Академический Документы
Профессиональный Документы
Культура Документы
ENG-3200b
Document # 67-162884-00 GAS PANEL SYSTEMS TESTING & ACCEPTANCE 2 OF 18
1.0 Purpose
The intent of this document is to define the test criteria and limits for gas panel systems.
These tests are to be performed by the Novellus supplier who fabricates a gas delivery
system prior to delivery to Novellus.
2.0 Scope
This document applies to gas panel assemblies that are fabricated by Novellus suppliers
and subsequently integrated into Novellus Vacuum based process tools. For the
purposes of this document the term gas panel is considered generic for purge panels, gas
boxes, and other similar assemblies.
3.0 Definitions
Gas Panel - A complete system comprised of valves, filters, MFC’s, manifolds, etc. used to
control the flow of gasses to a Novellus Process Tool. Gas panels are usually
integrated to combine and control the flows of multiple gas types within a
common set of manifolds.
Gas Box - A gas panel that has been packaged within an enclosure, usually for the purpose
of providing a controlled exhausted environment.
Assembly - A supplier compiled package used to capture all gasbox information relevant to
Data Files its assembly, test, and performance.
6.0 General
7.1 It is recommended that all components to be used in gas panel assemblies be audited
against the appropriate Novellus control document prior to commencement of the
assembly process.
7.2 Audits are performed against one of the following document types, but not both:
7.2.1 The Novellus Systems, Inc. assembly BoM.
7.2.2 The Novellus specification document used to communicate new design
requirements.
7.3 Components are to be checked against the manufacturer' s documentation to verify
the functional information on the component (flow rate, gas type, flow direction,
etc) is correct.
8.0 Pre-Assembly Component Testing
8.1 Although not required, suppliers may perform pre-assembly component testing to
proactively remove non-conformant materials from the assembly process. Novellus
Systems, Inc. recommends the use of appropriate statistical methods to determine
the proper frequency and level of pre-assembly testing to be performed.
9.0 Post Assembly Component Audits
9.1 Post assembly Component audits are used to confirm that the builds have been
performed with the correct components, and are especially vital if pre-assembly
audits have not been performed.
9.2 All components in the assembly shall be audited, with particular emphasis on
critical components in the flow paths.
9.3 Verify that all VCR fittings have labels appropriately installed. See section 20.0 for
label requirements and installation examples.
Document # 67-162884-00 GAS PANEL SYSTEMS TESTING & ACCEPTANCE 5 OF 18
10.1 All components serialized by OEM manufacturers shall be reference catalogued for
inclusion in the data files.
10.2 Serialized components shall be identified in a matrix that associates the component
manufacturer, type/description, manufacturer serial number and Novellus reference
designator as defined in the Novellus flow schematic.
10.3 The serialized component matrix may be developed at the beginning or end of the
assembly process as dictated by Supplier preference. Often, this decision will be
based on the physical location of the OEM part serial number.
10.3.1 Note that component reject may necessitate update of this list if created
early in the process.
10.4 Serialized parts typically include, but are not limited to:
10.4.1 MFC'
s
10.4.2 MFM'
s
10.4.3 Pressure Regulators
10.4.4 Pressure Transducers & Display Units
11.0 Visual Inspection & Fit Check
11.1 Assemblies shall be visually inspected for defects in workmanship and cosmetic
flaws.
11.2 Painted surfaces to be free of scratches and chips, and should unless otherwise
specified conform to the finish requirements of Novellus Specification
75-00001-XX.
11.3 All fabricated parts shall be labeled per the appropriate section of the Novellus Part
Marking & Identification specification. ( 74-024094-00.)
11.4 Pneumatic connections are to be verified and labeled per the pneumatic schematic,
and shall be organized and tie wrapped into bundles. Extra length shall be provided
in the pneumatic lines to prevent stress or tension in the lines during operation and
maintenance.
11.5 All separable components (cover panels, doors, exhaust flanges, etc.) shall be
installed and verified for appropriate fit.
12.0 Enclosure Exhaust Verification (Applicable only to Gas Boxes)
12.1 Exhaust airflow is to be verified for all new designs and associated configurations in
accordance with the requirements defined in the Novellus Gas Box Airflow and
Tracer Gas Bench Testing Requirements Specification 67-162885-00.
12.1.1 Novellus recommends performing airflow testing directly after assembly
for new enclosure designs.
12.1.2 Subsequent design iterations are typically considered of low risk, so
testing may be performed later if preferred by the supplier.
Document # 67-162884-00 GAS PANEL SYSTEMS TESTING & ACCEPTANCE 6 OF 18
12.2 A new design is typically one that has one or more of the following features relative
to the "master" gas box:
12.2.1 Unique flow schematic
12.2.2 Enclosure modifications
12.2.3 Part changes that are significant enough to alter the airflow
characteristics of the finished assembly
12.3 Gas boxes considered to be of the same configuration will generally be
characterized by Novellus customer defined changes such as
12.3.1 Preferred part manufacturers or materials of construction
12.3.2 Color changes
12.3.3 Flow rate changes/special calibrations
12.4 Airflow test data shall be compiled in compliance with 67-162885-00.
12.5 Gas boxes of the same configuration may be qualified with airflow testing data from
the Master Configuration (in lieu of new testing).
12.5.1 In lieu of data is acceptable for "same" configurations, but must
reference the Novellus part number of the in lieu assembly.
13.0 Panel Leak Integrity
13.5.3 Apply VCR fitting label after fitting is tightened. See section 20.0 for
VCR fitting label requirement and installation examples.
14.1 Static Particle testing of finished assemblies is required for all assemblies.
14.1.1 Testing is to be performed after conclusion of all other functional
testing.
14.2 Static Test Criteria (Reference current SEMI E-49.8 standard and SEMI F-28 test
method)
14.2.1 Particle levels shall be confirmed by using a laser particle counter (LPC)
or a condensation nucleus counter (CNC) with a detection limit of .05µm
or better
14.2.2 Each flow channel must be tested at a minimum flow rate of .05 SCFM
N2 or Ar for a minimum duration per current SEMI standard.
14.2.3 Static Testing Detection
14.2.3.1 1 per sample for a particle size ≥ 0.05µm
14.2.3.2 Zero per sample for a particle size ≥ 0.1µm
15.0 Component Calibration & Performance Verification
15.1 Pressure regulator’s lock-up, creep, and set point stability shall meet manufacturer
specification. If manufacturer does not have the lock-up, creep, and set point
stability specified, use the following values for general purpose:
Reference SEMI F101 for test method.
Test measurement Specification
Lock-up rate 3 psi
Creep rate 10 psi for 8 hour period (include Lock-up rate)
Set point stability ± 5% of pressure set point
15.2 MFC & MFM calibration and performance is to be verified against the
manufacturer' s published literature or Novellus defined requirements (as identified
in the gasbox functional specification) using an appropriately sized calibrated
standard.
15.3 If no published standard condition and test information exists, the following
guidelines shall apply.
15.3.1 Standard Inlet pressure: As defined by Novellus Functional Specification
15.3.2 Standard Outlet pressure: Vacuum, <5 Torr
15.3.3 MFC and MFM
Document # 67-162884-00 GAS PANEL SYSTEMS TESTING & ACCEPTANCE 8 OF 18
16.1 General
16.1.1 Functional verification against expected operation (as defined by the
component manufacturer) is to be performed against all panel
components while in the completed assembly state. Individual
component testing prior to installation into the panel may also be
performed per supplier preference.
16.2 Grounding
16.2.1 Verify that all removable panels that have a ground wire attachment to
the chassis have a panel to chassis resistance no greater than .1Ω
Document # 67-162884-00 GAS PANEL SYSTEMS TESTING & ACCEPTANCE 9 OF 18
16.3 Interlocks
16.3.1 All interlock hardware supplied by the gas panel supplier shall be
verified for proper operation against the Novellus interlock matrix or
schematic.
16.3.2 Interlocks shall be tested individually.
16.3.3 Interlocks shall be verified for preferential gas valve closure per the
Novellus interlock schematic.
16.3.4 Electrical interlocks shall be verified for proper switch closures and
harness continuity at the bulkhead connectors on the enclosure.
16.4 Gas Flow Channels
16.4.1 All channels shall be tested under conditions that simulate the normal
functional state of the completed assembly. This includes, but is not
limited to parameters such as:
16.4.1.1 Gasline inlet gas pressures
16.4.1.2 MFC/MFM pressure differentials
16.4.1.3 Purge loop Transducer supply pressure
16.4.2 All component Electrical and Pneumatic functional testing shall be
performed from the appropriate interface bulkhead in order to ensure
integrity of the entire control circuit.
16.4.2.1 Direct connection to flow controllers, pneumatic valving,
transducers, etc. is only to be done for troubleshooting
purposes.
16.4.2.2 Read-back signals shall be verified for all flow controllers,
meters and transducers.
16.4.2.3 Channel final functional tests shall be invalidated by
disconnection of any tested device from its associated control
input.
17.0 Post Test Packaging Preparation
17.1 All channels shall be fully N2 purged for one minute using the inlet pressure
identified within the Novellus Specification.
17.2 After completion of the 1-minute flow period, the outlet fitting shall be capped and
the line allowed charging to inlet pressure, at which point the most upstream
isolation valve shall be closed.
17.3 Cap the inlet fitting, and affix a removable tag to enclosure indicating that all
channels have been charged with N2 at the respective channel pressures.
18.0 Pre-shipment Inspection and Packaging
18.3 Verify all panels or other components removed during functional test have been
reinstalled.
18.4 Verify that all necessary hazard identification labels have been applied to the
exterior of the assembly.
18.5 Verify that flow schematic label has been affixed to interior of enclosure door.
18.6 Wipe down the assembly with cleanroom wipes and IPA.
18.7 Double package the assembly in cleanroom compatible anti static bags. The first
package shall be N2 purged and sealed prior to insertion into the second bag.
19.0 Panel Data Files
19.1 General
19.1.1 Data Files serve as the quality record for production of the assembly,
and may be used for verification purposes in the future.
19.1.2 Assembly Data Files shall be archived by the supplier for a period of
five years.
19.2 Content
19.2.1 All data collected per section 10.0 Part Serialization.
19.2.2 OEM manufacturer'
s data sheets for testing, calibration, certification
19.2.3 Evidence of the component audit
19.2.4 Serialized component cross reference matrix
19.2.5 Air Flow Test report (in lieu of document if applicable)- gas boxes only
19.2.6 Supplier specific test reports and calibration verification information
19.2.6.1 Tested performance of MFC' s with list of correction factors
corresponding to nitrogen gas
19.2.6.2 Panel Leak Test Report
19.2.6.3 Visual Inspection Report
Vendor Code
1.00"
FIGURE 1
Acceptable Methods
Tightened
FIGURE 1
FIGURE 2
Label shown applied across fitting on the outlet of Manual Shut off valve. Do not cover leak check
port(s).
FIGURE 3
Label shown applied across Male-Female VCR fitting. Do not cover leak check port(s). Do not
cover component part number(s).
VCR connection with Filter
Acceptable, see
section 2.3
FIGURE 4
Label shown applied across fitting connection on the input and output of filter. Do not cover leak
check port(s). Do not cover component part number(s).
Do not cover
component part
number(s)
FIGURE 5
Label shown applied across fitting connections on input and output flow restrictor. Do not cover leak check
port(s). Do not cover component part number(s).
FIGURE 6
Label applied across 1/8” VCR fitting. Do not cover leak check port(s).
Document # 67-162884-00 GAS PANEL SYSTEMS TESTING & ACCEPTANCE 15 OF 18
Overall Appearance
FIGURE 7
Labels and label texts should line up in the same direction and orientation.
Unacceptable Methods
FIGURE 8
Document # 67-162884-00 GAS PANEL SYSTEMS TESTING & ACCEPTANCE 16 OF 18
FIGURE 9
Damaged Label
FIGURE 10
FIGURE 11
Tightened
FIGURE 12
Document # 67-162884-00 GAS PANEL SYSTEMS TESTING & ACCEPTANCE 18 OF 18
21.1 Part Shortages or other build deficiencies that are not considered to be
shipment disabling may be acceptable to Novellus Systems, Inc. when
properly documented using the Novellus SRD process. Contact Novellus
Supplier Quality Engineering for further information.