------------------------ Inspection optimization

Defining accuracy levels for data


Verifying through quality checksinput/output;
Manually calculating risk
Display results in understandable way
Prepare reports on the RBI analysis. Risk Analyst is a resource to conducting cost-
benefit analysis
-----------------------------------------------------------------------------------
---------------------------------------------------------- Environmental / Safety
Personnel
Provide data on environmental / safety systems / regulations.
Assessing / recommendingon risk management, establishing risk acceptance criteria,
Providing framework / mechanism for others to make these decisions based on RBI
results
Providing the resources
-----------------------------------------------------------------------------------
---------------------------------------------------------- The RBI expected to
determine linkage of risks with appropriate inspection or other risk mitigations
-----------------------------------------------------------------------------------
---------------- After risk acceptability criteria established, it is found not
every failure will lead to an undesirable incident / consequence
-----------------------------------------------------------------------------------
---------------------------------------------------------- Mechanical damage is a
major deterioration mechanism in the hydrocarbon / chemical industry
-----------------------------------------------------------------------------------
--------------------------------------------Use of high-quality data and
knowledgeable personnel increase accuracy of an RBI analysis
-----------------------------------------------------------------------------------
---------------------------------------------------------- Damage mechanisms is
oCorrosion Specialist Assessing damage mechanisms types / applicability / severity
to the equipment considering process conditions, environment, metallurgy, age.
Compare this assessment to actual condition of equipment Determine the reasonne of
the primary considerations in determining failure probability
-----------------------------------------------------------------------------------
---------------------------------------------------------- Proper isolation valve
locations

Inspector / materials / corrosion specialist responsible for assessing the


effectiveness of past inspections. Inspector is responsible for implementing
inspection plan from RBI assessment.
-----------------------------------------------------------------------------------
---------------------------------------------------------- Corrosion Specialist