UNION SIX CONSTRUCTION SDN. BHD.

3METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: INTERNAL CEILING FINISHES (Ceiling Board) (masjid) PAGE NO: 1/5

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
1 Supply and fix plaster
ceiling panel including 430m2 Measuring 1 Skilled workers output 4 days
accessories and all tape = 3.50m2/h
necessary works all in 4 General
accordance with the Pencil labor 3.50m2/hr x 5
manufacturer’s = 17.5m2/h
specification and Folding utility
instructions and to the knife (430m2/17.5m2
Architect's approval. /Hr)/8hr = 3.07
Straight edge days

Hammer

Cutting drywall
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: INTERNAL CEILING FINISHES (Ceiling Board) (masjid) PAGE NO: 2/5

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
2 Ditto: Slanting plaster
ceiling 350m2 Measuring 1 Skilled workers output 3 days
tape = 3.50m2/h
4 General
Pencil 3.50m2/hr x 5
= 17.5m2/h
Folding utility
knife (350m2/72.5m2
/hr)/8hr = 2.5
Straight edge days

Hammer

Cutting drywall
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: INTERNAL CEILING FINISHES (Ceiling Board) (masjid) PAGE NO: 3/5

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
3 Approved cement based
skim coat plaster system 500m2 Trowel 3 skilled labor Worker output 3 days
consisting of one base = 3.5m2/hr
coat troweled smooth all Bucket 3 general labor
in accordance with the 3.5m3/hr x 6 =
architect's details and 21m2/hr
instructions
(500m2/21m2/h
r)/8hr =2.97
days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: INTERNAL CEILING FINISHES (Ceiling Board) (masjid) PAGE NO:4/5

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
4 Supply and fix timber
lattice ceiling with timber 54m2 Measuring 1 skilled labor Worker output 1 days
dressing including tape = 3.5m2/hr
accessories and all 3 general labor
necessary works all in Pencil 3.5m2/hr x 4 =
accordance with the 14m2/hr
manufacturer’s Folding utility
specification and knife (54m214/m2/hr)
instructions and to the /8hr =0.48
Straight edge days
Architect's approval.
Hammer

Cutting drywall
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: INTERNAL CEILING FINISHES (Painting) (masjid) PAGE NO: 5/5

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
5 Prepare and apply one
undercoat and two 1,334m2 Hand mixer 3 Skilled workers output 4 days
finishing coats of = 5.5 m2/h
emulsion paint as Bucket 5 General
specified to: - 5.50m2/hr x 8
General surface of ceiling Sponge =44 m2/h

Steel blade (1,334m2/44m2


scraper /h)/8hr = 3.78
days
Mud pan

Paint brush

Paint roller

Roller tray