1 Operator Cabin:
Present Condition:
• Cabin Bottom Sheets rusted /body need the
fabrication work.
• Electrical cable routing work.
Reasons of Damage :
• Old unused for long duration & reduced the
strength.
• Storage on open due to rainwater sheet
plates rusted & lost the strength.
Repairing Method :
• Can be repair through fabricator & painting
can be done at site.
Repair Duration :
• 8 days.
2 Masts:
• 1600 mm *1600 mm*3000 mm Long.
• Qty: 22 nos.
Present Condition:
• Good in condition only need the painting.
Reasons of Damage :
• Old & Unused open storage.
Repairing Method:
• Only Painting required.
Page 1 of 5
INSPECTION REPORT FOR TOWER CRANE: 05 TON (MAKE-HAUTA, MODEL 5013)
• 1.5 Lacs
Duration:
• 8 days.
3 Jibs:
• Triangular -10 Mtr Long.
• Qty: 05 nos.
Present Condition:
• Good in condition only need the painting.
• Pulleys – Need to lubrication only-No issue.
Reasons of Damage :
• Old & Unused open storage.
Repairing Method:
• Painting & Lubrication required.
Duration:
• 8-10 days.
Present Condition:
• General in good in condition
• Power Pack & Jack need the service
Page 2 of 5
INSPECTION REPORT FOR TOWER CRANE: 05 TON (MAKE-HAUTA, MODEL 5013)
Reasons of Damage :
• Old & Unused open storage.
Repairing Method:
• Painting & General servicing required.
• Replacement of pins
• Change of Hydraulic hose fittings.
Duration:
• 8 days.
Present Condition:
• Opened, broken electrical contractors
/switches
Reasons of Damage :
• Old & Unused open storage.
Repairing Method:
• Replacement of electrical contractor,
rewiring in panel.
Appox. Repairing Cost :
• Servicing cost – 1,70,000/-
• Total Cost : 1.75 Lacs*2 Nos =3,50,000/-
Duration:
• 8-10 days.
Page 3 of 5
INSPECTION REPORT FOR TOWER CRANE: 05 TON (MAKE-HAUTA, MODEL 5013)
Present Condition:
• Good condition
Reasons of Damage :
• Old & Unused open storage.
Repairing Method:
• General Service, lubrication to wire rope.
• Need to change the bearing of trolley
wheels.
• Wire rope need to change after 2-3 months.
Duration:
• 8-10 days.
7 Electrical Motors :
• Qty: 03 nos.
Present Condition:
• Open /Loose condition
Reasons of Damage :
• Old & Unused open storage.
• Water interned inside.
Repairing Method:
• Electrical service/varnish
• Need to change the bearing of trolley
wheels.
• Wire rope need to change after 2-3 months.
Duration:
• 8-10 days.
8 Slewing Head :
• Qty : 01 set
Present Condition:
• Good condition
9 Counter Weights :
• Qty : 01 set
Present Condition:
• Good condition.
Duration: Nil
Page 5 of 5