Вы находитесь на странице: 1из 7

Project Activity Schedule

ID Activity Name Activity Description Duration Dependency Resources


1 Site Establishment site survey boundary pegs, fence, sheds, power & water,.. 5 surveyor
2 Construction Set Out set out of all primary building lines 1 1 surveyor
3 Bulk Excavation over site clearing 3 2 D7 Dozer, 2 truck
4 Detailed Excavation strip & pad footing 1 3 Kubota 6t Tracked excavator
5 Plumbing Service Rough In initial drainage & water rough in works 2 4 Licensed plumber
6 Inspection inspection of reinforcement prior to concrete pour 1 5 Engineer
7 Order bricks Brick supplier‐ Boral 5 9SF
8 Strip Footings reinforcement and concrete to excavated trenches 3 6 Steel fixers / Concerters
9 Brickwork (SF) sub‐floor brick walls 2 8 1 Bricklayer
10 Survey check external wall position 1 9 surveyor
11 Termite Barrier Kordon vapour/termite barrier 1 9,10 SS/C
12 Inspection inspection of reinforcement prior to concrete pour 1 11 Engineer
13 PCA inspection insection for termite protection 1 11,12 PCA inspector
14 RC Garage Slab N25 concrete 1 11,12,13 Steel fixers / Concerters
15 Order Windows window manufacturer‐Stegbar 10 20SF
16 Ground Floor Frame Bearers & floor joists and sheet flooring 3 14 3 Carpenters
17 Wall Framing (GF) prefabricated timber stud wall frames 3 16 3 Carpenters
18 Floor Framing (FF) LVL floor joists and floor sheets 2 17 3 Carpenters
19 Wall Framing (FF) prefabricated timber stud wall frames 2 18 3 Carpenters
20 Window/Door Units install windows and doors in timber reveals 2 19 3 Carpenters
21 Brickwork (GF‐FF) brickwork GF to FF 7 20 2 Bricklayers, 1 labourer
22 Brickwork (FF) brickwork FF to roof 4 21 2 Bricklayers, 1 labourer
23 Brick Cleaning high pressure water clean 1 22 SS/C
24 Order Roof Tiles Roof tile supplier‐Monier 20 28SF
25 Roof Framing prefabricated timber trusses and roof framing 5 22 3 Carpenters
1
ID Activity Name Activity Description Duration Dependency Resources
26 Frame inspection PCA inspection after all timber framing complete 1 25 PCA inspector
27 Roof Plumbing & Drainage gutters & down pipes installed 2 26 2 Roof plumber/Drainer
28 Roof Cladding sarking, battens, roof tiles and capping 3 27 2 Roof tilers, 1 labourer
29 Survey Final check final survey certificate 1 28,22 surveyor
30 Order wall & floor tiles wall & floor tile supplier 5 33SF
31 Waterproofing wet area floor/wall waterproofing 1 18 SS/C
32 PCA inspection of wet area inscpection of wet area flashing & waterproofing 1 31 PCA inspector
33 Ceramic Tiling wall/floor tiles 2 32 2 Wall&floor tilers
34 Order Joinery joinery‐ southern stairs 15 35SF
35 Joinery Works timber stairs, handrails, kitchen 3 33 SS/C
36 Electrical Service Rough In initial electrical rough in 2 17,19 Licensed electrician
37 Interior Linings plasterboard walls, ceilings 6 28,36 4 Plasterers, 2 labourers
38 Order Cabinets cabinetmaker‐scott's kitchens 10 39SF
39 Carpentry Fix Out dressed timber door jambs, architraves & skirtings 1 37 Carpenters
40 Interior Painting internal painting for all required surfaces 2 39 Painters
41 Order Plumbing & Electrical PC iteOrder plumbing and electrical PC items from Reece and Harvey N 15 42SF
42 Service Fit Out & Connect final plumbmg and electrical installation 1 40 Licensed plumber & electrician
43 Inspection‐electrical ready for test inspection 1 42
44 Inspection‐plumbing ready for test inspection 1 42
45 Exterior Cladding wall wrap and fiber cement boarding 4 20,23 Carpenters
46 Exterior Painting external painting to all required surfaces 3 45 Painters
47 External Site Works paths, paving, fencing 5 46 Builder
48 Floor Finishes underlay and carpet laying 2 47,42 SS/C
49 Final Clean Up decommission 1 48 Builder
50 Final Inspection PCA to issue OC 1 49,43,44,29 PCA inspector

2
Calculations: 

1. Bulk Excavation: initial over site cleaning 150mm. 

Using D7 dozer. 

Area = 22 x 41.6  = 915.2 m2 

Excavation volume = 915.2 x 0.15 x 1.2 = 164.736 m3 

Using 10 m3 trucks, then: 

Number of trips = 164.7/10 = 16.5 = 17 trips (2 truck, 3 trips/days) 

Duration = 17/2/3  = 3 days. 

2. Detailed Excavation: strip and pad footings 
 
Using Kubota 6t tracked excavator 
 
Strip footings = 15.2 x 4 + 14.8 x 2 + 5.5 + 7.5 + 2 = 105.4 m 
105.4 x 0.45x0.3 = 14.23 m3 
 
Bad footings = 15 x 0.45 x 0.45 x 0.3 = 0.91 m3 
 

Total excavation = 14.23 + 0.91 = 15.14 m3 
 
From the production rate tables, (0.2 hrs/cum) 
Duration = 0.2 x 15.14 = 3.03 hrs  = 1 day. 
 
 
 
 

3
3. Strip footing: reinforcement and concrete to excavated trenches 
 
Reinforcing steel = 105.4 x 2 = 210.8 m 
Area = 210.8 x 0.35 = 74 m2 
 
Rate from table = 0.07 hrs / spm 
Reinforcement time = 74 x 0.07 = 5.18 hrs = 1 day 
Concrete placement of 15.14 m3   
Rate from table = 0.9 hrs/ sqm 
Concrete time = 15.14 x 0.9 = 13.63 hrs = 2 days 
 
Total duration of strip footing activity = 3 days. 
 
 
4. Brickwork (SF): subfloor brickworks and piers. 
Three courses of subfloor single brick walls and piers 
 
Single brick walls = 15.1 + 5.8 + 5.6 x 4 + 9.4 + 7.5 + 3.7 + 2 + 9.2 = 75.1 m 
75.1 x 1000/230 x 3 = 980 bricks 
Engaged piers = 45 x 3 = 135 bricks 
Piers = 15 x 2 x 3 = 90 bricks 
 
Total bricks = 1205 bricks 
 
Rate from table = 12 hours/ 1000 bricks 
Duration = 1205/1000 x 12 = 14.5 hours  
1 bricklayers, 1 labourer =  2 days 
 
 
5. Ground floor framing: Bearers & floor joists and sheet flooring 
 
Bearers = 8.8 x 3 + 12.6 + 7.28 x 6 = 82.68 m (100 x 75mm) 
Joists   = 17 x 5.5 + 9.2 x 14 = 222.3 m (100 x 50mm) 
Sheets = 7.2 x 9.2 + 5.5 x 8.4 = 112.44 m2 
 

4
Rate for bearers = 13 hrs/100m 
Rate for joists =  8.5 hrs/100m 
Rate for floor sheets = 35 hrs/100m2  
 
Duration = 82.68/100 x 13 + 222.3/100 x 8.5 + 112.44/100 x 35 = 69 hrs 
Using 3 carpenters  
Duration = 69/3/8 = 2.9 = 3 days 
 
 
6. Brickwork GF to FF: brickwork from ground floor to first floor 
Face brick walls = 7.5 + 9.4 + 15.1 + 9.2 + 2 + 5.6 + 5.8 = 54.6 m 
54.6 x 2.4 = 131 m2  ‐ 24 m2(openings)  = 107 m2 
107 x 50 = 5352 bricks 
 
Rate from table = 18 hrs/ 1000 bricks 
 
2 bricklayers, 1 labourer 
 
Duration = 5352/2/1000 x 18 = 48.17 hours = 7 days 
 
 
 
7. Brickwork FF: brickwork from first floor to roof 
Face brick walls = 4.7 + 15.2+ 7.35 = 27.25 m 
27.25 x 2.4 = 65.4 m2 – 4.5 m2 (openings) = 60.9 m2 
60.9 x 50 = 3045 bricks 
 
Duration = 3045/2/1000 x 18 = 27.4 hours = 4 days 
 
 
8. Roof tiling: roof pitch 15 degrees 
Upper roof area = (5.65 x 9.55 + 8.25  x 5.65) / cos 15 = 104.1 m2 
Lower roof area = (5.65 x 6.7 + 3.2 x 6.4 + 2.45 x 9.05)/ cos 15 = 83.4 m2 
 
Total roof area = 187.5 m2 

5
 
Rate from tables = 17 hrs/100 sqm 
2 tilers and 1 labourer 
 
Time needed = 187.5/2/100 x 17 = 15.9 hrs = 2 days + 1 day for sarking 
and capping  
 
Duration = 3 days 
 
 
9. Roof guttering and drainage:  installation of gutters and down pipes 
 
Gutter length = (15.2 + 0.3 x 2) x 4 = 63.2 m 
Down pipes length = 4.8 x 4 + 2.4 x 4 = 28.8 m 
 
Rate for gutter = 0.3 hr/m, rate for downpipe = 0.3 hr/m 
 
Duration = (63.2 + 28.8) x 0.3 = 27.6 hrs = 2 days (2 roof plumbers) 
 
 
10. Internal lining: plasterboard walls, ceilings 
 
Area of walls = (7.3x4 + 15.2x4 + 21) x 2.4 + (15.2 x3 + 7.5 x 6 + 2 + 5.3) x 
2.4  = 501.4 m2 
 

Area of ceiling = 112.4 + 4.7 x 9.55 + 5.65x7.35 = 198.8 m2 
 
Rate for walls = 0.24 hr/sqm 
Rate for ceiling = 0.27 hr/sqm 
 
Duration = 501.4 x 0.24 + 199 x 0.27 = 174 hrs 
Using 4 plasterers and 2 labourers  
 
Duration = 174/8/4 = 5.4 = 6 days  

6
ID Task Name Duratio Predecessors 16 Nov '15 23 Nov '15 30 Nov '15 7 Dec '15 14 Dec '15 21 Dec '15 28 Dec '15 4 Jan '16 11 Jan '16 18 Jan '16 25 Jan '16 1 Feb '16 8 Feb '16 15 Feb '16 22 Feb '16
SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S S
1 Site Establishment 5 days
2 Construction Set Out 1 day 1
3 Bulk Excavation 3 days 2
4 Detailed Excavation 1 day 3
5 Plumbing Service Rough In 2 days 4
6 Inspection 1 day 5 2/12
7 Order bricks 5 days 9SF
8 Strip Footings 3 days 6
9 Brickwork (SF) 2 days 8
10 Survey check 1 day 9 10/12
11 Termite Barrier 1 day 9,10
12 Inspection 1 day 11 14/12
13 PCA inspection 1 day 11,12 15/12
14 RC Garage Slab 1 day 11,12,13
15 Order Windows 10 days20SF
16 Ground Floor Frame 3 days 14
17 Wall Framing (GF) 3 days 16
18 Floor Framing (FF) 2 days 17
19 Wall Framing (FF) 2 days 18
20 Window/Door Units 2 days 19
21 Brickwork (GF‐FF) 7 days 20
22 Brickwork (FF) 4 days 21
23 Brick Cleaning 1 day 22
24 Order Roof Tiles 20 days28SF
25 Roof Framing 5 days 22
26 Frame inspection 1 day 25 26/01
27 Roof Plumbing & Drainage 2 days 26
28 Roof Cladding 3 days 27
29 Survey Final check 1 day 28,22 3/02
30 Order wall & floor tiles 5 days 33SF
31 Waterproofing 1 day 18
32 PCA inspection of wet area 1 day 31 30/12
33 Ceramic Tiling 2 days 32
34 Order Joinery 15 days35SF
35 Joinery Works 3 days 33
36 Electrical Service Rough In 2 days 17,19
37 Interior Linings 6 days 28,36
38 Order Cabinets 10 days39SF
39 Carpentry Fix Out 1 day 37
40 Interior Painting 2 days 39
41 Order Plumbing & Electrical  15  42SF
PC items days
42 Service Fit Out & Connect 1 day 40
43 Inspection‐electrical 1 day 42 17/02
44 Inspection‐plumbing 1 day 42 17/02
45 Exterior Cladding 4 days 20,23
46 Exterior Painting 3 days 45
47 External Site Works 5 days 46
48 Floor Finishes 2 days 47,42
49 Final Clean Up 1 day 48
50 Final Inspection 1 day 49,43,44,29 22/02

Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish‐only


Split Project Summary Inactive Task Manual Task Manual Summary Deadline
Milestone External Tasks Inactive Milestone Duration‐only Start‐only Progress

Page 1
7

Вам также может понравиться