDULE (TOOLS & TECHNIQUES)
AMIDEAST KUWAIT 72
6.5 DEVELOP SCHEDULE (TOOLS & TECHNIQUES)
AMIDEAST KUWAIT 73
6.5 DEVELOP SCHEDULE (TOOLS & TECHNIQUES)
AMIDEAST KUWAIT 75
6.5 DEVELOP SCHEDULE (TOOLS & TECHNIQUES)
A (2wks) 3200 $
B (2wks) 800$
After Crashing
AMIDEAST KUWAIT 76
6.5 DEVELOP SCHEDULE (TOOLS & TECHNIQUES)
A (3wks) 2000 $
B (2wks) 800$
AMIDEAST KUWAIT 77
6.5 Develop Schedule (TOOLS & TECHNIQUES)
AMIDEAST KUWAIT 78
6.5 Develop Schedule (TOOLS & TECHNIQUES)
a. A, C, E, and F
b. A, B, D, and F
c. A, B, E, and F
d. C, A, F, and G
AMIDEAST KUWAIT 79
6.5 DEVELOP SCHEDULE (OUTPUT)
AMIDEAST KUWAIT 80
DIFFERENCE BETWEEN BASELINE
SCHEDULE AND PROJECT SCHEDULE
– The Project Schedule is a “living” document, whereas the Schedule Baseline
is the “frozen” version of it.
– The Project Schedule is updated as the project is being executed. On the
other hand, Schedule Baseline is only modified as a result of an approved
change request related to project scope changes.
– The Schedule Baseline is a “Target”, whereas the Project Schedule is
updated and reported in order to analyze the project’s current status.
– The Project Schedule is a Project Document. On the other hand the
Schedule Baseline is a part of the Project Management Plan.
AMIDEAST KUWAIT 81
6.5 DEVELOP SCHEDULE (OUTPUTS)
AMIDEAST KUWAIT 82
6.5 DEVELOP SCHEDULE (OUTPUTS)
AMIDEAST KUWAIT 83
6.5 DEVELOP SCHEDULE (OUTPUTS)
AMIDEAST KUWAIT 84
6.5 DEVELOP SCHEDULE (OUTPUTS)
Milestone Chart
61
AMIDEAST KUWAIT 85
PROJECT SCHEDULE MANAGEMENT
AMIDEAST KUWAIT 86
6.6 CONTROL SCHEDULE
Control Schedule
The process of
monitoring the status
of the project
activities to update
project progress and
manage changes to
the schedule baseline
to achieve the plan.
This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management
Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017, Page 534.
AMIDEAST KUWAIT 88
6.6 CONTROL SCHEDULE (TOOLS AND TECHNIQUES)
AMIDEAST KUWAIT 89
6.6 CONTROL SCHEDULE (TOOLS AND TECHNIQUES)
AMIDEAST KUWAIT 90
6.6 CONTROL SCHEDULE (TOOLS AND TECHNIQUES)
AMIDEAST KUWAIT 92
6.6 CONTROL SCHEDULE (TOOLS AND TECHNIQUES)
AMIDEAST KUWAIT 93
THANK YOU
94