PACKAGE NO. 2
PART 2
SUPPLY REQUIREMENTS
CHAPTER V
SCOPE OF SUPPLY
The detailed scope is listed in price schedules of Chapter IV – Bidding forms and
described in section 2 of this chapter.
Scope of supply as above but not limit, Bidder shall design and supply adequately
all equipment and necessary services to ensure for plant after installing and
testing that normal operation with having no any supplemental cost as stipulated
in the Contract.
2. Delivery Schedule
Delivery
No. Good items / Services Schedule
place
Head office
1 Submit engineering drawings 30-240 days
of Purchaser
2 Delivery embedded parts 240 days At site
3 All remaining goods 330 - 375 days At site
Instruction and supervisory of Completion time shall
4 At site
installation, testing and commissioning be 15 months.
Note: Above time shall be calculated from valid date of the Contract