· A mixture of lumps and fines in which not more than 10% are lumps ranging from maximum size to one half of the
maximum, and 90% are lumps smaller than one half of the maximum size.
· A mixture of lump and fines in which not more than 25% are lumps ranging from the maximum size to one half of the
maximum, and 75% are lumps smaller than one half of the maximum size.
· A mixture of lump only in which 95% or more are lumps ranging from maximum size to one half of the maximum size
and 5% or less are lumps less than one tenth of the maximum size.
The allowable size of a lump in a screw conveyor is a function of the radial clearance between the outside diameter of the
central pipe and the radius of the inside of the screw trough, as well as the proportion of the lumps in the mixture.
converted by Web2PDFConvert.com
The lump size of the material affects the selection of screw diameter which should be at least 12 times larger than the lump
size of a sized material and four times larger than the largest lumps of an un-sized material.
Example, if screw diameter is 250mm means radial clearance is 105mm, & Maximum lump size is 60mm of 10% lumps.
Capacity of Screw Conveyor:
The capacity of a screw conveyor depends on the screw diameter, screw pitch, speed of the screw and the loading efficiency
of the cross sectional area of the screw. The capacity of a screw conveyor with a continuous screw:
Q = V. ρ
Q = 60. (π/4).D2.S.n.ψ.ρ.C
Where,
Q = capacity of a screw conveyor
V = Volumetric capacity in m3/Hr
ρ = Bulk density of the material, kg/m3
D = Nominal diameter of Screw in m
S = Screw pitch in m
N = RPM of screw
Ψ = Loading efficiency of the screw
C = Factor to take into account the inclination of the conveyor
Screw Pitch:
Commonly the screw pitch is taken equal to the diameter of the screw D. However it may range 0.75 – 1.0 times the diameter
of the screw.
converted by Web2PDFConvert.com
Screw Diameter:
RPM of Screw:
The usual range of RPM of screw is 10 to 165. It depends on the diameter of screw and the type of material (Max RPM of screw
conveyor is 165)
Loading efficiency:
The value of loading efficiency should be taken large for materials which are free flowing and non abrasive, while for materials
converted by Web2PDFConvert.com
which are not free flowing and or abrasive in nature, the value should be taken low:
Ψ = 0.12 to 0.15 for abrasive material
= 0.25 to 0.3 for mildly abrasive material
= 0.4 to 0.45 for non abrasive free flowing materials
Inclination Factor:
The inclination factor C is determined by the angle of screw conveyor with the horizontal.
332
SHARES
Related Posts:
LEAVE A REPLY
Your email address will not be published. Required fields are marked *
Comment
Name *
converted by Web2PDFConvert.com
Email *
Website
Post Comment
converted by Web2PDFConvert.com