Вы находитесь на странице: 1из 3

DACHOMO 2 HYDROPOWER PROJECT BIDDING DOCUMENST – PACKAGE NO.

DACHOMO 2 HYDROPOWER PROJECT

PACKAGE NO. 2

Design, Engineering, Manufacture, Supply, and Supervision and


Guidance of Erection, Testing & Commissioning of Electro-
Mechanical Equipment

PART 2
SUPPLY REQUIREMENTS

CHAPTER V
SCOPE OF SUPPLY

Part 2 – Supply requirements Page 1/3


Chapter V – Scope of supply
DACHOMO 2 HYDROPOWER PROJECT BIDDING DOCUMENST – PACKAGE NO. 2

PART 2. SUPPLY REQUIREMENTS


CHAPTER V. SCOPE OF SUPPLY

Section 1. Scope and delivery schedule

1. Scope of supply of Goods and Technical Services

Scope of supply of Goods consist of Hydraulic-mechanical equipment, indoor electric


equipment, control and protection equipment for project, auxiliary equipment system,
turbine inlet valve, 22kV indoor switchyard etc. including mandatory spare parts and
technical documents to ensure the normal operation of hydropower plant.

Technical Services consist of design; witness test at factory; instruction and


supervisory of installation, testing and commissioning; Training and operation
instruction, technology transfer at site.

The detailed scope is listed in price schedules of Chapter IV – Bidding forms and
described in section 2 of this chapter.

Scope of supply as above but not limit, Bidder shall design and supply adequately
all equipment and necessary services to ensure for plant after installing and
testing that normal operation with having no any supplemental cost as stipulated
in the Contract.

2. Delivery Schedule

Delivery
No. Good items / Services Schedule
place
Head office
1 Submit engineering drawings 30-240 days
of Purchaser
2 Delivery embedded parts 240 days At site
3 All remaining goods 330 - 375 days At site
Instruction and supervisory of Completion time shall
4 At site
installation, testing and commissioning be 15 months.

Note: Above time shall be calculated from valid date of the Contract

Section 2. Technical requirements

Technical requirements is detailed in following Chapters and Appendixes:


- Chapter V – A: General introduction about project and package
- Chapter V – B.I: General technical requirement
- Chapter V – B.II: Detailed technical requirement
 B.II.1: Turbines and auxiliary equipment
 B.II.2: Generator
 B.II.3: Indoor electrical equipment
 B.II.4: Main transformer (Not used)
 B.II.5: 22kV indoor switchyard
Part 2 – Supply requirements Page 2/3
Chapter V – Scope of supply
DACHOMO 2 HYDROPOWER PROJECT BIDDING DOCUMENST – PACKAGE NO. 2

 B.II.6: Auxiliary equipment system for mechanical equipment


 B.II.7: Auxiliary system for electrical equipment
 B.II.8: Technical systems for powerhouse and project (Not used)
- Chapter V – C: Other requirements
- Appendix 1: Manufacturer, origin of equipment, design standard, manufacture
standard and take over, place of testing and verification
- Appendix II.1: Assured technical parameters of mechanical equiment
- Appendix II.2: Assured technical parameters of electrical equiment
- Appendix II.3: Assured technical parameters of powerhouse and project (Not
used)
- Appendix II.4: List of technical specification of bidder equipment
- Appendix III: Drawings

Part 2 – Supply requirements Page 3/3


Chapter V – Scope of supply

Вам также может понравиться